HomeMy WebLinkAbout20120229order_no_32472_errata.pdfOffice of the Secretary
Service Date
February 29,2012
BEFORE THE IDAHO PUBLIC UTILITIES COMIVHSSION
IN THE MATTER OF THE APPLICATION )
OF IDAHO POWER COMPANY FOR )CASE NO.IPC-E-11-24
AUTHORITY TO MODIFY ITS RULE H )
TARIFF RELATED TO THE GENERAL )ERRATA TO
OVERHEAD RATE.)ORDER NO.32472
________________________________________________________________________________________
)
On February 28,2012,IPUC Order No.32472 was issued by this Commission.The
following change should be made to that Order:
Page 4.Order Paragraph 1:
READS:
IT iS HEREBY ORDERED that the Application of Idaho Power Company
for authority to modify its Rule H (line extension)tariff related to the general
overhead rate is approved.Idaho Power is authorized to collect a general
overhead rate of 21.5%relating to new service attachments and distribution
line installations and alterations under its Rule H tariff.
SHOULD READ:
IT IS HEREBY ORDERED that the Application of Idaho Power Company
for authority to modify its Rule H (line extension)tariff related to the general
overhead rate is approved.Idaho Power is authorized to collect a general
overhead rate of 21.5%relating to new service attachments and distribution
line installations and alterations under its Rule H tariff,effective on March
15,2012.
DATED at Boise.Idaho this day of February 2012.
/1 •/1:4 J
Jean D Jewel!
COmmission Secretary
O:IPC-E-I 1-24ks2 Errata