HomeMy WebLinkAbout20120206Affidavit on Remand.pdfDONOVAN E. WALKER (ISB No. 5921)
JASON B. WILLIAMS (ISB No. 8718)
Idaho Power Company
1221 West Idaho Street (83702)
P.O. Box 70
Boise, Idaho 83707
Telephone: (208) 388-5317
Facsimile: (208) 388-6936
dwalkertæidahopower.com
jwilliamsß!idahopower.com
Attorneys for Idaho Power Company
RECEIVED
1012 FEB -6 PH 4: 35
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR A
DETERMINATION REGARDING A FIRM
ENERGY SALES AGREEMENT
BETWEEN IDAHO POWER AND
GROUSE CREEK WIND PARK, LLC
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR A
DETERMINATION REGARDING A FIRM
ENERGY SALES AGREEMENT
BETWEEN IDAHO POWER AND
GROUSE CREEK WIND PARK II, LLC
STATE OF IDAHO)
) ss.County of Ada )
)
) CASE NO. IPC-E-10-61
)
) AFFIDAVIT OF RANDY ALLPHIN
) IN SUPPORT OF IDAHO POWER
) COMPANY'S MEMORANDUM ON
) REMAND
)
)
) CASE NO. IPC-E-10-62
)
) AFFIDAVIT OF RANDY ALLPHIN
) IN SUPPORT OF IDAHO POWER
) COMPANY'S MEMORANDUM ON
) REMAND
)
I, Randy Allphin, do declare the following and if called to testify, would and could
competently testify thereto:
AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF
IDAHO POWER COMPANY'S MEMORANDUM ON REMAND - 1
1. I am over the age of eighteen and I am the Senior Energy Contract
Coordinator at Idaho Power Company ("Idaho Powet' or "Company"). I have been
employed by Idaho Power for approximately 30 years, and dealing with Public Utilty
Regulatory Policies Act of 1978 ("PURPA") power purchases for 26 of those years.
2. My primary responsibilties include daily administration of existing and the
negotiation of new PURPA and other renewable energy contracts.
3. I negotiated the Power Purchase Agreements with Grouse Creek Wind
Park, LLC, and Grouse Creek Wind Park II, LLC ("Grouse Creek" or "Project") with the
project developer, Wasatch Wind, for its proposed PURPA qualifying facilities ("QF").
4. Attached hereto as Attachment NO.1 is a listing of many of the e-mail
communications and some letters that were exchanged between Idaho Power and
representatives of Wasatch Wind. This list does not include the phone calls and other
conversations that took place with regard to Wasatch Wind and its proposed PURPA
projects.
5. Wasatch Wind first contacted Idaho Power inquiring as to a potential
PURPA project ranging from 10 average megawatts ("aMW") to 80 megawatts ("MW")
on February 26, 2010, by Christine MikelL. Attached hereto as Attachment NO.2 are
several of the initial e-mail exchanges between myself and Ms. Mikell from February 26
through March 3, 2010, regarding this initial inquiry and Idaho Powets initial response.
The Project was informed at this time that, among other things, because it was an off-
system QF, sufficient information regarding delivery of its output to Idaho Powets
system would need to be provided.
AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF
IDAHO POWER COMPANY'S MEMORANDUM ON REMAND - 2
6. Attached hereto as Attachment No. 3 are several communications from
April and May 2010, again between myself and Ms. MikelL. These communications
show that the Project continued to change its configuration, inquiring as to a 60 MW
project. As the proposed project was over 10 aMW, pricing was to be calculated
pursuant to the Integrated Resource Plan ("IRP") methodology. As such, Idaho Power
needed one yeats worth of hourly generation data from the Project in order to calculate
pricing in the IRP modeL. Some of these communications concerned the data to be
submitted by the Project, and notification that the data from the Project appeared to
contain errors.
7. Attached hereto as Attachment NO.4 are several communications from
the month of June 2010. Many of these communications relate to the letter of
understanding and transmission questionnaire that is required to enable Idaho Powets
merchant business unit to make a transmission service request ("TSR") to the
Company's transmission business unit to establish sufficient transmission capacity on
Idaho Powets system to designate the Project's output as a network resource to serve
load on Idaho Powets system. Also included is a June 2 communication where Idaho
Power forwarded initial indicative pricing to the Project based upon the run of the IRP
avoided cost methodology. On June 24, the Project provided a Bonnevile Power
Administration ("BPA") feasibilty study for a 150 MW project, and advised that it was
having complications with golden eagle nests near the Project site, and wished to now
change configurations and discuss a single 10 aMW project, and possibly another at a
later date. There are some follow-up communications from Idaho Power providing
information on the published rate process.
AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF
IDAHO POWER COMPANY'S MEMORANDUM ON REMAND - 3
8. Attached hereto as Attachment No. 5 are several communications
between Idaho and the Project from the month of July 2010. The Project submitted
information regarding various configurations, turbines, and transmission arrangements.
Idaho Power continued to try and clarify information from the Project with respect to the
TSR.
9. Attached hereto as Attachment NO.6 are communications from the month
of August showing further dialogue regarding clarification as to the project configuration,
the number of proposed projects, accuracy of the data, and the requirements of 10
aMW and one-mile separation.
10. Attached hereto as Attachment No. 7 are two letters from Peter
Richardson, counsel for the Project, dated October 1, 2010, for Grouse Creek Wind and
Grouse Creek Wind II, respectively. These letters request PPAs, provides information,
objects to the posting of security required by the contracts, changes the project from 30
MW to 21 MW, and requests revision of the TSR from 30 MW to 21 MW, among other
things.
11. Attached hereto as Attachment No. 8 are November 1 letters from Idaho
Power to Mr. Richardson, responding to his October 1 letter and pointing out several of
the open items remaining with the various proposed projects. Also forwarded with these
letters were copies of: Network Resource Integration Study Agreements, Transmission
Capacity Application Questionnaires, and Draft Firm Energy Sales Agreements.
12. Attached hereto as Attachment NO.9 is a November 4 e-mail from myself
to Mr. Richardson advising that the submitted TSRs were rejected because the
information provided by the Project did not sync up with the Project's transmission
AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF
IDAHO POWER COMPANY'S MEMORANDUM ON REMAND - 4
requests on BPA's system. The communication asks for updated transmission
information from the Project that was needed to proceed with the TSRs, and advised of
the need for ancilary services. Also included in Attachment No. 9 is a November 24
letter from Donovan Walker to Mr. Richardson confirming a prior letter and meeting
between the Project and Idaho Power, and summarizing the current status of
negotiations as to some of the previously contested terms and conditions. Also
attached in Attachment No. 9 is a November 29 e-mail from Mr. Richardson to Kris
Sasser, counsel for the Idaho Public Utilties Commission ("Commission") Staff
regarding Grouse Creek's Complaints.
13. Attached hereto as Attachment No. 10 is a December 2 letter from Mr.
Richardson forwarding Draft Firm Energy Sales Agreements ("FESA") containing the
Projects' mark-up and provision of Project information into the Draft FESA.
14. On December 6, Idaho Power received a revised Transmission
Questionnaire from the Projects containing corrected information for re-submission of
the TSRs, which was forwarded to Idaho Power transmission on the same day.
15. Attached hereto as Attachment No. 11 is a December 7, 1 :50 p.m. e-mail
and letter from me to Mr. Richardson acknowledging receipt of the December 2 mark-up
of the Draft FESA from the Project, the December 6 updated transmission information,
and reviewing/confirming the negotiations and status of moving the Projects towards
final agreements.
16. Attached hereto as Attachment No. 12 is a December 7, 7:49 p.m. e-mail
communication to Mr. Richardson forwarding updated Draft FESAs for the Projects,
incorporating the information provided by the Projects, and working toward executable
AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF
IDAHO POWER COMPANY'S MEMORANDUM ON REMAND - 5
versions of the FESAs. This communication also notifies the Projects of missing
information from the Projects necessary to confirm the required one-mile separation
between the Projects and necessary to complete the Draft FESAs. Also on December
7, Idaho Power began the internal review process on the Draft FESAs, even though
they were not yet complete, nor accepted by the Projects, so as not to unduly impede
the ultimate execution of the FESAs once accepted by the Projects, since the
December 14, 2010, date previously set by the Commission as the effective date for the
reduction in the published rate eligibilty cap to 100 kilowatts was drawing near. Also
attached in Attachment No. 12 is a December 9 e-mail from Mr. Richardson confirming
the Projects' agreement to the security provisions of the contract and requesting a
change in the Scheduled First Energy Dates as well as the Scheduled Operation Dates.
17. Attached hereto as Attachment No. 13 is a December 14 e-mail from
Idaho Power to Mr. Richardson requesting that the Projects provide missing necessary
information required for completion of the Draft FESAs. This information included
naming the proper transmission entity, as previous communication had indicated at
different times both BPA and PacifiCorp, and requested again that the Project provide a
complete location designation, which is necessary to establish the proper one-mile
separation and legal description of the Projects' location.
18. Attached hereto as Attachment No. 14 is a December 15 e-mail from
Idaho Power to Mr. Richardson confirming Idaho Powets receipt and acceptance of the
Projects' revised First Energy and Scheduled Operation dates, and indicating the same
would be incorporated into the final Draft FESAs. This communication also reiterates
Idaho Power's December 14 request from the previous day for additional required
AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF
IDAHO POWER COMPANY'S MEMORANDUM ON REMAND - 6
information regarding the Transmitting Entity and completion of the location description
for the Projects. The Projects were informed that this information was required to
continue processing the proposed agreements. Also attached in Attachment No. 14 is a
December 15 response from Mr. Richardson's office responding to Idaho Powets
requests for completed information.
19. Attached hereto as Attachment No. 15 is an e-mail communication
between Idaho Power and Greg Adams from Mr. Richardson's offce. This
communication contains a December 15 request from Idaho Power to confirm that the
Schedule First Energy and Scheduled Operation Dates, as well as the location
description for the Projects, were correct. This information was confirmed on December
16, at 8:19 a.m. by Mr. Adams. Also included in Attachment No. 15 is a December 16,
9:53 a.m. communication from Idaho Power that final Draft FESAs are completed, and
ready for the Projects' review. The e-mail asks if they prefer to pick up the hard copies
at Idaho Power, or if they wish for the Draft FESAs to be placed in the maiL. Mr. Adams
responded that he would pick up the Agreements.
20. After the Projects picked up final Draft FESAs for their review on
December 16, 2010, the Projects signed the FESAs on December 21, thereby
committing the Projects to sell their output to Idaho Power pursuant -to.t~e negotiated
terms and conditions contained in those Agreements. The Projects sigMdthe:~ESAs
-~
on December 21, 2010, and sent them back to Idaho Power .vi8\Ov~rñighf"del~ery.,t . G.~. ".ii ì";i'
Idaho Power completed its final review, approval, and required sarbli~~~YJeview
..,"';¡ .,.,.,.,-,- ----~/'
process and signed the Agreements on December 28, 201 O. OnDecemÐè(~, Idaho
è'''''
Power filed the executed FESAs with the Commission for its review.
AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF
IDAHO POWER COMPANY'S MEMORANDUM ON REMAND - 7
21. Idaho Power negotiated in good faith with Grouse Creek, dilgently
responded to the Projects' requests, and made every effort to work in good faith with the
Projects through several different iterations of the Projects' own development and
configurations. Idaho Power not only did not delay the Projects but actually went to
extra efforts seeking necessary information from the Projects in an attempt to move the
draft agreements forward prior to December 14, 2010. It was the Projects' own failure
to provide complete and accurate information that delayed their own review of the
Agreements unti after the December 14,2010, date had passed. Grouse Creek did not
commit itself to sell its output to Idaho Power until December 21, 2010, after it reviewed
the final draft Agreements and executed them.
I declare under penalty of perjury of the laws of the state of Idaho that the
foregoing is true and correct.
DATED this 6th day of February 2012.
~t~.RÄ Y C. ALLr\
SUBSCRIBED AND SWORN to before me this 6th day of February 2012.
ß\:'~~çl~Notary Public for ~
Residing at: :feii Siç. :Lctú'r D
My commission expires: 02/ 0tt 7 Q I 5
AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF
IDAHO POWER COMPANY'S MEMORANDUM ON REMAND - 8
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on the 6th day of February 2012 I served a true and
correct copy of the AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF IDAHO
POWER COMPANY'S MEMORANDUM ON REMAND upon the following named
parties by the method indicated below, and addressed to the following:
Commission Staff
Kristine Sasser
Deputy Attorney General
Idaho Public Utilties Commission
472 West Washington (83702)
P.O. Box 83720
Boise, Idaho 83720-0074
Grouse Creek Wind Park, LLCs
Brett Woodard
Wasatch Wind Intermountain, LLC
2700 Homestead Road, Suite 210
Park City, Utah 84098
Peter J. Richardson
Gregory M. Adams
RICHARDSON & O'LEARY, PLLC
515 North 27th Street (83702)
P.O. Box 7218
Boise, Idaho 83707
-- Hand Delivered
U.S. Mail
_ Overnight Mail
FAX
-- Email Kris.Sasser(gpuc.idaho.gov
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email bwoodard(gwasatchwind.com
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email peter(grichardsonandoleary.com
greg(grichardsonandoleary.com
¿;yd(¿
Donovan E. Walker
~..
AFFIDAVIT OF RANDY ALLPHIN IN SUPPORT OF
IDAHO POWER COMPANY'S MEMORANDUM ON REMAND - 9
BEFORE THE
IDAHO PUBLIC UTiliTIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO.1
e-
m
a
i
l
Tu
e
M
a
r
2
.
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
e-
m
a
i
l
We
d
M
a
r
3
.
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
e-
m
a
i
l
We
d
M
a
r
3
.
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
e-
m
a
i
l
We
d
M
a
r
3
.
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
s
t
i
n
e
M
i
k
e
l
l
e-
m
a
i
l
We
d
M
a
r
3
.
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
e-
m
a
i
l
We
d
M
a
r
3
.
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
e-
m
a
i
l
Th
u
A
p
r
2
2
.
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
e-
m
a
i
l
Th
u
A
p
r
2
2
.
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
e-
m
a
i
l
We
d
M
a
y
5
.
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
e-
m
a
i
l
Th
u
M
a
y
1
3
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
e-
m
a
i
l
Fr
i
Ma
y
14
.
20
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
e-
m
a
i
l
We
d
M
a
y
1
9
.
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
e-
m
a
i
l
We
d
M
a
y
1
9
.
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
e-
m
a
i
l
Tu
e
J
u
n
1
.
2
0
1
0
Ch
r
i
s
t
i
n
e
M
l
k
e
i
l
Ra
n
d
y
A
l
l
p
h
i
n
Id
a
h
o
P
o
w
e
r
r
e
s
p
o
n
s
e
a
s
k
i
n
g
f
o
r
c
l
a
r
i
f
i
c
a
i
o
n
a
n
d
w
e
n
t
t
h
r
o
u
g
h
t
i
s
s
u
e
s
w
i
t
h
o
f
s
y
s
t
e
m
p
r
o
j
e
c
t
(
r
a
f
t
r
i
v
e
r
i
n
t
e
r
c
o
n
n
e
c
i
o
n
.
b
p
a
tr
a
n
s
m
i
s
i
s
o
n
.
I
d
a
h
o
P
o
w
r
t
r
a
n
s
m
i
s
s
i
o
n
.
o
n
l
y
b
e
a
b
l
e
t
o
e
x
e
c
u
t
e
a
P
P
A
o
n
c
e
t
h
e
s
e
I
n
t
e
r
c
o
n
n
e
c
t
i
o
n
I
s
s
u
e
s
r
e
s
o
l
v
e
d
)
.
No
t
i
f
i
e
d
p
r
o
j
e
c
o
f
I
d
a
h
o
P
o
w
e
r
t
r
a
n
s
m
i
s
s
i
o
n
p
r
o
c
e
s
s
i
n
g
t
i
m
e
l
l
n
e
Pr
o
j
e
a
s
k
e
d
q
u
e
s
i
o
n
s
a
b
o
u
t
p
r
i
c
i
n
g
f
o
r
a
6
0
M
W
p
r
o
j
e
c
t
.
Id
a
h
o
P
o
w
r
p
r
o
v
d
e
d
Q
F
p
r
s
r
e
q
u
i
r
e
m
e
n
t
s
Pr
o
j
e
q
u
e
s
t
i
o
n
s
o
n
a
v
o
i
d
e
d
c
o
s
t
s
f
o
r
1
0
a
M
W
p
r
o
j
e
c
t
Cl
a
r
i
f
i
e
d
w
l
n
d
I
n
t
e
g
r
t
i
o
n
c
h
a
r
g
.
a
l
s
o
d
i
r
e
c
t
e
d
t
h
e
p
r
o
j
e
c
t
t
o
I
P
U
C
w
e
b
s
i
t
e
t
o
s
e
e
c
o
p
i
e
s
o
f
f
i
l
e
d
c
o
n
t
r
a
c
t
s
Pr
o
j
e
c
t
p
r
o
v
i
d
e
d
g
e
n
e
r
a
t
i
o
n
p
r
o
f
i
l
e
f
o
r
a
2
.
5
M
W
c
l
i
p
p
e
r
t
u
r
b
i
n
e
Ad
i
t
i
o
n
a
l
e
-
m
a
i
l
s
t
r
y
i
n
g
t
o
g
e
t
d
a
t
a
i
n
p
r
o
p
e
r
f
o
m
.
Pr
o
j
e
c
r
e
u
e
s
t
e
d
u
p
d
a
t
e
o
n
I
d
a
h
o
P
o
w
e
r
p
r
i
c
i
n
g
m
o
d
e
l
s
Id
a
h
o
P
o
w
e
r
n
o
t
i
f
i
e
d
p
r
o
j
e
c
t
t
h
a
t
d
a
t
a
p
r
o
v
i
d
e
d
w
a
s
n
o
t
g
o
o
d
.
i
t
s
h
o
w
e
d
g
e
n
e
r
a
t
i
o
n
i
n
e
v
e
r
y
h
o
u
r
.
Pr
o
j
e
c
t
r
e
s
p
o
n
d
e
d
w
i
t
h
f
u
l
l
o
u
t
p
u
t
d
a
t
a
f
o
r
e
n
t
i
r
e
w
i
n
d
f
a
r
m
.
s
t
i
l
g
e
n
e
r
a
t
i
o
n
i
n
e
v
e
r
y
d
a
y
.
P
r
o
p
o
s
e
d
p
r
o
j
e
c
t
n
o
w
6
5
M
W
Pr
o
j
e
s
t
i
l
w
o
r
k
i
n
g
o
n
g
e
t
t
i
n
g
e
s
t
i
m
a
t
e
d
o
n
l
i
n
e
d
a
t
e
,
a
l
s
o
a
s
k
e
d
a
b
o
u
t
a
n
o
t
h
e
r
p
r
o
j
e
c
t
n
e
a
r
J
i
m
B
r
i
d
g
e
r
.
Re
s
p
o
n
d
e
d
t
o
C
h
r
s
t
i
n
e
e
m
a
i
l
-
J
i
m
b
r
i
d
g
r
q
u
e
s
t
i
o
n
.
R
F
P
s
e
t
c
Ch
r
i
s
t
i
n
e
l
o
o
k
i
n
g
f
o
r
I
n
d
i
c
a
t
i
v
e
p
r
i
c
i
n
g
.
.
J
:
:
'
~
;.
r-
m
a
l
l
We
d
J
u
n
2
.
2
0
1
0
Ra
n
d
v
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
p
r
o
v
i
d
e
d
i
n
d
i
c
a
t
i
v
e
p
r
i
c
i
n
g
.
a
l
s
o
r
e
m
i
n
d
e
d
p
r
o
j
e
c
t
h
e
y
m
u
s
t
c
o
m
p
l
e
t
e
l
e
t
t
e
r
o
f
u
n
d
e
r
s
t
a
n
d
i
n
g
f
o
r
u
s
t
o
b
e
i
n
g
T
S
R
p
r
o
c
e
s
s
.
.~
~
n
z
Pr
o
j
e
c
t
s
t
i
l
f
i
l
l
n
g
i
n
i
n
f
o
r
m
a
t
i
o
n
o
n
f
o
r
m
I
d
a
h
o
P
o
w
e
r
s
e
o
n
J
u
n
e
2
n
d
'5
~
m
a
i
l
We
d
J
u
n
1
6
.
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
=
h
.
.
()
;
;
~
-0~CD So~
si =¡~..~
e-
m
a
i
l
e-
m
a
i
l
e-
m
a
i
l
e-
m
a
i
l
e-
m
a
i
l
e-
m
a
i
l
e-
m
a
i
l
Th
u
J
u
n
1
7
,
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
We
d
J
u
n
2
3
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Th
u
J
u
n
2
4
,
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
Fr
i
Ju
n
2
5
,
2
0
1
0
Ra
n
d
y
All
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Mo
n
J
u
n
2
8
,
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
Tu
e
J
u
n
2
9
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
We
d
J
u
l
1
4
,
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
We
d
J
u
l
2
1
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
I
n
e
M
i
k
e
l
l
We
d
J
u
l
2
1
,
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
e-
m
a
i
l
e-
m
a
i
l
e-
m
a
i
l
Mo
n
A
u
g
2
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
le
t
t
e
r
o
f
u
n
d
e
r
s
t
a
n
d
i
n
g
s
i
g
n
e
d
b
y
p
r
o
j
e
c
t
a
n
d
r
e
t
u
r
n
e
d
(
l
e
t
t
e
r
s
e
n
t
t
o
t
h
e
P
r
o
j
e
c
t
o
n
M
a
r
c
h
1
2
,
2
0
1
0
1
,
i
n
f
o
r
m
a
t
i
o
n
i
n
d
i
c
a
t
e
s
a
6
9
M
W
pr
o
j
e
c
t
,
o
n
l
i
n
e
D
e
c
2
0
1
1
.
ad
v
i
s
e
d
p
r
o
j
e
c
t
t
h
a
t
w
e
n
e
e
d
e
d
c
o
n
f
i
r
m
e
d
B
P
A
t
r
a
n
s
m
i
s
s
i
o
n
a
g
r
e
m
e
n
t
o
r
a
t
t
h
e
m
i
n
i
m
u
m
a
d
d
i
t
i
o
n
a
i
i
n
f
o
r
m
a
t
i
o
n
o
n
t
h
e
B
P
A
tr
a
n
s
m
i
s
s
i
o
n
a
v
a
i
l
a
b
l
i
t
y
.
Pr
o
j
e
c
t
p
r
o
v
i
d
e
d
c
o
p
y
o
f
B
P
A
f
e
a
s
i
b
l
i
t
y
s
t
u
d
y
f
o
r
a
1
5
0
M
W
p
r
o
j
e
c
t
,
a
p
p
e
a
r
s
t
o
b
e
f
o
r
i
n
t
e
r
c
o
n
n
e
c
t
i
o
n
.
A
l
s
o
a
d
v
i
s
e
d
w
o
u
l
d
n
e
e
d
t
o
ch
a
n
g
e
f
r
o
m
o
n
e
l
a
r
g
e
p
r
o
j
e
c
t
t
o
a
s
i
n
g
l
e
2
1
M
W
p
r
o
j
e
c
t
a
n
d
w
o
u
l
d
m
a
y
b
e
r
e
q
u
e
s
t
a
s
e
c
o
n
d
p
r
o
j
e
c
t
l
a
t
e
r
.
ad
v
i
s
e
d
p
r
o
j
e
o
f
1
0
a
M
W
p
r
i
c
i
n
g
a
n
d
m
o
r
e
i
n
f
o
r
m
a
t
i
o
n
f
o
r
t
r
a
n
s
m
i
s
s
i
o
n
i
s
s
u
e
s
Lo
k
i
n
g
f
o
r
a
s
a
m
p
i
e
1
0
a
M
W
c
o
n
t
r
a
c
t
Ad
v
i
s
e
d
n
e
e
d
m
o
r
e
i
n
f
o
r
m
a
t
i
o
n
f
o
r
d
r
a
f
t
s
.
Re
q
u
e
s
t
f
r
o
m
p
r
o
j
e
c
t
f
o
r
tw
o
1
0
a
M
W
p
r
o
j
e
c
t
s
,
G
r
o
u
s
e
C
r
e
e
k
i
n
a
m
e
p
l
a
t
e
o
f
3
0
M
W
,
I
I
n
a
m
e
p
l
a
t
e
o
f
2
1
M
W
.
se
n
t
p
r
o
j
e
c
t
i
n
f
o
r
m
a
t
i
o
n
o
n
T
S
R
p
r
o
c
e
s
s
,
i
s
s
u
e
w
i
t
h
n
e
e
d
i
n
g
B
P
A
t
r
a
n
s
m
i
s
s
i
o
n
c
o
n
f
i
r
m
a
t
i
o
n
n
o
w
a
t
d
i
f
f
r
e
n
t
p
r
o
j
e
c
s
i
z
e
s
t
h
e
n
a
l
l
pr
e
v
o
u
s
r
e
q
u
e
s
t
s
.
co
n
f
i
r
m
a
t
i
o
n
a
n
d
q
u
e
s
t
i
o
n
s
a
b
o
u
t
t
i
m
e
l
i
n
e
s
f
o
r
s
t
u
d
i
e
s
.
ak
s
i
n
g
f
o
r
c
l
a
r
i
f
i
c
a
t
i
o
n
i
f
p
r
o
j
e
i
s
2
1
M
W
o
r
3
0
M
W
e-
m
a
i
l
Mo
n
A
u
g
2
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
a
s
k
i
n
g
q
u
e
s
t
i
o
n
s
a
b
o
u
t
q
u
a
l
i
f
c
a
t
l
o
n
s
-
p
r
e
v
i
o
u
s
d
a
t
a
i
n
d
i
c
a
t
e
d
a
4
0
c
a
p
a
c
i
t
y
f
a
c
t
o
r
,
t
h
e
r
e
f
o
r
e
m
a
y
n
o
t
b
e
e
l
i
g
i
b
l
e
f
o
r
a
1
0
a
M
W
co
n
t
r
a
c
t
,
s
e
p
a
r
a
t
e
Q
F
'
s
(
1
m
i
l
e
)
,
o
t
h
e
r
i
n
f
o
r
m
a
t
i
o
n
p
r
o
v
i
d
e
d
i
n
d
i
c
a
t
e
s
a
s
i
n
g
l
e
5
1
M
W
p
r
o
j
e
c
t
(
s
a
m
e
p
r
o
j
e
c
t
l
o
c
a
t
i
o
n
,
s
a
m
e
in
t
e
r
c
o
n
n
e
c
t
i
o
n
,
s
a
m
e
B
P
A
t
r
a
n
s
m
i
s
s
i
o
n
r
e
q
u
e
s
t
,
e
t
c
)
Ch
r
i
s
t
i
n
e
a
d
v
i
s
e
d
t
h
e
y
h
a
d
1
m
i
l
e
s
e
p
a
r
a
t
i
o
n
.
e-
m
a
i
l
Mo
n
A
u
g
2
,
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
e-
m
a
i
l
Mo
n
A
u
g
2
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Id
a
h
o
P
o
w
e
r
a
d
v
i
s
e
d
,
b
a
s
e
d
o
n
p
r
e
v
i
o
u
s
i
n
f
o
3
0
M
W
n
a
m
e
p
l
a
t
e
a
t
4
0
c
a
p
a
c
i
t
y
f
a
c
t
o
r
w
o
u
l
d
n
o
t
q
u
a
l
i
f
f
o
r
a
l
D
a
M
W
c
o
n
t
r
a
c
t
.
I
s
d
a
t
a
co
r
r
e
c
?
W
h
i
c
h
p
r
o
j
e
d
o
y
o
u
f
i
l
e
d
i
n
t
h
e
T
S
R
p
r
o
c
e
s
s
f
i
r
s
t
?
tr
i
e
d
t
o
s
c
h
e
d
u
l
e
p
h
o
n
e
c
a
l
l
w
i
t
h
t
h
e
p
r
o
j
e
;g
~
Q
~
-
m
a
i
l
(Q
"
C
C
I
I
l
CD
õ
2
C
D
g
.
1\
:
:
z
3
o
,
.
0
C
D
-:
l
!
"
:
:
~'
i
:
¡
~
m
a
i
l
ã:
n
~
-ü
~
l
()
~
ll ~~
8/
3
/
2
0
1
0
-
8/
1
1
/
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Tu
e
A
u
g
1
7
,
2
0
1
0
Ch
r
i
s
t
i
n
e
M
i
k
e
l
l
Ra
n
d
y
A
l
l
p
h
i
n
fo
r
m
a
l
r
e
q
u
e
s
t
f
o
r
t
w
o
p
r
o
j
e
c
t
s
,
g
e
n
e
r
a
t
i
o
n
l
i
m
i
t
e
r
s
w
i
l
l
b
e
i
n
s
t
a
l
l
e
d
t
o
l
i
m
i
t
p
r
o
d
u
c
t
i
o
n
t
o
1
0
a
M
W
p
e
r
m
o
n
t
h
,
o
n
l
i
n
e
d
a
t
e
e
s
t
i
m
a
t
e
d
t
o
be
d
e
c
2
0
1
2
.
N
e
w
t
S
R
a
p
p
l
c
a
i
t
o
n
s
s
e
n
t
i
n
G
r
o
u
s
e
c
r
e
e
k
1
-
3
0
M
W
,
i
i
-
2
1
M
W
Fr
o
m
G
r
e
g
A
d
a
m
s
E-
m
a
i
l
a
n
d
l
e
t
t
e
r
Fr
i
Oc
t
1
,
2
0
1
0
sig
n
e
d
b
y
P
e
t
e
r
Ra
n
d
y
A
l
l
p
h
i
n
Ri
c
h
a
r
d
s
o
n
Fr
o
m
G
r
e
g
A
d
a
m
s
E-
m
a
i
l
a
n
d
l
e
t
e
r
Fr
i
Oc
t
1
,
2
0
1
0
sig
n
e
d
b
y
P
e
t
e
r
Ra
n
d
y
A
l
l
p
h
i
n
Ri
c
h
a
r
d
s
o
n
Le
t
t
e
r
Mo
n
N
o
v
1
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Pe
t
e
r
R
i
c
h
a
r
d
s
o
n
Gr
o
u
s
e
C
r
e
e
k
I
le
t
t
e
r
-
2
1
M
W
p
r
o
j
e
c
t
,
r
e
f
e
r
e
n
c
e
s
G
r
o
u
s
e
C
r
e
e
k
I
I
.
O
b
j
e
c
t
o
t
h
e
$
4
5
s
e
c
u
r
i
t
y
N
o
t
e
s
t
h
a
t
t
h
e
o
r
g
i
n
a
l
r
e
q
u
e
s
t
w
a
s
f
o
r
30
M
W
,
t
h
i
s
l
e
t
t
e
r
r
e
v
i
s
e
s
t
o
2
1
M
W
.
A
l
s
o
r
e
q
u
e
s
t
e
d
r
e
v
i
s
i
o
n
o
f
t
h
e
p
r
e
v
i
o
u
s
l
y
p
r
o
v
i
d
e
d
T
S
R
f
r
m
3
0
t
o
2
1
M
W
Sa
m
e
l
e
t
e
r
o
n
l
y
f
o
r
G
r
o
u
s
e
C
r
e
e
k
I
I
Le
t
t
e
r
f
o
r
G
r
o
u
s
e
I
,
I
I
a
n
d
t
h
e
t
w
o
S
w
e
n
y
p
r
o
j
e
c
t
s
.
I
d
a
h
o
p
o
w
e
r
d
i
s
a
g
r
e
e
s
w
i
t
h
t
h
e
i
r
c
l
a
i
m
s
.
A
g
e
e
t
o
s
t
a
n
d
a
r
d
t
e
r
m
s
o
f
t
h
e
S
a
w
t
o
o
t
h
wi
n
d
c
o
n
t
r
a
c
t
,
t
h
i
s
c
o
n
t
r
a
c
t
s
u
b
s
t
a
n
i
c
a
l
l
y
d
i
f
f
e
r
e
n
t
(
o
n
s
y
s
t
e
m
e
t
c
)
a
l
s
o
c
o
n
t
a
i
n
s
d
e
l
a
y
d
a
m
a
g
e
s
t
h
a
t
G
r
o
u
s
e
C
r
e
e
k
o
b
j
e
c
t
s
t
o
.
D
i
s
c
u
s
s
i
o
n
ab
o
u
t
c
o
n
f
u
s
i
o
n
o
n
p
r
o
j
e
c
t
s
i
z
e
s
,
S
w
e
e
n
y
r
a
n
c
h
s
t
i
l
i
n
p
l
a
y
,
e
t
c
.
E-
m
a
i
l
Ra
n
d
y
A
l
l
p
h
i
n
Pe
t
e
r
R
i
c
h
a
r
d
s
o
n
Th
u
N
o
v
4
,
2
0
1
0
ad
s
e
d
P
e
t
e
r
o
f
t
h
e
i
s
s
u
e
s
o
f
t
h
e
t
r
a
n
s
m
i
s
s
i
o
n
r
e
q
u
e
s
t
-
T
S
R
a
p
p
l
i
c
a
t
i
o
n
w
a
s
r
e
j
e
c
t
e
d
a
s
p
r
o
j
e
c
t
i
n
f
o
r
m
a
t
i
o
n
w
a
s
1
2
/
1
/
2
0
1
2
o
n
l
i
n
e
d
a
t
e
,
BP
A
t
r
a
n
s
m
i
s
s
i
o
n
i
s
s
e
t
f
o
r
J
u
n
e
2
0
1
3
,
B
P
A
t
r
a
n
s
m
i
s
s
i
o
n
i
n
d
i
c
a
t
e
s
a
2
1
M
W
a
n
d
a
3
0
M
W
P
o
r
j
e
c
t
,
l
a
s
t
i
n
f
o
r
m
a
t
i
o
n
t
o
I
d
a
h
o
p
o
w
e
r
w
a
s
fo
r
t
w
o
2
1
M
W
p
r
o
j
e
c
t
s
.
A
d
v
i
s
e
d
t
h
e
p
r
o
j
e
c
t
t
o
p
r
o
v
i
d
e
n
e
w
t
r
a
n
s
m
i
s
s
i
o
n
I
n
f
o
r
m
a
t
i
o
n
t
h
a
t
i
s
c
o
n
s
i
s
t
e
n
t
w
i
t
h
t
h
e
B
P
A
I
n
f
o
r
m
a
t
i
o
n
a
n
d
I
wo
u
l
d
w
a
i
t
t
o
f
i
l
e
a
n
e
w
T
S
R
u
n
t
i
l
I
h
a
d
r
e
c
l
e
v
e
d
t
h
a
t
r
e
i
s
e
d
i
n
f
o
r
m
a
t
i
o
n
.
A
l
s
o
a
d
v
i
s
e
d
t
h
a
t
t
h
e
p
r
o
j
e
c
t
w
o
u
l
d
n
e
e
d
t
o
ac
q
u
i
r
e
a
n
c
i
l
a
r
y
se
r
v
c
e
s
f
r
o
m
s
o
m
e
o
n
e
o
t
h
e
r
t
h
e
n
I
d
a
h
o
P
o
w
e
r
a
s
t
h
e
s
e
p
r
o
j
e
c
t
a
r
e
n
o
t
i
n
I
d
a
h
o
P
o
w
e
r
s
e
r
v
i
c
e
t
e
r
r
i
t
o
r
y
.
Le
t
e
r
We
d
N
o
v
2
4
,
2
0
1
0
Do
n
o
v
a
n
W
a
l
k
e
r
Pe
t
e
r
R
i
c
h
a
r
d
s
o
n
To
K
r
i
s
s
S
a
s
s
e
r
,
E-
m
a
i
l
Mo
n
N
o
v
2
9
,
2
0
1
0
Pe
t
e
r
R
i
c
h
a
r
d
s
o
n
Id
a
h
o
Po
w
e
r
co
p
i
e
d
Fr
o
m
G
r
e
g
A
d
a
m
s
E-
m
a
i
l
a
n
d
l
e
t
t
e
r
Th
u
D
e
c
2
,
2
0
1
0
si
g
n
e
d
b
y
P
e
t
e
r
Do
n
o
v
n
W
a
l
k
e
r
Ri
c
h
a
r
d
s
o
n
Mo
n
D
e
c
6
,
2
0
1
0
Mi
c
h
a
e
l
Da
r
r
i
n
g
t
o
n
E-
m
a
i
l
Tu
e
D
e
c
7
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Pe
t
e
r
R
i
c
h
a
r
d
s
o
n
le
t
e
r
p
u
t
t
i
n
g
p
r
o
j
e
c
t
s
o
n
n
o
t
i
c
e
t
h
a
t
t
h
e
y
w
e
r
e
r
e
q
u
e
s
t
i
n
g
t
o
m
o
v
e
f
o
r
w
a
r
d
w
i
t
h
a
t
P
P
A
p
r
i
o
r
t
o
t
h
e
I
n
t
e
r
c
o
n
n
e
c
t
i
o
n
I
t
r
a
n
s
m
i
s
s
i
o
n
Is
s
u
e
s
a
n
d
c
o
s
t
s
b
e
i
n
g
k
n
o
w
n
Re
q
u
e
s
t
e
d
I
P
U
C
s
t
a
f
f
to
n
o
t
i
s
s
u
e
s
u
m
m
o
n
s
t
o
I
d
a
h
o
p
o
w
e
r
a
s
t
h
e
y
"
t
e
n
t
a
t
i
v
e
l
y
r
e
a
c
h
e
d
a
s
e
l
e
m
e
n
t
w
i
t
h
I
d
a
h
o
P
o
w
e
r
"
a
n
d
f
i
n
a
l
se
t
t
l
e
m
e
n
t
s
h
o
u
l
d
b
e
I
n
t
w
o
o
r
t
h
r
e
e
w
e
e
k
s
.
Ac
k
n
o
w
l
e
d
g
e
d
D
o
n
o
v
a
n
s
l
e
t
t
e
r
o
f
N
o
v
2
4
,
a
s
k
d
e
d
f
o
r
T
S
R
c
o
n
f
i
r
m
a
t
i
o
n
f
o
r
t
w
o
2
1
M
W
p
r
o
j
e
c
t
s
,
f
i
r
s
t
e
n
e
r
g
d
a
t
e
s
o
f
d
e
c
2
0
1
2
.
T
h
e
y
a
r
e
re
a
d
y
t
o
s
i
g
n
,
b
u
t
u
n
d
e
r
s
t
a
n
d
o
u
r
n
e
e
d
f
o
r
a
d
d
i
t
i
o
n
a
l
r
e
v
i
e
w
,
t
h
e
y
e
n
c
l
o
s
e
d
t
h
e
i
r
c
o
p
i
e
s
o
f
t
h
e
c
o
n
t
r
a
c
t
s
(
n
o
t
e
t
h
e
c
o
n
t
r
a
c
t
c
o
p
i
e
s
n
o
w
sh
o
w
P
a
c
l
f
i
C
o
r
p
a
s
t
h
e
t
r
a
n
s
m
i
s
s
i
o
n
p
r
o
v
i
d
e
r
?
)
Re
c
e
i
v
e
d
r
e
v
i
s
e
d
T
r
a
n
s
m
i
s
s
i
o
n
Q
u
e
s
t
i
o
n
a
l
r
e
Dr
a
f
t
c
o
n
t
r
a
c
t
s
s
e
n
t
t
o
P
e
t
e
r
,
a
d
v
i
s
e
d
t
h
e
m
t
h
a
t
t
h
e
d
r
a
f
t
a
g
r
e
e
m
e
n
t
s
p
r
o
v
i
d
e
d
b
y
t
h
e
p
r
o
j
e
c
t
h
a
d
a
l
o
t
o
f
f
o
r
m
a
t
i
n
g
,
f
o
n
t
a
n
d
o
t
h
e
r
is
s
u
e
s
,
r
e
q
u
i
r
e
d
t
h
a
t
w
e
c
r
e
a
t
e
n
e
w
d
r
a
f
t
a
g
r
e
e
m
e
n
t
s
.
A
d
v
l
s
e
d
w
e
s
t
i
l
n
e
e
d
e
d
a
c
c
u
r
a
t
e
l
o
c
a
t
i
o
n
i
n
f
o
r
m
a
t
i
o
n
a
s
t
h
e
p
r
o
j
e
c
t
p
r
o
v
i
d
e
d
dr
a
f
t
s
h
a
d
i
d
e
n
t
i
c
a
l
lo
c
a
t
i
o
n
s
f
o
r
b
o
t
h
p
r
o
j
e
c
t
s
.
~;
i
Q
'ä
~
~
CÑ
:
i
Z
g,
~
~
l
.
m
a
i
l
..
c
.
_
,
.
II
"
t
z~-
::
~
.
.
()
~
E
-
m
a
i
l
Tu
e
D
e
c
7
,
2
0
1
0
Ra
n
d
y
A
l
l
p
h
i
n
Id
a
h
o
P
o
w
e
r
i
n
t
e
r
n
a
l
r
e
v
i
e
w
o
f
d
r
a
f
t
c
o
n
t
r
a
c
t
b
e
g
u
n
Th
u
D
e
c
9
,
2
0
1
0
Pe
t
e
r
R
i
c
h
a
r
d
s
o
n
Ra
n
d
y
an
d
Do
n
o
v
a
n
Mi
c
h
a
e
l
Da
r
r
i
n
g
t
o
n
Pe
t
e
r
R
i
c
h
a
r
d
s
o
n
re
q
u
e
s
t
e
d
a
d
d
i
t
i
o
n
a
l
i
n
f
o
r
m
a
t
i
o
n
t
o
c
o
m
p
l
e
t
e
t
h
e
c
o
n
t
r
a
c
t
s
,
t
r
a
n
s
m
i
s
s
i
o
n
e
n
t
i
t
y
,
lo
c
a
t
i
o
n
d
e
s
c
r
i
p
t
i
o
n
s
Tu
e
D
e
c
1
4
,
2
0
1
0
~T ~
Gr
o
u
s
e
C
r
e
e
k
a
g
r
e
e
s
t
o
t
h
e
d
e
l
a
y
p
r
o
v
i
s
i
o
n
s
,
b
u
t
a
s
k
i
n
g
t
o
c
h
a
n
g
e
t
h
e
f
i
r
s
t
e
n
e
r
g
y
a
n
d
o
p
e
r
a
i
o
n
d
a
t
e
s
.
F
r
o
m
1
2
/
1
2
a
n
d
6
/
1
3
t
o
6
/
1
3
an
d
1
2
/
1
3
E-
m
a
i
l
We
d
D
e
l
;
,
2
0
1
0
Ra
n
d
A
I
p
/
n
Pe
I
'
R
.
l
d
l
a
r
d
s
o
E,
m
a
i
l
We
d
D
e
1
5
,
2
0
1
0
Gre
g
Ad
m
s
Ri
d
y
,
M
i
d
l
an
d
Oo
o
v
a
n
E-
m
a
i
l
Th
u
D
e
1
6
,
2
0
1
0
Ml
d
i
a
e
l
G.
.
A
d
a
m
s
f!
n
E.
m
a
l
Th
u
D
e
1
6
,
2
0
1
0
Ra
n
d
v
A
l
1
p
t
i
l
'
G.
.
A
d
m
s
Ra
i
:
t
h
e
d
i
n
p
i
n
d
i
e
s
r
e
q
~
b
y
P
e
r
In
12
1
9
e
-
m
a
i
l
a
n
d
a
s
.
t
o
p
t
d
e
~
e
!
n
r
m
l
o
n
M
i
d
i
h
a
d
t
e
q
U
è
t
è
d
.
S.
.
p
r
o
v
l
d
e
l
o
t
l
d
e
s
p
t
O
l
S
a
n
d
t
r
n
s
m
Î
$
n
p
l
'
r
n
a
m
e
b
e
l
l
'
B
P
A
.
Ml
d
i
r
e
q
u
e
v
e
i
1
1
o
o
f
t
h
e
d
a
-
G
r
e
h
a
n
o
P
f
d
è
t
l
l
l
u
a
l
d
a
y
I
n
h
l
s
p
t
e
r
e
.
/
4
d
e
d
a
m
a
g
e
a
r
e
bi
s
è
o
n
a
c
t
a
l
d
a
y
s
,
t
h
e
d
a
v
i
n
f
o
I
s
v
e
i
m
p
o
D
e
1
v
s
D
e
3
1
c
a
n
m
l
k
f
1
v
e
b
l
i
d
l
f
n
æ
.
NÐ
t
e
d
,
t
h
e
p
r
j
l
~
W
l
r
e
l
'
f
o
r
$
i
g
n
r
e
a
s
l
f
:
t
w
a
e
d
t
i
s
w
,
m
a
t
h
e
m
o
r
If
t
h
e
w
o
u
l
d
p
1
k
t
l
è
l
u
p
.
E.
-
m
a
i
l
Th
u
D
e
i
6
,
2
0
0
Gì
1
A
d
m
s
fl
n
d
a
l
'
d
M
i
d
e
a
l
G
r
e
s
a
d
t
h
w
o
u
l
d
p
!
d
t
h
!
l
m
u
p
i
l
l
'
n
.
T\
D
e
2
!
,
2
0
Co
í
t
r
,
s
l
J
l
b
y
th
p
r
j
é
Tu
e
D
e
2
!
,
2
0
0
Cø
r
a
e
t
s
e
t
b
i
i
ø
l
d
à
o
P
O
v
l
a
o
v
l
g
h
d
e
l
i
v
r
y
Tu
e
Q
e
2
8
,
2
0
1
0
Qi
i
:
s
l
p
b
y
l
d
l
1
o
P
O
We
d
D
e
2
9
,
2
0
1
0
CO
i
:
f
l
l
e
d
a
t
I
P
U
C
;'
~
Q
ì
1
lQ
"
O
c
i
1
l
CD
2
:
C
D
9
-
""
:
J
Z
3
a
~
l
i
C
D
~
i
s
:
"
a
II
"
U
z
~n
?
:-
m
.
.
"U
.
:
("
~
ii ~~~
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO.2
&hin, Randy
From:
sent:
To:
Subject:
Allphin. Randy
Wednesday,'NIãf~ oa. 201. 12:24 PM
'Christine Mikell
RE: sample PPA. interconnectin and transmission capacit press
Yes, there is a deduction from the avoided cost for wind projects as well as the price in seasonalized and adjusted for
Heavy load and light load hours.
If you follow this link to the Idaho Public Utilty Commission website" it Isa wind contract that was flied and approved in
2009. This wil provide you the general concepts that would be In a potential cOntract for your project.
The prices, wil need to be adjusted to prices approved by the IPUC at the time an agreemerit is e)(ecuted as well as any
other current rules and regulations wil need to be included in any agreement we were to enter irito.
htiø:J/ww.puc.idaho.gO'/intetnet/cases/elec/IPC/IPCE0925/20011APPUCATION.POF
Randy
From: i(;lit!~~Mjk'etl (manto:christine(gwasatehwind.comJ
set: Wednesday¡;tl~r(thQat?OlQl1:49 AM
To: Allphin, Randy
SLlbje: RE: sample PPA, interconnecn and transmission capaci prces
i hate to do this, but i have another, hopefuiiy last question. Is there a balancing charge on all QF's or Just the 10 A MW
projects? We are having an internal debate and clearly subtracting out the $5 !MW from the PPA rate is Significant.
Thanks.
From: A1lphUî,Ranciy Imalfto:RAllphin(gkJahopower.comJ
sent: Wedney,Mard:OI,2010 LO:52 AM
To:, Christine Mikell
Subjec: sample PPA, interconnecin and trnsmission capacity proces
Christine - copied below Is the generic language that I put in letters to potential PURPA projects that are wanting
contracts with Idaho Power. As your project is off of the Idaho Power system~ added steps to deal with the
interconnection and transmission provider(s) arrangements would need to be added to this letter for your specific
project.
In thinking through the process, I envision that at the point you provide confirmation of the IA and BPA transmission l
would put an official letter together for you with this information, requests and requirements.
This e-mail isfergenericil1formation purposes only, it is not 21 commitment by IdahO' Power
to purchase energy from this project, or is it to be con$idered to be offcial notification of a
specifie process.
1 Attachment NO.2
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of 10
Randy
xxxxxxx,
Summarized below is a brief outline of the purchase power agreement, interconnection procéSS and
transmission capacity requirements for your proposed generation project.
Purchase Power Agreement
The project you have described appears to be eligible for a purchase power agreement under the guidelines for
a Qualifying Facilty as defined by the Public Utilties Regulatory Policies Act of 1978 (PURPA). At the time you are
ready to proceed with a purchase power agreement for this project, Idaho Power wil prepare a purchase power
agreement that complies with the current rules and regulations that govern these PURPA agreements, any draft
purchase pOwer agreements previously provided to you for review must be updated to include current rules arld
regulations.
PrIor to Idaho POWer executing a purchase power agreement it wil be required thatyo,- have;
1.) Provided documentation thatsubstantiates that the project has fied for interconnection and IS in
compliance with any payments and/orother requirements specified in the Interconnection process
for this project and;
2 Attachment No. 2
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of 10
2.) Receivedaild accepted an interconnection feasibilty study for this project and;
3.) Returned a signed copy of this letter Of understanding and all of the required infOrmation to enable
Idaho Power to file an application requesting transmission capacity for this project. Co.mpletion of the
enclosed Transmìssion Capatity Application Questionnaire wil provide the majority of thìs
information and;
4.) Confirmation that the results of the initial transmission capacity application are known and the
project accepts these results and intends tlJ continue with the development of t~e prlJject inc:luding.
if applicable, execution of a Network Resource integration StudY Agreement in the formendosed
herein.
Interconnection and Transmission Capacity
Your project wil be responsible for all costs of physically interconnecting the project to the Idaho Power
electrical system and any costs associated withacquìring adeqUate firm transmission capacity on the Idaho Power
transmision system to enable the project's energy to be delivered to Idaho Power c:ustomers.
Interconnection
Your project wil be required to complete the interconnection process and execute a Generation
Interconnection Agreement (tiGIAN).
TransmissIon Qipacity
To sell your projects energy to Idaho Power, your project must be designated as a Netwrk
ResourCe ("DNRN).
In order for this project to achieve DNR status, Idaho POWer is required to make a request (complete
and file an appUcation) and be granted firm transmission capacity from the Idaho Power delivery
business unit (tiDelivery") to move your projects energy from the physical interc:onnection point to
Idaho Power customers. In accordance with various rules and regulations, the project must be granted
DNR status no later than 60 days prior to the project delivering any energy to Idaho Power.
IdahO Power wil begin this firm transmission capacity application process only after the project has
returned a signed copy of this letter of understanding and aU of the information reqUired for Idaho
Power to file this application (see attached Transmission Capacity Application Questi.onnaire).
After filng a complete firm transmission capacity application with Delivery, Idaho Power wil receive
notification back from Delivery Within 30 days that: (a) ade.quate transmissìoneapacity is available for
this project without the need to construct upgrades; or (b) a transmission capacity system impact study
is required to determine the available transmission capacity and/or required upgrades; .or (c) a
statement of the required transmission upgrades and the associated costs. Idaho Power wil notify the
project of this response to the transmissi.on c!'pacity application in a timely manner after the response
is received from Delivery.
If the response from Delivery is as specified in item (a) (transmission capacity is avatlable), the
project wil be required to execute a purchase power agreement with Idaho POwer Within 30 days in
order to retain this transmission capacity reservation.
If the response from Delivery is, as specified in items (b) or (c) (stUdies reqUired and/or Upgrades
required), the project wil be required to execute a Network Resurce Integration Study Agreement
(sample copy attached for your information) and submit all required deposit or fees within 15 days
after receiving notification of this requirement in order for Idaho Power to continue the transmission
capacity request. This Network Resource integration Study Agreement wil specify that the project wil
Attachment No. 2
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 3 of 10
3
be responsible for costs incurred by Idaho Power to perform any required studies. If, after the studies
are concluded the project wishes to continue the pursuit of transmission capacit, the project wil also
be responsible for all transmission system upgrade costs identified within the studies. The fees and
costs will be in the form of both initial deposits as well as actual costs. If at any time after executing
the Network Resource Integration Study Agreement the project does not pay any required fees, or
elects to stop the transmission study or upgrade process, the project shall be responsible for all costs
incurred by Idaho Power in performing the studies or upgrades up to the point of termination of the
Network Resource Integration Study Agreement.
Upon successful completion of the above described transmission capacitY upgrade process, a
transmission capacity reservation wil exist for this project. However, in order to. finalize this
transmission caPacitY reservation, a purchase power agreement with Idaho Power must be executed
no later than30 days after the transmission capacity upgrades are completed. If the purchase poWer
agreement is not executed by this deadline, the transmission capacitY reservation wil be released aM
this process wil have to be repeated jfthe projed later requests transmission capacitY.
As noted earlier, this tran.smission capacitY acquisitioriand assoc.lated Network Resource
designation must be comp.leted, at the minimumi 60 days prior to the project delivering any energy to
Idaho Power. In addition, the project must provide routine updates to Idaho Power of the expected
online date of the generation project to ensure Idaho Power is capable of accepting the energy from
the project on the actual date the project comes online.
From:i€hristine;Mikèll rmailto:chriStine~wasatchwind.com)
s.nt: Wedneday, MarClti ,Qs,20i09:19 AM
To: Aiiphin, Randy
Subjec: RE: QF contract reuest
Hi Randy,
Thanks for your quick response. As a follow-up (I also left you a VM), if we were to pursue a 60 MW OJ project, how is
the pricing determined? I~ it based on n.atural gas or coal avoided cost? Is there a range that you have been dealing with
I,ately. The CFO and I have been going back and forth about this-l think that the Q,F pricing would be north of $71/MW
and he thinks it is significan.tly less.
Also, the pricing, is it leveUzed and is there a component of time of day pricing?
Thanks,
Christine
From: Allphil'i Randy (mailto:RAllphin(§idhopower,comJ
sent: Wednesay, MardJ 03, lQl0 8:42 AM
To: Christine Mikell
Subjec: RE: QF Clontract request
Christine,
I received word back from the transmission group on timelines in regards to notification to transmIssion capacitY
application filngs.
They advised that they are required to provide an inftial response to an application within 30 days of r'Eèeivng the
"complete" application (if information is missing, etc the 30 days does not start until all required information is
subriitted). This initial response wil be in the form that transmission capacity is available or that it is not available and
additional studies are required. The applicant then has 15 days to act on the response received from the transmission
4 Attachment No. 2Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 4 of 10
group in order to retain the statues (que position) of the Initial request. l,am not sure hOw many days they have to
complete any required studies.
Randy
From: AfJphin, 'Randy
Sent: Wednesday; Ma.rch 03, 1010 7:03 AM
To: 'Christine Mikell'
Subjec: RE: QF contract request
Christine, i am around all day today (Wednesday).
Idaho Power transmission - we can get the application flied within a couple weeks of when you supply all of the
required information and confirmation of the IA and BPA transmission. As far as how long i,t takes to get a response
back from our transmission group, they have some strict FERC guidelines they must adhere to and I believe they have 60
days to respond to the application. There response to the application may very well be that they must perform system
impact studies to determine if there is transmission. If this is the case, then more time is needed to get transmission
answers.
I wil double check on these time lines and get bacho you this morning.
Project size - if it is determined that you are simply splitting up a single larger project into two smaller projects to take
advantage of the 10 average MW pricing, Idaho Power wil most likely not agree to sign these agreements as We believe
this is truly not the intent of this 10 average MW designation and is actually "gaming" the process. You wil be weltome
to take your case to the commission and we would then both abide by their ruling.
Randy
From: .(brl~neMlkell Cmailto:christne(gwasatchwind.com)
Sent: TuesdY,llarc~ .02, .201.0 4:a6 PM
To: Allphin, Randy
Subjec: RE: QFcontract reques
AnsWèrs below in black. So" if we can get the Transmission secured and the IA signed by the end of the week, do you
think that Idaho Power could confirm tran.smÎsslon in the next two weeks. In the meantime, Would you be able to supply
us with the PPA so we can work with our investor to post the project development security?
Thanks.
From: AIIPJ'ir, ~I'd¥ (manto:AAllphintQldhopower.com)
Sent: Tuesay, Marc 02/2010 7:44 AM
To: Christine Mikell
Cc: John Aubrecht
Subject: RE: QF contract request
Christine,
Thanks for thIs information, some details (clarification) i need before I can start sorting out where we go from
here-
No question, the fact that your project is not in the Idaho Power serviçe territory creates a lot of complications,
5 Attachment No. 2
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 5 of 10
1. Raft River interconnection - you do have a completed interconnection ,agreement with Raft RiVer or with
SPA? No. bUt it is something we cán get in the next two weeks. If so what Is the nameplate rating contained
within that liiterconnectionagreement? We are grappling between one 10 Average MW project or two 20
MW project with a mile separation What is the estimated construction schedule etc of the
interconnection? Online date would be 1st quarter 2011
2. BPA transmission - you have not yet actually filed a transmission request with BPA? No Does the BPA
process require a non refundable deposit right from the start? I am verifying
3. Project size - utilmately, Idaho Power Power supply will need to request transmission capacitY for your
project from the Idaho Power transmission group (If you wish to sell your energ to Idaho P'Ower). To do this
we wil need to know the exact nameplate capacity of your planned project.
a. Back tQ' the chicken and egg. I know from past experience thi:t the Idaho Power transmlssion group
(FERC requìrements) wil require in the application for transmission cclpacity on the Idaho Power
system informcltion that the project has secured interconnection from the hQst utility (Raft river)
and that the project has verified with the transmitting entity(s) (BPA) that firm transmission for the
full nameplate rating is available to the Idaho Power interconnection point before they wil even
accept an applicøtion requesting review of available transmissfon capacity on the Idaho Power
system,
4. PPA -Idaho Power wil not execute a PPA until the project is able to demonstrate that all three of the atrve
issues are resolved. That is the project does have an interconnection agreement and firm transmission
capacity is available and reserved on both the BPA and Idaho Power transmission sYstem to get the energy
from the project to Idaho POwer customer I.oads.
a. One of the key items in any PPA Idaho Power wil sign wil be thc1t the project is required to post
security of approximately $4$ per KW (nameplate -10 IVW nameplate would equal $450,000) at
the time the contract is signed and if the project does not begin deliveries of .energy to Idaho Power
within 90 days of the estimated online date, the project will forfeit dami:ges tQ Idaho Power equal to
the $45 per KW, Delays in interconnection. unavailabilty of finn transmission,. etc are not relief
from performance within the agreement, Therefore as you can see, even if Idaho Power were able
to sign a PPA prior to having the interconnection and transmission capae:ity seciired, there is
tremendous fil'ancial risk your project would be e)(posed to ifthe interconnection and transmission
capacity is nOt resolved prior to signing a PPA,
b. Energy price and potential chi:nges -I haVe also heard rumors thc1t the cQmmission may possibly be
changing the PURPA published c1voided cost rates. Idaho PQwer wil have no choiceb.ut to adhere
to any new orders issueci by the commission at the time the orders become effective.
No black and white answers. and I realize the answers to my questions may be in your letter. but I want to be absolutely
sure of the answers to these questions before I continue working these issues over with the appropriate experts.
Randy
From: Christine Mikell (mailt:christine(gwasachind.comJ
sent: Friday, Febru~ry 26, 20105.30 PM
To: Allphin, Randy
Cc: John Aubrecht
Subject: QF contract request
Randy Allphin
6 Attachment NO.2
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 6 of 10
Senior Planning Administrator
1221 W Idaho Street
Boise, 10 83702
Tel: (208) 388-i614
raUphin t!idahopower.com
Dear Mr. Allphin,
Wasatch Wind Int.ermountain would like to request that Idaho Power commence Power Purchase Agreement
negotiations with oUr subsidiary, Grouse Creek Wind Park, LLC for .elther a 10 Average MW or something less
than 80 MW Qualifying Facilty under PURPA. We believe we have completed the necessary due dilgence to
move forward with Idaho Power.
The project, in Northwestern Utah on private land, is unique in that we interconnect to a Raft River Electric
line that is leased to Bonnevile Power Adminlstration. We recently signed the faciltY study agreement with
BPA and expect to have an executed interconnection agreement with Raft River Electric by June. We (Jre
currently working with Idaho Power to determine its requirements because they are the balancing authority.
Due to the project's location on private land, there is no requirement for a NEPA analysis. However.. WWI has
conducted two years of wildlife surveys. We have had two met towers up for about two years. We hold the
land lease with the private landowner where the wind farm is located and we are in final negotiations with the
landowner where the transmission line wil be routed. The miltary has supported the project as long as the
intertie line is under 100 feet.
Having said all this, we understand that in order for you to view our project as serious and tender the Power
Purchase Agreement and to make the necessary Network Service request for this Qualifying Facility, Idaho
Power needs to be sure that we have the necessary transmission rights secured. BPA has maintained we wm
be able to make that transmission service request sometime next week. However, as you probably know,
when a deposit is made to secure firm point to point transmission and the request is approved, the
transmission is binding to WWI through the take or pay contract provision. Per your suggestion, WWI went
ahead and confirmed on OASIS to the best of our abilty that there is capacity from Minidoka Substation to
Treasure. Valley for Idaho Power to obtain the Network Service on behalf of our Qualifying Facilty. If there
truly is available ATC between these two points, we wil make our transmission service request.
We find ourselves in a chicken and egg dilemma by which, if we are wrong and there is no available ATt, we
have firm stranded transmission with no buyer. Here we sit, knowing that the pricing will change downwardly
by the end of March and we are desperate to know about the available ATC. We must act quickly, but at the
same time we must be prudent. Has this situation occurred during your time In this position? Do you see
that Idaho Power would move forward on a network service request on our behalf? Or is the only solution that
we make a TSR to Idaho Power between these two points and then if there is capacity, somehow withdraw
our request before it Is binding?
Any thoughts that you may have would be greatly appreciated.
Kind regards,
7 Attachment No. 2
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 7 of 10
Chrne Watn Mlkensenior Pt oewlomeMaàgOirêt .4353-14
MØb.lø:ao1~104
GleanMeY. Clönait..cleárt èBl.WW~i:,eøi.
Wasach Wind
Tkistinmøy __ ìnrQmiotba æprvill ~lImi im~lI~claw.It~~..l~..~ ~.~
øofi,ii any tr*~~ll disiriMi:U$oflh ibtò~lM (îllwri~ tleo) IdTlUCTLYPaJlBIT. ftyon:vetli:lg~Ùl ibem,~ im.iIeMll, il,Si aM ~lhin ibitteitlre. wl~ba ib"~~ haKl. _ tØl TkIl~
.Attachment NO.2
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 8 of 10
Wasatch Wind
R~ndy Allphin
Senior Planning Administrator
1221 W Idaho Street
Boise, /083702
Tel: (208) 388-2614
rallphin(§idahopower .com
Dear Mr. Allphin,
Wasatch Wind IntermOuntain would like to request that Idaho Power comme.nce Power
Purchase Agreement negotiations With our subsidiary, Grouse Creek Wind Park, LlC for either Cl
10 Average MW or something less than 80 MW Qualifying Facility under PUR;PA. We believe we
have completed the necessary due diligence to move forward with Idaho Power.
The project, in Northwestern Utah on private land, is unique in that we interconnect to a Raft
River Electri,c line that is leased to Bonnevile Power Administration. We recently signed the
facilty study agreement with BPA and expect to have an executed interconnection agreement
with Raft River Electric by June. We are currently working with Idaho Power to determine its
requirements beCause they are the balancing authority.
Due to the project's location on private land, there is no requirement for a NEPA analysis.
However, WWI has conducted two years of wildlife surveys. We have had two met towers up
for about two years. We hold the land lease with the private landowner where the wind farm is
located and we are in final negotiations with the landown,er where the transmission line wil be
routed. The miltary has supported the project as long as the intertie line is under 100 feet.
Having said all this, we understand that in order for you to view our project as serious and
tender the Power Purchase Agreement and to make the necessary Network Service request for
this Qualifying Fa,cility, Idaho Power needs to be sure that we have the necessary transmission
rights secured. SPA has maintained we wil be able to make that transmission service reque,st
sometime next week. However, as you probably know, when a deposit is made to secure firm
point to point transmission and the request is approved, the transmission is binding to WWI
through the take or pay contract provision. Per your suggestion, WWI Went ahe.ad and
confirmed on OASIS to the best of our abilty that there is capacity from Minidoka Substation to
Treasure Valley for Idaho Power to obtain the Network Servce on behalf of OUr Qualifying
2700 Homestead Road. Suite 210. Park, C, it, . Utah ., &40ge. Offce: 435-657,2550. ww.wasatèhwind.com. Attachment NO.2clean energy. Clean atr. clean earth. Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 9 of 10
~Wasach Wind
Facilìty. If there truly is available ATC beteen these two points, we wil make our transmission
service request.
We find ourselves in a chicken and egg dilemma by which, if we are wrong and there is no
available ATC, we have firm stranded transmiSsion with no buyer. Here vr sit, knowing that
the pricing wil change downwardly by the end of Marchand we are desperate to know about
the available ATC. We must act quickly, but at the same time we must be prudent. Has this
situation occurred during your time in this position? 00 you see that Idaho Power woliid
move forward on a network service request on our behalf?
Any thoughts that you may have would be greatly appreciated.
Kind regards,
Christine Watson Mik.ell
435-503-8814
2700 Homestead Road. Suite 210. Park City. Utah,. 84098 . Offce: 435-657~2550. ww.wasatchwind.oom. .' Attachment No. 2clean enegy. clean air. clean earth. Case Nos. IPC~E~10~61 & IPC~E~10-62
Allphin Affidavit, IPC
Page 10 of 10
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO.3
~hin!Randy
From:
Sent:
To:
Subject:
Attchments:
G/lristine Mikell (christine~wasatchwind.coml
Thursday. April 22,2010 11:54 AM
Allphin, Randy
12X24 for Grouse Creek OF request
Grouse Creek 12X24201 0_ 4_22. pdf
Hi Randy,
Attached you wil find the 12 X 24 for your pricing model. Let me know if you need an excel version of it.
Thanks,
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air, clean earth.
ww.wasatchwind.com
Wasatch Wind
:-i;
This message and any attachments contain information that iS propnetary, confidentlal and privileged They are intended for the pnvate and exclusive use of the addressee arid are covered by the
Elecronic Communications Privacy Act, 18 U$ C §§ 2510~2521 Unless you are the addressee (or authorize to receive for the addressee) you may eot use, copy, print or disclose to anyone this
message or any information contained in the message and anyatlachmenls If you have receiveå this communication in eror. please advise the sender by reply and delete this message
From: Allphin, Randy (ma11t:RAlph1n(Qldahopor.col
sent: Wednesday, April 21, 2010 2:27 PM
To: Christine Mikell
Subject: RE: sample PPA, lnterconnecin and transmission capacity process
Thanks for the information, I wil get a letter turned around to you.
Last we spoke you were not sure of the project size, if you are settling in on the 57 - 65 mW project I wil need to
develop energy prices for this project. The published prices apply to only projects that are 10 average MW or smaller.
To enable me to start running the pricing models we wil need at minimum estimated monthly energy shape from your
project (daily or hourly is even better).
Randy
1
Attachment NO.3
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of6
~hin! Randy
From:
Sent:
To:
Subject:
Christine Mikell (christine~asatchwind.comi
Wednesday, May 05. 2010 3:53 PM
Allphin, Randy
RE: Grouse Creek OF request
Hi Randy,
I wanted to check in to see where we are at with our Grouse Creek QF request. I assume you have all that you need. If
you can give me an update, that would be helpful!
Thanks,
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth,
WW.wasatchwind.com
Wasatch Wind
This message and any attachments contain Information that is proprietary, confidential and priviege They are intended fo the private and ""clusive use of the addresee and are covere by !he
Beclron,c Communications Privacy Act, 18 USC, §§ 2510-2521 Unless you are !he addressee (or authonze to reeive for the addressee) you may not use, copy. prini or disclose to anyone lhis
mesage or any information contained in the message and any attachments If you have received this comunication in error, please advise the sender by reply and delete this message
From: Allphin, Randy fmajlt:RAlghioClldhopor.col
sent: Wednesday, April 21, 2010 2:27 PM
To: Christne Mikell
Subjec: RE: sample PPA, interconnecin and transmission capacity process
Thanks for the information, I wil get a letter turned around to you.
Last we spoke you were not sure of the project size. if you are settling in on the 57 - 65 mW project I wil need to
develop energy prices for this project. The published prices apply to only projects that are 10 average MW or smaller.
To enable me to start running the pricing models we wíl need at minimum estimated monthly energy shape from your
project (daily or hourly is even better).
Randy
1
Attachment NO.3
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of6
.chin, Randy
From:
Sent:
To:
Cc:
Subject:
Attachments:
Christine Mikell (christine~asatchwind.comJ
Friday, May 14,20109:21 AM
Allphin, Randy
Pagoaga, Richard; John Aubrecht
RE: Wind generation data
Grouse Creek 12X242010.-..4_22IDPCO 2010..ß_13.xlsx
Hi Randy,
Attached is the 12X24 matrix with the total for all turbines. i am not sure how to address your concern about having
hours of the days with no winds. We simply took the data from our met towers, correlated it to historical wind data and
that 12X24 matrix came out. You wil see that in the summer months in some ofthe hours there is significantly little
winds, but at no time over the course of those hours in a month are they zero. I would be happy to walk you through
this should you have any questions.
Thanks,
Christine
From: Allphin, Randy rmârt:RAIPhiriOldahopøeørnl
Sent: Thursay, May 13, 2010 3:05 PM '
To: Christine Mikell
Cc: Pagoaga, Richard
Subjec: Wind generation data
Christine,
As we work through the model to create pricing for your project we have found that the data you previously
supplied does not get us the information we need to be able to run the pricing modeL.
In order to run our model, we need estimated hourly energy deliveries to Idaho Power for each day of at least
on full year and for the entire facilty. The data you previously supplied appears to be just data for one turbine and also
it indicates that the turbine wil generate every hour of every day. This does not seem realistic as I assume there wil be
hours when the wind is not blowing.
If you could please Itreply to all" to this e-mail your response and data wil also be routed to our team members
that are running the model so they can get working on things as soon as it is received
Thanks Randy
BEt.M~æp~
1
Attachment NO.3
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 3 of6
Thli uwiniø! iny cOnllrt infullÎon that l$pn..i~ eollfitialai(l exei ii di~ ii lJlkall (aw.lfyó at il ih ii reyoiuiie iinotified tl any dÎløCopii dii;nbuill or us of ih inRili()litai he (inlllng any reliçe 1l1!) idTRICT Y PROHIBIT. rfyc revell
iiiniS$101l in Q',plæs imrrately conlad the se an des the inteîal in it en, wbeineleìc lltliii c: lb. Thk yo
1,Attachment No.3
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 4 of6
~hin, Randy
From:
Sent:
To:
Subject:
Christine Mikell (christine~wasatchwind.comJ
Wednesday, May 19,20103:23 PM
Allphin, Randy
update
Hi Randy,
It may take us another week to get you the signed document for Grouse Creek, we need to hone in on a better COD date
and get with our consultants to help fill in the paperwork. I hope that is okay. When do you anticipate having the pricing
given the fact that we just got you, hopefully, the right data.
On another note, we are preparing to submit an interconnection application to ipea at a Wyoming wind project of ours
to the Jim Bridger Power Plant. I would assume we could work with you on a QF project in Wyoming that interconnects
directly into your system and save some of the hassles we have had with our Grouse Creek project? Also, do you believe
that ID Power wil be putting out any RFP's any time soon for wind? Here is a crazy question, I imagine that you won't
be backing down the Jim Bridger plant anytime soon!
Look forward to your answers.
Thanks.
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
W\,wasatchwind,com
Wasatch Wind
This message and any attachents contain information lhat is proprietary, confidentiai and priviteged They are intended for the pnvate and exclusive use of the addressee and are covered by the
Eleclronic Communications Pnvacy Act. 18 USC §§ 2510-2521 Unless you are the eddressee (or aulhonzed 10 receive for the addressee) you may nol use, copy, pont or disclos to anyone thismessage or any information contained in the message and any attachments If you have reeived this comunication in error, please advise the sender by reply and delete this mesage,
1 Attachment NO.3
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 5 ot6
~hin,RandY
From:
Sent:
To:
Subject:
Allphin, Randy
Wednesday, May 19, 2010 3:29 PM
'Christine Mikell
RE: update
Numbers are crunching on the pricing, hope to have something early next week.
Wyoming - yes we own a share of Jim Bridger and the Bridger transmission lines. However, delivery of energy to Jim
Bridger is not considered delivery to our system. Mayor may not be easier, but we can work our way through things.
I am not aware of any immediate RFPs.
Does not make a lot of sense to back down a clean, base load, inexpensive coal plant. No question we have to consider
long term carbon issues, but at least no plans for immediate back downs.
Randy
From: Christine Mikell (mailto:christloet§wawfnd.ÇQml
Sent: Wednesday, May 19, 2010 3:23 PM
To: Allphin, Randy
Subjec: update
Hi Randy,
It may take us another week to get you the signed document for Grouse Creek, we need to hone in on a better COD date
and get with our consultants to help fil in the paperwork. I hope that is okay. When do you anticipate having the pricing
given the fact that we just got you, hopefully, the right data.
On another note, we are preparing to submit an interconnection application to IPCO at a Wyoming wind project of ours
to the Jim Bridger Power Plant. I would assume we could work with you on a QF project in Wyoming that interconnects
directly into your system and save some of the hassles we have had with our Grouse Creek project? Also, do you believe
that ID Power wil be putting out any RFP's any time soon for wind? Here is a crazy question, I imagine that you won't
be backing down the Jim Bridger plant anytime soon!
Look forward to your answers.
Thanks.
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
IN. wasatchwind.com
Wasatch Wind
1 Attachment NO.3
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 6 of6
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO.4
~hln,RandY
From:
sent:
To:
Subjec:
Chrti Mikell (c:ristinetmsathwind.comI
Tuesay, June 01, 2010. 11 :56 AMAllphin, Rand .
aliynéW'?
Hey Randy,
Junchecklng to see when you thought the model would be ready for Indicative pricing?
Thanks.
Chritine Watn Mikell
Senior Proje Development Manager
Direct: 43503-814
Mobile: 801-45-1045
clesn energy. c/98n air. clean earh.
ww.wasawind.com
Wasatch Wind
i
li
1 Attachment No.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of38
~hinr Randy
From:
Sent:
To:
Subject:
Attchments:
Allphin, Randy
Wednesday, June 02, 2010 9:21 AM
'Christine Mikell'
RE: any new?
Wasatch wind Grouse creek porposed project.PDF
Christine,
Attached is a letter with the potential pricing. I am sending the original via US mail.
Randy
From: Christine Mikell (iilt:chrfwøtid.lcoJ
Sent: Tuesay, June 01, 2010 11:56 AM
To: Allphin, Randy
Subjec: any news?
Hey Randy,
Just checking to see when you thought the model would be ready for indicative pricing?
Thanks.
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503.8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
ww.wasatchwind.com
Wasatch Wind
This message and any attachments contain information that is proprietary. COnfidettlal and privilegad Thay ara intended for tha private and exclusive use of the addressee and are coverd by the
Electrc Commullcatlons Privacy Act. 18 U,S.C §§ 2510-2521" Unless you are th addressee (or authonzed to recive for the addressee) you may nol use, coy, prinl or dIsclose 10 anyoe this
message or any informtion cotained m the massage and snyattachments. ff you have receIved thIs communicalion in error, please advise the aender by reply and delete thIs meage.
1
Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of 38
a_.
An IDAC comrinv
June 2,2010
Wasatch Wind
Attn: Chrstine Watson Mikell
2700 Homestead Road. Suite 210
Park City, tI 84098
Randy C. AIphiD
Senor Energy Contrct Coordinator
Tel: (208) 388-2614
rallphiniaidahopow,com
Originl: US Mail
E-mail Copy:ChristineMikell-chrtine§wasatchwind.com
RE: Proposed Grouse Creek Win Project
Ms. Mikll,
As we have been discussing, there ar stil some key transmission and interconnection issues
that your project wil nee to work through prior to Idaho Power being able to accept energy from
your proposed PURA project. i have provided you with a Letter of Understanding and associated
infonntion that must be completed to enable us to begin the transmission capacity request process.
In addition, a purchase power agreement wil nee to be agreed to, executed and approved by
the Idaho Public Utilities Commssion prior to Idaho Power purchasing any energy frm your
proposed project.
Proposed Energy pricing -
The Idaho Public Utilities Comnssion has established a ver specific process tht Idaho
Power is required to use to devlop a potential energy price to be paid to PUR A proj ects that are
larger than 10 average MW, Ths process requir that we input the estimated hourly energy from
your proposed projec into our economic system model (AURORA) to deterne the energy pricing
that can be offered to your specific project.
In reviewing the generation data you have provided we are fmding tht the capacity factor
appears to be much higher than what we have typically seen for this area. However at ths point we
Page 1 of2
POBox 70 Boise Idaho 83707 1221 W Idaho Sl Boise, Idaho 83702
Attchment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 3 of 38
have input the data you have provided into our economic dispatch model (AURORA) and calculated
energy prices that would be available for your proposd wind project based on the generation data
you provided. Prior to formulizing these energy prices, we wil need to do additional review of the
estimated generation data you have provided.
The proposed energy pricing is contained in the attached pricing schedule.
Examples of how to read this schedule:
Energy delivered to Idaho Power in March of 2011 -
The price paid for energy delivered during Heavy load hours would be $34.21 per MWh
The price paid for energy delivered duing light load hours would be $28.86 per MWh.
Ener delivered to Idaho Power in July of2011 -
The price paid for energy deliverd during Heavy load hours would be $55.85 per MW
The price paid for energy delivered during light load hour would be $47.11 per MWh.
Ths letter is not a binding commtment from Idaho Power to purchase energy from your
project, only after aU interconnection an transmission capacity processes have been completed, a
purhase power agreeent has been executed by both parties and the agrent has been approved
by the Idaho Public Utilties Commssion wil an effective and binding commtment exist.
After your review of this data" if you wish to continue to pursue a PUR A purchase power
agrent with Idaho Power, please retu the previously provided Letter ofUndertimding and the
infonnation reuired so that we can bein the trnsmssion capacity review proes. It wil be
requir that prior to additional work being done on a potential purchase power agreement the
trnsmission capacity availabilty and/or required network upgrades be identifed and widerstood.
Please contact me at your convenience with any questions you may have.
Sincerely,
Ae~'
Randy C Allphi
Idaho Power Compay
POBox 70 Boise, Idabo 83707 1221 W 1dahoSt. Boise, Idaho 83702
Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 4 of 38
;;
;
g
&
'
~
lC
i
:
l
i
D
l
(1
=
.
(
1
g
.
O!
:
:
Z
3
0)
:
0
(
1
-
3
l
!
'
:
:
(.
Q
.
_
_
()
D
l
1
J
Z
~
Ç
l
?
__
m
.
.
1J
~
()
~
..Qo =ö()im~~
Se
a
s
o
n
a
l
i
z
a
t
i
n
F
a
c
t
o
r
s
Se
a
s
n
1
73
.
5
0
%
(
A
p
p
l
i
e
d
t
o
M
a
r
h
.
A
p
r
a
n
d
M
a
y
)
Se
a
s
o
2
12
0
.
0
0
%
(
A
p
p
l
i
e
d
t
o
J
u
l
y
,
A
u
g
u
s
t
.
N
o
v
e
m
b
e
r
a
n
d
D
e
c
m
b
e
)
Se
a
s
o
n
3
10
0
.
0
0
%
(
A
p
p
l
i
e
d
t
o
J
u
n
e
,
S
e
p
t
e
m
b
e
r
,
O
c
t
o
b
e
r
,
J
a
n
u
a
r
y
a
n
d
F
e
b
r
u
a
r
y
)
Co
n
t
r
a
c
t
P
r
i
c
e
En
e
r
g
P
r
i
c
i
n
g
Se
a
s
o
n
1
P
r
i
c
i
n
g
(
7
3
.
5
0
%
)
Se
a
s
o
n
2
P
r
i
c
i
n
g
(
1
2
0
.
0
0
%
)
Se
a
s
o
n
3
P
r
i
c
i
n
g
(
1
0
0
.
0
0
%
)
He
a
v
y
$7
.
2
8
Ma
r
ç
h
.
A
p
r
i
a
n
d
M
a
y
Ju
l
y
,
A
u
g
u
s
t
,
N
o
v
e
m
b
e
r
a
n
d
Ju
n
e
,
S
e
p
t
e
m
b
e
r
,
O
c
t
b
e
,
J
a
n
u
a
i
an
d
U
g
h
t
De
c
e
m
b
e
r
an
d
F
e
b
r
u
a
r
y
Lo
a
d
Ho
u
r
$3
.
2
($
4
.
0
4
)
He
a
v
y
Li
g
h
t
Fl
a
t
Lo
a
d
Lo
a
d
Fl
a
t
He
a
v
y
Lo
a
d
Lig
h
t
Lo
a
d
Fl
a
t
He
a
v
y
Lo
a
d
Lig
h
t
Lo
a
d
Fl
a
t
He
a
v
y
Lo
a
d
Lig
h
t
Lo
d
Ye
a
r
Ho
u
r
Ho
u
r
Pr
i
c
i
n
g
Ho
u
r
Pr
i
c
e
Ho
u
r
P
r
i
c
e
Pr
i
c
i
n
g
Ho
u
r
Pri
c
e
Ho
u
r
P
r
i
c
c
Pr
i
n
g
Ho
u
Pri
c
e
Ho
u
r
Prc
e
20
1
1
43
.
3
0
46
.
5
4
39
.
2
6
31
.
8
3
34
.
2
1
28
.
8
6
51
.
9
6
55
.
8
5
47
.
1
1
43
.
3
0
46
.
5
4
39
.
2
6
20
1
2
44
.
0
8
47
.
3
2
40
.
0
4
32
.
4
0
34
.
7
8
29
.
4
3
52
.
9
0
56
.
7
8
48
.
0
5
44
.
0
8
47
.
3
2
40
.
0
4
20
1
3
45
.
3
0
48
.
5
4
41
.
2
6
33
.
3
0
35
.
6
8
30
.
3
3
54
.
3
6
58
.
2
5
49
.
5
1
45
.
3
0
48
.
5
4
41
.
2
6
20
1
4
46
.
5
4
49
.
7
8
42
.
5
0
34
.
2
1
36
.
5
9
31
.
2
4
55
.
8
5
59
.
7
4
51
.
0
0
46
.
5
4
49
.
7
8
42
.
5
0
20
1
5
47
.
8
3
51
.
0
7
43
.
7
9
35
.
1
6
37
.
5
4
32
.
1
9
57
.
4
0
61
.
2
8
52
.
5
5
47
.
8
3
51
.
0
7
43
.
7
9
20
1
6
49
.
1
4
52
.
3
8
45
.
1
0
36
.
1
2
38
.
5
0
33
.
1
5
58
.
9
7
62
.
8
6
54
.
1
2
49
.
1
4
52
,
3
6
45
.
1
0
20
1
7
50
.
4
9
53
.
7
3
46
.
4
5
37
.
1
1
39
.
4
9
34
.
1
4
60
.
5
9
64
.
4
8
55
.
7
4
50
.
4
9
53
.
7
3
46
.
4
5
20
1
8
51
.
8
8
55
.
1
2
47
.
8
4
38
.
1
3
40
.
5
1
35
.
1
6
62
.
2
6
66
.
1
4
57
.
4
1
51
.
8
55
.
1
2
47
.
8
4
20
1
9
53
.
3
1
56
.
5
5
49
.
2
7
39
.
1
8
41
.
5
6
36
.
2
1
63
.
9
7
67
.
8
6
59
.
1
2
53
.
3
1
56
.
5
5
49
2
7
20
2
0
54
.
7
8
58
.
0
2
50
.
7
4
40
.
2
6
42
.
6
4
37
.
2
9
65
.
7
4
69
.
2
60
.
8
9
54
.
7
8
58
.
2
50
.
7
4
20
2
1
56
.
2
9
59
.
5
3
52
.
2
5
41
.
3
7
43
.
7
5
38
.
4
0
67
.
5
5
71
.
4
4
62
.
7
0
56
.
2
9
59
.
5
3
52
.
2
5
20
2
2
57
.
8
4
61
.
0
8
.
5
3
.
8
0
42
.
5
1
44
.
8
9
39
.
5
4
69
.
4
1
73
.
3
0
64
.
5
6
57
.
8
4
61
.
0
8
53
.
8
0
20
2
3
59
.
4
3
62
.
6
7
55
.
3
9
43
.
6
8
46
.
0
6
40
.
7
1
71
.
3
2
75
.
2
0
66
.
4
7
59
.
4
3
62
.
6
7
55
.
3
9
20
2
4
61
.
0
6
64
.
3
0
57
.
0
2
44
.
8
8
47
.
2
6
41
.
9
1
73
.
2
7
n.
1
6
68
.
2
61
.
0
6
64
.
3
0
57
.
0
2
20
2
5
62
.
7
4
65
.
9
8
68
.
7
0
46
.
1
1
48
.
5
0
43
.
1
4
75
.
2
9
79
.
1
8
70
.
4
4
62
.
7
4
65
.
9
8
58
.
7
0
20
2
6
64
.
4
7
67
.
7
1
60
.
4
3
47
.
3
9
49
.
7
7
44
.
4
2
77
3
6
81
.
5
72
.
5
2
64
.
4
7
67
.
7
1
60
.
4
3
20
2
7
66
.
2
4
69
.
4
8
62
.
2
0
48
.
6
9
51
.
0
7
45
.
7
2
79
.
4
9
83
.
3
8
74
.
6
4
66
.
2
4
69
.
4
8
62
2
0
20
2
8
68
.
0
7
71
.
3
1
64
.
0
3
50
.
0
3
52
.
4
1
47
.
0
6
81
.
8
85
.
5
7
76
.
8
4
68
.
0
7
71
.
3
1
64
.
0
3
20
2
9
69
.
9
4
73
.
1
8
65
.
9
0
51
.
4
1
53
.
7
9
48
.
4
4
83
.
9
3
87
.
8
2
79
.
0
8
69
.
9
4
73
.
1
8
65
.
9
0
20
3
0
71
.
8
7
75
.
1
1
67
.
8
3
52
.
8
2
55
.
2
1
49
.
8
5
86
.
2
4
90
.
1
3
81
.
4
0
71
.
8
7
75
.
1
1
67
.
8
3
20
3
1
20
3
2
20
3
3
20
3
4
20
3
20
3
20
3
7
.chin, Randy
From:
Sent:
To:
Subjec:
Chrstine Mikell (christine(Cwasatchwind.com)
Wednesday, June 16,20105:36 PM
Allphin, Randy
Grouse Creek wind projec
Hey Randy,
I am just filling in the last of the information on the form you send June 2nd and anticipate scanning it tomorrow and
sending it to you with a hard copy to follow on Friday. Are you around to chat tomorrow? Also, i wonder if it would
make sense to meet you in person sometime.
Are you around in a couple of weeks?
Thanks!
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
YM.wasa1chwind.com
Wasatch Wind
This message and any attachments contain Information thai is proprietary. confdential and privileged, They are intended for the pnvate and exclusive use of the addresee and are covered by the
EleClronic Communicatlons Pnvacy Ac!. 18 U ,8 C §§ 2510-2521 Unless you are the addressee (or authorized 10 receive for the addressee) yo may not use, cop, pnnl or disdose to anyone Ihis
mesaga or any infomahon contained in the message and any attachments If you have received this comunication in err, plaase edv,se the sender by reply and delete this message,
1
Attachment No, 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 6 of 38
.2hin, Randy
From:
Sent:
To:
Subject:
Attchments:
Chrst,ine Mikell (christinecæwasatchwind.com)
Thursday, Ji;ne 17,20101:22 PM
Allphin, Randy
Proposed Grouse Creek Wind Project
0197 _OO01.pdf
Hi Randy,
Attached you wil find out letter of understanding. Please let me know if you would like the hardcopy too.
Kind regards,
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-53-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
ww.wasatchwind.com
Wasatch Wind
This message and any allachments conlain infrmalion that is proprietary. confidenllal and privileged They are intended fo Ihe private and exclusive us of the addreee and are coered by the
Electronic Commuoicallons Pnvacy Act, 18 U.S.C. §§ 2510-2521, Unless you are the addressee (or authOOzed to receive for the addresse) you may nol use, copy, print or disdose 10 anyone this
message or any Information contained in the message and anyaUachmanls If you have receive Ihis communication in error. please advise the sender by reply and delete this message
i Attchment NO.4
Case Nos. IPC-E-1Q-1 & IPC-E-10-62
Allphin Affdavit, IPC
Page 7 of 38
BBi.
An IDACOIlP Company
..
"Marh 12, 2010
Randy C. Allpbin
Sr. Energy Contract Coordinator
Tel: (208) 388.2614
ralløhin((idabopower.co
Wastc Win
Att: Christine Watson Mikell
2700 Homestead Rod. Suite 210
Park City, UT 84098
Original: U SMail
E-mail Copy:ChrstieMikell-christin~wasatcliwínd.com
RE: Letter of Undertanding
Proposed Grouse Creek Wind Project
Chrsti,
In our conversations and e.mals we have bee discussing your proposed Gruse Cree Wind
projec an the process to sell energy to Idaho Power under a PURA agrent. The latest
discusions have been around the BPA trasmission requireients. as it appears we now have a pretty
good unerstanding of the interconnection status and potential BP A solutions we need to put into
motion the process of documting the various reuirments, detemning Idaho Power transssion
system capacity and ultimately begin negotiations of a PURA purchse power agrmet. Much of
the process identified in this letter we have already discussed and/or has bee provided to you via e-
mail.
P 0 Boii 70 Boise, Idaho 83707 1221 W Idaho Sl. Bois Idaho 83702
Attachment No.4
Case Nos. IPC-E-10-61 & IPC-Ej.-62
Allphin Affdavit, IPC
Page 8 of 38
A$ your proposed Grouse Creek Wind Project is: a) not within the Idaho Power service
terrtory an b) it wil be physically internnecting to a utility other than Idaho Power ("host utilty")
and c) wil need to arrange for transmission of the project's energy to Idaho Power across the other
utiities syste and the BPA trnsmission system ("transmitting entities" creates additiona steps and
complexities in orde for the project to sell ener to Idaho Power under a PUR A agrement.
Summrized below is a brief outline of the purhase power agreement, inteconnection process
and transmission capacity requirements that are applicable to your proposed generation project. This
summary is intended to provide geeral infurntion and steps required to enable this pi"Oject to
potentially be able to deliver energy to Idaho Power under a potential PURA agreement. Prior to
Idaho Power accepting any energy from tms project a PUR A agreement must be agreed to and
executed by both parties and also the Idalio Public Utilities Commission (IPUC) must approve any
PURA agreemet executed betwee U1e parties prior to it being binding and effective.
Purchase Power Agreement
The projec you have described appers to be eligible for a purchase power agremnt under the
gudelines for a QualifYing Facilty as defned by the Public Utilities Reguatory Policies Act of 1978
(PURA). At the time you ar ready 10 preed WiU1 a purcha power agent for ths project,
an U1e prject has completed the requiemets specified below Idaho Power wil prepare a drft
purchase power agreement that complies with U1e current rules and reglations that gover these
PURA agreeents, any draft purhase power agreements previously provided to you for review
must be update to include cUlTent rules and regulations.
As we have discused, as your propoed project is greater than 10 iiverage MW. the published
avoided cost energy pricing is not applicable to your project. Instead. there are specific IPUC rules
and order that specify that Idao Power must calculate a specific energy price for your proposed
project by usin an economic system dispatch model (AURORA) that Idaho Power uses in its
resur plann proces. You have preiously provided th basic energy shape from your project
and we are populatig the model with this energy sha and runnng U1e model to determie U1e
approriate energy price.
Prior to Idaho Power executing a purchase power agrement it wil be reuired that you have:
1.) Provided documentation that substantiates that the project has filed for intetconnection
wiU1 the bost utilty and is in compliace wiU1 any payments and/or other
requiremnts speified in the internnection proces for this project and;
2.) Received and accepted an interonnection feasibilty study for tl projec an;
3.) Retrned a signed copy of this letter of understanding and all of tbe reuire
informtion to enable Idaho Power to tie an application requesting trnsmission
capacity on the Idaho Power electrical system for this project. Completion of the
enclosed Transnussion Capacity Application Questionnaire wil provide the majority
of this infonnation and;
4.) Confintion that tlie results of the initial trasmission capacity application are known
and the projec accepts these reslts and intes to contiue with the deveJopment of
the project including. if applicable, execution of a Network Resour Inegration
Study Agrement in the fonn enclosed herein.
Page i of 5
POBox 70 Boise, Idaho 83707 1221 W Idaho Si. Bois,ldaho83702
Attachment No.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 9 of 38
Intercnnon and Transs§ion CapacitY
Your project wil be responsible for all costs of physically intercolUiecting the projec to the host
utilty and the Idaho Power electrical syste and any costs associated with acquirin adequate fin
traiiion capacty on the Idaho Power trai:misson system to enble the projects energy to be
delive to Idaho Power customes.
Inte~sciion
Your project will be reuir to complete the interconnecion proces and execute an
appropriate interconntion agreeent with the host utilty. This interconnectioii
agreement wil nee to be in substantially the same foim as Idaho Power's Generation
Internnection Ageement ("GIN').
Tragsion Capacit)(
To sell your prjec's enrgy to Idaho Power, your project must be designated as a
Netork Resource (CCDNR").
In order for tls project to achieve DNR status,
a.) The project must acquire fiim trnsmission frm aU transmitting entities required
to deliver the projects maximum capacity rating to a specifc physical point of
delivery on the Idaho Power electrical system for the full ten of the purchase
power agrement an;
b.) Idaho Power is required to make a request (complete and fie an application) and
be grnted finn transmission capacity on the Idaho Power transmission system
&on1 the Idaho Power delivery business unt ("Delivery") to move your project's
ener from the physical point of delive to Idaho Power customers an;
c.) In accordance with various 111es and regulations, the projec must be grnted
DNR stas no later thn 60 days prior to the project delivering any energy to
Idaho Power.
Idah Power wil begin ths Idaho Power fiim trnsmission capacity application
process only after the project ha return a sign copy of this letter of undertanding
and all of the information require for Idaho Power to fie this application requesting
fiim transssion capacity on the Idaho Power electrcal system (see attached
Trasmission Capacity Application Questionnair).
Afer fiing a complete fir transmission capacity application wit Deliver, Idaho
Power wil reeive notification back from Delivery within 30 days tht: (a) adequat
transmission capacity is available for ths project without the nee to constrct upgrdes;
or (b) a trnsmission capacity system impact study is requir to determine the available
Ida Power transmission capacity and/or required upgrades; or (0) a statemnt of the
Page 3 of5
POBox 10 Boise. Idaho 83707 1221 W Idal0 St. Boise Idao 83702
Attachment No, 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 10 of 38
Plea muall re inormtion to:
Id Power Comy
Attn: R.y C. Allp
POBo:i10
Bois ID 83107
B--: raUpn(dahoer.co
Sincely,
ß eru'
Ray C Allphi
Ida Power Compy
Prit Nam
J~.2010
Sipti
Title ~~
P OBal' 70 Balsء Idaho 83707 1221 W Idio St. Baliildlho l:l702
Attachment NO.4
Case Nos. IPC-E-1Q-1 & IPC-E-10-62
Allphin Affdavit, IPC
Page 11 of 38
6~i.
M lOilico_
Transmission Capacity Application Questionnaire
This list is the known informauon requirements 88 of the date of the letter trnsmring this request. If additional infomation
is required. Idaho Power wilf promptly notif the projt developer of the additional infomation requirements.
A. Project Name
C3~ GV-t-G-\c \hi \\ "?çx:\LJ:(.
B. Project Location
C.Project Developer
Name
Address
City I State I Zip
Phone Number
E-mail
\N4\NAti\i \oi\'c,clri3:u \:)\Ilsk~
lw"-. C \ h. t v~l
~\~~çQs-:)xi; l t.
C\tV'.-cs;h~(? lNg,'ø b;bk-1x;. ''''n
tLJ. . ç; \k i \rÁ 1 .1 \i
öiuj t
D. Interconnection "Que" reference number (if not known, please contact the host utilty
Interconnection group)
G1C 3',- t,
E. Evidence of the Project's good standing status in the host utility's interconnection process
fA ti \\ÌY ShM'1 (,So daH. ~ \iIIASßtt Vi b" ,viQf :j \AVl.! " '
F. Copy of the Interconnection feasibility study and a statement from the project that the project
has accepted the results of the interconnection feasibilty study and is continuing the process
of interconnecting and developing the generation project.
G.Maximum Capacity (MW)~ti
Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 12 of 38
H. Beinning day and time of energy deliveries
Day (mm/ddfyyyy) I 1- . .~ \ # ~ 0 \ \
Time I 0 (.\.W'
i. Ending day and time of energy deliveries
Day (mmtd!l t'~ . 3il ..~
Time
K.
"P t"N\W tf::6.~.iVAR capabilty (both leading and iaggin¡) of all generators lor Iivt ~ ~.~ ,...
t\ffP-'-è-r fO\ ls) -= t~ch'f ;9.r-~ i.(.~l M,vJ, o.YùÍ\o ('5*"'2.-l~'X2)(S)
Identification of the control area( s) from which the energy will originate ~,~ 1. ~ \i Y,', -; l5L.O y.\i lA
\ A (A\Ú s\ 'Pn'-I\~L(
J.
L.List any periods of restricted operations throughout the year
M.Maintenance schedule
Minimum loading level of each generation unit Ì",Ä Vl"S'\b~W -. 11, 1. k.\N IJ rv
\V~)( L tW~1A VVV'n fI" );1- k.W
O. Normal operating level of each generation unit. SfL, 1L.:i V:'
N.
P. Any must-run generation unit designations required for system reliabilty or contractual reason
N.olh OlA,v Ïdo;Cw \.u Sf . .
Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 13 of 38
Q. Approximate variable generation cost ($/MWh) Note - this will be estimatd energ prng from 8 pontiel
purchse power agreement tha this prjet may be eligible for.
l: eCn - tl 9i I flM,.;Vi \. Ó-;tjIJ
R. If the generation resource is to be located in the Idaho Power Balancing Authority Area and if
only a portion of the resource output is to be designated as a Network Resource, then explain
arrangements governing sale and delivery of additional output to third parties.
S. If the project is not directly interconnected to the Idaho Power transmission system. provide
the transmission provider(s) name, physical Point of Receipt, Point of Delivery and the
transmission reservation number for all of the transmission providers required to deliver the
project's energy to Idaho Power.
Transmission Provider(s) Name Buvw\L \J " \ LL l VY,Kf Ad li i'J \ ) \v"Çvb ~b
Point of Receipt ex hvu..V\ \i\t¿\t'- Ov"(" :ç B r\ k.. s\.\. \.~ \--"/'lh ~y)
Point of DeHvery N\ '\ l\ Jií. 0\ u lL v. ') "Aib -:" \-0. \1 i: 6
Transmission Reservation Numbes) 1- d\
T. If the project is directy interconnected to the Idaho Power transmission system. provide the
Point of Receipt, physical/acation and voltage.
Point of Receipt
Physical
Voltage
U. Is the project committed to execute a purchase power agreement with Idaho Power upon a
favorable resolution of the identified interconnection and transmission costs?
YesR No 0
V. Is any portion of the maximum capacity identified for this project committed to any other party?
Yes 0 NO'~
Signature Date ~(¡-(O
Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 14 of 38
~hin, Randy
From:
Sent:
To:
Subject:
Allphin, .Randy
Wednesday, June 23,2010 8:07 AM
'Christine Mikell'
RE: Proposed Grouse Creek Wind Project
Christine,
Thanks for this information, I have been looking it over and making our preparations to make the transmission capacity
request on the Idaho Power system. I expect that the transmission group will not accept our request without more
detail and/or assurance that the BPA transmission is available from your project to the point of delivery on the Idaho
Power system.
I know we have discussed this quite a bit - but could you send me a write up in regards to the availabilty of the BPA
transmission capacity. If possible, include as much reference to your actual filngs in the BPA process and status. Clearly
the best solution would be to be able to state that BPA transmission capacity is available and the project has rights to it.
Another note - on the interconnection section you state that the Facility study is due the end of June. i would assume
then that a Feasibilty study is already complete and you have accepted the results of that study - could you send me
your answer to this also in written form (basically an answer to item F of on the transmission questionnaire)
Thanks Randy
From: Christine Mikell (maJIt;ch~asw!nd.comJ
sent: Thursay, June 17, 2010 1:22 PM
To: Allphin, Randy
Subjec: Proposed Grouse Creek Wind Projec
Hi Randy,
Attached you wil find out letter of understanding. Please let me know if you would like the hardcopy too.
Kind regards,
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
ww.wasatchwind.com
Wasatch Wind
r ,\
This message and any allaGhments COleln informalion that Is proprietary, confienlial and privilaged, They are intended for the pnveie and exclusive use of the addressee an are covered by the
Electronic Commurlications Privacy Act, 18 u.,s C §§ 2510-2521 Uniess you are the addressee (or authorized to rec",ve tor Ihe addreee) you may not use, copy, pnni or disclose 10 anyone this
message or any informahon contained In the message and any attachments, If you have received this communication in error, plesse advise the sender by reply and delete !his message
1 Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 15 of 38
Allphin, Randy
From:
Sent:
To:
Subject:
Attachments:
Chrstine Mikell (chnstine~wasatchwind.comi
Thursday, June 24,20102:16 PM
Allphin, Randy
RE: Proposed Grouse Creek Wind Project
BPA Feasibility study. pdf
Hi Randyi
I just left you a message. In short, we have three golden eagle nests within about .5 miles from some of our turbines.
After meeting with USFW service recently, it looks like to mitigate impacts to golden eagle populations we wil have to
have greater setbacks between golden eagles and the turbines, Le. drop turbines because the land is constrained. Based
on this, it appears that we wil need to discuss with you changing our initial request to a 10 MWA request. Is this
something that is easy for you to rerun, or do you anticipate that it wil result in the same answer? I know that when we
spoke some time ago that you suggested that the new natural gas pricing would mean the 10 MWA and less than 80
MW PPA prices would be about the same. I think you had guessed that the pricing would be about $70/MWh. Since the
pricing is at $55/MWh for the larger QF, I thought perhaps there was stil that price disparity.
We would like to discuss with you the option to build one 10 MWA QF and possibly another 21 MW's at a later date. We
plan to make a transmission service request to BPA for 30 MW's and possibly another 21 MW's. Based on our
interconnect studies and conversations that we have had with BPA (not to mention the analysis that we presented to
you that BPA gave us), there are 93 MW's available on that line to the Minnidoka substation.
The feasibilty study is completed and attached and yes we acknowledged/accepted the results of that study.
Let me know a good time to talk. i am out after about 3:30, but back again tomorrow. Love to catch up so we know how
to make the proper TSA with BPA~ by Wednesday.
Thanks,
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
ww.W5satchwiod.com
Wasatch Wind
This message and any attachments contain information that is propnetary, confidential and pnvileged They are intended for the pnvate and exclusive use of the addressee and are covered by the
Electronic Communlcatiol1s Pnvacy Act, 18 U,S.C §§ 2510-2521 Unless you are the addresee (or authonzed 10 receve for the addresse) yo may not use. copy, pnnt or disdose to anyone this
mesage or any informalJOi contained In the message and any attachments lfyou have recve this communication ir error, please advise the serief by reply and delete this message~
From: Allphin, Randy (mailt:RAllphinC9idahopower.com)
sent: Wednesay, June 23, 2010 8:07 AM
To: Christine Mikell
Subject: RE: Propose Grouse Creek Wind Project
1 Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 16 of 38
Christine,
Thanks for this information, I have been looking it over and making our preparations to make the transmission capacity
request on the Idaho Power system. I expect that the transmission group wil not accept our request without more
detail and/or assurance that the SPA transmission is available from your project to the point of delivery on the Idaho
Power system.
I know we have discussed this quite a bit - but could you send me a write up in regards to the availabilty of the BPA
transmission capacity. If possible, include as much reference to your actual filngs in the SPA process and status. Clearly
the best solution would be to be able to state that BPA transmission capacity is available and the project has rights to it.
Another note - on the interconnection section you state that the Facilty study is due the end of June. I would assume
then that a Feasibilty study is already complete and you have accepted the results of that study - could you send me
your answer to this also in written form (basically an answer to item F of on the transmission questionnaire)
Thanks Randy
From: Christine Mikell (mailto:christine(§wasatchwind.comJ
sent: Thursay, June 17, 2010 1:22 PM
To: Allphin, Randy
Subjec: Proposed Grouse Creek Wind Proje
Hi Randy,
Attached you wil find out letter of understanding. Please let me know if you would like the hardcopy too.
Kind regards,
Christine Watson Mikell
Senior Projec Development Manager
DIrect: 435-503-814
Mobile: 801-455-1045
clean energy, clean air, clean earth.
ww,wasatchwind.cgm
Wasatch Wind
This message and any allactmients eolain mfomialion lhat ,s propnetary, confidenbal and pr,vileged They are irierded for tt pnvale and e~clusive use of Ihe addrsee and are COrad by the
Electronic Communicalions Pnvacy Act, 18 U SC §§ 2510-2521 Unless you are lhe addressee (or aulhonze 10 receive for the addresee) you may not use, copy, pnnl or disclose to anyone its
message or any informalion conlamea In Ihe mesage and any allachmenls It you have received this conmunicalion In "iror, please advise lhe sender by repiy and delele !his message.
HR.../_.~
2 Attchment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 17 of 38
Th ti, ma co iiomkm li is pr1lCOØdlICl It dilo imap ii, ir~ If ii it lw Rl)'1I liootl -lI dllo ~ ~ll_iillilkm ~ll (li~lI~~) Is snicv PROHIT.lf,on:vc thUlit in il, pi ~ i:ia it Bdll Ør it mi li il eiÆt)'. wl li el or bI co l'. 1l yo
3 Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 18 of 38
Department of Energy Ofíkinl rile CI'P~
Bonneville Power Administration
P.O. Box 491
Vancouver, Washington 98666-0491
TRANSMISSION SERVICES
November 12.2008
In reply refer to: TPP/DITT-2
Ms. Christine Watson - Mikell
Wasatch Wind, Inc.
357 W 910 South
Suite A
Herber. UT 84032
Dear Ms. Watson ~ MikeIJ:
Enclosed is the Final Generation Interconnection Feasibility Study (IFES) report addressing
local interconnection requirements for the Grouse Creek Wind Project (Project). This project
is being developed by Wasatch Wind, LLC. The Project is listed as queue request number
G0326 in the Bonnevile Power Administration Transmission Service's (BPA-TS) for
interconnection queue. The study was performed under Study Agreement No. 08TX- I 3540.
This Final report includes non-binding good faith cost estimates.
Please handle this Omi~hil tsc Only document with appropriate discretion.
If you have any questions or comments, please contact Matl Ingold at 360-418-2339 or
myself at 360-418-8414,
Sincerely,
Charles E. Matthews
Process Manager. Generation Integration Planning
Transmission Planning
Enclosure:
Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 19 of 38
IntercOlUiection Feasibiltv E\'aluation Studv (. .
Intel'~onnection of: \Vasutch \\'ind -
-ISO
I
USE ONLY
Information
!)ISTRIlHm. PPllUSH
AL;l l-O~IZEi) BY BPA
OFfiCIAL USE ONLY
Mdy Ii-. rNm pal'liuu.. mc'~ of lnr~ Ai:
(5 I..lU:. :'si). .i_t11illl nllfllhr mid ."iicii11ly.
..
....A~:1'1''1I.i:~iiOlWI
OFCIA ONLY Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 20 of 38
BONNEYILLlh::"d l A..llUUIIJl Ue"
Report Prepare by:
Matt Ingold, TPP
Petr J. PongczBart TPM
OFfCIAL USE ONLYThis nipol1 ~tlll1 BoiJle Pow Adinilioo CtltiCllnl1~ lìl~ (CD).Distrilmilo of thÎ$ ,. im be lìnte to pm UW.ll . _ to !m M'hiv fifirfe
noo..iiilR t1ulnits wih th Boneille Pøw Adinislon.
Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 21 of 38
. ,
TABLE OF CONTENTS
l.
i.
3,
:ti
3,2
,D ..... Ni:work R.esouce
4. Trip Relaying artd
5. Comrm,inications, Contrøl
6. TQÇhnical
6.1
6,2
63
lntroouction................,...............................................,...............".........................,................ 2.
Conclusíous and ... ......................................................................_......... :1IntertOl'QÇtÌOIl i
Intdc,onnectio at
...."",.."'''''"....''''..."".".....''......:''*"...........''..."...,."........"."....~l....."'''''.."...,.."..."..."..;~;.....?"".'".;¡,..'".. 8
Intennnei:íôJ
hi~rcQfnei:iQf at New
6.6 Fàult Studies
7. Cost 11
Attaebment A: Preliminary Sketh witb Interconn~on.t Bri."138-kV Substaton.
o .../\s:.d~,, d d"'''::'c'' . ,Attachment B: Prelimiary Sketcb M.th "tlronn~ .'óng tbe BridgeWest Wendover
138-kV Transmission Line.t&", ",'4,:..\
OFFICIA USE ONLYThis report Critíel Infrtrre
Disbuilon ofttis repot1inus tk,limited to paies that have a nee ttl1mw and
reirefSwIlh tteBolllw,vile Power Admiuilllioo.
Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 22 of 38
i. Introduction
This report is the Generation Interconnection FeasibiliLy Study (IFES) addressing local
interconnection requirements for the GroU$ Creek Wind Project (Project). This project is being
developed by Wasatch Wind LLC. The Projce is listed as requcst No. G0326 in the Bonncvi1c
Power Administration Transmission Services' (BPA-TS) OASIS queue for interconnection of
generation.
The Project as proposed is alSO MW wind genertion facilty. whìth wiUbc built in twophase.
The first phase wìH consist of 100 MW with an enc . tion datp.~llc 20 to, an the seeond
phase wil consist of 50 MW with an encrgi of ~ir 20 i O. This Feasibilty
Study is performed to address the follo~ìdg ,': 'p"
"~, "t-
a) IdentHy facilities reqiiiièd O:lliitlie'nPA system for the proposed interconnection;
i. ",.
b) Provide non-bi!?,!iri'gi'gÓ~d-faith estimated cost ofBPA required facilities; and
c) Provide a non-binding good- fàith estimated schedule for implementation of BPA
required facilities.
The Points Of Interconnection (POI) addressed in this study include BPA-TS's Bridge I 38-kV
Substation and a new switch station looped into the Bridge-West Wendover I 38-kV transmission
line, just south oflynn, Utah.
The tecbnical study results includ ~ tli~tl~a~l\ie for interconnection only.
Technical studies for trans niee .fOl deH'very of output beyond the point of
interconnection are not includ ~~ísñiission servce for delivery beyond the point of
iutercounection mnst be requ~ 1índ arrnged for separately.
',\,f;
These studies were C6fiâ'bèted using the best available information at the time of the study.
Findings and recommendations are based on assumptions, which could cbange. Bonnevile
reserves the right to modify the conteiit in this report as necessary with pertinent
justification.
2. Conclusions and Recommendations
The JFES study supports the interconnection of up to 33 MW of generation, with a protective
remedial action scheme, into the Bridge 138 kV Substation as indicated on the Preliminary
Sketch in Attachment A. This capacity is based 011 existing and planned facilities in the arca.
including generation interconnection requests preceding the Grouse Creek Wind Project in BPA-
TS's OASIS interconnection queue. The generation that can be supported by the system in the
area is limited by the potential for overloads during all lines in-service conditions on the
Minidoka PH-Bridge 138 kV, which serves as the only transmission path for generation south of
Minidoka. Single line outages in the area could potentially reduce the available capacity further
OFFICIAL USE ONLY 2
This report contains BonncviJli; Power Administration Critìcallntr.structure Information (eii),
Distribution of this report must be limited to parties that have a need to know and have fulfilled
non-disclosure requirements with the Bonneville Power Administration,
Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit. IPC
Page 23 of 38
~;.i.. ~"l : I:J . t i:; . .. ".\\ \. ''', ~'. I. t
to 3 MW. This limitation can be mitigated by installng a Remedial Action Scheme to trip
Grouse Creek Wind. The capacity ofthc system is subject to Generation Interconnection
requests 00245, G0246, G0247, and 00248, and could increase if these projects were withdrawn
from the interconnection queue. In this scenario, up to 93 MW of generation could be
interconnected.
The study also supports the proposed interconnection of up to 33 MW onto the Bridge-West
Wendover 18.kV transmission line. The system capacity for this interconnection option wil be
subject to summertime limitations and generation resources preceding the Wasatch Wind Project
in BPA-TS's Interconnection Queue in the samc way as the Bridge 138-kV interconnection. Thc
BPA-TS recommendcd plan of service is to build a p.ew 3-brcakcr l38-kV substation as
indicated on the Preliminary Sketch in Attaehinentß. '." ,,;", \'1. ...$;~Y'
The Minidoka PH-Bridge 138 k
are owned by the Raft River
arrangement is to assume a 5
to usc.
as the Brídge- Tecoma 139 kV lines
by BPA-TS. BPA-TS's policy for such an
for the line, unless the owner supplies different ratings
.tto ". ~::',The Minidoka PH S\bStation is owned by the Bureau of Reclamatioii. It is assumed that
Wasatch Wind will coordinate wíth the Bureau of Reclamation to ensure that the breakers and
other statìon equipment at Minidoka are adequate to support the new generation on the Minidoka
PH-Bridge line.
Non-binding good faith estimated costs have been developed for fqF different interconnection
options. These costs are based on similar projccls, ;4~d include high voltage
equipment, controls, meter. and comml,i:l / rhead costs. The cost for
interconnection at the Bridgc i ¥,SU requests 00245, G0246. G0247. and
00248 interconnect into the 'M'p inc is $3.3M. If these projects are withdrawn
the cost for interconnection at th i¡t38 kY substation is $4M. The cost for
interconnection 011 the Bri Wendover 138 kV line assuming requests G0245. G0246.
G0247, and G0248 into the Minidoka PH-Bridge lìne is $13.2M. Ifthese projects
arc withdrawn the interconnection on the Bridge-West Wendover line is $14.6M. The
estimated ti11clinc for completion of this project is 18-24 months following NEPA clearance.
3. Interconnection General
This feasibilty study report addresses two possible points of interconnection. The first is at
Bridge 138- kV Substation, the second is a new substation along thc Bridge-West Wendover
I 38-kV transmission linc. Existing and planned facilties as well as interconnection requcsts
preceding this project in BPA-TS's OASIS queue were included in the study. Two projects that
have an impact on this project are U.S Geothem1al, and Generation Request numbers 00245,
G0246, 00247, and G0248 (G0245-G0248). u.s, Geothennal is an existing 36 MW resource
interconnected to BPA-TS's Bridge Substatl0n. G0245.G0248 arc for four 20 MW wind
resources (for a total of 80 MW) that have requested interconnection at the Idahome Substation,
OFFICIAL USE ONLY 3
This report contains Bonneville Power Admini51ration Critical Infrastnictufc Information (eii).
Distribution of this rcport must be limited to parties that have a need to know and ha\'c fiiltìlled
non-disclosllc rcquirements with the Bonneville Power Administration.
Attachment No, 4
Case Nos, IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 24 of 38
This project lies within the Idaho Power Company Control Area. As such it is the responsibilty
of thc developer to make agreements with Idaho Power regarding thcir network and AGe
(Automatic Generation Control) requirement... Additional hardware and communications
functions may be required over and above those requirements stated in this study.
3.1 Interconnection at the Bridge Substation
The first alternative interconnection. Option IA. to the aPA~rS system ìs at Bridge 138 kV
Substation. The pOint of intercoMectioii wiJinclude a new i 38-kV temlJntl at Bridge
Substation, The work at the terminal includes a cireuit breker. three switches and asiat~
relaying and controls. A more detailed analysis of the substation work wil be çoinlete in the
hitercoMectÎOn Facilty Study. At this time, the MinidokaPH-Bridgc 138 leV ininsmisliotl line
wil overload during summer time light load holl with U.s. Getherml and Gl 24S~248 at peaklevels ¡fthe Grouse Creek Wind Project gènertion exceeds 33 MW. The overload is
exacerbate by any contingency which trps radial load. A Remedial ActÎon Sceme (RAS) wil
be necessar to trip generation at the Project during sUPlmcr time. lo,.,load hours in the event of
such a I.08S ofload. In addition Bridge has aìiection,to.imdoka PH vias 40 mile
long transmission Une. A RAS is also ' tptate Line Los Logic (LLL) at
the Minidoka PH Substation tt) trip,ge et in the event oia eontingency of the
Minidoka PH-Bridge i 38~kV liiitl.i '\
i,
A varation on the iniereonn~rhridge Substation. Option i a, occurs in the event that
00245-00248 do not" , ot at ldaome Substation. In tbis scenario the maximum peak
level of generation at se Creek Wind Projeot would be limited to 93 MW, wbich is less than
the requested 150 MW. and subject to the sae remedial action sche as desçrbed fOr the
Option lA MW peak generation leveL. In addition to requirements for Option I A, Option i B
requires placement of addítional BPA control equipment at Grouse Cre Wind Collector
Substation and 36 miles of fiber optic cable instaled betwen the CoUcctor Substation and
Bridge Substation.
(n the last 10 years. the Minidoka PH-Bridge~i1Í.llåsba ~tb''àf11 non..momentary outages
with un average length of 56 mimitçsJorèàcho MÎiiidokaPowerhous Substation.
owned by the Bureau of Reclamájìò~ (Burea;L); old subståtion imd it is likely that breakers
and other station equipment may Jiced tø'Wtipgradcd to support the new generation.
'"''v''''' v.,
It is assumed that Was¿itcñWiiid wil be responsible for securing the right of way and
construction ofthc 13~4('V transmission line from the Grouse Creek Wind Collector Substation
to Brìdge Substation (BPA-TS) and development of facilities at the Grouse Creek Wind Project.
Wasatch Wind wil be responsible for installing a 36 fiber, fiber-optic cable between the 138 kV
generation project step-up substation (Collector Substation) and Bridge Substation. BPA-TS
requires the exclusive use of 12 fibers. The Collector Substation shall include space in the
control building for all BPA-TS equipment, for options that require it. in addition to Wasatch
Winds needs.
OFFICIAL USE ONLY 4
This report contains Bonneville Power Administration Ciìtìcal Infrdstructure Information (elli,
Distribution of this rl.-port must he limited to i,arties thaI have a need to know and have fulfilled
non-disclosure requirements with the Bonneville Power AdininísiralÌon,
Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 25 of 38
: ,.11.... \'í ..3
Please notc: For both options I A and 1 B Wasatch Wind needs to contact thc Idaho Power
Company (IPe) since the generation is located in IPC's load control area and they are one of the
affected transmission systems.
3.2 Interconnection on Bridge-West Wendover 138.kV Line
The second alternative, Option 2A, point of interconnection is along the Bridge-West Wendover
i 38-kV Line. The point ofinterCOllnectÍon would be approximately 36 miles Oiit from the
Bridge Substation towards West Wendover. The work at the New POI Substation (ncar Lynn,
Utah) includes a 3-breaker ring bus. associated relaying and controls, control house. and
communications equipment. A more detailed analysis of the substation work will be completed
in the Interconnection Facilty Study. It is assumea klh . 'Wil be responsible for
all transmissionlìne Right-or-Way acquisition, of the 138 kV line tì'om its
Collector Substation to the New POl ~!J~aiil 8" opmcnt oftàciltics at Grouse
Creek Wind Project. Option 2A i~fW~ lùnte~Jpjl peak level of generation with similar
remedial action schemes proposed rorO~*fA, except that the generation trip wil occur at the
New POl Substation. CommunicaliaPs\vìI be extended from Bridge Substation via new fiber
optic cable to the New POl,s"UpStûHon over the Raft River owned. BPA-TS leased transmissionline. '~\¡'i,;~'
A variation on the interconnection at the New POI Substation, Option 2B, occurs in the event
that the G0245-G0248 do not interconnect into Idahome Substation. The maximum peak level
of generation at Grouse Creek Wind Project in this scenario would be limited to 93 MW. which
is less than the requested iso MW, and subject to the same remedial aq~on schemes as described
for the Option 2A 33 MW peak generation leveL. Iit. ,rHon to ,\i~lirements for Option 2A,
Option 2B wm reuire generation trp equip~: Wind Collector Substation
and extension of comunieaiionsviaJlbß"df,úc Cll the new POI Substation.
'\,++î*'~' ,,,' \
Wasatch Wind wil be responsible fO~)llSt'¡:Mlrlg a 36 fiber, tiber optic cable between the Grouse
Creek Wind Collector SubstatiQi:ai&tlic New POl substation. BPA-TS requires the exclusive
use of 12 fibers, Wasatcp,,'l'¡Ôdshall include space in the control building at Grouse Creek
Wind Collector Substatid'ìl for all BPA- TS equipment in Option 2B, in addition to Wasatch
Wind's needs. Also as mentioned in section 3,1 above, the Minidoka Powerhouse Substati()!,,
owned by the Bureau, is an old substation and it is likely that breakers and other station
equipment may need to be upgraded to support uic new generation.
For Options 2A and 2B, Wasatch Wind needs to contact ipe sinee the gciicration is located in
IPe's load control area and they are one of the affected transmission systems.
3.3 Network Resource Interconnection Service
The LGIP defines Network Resource Interconnection Service as Interconnection Service that
allows the lnterconnection Customer to integrate its large Gcnerating Facility with the
Transmission Provider's transmission system in a manner comparble to that in which the
Transmission Provider would integrate new generating facilities to serve nntive load customers.OFFICIAL USE ONLY .)
This report contains Bonnevílc Power AdmiiiislTiltion Critical Infrastructure Infol1iation (eii).
Distribution ofthis report must be limited 10 parties thai have a need to know and have fulfiled
non-disclosure reuirements with the Bonneville Power Administration,
Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-1Q-62
Allphin Affdavit, IPC
Page 26 of 38
FERC has stated that the Interconnection Customer may designate their large Generating Facility
as a Network Resource any time before the Commercial Operation Date (COD). Further. the
LGIP states that Network Resource In,terconncction Servic~ does not convey in iud of itslf
transmission service. A new or existing Network Customer of the TransmissIon Provider must
fie a Transmission Service Request to designate the Large Generating facilty as a Network
Resource. Once the interconnection Customer has obtained Network Reurce Interconntion
Service, requests for network Integration Transmission Service from the Generating Facility to
points inside the Transmission Provider's transmission system will not require additional
interconnection studies or additional upgrades. However. requests for delivery service inside the
Transmission Provider's transmission system may require additional studies and upgrades if they
are necessary to reduce congestion to acccptablt¡ levels.
, . l'\..;,!~'1(t.'i~.~ '/,,' ", .£,",:.;/~::,. ~;Assuming tlúsprojeçt wouldsc . ~A\:TS~oti(loads in the Southern Idaho area, llétwork
addit,ions would ootbe re . c eho1lè\iuired for interconnection. Service to BPA- TS's
network loads beond the theqil4ò ara would require transmission additions from
Souther Idaho to those lOllQ,$S; Ìice BPA-TS does not own a continuous transmission path
from Southern Idahq,t!?'9t,et parts of the BPA-TS system in the Northwest.
$ ";.¡ i¡ .'ft""
4. Transfer Trip Relaying and Remedial Action Scheme (RAS)
BPA-lS wil not require trnsfe triprelaying for the project line tcminal at either Bridge
Substation or the new POi Substaüon along the Bridge-West Wendover 138-k V Line. Wasatch
Wind wil be responsible for the line. fiber cable on the line and tenniiial at the 138 kV Grouse
Creek WindCoUectorSubstation. Agreeinents ~tween Brtt1.s. Raft River. and Wastch Win
wUl need to be completed to acommodl\.7t\~ttqu!Il~~htlesatthe interconnection sites.
ft" ef; '"'" t.:~" "\ *,.A local RAS with redund ~ ir(mics.~ ilrcd ,to trip Grouse Creek Wii\d genetion for (I)
Bridge-MinidOka PH ( ine~)~aäing çonditions and (2) opening of the I :l8K V PCB to
the power grd at Minidoka", \:,'~.
t:T',\
~, 'For Option IA.li~tlêtient sensing (requires addition ofCT's) at the Minidoka PH end ofthc
Bridge Substation line and LLL for the PCB at the Minidoka PH end of this same line are used to
trip generation at Bridge Substation.
For Option 2A, the same conditions arc sensed at Minidoka PH and used to trip project
generation of 33 MW at the new POl Substation (two PCB's),
For Options 1B and 2B. an additional condition is added requiring sensing ofline current at the
Bridge Substation end of the line to Minidoka PH (requires addition of CT' s) to trip generation at
Grouse Creek Wind Collector Substation. The LLL input from Minidoka PH is used to trip the
entire Grouse Creek Wind Project generation output at Bridge Substation (Option i B) 01' at the
Grouse Creek Wind Collector Substation (Option 2B)
Whcnever the entire generation is tripped for any reason. Wasatch Wind will need to get
pennission from ipe to begin generating again.OFFICIAL USE ONLY 6
This report cont¡¡in~ Boonevile Power Administration Criticallnfmstrcture Information (Cll.
Distribution oftliis report must be limited to parties that have li need 10 know and have fulfilled
non-disclosure requirements with the Bonnevile Power Administration,
Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 27 of 38
1.1-." ¡'d ¡., ,"
5. Communications, Control and Metering
BPA-TS will install. own and operate the Fiber Optic (FO) and Communication and Control
(C&C) equipment at either Bridge Substation or the new POI Substation along the Bridge-West
Wendover 13l: kV line and the I 3H kY Grouse Creek Wind Project step-up collector substation.
For Options I A and 2A, BPA-TS wil install 138 kV PCB B-switcl indication and
of Voltage, Kilowatts and Kilovars at the Grouse Creek Wind Collector Substation
line to Bridge Substation. Wasatch Wind shall provide the leased line for BPA..TS's usc.
(Public Switched Telephone Network) connectivity. .. be Wastch Wind to
enable BPA-TS'g MV-90 (Revenue Meteri the ¡PC
Meters at the Grouse Creek Wind C:qBtllttdr asatch Wind wUlbc required to i.tall
36 tiber, fiber optic cable for Op1~ rB ll!1tl$ n Wind Colteetor
Substation and the new POl Substti~9A~åttynn, Utah.
~~ .,; ."
BPA- TS will upgrade J.%~~is(ihg analog radio link between Bridge Substation and Albion Butte
Radio Station to digitaf:tìdio, Options lA, i B. 2A and 2B. The radio link from Albion Butte to
Minidoka Radio Station is being upgraded 10 digital radio under another project and its cost is
not included here. BPA-TS wìl install new SONET (Synchronized Optical Network) equipment
on BPA-TS installed fiber optic cable from Bridge Substation to the new POi Substation
(Options 2A and 2B), and Wasatch Wind installed fiber optic cabl.c (Option 2B). BPA-lS wil
add thc required circuits over the new facilties and itscxistil1g cqtl~nication facilities for
BPA- TS implementation of all the control CirC\lit:r~iÌ'mcnts'fifihìs pr~ject as dictated by
Options I A, i B, 2A and 2B.' \ ~
\5 ",;o;_+;"'tBPA-TS's C&C requirements indlutfe: ",~: ",,4;
. Voice: Dial Party circujH~i'ilùiccCSS to the OATS (Dial Automatic Telephone
System) for maiiltelliinbè purposes at the new POI Substation and at the Collector
Substation rprÒ¡11íons I Band 2B.
. Data: ~
a A PSTN (Public Switched Telephone Network) phone line for remote access of
the ipe generation meterS at the Grouse Creek Wind Collector Substation by
BPA-TS's MV-90 system,
a Since this project is within the ldaho Power Company's control area they wil
need data from the project for their network operation, AGC (Automatic
Gcneration Control), Generation Metering and Biling functions. The
requirements for this infomiation niust be provided by Idalio Power Company
and is not a part of this study ~
a BPA-TS will collect PCB and relay status and alarm information from
transducers, relays, RAS and communication equipment via a SCADA RTO.
SER (Sequential Events Recorders), FfN (Field lnformation Network) at Bridge
Substation (Options lA, lB, 2A and 2B), Minidoka PH (Options lA, lB, 2/\ and
2B), the new POI Substation along the Bridge-West Wendover 138 kV lineOFFICIAL USE ONLY 7
This rep~)rt contain, Bonnevile Power Administration Crittcallnlhistructurc Information (('I),
Distribution oftJiis repan must be limited to parties that have u need to know and have fulfillcd
non-disclosure requirements with the Bonnevillc Power Administration.
Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 28 of 38
(Options 2A and 2B) and at the Grouse Creek Wind Collector Substation
(Options 1B and 2B),
o For Options IA and 2A, BPA will add 138 kV breaker status indication (8-
switch) and telcmetcrillg ofVo1tagc, kW and KVar at Grouse Creek Wind
Collector Substation via leased line (provided by Wasatch Wind) to Bridge
Substation and integratcd into the SCADA RTlJ at Bridge Substation.
.BPA-TS wíl add SCADA control, at Bridge Substation (Options IA and 2A) and at
the new POI Substation along the Bridge-West Wendover I 38-kV Line (Opti011s i B
and 2B).
Protection relaying is required on the ncwCl~~ßkY liPts~\ît:is anticipated that TT
(Transfer Trip) to provide high sfleéd clearing, lil(pÒwer system faults wil not beneccssaiy. \:~ '1 ','
.
.RAS (Remedial Action Scl)ølné)0~~e paragraph 5.0: RAS requirements have been
identifled and the ei~cîróÜtês are redundant for maintainability. Generator dropping
schemes wíI needfó"bc incorporated,
.For Options 1 Band 2B, some of BPA-TS's C&C equipment wil operate from the
Grouse Creek Wind Collector Substation '8 129VDC station batteries. (Load to be
defined later.). Also, BPA-TS will add a 48VDC Battery and Charger System for its
communications equipmcnt at the Grouse Creek Wjnd Collector Stbstntion" '.. ",.
.The BPA- TS C&C equipment must bc:intlb~~ (a~a~;,ftòri./ilirt!mOisturc) in a climate
controlled tàcility between 60,~Ð,d 8ll.DCgrecs~f.\ ' .
l~t4. '""
For cyber security reasons, somc'QNÌi~'BPA-TS equipment wil be housed in a
locked cabinet.,,,. ' ",
.
The estimates in Seclioh 7.0 assume that the control house at Bridge Substation has
adequate space to house all new equipment for communication and control associated
with this project. A morc detailed analysis of the control house capacity and more
accurate estimates wil be completed in the Interconnection Facility Study along with a
dctaílcd communications plan and estimates.
6. Technical Analysis
Steady State Powcrflow, reactive margin Q-V curve analysis, and thermal analysis have been
conducted for this project. Assumptions, models and results arc described below.
OFFICIAL USE ONLY 8
This report contains Bonneville Power Administration Criticallnfrastructure Information (cIl.
Distribution of this report must be limited to partic.~ that have a need to know and have fulfilled
non.disclosure requirements with the Bonnevile Power AdiuiniMration.
Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 29 of 38
',' ; .,',. ~t..~ ,:".., . .. ~, , f !:t.1 .. Ì' ; ~ :
6.1 Analytical Approach
Two types of computer based contingency simulations were performed and analyzed for this
IFES: (In addition, short circuit studies were performed. which arc given on the Draft PRD)
. Powertlow studies to evaluate thermal loading and post-transient voltage levels.
. Q-V curve power margin studies to eval~~e rela,!i~e'êifihge in the transmission
system capability with additìonpf oJect. " '~\'
.",J..'~ t ,~A,'t '.;. '\Powerflow, thermal and rçâclVC ll~l: Q"V curve study work for the IFS were
performed using PowerWorld,Sjjifa'tor Version 12.0 OPF, ATC, SimAuto integrated
transmission analysis softWe'~ ",.,~t-". . '
6.2 -if 1',"'1:Powerf1ow Model"
The approach used was to model the most severe conditions that have occurred in the past that
could impact the generation interconnection capacity. The most severe condition appears to be
light loadings on the radial 138 kV line from Minidoka P.H. to Wendover. Nevada. Multiple
generation patterns were modeled to investigate the limiting conditiol~~ that inay detcimine
system expansion requirements. ','\ ", .. .
6.3 Study Scenarios
';~:;f't; '0,_ '''
In order to assess the impact ofintérconi;er;tihg'Wasatch Wind into the BPA-TS's transmission
system, BPA-TS perfonl1ed Pow~rtiòw;šiudies using BPA-TS suminer and winter 2010-Uz, ~. "Ypowertlow base cases.'~
The shidics include gcncratìon resources that precede the Wasatch Wind Projects in BPA's
Interconnection Queue as well as resources scheduled to be in-service prior to the Wasatch Wind
Projects and integrating into other transmission provider's systems. These faci1ilÌcs include; the
U.S, Geothermal integrated into BPA's Bridge J 3R-kV Substation with a net nominal output of
approximately 36 MW. Also included as in this study were requests numbers G0245, G0246.
G0247, and 00248, totaling 80 MW. which have requested interconnection onto the Minidoka
PH-Bridge 138 kV line.
. Seasonal cases during peak load and light load (30% of peak) hours,
. Seasonal cases with and without summer and winter peak generation at Minidoka,
. Seasonal simulations with and without local capacitors available,
. Seasonal cases with and without reactive support at proposed Wasatch Wind projects.
. Seasonal simulations with and without generation at U.S. GeothermaL.
. Seasonal cases with Wasatch Wind Generation modeled at Bridge and with Wasatch
Wind Generation modeled along the Bridge-West Wendover 138-kV Transmission
Line.OFFICIAL USE ONLY 9
This report contains Bonncvílc Power Administration Critical Infrastructure Information (ell,
Distribution of this report must be limited to parties that have II need to know lind have fulfilled
non-disclosure requirements with the Bonnevile Power Administration,
Attachment No.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 30 of 38
6.4 Interconnection at Bridge
With all other generation sources operating at peak Icvel including requests covered by 00245.
00246.00247. and 00248, dlling summertime low load hours, the introduction of more than 33
MW (Option lA) of generation interconnected at the Bridge I 38-kV Substation causes
overloading on the Minidoka Powerhouse-Bridge 138-kV transmission line. This ovcrload is
exacerbated by the loss of either the Brídge-Curlew or Bridge-Wendover I 38-kV lines.
However. even during the worst coiitingency, the line would be able to SUppoit up to 3 MW
interconnected at Bridge. In order to safely interconnect 33 MW of generation. a remcdial action
scheme (RAS) will need to be implemented to drop excess generation in case the line overloads.
In the event that the requests in the queue, 00245, 00246, 00247, and 00248, ahead of Wasatch
Wind's request were withdrawn for some reason, tlewerconl1 ø;cßould accommodate up to
93 MW of generation composed of two incrc~Wtrt MW (Option 1 B). During
summertime low load hours, the inir()d,~cti9n \1 nio~~ MW of generation interconnected
at the Bridge J 38-kV Substation,~~esÔvc hitn the Minidoka Powerhouse-Bridge 138-
kV transmission line. This overldád is .~, d by the loss of either the Bridge-Curlew or
Bridge-Wendover i 38-kV lines. ~Wevcr, even during the worst contingency, the line would be
able to support up to 63 I'vl,¥.iriærconnected at Bridge. In order to sa.fèly interconnect 93 MW of
generation, a remcdiahnêtióri scheme (RAS) will need to be implemented to drop excess
generation in case the line overloads.
6.5 Interconnection at New Substation
Along Bridge-West Wendover 138-kV Line with an other generation sources operating at peak
level including requests eovered by 00245, 00246, 47, and ~S, (Option 2A) during
summertime low load bOUT, the system capac~t " nnection is also limited
by the potential (or overloads on the M,!iiíqpk.' rfl-Bf kV line. The generation is limited
to MW, with a remedial aciiotl,s~cih to ratioii in the $iime way as thc
interconnection at Bridge Substaikln:
:¡,,"""t)
In the event that the requcsts..i~Jt1ëqucuc, G0245, G0246, G0247, and 00248, ahcad of Wasatch
Winds request did interètifii1ect on the Minidoka PH-Bridge 138 kV line. the interconnection
could accommodate up to 93 MW of generation composed of two increments, 33 MW and 60
MW (Option 2B). During summertime low load hours. the system capacity for this point of
interconnection is also limited by the potential for overloads on the Minidoka PH-Bridge i 38 kV
line. The generation would bc limitcd to 93 MW, with a remedial action scheme to drop 33
MW. in the same way as the interconnection at Bridge Substation.
6.6 Fault Studies
Preliminary short circuit CUlTcnt values shown on the sketches are present values. System fault
studies will be conducted in the Interconnection Impact Study incorporatÍng proposcd system
additÍons and gencrators, Although, prcliminary brcaker screening analysis indicates that noOFFICIAL USE ONLY to
This report contains Bonnevile Power Administration Critical fnfrastnicture Information (CII),
Distribution of this report must be limited to parties that have a need to know and have fulfiled
non-disclosure requirements with the Bonnevile Power Administration.
Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 31 of 38
~". . ~., lltJ' d,.,t . \ ',.
breakers will need to be replaced due to increased fàult duty requirements, there remains a
possibility Breakers may need to be replaced. Customer equipment should be sized to
accommodate system growth.
7. Cost Estimates
Good faith non-binding Estimates of customer costi for ¡DrereaDD tion options I A, lB, 2A,
and 28 arc given in Table I. These estimatc~\~~d on for similar projects. These
costs are only for the Bonneville supplipd (sQBes k~'tlt is time. Existing equipment in
the substation and nearby substatin&,p eplaced at additional cost iffault duties
require it. There may be additii co Vll'g one or more transmission lines associated
with options 2A and 2B. I . Wasatch Wind wil be responsible for aU
equipment, facilities deve site development including land acquisitions, and
permitting, includi~t impact assessment.
"i,'
BPA wil make thc decision 10 proceed WiÙl this interconnection based on an environmental
evaluation as required by the National Environmental Policy Act (NEPA). Onee the decision is
made to proceed. the typical schedule for completion is i 8-24 months.
Table i - Cost Estimates
OFFICIAL USE ONLY I i
This rcport contains Bonneville rower Administration Criticalliifrastructure lntonnation (ell,
Distribution of this report must be limited to 11arlics that havc a need to know iind have fulfilled
non-disclosure requireinents with the Bonnevile Power Administration.
Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 32 of 38
~hin, Randy
From:
Sent:
To:
Subjec:
Allphin, Randy
Friday,. June 25. 2010 7:48 AM
'Christine Mikell'
RE: Proposed Grouse Creek Wind Project
Christine,
I am buried today and traveling Monday.
Lets break this down into two parts-
PPA - if you are less then 10 average MW, the project wil qualify for the published avoided cost rates contained in IPUC
order 31025. No pricing runs on my part required. There are some seasonality and HL and LL factors that are applied to
the prices within that order. In addition, the contract is pretty standard, very little negotiation by either part as the
contract is pretty well established by numerous commission orders.
Transmission - my process to file for the transmission capacity request is no different whether you are 10 MW or 69
MW. However, the application we file wil contain a single maximum capacity number. Currently the information you
provided me was for 69 MW, please send me a new information page with your new size.
The feasibilty information is exactly what I needed for that piece.
BPA capacity - sorry if I overlooked the previous information you sent, but could you resend the information
with a summary cover letter.
Future projects - we could not agree to anything today, have to deal with future projects at the time you propose them.
Thanks Randy
From: Christine Mikell (mailto:christine(Çwasatchwind.com)
Set: Thursay, June 24, 20102:16 PM
To: Allphin, Randy
Subject: RE: Propo Grouse Creek Wind Projec
Hi Randy,
i just left you a message. In short, we have three golden eagle nests within about .5 miles from some of our turbines.
After meeting with USFW service recently, it looks like to mitigate impacts to golden eagle populations we wil have to
have greater setbacks between golden eagles and the turbines, i.e. drop turbines because the land is constrained. Based
on this, it appears that we wil need to discuss with you changing our initial request to a 10 MWA request. Is this
something that is easy for you to rerun, or do you anticipate that it wil result in the same answer? i know that when we
spoke some time ago that you suggested that the new natural gas pricing would mean the 10 MWA and less than 80
MW PPA prices would be about the same. I think you had guessed that the pricing would be about $70!MWh. Since the
pricing is at $55!MWh for the larger QF, i thought perhaps there was stil that price disparity.
We would like to discuss with you the option to build one 10 MWA QF and possibly another 21 MW's at a later date. We
plan to make a transmission service request to BPA for 30 MW's and possibly another 21 MW's. Based on our
interconnect studies and conversations that we have had with BPA (not to mention the analysis that we presented to
you that BPA gave us), there are 93 MW's available on that line to the Minnidoka substation.1 ~~~~~4Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 33 of 38
The feasibilty study is completed and attached and yes we acknowledged/accepted the results of that study.
Let me know a good time to talk. I am out after about 3:30, but back again tomorrow. love to catch up so we know how
to make the proper TSA with BPA:: by Wednesday.
Thanks,
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth,
ww.wasatchwind.com
Wasatch Wind
This message and any aUachment. contain 'nformalion thal is proprietary, conridenbal and pnviteged, They are inlended lor the privale and exclusive use of the addressee and are covered by tie
Electronic Communications Privacy Act, 18 U,S.C §§ 2510.2521 Unless you are the addressee (or authanzed to receive for the addressee) you may not use, copy, pnnt or disclos to anyone thl.
message Of any informatian c:ined in ihe message and any attachments If yo have rece've this communication 'n error, please advise the sender by reply and delete this message
From: Allphin, Randy (mailto:RAllphin(gidahopower.com)
sent: Wednesay, June 23, 2010 8:07 AM
To: Christine Mikell
Subject: RE: Proposed Grouse Creek Wind Projec
Christine,
Thanks for this information, I have been looking it over and making our preparations to make the transmission capacity
request on the Idaho Power system. I expect that the transmission group wil not accept our request without more
detail and/or assurance that the BPA transmission is available from your project to the point of delivery on the Idaho
Power system.
I know we have discussed this quite a bit- but could you send me a write up in regards to the availability of the BPA
transmission capacity. If possible, include as much reference to your actual filngs in the BPA process and status. Clearly
the best solution would be to be able to state that BPA transmission capacity is available and the project has rights to it.
Another note - on the interconnection section you state that the Facilty study is due the end of June. I would assume
then that a Feasibilty study is already complete and you have accepted the results of that study - could you send me
your answer to this also in written form (basically an answer to item F of on the transmission questionnaire)
Thanks Randy
From: Christine Mikell (mallto:christine(gwasatchwind.com)
sent: Thursay, June 17, 2010 1:22 PM
To: Allphin, Randy
Subjec: Propos Grouse Creek Wind Project
2 Attachment NO.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 34 of 38
Hi Randy,
Attached you wil find out letter of understanding. Please let me know if you would like the hardcopy too.
Kind regards,
Christine Watson Mikell
Senior Project Development Manager
Direct 435-503-8814
Mobile: 801-455-1045
clean energy, clean air. clean earth.
ww.wasatchwind.com
Wasatch Wind
This message and any attachments contain ,nformabon thaI is propnelary. confidential and priviegd, They are íntended fo th priate and exusive use of the addreee an ere coved by the
Electronic Communicabona Prvacy Acl. 18 US,C §§ 2510-2521 Unles yo are li addressee (or authorzed 10 reve for the addressee) you may no use, coy, prim or disclos to anyone ths
mege or any informtion contained in the message and any allchments ø you have reíva this comunicalíon In eror, please advíse the sender by rely and delete ths meage
B_~
This transmission may contain inforion that is privileged, confidential and/or exempt from disclosure under applicable law. If yo are not the inten reipient, yo are hereby
notified that any disclosure, coying, distribution or use of the informtion containe hern (including any reliance ther) is STRICTLY PROHIBITD. If you reeived thistrsmission in err, pleas immedately contact the sede and deroy the material in iti entirety. whether in elecroc or ba coy formt. Thank you.
3 Attachment NO.4
Case Nos. IPC-E-10-1 & IPC-E-10-2
Allphin Affdavit, IPC
Page 35 of 38
Allphin, Randy
From:
Sent
To:
Subjec:
~hti$titi NW £christinetmsatchwlnd.coml
Monday, June.2. 201tl S;05 PM
Allphin; Randy
10 MW PPA
Hey Randy,
Is the PPA contract online for the 10 MW QF?
Thanks!
Christine Watson Mikell
Senio Projec Devement Manaer
Direct: 435--03-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
ww.wasatchwlnd.com
Wasatch Wind
1 Attachment No.4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 36 of 38
.chin, Randy
From:
Sent:
To:
Subject:
Allphin, Randy
TGesdRV, June 29, 2010.6:48 AM
'Christine Mikell'
RE: 10 MW PPA
My routine process is to not develop a draft agreement for a specific project until the transmission and interconnection
is pinned down - however, I am currently working up a draft agreement for another project, I am thinking I should be
able to duplicate that draft contract for your project. It wil be a week or two before I have it ready to go.
Randy
From: Christine Mikell (rnllt:øhl1riWlDØ.col
Sent: Monday, June 28, 2010 9:51 PM
To: Allphin, Randy
Subject: RE: 10 MW PPA
Can we get a copy or do we need to wiat?
From: Allphin, Randy rmailt:RAllphinOld~col
sent: Monday, June 28, 2010 7:48 PM
To: Christine Mikell
Subjec: RE: 10 MW PPA
No
From: Christine Mikell rma1lt:øhl1neC9watttind.coJ
sent: Monday, June 28, 2010 5:05 PM
To: Allphin, Randy
Subjec: 10 MW PPA
Hey Randy,
Is the PPA contract online for the 10 MW QF?
Thanks!
Christine Watson Mikell
Senior Project Development Manager
Direct: 435.503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
ww.wasatc:hwind.com
Wasatch Wind
This message and any attachmets contain information that is ptopnetary. confidential and p'IlIlegad, Thay ara Intende for th prvate and exclusive usa of the adâlssee and a'e covere by theEIeclronlc CommunlcatLons Pnvacy ACI, 18 USC §§ 2510-2521., Unless you are th addressee (or authorzed to ,eceive for the addresee) you may not use, copy. pnnt or disclose 10 anyoe this
message or any informalion conLalned in Ihe message and any attachments. If you have received this comunicalion in error, pLease advise the sende, by reply and deLete this message
1 Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 37 of 38
i Attachment No. 4
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 38 of 38
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION\
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO.5
~hini Randy
From:
Sent:
To:
Subject:
Attachments:
Christine Mikell (christine(§wasatchwind.com)
Wednesday, July 14,20103:52 PM
Allphin. Randy
RE: 10 MW PPA
GrouseCreekCLlPC02010J _14.pdf; GrouseCreekQF1 indicpric_201 OJ _14.pdf;
GrouseCreekQF2indicpric_2010 J _14. pdf; GrouseCreek- Timeseries Vestas201 OJ _14.xlsx;
V112 Gen Spec. pdf
Hi Randy,
As we discussed on the phone earlier, here a cover letter, two 10 AMW QF requests, the time series for a Vestas
machine and the specifications for the Vestas V112. You should be receiving the Fedex package tomorrow.
Look forward to hearing your feedback. Also, if you have made any headway in the draft agreement for the other
project, would love to see that!
Thanks,
Christine Watson Mikell
Senior Project Development Manager
Direct: 435.503-8814
Mobile: 801-455-1045
www.wasatchwind.com
Wasatch Wind
clean energy. clean air. clean earth,
This message and any attachments contain information that IS proprietary, confidential and privileged They are intended for the pnvate and exclusive use of the addressee and 8re covered by the
Eleetronie Communications Privacy Act. 18 U.S,C § 2510-2521 Unless you are the addressee (or authorized to receive for the addressee) you may not use, copy, pnnt or disdose to anyone this
message or any Informa1ion contained in the message and any aUachmenls If you have received this communication In error, please advise the sender by reply and delete this message"
From: Allphin, Randy rmaJlto:RAlIphiI10ldho.coml
Sent: Tuesday, June 29, 2010 6:48 AM
To: Christine Mikell
Subject: RE: 10 MW PPA
My routine process is to not develop a draft agreement for a specific project until the transmission and interconnection
is pinned down - however, I am currently working up a draft agreement for another project, I am thinking I should be
able to duplicate that draft contract for your project. It wil be a week or two before i have it ready to go.
Randy
From: Christine Mikell (pillt:chrfnetmastcwind,co)
Sent: Monday, June 28, 2010 9:51 PM
To: Allphin, Randy ,
Subjec: RE: 10 MW PPA
Can we get a copy or do we need to wiat?
i Attachment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of22
From: Allphin, Randy (mallto:RAlphin(cldahogger.c;ml
sent: Monday, June 28, 2010 7:48 PM
To: Christine Mikell
Subject: RE: 10 MW PPA
No
From: Christine Mikell (mallto:chrlsnesatcblnd,col
Sent: Monday, June 28, 2010 5:05 PM
To: Allphin, Randy
Subject: 10 MW PPA
Hey Randy,
Is the PPA contract online for the 10 MW QF?
Thanks!
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earth.
ww.wasatchwind.com
Wasatch Wind
This message and any allachments cotain in/ormalion Ihaiis propnetary. conldenl,al and pnvileged They are intded for the pnvele and exclusive use of the addressee and are covered by the
Eleclronic Communicalions Povacy Act. 18 U S,C §§ 2510-2521 Unless you are the addresee (or autonzed to receive for Ihe addressee) you may not use. copy, print or discose to anyone this
message or any inforation conlained in Ihe mesage and any attchments If you have receive this communication in error, please advise the sender by reply and delete this messege
This trnsmission may contain information that is privileged, confidential and/or exempt from dil09ureunder applicable law, If you are not the intened reipient, you are hereby
notified tht any disclosure, copying, dislribulion, or use of the infonntion contained herin (including any reliance Ihern) is STRICTLY PROHffITED. If you reeived this
transmission in errr. please immediately contact the sender and destroy the mateal in ils entiret, whether in electronic or ha copy format. Thank you.
2 Attachment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 Of 22
.BI
Transmission Capacity Appicatlon Questionnaire Al IO ce
Ths list is the kno Infomatk reme as of the ds of the lett trnsmng ths request. If adlnmati
Is required, Idaho Po wUt pry noif th project devlor of the addtional infoti requirement.
A. Project Name
(3VOLAs,G Cvt"ck.W\Y\d PørL. i
B. Projec location
:3 Mi \ 'Sa Go.\ heaSt- 0 f- I.Vln lAiM=r 14 h' R \7 \,
c.Project Developer
Name
Addre
City I Stte I Zip
Phone Number
E-mail
Wg,sa h. \U.lluQ :Ix\=\r:rn:tA\o, Lt...L
1.100 l+m.nJ,(' £'alf $14 fß.'2Î 0
~yt ~ì ~i i~r ~~o'8à öC =ç;; I u; t- j == 5- 503-ß~I:q
c:.hr: i 511 he.. (2\I\ß\l.h" Y\I ,,,øl .(oVV
D. Internnedon "Q" rerence number (if not knon. please coct th host utlity
Intrcnnection group)
GO" 3U
E. Evidence of the Projet's good standing status in the host utlftys Intrcnncton process
V dc, uta Sh(Q~:k d
F. Coy of the Internnectn feasibilit stuy and a sttement from th prect that the project
has accpted the reults of th Intrcnecton fesibilty study and Is cotiuing the proces
of Interonnecting and developing the genertion project.
G.Maxium Caacit (MW)jo MWls
Pilei oU
Attachment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 3 of 22
H. Beginning day and time of energy derivries
Day (øi) t 1.11 J 2.ti.
Time 00' 120Pd'C'ìb c ìlvv
t Ending day and time of energy delivrie
De (mmll I J.l I /2.02 7-
Time 00 ." Qi) Fe. c16, , til"
J. VAR capability (both leading and lagging) of all genertors :)c' ( Co, 't h: (() ¡ i~ t~
K. Identifican of the contrl araa(s) from which the energy wlll onginate
'-r cia he Poy'c~--
L. List any periods of restrcted optio throou the year
M. Maintenanc schedule-
N. Minimum loading level of eac generation unit (Vh v ( ", I f'b I Sf ( llRtí c1wi: ::;¿. S' l"eel J'L .~
o.Norml operating level of each generation unit. S C -t .IU2.4
P. Any must-rn generation unit designations reuire for system reiabilty or contrctal reson
~o: ~ w: ~~o~kaß::
Pii2 of3
Attchment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 4 of 22
Q. Apprximate vanable generation cost ($IMWh) Noe-lhwfbeeBlenpdfteponl
pu po agem thet th Ptct may be øI ti.
R. If the genertion reour is to be locte In th Idaho Power Bancing Authrity Ar and if
only a portion of th reurce outut Is to be designate as a Netwrk Resur, the explain
arrngements governing sale and deliv of additional output to third partes.
S. If the prjec is no direly interconed to the Idaho Pow trmission system, proe
th trnsmission prvlder(s) name, physical Pont of Receipt, Point of Deliv and the
trnsmission resetion number fo all of die tramissin prvider reuired to deliver the
projec's energy to Idaho Po.
trals Priilcli) Nae BfA.f'ointotRe ß1rlw("Y' We.V\4OVC'" d ßvJi¿ SlA~~
PointofDelve MinidokA. S\Ak£;.lØhAo
Tranllisn Rell Nmbes) B: ß,££ - 7 'j y , i. "3 S
T. if the proct Is dirly IntDne to th Idaho Po trnsmission sysm, prode th
Point of Recept, physical location and voltae.
flOint or Hept
Pl\ i.
Volae
U. Is the project committ to exete a purcase power agreement with Idaho Pow upon a
favorable relution of the identied Intennecton and trnsmission cots?
Yes)f No 0
V. Is any poron of th maximum capacity Identied for this prjec committ to any other part
Y81 0 No Jl
Signatu Date 7-( ~~ ;)(0
Pa3of3
Attachment No. 5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit. IPC
Page 5 of 22
Exhibit A: Ansr tv Qun J
VAR cabilty (both Jeadl,. and Jagng) of aU generators)
î 0,0-0°
...1
0,5
0 01 02 03 04 05 06 07 08 09 10
¡
OA8pu
O,48W
0.4
0.3
0.2
0.1 ..øv-e~~CacJl
.. Un..xile~t¡lludle.
-0,2
-0,3
.(1.
-0.5 P(pu)
Attachment No. 5
Case Nos. IPC-E-10-61 & IPC-E-1Q-62
Allphin Affdavit, IPC
Page 6 of 22
Exhibit B-Documentation of Transmission Service Request
This customer wil be part of the 2010 Network Open Season. No notification to opt out
submitted in comments section of TSRs received
3.5 Reæipt of TSR Deposit
3.5.1 The TSR Deposit must be deposited with BPA, or into an Escrow Account, by Close of
Business 10 Business Days after the TSR status is changed to RECEIVED in OASIS or the TSR
status wil be changed to DECLINED.
If the custmer wishes to pay the TSR Deposit via Escrow, please contact the bank
directly. To allow for timely processing and to ensure the TSR deposit deadline of
7/15/10 is met, BPA reuires the Escrow Agrement, with customer signature,
from the bank within 5 business days aftr the Reæived date of 6/30/10 (by
7/8/10).
4 Non-Refundable Proessing Fee
4.1 In addition to a TSR Deposit, when making a L TF PTP or NT TSR, the Customer must
submit a separate $2500 non-refundable Processing Fee to BPA.
4.3.1 SPA Transmission Services must receive the TSR Processing Fee by Close of Business 10
Business Days after the TSR is RECEIVED on OASiS or the TSR wil be DECLINED and
receive no further consideration.
4.4.1 The TSR Processing Fee must be paid direcly to BPA Transmission Services and cannot
be placed into an Escrow Account
T . . S . R laæ' RECEIVED Sransmission ervice (ØQUEll$ Dl,in taus
Non.
Refundable
Rec'd TSRDeposit Processing 10 Day
AREF Related Ref Name Date Rate MW Due Fee Due Due Dat
Wasatch Wind
74412433 Development 6/30/10 PTP 1.298 30 $38.940.00 $2500 7/15/10
Wasatch Wind
74412442 Development 6/30/10 PTP 1.298 21 $27.258.00 $2500 7/15/10
$0.00 $0
$0.00 $0
Subtotal:$66.198.00 $5.000 7/15/10
Total
Due:$71.198
A New Long Term Reservation (TSR 74412433 ) has been RECEIVED for Wasatch Wind
Development LLC
Click here to. se Transmission Request in CBSA
A New Long Ter Reservation (TSR 74412442 ) ha been RECEIVED for Wasatch Wind
Attachment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 7 of 22
"'
~
(
,
~
1l
"
Õ
I
I
I
I
~:
r
(
1
g
.
oo
:
:
Z
3
o
)
:
0
(
1
-
3
1
~
:
:
1\
0
.
_
.
.
I\
I
I
"
'
Z
~
Ç
'
9
:.
m
o
i
"'
.
:
('
~
si ~m,..~
he
P
O
F
C
a
l
c
.
l
l
a
t
o
r
I
s
a
t
o
o
l
d
e
s
i
g
n
e
d
f
o
r
u
s
e
i
n
C
f
h
e
L
o
n
g
-
T
e
r
m
F
i
r
m
(
i
.
T
i
=
r
m
-
ã
r
k
e
l
a
n
i
î
l
r
i
l
K
e
N
e
l
W
ò
-
r
i
r
S
e
r
v
i
c
e
(
N
T
r
m
a
r
k
e
f
.
l
f
e
m
p
l
o
y
s
'E
v
a
l
u
a
t
e
d
"
P
O
R
s
a
n
d
P
O
D
s
a
n
d
t
h
e
i
r
a
s
s
o
c
i
a
t
e
d
P
a
t
h
U
t
i
l
z
a
t
i
o
n
F
a
c
t
o
r
s
(
P
U
F
s
)
t
o
d
e
t
e
r
m
i
n
e
t
h
e
i
m
p
a
c
t
o
f
a
g
i
v
e
n
r
e
q
u
e
s
t
t
o
i
n
t
e
r
n
a
l
,o
w
g
a
t
e
s
(
r
e
f
e
r
t
o
t
h
e
p
o
s
t
e
d
A
T
C
I
m
p
a
c
t
s
o
f
L
o
n
g
-
T
e
r
m
F
i
r
m
R
e
q
u
e
s
t
s
f
o
r
m
o
r
e
I
n
f
o
r
m
a
t
i
o
n
)
.
he
P
U
F
C
a
l
c
u
l
a
t
o
r
ca
n
b
e
u
s
e
d
t
o
c
e
l
c
u
l
a
t
e
t
h
e
i
m
p
a
c
t
of
a
n
O
r
i
g
i
n
a
l
L
T
F
r
e
q
u
e
s
t
a
n
d
t
h
e
I
m
p
a
c
t
o
f
a
N
T
r
e
q
u
e
s
t
t
o
t
h
e
In
t
e
r
n
a
l
f
1
0
w
g
a
t
e
s
nd
c
o
n
t
a
I
n
s
t
h
r
e
e
f
i
e
l
d
s
t
h
a
t
r
e
q
i
.
i
r
e
d
a
t
a
e
n
t
r
y
:
E
v
a
l
u
a
t
e
d
P
O
R
,
E
v
a
l
L
J
a
t
e
d
P
O
D
,
a
n
d
R
e
q
u
e
s
t
e
d
De
m
l
i
n
d
(
M
W
.
)
.
T
h
e
s
e
,
l
i
r
e
t
h
e
w
h
i
t
e
te
x
t
ie
l
d
s
t
o
t
h
e
f
a
r
l
e
f
t
b
e
n
e
a
t
h
t
h
e
t
o
o
l
t
i
t
l
e
,
w
h
i
c
h
a
p
p
e
a
r
s
i
n
r
e
d
.
T
o
f
i
l
l
t
h
e
P
O
R
a
n
d
P
O
D
fi
e
l
d
s
,
h
i
g
h
l
i
g
h
t
t
h
e
w
h
i
t
e
t
e
x
t
f
i
e
,
l
d
t
o
b
e
f
i
l
l
ø
d
a
n
d
he
n
t
h
e
p
u
l
l
-
d
o
w
n
m
e
n
u
a
r
r
w
a
p
p
e
a
r
s
t
o
t
h
e
r
i
g
h
t
,
h
i
g
h
l
l
g
h
t
t
h
e
a
r
r
o
w
a
n
d
c
h
o
o
s
e
a
p
o
i
n
t
f
r
o
m
t
h
e
se
l
e
c
t
i
o
n
.
T
o
f
i
l
l
t
h
e
R
e
q
u
e
s
t
e
d
em
an
d
(
M
W
)
f
i
e
l
d
.
s
i
m
p
l
y
h
i
g
h
l
i
g
h
U
h
e
w
h
i
t
e
t
e
x
t
f
i
e
l
d
a
n
d
ty
p
e
I
n
t
h
e
n
u
m
e
r
i
c
v
a
l
u
e
t
o
be
a
n
a
l
y
z
e
d
.
i
n
m
e
g
a
w
a
t
t
s
.
W
h
e
n
al
l
t
h
r
e
e
w
h
i
t
e
:e
x
t
f
i
e
l
d
s
a
r
e
f
i
l
l
e
d
,
t
h
e
c
a
l
c
u
l
a
t
e
d
i
m
p
a
c
U
o
t
h
e
l
t
t
e
r
n
a
l
f
l
o
w
g
a
t
e
s
(
i
n
M
W
s
)
w
i
l
l
a
p
p
e
a
r
b
e
n
e
a
t
h
t
h
e
"
E
v
a
l
u
a
t
e
d
I
m
p
a
c
t
o
f
R
e
q
u
e
s
t
"
f
i
e
l
d
.
hi
s
c
a
l
c
u
l
a
t
o
r
w
i
l
n
o
t
I
n
d
i
c
a
t
e
w
h
e
t
h
e
r
t
h
e
i
m
p
a
c
t
m
a
y
b
e
c
o
n
s
i
d
e
r
e
d
d
e
m
i
n
i
m
i
s
(r
e
f
e
r
t
o
th
e
p
o
s
t
e
d
A
T
e
M
e
t
h
o
d
o
l
o
g
y
M
a
r
g
i
n
(
A
M
M
l
a
n
d
'e
M
i
n
i
m
i
s
Im
p
a
c
t
D
e
a
d
.
.
B
s
n
d
f
o
r
m
o
r
e
i
n
f
o
r
m
a
t
i
o
n
)
.
NT
r
e
q
u
e
s
t
s
w
i
t
h
t
h
e
F
e
d
e
r
a
l
C
o
l
u
m
b
i
a
R
i
v
e
r
P
o
w
e
r
S
y
s
t
e
m
(
F
C
R
P
S
)
a
s
t
h
e
P
O
R
o
r
P
O
D
m
a
y
e
n
t
e
r
"
F
C
R
P
S
"
i
n
t
h
e
E
v
a
l
u
a
t
e
d
P
O
R
o
r
va
l
u
a
t
e
d
P
O
D
f
i
e
l
d
.
T
h
e
a
s
s
u
m
p
t
i
o
n
s
a
b
o
u
t
t
h
e
F
C
R
P
S
u
s
e
d
b
y
t
h
e
P
U
F
C
a
l
c
u
l
a
t
o
r
m
a
y
'
b
e
d
i
f
f
e
r
e
n
t
t
h
a
n
t
h
e
a
s
s
u
m
p
t
i
o
n
s
a
b
o
u
t
t
h
e
FC
R
P
S
i
n
d
i
c
a
t
e
d
i
n
t
h
e
c
u
s
t
o
m
e
r
'
s
c
o
n
t
r
a
c
t
.
T
h
e
r
e
f
o
r
e
.
t
h
e
a
c
t
u
a
l
i
m
p
a
c
t
s
o
f
a
n
e
q
u
i
v
a
l
e
n
t
N
T
r
e
q
u
e
s
t
m
a
y
b
e
d
i
f
f
e
r
e
n
t
t
h
a
n
t
h
e
i
m
p
a
c
t
s
Ic
u
l
a
t
e
d
b
y
t
h
e
P
U
F
C
a
l
c
u
l
a
t
o
r
.
C
u
s
t
o
m
e
r
s
w
i
l
l
c
o
n
t
i
n
u
e
t
o
b
e
u
n
a
b
l
e
t
o
u
s
e
F
C
R
P
S
a
s
t
h
e
E
v
a
l
u
a
t
e
d
P
O
R
o
r
E
v
a
l
u
a
t
e
d
P
O
D
f
o
r
L
T
F
'r
e
q
u
e
s
t
s
.
IP
l
e
a
s
e
n
o
t
e
t
h
a
t
t
h
i
s
t
o
o
l
c
a
n
n
o
t
b
e
u
s
e
d
t
o
a
c
c
u
r
a
t
e
l
y
d
e
t
e
r
m
i
n
e
t
h
e
c
a
l
c
u
l
a
t
e
d
i
m
p
a
c
t
o
f
S
h
o
r
t
-
T
e
r
m
F
i
r
m
(
S
T
F
)
r
e
q
u
e
s
t
s
.
R
e
f
e
r
t
o
t
h
e
Ip
o
s
t
e
d
S
h
o
r
t
-
T
e
r
m
F
i
r
m
A
T
C
M
e
t
h
o
d
o
l
o
g
y
f
o
r
m
o
r
e
i
n
f
o
r
m
a
t
i
o
n
.
Di
s
c
l
a
i
m
e
r
:
T
h
e
i
n
f
o
r
m
a
t
i
o
n
c
o
n
t
a
i
n
e
d
h
e
r
e
i
n
i
s
c
o
m
p
i
l
e
d
f
o
r
i
n
f
o
r
m
a
t
i
o
n
a
l
p
u
r
p
o
s
e
s
a
n
d
i
s
f
u
r
n
i
s
h
e
d
w
i
t
h
o
u
t
a
s
s
u
r
a
n
c
e
o
f
o
r
ir
e
s
p
o
n
s
i
b
i
l
i
t
y
f
o
r
i
t
s
a
c
c
u
r
a
c
y
.
T
h
e
a
c
t
u
a
l
i
m
p
a
c
t
s
v
a
r
y
d
e
p
e
n
d
i
n
g
u
p
o
n
s
y
s
t
e
m
c
o
n
d
i
t
i
o
n
s
.
T
h
e
i
n
f
o
r
m
a
t
i
o
n
i
s
,
t
h
e
r
e
f
o
r
e
,
s
u
b
j
e
c
t
t
o
c
h
a
n
g
e
it
h
o
u
t
n
o
t
i
c
e
a
n
d
m
a
y
n
o
t
b
e
u
s
e
d
t
o
m
a
k
e
p
r
o
j
e
c
t
i
o
n
s
.
T
h
e
i
n
f
o
r
m
a
t
i
o
n
i
s
a
v
a
i
l
a
b
l
e
t
o
t
h
e
s
i
t
e
v
i
s
i
t
o
r
o
n
t
h
e
c
o
n
d
i
t
i
o
n
t
h
a
t
e
r
r
o
r
s
,
mi
s
s
i
o
n
s
a
n
d
/
o
r
c
h
a
n
g
e
s
s
h
a
l
l
n
o
t
b
e
m
a
d
e
t
h
e
b
a
s
i
s
f
o
r
a
n
y
c
l
a
i
m
,
d
e
m
a
n
d
o
r
c
a
u
s
e
f
o
r
a
c
t
i
o
n
.
D
e
c
i
s
i
o
n
s
b
a
s
e
d
u
p
o
n
t
h
e
i
n
f
o
r
m
a
t
i
o
n
nt
l
i
i
n
e
d
i
n
t
h
e
s
e
p
a
g
e
s
a
r
e
t
h
e
s
o
l
e
r
e
s
p
o
n
s
i
b
i
l
i
t
y
o
f
t
h
e
v
i
s
i
t
o
r
.
Q
u
e
s
t
i
o
n
s
a
n
d
c
o
m
m
e
n
t
s
s
h
o
u
l
d
b
e
d
i
r
e
c
t
e
d
t
o
y
o
u
r
A
c
c
o
u
n
t
E
x
e
c
u
t
i
v
e
o
r
BL
R
e
s
e
r
v
a
t
i
o
n
s
D
e
s
k
a
t
t
b
l
r
e
s
d
e
s
k
SO
U
T
H
OF
AL
L
S
T
O
N
O.
O
M
W
CA
S
C
A
D
E
S
NO
R
T
H
O.
O
M
\
\
MO
N
R
O
E
-
EC
H
O
LA
K
E
O.
O
M
W
NO
R
T
H
OF
JO
H
N
DA
Y
O.
O
M
W
PA
U
L
TO
AL
L
S
T
O
N
-O.
O
M
W
WE
S
T
OF
SL
A
T
T
O.
O
M
W
RA
V
E
R
TO
PA
U
L
O.
O
M
W
WE
S
T
OF
MC
N
A
R
Y
O.
O
M
W
CA
S
C
A
D
E
S
SO
U
T
H
õ.
NO
R
T
H
OF
HA
N
F
O
R
D
O.
O
M
W
L
T
P
U
F
C
a
l
c
u
l
a
t
o
r
Re
v
i
s
e
d
:
S
e
p
t
e
m
b
e
r
2
9
,
2
0
0
9
.B&
Transmission Capacity Application Questionnaire Al lIllCOIi
Ths 8st Js the knwn Infor reirment as of the date of th ler tr this reue Jf adtial fnlan
Is required, Idaho Powe wil promy no ih pro develope of /he addltlollnftlon reuirments.
A Project Name
Gæ\ò~(. CV-cc'L W)V\c\ 'ltÃ~Jr
B. Prject Locaon
3 \M\ \t~ V\~~Ø:t Ot l.'jlA \A ìa L;i=r Ii N ß. 11 w~
c.Projec Developer
Name
Address
City J State I Zip
Phone Number
EamalJ
WpYteh ~l ::Y1\cVV!9~lA LLL
';3P l-yv Xc "-1 ß.A $1A i -k z \ ~
~rL u~. ~ r e,'J~~
\ ~ ; S-~ -=o~S-= 4- sC: ~)3a- it) '"J
G\v, Ç,D Y\(, Q; \bu~.$økh,lc(\Yi"'., Lo~
O. Intercnnecton -Que" rerece numbe (if not knwn. plase contct th host utility
Intercnnecon group)
6 0 ~ ::'l\.
E. Evience of the Project's good standing status in the hot utlity's Intercnnection procs
Ea,Cl htJ smtA'1 (ovy?\LlLcÎ
F. Copy of th Interconnectn fesibilit study and a sttent fr the prec that the proec
has accpted the result of the Intercnnon feslbty study and is contnung the proc
of Inteconnecting and developing the generation proje
G. Maximum Capacity (MW) J L M W
Pap 1 or3
Attchment No. 5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 9 of 22
H. Beinning day and time of ener deveries
Da (irl- 1.1 , /1. 0 l i.TIe tlt;; 00 'Ð:icìfxc. h 'i
i. Ending day and time of energy deliveri
Da (mm/ddL- 'L'! I 1.t' 3 '2-Time ((o: D Q lh.f ì 4 r -\1 '"
J. VAR capabilit (both leading and lagging) of all generators See ¡2;Ch: ~ it .13
K. Identification of the control area(s) from which the energy wil origInate
:Jda.\ro 'Rwec
L. List any periods of restricted operations throgho the year
M. Maintenanc schedule'-
N. Minimum loading levl of each generation unit o,c.h v L ~ . \ 12\ I ')\ ( 'j n'dJ" b V'\ ~-,) , S"l',,l';X,C
O. Normal operating level of each generation unit. Soc -L lix 2. LI
P. Any must-4n generion unit designations reuire for system reialit Of contctal rean
NC)~ l: O\lr kMQ&l(ol'~
PageZof3
Attachment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 10 of 22
Q. Approximate variab generation oost ($IMWh) No -th wI b& es eM pt ir. po
"ur_ par agHm tha th ptet may be eI fo.
R. ff the generation reource is to be locate in the Idaho Powr Balancing Authorty Ara and If
only a portion of the resur outut Is to be designated as a Netwrk Resurc, then explan
arrngements governing sale and delivery of addltonal output to third partes.
S. If the project is not dire Intenecd to th Idaho Power trnsmission system, provie
th trnsmission provider(s) name, phyl Pont of Recpt, Point of Deivery and th
trnsission rervtion number fo all of the trnsmission prvider reuire to deliver th
projecs energy to Idaho Power.
Tninsll Pides) Nae B 1: I\
Poin afRecpt l3nNt:tA W('Movtr 1f.t1J",,$.!61-.
Point afOeliV4 J. in iøc\L&' $. y.\:~
Tren Re_lion Numbes) .At e. - 7 Y: 'j i Z, 4 4'
T. If the projec Is djr Intecone to th Idaho Power trnsmission sysem, proide the
Point of Receipt, physica loction and voltage.
Paint of Rø
Phycal Loti
Vcitøe
U. Is the project committ to execute a purce por agreement wih Idaho Powr upon a
favorable reoluti of the idened Intercnecton and trnsmission costs?
Vee ê( No 0
V. Is any poron of the maxmum capaci Ident for this project commited to any other part
Yes 0 NO~
Signatur oate '2 ,. ( 3." '2 i ()
Pa3of3
Attachment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 11 of22
exhibit A: Answer to Questio J
VAR capability (both leadIng and laglng) of all générators)
i 0,0..a 0
.0,1
0,5 ----r-- .
.0 (11 02 03-04 05 06 07 08 09 1
O,48pu
o
.. Onr..xcledUlnøCapi:e
..urier~lalIInuêlve
0;4
0.3
0,2
0.1
...,2
-0.3
-0,4
.0.5
p (pu)
0,48 pu
Attachment No. 5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 12 of 22
Exhibit B-Documentation of Transmission Service Request
This customer wil be part of the 2010 Network Open season. No notification to opt out
submitted In comments section of TSRs received
3.5 Recipt of TSR Deposit
3.5.1 The TSR Deposit must be deposited with BPA, or into an Escrow Account, by Close of
Business 10 Business Days after the TSR status is changed to RECEIVED in OASIS or the TSR
sttus wil be changed to DECLINED.
If the customer wishes to pay the TSR Deposit via Escrow, please contact the bank
directy. To allow for timely procssing and to ensure the TSR deposit deadline of
7/15/10 is met, BPA requires the Escrow Agrement, with customer signature,
from the bank within 5 business days aftr the Recived date of 6/30/10 (by
7/8/10).
4 Non-Refundable Processing Fee
4.1 In additn to a TSR Deposit when making a L TF PT or NT TSR, the Customer must
submit a separate $2500 non-refundable Processing Fee to BPA.
4.3.1 BPA Transmission Services must receive the TSR Processing Fee by Close of Business 10
Busines Days after the TSR Is RECEID on OASiS or the TSR wil be DECLINED and
receive no further consideration.
4.4.1 The TSR Processing Fee must be paid directly to BPA Transmission Services and cannot
be placed into an Escrow Account
Transmission Service Reauass D1aced in RECEIVED Status
Non-
Refndable
Rec'd TSR Deposit Processing 10Day
AREF Related Ref Name Dite Rate MW Due Fee Due DueDite
Wasatch Wind
74412433 Development 6/30/10 PTP 1.298 30 $38940.00 $2500 7/15/10
Wasatch Wind
74412442 Development 6/30/10 PTP 1.298 21 $27258.00 $2500 7/15/10
$0.00 $0
$0.00 $0
Subtotal:$66198.00 $5,000 7/15/10
Total
Due:$71198
A New Long Ter Reservation (TSR 74412433 ) has been RECENED for Wasatch Wind
Development LLC
Click here to See Tramision Request in CBSA
A New Long Term Reservation (TSR 74412442) has been RECEIVED for Wasatch Wind
Attachment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 13 of 22
"t
)
:
(
)
~
Q)
=
m
,
.
CC
"
'
(
I
I
l
CD
~
C
D
g
.
..
:
:
Z
3
~)
:
°
C
D
o
3
1
!I
:
:
-"
0
.
_
'
-
"'
I
l
"
t
z
"'
:
:
.
(
)
0
..
I
.
__
m
(
J
"t
~
()
:
£
..
fi
e
P
U
F
C
i
:
l
c
u
l
a
t
o
r
i
s
a
t
o
o
l
d
e
s
i
g
n
e
d
f
o
r
u
s
e
i
n
t
h
e
L
o
n
g
-
T
e
r
m
F
i
r
m
(
L
T
F
)
m
a
r
k
e
t
a
n
-
d
¡
n
T
n
e
R
e
l
.
o
-
r
1
S
e
r
v
i
c
e
(
N
T
)
m
a
m
e
:
t
-
n
e
m
p
l
o
y
s
Ev
a
l
u
a
t
e
d
"
P
O
R
s
a
n
d
P
O
D
s
a
n
d
t
h
e
i
r
a
s
s
o
c
i
a
t
e
d
P
a
t
h
U
t
i
l
z
a
t
i
o
n
F
a
c
t
o
r
s
(
P
U
F
s
)
t
o
d
e
t
e
r
m
i
n
e
t
h
e
i
m
p
a
c
t
o
f
a
g
i
v
e
n
r
e
q
u
e
s
t
t
o
i
n
t
e
r
n
a
l
ow
g
a
t
e
s
(
r
e
f
e
r
t
o
t
h
e
p
o
s
t
e
d
A
T
C
I
m
p
a
c
t
s
o
f
L
o
n
g
-
T
e
r
m
F
i
r
m
R
e
q
u
e
s
t
s
f
o
r
m
o
r
e
in
f
o
r
m
a
t
i
o
n
)
.
he
P
U
F
C
a
l
c
u
l
a
t
o
r
c
a
n
b
e
u
s
e
d
t
o
c
a
l
c
u
l
a
t
e
t
h
e
i
m
p
a
c
t
o
f
a
n
O
r
i
g
i
n
a
l
L
T
F
r
e
q
u
e
s
t
a
n
d
t
h
e
i
m
p
a
c
t
o
f
a
N
T
r
e
q
u
e
s
t
t
o
t
h
e
I
n
t
e
r
n
a
l
f
l
o
w
g
a
t
e
s
nd
c
o
n
t
a
i
n
s
t
h
r
e
e
f
i
e
l
d
s
t
h
a
t
r
e
q
u
i
r
e
d
a
t
a
e
n
t
r
y
:
E
v
a
l
u
a
t
e
d
P
O
R
,
E
v
a
l
u
a
t
e
d
P
O
D
,
a
n
d
R
e
q
u
e
s
t
e
d
D
e
m
a
n
d
(
M
W
)
.
T
h
e
s
e
a
r
e
t
h
e
w
h
i
t
e
t
e
x
t
Id
s
t
o
t
h
e
f
a
r
l
e
f
t
b
e
n
e
a
t
h
t
h
e
t
o
o
l
t
i
t
l
e
,
w
h
i
c
h
a
p
p
e
a
r
s
i
n
r
e
d
.
T
o
f
i
l
t
h
e
P
O
R
a
n
d
P
O
D
f
i
e
l
d
s
,
h
i
g
h
l
i
g
h
t
t
h
e
w
h
i
t
e
t
e
x
t
f
i
e
l
d
t
o
b
e
f
i
l
l
e
d
a
n
d
he
n
t
h
e
p
u
l
l
-
d
o
w
n
m
e
n
u
a
r
r
o
w
a
p
p
e
a
r
s
t
o
t
h
e
r
i
g
h
t
,
h
i
g
h
l
i
g
h
t
t
h
e
a
r
r
o
w
a
n
d
c
h
o
o
s
e
a
p
o
i
n
t
f
r
o
m
t
h
e
s
e
l
e
c
t
i
o
n
.
T
o
f
i
l
t
h
e
R
e
q
u
e
s
t
e
d
De
m
a
n
d
(
M
W
)
f
í
e
l
d
,
s
i
m
p
l
y
h
i
g
h
l
i
g
h
t
t
h
e
w
h
i
t
e
t
e
x
t
f
i
e
l
d
a
n
d
t
y
p
e
i
n
t
h
e
n
u
m
e
r
i
c
v
a
l
u
e
t
o
b
e
a
n
a
l
y
z
e
d
,
i
n
m
e
g
a
w
a
t
t
s
.
W
h
e
n
a
l
l
t
h
r
e
e
w
h
i
t
e
:e
x
t
f
i
e
l
d
s
a
r
e
f
i
l
l
e
d
,
t
h
e
c
a
l
c
u
l
a
t
e
d
i
m
p
a
c
t
t
o
t
h
e
i
n
t
e
r
n
a
l
f
l
o
w
g
a
t
e
s
(
i
n
M
W
s
)
w
i
l
l
a
p
p
e
a
r
b
e
n
e
a
t
h
t
h
e
"
E
v
a
l
u
a
t
e
d
I
m
p
a
c
t
o
f
R
e
q
u
e
s
t
"
f
i
e
l
d
.
hi
s
c
a
l
c
u
l
a
t
o
r
w
H
l
n
o
t
i
n
d
i
c
a
t
e
w
h
e
t
h
e
r
t
h
e
I
m
p
a
c
t
m
a
y
b
e
c
o
n
s
i
d
e
r
e
d
d
e
m
i
n
i
m
i
s
(
r
e
f
e
r
t
o
t
h
e
p
o
s
t
e
d
A
T
C
M
e
t
h
o
d
o
l
o
g
y
M
a
r
g
i
n
(
A
M
M
)
a
n
d
in
i
m
i
s
I
m
p
a
c
t
D
e
a
d
-
B
a
n
d
f
o
r
m
o
r
e
i
n
f
o
r
m
a
t
i
o
n
)
,
NT
r
e
q
u
e
s
t
s
w
i
t
h
t
h
e
F
e
d
e
r
a
l
C
o
l
u
m
b
i
a
R
i
v
e
r
P
o
w
e
r
S
y
s
t
e
m
(
F
C
R
P
S
)
a
s
t
h
e
p
a
R
o
r
P
O
D
m
a
y
e
n
t
e
r
"
F
C
R
P
S
"
i
n
t
h
e
E
v
a
l
u
a
t
e
d
p
a
R
o
r
Ev
a
l
u
a
t
e
d
P
O
D
f
i
e
l
d
.
T
h
e
a
s
s
u
m
p
t
i
o
n
s
a
b
o
u
t
t
h
e
F
C
R
P
S
u
s
e
d
b
y
t
h
e
P
U
F
C
a
l
c
u
l
a
t
o
r
m
a
y
b
e
d
i
f
f
e
r
e
n
t
t
h
a
n
t
h
e
a
s
s
u
m
p
t
i
o
n
s
a
b
o
u
t
t
h
e
FC
R
P
S
i
n
d
i
c
a
t
e
d
i
n
t
h
e
c
u
s
t
o
m
e
r
'
s
c
o
n
t
r
a
c
t
.
T
h
e
r
e
f
o
r
e
,
t
h
e
a
c
t
u
a
l
i
m
p
a
c
t
s
o
f
a
n
e
q
u
i
v
a
l
e
n
t
N
T
r
e
q
u
e
s
t
m
a
y
b
e
d
i
f
f
e
r
e
n
t
t
h
a
n
t
h
e
i
m
p
a
c
t
s
it
e
u
l
a
t
e
d
b
y
t
h
e
P
U
F
C
a
l
c
u
l
a
t
o
r
.
C
u
s
t
o
m
e
r
s
w
i
l
l
c
o
n
t
i
n
u
e
t
o
b
e
u
n
a
b
l
e
t
o
u
s
e
F
C
R
P
S
a
s
t
h
e
E
v
a
l
u
a
t
e
d
P
O
R
o
r
E
v
a
l
u
a
t
e
d
P
O
D
f
o
r
L
T
F
¡r
e
q
u
e
s
t
s
.
¡l
p
l
e
a
S
e
n
o
t
e
t
h
a
t
t
h
i
s
t
o
o
l
c
a
n
n
o
t
b
e
u
s
e
d
t
o
a
c
c
u
r
a
t
e
l
y
d
e
t
e
r
m
i
n
e
t
h
e
c
a
l
c
u
l
a
t
e
d
i
m
p
a
c
t
o
f
S
h
o
r
t
-
T
e
r
m
F
i
r
m
(
S
T
F
)
r
e
q
u
e
s
t
s
.
R
e
f
e
r
t
o
t
h
e
po
s
t
e
d
S
h
o
r
t
-
T
e
r
m
F
i
r
m
A
T
C
M
e
t
h
o
d
o
l
o
g
y
f
o
r
m
o
r
e
i
n
f
o
r
m
a
t
i
o
n
.
Di
s
c
l
a
i
m
e
r
:
T
h
e
i
n
f
o
r
m
a
t
i
o
n
c
o
n
t
a
i
n
e
d
h
e
r
e
i
n
i
s
c
o
m
p
i
l
e
d
f
o
r
i
n
f
o
r
m
a
t
i
o
n
a
l
p
u
r
p
o
s
e
s
a
n
d
i
s
f
u
r
n
i
s
h
e
d
w
i
t
h
o
u
t
a
s
s
u
r
a
n
c
e
o
f
o
r
'e
s
p
o
n
s
i
b
i
l
t
y
f
o
r
i
t
s
a
c
c
u
r
a
c
y
.
T
h
e
a
c
t
u
a
l
i
m
p
a
c
t
s
v
a
r
y
d
e
p
e
n
d
i
n
g
u
p
o
n
s
y
s
t
e
m
c
o
n
d
i
t
i
o
n
s
.
T
h
e
i
n
f
o
r
m
a
t
i
o
n
i
s
,
t
h
e
r
e
f
o
r
e
,
s
u
b
j
e
c
t
t
o
c
h
a
n
g
e
it
h
o
u
t
n
o
t
i
c
e
a
n
d
m
a
y
n
o
t
b
e
u
s
e
d
t
o
m
a
k
e
p
r
o
j
e
c
t
i
o
n
s
.
T
h
e
i
n
f
o
r
m
a
t
i
o
n
i
s
a
v
a
i
l
a
b
l
e
t
o
t
h
e
s
i
t
e
v
i
s
i
t
o
r
o
n
t
h
e
c
o
n
d
i
t
i
o
n
t
h
a
t
e
r
r
o
r
s
,
mi
s
s
i
o
n
s
a
n
d
/
o
r
c
h
a
n
g
e
s
s
h
a
l
l
n
o
t
b
e
m
a
d
e
t
h
e
b
a
s
i
s
f
o
r
a
n
y
c
l
a
i
m
,
d
e
m
a
n
d
o
r
c
a
u
s
e
f
o
r
a
c
t
i
o
n
.
D
e
c
i
s
i
o
n
s
b
a
s
e
d
u
p
o
n
t
h
e
i
n
f
o
r
m
a
t
i
o
n
.n
t
a
i
n
e
d
i
n
t
h
e
s
e
p
a
g
e
s
ar
e
t
h
e
s
o
l
e
r
e
s
p
o
n
s
i
b
i
l
i
t
y
o
f
t
h
e
v
i
s
i
t
o
r
.
Q
u
e
s
t
i
o
n
s
a
n
d
c
o
m
m
e
n
t
s
s
h
o
u
l
d
b
e
d
i
r
e
c
t
e
d
t
o
y
o
u
r
A
c
c
o
u
n
t
E
x
e
c
u
t
i
v
e
o
r
BL
R
e
s
e
r
v
a
t
i
o
n
s
,
D
e
s
k
at
t
b
l
r
e
s
d
e
s
k
l
A
b
P
a
.
a
o
v
.
SO
U
T
H
OF
AL
L
S
T
O
N
O.
O
M
W
CA
S
C
A
D
E
S
NO
R
T
H
O.
O
M
W
NO
R
T
H
OF
HA
N
F
O
R
D
O.
O
M
W
PA
U
L
TO
AL
L
S
T
O
N
O.
O
M
W
CA
S
C
A
D
E
S
SO
U
T
H
'õ
MO
N
R
O
E
-
EC
H
O
LA
K
E
O.
O
M
W
NO
R
T
H
OF
JO
H
N
DA
Y
õ.
RA
V
E
R
TO
PA
U
L-O.
O
M
W
WE
S
T
OF
MC
N
A
R
Y
O.
O
M
W
WE
S
T
OF
SL
A
T
T
O.
O
M
W
Qo =öom~~
L
T
P
U
F
C
a
l
c
u
l
a
t
o
r
Re
v
i
s
e
d
:
S
e
p
t
e
m
b
e
r
2
9
,
2
0
0
9
.chin, Randy
From:
Sent:
To:
Subject:
Allphin, Randy
Wednesday, July 21,20102:46 PM
'Christine Mikell'
RE: 10 MW PPA--update
Christine, no I have not yet been able to submit the TSR. Been getting buy in from various people, looks like I wil
probably be filng the TSR sometime next week.
I am not sure what process you are referencing in your e-mail.
This is transmission capacity we are asking for not interconnection. The way it wil work we file the Transmission service
request (TSR) if there is transmission capacity available, we will get a response back saying so and any associated costs.
If there is not transmission capacity available we wil get a response back saying so and if we want to move forward they
wil begin a transmission study that requires a $10,000 deposit to start. Then once this study is started, I assume they
have various meetings etc to work in the right direction. As a PURPA project you wil be responsible for all of the costs
($10,000 deposit etc).
So at least to start with, once I get approval to file the TSR, it is paperwork we have to fil out with your information and
then wait for the transmission groups response.
Hope this helps
Randy
From: Christne Mikell rmallt:chlstlnewasalnQ,comJ
sent: Wednesday, July 21, 2010 2:32 PM
To: Allphin, Randy
Cc: Sam Uchenstein
SUbject: RE: 10 MW PPA--update
Hi Randy,
i just wanted to check to see if you had gotten the approval to make the TSR for our Grouse Creek projects? If memory
serves, once you make that request, 10 days from then we must have a scoping meeting? If this correct?
We have started some expensive eagle studies and we would hate to get too far into it and find out there isn't any
transmission available!
Thanks!
Christine
From: Allphin, Randy (majlt;RAlphlnt§ldahower.coJ
Sent: Tuesay, June 29, 2010 6:48 AM
To: Christine Mikell
Subject: RE: 10 MW PPA
My routine process is to not develop a draft agreement for a specific project until the transmission and interconnection
is pinned down - however, i am currently working up a draft agreement for another project, I am thinking I should be
able to duplicate that draft contract for your project. It wil be a week or two before i have It ready to go.
Attachment No. 5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 15 of 22
1
Randy
From: Christine Mikell únilt;chrlneilwasaIri,coml
sent: Monday, June 28, 2010 9:51 PM
To: Allphin, Randy
Subject: RE: 10 MW PPA
Can we get a copy or do we need to wiat?
From: Allphin, Randy (ma!t:BAJI:iblnillQhor.col
sent: Monday, June 28, 2010 7:48 PM
To: Christine Mikell
Subject: BE: 10 MW PPA
No
From: Christine Mikell (mai!t:chrineOwastchwind.çoml
Sent: Monday, June 28, 2010 5:05 PM
To: Allphin, Randy
Subjec: 10 MW PPA
Hey Randy,
Is the PPA contract online for the 10 MW QF?
Thanks!
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air, clean earth.
ww.wasatchwind.com
Wasatch Wind
This mesage and any aUachmenls conlain information thai is propretary, conßdenlial and privileged They are intended for the private and exclusive use oIlhe addressee and are covered by the
Elecronic Communicahons Pnvacy Acl, 18 USC §§ 2510-2521, Unless you are the addressee (or authonzed 10 receive for the addressee) you may nol use, copy, print or disclose to anyone this
message or any information contained in the message and any attachments, If you have received this comunicalion in eror, please advise the sender by reply and delele this mesage
2 Attachment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 16 of 22
BlI----
This ~is!iiin ~ ciotiiin loftiiìl' that Î!lîiivile, èOtidentil\laiÖI~enpt ih di¡1ol\l undr ap~ Iàw. If)'u ar noll iiiêl Î'lp¡ei~YO!l ii ~
noifed thllY dIscloure ~fI diSlrll:io, anise oflbe ioÌÌtii: coiiioed hein (Including iiyreli; ~n)li STRICTY P'R.OHlBJT.lf~~ Ibis
tlllon In em.l'leimiiidy i;olllii the scder and deoy the I'tcrii in Its entiry. wl: in clecroíe or hà ooy Ibt. Tl yo
3 Attchment No. 5
Case Nos. IPC-E-1Q-61 & IPC-E-10-62
Allphin Affdavit. IPC
Page 17 of 22
~hin,Randy
From:
Sent:
To:
Cc:
Subject:
Christine Mikell rchristine~wasatchwind.comJ
Wednesday, July 21, 2010 2:32 PM
Allphin, Randy
Sam Lichenstein
RE: 10 MW PPA--update
Hi Randy,
I just wanted to check to see if you had gotten the approval to make the TSR for our Grouse Creek projects? If memory
serves, once you make that request, 10 days from then we must have a scoping meeting? If this correct?
We have started some expensive eagle studies and we would hate to get too far into it and find out there isn't any
transmission available!
Thanks!
Christine
From: Allphin, Randy rooålltjRAllphlncaldêlwer.com)
Sent: Tuesday, June 29, 2010 6:48 AM
To: Christine Mikell
Subjec: RE: 10 MW PPA
My routine process is to not develop a draft agreement for a specific project unti the transmission and interconnection
is pinned down - however, J am currently working up a draft agreement for another project, I am thinking i should be
able to duplicate that draft contract for your project. It wil be a week or two before I have it ready to go.
Randy
From: Christine Mikell rmailt:çhistneßWimhwlnd.aJ)
Sent: Monday, June 28, 2010 9:51 PM
To: Allphin, Randy
Subject: RE: 10 MW PPA
Can we get a copy or do we need to wiat?
From: Allphin, Randy rmallt:BAlphlntAklhQr.c:m)
Sent: Monday, June 28, 2010 7:48 PM
To: Christine Mikell
Subject: RE: 10 MW PPA
No
From: Christine Mikell (malfto:did~tcnd.aJ)
Sent: Monday, June 28, 2010 5:05 PM
To: Allphin, Randy
Subject: 10 MW PPA
Hey Randy,
1 Attachment No.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 18 of 22
Is the PPA contract online for the 10 MW QF?
Thanksl
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy. clean air. clean earlh.
ww.wasatchwind.com
Wasatch Wind
This message and any attachmets cotain information that is propnetary, confidential and pnvileged They are intended fOf the pnvale and exclusive use of the addressee and are covered by the
Electronic Communications Pnvacy Act, 18 U,S.C §§ 2510-2521 Unless you are the addresee (or authonzed to receive fer the addressee) you may not use. copy, print or disclose to anyone this
message or any information contaIned in the message and any attachments, If you have received this communication in error, please advise the sender by reply and delete this message
øM1.
This transisson may contain information that is privileged, confidential anor exempt from disclosue unde applicable law. If you are not the intended reipient, you are herby
notified tht any disclosur, coping, distributon, or use otthe information containe herein (including any reliance thereon) is STRICTLY PROHffIT. If you received th
transmission in err, please immediately contact the seder and desroy the material in its entirey, whether in electrnic or hard copy format. Thank you,
2 Attachment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 19 of 22
~hinlRandy
From:
Sent:
To:
Cc:
Subject:
Christine Mikell (christine~wasatchwind.comi
Wednesday, July 21,20104:33 PM'
Allphin, Randy
Sam Lichenstein
RE: 10 MW PPA--update
Hi Randy,
Great news that you wil be able to file something maybe next week. Based on your response below, is it 30 days from
when you submit the TSR before you get your answer regarding transmission capacity and whether you need a
feasibility study?
Thanks,
Christine
From: Allphin, Randy rmallt:RAllphio~iøbopor¡CQmJ
sent: Wednesday, July 21, 2010 2:46 PM
To: Christine Mikell
Subject: RE: 10 MW PPA--update
Christine, no I have not yet been able to submit the TSR. Been getting buy in from various people, looks like i wil
probably be filng the TSR sometime next week.
I am not sure what process you are referencing in your e-mail.
This is transmission capacity we are asking for not interconnection. The way it wil work we file the Transmission service
request (TSR) ifthere is transmission capacity available, we will get a response back saying so and any associated costs.
If there is not transmission capacity available we wil get a response back saying so and if we want to move forward they
wil begin a transmission study that requires a $10,000 deposit to start. Then once this study is started, I assume they
have various meetings etc to work in the right direction. As a PURPA project you wil be responsible for all of the costs
($10,000 deposit etc).
50 at least to start with, once i get approval to file the T5R, it is paperwork we have to fill out with your information and
then wait for the transmission groups response.
Hope this helps
Randy
From: Christine Mikell (mallt;ctr!neOwaøtc.CQml
sent: Wednesday, July 21, 2010 2:32 PM
To: Allphin, Randy
cc: Sam Lichenstein
Subject: RE: 10 MW PPA--update
Hi Randy,
i just wanted to check to see if you had gotten the approval to make the TSR for our Grouse Creek projects? If memory
serves, once you make that request, 10 days from then we must have a scoping meeting? 1ft his correct?
1 Attachment No.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 20 of 22
We have started some expensive eagle studies and we would hate to get too far into it and find out there Isn't any
transmission available!
Thanks!
Christine
From: Allphin, Randy (mallt:RAlphln(9!dhagower,comJ
sent: Tuesday, June 29, 2010 6:48 AM
To: Christine Mikell
Subject: RE: 10 MW PPA
My routine process is to not develop a draft agreement for a specific project until the transmission and interconnection
is pinned down - however, I am currently working up a draft agreement for another project, i am thinking i should be
able to duplicate that draft contract for your project. It wil be a week or two before I have it ready to go.
Randy
From: Christne Mikell (mailto;çbtbtinei,asteind,col
Sent: Monday, June 28, 2010 9:51 PM
To: Allphin, Randy
Subject: RE: 10 MW PPA
Can we get a copy or do we need to wiat?
From: Allphin, Randy (mllt:RAløhlntmldahopoerml
sent: Monday, June 28, 2010 7:48 PM
To: Christine Mikell
Subject: RE: 10 MW PPA
No
From: Christine Mikell rmallto:ChrlstneC9asab:bwlnd.coJ
sent: Monday, June 28, 2010 5:05 PM
To: Allphin, Randy
Subject: 10 MW PPA
Hey Randy,
Is the PPA contract online for the 10 MW QF?
Thanksl
Christine Watson Mikell
Senior Project Development Manager
Direct: 435-503-8814
Mobile: 801-455-1045
clean energy, clean air. clean earth,
ww.wasatchwind.com
Wasatch Wind
2 Attchment NO.5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 21 of22
This ~!liilillllY "lllcii_ WItll inI"l/Uøn Ihai " prOPNOlll. Ç(lidlÍii and pnWt Thoy me intol' lor ¡he iinvi:ll an 8KWl_of th ad_ ii m~~!l~ tl~
BoorooisCiiiliow,;11O l'\/~yh:I, 18 U.S C §§ 2510251 Unl vo _ tllilldiiiiiSOO lot ouLe io'ecw lo th1lns) ýOU mani,\4, coy, ptllöl diili~ llii~ Qt lly ¡llölllllliìÍ ~n!li".d .n lhu mllIUand &taltlmonts H VO have ",co,vi iÌls OOM""catr II ""Ot. ii OOIl" tl SOOdll by ,e¡:y ii dtl..ll lls ll~.
This ~Sl¡il' mI'co11l ìnrorllioo ili 1$ prvileg, i:iifideiiafaior lIeitm d"1li-un,~ Iá ir)'uvel'llin reiple, yw-li
iilili ilti anydise~ i:ng, rIlslbli or U$ ¡ifll ìnrl'l'n¡liii COlllaed ller (im:lìig liy ~~) is STRICT Y PIlHlSlTD. If)1~¥elliinll Ílllr. pl_ Îlltl,y OOtaclllsadllW desy lImaerl inlll enlÍrey. wlillllÍl elOl!ll,or lleo Ilnnlil. TI yo.
3 Attachment No. 5
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 22 of 22
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO.6
~phinr Randy
From:
Sent:
To:
Subjec:
l\lphin. ,Randy
Monday, August 02, 20103:02 PM
'Christine Mikell'
21 or 30 MW?
Christine, I am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications in your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
1 Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of27
~hin,Randy
From:
Sent:
To:
Subject:
Allphin, Randy
Mònday, August 02, 2010 3:21 PM
'Christine Mikell'
RE:210r30MW?
Christine -I guess I read things wrong - this information is now suggesting is two separate projects (20 MW and a 31
MW) for a total of 51 MW?
You are suggesting they are two separate 10 average MW projects. In prior information you have suggested a capacity
factor over 40%, if this is the case the 30 MW would not qualify for a 10 MW average project and even the 21 MW
project would be questionable, based on the previous data you provided.
Do the projects qualify as separate facilties? Individual QF certificates from FERC? At least physically a mile apart?
Unfortunately this size and number of projects continues to cause delays and complications in the transmission capacity
request-
If they are truly separate projects - which one do you want me to file for first? (there may be room for one but not the
other)
If we get approval for one and/or both as separate projects, but then find out they must be combined into one project
we will have to re file for transmission as the two filings cannot be combined into one at a later time.
To do this right the first time, we need to determine if they are separate projects. Even if they are separate projects do
they qualify for the 10 average MW contract?
Based on the information you have provided, it appears they are the same project (same project location, same
interconnection, same BPA capacity reservation etc). If this is the case, then I need to file one 51 MW transmission
request and we wil need to rerun the pricing models to determine the energy pricing.
Randy
From: Allphin, Randy
sent: Monday, August 02,20103:02 PM
To: 'Chnstine Mikell'
Subject: 21 or 30 MW ?
Christine, I am making some progress on the transmission requests, however the first questions i encountered was if the
project would be 21 or 30 MW. As you included both applications in your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
1 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of27
.ehin, Randy
From:
Sent:
To:
Subject:
Allphin, Randy
Monday, August 02, 2010 3:34 PM
'Christine Mikell'
RE: 21 or 30 MW ?
Based on the previous production data you provided, the 31 MW project does not qualify for the 10 average MW
contract, and the 20 MW project is questionable?
Was the previously provided production data accurate - if so we need to rerun pricing models, the price wil most likely
be similar to the previous pricing I provided are the projects viable at those prices?
If the previously provided data was not accurate, the previous provided pricing may not be accurate.
If they are viable, which transmission request should 1 submit first?
Randy
From: Christine Mikell (mallt:chnsti:aswind.col
sent: Monday, August 02, 2010 3:22 PM
To: Allphin, Randy
Subjec: Re: 21 or 30 MW ?
Yes, with a mile separation.
From: Allphin, Randy ':RAllphin(gidahopower.com~
To: Christine Mikell
Sent: Mon Aug 02 17:21:20 2010
Subject: RE: 21 or 30 MW ?
Christine -I guess I read things wrong - this information is now suggesting is two separate projects (20 MW and a 31
MW) for a total of 51 MW?
You are suggesting they are two separate 10 average MW projects. In prior information you have suggested a capacity
factor over 40%, if this is the case the 30 MW would not qualify for a 10 MW average project and even the 21 MW
project would be questionable, based on the previous data you provided.
Do the projects qualify as separate facilties? Individual QF certificates from FERC? At least physically a mile apart?
Unfortunately this size and number of projects continues to cause delays and complications in the transmission capacity
request-
If they are truly separate projects - which one do you want me to file for first? (there may be room for one but not the
other)
If we get approval for one and/or both as separate projects, but then find out they must be combined into one project
we wil have to re file for transmission as the two filngs cannot be combined into one at a later time.
1 Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 3 of 27
To do this right the first time, we need to determine if they are separate projects. Even if they are separate projects do
they qualify for the 10 average MW contract?
Based on the information you have provided, it appears they are the same project (same project location, same
interconnection, same BPA capacity reservation etc). If this is the case, then I need to file one 51 MW transmission
request and we wil need to rerun the pricing models to determine the energy pricing.
Randy
From: Allphin, Randy
sent: Monday, August 02, 2010 3:02 PM
To: 'Christine Mikell'
Subject: 21 or 30 MW ?
Christine, I am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications in your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
This trisson may contain infuation tha is privileged, confidential and/or exemt from disclosre unde applicable law. If you ar not the intended recipient. yo ar herby
notified that any disclosure, copyin disibution, or use oftbc infonnation contai herei (inluding any relince thn) is STRIClL Y PROHIBITED. If you reeived t1is
trission in er, plea immediately cotact t1e sende an destroy t1e mateal in its entirety. wheter in electric or hard cop formL. Th you.
2 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 4 of 27
~hin, Randy
From:
Sent:
To:
Subject:
Christine Mikell (christine~wasatchwind.coml
Monday, August 02, 2010 3:22 PM
Allphin, Randy
Re: 21 or 30 MW ?
Yes. with a mile separation.
From: Allphin, Randy ocBAnphln!tlQllfitIÇQ~
To: Chritine Mikell
sent: Mon Aug 0217:21:202010
Subjec: RE: 21 or 30 MW ?
Christine - I guess I read things wrong - this information is now suggesting is two separate projects (20 MW and a 31
MW) for a total of 51 MW?
You are suggesting they are two separate 10 average MW projects. In prior information you have suggested a capacity
factor over 40%, if this is the case the 30 MW would not qualify for a 10 MW average project and even the 21 MW
project would be questionable, based on the previous data you provided.
Do the projects qualify as separate facilities? Individual QF certificates from FERC? At least physically a mile apart?
Unfortunately this size and number of projects continues to cause delays and complications in the transmission capacity
request-
If they are truly separate projects - which one do you want me to file for first? (there may be room for one but not the
other)
If we get approval for one and/or both as separate projects, but then find out they must be combined into one project
we wil have to re file for transmission as the two filngs cannot be combined into one at a later time.
To do this right the first time, we need to determine if they are separate projects. Even if they are separate projects do
they qualify for the 10 average MW contract?
Based on the information you have provided, it appears they are the same project (same project location, same
interconnection, same BPA capacity reservation etc). if this is the case, then I need to file one 51 MW transmission
request and we wil need to rerun the pricing models to determine the energy pricing.
Randy
From: Allphin, Randy
Sent: Monday, August 02, 2010 3:02 PM
To: 'Christine Mikell'
Subject: 21 or 30 MW?
1 Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 5 of 27
Christine, I am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications in your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
This tramission may cotain inforation that is privileged. confdential andfor exempt fr disclosure under applicable law. If you ar not the intended reipient, you ar herby
notified that any discloure. copng distnbuon, or use of the information containe hern (including any reliace theren) is STRICTLY PROHIBIT. If yOu reeive ths
transmssion in er, please imediately conta the sender and destry the materal in its entire. whether in electronic or har copy format. Thk yOu.
2 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 6 of 27
~hin, Randy
From:
Sent:
To:
Subject:
Christine Mikell (christinetgwasatchwind .com)
Monday, August 02, 2010 3:19 PM
Allphin, Randy
Re: 21 or 30 MW ?
Hi Randy,
One OF is for 30 MW's and the second OF is for 21 MW's. Does that help?
Thanks.
From: Allphin, Randy ..RAllphrnß!ahoplcorn~
To: Christine Mikell
Sent: Mon Aug 02 17:01:53 2010
Subject: 21 or 30 MW ?
Christine, i am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications in your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
This transmission may contain information that is privileged, confiential and/or exempt frm dilosur under applicable law. If you ar not the intended reipient, you ar herby
notified that any disclosure copying, distribution, or use of the infonation conained herein (including any reliance theren) is STRICTLY PROHIBITED. If you reeived this
transmission in err. please immedtely contact the sende and destroy the material in its entiret, whether in electronic or ha copy fonnal. Thank you.
i Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 7 of27
~hin! Randy
From:
Sent:
To:
Subject:
Christine Mikell (christine(§satchwind.com)
Monday, August 02,20104:16 PM
Allphin, Randy
Re: 21 or 30 MW ?
We calculated it, the higher winds are to the north with fewer turbines and lower winds are to the south. Do you need
something from us to make this case?
Thanks.
From: Allphin, Randy ..RAllphin(âidahopower.com~
To: Christine Mikell
Sent:Mon Aug 02 17:33:58 2010
Subject: RE: 21 or 30 MW ?
Based on the previous production data you provided, the 31 MW project does not qualify for the 10 average MW
contract, and the 20 MW project is questionable?
Was the previously provided production data accurate - if so we need to rerun pricing models, the price wil most likely
be similar to the previous pricing I provided are the projects viable at those prices?
If the previously provided data was not accurate, the previous provided pricing may not be accurate.
If they are viable, which transmission request should i submit first?
Randy
From: Christine Mikell (mallto:d:rlstndwawlnd.comi
sent: Monday, August 02,20103:22 PM
To: Allphin, Randy
Subjec: Re: 21 or 30 MW ?
Yes, with a mile separation.
From: Allphin, Randy ..BAlIphlnOIdohogowe&oop
To: Christine Mikell
Sent: Mon Aug 02 17:21:202010
Subject: RE: 21 or 30 MW ?
Christine - i guess i read things wrong - this information is now suggesting is two separate projects (20 MW and a 31
MW) for a total of 51 MW?
You are suggesting they are two separate 10 average MW projects. In prior information you have suggested a capacity
factor over 40%, if this is the case the 30 MW would not qualify for a 10 MW average project and even the 21 MW
project would be questionable, based on the previous data you provided.
1 Attachment No.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 8 of 27
Do the projects qualify as separate facilties? Individual QF certificates from FERC? At least physically a mile apart?
Unfortunately this size and number of projects continues to cause delays and complications in the transmission capacity
request-
If they are truly separate projects - which one do you want me to file for first? (there may be room for one but not the
other)
If we get approval for one and/or both as separate projects, but then find out they must be combined into one project
we wil have to re file for transmission as the two filngs cannot be combined into one at a later time.
To do this right the first time, we need to determine if they are separate projects. Even if they are separate projects do
they qualify for the 10 average MW contract?
Based on the information you have provided, it appears they are the same project (same project location, same
interconnection, same BPA capacity reservation etc). If this is the case, then I need to file one 51 MW transmission
request and we wil need to rerun the pricing models to determine the energy pricing.
Randy
From: Allphin, Randy
sent: Monday, August 02, 2010 3:02 PM
To: 'Christine Mikell'
Subject: 21 or 30 MW ?
Christine, I am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications in your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
s.lD,.,PO.M~l!ii~
This transmission may contain infonation that is privileged, confidential and/or exempt from disclosure under applicable law. If yo are not the intended reipient. you are herby
notified that any disclosure, copying, distribution, or use of the infonnation contained herein (including any reliance thern) is STRICTLY PROHIBITED. ¡fyou reved this
trsmisson in eror, please immediately contact the sende and destry the material in its entiret, whether in electronic or ha copy funnai. Thank you.
2 Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 9 of 27
&hin, Randy
From:
Sent:
To:
Subject:
Allphin, Randy
Tuesday, August 03. 2010 6:49 AM
'Christine Mikell'
RE: 21 or 30 MW ?
Lets plan on a quick phone call to get things sorted out. i am available pretty much available anytime today (Tuesday
Aug 3) e-mail a suggested time or you can just give me a try on the phone.
Randy
From: Christine Mikell (mailto:chrle(§wasandicol
sent: Monday, August 02, 2010 4:16 PM
To: Allphin, Randy
Subject: Re: 21 or 30 MW ?
We calculated it, the higher winds are to the north with fewer turbines and lower winds are to the south. Do you need
something from us to make this case?
Thanks.
From: Allphin, Randy -cRAlIphlnfildbopor.oom::
To: Christine Mikell
Sent: Mon Aug 0217:33:582010
SUbject: RE: 21 or 30 MW ?
Based on the previous production data you provided, the 31 MW project does not qualify for the 10 average MW
contract, and the 20 MW project is questionable?
Was the previously provided production data accurate - if so we need to rerun pricing models, the price wil most likely
be similar to the previous pricing i provided are the projects viable at those prices?
If the previously provided data was not accurate, the previous provided pricing may not be accurate.
If they are viable, which transmission request should i submit first?
Randy
From: Christine Mikell (møllt;çhtlstnéfwlnd.col
Sent: Monday, August 02, 2010 3:22 PM
To: Allphin, Randy
Subject: Re: 21 or 30 MW ?
Yes, with a mile separation.
From: Allphin, Randy -CRAllphinlâidahopower.com::
To: Christine Mikell
1 Attachment No.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 10 of 27
sent: Mon Aug 02 17:21:20 2010
Subject: RE: 21 or 30 MW ?
Christine - I guess I read things wrong - this information is now suggesting is two separate projects (20 MW and a 31
MW) for a total of 51 MW?
You are suggesting they are two separate 10 average MW projects. In prior information you have suggested a capacity
factor over 40%, if this is the case the 30 MW would not qualify for a 10 MW average project and even the 21 MW
project would be questionable, based on the previous data you provided.
Do the projects qualify as separate facilities? Individual QF certificates from FERC? At least physically a mile apart?
Unfortunately this size and number of projects continues to cause delays and complications in the transmission capacity
request-
If they are truly separate projects - which one do you want me to file for first? (there may be room for one but not the
other)
If we get approval for one and/or both as separate projects, but then find out they must be combined into one project
we wil have to re file for transmission as the two filngs cannot be combined into one at a later time.
To do this right the first time, we need to determine if they are separate projects. Even if they are separate projects do
they qualify for the 10 average MW contract?
Based on the information you have provided, it appears they are the same project (same project location, same
interconnection, same BPA capacity reservation etc). If this is the case, then i need to file one 51 MW transmission
request and we will need to rerun the pricing models to determine the energ pricing.
Randy
From: Allphin, Randy
Sent: Monday, August 02,20103:02 PM
To: 'Christne Mikell'
Subjec: 21 or 30 MW ?
Christine, I am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications in your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
2 Attachment NO.6
Case Nos. IPC-E-1D-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 11 of27
Thii tl'ill miy etljiininlilk\n,lll il ¡ivlic~ l;ficltùl. uiOl ~~eiPi rtomdiiloll ui~ablelaw. ir~ lIA:lI illiWlî rtieyll an heY
lIlfiè: ihaiiiiiy diilosre C!1l dillrlOOllll or ii ølllle inlbl'lilill Clalned litin(looti.í\ lIyreill ibn) Is STRICTY PROl$lrEP.tr~1i ~\'è: tbii .
i_l'llln ei. pi~ imiooiiiiely CQIIiI ibe se and desy the maeilnits eniirty, wbeln eleroie or hacop ibii. Ttiilt yl
3 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 12 of 27
~hin, Randy
From:
Sent:
To:
Subject:
Christine Mikell rchristine~wasatchwind.comi
Tuesday, August 03,20109:00 AM
Allphin. Randy
Re: 21 or 30 MW ?
Hi randy. On vacation but wil tru to call you in the mix of things. How about 1 or 2 pm your time?
From: Allphin, Randy "RAllphIDi!dhopof1gm~
To: Christine Mikell
sent: Tue Aug 03 08:49:01 2010
Subject: RE: 21 or 30 MW?
Lets plan on a quick phone call to get things sorted out. I am available pretty much available anytime today (Tuesday
Aug 3) e-mail a suggested time or you can just give me a try on the phone.
Randy
From: Christne Mikell (mallt:cbrineiwaslnd.gm)
sent: Monday, August 02,20104:16 PM
To: Allphin, Randy
Subject: Re: 21 or 30 MW?
We calculated it, the higher winds are to the north with fewer turbines and lower winds are to the south. Do you need
something from us to make this case?
Thanks.
From: Allphin, Randy "RAIlf¡hlnca!dahopower.øm~
To: Christine Mikell
sent: Mon Aug 0217:33:582010
Subject: RE: 21 or 30 MW ?
Based on the previous production data you provided, the 31 MW project does not qualify for the 10 average MW
contract, and the 20 MW project is questionable?
Was the previously provided production data accurate - if so we need to rerun pricing models, the price wil most likely
be similar to the previous pricing I provided are the projects viable at those prices?
If the previously provided data was not accurate, the previous provided pricing may not be accurate.
If they are viable, which transmission request should I submit first?
Randy
From: Christine Mikell (rnllto¡chrfstneCëaand.co)
Sent: Monday, August 02, 2010 3:22 PM
1 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 13 of 27
To: Allphin, Randy
Subject: Re: 21 or 30 MW ?
Yes, with a mile separation.
From: Allphin, Randy .iRAllphlnOidbopo.conp
To: Christine Mikell
sent: Mon Aug 02 17:21:20 2010
Subjec: RE: 21 or 30 MW ?
Christine - I guess I read things wrong - this information is now suggesting is two separate projects (20 MW and a 31
MW) for a total of 51 MW?
You are suggesting they are two separate 10 average MW projects. In prior information you have suggested a capacity
factor over 40%, if this is the case the 30 MW would not qualify for a 10 MW average project and even the 21 MW
project would be questionable, based on the previous data you provided.
Do the projects qualify as separate facilities? Individual OF certificates from FERC? At least physically a mile apart?
Unfortunately this size and number of projects continues to cause delays and complications in the transmission capacity
request-
If they are truly separate projects - which one do you want me to file for first? (there may be room for one but not the
other)
If we get approval for one and/or both as separate projects, but then find out they must be combined into one project
we wil have to re file for transmission as the two filngs cannot be combined into one at a later time.
To do this right the first time, we need to determine if they are separate projects. Even if they are separate projects do
they qualify for the 10 average MW contract?
Based on the information you have provided, it appears they are the same project (same project location, same
interconnection, same BPA capacity reservation etc). If this is the case, then I need to file one 51 MW transmission
request and we wil need to rerun the pricing models to determine the energy pricing.
Randy
From: Allphin, Randy
sent: Monday, August 02, 2010 3:02 PM
To: 'Christine Mikell'
Subject: 21 or 30 MW ?
Christine, I am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications in your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are still unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
2 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 14 of 27
Randy
ThîSitlSloolillY oonllin infotl tbít Îl prvile coßdlltlli1 andoreieipt liom dllOll IIdeiwiça 'law. IfYOlmnoi ilinei~, yu lW1iøb
llilied l!itsny dilll~ eopyin¡:, disribuÌln, or \I of the InfçrmtÍQ cotaine ,~in (ìnl\llng any relli ilu) ¡s. STRCT Y PROHIBIT. If you ~vC\th
iniinon in mor. ¡ii- iiiiníniely i;nti ilisi andcroy il maieral In LIS eiilry.wlher in eleronic or li cop ft. Thk yo
:1 Attchment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 15 of 27
~hin,Randy
From:
Sent:
To:
Subject:
Allphin, Randy
Tuesday, August 03,20109:10 AM
'Christine Mikell'
RE: 21 or 30 MW ?
We can plan on 2pm. If you prefer to wait for another day, I wil be around every day except Friday. Just let me know
Randy
From: Christine Mikell (mallt:cbi1netsat:nd.c:J
Sent: Tuesday, August 03, 2010 9:00 AM
To: Allphin, Randy
SUbject: Re: 21 or 30 MW?
Hi randy. On vacation but will tru to call you in the mix of things. How about 1 or 2 pm your time?
From: Allphin, Randy -:RAllohin(§idahooower.com;:
To: Christine Mikell
sent: Tue Aug 03 08:49:012010
Subject: RE: 21 or 30 MW ?
lets plan on a quick phone call to get things sorted out. I am available pretty much available anytime today (Tuesday
Aug 3) e-mail a suggested time or you can just give me a tryon the phone.
Randy
From: Christine Mikell (mailt:çbrlstndsand.com 1
sent: Monday, August 02,20104:16 PM
To: Allphin, Randy
Subjec: Re: 21 or 30 MW ?
We calculated it, the higher winds are to the north with fewer turbines and lower winds are to the south. Do you need
something from us to make this case?
Thanks.
From: Allphin, Randy -:RAllphin(§idahopower.com;:
To: Christine Mikell
Sent: Mon Aug 02 17:33:582010
Subjec: RE: 21 or 30 MW ?
Based on the previous production data you provided, the 31 MW project does not qualify for the 10 average MW
contract, and the 20 MW project is questionable?
Was the previously provided production data accurate - if so we need to rerun pricing models, the price wil most likely
be similar to the previous pricing I provided are the projects viable at those prices?
If the previously provided data was not accurate, the previous provided pricing may not be accurate.
1 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 16 of 27
If they are viable, which transmission request should I submit first?
Randy
From: Christine Mikell rmallt:C!i1neaswlnd.comJ
Sent: Monday, August 02,2010 3:22 PM
To: Allphin, Randy
Subject: Re: 21 or 30 MW ?
Yes, with a mile separation.
From: Allphin, Randy -:RAiiphlnlâidahopower.com~
To: Christine Mikell
Sent: Mon Aug 02 17:21:20 2010
Subject: RE: 21 or 30 MW ?
Christine -I guess I read things wrong - this information is now suggesting is two separate projects (20 MW and a 31
MW) for a total of 51 MW?
You are suggesting they are two separate 10 average MW projects. In prior Information you have suggested a capacity
factor over 40%, if this is the case the 30 MW would not qualify for a 10 MW average project and even the 21 MW
project would be questionable, based on the previous data you provided.
Do the projects qualify as separate facilities? Individual QF certificates from FERC? At least physically a mile apart?
Unfortunately this size and number of projects continues to cause delays and complications in the transmission capacity
request -
If they are truly separate projects - which one do you want me to file for first? (there may be room for one but not the
other)
If we get approval for one and/or both as separate projects, but then find out they must be combined into one project
we wil have to re file for transmission as the two filngs cannot be combined into one at a later time.
To do this right the first time, we need to determine if they are separate projects. Even if they are separate projects do
they qualify for the 10 average MW contract?
Based on the information you have provided, it appears they are the same project (same project location, same
interconnection, same BPA capacity reservation etc). If this is the case, then I need to file one 51 MW transmission
request and we will need to rerun the pricing models to determine the energy pricing.
Randy
From: Allphin, Randy
Sent: Monday, August 02,2010 3:02 PM
2 Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 17 of 27
To: 'Christine Mikell'
Subjec 21 or 30 MW ?
Christine, I am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications In your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
._~
11ÌlIn~Qtm.y co_lufmil ~ is prv:~, cøl'eiilal iinder exem ir diski iiiippli law. Ifyw. iino Ilæ,ìned reipeii,yw ar hmnotified ihii ¡iy l!l(ll' copyil: diibiiilci, or ii of iiie. .ln~il C(IlIIl hi:(inludlllim rel~ ~)iSSTRCTY PRHlBlT. If yw re\ilbis
ltlsson in er, ple lmimliiely coiilac ihesi llde the Ulllìå in ìll éiy. wbelerm eleroeer ti e¡ tørll 11k you.
3 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 18 of 27
~hin, Randy
From:
Sent:
To:
Subject:
Allphin, Randy
Wednesday, August 11, 2010 7:12 AM
'Christine Mikell'
RE: 21 or 30 MW ?
Christine,
Sorry I missed you on Tuesday, got tied up in meetings.
Would today (Wednesday) 11 am Boise time work for you?
Randy
From: Christine Mikell (mailto:christine~wasatchwind.com)
sent: Tuesday, August 10, 2010 12:20 PM
To: Allphin, Randy
Subjec: RE: 21 or 30 MW ?
Hi Randy,
What time can we talk today or tomorrow? I am available after 3 pm.
Thanks.
From: Allphin, Randy (mailto:RAllphin(§idahopower.com)
Sent: Tuesday, August 03,20109:10 AM
To: Christine Mikell
Subject: RE: 21 or 30 MW?
We can plan on 2pm. If you prefer to wait for another day, I wil be around every day except Friday. Just let me know
Randy
From: Christine Mikell (mailto:christine~wasatchwind.com)
sent: Tuesay, August 03, 2010 9:00 AM
To: Allphin, Randy
Subjec: Re: 21 or 30 MW ?
Hi randy. On vacation but will tru to call you in the mix of things. How about 1 or 2 pm your time?
From: Allphin, Randy c:RAllphin(§idahopower.com:;
To: Christine Mikell
Sent: Tue Aug 03 08:49:01 2010
Subject: RE: 21 or 30 MW ?
Lets plan on a quick phone call to get things sorted out. I am available pretty much available anytime today (Tuesday
Aug 3) e-mail a suggested time or you can just give me a tryon the phone.
1 Attachment No.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 19 of 27
Randy
From: Christine Mikell (mailto:christine(§wasatchwind.com)
sent: Monday, August 02,20104:16 PM
To: Allphin, Randy
Subject: Re: 21 or 30 MW ?
We calculated it, the higher winds are to the north with fewer turbines and lower winds are to the south. Do you need
something from us to make this case?
Thanks.
From: Allphin, Randy oeRAllphin(Qidahopower,com;:
To: Christine Mikell
sent: Mon Aug 02 17:33:582010
Subject: RE: 21 or 30 MW ?
Based on the previous production data you provided, the 31 MW project does not qualify for the 10 average MW
contract, and the 20 MW project is questionable?
Was the previously provided production data accurate - if so we need to rerun pricing models, the price wil most likely
be similar to the previous pricing I provided are the projects viable at those prices?
If the previously provided data was not accurate, the previous provided pricing may not be accurate.
If they are viable, which transmission request should I submit first?
Randy
From: Christine Mikell (mailto:christine(gwasatchwind.com)
Sent: Monday, August 02,2010 3:22 PM
To: Allphin, Randy
Subject: Re: 21 or 30 MW?
Yes, with a mile separation.
From: Allphin, Randy oeRAllphin(Qidahopower.com;:
To: Christine Mikell
Sent: Mon Aug 02 17:21:202010
Subject: RE: 21 or 30 MW ?
Christine - I guess I read things wrong - this information is now suggesting is two separate projects (20 MW and a 31
MW) for a total of 51 MW?
You are suggesting they are two separate 10 average MW projects. In prior information you have suggested a capacity
factor over 40%, if this is the case the 30 MW would not qualify for a 10 MW average project and even the 21 MW
project would be questionable, based on the previous data you provided.
Do the projects qualify as separate facilities? Individual QF certificates from FERC? At least physically a mile apart?
2 Attchment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 20 of 27
Unfortunately this size and number of projects continues to cause delays and complications in the transmission capacity
request-
If they are truly separate projects - which one do you want me to file for first? (there may be room for one but not the
other)
If we get approval for one and/or both as separate projects, but then find out they must be combined into one project
we wil have to re file for transmission as the two filings cannot be combined into one at a later time.
To do this right the first time, we need to determine if they are separate projects. Even if they are separate projects do
they qualify for the 10 average MW contract?
Based on the information you have provided, it appears they are the same project (same project location, same
interconnection, same BPA capacity reservation etc). If this is the case, then i need to fie one 51 MW transmission
request and we wil need to rerun the pricing models to determine the energy pricing.
Randy
From: Allphin, Randy
sent: Monday, August 02, 2010 3:02 PM
To: 'Christine Mikell'
Subject: 21 or 30 MW?
Christine, I am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications in your package i had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
3 Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 21 of27
Thilllråníøri iny 001l infómi!!oii Ull Í$Privll~, lliitktilJiior exem ft dlscloú1 aplicle law. Ifyu_oolhe inteiiwpleil. )'u ar bei
riQtlfi Ul ~ydiiur eopillJtdlSlribilioii, or us ofih irilbmilltlll c:lliill bi (Includng an re~ Ih~ri) II STRICi,V PRpH18mD. Ifyu~wdiliiIiriilllo in er, pl_ imillely 00 ihe Sl ii Ù/lrotlimiterl in illlClire. wli inek:icQl ba co Ibl, ThÌlK)'
4 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 22 of 27
~phinJ Randy
From:
Sent:
To:
Subject:
Attachments:
Christine Mikell (christine~wasatchwind.com)
Tuesday, August 17,20105:32 PM
Allphin, Randy
RE: 21 or 30 MW ?
GrouseCreekQF1 indicpric_201 OJ _14.pdf; GrouseCreekQF2indicpric_2010_7 _14.pdf
Dear Randy,
I thought it would be helpful to provide you with an overview of our plans so that we can make progress toward
getting the 30 MW Grouse Creek Wind Park I and the 21 MW Grouse Creek Wind Park II up and running. My apologies
if our e-mail communications have been less than clear.
First please consider this a formal request for two separate, standard, non-Ievelized, under-ten-average-
monthly-megawatt, twenty year power purchase agreements. The projects wil be located in Northern Utah and wil
interconnect with Raft River Rural Electric Cooperative. Bonnevile Power Administration wil deliver the output to an
interconnection with your system at the Minidoka Substation in Southern Idaho.
The output from the two projects wil by physically limited such that neither project wil be capable of
generating more than ten average megawatts in any given month.
i understand that Idaho Power has a new process whereby a project must be designated as a network resource
prior to obtaining a power purchase agreement. i have enclosed a completed "Transmission Capacity Application
Questionnaire" to start Idaho Power's internal process to designate the two projects as network resources. I also
understand that this project may be located on a part of the Idaho Power system that requires upgrades to the
backbone transmission. Therefore I anticipate that there wil have to be a study to determine what upgrades our
projects will be responsible for. That said, i do not believe the study process should delay the submission of execution
ready power purchase agreements. With the substantial delay security being required in recent Idaho Power PPAs, the
risk of our project's failng to come on line due to transmission constraints is completely mitigated.
The expected on line date for the two projects is December 31, 2012.
Randy, I hope this is helpfuL. We are looking forward to a long and mutually beneficial relationship with Idaho
Power Company.
Sincerely yours
Christine Mikell
Director of Development
Wasatch Wind
From: Allphin, Randy (mailto:RAllphin(§idahopower.com)
sent: Wednesday, August 11, 20107:12 AM
To: Christine Mikell
Subject: RE: 21 or 30 MW?
Christine,
Sorry I missed you on Tuesday, got tied up in meetings.
1 Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 23 of 27
Would today (Wednesday) 11 am Boise time work for you?
Randy
From: Christine Mikell (mailto:christinel§wasatchwind.com)
sent: Tuesday, August 10, 2010 12:20 PM
To: Allphin, Randy
Subjec: RE: 21 or 30 MW ?
Hi Randy,
What time can we talk today or tomorrow? I am available after 3 pm.
Thanks.
From: Allphin, Randy (mailto:RAllphinl§idahopower.com)
sent: Tuesday, August 03,20109:10 AM
To: Christine Mikell
Subjec: RE: 21 or 30 MW ?
We can plan on 2pm. If you prefer to wait for another day, I will be around every day except Friday. Just let me know
Randy
From: Christine Mikell (mailto:christinet§wasatchwind.com)
Sent: Tuesday, August 03,20109:00 AM
To: Allphin, Randy
Subject: Re: 21 or 30 MW ?
Hi randy. On vacation but wil tru to call you in the mix of things. How about 1 or 2 pm your time?
From: Allphin, Randy .cRAllphin(iidahopower.com;:
To: Christine Mikell
sent: Tue Aug 03 08:49:01 2010
Subjec: RE: 21 or 30 MW ?
Lets plan on a quick phone call to get things sorted out. I am available pretty much available anytime today (Tuesday
Aug 3) e-mail a suggested time or you can just give me a tryon the phone.
Randy
From: Christine Mikell (mailto:christinel§wasatchwind.com)
Sent: Monday, August 02, 2010 4:16 PM
To: Allphin, Randy
Subject: Re: 21 or 30 MW ?
We calculated it, the higher winds are to the north with fewer turbines and lower winds are to the south. Do you need
something from us to make this case?
Thanks.
2 Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 24 of 27
From: Allphin, Randy ieRAllphin(§idahopower.com::
To: Christine Mikell
Sent: Mon Aug 02 17:33:58 2010
Subject: RE: 21 or 30 MW ?
Based on the previous production data you provided, the 31 MW project does not qualify for the 10 average MW
contract, and the 20 MW project is questionable?
Was the previously provided production data accurate - if so we need to rerun pricing models, the price wil most likely
be similar to the previous pricing I provided are the projects viable at those prices?
Ifthe previously provided data was not accurate, the previous provided pricing may not be accurate.
If they are viable, which transmission request should I submit first?
Randy
From: Christine Mikell (mailto:christine(gwasatchwind.com)
Sent: Monday, August 02, 2010 3:22 PM
To: Allphin, Randy
Subject: Re: 21 or 30 MW ?
Yes, with a mile separation.
From: Allphin, Randy ieRAllphin(gidahopower.com::
To: Christine Mikell
Sent: Mon Aug 02 17:21:202010
Subjec: RE: 21 or 30 MW?
Christine -I guess i read things wrong - this information is now suggesting is two separate projects (20 MW and a 31
MW) for a total of 51 MW?
You are suggesting they are two separate 10 average MW projects. In prior information you have suggested a capacity
factor over 40%, if this is the case the 30 MW would not qualify for a 10 MW average project and even the 21 MW
project would be questionable, based on the previous data you provided.
Do the projects qualify as separate facilities? Individual QF certificates from FERC? At least physically a mile apart?
Unfortunately this size and number of projects continues to cause delays and complications in the transmission capacity
request-
If they are truly separate projects - which one do you want me to file for first? (there may be room for one but not the
other)
If we get approval for one and/or both as separate projects, but then find out they must be combined into one project
we wil have to re file for transmission as the two filngs cannot be combined into one at a later time.
To do this right the first time, we need to determine if they are separate projects. Even if they are separate projects do
they qualify for the 10 average MW contract?
3 Attachment No.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 25 of 27
Based on the information you have provided, it appears they are the same project (same project location, same
interconnection, same BPA capacity reservation etc). If this is the case, then I need to file one 51 MW transmission
request and we wil need to rerun the pricing models to determine the energy pricing.
Randy
From: Allphin, Randy
Sent: Monday, August 02, 2010 3:02 PM
To: 'Christine Mikell'
Subject: 21 or 30 MW ?
Christine, I am making some progress on the transmission requests, however the first questions I encountered was if the
project would be 21 or 30 MW. As you included both applications in your package I had assumed you were not sure at
time you submitted this information. Do you have any updated information?
If you are stil unsure, probably be best to submit for the 30 MW, if this is available would be logical that 21 MW would
be available.
Randy
4 Attachment NO.6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 26 of 27
This t~I'Y cOIln informtion ilt istivìlii eiíiridliitanQf lll:Pi ~dllø l\detlliCble law. IfYQ ~ nlllllillll ~.)'llli,
notified that any disloiireaing. dÍ5'btiOl, Of us of the lnftlon contain hl(lnluding an reftcther)ls mlCT Y PROHllT. U'you,reel'loolhs
tiIS$mn In emr. plea iml'i:aldy coniiCl the $e an dey the matel in I'" coy, whethe In deroniçQf li COY foat. 1l yt
5 Attachment No. 6
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 27 of 27
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO.7
~hin,Randy
From:
Sent:
To:
Cc:
Subject:
Attachments:
Greg Adams (Greg~richardsonandoleary.coml
Friday, October 01, 2010 11 :58 AM
Allphin, Randy
Walker, Donovan; Peter Richardson
Wasatch Wind -- Grouse Creek Wind Park
10-1-10-Letter- GCWP.pdf
Randy,
Please see the attached letter from Pete Richardson. We'll drop a paper copy off at the front desk today.
Greg
OregAdams
Richardson & O'Lear PLLC
515 N. 27th Street, 83702
P.O. Box 7218,83707
Boise, Idaho
Voice: 208.938.2236
Facsimile: 208.938.7904
Informtion contained in this electronic message and in any attachments hereto may contain infonnation that is confidential, protected
by the attorney/client privilege and/or attorney work product doctrine. This email is intended only for the use of the individual or
entity named above. Inadvertnt disclosure of the contents of this email or its attchments to unintended recipients is not intended to
and does not constitute a waiver of the attorney/client privilege and/or attorney work product doctrne. This tranmission is fuer
covered by the Electronic Communication Privacy Act, is U.S.C. §§ 2510-2521.
If you have received this email in error, immediately notify the sender of the errneous receipt and destry this email and any
attchments of the same either electronic or printed. Any disclosur, dissemination, distrbution, copying or use of the contents or
information received in error is strctly prohibited.
Th you.
1 Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of 16
Ri.cJlSON & OLEY. PU
ATTORNEYS AT LAW
Peter Richardson
Tel: 208-938,7901 Fu: 208.9.l8.7904
pi:~r(lridu.rdlo nandoJ i:ary.co m
P,Q, Box 7218 Boi... II 83707 . 5 i 5 N, 271n 51, 8oi,.. ll 83702
October i, 2010
Via Hand Delivery and Electronic Mail
Randy Allphin
PUR A Contracts Administrator
Idaho Power Company
P.O. Box 70
Boise, Idaho 83707
Re: Wasatch Wind - Grouse Creek Wind Park
Dear Randy:
I write on behalf of my client, Wasatch Wind, regarding its request for a power purchase agreement
(PPA) for a quaifYing facilty (QF) under the Public Utilties Regulatory Policy Act of 1978
(PURP A) - the 21 megawat (MW) Grouse Creek Wind Park. As you know, Wasatch Wind has
been in contact with you and has provided Idaho Power with substatial amounts of informaton
regarding this PURP A project in its efforts to secure a PPA over the past few months. Furer, you
and I discussed issues related to interconnection and trsmission for this project on August 30,
2010.
As descrbed in more detail below, the project is in Northern Uta and will interconnect with the
Raf River Rural Electrc Cooperative. Wasatch Wind is aranging for an agreement to have
Bonneville Power Administation (BPA) deliver the output to Idaho Power's system at the
Minidoka substation. This QF project is, and has been, ready willng and able to obligate itself to a
PURP A PP A with Idao Power containing the standad rates, ter, and conditions approved by the
Idaho Public Utilities Commssion (Commission) to projects that will deliver under 10 average
monthly megawatts (aMW). Those terms include the daily and seasonality load shape pnce
adjustments (Order No. 30415), as well as the wind integration charge, mechaical availabilty
guantee, and wind forecasting and cost sharg provisions (Order No. 30488). The most reently
approved PURPA wind PPA contaning the applicable provisions is the Idaho Winds LLC PP A,
which is on file at the Commission in Case No. IPC-E-09-25, and could be used as a template.
I wrte this letter to clarfy Wasatch Wind's position on some issues of contention, or perhaps
simply misunderstanding, regarding this project, and to provide you with all the project specifc
inormation you should ne to complete a standar PURP A PP A under one cover.
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-2
Allphin Affdavit, IPC
Page 2 of 16
Mr. Allphin
October 1,2010
Page 2
Interconnectionlramission Request Processin
First, I need to address the trsmssion and interconnection application process. As we discusse
on Augut 30, 2010, Wasatch Wind has another nearby wind QF -the Grous Creek Wind Park 11-
that it plan to bring online in parlel with the Grouse Creek Wind Park. Thes projects will be at
leat one mile apar, will be separate QFs, and will be owned and operated by separate limited
liabilty companes (the Grouse Creek Wind Park LLC and the Grouse Creek Wind Park II LLC).
Wasatch Wind's position is that it is entitled to request separte PPAs and separate interconnection
argements for each project simultaneously, and to have the processes to obtan PPAs and
interconnection arangements for each project progress in parallel. You appeared to indicate that
Wasatch Wind may only submit, and/or Idaho Power will only process, one project's
interconnection application at a time. In other words, iff understood you correctly, Idaho Power
would have Wastch Wind submit a single interconnection/tranmission reuest for one project, and
then wait the six to nie months it may tae for completion of processing of tht request, pror to
even submitting/processin the request for the secnd project.
There is no basis in fact or law for imposing such a requirement on Wasatch Wind. Both projects
should proced though the interconnection/tranmission stdy process simultaeously, as Wasatch
Wind has requested. These are two separate QFs, sepaated by at least one mie, and, for power sale
and interconnection/transmission request purses, should be trated as two separte entities. If
those simultaneous studies reveal a transmission constraint, the project placed in the trmission
queue second wil then have to decide whether it will pay for any necessar upgrade, or make
another argement base on its poition at that time. It is simply unair to completely stal
progrss of one project whle studying transmission availabilty for the other project.
Wasatch Wind has submitted a trsmission capacity application for the Grouse Creek Wind Park
and Grouse Creek Wind Park II on August 19, 2010, in an effort to become a network resoW'e, and
hereby fonnally reiterates its reuest that the application be processed in parallel with the
application for the Grouse Creek Wind Park n. Failur to do SO would prejudice the rights of
Wasatch Wind and its affiliates of obtaining separate PPAs for these separate QFs.
It necessary to point out tht Idaho Power's unjustified actions have already delayed progress of
these two QF developments' efforts to arrange to wheel their output over BPA's system. This
year, BPA initiated a network open season (NOS) so that BPA could improve transmission
availabilty on its system for customers and relieve a backlog of requests. Wasatch Wind made
an NOS request in June 2010 in order to resere space for its Grouse Creek Wind Park and
Grouse Creek Wind Park II projects. This is around the same time that Wasatch Wind contacted
Idaho Power, and requested PPAs and transmission on Idaho Power's system. BPA's NOS
process included a requirement that Wasatch Wind post a perfonnance assurance amount of
$794,376 for these two QFs by August 18,2010. Wasatch Wind hope that by making the BPA
request concurently with its request to Idaho Power for PP As and trasmission that it would
obtain some sort of assurance from Idaho Power by August i 8 that its requests were being
processed. But because Idaho Power refused to make the trasmission request, Wasatch Wind
could not risk losing that large sum of money required for BPA's NOS, and had to pull out of
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 3 of16
Mr. Allphin
October 1,2010
Page 3
BPA's NOS. Subsequent to that, Wasatch Wind submitted two new Transmission Service
Requests to Idaho Power, as of August i 8, and has renewed its efforts with BPA.
Delay Default Liquidated Damages Security Provision
The other item that I need to raise at this time is that of a delay default liquidated damages
security provision. Wasatch Wind understads that Idao Power has recently begun requiring
delay default liquidated damages securty provisions in PURP A PPAs whereby the QF must post
a delay securty of $45/kw of nameplate capacity for the project, which sum Idaho Power would
retain as liquidated damages in the event the QF fails to achieve the PPA's online date. For this
21 MW project, such a provision would require the QF to post $945,000.
In Order No. 30608, the Commission stated that delay default liquidated damages security must
be a "fair and reasonable offset of a regulated utility's estimated increase in power supply costs
attributable to the PURPA supplier's failure to meet its contractually scheduled operation date."
The Commission's statement is consistent with Idaho law, which clearly prohibits use of
liquidated damages provisions when damages are easily estimated, or when such provisions are
punitive or designed to deter a breach of the contract. See Magic VaJ/ey Truck Brokers, Inc. v.
Meyer, 133 Idao 11 0, 117, 982 P.2d 945, 952 (Ct. App. 1999); i.e. § 28-2-718(1). Idaho
Power's actual damages caused by a QF's delay in achieving its online date would not be
difficult to calculate, and the amount of $45/kw is far in excess of the costs of replacement power
or administrative expenses Idaho Power may incur. A $45/kw liquidated damages clause is
simply not legal in Idaho and would be rejected by Idaho courts. And requiring a QF to post an
uneasonably high delay default security frustrates PURPA's mandatory purchase provisions.
Wasatch Wind wil not agree to a $45/kw delay security, unless the Commission orders that
amount is reasonable. Wasatch Wind intends to obligate itself at this time only to a PPA
requiring it to post no delay default security amount, or to any amount deemed reasonable by the
Commission if Idaho Power insists on a provision requiring Wasatch to post a delay default
liquidated damages security.
Project Information
For the remainder of this letter, I wil provide detailed infonnation regarding the Gruse Creek
Wind Park, available to you in one location for your convenience in completing the requested
stadard PPA. Please complete a stadard PPA for Wasatch Wind according to the information
provided below. Ifwe ar unable to resolve any remaining disagreement regarding the timing of the
interconnection/trsmission applications or the delay default liquidated damages security
provisions, Wasatch Wind requests that you provide a PPA containing all undisputed terms and
conditions, and that Idaho Power and the QF proceed to the Commission for a determination as
to any disputed terms. For any such disputed terms, Wasatch intends at this time to obligate
itself to a PPA containing the terms that the Commission ultimately concludes to be just and
reasonable.
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 4 of 16
Mr. Allphin
October 1, 2010
Page 4
(a) abilty to obtain QF status
As a wid generating facilty utilizing a renewable fuel source, the facility wil be a qualifying
facility as defined in 18 C.F.R. § 292.203(a) and (c).
(b) design capacity (M
This project will have a naeplate rating of21 MW, but under nonnal operating conditions in any
given month Wastch Wind's proposed design of the project will generate less th 10 aMW.
Specifically, Wastch Wind wil design the facilty in such a way tht the tubines switch to
maintenance mode, and thus cease generating electricity to be delivered to Idaho Power, if
production levels for a given month reach the 10 aM cap. The engineerig te wil do so by
adding some "logic" to the metering equipment. Once the output has reached a predetennined
level, the metering equipment will communicate with the control equipment and put the turbines
into maintenance mode. Monthly generation wil not exceed the 10 aMW cap, and Wastch
Wind wil provide appropriate engineering certification of this fact. Therefore, in accordance
with Commission Order No. 29632, Wasatch Wind agrees to a provision in the PPA providin tht
a cap on the maximum monthly generation that qualifies for published rates at the total
number of hours in the month multiplied by 10 MW.
The Commission has approved PURPA PPAs for projects with design specifications such as this in
the past. For example, in Order No. 30028, the Commission approved a PPA at the published rates
for a cogeneration facility with a design capacity of over 10M W because it would only generate 10
aMW in nonnal and/or average conditions based on data supplied by the QF. Likewise, Wasatch
Wind proposes to design the Grouse Creek Wind Park facilty as a QF that will deliver less than 10
aMW, and will provide appropriate certfication to Idao Power of that design speification.
I understand that Wasatch Wind's existing request for a PPA for ths project indicated the project
would have a nameplate capacity of 30 MW. Pleas consider that request amended to specify this
project will have a nameplate capacity of21 MW. Please also amend the Tranmission Capacity
Application Questionaire submittd on August 19,2010, accordingly. This decrease in naeplate
capacity should not present additional PPA or transmission problems and should not stall progrss
of the Idaho Power's prcessin of the PPA and transmission requests.
(c) generation technology and other related technology applicable to the site
The facility will be a wind generation project consistig of3.0 MW machines, whch wil be Vesta
V-I12 machines.
(d) proposed site location
The facilty will be located in Box Elder County, near Lyn, Uta. More speifically, Wasatch
Wind provides the followig legal description of the real propert associated with Grouse Creek
Wind Park:
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 5 of 16
Mr. Allphin
October 1,2010
Page 5
TOWNSHIP 14 NORTH, RANGE i 7 WEST OF THE SALT LAKE BASE MERIDIAN,
all of which is located in Box Elder County Utah, containing approximately 806.49 acres,
more or less.
Parcel 08-017-0016
Parcel 08-017-01 12
Parcel 08-017-0114
Part lying in the South half in Section 8, Townhip 14 North 17 West known as
parcel No. 08-017-0016
Part ofthe West Half of Section 16, T 14 N, R 17 W. Salt Lake Base and
Meridian, Box Elder County, Utah.
DESCRIPTION: Beginning at Southwest Comer of Section 16, T 14N,R 17W,
SLB&M a Stone Monument with 5/8" rebar and 2" cap alongside found by
Desert West Land Surveys and RUNING THENCE N 00°35'06" E 4277.40
feet along the section line to a point on ridge, said point being a rebar and cap set
by Desert West Land Surveys; thence the following ten (10) courses along said
ridge to rebars and caps set by Desert West Land Surveys: (1) S 40°04'35/1 E
250.59 feet (2) S 07°47'58/1 E 516.55 feet (3) S 13°43'10" W 452.69 feet (4) S
20°27'39/1 E 204.52 feet (5) S 50°12'36" E 316.89 feet (6) S 24°55'14" E 430.68
feet (7) S 21 °50'37" E 749.05 feet, (8) S 45°45'09" E 581.60 feet, (9) S
40031'30"E 1403.24 feet, (10) S 04°12'26" E 138.01 feet; thence S 88°54'25/1W
2281,86 feet along section line to the point of beginning. Containing 87.51 acres,
more or less.
DESCRIPTION: Beginning at the Southeat Comer of Section 17, T 14 N, R
17W, SLB&M a Marked Stone Monument with rebar and cap alongside stamped
PLS 5754 by Desert West land Survey and RUNNING THENCE N 87°22'41" W
2718.20 feet to Marked Quarter Corner Stone Monument with rebar and cap
alongside by Johnston Engineering, P .C., stamped JEPC PLS i 52173: thence S
89°59'32" W 2628.40 feet to the Southwest Corner of said Section 17, a fence
comer: thence N 00°09'23" W 2590. i 4 feet to Marked Quarer Comer Stone
Monument with rebar and cap alongside stamped JEPC PLS 152173; thence N
00°40'09" E 1329.28 feet to the Southwest Comer of the Northwest Quarter of
the Northwest Quarer of said Section 17; thence N 89°29'16" E 1336.70 feet to
the Southeast Corner of the Northwest Quarer of the Northwest Quarter of said
Section 17; thence N 00°43'21" E 1340.23 feet to the Northeast Corner of the
Northwest Quarter of the Northwest Quarter of said Section 17; thence N
89°01'13" E 1338.22 feet to Marked Quarr Comer Stone Monument with rebar
and cap alongside stamped JEPC 152 i 73; thence N 89°36'50" E 1784.26 feet
along section line to fence line on ridge; thence the following four (4) courses
along fence lines on ridge; (i) S 04°33'59" E 662.48 feet, (2) S 78°53'18" E
583.12 feet, (3) S 28°18'19" E 155.75 feet, (4) S 40°03'33" E 3 i 7.70 feetto
Rebar and Cap set on the east line of said Section 17 by Desert West land
Survey: thence S 00°35'06" W 4277 .40 feet along said section line to the point of
beginning. Containing 598.32 acres, more or less.
(e) schedule of monthly power deliveries
The table below sets forth the expected schedule of monthly power production in a typical year.
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 6 of 16
Mr. Allphin
October 1, 20 i 0
Page 6
These production estimates do not account for station use or for line losses occuring between
the QF and the point of delivery to Idaho Power's system:
Month
January
February
March
April
May
June
July
August
September
October
November
December
Total
MWh
6,178.9
6,720.0
7,440.0
5,614.1
4,547.0
640.5
1,524.5
2,513.4
3,566.3
6,306.5
6,686.3
6,941.4
58,679
(t) motive force or fuel plan
The motive force is wind.
(g) proposed online date and other signifcant dates required to complete the milestones
Construction of the facilty and other necessar infrastrctu is scheduled to be complete and ready
for operation on December 31, 2012. The proposed online date to commence operation for
electricity sales to Idaho Power is December 31, 2012.
(h) proposed contract term and pricing provisions
Wasatch Wind requests a 20-year contract at the non-Jevelized rates in the avoided cost rate
schedule on file today with the Idaho Public Utilties Commission (errata to Idao Public Utilities
Commission Order No. 30125).
(i) status of intereonneetion or transmission arrngements
Wasatch Wind is arranging for an agreement to have BPA deliver the output to Idaho Power's
system at the Minidoka substaion. Wasatch Wind submitted a trasmission capacity application
questionne for Grouse Creek Wind Park to Idaho Power on August 19, 2010, and ha requested
that Idaho Power initiate any necessar processing of interconnection and transmission stdies or
ageements for the project.
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 7 of 16
Mr. Allphi
October t, 2010
Page 7
(j) point of delivery or interennection
Wasath Wind will deliver the output (net of station use and losses) to Idaho Power at the Minidoka
substation.
Conclusion
I hope tht ths lett has clarfied Wasch Wind's position regarding ths request, an will be
usefu in your processng of Wasath Wind's PURA project. Pleas contact me with any
questions, or with requests for any additional infonnation necessar to process ths request.
Very trly your,t.JO.~
Peter J. Richadson
Attorney for Wasatch Wind
cc: Donovan Waler, Attorney for Idaho Power (hd delivery and electronic mail)
Chrstine Mikell, Wasatch Wind (electronic mail)
Enclosure
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 8 of 16
~hin.Randy
From:
Sent:
To:
Cc:
Subject:
Attchments:
Greg Adams (Greg~richardsonandoleary.coml
Friday, October 01, 2010 12:00 PM
Allphin, Randy
Walker, Donovan; Peter Richardson
Wasatch Wind -- Grouse Creek Wind Park II
10-1-10-Letter- GCWP Il.pdf
Randy,
Please see the attached letter from Pete Richardson. We'll drop a paper copy off at the front desk today.
Greg
Greg Adams
Richardson & O'Lear PLLC
515 N. 27th Street, 83702
P.O. Box 7218,83707
Boise, Idaho
Voice: 208.938.2236
Facsimile: 208.938.7904
Infonnation contained in ths electronic message and in any attachments hereto may contain infonnation that is confidential, protected
by the attorney/client privilege and/or attorney work product doctre. This email is intended only for the use of the individul or
entity named above. Inadvertent disclosure of the contents of this email or its attchments to unintended recipients is not intended to
and does not constitute a waiver of the attorney/client privilege and/or attorney work product doctrne. This transmssion is fuer
covered by the Electronic Communication Privacy Act, 18 V.S.C. §§ 2510-2521.
If you have received this email in error, imediately notify the sender of the erroneous receipt and destry ths email and any
attchments of the same either electronic or prited. Any disclosur, dissemination, distrbution, copying or use of the contets or
infonnation received in errr is strctly prohibited.
Than you.
1 Attachment No. 7
Case Nos. IPC-E-1D-1 & IPC-E-1O-62
Allphin Affdavit, IPC
Page 9 of 16
RICHASON & O'LE. PU
ATTORNEYS AT LAW
Peter Richardson
Tel: 208-938-7901 Fax: 208.938.:904
pece r~ rich ardsonandol ~ary,com
1'.0, 80x 72J8 Boi... ID 83707 . 51 S N. 27,h S,. 80i,.. ID 83702
October t, 20 t 0
Via Hand Delivery and Electronic Mail
Randy Allphin
PURP A Contracts Administrator
Idaho Power Company
P.O. Box 70
Boise, Idaho 83707
Re: Wasatch Wind - Grouse Creek Wind Park II
Dear Randy:
I wrte on behalf of my client, Wasatch Wind, regarding its reuest for a power purchase agrement
(PPA) for a qualifying facility (QF) under the Public Utilties Regulatory Policy Act of 1978
(PURP A) - the 21 megawatt (MW) Grouse Creek Wind Park II. As you know, Wasatch Wind has
been in contact with you and ha provided Idaho Power with substatial amounts of information
regarding this PURPA project in its efforts to secure a PPA over the past few months. Furher, you
and I discussed issues related to interconnection and transmission for this project on August 30,
2010.
As described in more detail below, the project is in Northern Utah and will interconnect with the
Ra River Rural Electnc Cooperative. Wasatch Wind is arging for an agreement to have
Bonneville Power Admstration (BPA) deliver the output to Idaho Power's system at the
Minidoka substtion. Ths QF prject is, and has been, ready wiling and able to obligate itselfto a
PURP A PPA with Idao Power containing the standad rates, tens, and conditions approved by the
Idaho Public Utilities Commission (Commission) to projects that will deliver under 10 average
monthly megawatt (aM. Those tenn include the daly and seasonality load shape price
adjustments (Order No. 30415), as well as the wind integration chare, mechanical availabilty
guarantee, and wid forecasting and cost sharing provisions (Order No. 30488). The most recently
approved PURP A wind PPA containing the applicable provisions is the Idaho Winds LLC PPA,
which is on fie at the Commission in Case No. IPC-E-09-25, and could be used as a template.
I write this letter to clarfy Wasatch Wind's position on some issues of contention, or perhaps
simply misunderstading, regarding this project, and to provide you with all the project specific
information you should need to complete a standard PURP A PPA under one cover.
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 10 of 16
Mr. Allphin
October 1, 2010
Page 2
Interconoecüonfransmissioo Request Processing
Firt, I need to addrss the tramission and interconnection application process. As we discussed
on August 30, 2010, Wastch Wind has another neary wid QF - the Gruse Crek Wind Park -
tht it plans to bring online in paalel with the Gruse Creek Wind Park n. These projects will be
at lea one mile apar will be separte QFs, and will be owned and opemted by separte limited
liabilty companes (the Grouse Creek Wind Par LLC and the Grouse Crek Wind Park II LLC).
Wasatch Wind's position is tht it is entitled to request septe PPAs and separate interconnection
argements for each project simultaneously, an to have the processes to obtain PPAs and
interconnection argements for each project progrss in parlleL. You appea to indicate that
Wasatch Wind may Oiuy submit, and/or Idao Power will oiuy process, one project's
'intercnnection application at a time. In other words, if I understood you corrtly, Idaho Powe
would have Wasatch Wind submit a single interconnection/tramission request for one project, and
then wait the six to nine months it may tae for completion of prcessing of that request, prior to
even submittng/prcessing the request for the second project
There is no basis in fact or law for imposing such a requirement on Wash Wind. Both projec
should proceed though the interconnection/tranission study process simultaeously, as Wasath
Wind has requeted. These are two separate QFs, separted by at least one mile, and, for power sae
and interconnection/smission puroses, should be trated as two separte entities. If those
simultaeous stdies reveal a transmission constaint, the project place in the trsmission queue
second wil then have to decide wheter it will pay for any necessar upgrde, or make another
argement based on its position at that time. It is simply unair to completely stall progrss of one
project while studying trsmission avaiability for the other project.
Wasatch Wind has submitted a trsmission capacity application for the Gruse Crek Wind Park
and Grouse Creek Wind Park II on August 19, 20 I 0, in an effort to become a network resoure, and
hereby fonnally reitertes its request that the application be processd in parallel with the
application for the Grouse Creek Wind Park. Failure to do so would prejudice the rights of Wastch
Wind and its affilates of obtg separate PPAs for these separte QFs.
It necessary to point out that Idaho Power's unjustified actions have already delayed progress of
these two QF developments' efforts to arrge to wheel their output over BPA's system. This
year, BPA initiated a network open season (NOS) so that BPA could improve trsmission
availability on its system for customers and relieve a backlog of requests. Wasatch Wind made
an NOS request in June 20 lOin order to reserve space for its Grouse Creek Wind Park and
Grouse Creek Wind Park II projects. This is around the same time that Wasatch Wind contated
Idaho Power, and requested PPAs and transmission on Idao Power's system. BPA's NOS
process included a requirement that Wasatch Wind post a perormance assurance amount of
$794,376 for these two QFs by August 18, 2010. Wasatch Wind hoped that by making the BPA
request concurently with its request to Idaho Power for PPAs and transmission that it would
obtain some sort of assurance from Idaho Power by August 18 that its requests were being
processed. But because Idao Power refused to make the transmission request, Wasatch Wind
could not risk losing that large sum of money required for BPA's NOS, and had to pull out of
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 11 of 16
Mr. Allphin
October 1, 2010
Page 3
BPA's NOS. Subsequent to that, Wasatch Wind submitted two new Tranmission Service
Requests to Idaho Power, as of August 18, and has renewed its efforts with BPA.
Delay Default Liquidated Damages Seturity Provision
The other item that I need to raise at this time is that of a delay default liquidated damages
securty provision. Wasatch Wind understands that Idaho Power has recently begun requiring
delay default liquidated damages security provisions in PURP A PPAs whereby the QF must post
a delay security of $45/kw of naeplate capacity for the project, which sum Idaho Power would
retain as liquidated damages in the event the QF fails to achieve the PPA's online date. For this
21 MW project, such a provision would require the QF to post $945,000.
In Order No. 30608, the Commission stated that delay default liquidated damages security must
be a "fair and reasonable offset ofa regulated utility's estimated increase in power supply costs
attrbutable to the PURP A supplier's failure to meet its contractually scheduled operation date."
The Commission's statement is consistent with Idaho law, which clearly prohibits use of
liquidated damages provisions when damages are easily estimated, or when such provisions are
puntive or designed to deter a breach of the contract. See Magic Valley Truck Brokers, Inc. v.
Meyer, 133 Idaho 110,117,982 P.2d 945, 952 (Ct. App. 1999); I.C. § 28-2-718(1). Idao
Power's actual damages caused by a QF's delay in achieving its online date would not be
diffcult to calculate, and the amount of $45/kw is far in excess of the costs of replacement power
or administrative expenses Idaho Power may incur. A $45/kw liquidated damges clause is
simply not legal in Idaho and would be rejected by Idaho cours. And requiring a QF to post an
unreasonably high delay default security frstrates PURPA's madatory purhase provisions.
Wasatch Wind wil not agree to a $45/kw delay security, unless the Commission orders that
amount is reasonable. Wasatch Wind intends to obligate itself at this time only to a PPA
requiring it to post no delay default securty amount, or to any amount deemed reasonable by the
Commission if Idaho Power insists on a provision requiring Wasatch to post a delay default
liquidated damages security.
Project Information
For the remaider of ths letter, I wil provide detailed infonnation regarding the Grouse Creek
Wind Park II, avaiable to you in one location for your convenience in completing the requested
standad PPA. Please complete a stadard PPA for Wastch Wind according to the infonnation
provided below. Ifwe ar unable to resolve any remaiing disaeement regarding the timing of the
interconnection/transmission applications or the delay default liquidated damages security
provisions, Wasatch Wind requests that you provide a PPA containing all undisputed tenns and
conditions, and that Idaho Power and the QF proceed to the Commission for a detennination as
to any disputed tenns. For any such disputed terms, Wasatch intends at this time to obligate
itselfto a PPA containing the tenns that the Commission ultimately concludes to be just and
reasnable.
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 12 of 16
Mr. Allphin
October 1,2010
Page 4
(a) abilty to obtain QF status
As a wind generating facilty utilzing a renewable fuel soure, the facilty will be a qualifYing
facility as defined in 18 C.P.R. § 292.203(a) and (c).
(b) desig capacit (MW)
This project will have a nameplate ratin of 2 1 MW, but under normal operating conditions in any
given month Wasatch Wind's proposed design of the project wil generate less than 10 aMW.
Specifically, Wasatch Wind will design the facility in such a way tht the turbines switch to
maintenance mode, and thus cease generating electricity to be delivered to Idao Power, if
production levels for a given month reach the 10 aMW cap. The engineering team wil do so by
adding some "logic" to the metering equipment. Once the output has reached a predetermned
level, the metering equipment will communicate with the control equipment and put the turbines
into maintenance mode. Monthly generation will not exceed the i 0 aMW cap, and Wasatch
Wind wil provide appropriate engineering certification of this fact. Therefore, in accordance
with Commission Order No. 29632, Wasatch Wind agees to a provision in the PPA providing tht
a cap on the maximum monthly generation that qualifies for published rates at the total
number of hours in the month multiplied by 10 MW.
The Commission has approved PURPA PPAs for projects with design specifications such as this in
the past. For example, in Order No. 30028, the Commission approved a PPA at the published rates
for a cogeneration facilty with a design capacity of over 10 MW because it would only generate 10
aMW in normal and/or average conditions based on data supplied by the QF. Likewise, Wasatch
Wind proposes to design the Grouse Creek Wind Park II facilty as a QF that will deliver less than
10 aMW, and will provide appropriate certification to Idaho Power of that design specification.
(c) generation technology and other related technology applicable to the site
The facilty will be a wind generation project consisting of3.0 MW machines, which will be Vest
V - i 12 machines.
(d) proposed site location
The facilty will be located in Box Elder County, near Lyn, Utah. More specifically, Wasatch
Wind provides the following legal description of the real property assoiated with Grouse Creek
Wind Park II:
TOWNSHIP 14 NORTH, RANGE i 7 WEST OF THE SALT LAKE BASE MERIDIAN,
all of which is located in Box Elder County Utah, containing approximately 730.79 acres,
more or less.
Parcel 08-01 7-0047 SE/4 of Section 21, Township 14 Nort Range 17 West, SLB&M. containing 160
acres more or less.
Attchment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 13 of 16
Mr. Allphin
October 1,2010
Page 5
Parcel 08-017-0070 AU of Section 28 Township 14 North Range 17 West, SLB&M. Less E/2ofE/2
& SW/4 ofSW/4 containing 440 acres more or less.
Parcel 08-017-0098 Part of the East half of the Northeast Quarter of Section 28, T 14 N, R 17W,
SLB&M, Box Elder County, Uta.
DESCRIPTION: Beginning at the Northwest Corner of the Northeast Quarter of
the Norteast Quarter of Section 28, T 14 N, R 17 W, SLB&M, Box Elder
County, Utah; thence south 0 degrees 07'42/l East along the West line ofthe
Northeast Quarter of the Northeast Quarer for 393.39 feet to the point of
beginning,
Thence South 28 degres 40'53" East for 510.66 feet to a Y2 inch rebar; thence
South 28 degrees 40'53" East for 1643.06 feet to an Y2 rehar; thence South 57
degrees 30'39/l West for 1218.68 feet to a point on the West line of the East half
of the Northeast Quarter; thence North 0 degrees 07'42" West along the West
line of the East Half ofthe Norteast Quarter for 2544.8 feet to the point of
beginning, containing 24.59 acres more or less
SAVE AND EXCEPT the following-described parcel: (CONT. ..)
DESCRIPTION: Beginning at the Nortwest Corner of the Northeast Quarer of
the Northeast Quaer of Section 28, T 14 N, R 17W, SLB&M, Box Elder
County, Utah; thence South 0 degrees 07'42" East along the West line of the
Northeast Quarter of the Northeast Quarer for 393.39 feet to the point of
beginning; thence South 28 degrees 40'53" East for 510.66 feetto a Vi inch rebar;
thence South 28 degres 40'53/l East for 557.15 feetto the South line ofthe
Northeast Quarter of the Northeast Quarter; thence North 89 degrees 37'00"
West for 510.40 feet to the West line ofthe Norteast Quarter of the Northeast
Quarter; thence North 00 degrees 07'42" West for 933.39 feet to the point of
beginning.
Parcel 08-017-0099 DESCRIPTION: Beginning at the Northwest Comer of the Northeast Quarter of
the Northeast Quarter of Section 28, T 14 N, R 17W, SLB&M, Box Elder
County, Utah; thence South 0 degrees 07'42" East along the West line of the
Northeast Quarer of the Norteast Quarer for 393.39 feet to the point of
beginning; thence South 28 degrees 40'53" East for 510.66 feet to a Y2 inch rebar;
thence South 28 degrees 40'53" East for 557.1 5 feet to the South line ofthe
Northeast Quarter of the Northeast Quarter; thence North 89 degrees 37'00"
West for 510.40 feet to the West line of the Norteast Quarter of the Northeast
Quarter; thence North 00 degrees 07'42" West for 933.39 feet to the point of
beginning, containing 5.47 acres more or less.
Parcel 08-017-0102 Par of Section 27 and 28. Township 14 North, Range 17 West, Salt Lake Base
and Meridian, descrided as follows
Beginning at the East Quarter Comer of Section 28, Township 14 North. Range
17 West, Salt Lake Base and Meridian; Thence South 36°14'05" East 1661.99
Feet to a point on the South line of the Northwest Quarter of Southwest Quarer
of said Section 27; thence North 89°59'54" West 974.82 feet to the Northeast
Corner of Southeast Quartr of Southeast Quarer of said Section 28; thence
South 00°19'25" East 1340.56 feet to the Southeast Quarter of said section 28;
thence North 89°59'54" West 1329.58 feet to the Southwest Comer of the
Southeast quarter of Southeast Quarter of said Section 28; thence North
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 14 of 16
Mr. Allphin
October 1,2010
Page 6
57°30138" East 1218.7 feet on the East Corner of parcel described as Tax ID No.
08-017-0098; thence South 09°00'00" east 289.68 feet to the East line of said
Section 28; thence south 00° 19'25" feet the point of beginning. Containing
100.73 acres more or less.
(e) schedule of monthly power deliveries
The table below sets fort the expected schedule of monthly power production in a typical year.
These production estimates do not account for station use or for line losses occurrng between
the QF and the point of delivery to Idaho Power's system:
Month
January
Februar
Marh
April
May
June
July
August
September
October
November
December
Total
MWh
6,178.9
6,720.0
7,440.0
5,614.1
4,547.0
640.5
1,524.5
2,513.4
3,566.3
6,306.5
6,686.3
6,941.4
58,679
(:I motive force or fuel plan
The motive force is wind.
(g) proposed online date and other signifcant dates require to complete the milestones
Constrction of the facilty and other necessar infastrctu is scheduled to be complete and ready
for operation on Deceber 31, 2012. The proposed online date to commence operation for
electricity sales to Idaho Power is December 31, 2012.
(h) proposed contract term and pricing provisions
Wasatch Wind requests a 20-year contract at the non-levelized rates in the avoided cost rate
schedule on file today with the Idaho Public Utilties Commission (errata to Idaho Public Utilities
Commission Order No. 30125).
Attchment No. 7
Case Nos. IPC-E-1Q-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 15 of 16
Mr. Allphin
October 1, 2010
Page 7
(i) statu of intereonnection or trnsmission arrngements
Wasch Wind is aranging for an agrement to have BPA deliver the output to Idaho Power's
system at the Minidoka substation. Wasatch Wind submittd a tranmission capacity application
questionnre for Grouse Creek Wind Park II to Idaho Power on Augus 19, 20 i 0, and ha requested
that Idao Power intiate any necssar processing of internnecion and tranission stuies or
agreements for the project.
(j) point of delivery or interconnection
Wasatch Wind will deliver the output (net of station us and losses) to Idaho Power at the Minidoka
substation.
Conclusion
I hope tht ths letter ha clarfied Wastch Wind's position regarding this request, and will be
useful in your processing ofWash Win's PURA prject. Pleas contact me with any
questions, or with requests for any additiona infomition necessar to process ths request.
Very trly yours,P_J.t:.~
Attrney for Wasatch Wind
cc: Donovan Walker, Attorney for Idaho Power (hand delivery and electronic mail)
Chrstine Mikell, Wasatch Wind (electronic mail)
Enclosure
Attachment No. 7
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 16 of 16
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO.8
.chln, RandY
From:
Sent:
To:
Cc:
Subjec:
Attchments:
Allphin, Randy
Monday, November 01, 2010 2:06 PM
'Peter Richardson'
Walker, Donovan
Wasatch wind and SWeeney ranch documents
Wasatch wind cover letter. pdf; Wasatch wind draft agreement template 11-1-201 a.pdf
Tracking:Recpient
'petei Richn'
Walker, Donvan
Read
Read: 11/1/20102:09 PM
Peter,
Attached is a letter addressing the various Wasatch wind requests and also a draft agreement.
I left you a phone message, if I dO not hear back from by you by 3 pm I wil put the originals in U SMaiL.
Randy
1 Attchment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of 74
ø_.
An IDACORP Company
November 1,2010
Randy C. Allphin
Senior Energy Contrct Coordinator
Wasatch Wind
c/o Peter Richardon
5 i 5 North 27th Street
P.O. Box 7218
Boise, il 83702
Original: U SMail
E-mail copy:Peter~richardsonandolea.com
Re: Wasatch Wind - Grouse Creek Wind Park LLC, Grouse Creek Wind Park II LLC, Sweeney Ranch
Wind Park I and Sweeney Ranch Wind Park II.
Dear Mr. Richardson:
Idaho Power has received your letters of October 1 and October 28, 2010, regarding Grouse
Creek Wind Park and Grouse Creek Wind Park II, as well as your October 20, 2010, letter
regarding Sweeney Ranch Wind Park I and II.
Your letters are obvious attempts to establish a writing that evidences: 1) your client's
projects are ready wiling and able at this time to sign PURPA FESAs and 2) that the reason
your client does not have executed PURPA FESAs at this time is somehow due to some
action or inaction of Idaho Power. Neither is correct.
Your letters purport to "agree" to the "standard" tenns and conditions contained in the Idaho
Winds LLC FESA from Case No. IPC-E-09-25. There are three primary problems with your
assertion. First, as you are well aware, the Idaho Winds FESA contains delay damage and
security provisions that your same letter objects to, and does not agree with. Second, as you
are also aware, the Idaho Winds FESA does not contain the most recent and up-to-date
"standard" tenns and conditions of a PURPA FESA that have been approved by the
Commission and third, all of these proposed projects are not within the Idaho Power service
terrtory, thus as the FESA you referenced is for a project within the Idaho Power serice
terrtory it would not be applicable without the changes to accommodate the off system
projects you are proposing. As you are aware from your representation of other PURP A
clients, Idaho Power wil not agree to a PURP A FESA that does not contain the $45 per kW
nameplate rating security and damage provisions. Delay liquidated damages provisions have
p, 0, Box 70 (83707)
1221 W" Idaho St,
AttachM~fi'tIRi~fW
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of 74
been included in PURPA FESA contracts approved by the Commission since at least 2007.
See, Case No. IPC-E-06-36. In addition, one of the tirst Commission approved FESAs to
contain terms requiring the project to post liquid security was the FESA for Cassia Giilch
Wind Park and Tuana Springs Energy, Case No. IPC-E-09-24. In thut case the Commission
approved provisions requiring the posting of liquid security in the amount of $20 per kW of
project cap acíty , The Commission considered and approved provisions providing for the
posting of liquid security in the amount of $20 per kW of project capacity in at least four
other PURPA FESAs. See, Case No. IPC-E-09-18, (PC-E-09-19, (PC-E-0920, (PC-E-09-25.
The Commission has since analyzed and approved provisions requiring the posting of liquid
security in the ~U110unt of $45 per kW of nameplate capacity in at least seven difterent
PURPA FESAs, some of which have been belonged to your clients. See, Case No. IPC-E-
10-02, IPC-E-IO-05, IPC-E-lO-15, IPC-E-1O-l6, IPC-E-IO-17, IPC-E-lO-18, IPC-E-IO-19.
In reviewing the infoimation you have provided in your letter regarding the interconnection
and transmission request process, there appears to be a misunderstanding with regard to the
infonnation that Idaho Power has provided. In none of the information provided or
conversations with Idaho Power has Idaho Power ever stated that only one of the projects
Transmission Service Request ("TSR") could be processed at a single time. Instead, the
discussions were about the fact that TSR' s are processed in the order they are received by the
transmission group. And if there is limited transmission capacity on a path, the first TSR
filed may be accepted with little or no uPbJfade cost whereas the second TSR filed may
encounter network upgrade costs as a result of the first request being allocated the available
transmission capacity.
As all of these proposed projects are not within the Idaho Power service territory and wil not
be directly connecting to the Idaho Power electrical system it is required that each project
complete the interconnection process with the host utility and also secure firm transmission
capacity across all required transmission paths to deliver energy to a point of delivery on the
Idaho Power electrical system. The idaho Power TSR process discussed above is the process
to determine if there is transmission capacity available only on the Idaho Power electrical
system from the point of delivery to the Idaho Power customer loads.
Grouse Creek r iind II projects -
In the previously provided information the projects have indicated that an Interconnection
Facility study has been completed for each project with the host utility and a finn
transmission reservation is not in place on the BP A system, however it appears the
projects have been working dilgently to secure transmission on the BPA system.
Prcvíously, Idaho Power had not fied TSRs for these projects due to the fàct that the
projects had not committed to the actual size and contìguration of the projects or the
sequencing they desired for the filing of these TSRs. In the letter dated October 1, 2010,
the project has requested the Grouse Creek Wind Park I be resized to 21 MW vs the
previous information that the project be sized at 30 MW. Based on this latest
information, Idaho Power wil fie TSR's for Grouse Creek Wind Park I for a nameplate
rating of 2 i MW and Grouse Creek Wind Park n for a nameplate rating of 21 MW - both
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 3 of 74
to deliver energy to the Idaho Power Minidoka substation making use of firm
transmission capacity on the BPA trsmission system.
Sweeny Ranch Wind Park I and II -
Your letter dated October 20, 20 lOis the first information you have provided to Idaho
Power in regards to these projects. In order to continue through the transmission and
FESA process a "Letter of Understanding" and the information requested within that
letter wil need to be completed and returned to Idaho Power. A Letter of Understanding
for each of these project has been included with this letter.
Prior to Idaho Power filing a TSR for these projects, the projects wil need to demonstrate
that, at minimum, an acceptable feasibilty study for interconnection with the host utilty
has been completed and provide evidence that firm transmission is available from all
required transmission providers to move the project's energy from the point of
interconnection to the Point of Delivery on Idaho Power's electrical system.
Thank you for providing the additional "detailed" information about your client's projects
that you have requested Idaho Power insert into the "standard" FESA for Wasatch Wind.
However, from your past dealings with the Company you are aware that this type of
information provided by the project developer about their project is typically inserted by the
project developer, and not by Idaho Power. Enclosed please find a generic draft PURPA
Wind agreement (no specific project information included) that contains the most recent and
up-to-date ..standard" terms and conditions that have been approved by the Commission and
the off system requirements. Please fill in the appropriate project specific factual information
required and return to Idaho Power. Idaho Power wil then generate a final, executable copy
for signatures.
If you have any questions please do not hesitate to contact me at (208) 388-2614 or
rallphintiidahopower. com.
Sincerely,ßf.~.
Randy C. Allphin
Senior Energy Contract Coordinator
cc: Donovan Walker
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 4 of 74
~1lJii.PO~
An IOACORP Company
November 1, 2010
Randy C. Allphin
Sr. Energy Contract Coordinator
Tel: (208) 388-2614
rallphinÚÙidabopwercom
Sweeney Ranch Wind Park I
c/o Peter Richardson
515 North 2ih Street
P.O. Box 7218
Boise, ID 83702
Ongil: U SMail
E-mail copy:Peter~richardsonandolear.com
RE: Letter of Understanding
Sweeney Ranch Wind Park I - Proposed Wind Generation Project
Mr. Richardson,
Summarized below is a bnef outline of the purchase power agreement, interconnection process
and transmission capacity requirements for your proposed generation projec.
Purchase Power Agreement
The project you have descnbed appears to be eligible for a purchase power agreement under the
guidelines for a Qualifying Facilty as defined by the Public Utilties Regulatory Policies Act of 1978
(PURPA). At the time you are ready to proceed with a purchase power agreement for this project,
Idaho Power wil preare a purchase power agreement that complies with the currnt rules and
regulations that govern these PUR A agreements, any draft purchase power agrments previously
provided to you for review must be updated to include currt rules and regulations.
POBox 70 Boise. Idaho 83707 1221 W Idaho St. Boise Idaho 83702
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 50f74
Prior to Idaho Power executing a purchase power agreement it wil be required that you have:
1.) Provided documentation that substantiates that the project has fied for interconnection
with the host utility and is in compliance with any payments and/or other
requirements specified in the interconnection process for this project and;
2.) Received and accepted an interconnection feasibility study for this project and;
3,) Acquired or provide evidence that finn transmission capacity is available from all
transmission providers required to move the energy from your projects point of
interconnection to an acceptable poilit of delivery on the Idaho Power electrical
system.
4,) Returned a signed copy of this letter of understanding and all of the required
information to enable Idaho Power to fie an application requesting transmission
capacity on the Idaho Power transmission system for this project. Completion of the
enclosed Transmission Capacity Application Questionnaire wil provide the majority
of this infonnation and;
5.) Confimiation that the results of the initial Idao Power transmission capacity
application are known and the project accepts these results and intends to continue
with the development of the project including. if applicable, execution of a Network
Resource Integration Study Agreement in the form enclosed herein.
Note: As your project appears to not be located in the Idaho Power service territory
and in addition wil not be physically connected to the Idaho Power electrical
system, the interconnection otthis project must comply with the host utility's
interconnection process, the project must secure firm transmission capacity
for the full nameplate rating of the project for the full tenn of the purchase
power agreement tì'om all required transmission providers and also the
project shall be responsible for all transmission costs on the Idaho Power
electrical system to move the project's energy from the specified point of
delivery to Idaho Power customer loads.
Interconnection and Transmission Capacity
Your project wil be responsible tor all costs of physically interconnecting the project to the host
utilty electrical system, acquiring firm transmission capacity on all transmission providers electrical
systems and any Idaho Power electrical system costs associated with acquiring adequate firm
transmission capacity on the Idaho Power transmission system to enable the project's energy to be
delivered to Idaho Power customers,
Pagel of 5
POBox 70 Boise, Idaho 83707 1221 W Idaho St. Boise, Idaho il3702
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 6 of 74
Interconnection
Your project wil be required to complete the interconnection process and execute a
Generation Interconnection Agreement ("GIN') with the host utility.
Transmission Capacity
To sell your project's energy to fdao Power, your project must be designated as a
Network Resource ("DNR").
In order for this project to achieve DNR status -
The project must secur firm transmission capacity for the full nameplate capacity of
the project for a period of time not less than the term of any purchase agreement with
Idaho Power from all transmission providers between the project's point of
interconnection and the designated point of delivery on the Idaho Power electrical
system.
In addition - Idaho Power is required to make a transmission request (complete and
fie an application) and be granted finn transmission capacity from the Idao Power
delivery business unit ("Delivery") to move your project's energy from the designated
point of delivery on the Idaho Power electrical system to Idaho Power custoiners. In
accordance with various rules and regulations, the project must be granted DNR status
no later than 60 days prior to the project delivering any energy to Idaho Power.
Idaho Power wil begin this firm transmission capacity application process
(transmission capacíty on thc Idaho Power electrical system) only after the project has
returned a signcd copy of this letter of understanding, evidence of the interconnection
status, evidence of the required transmission agreements and all of the information
required for Idaho Power to me tlús application (see attached Transmission Capacity
Application Questionnaire).
After fiing a complete flrin transmission capacity application with Delivery, Idaho
Power will receive notitïcatìon back from Delivery within 30 days that: (a) adequate
transmission capacity is available for this project without the need to construct upgrades;
or (b) a transmission capacity system impact study is required to determine the available
transmission capacity and/or required upgrades; or (c) a statement of the required
transmission up¡,rrades and the associated costs. Idaho Power wil notify the project of
this response to the transmission capacity application in a timely manner after the
response is received from Delivery.
If the response from Delivery is as specified in item (a) (transmission capacity is
available), the project will be required to execute a ¡mrchase power agreement with
Idaho Power within 30 days in order to retain this transmission capacity reservation.
If the response from Delivery is as specified in items (b) or (c) (studies required
and/or upgrades required), the project wil be required to execute a Network Resource
Integration Study Agreement (sample copy attached for your intòrinatíon) and submit all
Page 3 ot5
POBox 70 Boise. Id,iho 83707 122\ W Idaho St. 8()ise, Idaho 83702
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-2
Allphin Affdavit, IPC
Page 7 of 74
required deposits or fees wit1n 15 days after reeiving notification of this requirement
in order for Idaho Power to continue the trnsmission capacity request. This Network
Resource Integration Study Agreement wil speify that the project wil be responsible
for costs incurred by Idaho Power to perform any require studies. If, after the studies
are concluded the project wishes to continue the pursuit of transmission capacity, the
project wil also be responsible for all transmission system upgrade costs identified
within the studies. The fees and costs wil be in the form of both initial deposits as well
as actual costs. If at any time after executing the Netork Resource Integration Study
Agreement the project does not pay any required fees. or elects to stop the transmission
study or upgmde process, the project shall be responsible for all costs incurred by Idaho
Power in performing the studies or upgrades up to the point of termination of the
Network Resource Integration Study Agreement.
Upon successful completion of the above described transmission capacity upgrade
process, a transmission capacity reservation on the Idaho Power electrical system wil
exist tor this project. However, in order to finalize this transmission capacity
reservation, a purchase power agreement with Idaho Power must be executed no later
than 30 days after the transmission capacity upgrades are completed, If the purchase
power agreement is not executed by this deadline, the transmission capacity reseration
wil be released and this process will have to be repeated if the project later requests
transmission capacity.
As noted earlier, this transmission capacity acquisition and associated Network
Resource designation must be completed, at the minimum, 60 days prior to the project
delivering any energy to Idaho Power. In addition, the project must provide routine
updates to Idaho Power of the expected online date of the generation project to ensure
Idaho Power is capable of accepting the energy from the project on the actual date the
project comes online.
Please return all required information to:
Idaho Power Company
Attn: Randy C. Allphin
POBox 70
Boise, lD 83707
E-mail: rallphin(cyidahopower.com
P~gê4 otS
POBox. 70 Boise, Idaho 83707 1221 W IdaJio St. Boise, r.\¡iho 83702
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-1Q-62
Allphin Affdavit, IPC
Page 8 of 74
Sincerely,
a,,~.
Randy C Allphin
Idaho Power Company
,2010Understood and accepted this _ day of
Signature
Print Name
Title
P 0 Bo" 70 Boise, Idaho 83707 1221 W Idaho St. Boise, Idaho 83702
Attachment No.8
Case Nos.IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 9 of 74
~IDA~POR~
An IOACOliP company
November 1,2010
Randy C. Allphin
Sr. Energy Contract Coordinator
Tel: (208) 388.2614
rallphintáidahopower.com
Sweeney Ranch Wind Park II
c/o Peter Richardson
515 North 27th Stree
P.O. Box 7218
Boise, ID 83702
Original: U SMail
E-mail copy:Peterrichardsonandoleary.com
RE: Letter of Understanding
Sweeney Ranch Wind Park II - Proposed Wind Generation Project
Mr. Richardson,
Summarized below is a brief outline of the purchase power agreement, interconnection process
and transmission capacity requirments for your proposed generation project.
Purchase Power Agreement
The project you have described appears to be eligible for a purchase power agreement under the
guidelines for a Qualifying Facility as defined by the Public Utilties Regulatory Policies Act of i 978
(PURP A). At the time you are ready to proceed with a purchase power agreement for this projec,
Idaho Power wil prepare a purchase power agrement that complies with the current rules and
regulations that govern these PUR A agreements, any draft purchase power agreements previously
provided to you for review must be updated to include currnt rules and regulations.
POBox 70 Boise, Idaho 83707 1221 W Idaho St. Boise Idaho 83702
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 10 of 74
Prior to Idaho Power executing a purchase power agreement it wil be required that you have:
1.) Provided documentation that substantiates that the project has fied for interconnection
with the host utilty and is in compliance with any payments and/or other
requirements specified in the interconnection process for this project and;
2.) Received and accepted an interconnection feasibility study for this project and;
3.) Acquired or provide evidence that finn transmission capacity is available from all
transmission providers required to move the energy from your projects point of
interconnection to an acceptable point of delivery on the Idaho Power electrical
system.
4.) Returned a signed copy of this letter of understanding and all of the required
informatioii to enable Idaho Power to tile an application requesting transmission
capacity on the Idaho Power transmission system for this project. Completion of the
enclosed Transmìssion Capacity Application Questionnaire wil provide the majority
of this information and;
5.) Confinnation that the results of the initial Idaho Power transmission capacity
application are known and the project accepts these results and intends to continue
with the development of the project including, if applicable, execution of a Network
Resource Integration Study Agreement in the fonn enclosed herein.
Note: As your project appears to not be located in the Idaho Power service territory
and in addition wí1 not be physically connected to the Idaho Power electrical
system, the interconnection of this project must comply with the host utility's
interconnection process, the project must secure finn transmission capacity
for the full nameplate rating of the project for the full ten of the purchase
power agreement from all required transmission providers and also the
project shall be responsible for all trasmission costs on the Idaho Power
electrical system to move the project's energy from the specified point of
delivery to Idaho Power customer loads.
Interconnection and Transmission Capacity
Your project will be responsible for all costs of physically interconnecting the project to the host
utilty electrical system, acquiring finn transmission capacity on all transmission providers electrical
systems and any Idaho Power electrical system costs associated with acquiring adequate firm
transmission capacity on the Idaho Power transmission system to enable the project's energy to be
delivered to Idaho Power customers.
Page ot's
POBox 70 Boise, Idaho 83707 122! W Idaho St. Boise, Idaho 83702
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 11 of 74
Interconnection
Your project wíl be required to complete the interconnection process and execute a
Generation Intercoriection Agreement ("GIA") with the host utilty.
Transmission Capacity
To sell your project's energy to Idaho Power, your project must be designated as a
Nctwork Resource ("DNR").
In order for this project to achieve DNR status -
The project must secure firm transmission capacity for the full nameplate capacity of
the project for a period of time not less than the term of any purchase agreement with
Idaho Power from all transmission providers between the project's point of
interconnection and the designated point of delivery on the Idaho Power electrical
system.
In addition - Idaho Power is required to make a transmission request (complete and
fie an applícation) and be granted firm transmission capacity from the Idaho Power
delivery business unit ("Delivery") to move your project's energy from the designated
point of delivery on the Idaho Power electrical system to Idaho Power customers. In
accordance with various rules and regulations, the project must be granted DNR status
no later than 60 days prior to the project delivering any energy to Idaho Power.
Idaho Power wil begin this firm transmission capacity application process
(transmission capacity on the Idaho Power electrical system) only after the project has
returned a signed copy of this letter of understanding, evidence of the interconnection
status, evidence of the required transmission agreements and all of the information
required for Idaho Power to fie this application (see attached Transmission Capacity
Application Questionnaire).
After fiing a complete firm transmission capacity application with Delivery, Idaho
Power will receive notification back from Delivery within 30 days that: (a) adequate
transmission capacity is available for this project without the need to construct upgrades;
or (b) a traítsmission capacity system impact study is required to determine the available
transmission capacity and/or required upgrades; or (c) a statement of the required
transmission upgrades and the associated costs. Idaho Power wil notify the project of
this response to the transmission capacity application in a timely manner after thc
response is received from Delivery.
If the response from Delivery is as specifed in item (a) (transmission capacity is
available), the project wil be required to execute a purchase power agreement with
Idaho Power within 30 days in order to retain this transmission capacity reservation.
If the response from Delivery is as specified in items (b) or (c) (studies required
amVor upgrades required), the project wil be required to execute a Network Resource
Integratíon Study Agreement (sample copy attached for your information) and submit all
Pftge 3 of 5
POBox 70 Boise, Idaho 83707 1221 W IdahoSt. Boise, ¡daho83702
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 12 of 74
required deposits or fees within 15 days after receiving notification of this requirement
in order for Idaho Power to continue the transmission capacity request. This Network
Resource Integration Study Agreement wil specify that the project will be responsible
for costs incurrd by Idaho Power to perfonn any required studies. It: aftr the studies
are concluded the project wishes to continue the pursuit of transmission capacity, the
project wíl also be responsible for all transmission system upgrade costs identified
within the studies, The fees and costs wil be in the form of both initial deposits as well
as actual costs. If at any time after executing the Network Resource Integration Study
Agreement the project does not pay any required fees, or elects to stop the transmission
study or upgrade process, the project shall be l'esponsible for all costs incurred by Idaho
Power in performing the studies or upgrdes up to the point of terination of the
Network Resource Integration Study Agreement.
Upon successful completion of the above described transmission capacity upgrade
process, a transmission capacity reservation on the Idaho Power electrical system wil
exist tor this project. However, in order to finalize this transmission capacity
reservation, a purchase power agrement with Idaho Power must be executed no later
than 30 days after the transmission capacity upgrades are completed. If the purchase
power agreement is not executed by this deadline, the transmission capacity reservtion
will be released and this process wil have to be repeated if the project later requests
transmission capacity.
As noted earlier, this transmission capacity acquisition and associated Network
Resource designation must be completed, at the minimum, 60 days prior to the project
delivering any energy to Idaho Power. In addition, the project must provide routine
updates to Idaho Power of the expected online date of the generation project to ensure
Idaho Power is capable of accepting the energy from the project on the actual date the
project comes online.
Please return all required information to:
Idaho Power Company
Attn: Randy C. Allphin
POBox 70
Boise, ID 83707
E-mail: rallphin(?idahopower.com
"
!Jage4 of5
POBox 70 Boise, Idaho 83707 1221 W Idaho St. Boise, Idaho 83702
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 13 of 74
Understood and accepted this _ day
Signature
Print Name
Title
Sincerely,
Ap.#'
Rady C Allphin
Idaho Power Company
2010
POBox 70 Boise, Idaho 83707 1221 W Idaho St. Boise, Idaho 83702
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 14 of 74
NETWORK RESOURCE INTEGRATION STUDY AGREEMENT
THIS Agreement is made and entered into this _ day of 20_
between Idaho Power Company ("Idaho Powet' or "Company") through its Power
Supply business unit ("Power Supply") and
("Developer'). Power Supply and Developer may hereinafter be referred to individually
as "Party" or collectively as "Parties."
RECITALS:
A. Developer has advised Power Supply that it intends to develop a
generating facilty that would meet the criteria for a Qualifying Facilty (OIQP') as that
term is defined in the Public Utilty Regulatory Policies Act of 1978. Developer desires
to sell the energy to be generated by the OF to Idaho- Power as a non-interruptible
designated network resource ("DNR").
B. In order for the OF to be classified as a DNR and for Idaho Power to
purchase the energy to be generated by the OF on a firm basis, a network resource
integration system impact study ("SIS") must be performed by Idaho Power's delivery
business unit ("Delivery"). The SIS wil identify the need and associated costs for
Delivery to install facilties, including "upgrades" (as that term is defined in Idaho Power
Company's Schedule 72), to allow the OF to operate as a DNR and deliver firm energy
to the Company's load centers. The Federal Energy Regulatory Commission's rules
require that Power Supply make the request to Delivery to perform the SIS. Delivery
wil bil Power Supply for the costs incurred to perform the SiS.
NETORK RESOURCE INTEGRATION STUDY AGREEMENT - 1
Attchment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 15 of74
AGREEMENTS:
1. Developer hereby requests that Power Supply initiate the process for
Delivery to conduct a SiS for determining the cost of the OF's becoming a DNR for the
Company. Developer agrees to pay all charges associated with any analyses that
Delivery determines are reasonably necessary to evaluate the impact of the OF on
Idaho Power's transmission system.
2. In order for Power Supply to initiate ä SiS, Developer must submit the
estimated SiS cost of within fourteen (1'4~ days of the date of this
Agreement. This amount is based on Delivery's estimate of the actual cost of
performing the SiS, including appropriate loadingånd administrative and general
overheads. Should the scope of the SiS be changed: by Developer or further study be
necessitated due to reasons beyond the control of Delivèry, Power Supply wil advise
Developer of the revised charges, if any.
3. Upon receipt of this Agreemént~ executed by Developer, payment of the
amount specifed in paragraph 2, and all information required to enable Power Supply to
complete the necessary request, Power Supply wil submit the necessary request and
documentation to Delivery to commence the SiS. Subject to Developer's providing
requested information and making any requested supplemental payments in a timely
manner, Delivery will perform the SiS with due diligence. Power Supply wil respond to
Developer's reasonable requests for information regarding an estimated completion
date for the SiS and, if necessary, with an explanation of why additional time is required
to complete the SiS.
NETWORK RESOURCE INTEGRATION STUDY AGREEMENT. 2
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 16 of 74
4. FolloWing eompletiol'of the SiS, a copy of the completed SiS shall be
provided to Developer. Power Supply and Developer shall then reconolle the payments
made for the SiS and "tre-up" any over or under payments rte by Developer. The
total charge to Developer for the SiS wil not exceed the acual cost of the SiS as bille
by Delivery to Power Supply.
IN WITNESS WHEREOF, the PartIes have caused this Agreement to be
executed effective on the flrst day wren above.
-IDAHO POWEïfCOMPANY
By:
Title:
DEVELOPER
By:
Title:
NETWORK RESOURCE INTEGRATION STUDY AGREEMENT - ;3
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-2
Allphin Affdavit, IPC
Page 17 of 74
611.
M IDA C6m¡V
Transmission Capacit Application Questionnaire
This list is the known information requirements as of the date of the letter transmiting this request. ff additonal information
is required, Idaho Power will promptly notffy the project developer of the additionsllnforation reuirements.
A. Project Name
B. Project Location
C. Project Developer
Name
Address
City I State I Zip
Phone Number
E-mail
D. Host utiity Interconnection "QueD reference number (if not known. please contact the host
utility Interconnection group)
E. Evidence of the Project's good standing status in the host utilty Interconnection Process
F. Copy of the host utilty Interconnection feasibility study and a statement from the project that
the project has accepted the results of the interconnection feasibilty study and is continuing
the process of interconnecting and developing the generation project.
G. Maximum Capacity (MW)
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 18 of 74
H. Beginning day and time of energy deliveries
Oay (mm/ddlyy)
I. Ending day and time of energy deliveries
Day (mmfddJyyyy)
'lliè
J. VAR capabìlty(both leading ând iagging) ofalf generators
K. li:enfificaool1 of the contrl aræ(s) from which the energy wilorigtnate
L. Listahy periods of restricted operations throughout the year
M. Maintenance schedule
N. Minimum loading level of each generation unit
O. Normal operating level of eaGh generation unìt
P. Any must.run generation unit designations reuired for sysem ,reUabilty or contractual reason
Pegc2 \.l3
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 19 of 74
Q. Approximate variable generation cost ($/MWh) Not - this wil bf estimated energy pricing from a potentlaf
purchase power agrement that this project may bf eligible for.
R. If the generation resource is to be located in the Idaho Power Balancing Authority Area and if
only a portion of the resource output Is to be designated as a Network Resource, then explain
arrangements governing sale and delivery of additional output to third parties.
S. If the project is not directly interconnected to the Idaho Power transmission system, provide
the transmission provider(s) name, Point of Receipt, Point of Delivery and the transmission
reservation number for all of the transmission providers required to deliver the project's energy
to Idaho Power.
Transmission Provlder(s) Name
Point of Receipt
Point of
Transmission Reservation Number(s)
T, If the project is directly interconnected to the Idaho Power transmission system, provide the
Point of Receipt, physical location and voltage.
Point of Receipt__
Physical
Voltage
U. Is the project committed to execute a purchase power agreement wih Idaho Power upon a
favorable resolution of the identified interconnection and transmission costs?
Yes 0 No 0
V. Is any portion of the maximum capacity identified for this project committed to any other part?
Yes 0 No 0
Signature Date
PBlçloO
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 20 of 74
Arcle
I
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
11
18
19
20
21
22
23
24
25
26
27
28
29
Draft: For Discussion Purposes Only
FIR ENRGY SALES AGREEMENT
BETW
IDAHO POWE COMPAN
AN
TABLE OF CONT
TITLE
Detiøns
No Relîaceon Idao Power
Wares
Conditi to Accta of En
Ter and uption Date
Puhas and Sale orNet Ener
Puhas Prce and.Metod øf Payment
Envionmental Attbutes
TräStssion Agrent
Recrd
Opons
ReliåbilityManageent Sys
Indeinification and Ince
ForeMaj~
Liability; Decation
Sevl Obligations
Waier
Choice of Laws and Venue
DiSputesand Default
Oovenental AuthoritiQU
Comisson Order
Succes$(t' and Asigns
Modifieaon
Taxes
Notice
Additional Tem and Conditions
Severbilty
COunters
EïtitAgrent Signatu
Appdix A
AppendixB
AppendiC
Appdi 0
AppdixE
o
Dn: For Dùaidn PwIU Only
10/2812010
Attachment No. 8
Case Nos. IPC-E-1D-1 & IPC-E-1Q-62
Allphin Affdavit, IPC
Page 21 of74
Draft: For Discussion Purposes
FIR ENERGY SALES AGREEMENT
(10 aMW or Less)
Project Name:
Projec Number:
THIS AGREEMENT, ented into on this _ day of 2010 between
, an (Seller), and IDAHO POWER COMPAN, an
Idaho corporation (Idao Power), hereinafter sometimes refered to collectively as "Partes" or
individually as "Pary."
WITSSETH:
WHERES, Seller will design, constnct own, matain and opete an electrc generation
facilty; and
WHEREAS, Seller wishes to sell, and Idaho Power is willig to purchase, firm electrc energy
produced by the Seller's Facilty.
THEREFORE, hi consideration of the mutual covenants and agreements hereinafter set fort, the
Paries agree as follows:
ARTICLE I: DEFINITIONS
As used in ths Agreement and the appendices attached hereto, the following terms
shall have the following meanings:
1. "Availability Shortall Price" - The curent month's Mid-Columbia Market Energy Cost minus
the cuent month' s All Hour Energy Prce specified in pargraph 7.3 of this Agreement. If this
calculation results in a value less than 15.00 Milslwh the result shall be 15.00 Millslwh.
1
Draft: For Dj§cussion
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 22 of 74
Draft: For Discussion Purposes Only
1.2 "Business Days" - means any calendar day that is not a Saturday, a Sunday, or a NERC
recognized holiday.
1.3 "Calculated Net Energy Amount" - A monthly estimate, prepared and documented after the fact
by Seller, reviewed and accepted by the Buyer that is the calculated monthly maximum energy
deliveries (measured in Kwh) for each individual wind tubine, totaled for the Facility to
deterine the total energy that the Facilty could have delivered to the Trasmitting Entity for
delivery to Idaho Power durng that month based upon: (1) each wind turbines Nameplate
Capacity, (2) Suffcient Prme Mover available for use by each wind turbine durg the month,
(3) incidents of Force Majeure, (4) scheduled maintenance, or (5) incidents of Forced Outages
and less Losses and Station Use. If the duration of an event charactered as item 3, 4 or 5 above
(measured on each individual occurence and individual wind turbine) lasts for less tha 15
minutes, then the event wil not be considerd in this calculation. The Seller shall collect and
maintain actual data to support this calculation and shall keep this data for a miimum of 3 years.
1.4 "Commission" - The Idaho Public Utilities Coimnission.
1.5 "Contrct Yeat' - The peod commencing each calendar yea on the same calendar date as the
Operation Date and ending 364 days thereafter.
1.6 "Delay Liquidated Damages" - Damges payable to Idaho Power as calculated in paragraph 5.3,
5.4, 5.5 and 5.6.
1.7 "Delay Period" - All days past the Scheduled Operation Date until the Seller's Facilty achieves
the Operation Date.
1.8 "Delay Price" - The currnt month's Mid-Columbia Market Energy Cost minus the current
month's All Hours Energy Price specified in paragrph 7.3 of this Agreement. If this calculation
results in a value less than 0, the result of this calculation will be O.
1.9 "Designated Dispatch Facilty" - Idaho Power's Systems Operations Group, or any subsequent
group designated by Idaho Power.
2
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 23 of 74
Draft: For DiscussioiiPurposcs Only
1.10 "Effective Date" - The date stated in the opening paragrph of this Finn Energy Sales
Agreement representing the date upon which th Firm Energy Sales Agreement was fully
executed by both Partes.
i .11 "Facility" - That electric generation facility described in Appendix B of this Agreement.
i .12 "First Energy Date" - The day commencing at 00:01 hours, Mountain Time, following the day
that Seller has satisfied the requirements of Arcle N and the Seller begins deliverng energy to
Idaho Power's system at the Point of Delivery.
1.13 "Forced Outage" - a parial or total reduction of a) the Facility's capacity to produce and/or
deliver Net Energy to the Point of Delivery, orb) Idaho Power's ability to accept Net Energy at
the Point of Delivery for non-economic reasons, as a result ofIdaho Power or Facility: 1)
equipment failure which was not the result of negligence or lack of preventative maintenance or
2) responding to a transmiion provider curailment order or 3) unplaned preventative
maintenance to repair equipment that left unepaired, would result in failure of equipment prior
to the planed maintenance perod 4) planned maintenance or constrction of the Facility or
electrical lines required to sere this Facilty. The Parties shall make commercially reasonable
efforts to perform this unplanned preventative maintenance during perods of low wind
availabilty.
1.14 "Heavy Load Hours" - The daily hours beginning at 7:00 am, ending at 11 :00 pm Mountain
Time, (16 hours) excluding all hour on all Sundays, New Year Day, Memorial Day,
Independence Day, Labor Day, Thankgiving and Chrstmas.
1.15 "Idaho Power Electrcal System Control Area" or "Control Area" - The geographical area of
integrted transmission and generation controlled by Idaho Power for which Idaho Power is
responsible for scheduling interchanges with other control ars and balancing supply and
demand within the area. The Control Area may include physical locations and/or electrcal
systems not served or owned by Idaho Power, but which are dependent upon Idaho Power's
operation of its generation and transmission to balance supply and demand,
3
Draft: For Discussionlurposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 24 of 74
Draft: For Discussion Purposes Only
1.16 "Inadvertent Energy" - Electrc energy Seller does not intend to generate. Indvertent energy is
more particularly described in paragraph 7.5 of this Agreement.
1.17 "Initial Capacity Deterination" - The process by which Idaho Power confinn that under
normal or average design conditions the Facility will generte at no more than 10 average MW
per month and is therefore eligible to be paid the published rates in accordance with Commission
Order No. 29632.
1. i 8 "Light Load Hours" - The daily hours beginning at 1 i :00 pm, ending at 7:00 am Mountain Time
(8 hour), plus all other hours on all Sundays, New Years Day, Memorial Day, Indepndence
Day, Labor Day, Thasgivig and Chstmas.
1.19 "Losses" - The loss of electrcal energy expressed in kilowatt hour (kWh) occurng as a result
of the transformation and trsmission of energy between the point where the Facilty's energy is
metered and the point the Facility's energy is delivered to the Idaho Power electrcal system by
the Transmitting Entity. The loss calculation formula will be as spcified in Appendix B of this
Agreement.
1.20 "Market Energy Reference Price" - Eighty-five percent (85%) of the Mid-Columbia Market
Energy Cost.
1.21 "Materal Breach" - A Default (paragraph 19.2.1) subject to paragraph 19.2.2.
1.22 "Maximum Capacity Amount" - The maximum capacity (MW) of the Facilty wil be as
specified in Appendix B of this Agreement.
1.23 "Mechanical Availability" - The percentage amount calculated by Seller with 5 days after the
end of each month of the Facility's monthly actl Net Energy divided by the Facility's
Calculated Net Energy Amount for the applicable month. Any daages due as a result of the
Seller falling short of the Mechancal Availability Guantee for each month shall be deterined
in accordance with paragraph 6.4.4.
1.24 "Mechanical Avalability Guarantee" shall be as defined in pargraph 6.4
4
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 25 of 74
Draft: For Discussion Purposes Only
1.25 "Mid- Columbia Market Energy Cost" - The monthly weighte averge of the daily on-peak
and off-peak Dow Jones Mid-Columbia Index (Dow Jones Mid-C Index) prices for non-firm
energy. If the Dow Jones Mid-Columbia Index price is discontinued by the reporting agency, both
Parties will mutually agree upon a replacement index, which is sIiilar to the Dow Jones Mid-
Columbia Index. The selected replacement index will be consistent with other sIiilar agreements
and a commonly used index by the electrical industr.
1.26 "Nameplate Capacity" -The full-load electrcal quantities assigned by the designer to a generator
and its prime mover or other piece of electrical equipment, such as transformers and circuit
breakers, under standardized conditions, expressed in amperes, kilovolt-ampeers, kilowatts, volts
or other appropriate units. Usually indicated on a nameplate attached to the individual machine
or device.
1.27 "Net Energy" - All of the electrc energy produced by the Facility, less Station Use and Losses,
expressed in kilowatt hours (kWh), which the Transmitting Entity delivers to Idaho Power on the
Seller's behalf, that is less than or equal to the Nameplate Capacity. Seller commits to deliver all
energy produced by the Facility, less Station Use, and Losses, to the Transmitting Entity for
delivery by the Transmitting Entity to Idaho Power at the Point of Deliver for the full term of the
Agreement. Net Energy does not include Inadvertent Energy.
1.28 "Operation Date" - The day commencing at 00:0 i hours, Mountain Time, following the day that
all requirements of paragraph 5.2 have been completed.
1.29 "Point of Delivery" - The location specified in Appndix B, where the Transmitting Entity
delivers the Facilty's Net Energy and Inadvertent Energy to the Idaho Power electrcal system.
1.30 "Prudent Electrical Practices" - Those practices, methods and equipment that are commonly and
ordinarly used in electrcal engineerng and operations to operate electrc equipment lawfully,
safely, dependably, efficiently and economically.
1 .31 "Scheduled Opration Date" - The date specified in Appendix B when Seller anticipates
achieving the Operation Date. It is expected that the Scheduled Operation Date provided by the
5
Draft: For Discussion Purposes
10/28/2010
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 26 of 74
Draft: For Discussion Purposes Only
Seller shall be a reaonable estimate of the date that the Seller anticipates that the Seller's Facility
shall achieve the Operation Date.
1.2 "Season" - The three periods identified in paragraph 6.2.1 ofthis Agreement.
1.33 "Station Use" Electrc energy that is used to opeate equipment that is auxiliary or otherse
related to the production of electricity by the Facility. As this Facility is not located in the
Idaho Power servce tertory, Idaho Power has no responsibility or ablity to provide Station Use
to this Facility.
1.34 "Suffcient Prime Mover" means wind speed that is (1) equal to or greater than the generation
unit's manufacturer-specified minimum levels required for the generation unt to produce energy
and (2) equal to or less than the generation unit's manufacturer-specified maximum levels at
which thè generation unit can safely produce energy.
1.35 "Surplus Energy" - All Net Energy produced by the Seller's Facility and delivered by the
Transmitting Entity on the Seller's behalf to the Idao Power electrcal system prior to the
Operation Date.
1.36 "Total Cost of the Facility" - The total cost of strctures, equipment and appurenances.
1.37 "Transmitting Entity" - The signatorys) (other than the Seller) to the Transmission Agreement
referred to in paragraph 9.1 and its successors and assign.
1.38 "Wind Energy Production Forecast" - A forecast of energy deliveres from this Facilty provided
by an Idaho Power administerd wind forecasting modeL. The Facility shall be responsible for an
allocated portion of the total costs of the forecasting model as specified in Appendix E.
ARTICLE U: NO RELIANCE ON IDAHO POWER
2.1 Seller Independent Investigation - Seller warrants and reresents to Idaho Power tht in enterg
into this Agrement and the undertakng by Seller of the obligations set fort herein, Seller has
investigated and determined that it is capable of perfonning hereunder and has not relied upon
the advice, experence or experise of Idaho Power in connection with the tranactions
contemplated by this Agrement.
6
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 27 of 74
Draft: For Discussion Purposes Only
2.2 Seller Independent Expert - All professionals or expes including, but not limited to, cngineers,
attorneys or accountants, that Seller may have consulted or relied on in undertakng the
transactions contemplated by this Agreement havc been solely those of Seller.
ARTICLE II: WARTIES
3.1 No Waranty by Idaho Power - Any review, acceptance or failure to review Seller's design,
specifications, equipment or facilities shall not be an endorsement or a confiration by
Idaho Powcr and Idaho Power makes no warranties, exprcssed or implied, regarding any aspect of
Seller's design, specfications, equipment or facilities, including, but not limited to, safety,
durability, reliability, strengt, capacity, adequacy or economic feasibility.
3.2 Qualifying Facility Status - Seller warants that the Facilty is a "Qualifyng Facility," as that ter
is used and defined in 18 CFR 292.201 et seq. After initial quaification, Seller will tae such
steps as may be required to maintain the Facility's Qualifying Facilty status durng the ter of
this Agreement and Seller's failure to maintain Qualifying Facility status wil be a Materal
Breach of this Agreement. Idaho Power reseres the right to review the Facility's Qualifyng
Facilty status and associated suppor and compliance documents at anytime during the ter of
this Agreement.
ARTICLE IV: CONDITIONS TO ACCEPTANCE OF ENERGY
4.1 Prior to the First Energy Date and as a condition of Idaho Power's acceptance of deliveries of
energy from the Seller under this Agreement, Seller shall:
4.1. i Submit proof to Idaho Power that all licenses, pennits or approvals necessar for Seller's
operations have been obtained from applicable federal, state or local authorities,
including, but not limited to, evidence of compliance with Subpart B, 18 CFR 292.201 et
seq. as a certified Quaifying Facility.
4.1.2 Opinion of Counsel - Submit to Idaho Power ar Opinion Letter signed by an attorney
admitted to practice and in good standing in the State of Idaho providing an opinion that
7
Draft: 1"01' Discussion
10/2812010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 28 of 74
Draft: For Discussion Purposes Only
Seller's licenses, penits and approvals as set forth in paragraph 4.1.1 above are legally
and validly issue, are held in the name of the Seller and, based on a reasonable
independent review, counsel is of the opinion that Seller is in substantia compliance with
said permits as of the date of the Opinion Letter. The Opinion Letter wil be in a for
acceptable to Idaho Power and will acknowledge that the attorey renderng the opinion
understands that Idaho Power is relying on said opinion. Idaho Power's acceptance of the
form will not be unreasonably withheld. The Opinion Letter will be governed by and
shall be interpreted in accordance with the legal opinion accord of the American Bar
Association Section of Business Law (1991).
4.1.3 Initial Capacity Deteiination - Submit to Idaho Power such data as Idaho Power may
reasonably require to perorm the Initial Capacity Detenination. Such data will include
but not be limited to, Nameplate Capacity, equipment spcifications, pnme mover data,
resource chacterstics, normal and/or average operating design conditions and Station
Use data. Upon receipt of this informtion, Idao Power wil revew the provided data
and if necessar, request additional data to complete the Initial Capacity Determination
withi a reasonable time.
4.1..1 If the Maxmum Capacity speified in Appendix B of this Agreement and the
cumulative manufactue Nameplate Capacity rating of the individual generation
units at this Facilty is less than 10 MW. The Seller shall submit detailed,
manufactuer, venfiable data of the Nameplate Capacity ratings of the actual
individual generation units to be installed at ths Facilty. Upon venfication by
Idaho Power that the data provided establishes the combined Nameplate Capacity
rating of the genertion unts to be installed at this Facilty is less than 10 MW, it
wil be deemed that the Seller has satisfied the Initial Capacity Deteiination for
this Facility.
8
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 29 of74
Draft: For Discussion Purposes Only
4.1.4 Nameplate Capacity - Submt to Idao Power manufacture's and engineerig
documentation that establishes the Nameplate Capacity of each individual generation unt
that is included within ths entire Facilty. Upon reeipt of this data, Idao Power shall
review the provided data and detenine if the Nameplate Capacity specified is reasonable
based upon the manufactuer's specifed generation ratings for the specific generation
units.
4.1. Enginee's Cerifications - Submit an executed Engineets Cerfication of Design &
Constrction Adequacy and an Engineets Cerfication of Opeations and Maintenance
(O&M) Policy as described in Commission Orde No. 21690. These cerficates will be
in the form specified in Appendix C but may be modified to the extent necessar to
recognize the different engineerg disciplines providing the cerficates.
4.1.6 Insurance - Submit wrtten proof to Idaho Power of all insurance required in Arcle XII.
4.1.7 Transmission Agreement - Provide Idaho Power with a copy of (l) the Trasmission
Agreement executed by the Seller and the Transmittng Entity in a form acceptable to
Idaho Power and (2) confirmation that the Idaho Power deliver business unit has agreed
to accept the Net Energy deliveres at the Point of Deliver in an amount up to the
Maximum Capacity Amount. Idaho Power's acceptance will not be uneasonably
withheld.
4.1.8 Network Resource Designation - The Seller's Facilty has been designated as an
Idaho Power network resource capable of delivering firm energy up to the amount of the
Maximum Capacity at the Point of Delivery.
4.1.9 Written Acceptance - Request and obtain wrtten confirmation from Idaho Power that all
conditions to acceptance of energy have been fullled. Such wrtten confirmation shall be
provided within a commercially reasonable time following the Seller's reuest and will
not be unrasonably witheld by Idaho Power.
9
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 30 of 74
Draft: For Discussion Purposes Only
ARTICLE V: TERM AND OPERATION DATE
5.1 Ter - Subject to the provisions of paragraph 5.2 below, this Agreement shal become effective
on the date first wrtten and shall continue in full force and effect for a perod of
(not to exceed 20 years) Contract Years from the Operation Date.
5.2 Opertion Date - The Operation Date may occur only after the Facility has achieved all of the
following:
a) Achieved the First Energy Date.
b) Commission approval of this Agreement in a form acceptable to Idaho Power has
been received.
c) Seller has demonstrated to Idaho Power's satisfaction that the Facility is complete and
able to provide energy in a consistent, reliable and safe maer.
d) Seller has requested an Opeation Date from Idaho Power in a wrtten forat.
e) Seller has received wrtten confinnation from Idaho Power of the Operation Date.
This confinnation will not be unreasonably withheld by Idaho Power.
5.3 Operation Date Delay - Seller shall cause the Facilty to achieve the Operation Date on or before
the Scheduled Operation Date. Delays in the interonnection and transmission network upgrade
study, design and constrction process by any par (i.e. Seller, Idaho Power, host utility,
Transmittng Entity(s), etc) tht m. Force Majeure events accepted by both Partes, shall not
prevent Delay Liquidated Damages from being due and owing as calculated in accordace with
this Agreement.
5.3.1 If the Operation Date occu afer the Scheduled Operation Date but on or pror to 90
days following the Scheduled Operation Date, Seller shall pay Idaho Power Delay
Liquidated Damages calculated at the end of each calenda month after the Scheduled
Operation Date as follows:
Delay Liquidated Damages are equal to ((Cunt month's Initial Year Net
Energy Amount as specified in paragraph 6.2.1 divided by the number of days in
10
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 31 of74
Draft: For Discussion Purposes
the current month) multiplied by the number of days in the Delay Period in the
curent month) multiplied by the curent month's Delay Price.
5.3.2 If the Opration Date does not occ within ninety (90) days following the Scheduled
Operation Date the Seller shall pay Idaho Power Delay Liquidated Damages, in addition
to those provided in paragraph 5.3.1, calculated as follows:
Forty five dollar ($45) multiplied by the Maximum Capacity with the Maximum
Capacity being measured in kW.
5.4 If Seller fails to achieve the Operation Date within ninety (90) days following the Scheduled
Operation Date, such failure will be a Materal Breach and Idaho Power may terinate this
Agreement at any time until the Seller cures the Material Breach. Additional Delay Liquidated
Damages beyond those calculated in 5.3.1 and 5.3.2 wil be calculated and payable using the
Delay Liquidated Damage calculation described in 5.3.1 above for all days exceeding 90 days
past the Scheduled Operation Date until such time as the Seller cures ths Materal Breach or
Idaho Power terinates this Agreement.
5.5 Seller shall pay Idaho Power any calculated Delay Damages or Delay Liquidated Damages withn
7 days of when Idaho Power calculates and presents any Delay Damages or Delay Liquidated
Damages bilings to the Seller. Seller's failure to pay these damages within the specified time
wil be a Materal Breach of this Agreement and Idaho Power shall draw fuds from the Delay
Security provided by the Seller in an amount equal to the calculated Delay Damages or Delay
Liquidated Damages.
5.6 The Paries agree that the damages Idaho Power would incur due to delay in the Facility
achieving the Operation Date on or before the Scheduled Operation Date would be diffcult or
impossible to predict with cerainty, and that the Delay Liquidated Damages are an appropriate
approximation of such damages.
5.7 Prior to the Seller executing this Agreement, the Seller shall have agreed to and executed a Letter
of Understanding with Idaho Power that contains at minimum the following requirements:
11
For Discussion
10/28/2010
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 32 of 74
Draft: For Discussion Purposes Only
a) Seller has fied for interconnection and is in compliance with all payments
and requirements of the interonnection process
b) Seller has received and accepted an interconnection feasibility study for this
Facility.
c) Seller has provided all information required to enable Idaho Power to fie an
initial transmission capacity request.
d) Results of the initial transmission capacity request are known and acceptable
to the Seller.
e) Seller acknowledges responsibilty for all interonnection costs and any costs
associated with acquig adequate firm tranmission capacity to enable the
project to be classified as an Idaho Power firm network resour.
f) If the Facilty is located outside of the Idaho Power service tetor, in
addition to the above requirements, the Seller must provide evidence that the
Seller has acquired firm transmission capacity frm all required tranmittig
entities to deliver the Facilty's energy to an acceptable point of delivery on
the Idaho Power electrcal system.
5.8 Within thiry (30) days of the date of a Commission Order as speified in Aricle XXI approving
this Agreement; Seller shall post liquid securty ("Delay Security") in a for as described in
Appendix D equal to or exceeding the amount calculated in paragraph 5.8.1. Failure to post ths
Delay Security in the time specified above will be a Material Breach of this Agrent and
Idaho Power may terminate this Agreement.
5.8. I Delay Securty The greater of fort five ($45) multiplied by the Maximum Capacity with
the Maximum Capacity being measured in kW or the sum of thee month's estimated
revenue. Where the estimated thre months of revenue is the estimated revenue
associated with the first three full month following the estimated Schedled Opertion
Date, the estimated kWh of energy production as specified in paragrph 6.2.1 for those
12
Draft: For Discussion Purposes Only
10/28/2010
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 33 of 74
Draft: For Discussion Purposes
the months multiplied by the All Hour Energy Price specifed in pargrph 7.3 for
each of those three months.
5.8.1. In the event (a) Seller provides Idaho Power with cerfication that (1) a
Generation Interonnection Agreeent and Transnnssion Agrement specifying
a schedule that will enable this Facility to achieve the Operation Date no later
than the Schedled Operation Date has ben completed and the Seller has paid all
required interconnection and trsnnssion costs or (2) a Generation
Interconnection Agreement and Transmission Agreement are substantially
complete and all material costs of interconnection and transmission have been
identified and agreed upon and the Seller is in compliance with all terms and
conditions of the Generation Interconnection Agreement and the Transmission
Agreement, the Delay Secuty calculated in accordance with pargrph 5.8.1
wil be reduced by ten pecent (10%).
5.8.1.2 If the Seller has reived a reduction in the calculated Delay Securty as specified
in paragraph 5.8.i. and subsequently (1) at Seller's request, the Generation
Interconnection Agreement specified in paragraph 5.8.1.1 is revised and as a
result the Facilty wil not achieve its Operation Date by the Scheduled Operation
Date or (2) if the Seller does not maintain compliance with the Generation
Interconnection Agreement, the full amount of the Delay Securty as calculated
in paragraph 5.8.1 wil be subject to reinstatement and wil be due and owing
withn 5 business days from the date Idaho Power requests reinstatement. Failur
to timely reinstate the Delay Securty wil be a Material Breach of this
Agreement.
5.8.2 Idaho Power shall release any remning security posted hereunder after all calculated
Delay Damages and/or Delay Liquidated Damges are paid in full to Idaho Power and the earlier
13
Draft: For Discussimi
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 34 of 74
Draft: For Discussion Purposes Only
of (1) 30 days afer the Operation Date has been achieved or (2) 60 days after the Agreeent has
been tenninated.
ARTICLE VI: PURCHASE AND SALE OF NET ENERGY
6.1 Delivery and Acceptance of Net Energy - Except when either Pary's pedormnce is excused as
provided hern, Idaho Power will purchase and Seller will sell all of the Net Energy produced by
the Facilty and delivered by the Transmitting Entity to Idaho Power at the Point of Delivery. All
Inadvertent Energy produced by the Facilty wil also be delivered by the Transmitting Entity to
Idaho Power at the Point of Deliver. At no time will the total amount of Net Energy and/or
Inadvertent Energy produced by the Facility and delivered by the Transmitting Entity on beha of
the Seller to the Point of Deliver exceed the Maximum Capacity Amount.
6.2 Net Energy Amounts - Seller intends to produce and the Transmitting Entity shal deliver Net
Mechaical Availabilty Guarantee.
Energy in the following monthy amounts. These amounts shall be consistent with the
6.2.1 Initial Year Monthly Net Energy Amounts:
Month
Season 1
Marh
Apri
May
Season 2
July
August
November
December
Season 3
June
September
October
Januar
Februar
kWhxxXXXXXxx
XXXXXXxxxx
xxxx:xXXXX:x
6.3 Unless excused by an event afForce Majeure, Seller's failure to produce and/or the Tramitting
Entity(s) failure to deliver Net Energy in any Contract Year in an amount equal to at least ten
14
Draft: For Discussion Purposes Only
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-1Q-62
Allphin Affdavit, IPC
Page 35 of 74
Draft: For Discussion Purposes
perent (10%) of the sum of the Initial Year Monthly Net Energy Amounts as specified in
paragraph 6.2 shall constitute an event of default.
6.4 Mechanical Availabilty Guartee - After the Optional Date ha been established, the Facility
shall achieve a minimum monthly Mechanical Availability of 85% for the Facility for each month
durng the full ter of this Agreement (the "Mechanical Availabilty Guarantee"). Failure to
achieve the Mechanical Availability Guarantee shall result in Idaho Power calculating damages as
specified in paragrph 6.4.4.
6.4.1 At the same time the Seller provides the Monthly Power Production and Availabilty
Report (Appendix A), the Seller shall provide and cerify the calculation of the Facilty's
curent month's Mechanical Availability. The Seller shall include a sum of all
information used to calcuate the Calculated Net Energy Amount including but not
limited to: (a) Forced Outages, (b) Force Majeure events, (c) wind speed and the impact
on generation output and (c) scheduled maintenance and Station Use information.
6.4.2 The Seller shall maintain and retain for thr year detailed documentation supporting the
monthly calcuation of the Facility's Mechancal Availability.
6.4.3 Idaho Power shall have the right to review and audit the documentation supporting the
calculation of the Facilty's Mechanical Availability at reasonable times at the Seller's
offces.
6.4.4 If the current month's Mechanical Availability is less than the Mechanical Availabilty
Guarantee, damages shall be equal to:
((85 percent of the month's Calculated Net Energy Amount) minus the
month's actual Net Energy deliveries) multiplied by the Availabilty Shortfall
Price.
6.4.5 Any damages calculated in pargraph 6.4.4 will be offset against the curent month's
energy payment. If an unpaid balance remains after the damages are offset against the
energy payment, the Seller shall pay in full the remaining balance within 30 days of the
15
Draft: For Discussion
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 36 of 74
Draft:Discussion Purposes Only
date of the invoice.
ARTICLE VII: PURCHSE PRICE AND METHOD OF PAYMNT
7.1 Heavy Load Purhase Prce - For all Net Energy received durng Heavy Load Hours,
Idaho Power will pay the non-Ievelized energy price in accordance with Commission Order
31025 and adjusted in accrdance with Comssion Order 30415 for Heavy Load Hour Energy
deliveries, and adjusted in accordance with Commission Order 30488 for the wind integration
charge and with seasonalization factors applied:
Season 1 - (73.50 %)Season 2 - (120.00 %)Season 3 - (100.00 %)
Year MilslkWh MilslWh MilslWh
2010 40.52 66.15 55.12
2011 42.80 69.87 58.24
2012 45.32 74.00 61.66
2013 47.71 78.18 64.92
2014 50.29 82.74 68.42
2015 53.05 87.64 72.17
2016 54.64 90.46 74.34
2017 56.20 93.23 76.61
2018 57.90 96.25 79.12
2019 59.57 99.21 81.59
2020 61.29 102.27 84.14
2021 63.33 105.90 87.16
2022 65.46 109.67 90.31
2023 67.67 113.59 93.57
2024 69.97 117.66 96.97
2025 72.35 121.90 100.50
2026 74.38 125.49 103.49
2027 76.62 129.20 106.58
2028 78.96 133.03 109.77
2029 81.8 136.97 113.06
2030 83.87 141.04 116.45
2031 87.22 146.51 121.01
2032 90.15 151.30 125.00
2033 93.19 156.26 129.13
7.2 Light Load Purchase Prce - For all Net Energy received durng Light Load Hours, Idao Power
16
Draft: For Discussion Purposes Only
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 37 of 74
For Discussion Purposes Only
will pay the non-levelize energy price in accordace with Commission Order 31025 and
adjusted in accordance with Commission Order 30415 for Light Load Hour Energy deliveries,
and adjusted in accordance with Commission Order 30488 for the wind integration charge and
with seasonalization factors applied:
Season 2 - (120.00 %)
MilslkWh
Season 3 - (100.00 %)
Mils/WhYea
Season 1 - (73.50 %)
Mils/Wh
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
35.59
37.88
40.40
42.79
45.37
48.13
49.72
51.28
52.97
54.65
56.37
58.41
60.54
62.74
65.04
67.43
69.45
71.55
73.70
76.03
78.52
81.87
84.80
87.84
58.11
61.84
65.95
69.86
74.06
78.91
81.73
84.50
87.51
90.47
93.53
97.16
100.93
104.85
108.92
113.16
116.76
120.47
124.29
128.24
132.31
137.77
142.56
147.52
48.42
51.54
54.96
58.22
61.72
65.48
67.64
69.76
72.07
74.35
76.86
79.88
83.03
86.29
89.69
93.22
96.21
99.30
102.49
105.78
109.17
113.73
117.72
121.85
7.3 All Hours Energy Price - The price to be used in the calculation of the Surlus Energy Price and
Delay Price shall be the non-leve1ized energy price in accordance with Commission Order 31025
and adjusted in accordance with Commission Order 30488 for the wid integration charge and
with seasonalization factors applied:
Season 1 - (73.50 %)Season 2 - (120.00 %) Season 3 - (100.00 %)
17
Draft: For Discussion
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 38 of 74
Draft: For Discussion Purposes Only
Year MilslWh MilslWh MilslkWh
2010 38.33 62.57 52.14
2011 40.61 66.30 55.26
2012 43.13 70.42 58.68
2013 45.52 74.33 61.93
2014 48.10 78.85 65.44
2015 50.86 83.75 69.19
2016 52.45 86.58 71.36
2017 54.01 89.35 73.48
2018 55.71 92.36 75.88
2019 57.37 95.32 78.35
2020 59.10 98.38 80.90
2021 61.4 102.01 83.92
2022 63.27 105.78 87.07
2023 65.48 109.70 90.33
2024 67.78 113.77 93.73
2025 70.16 118.01 97.26
2026 72.18 121.60 100.25
2027 74.28 125.31 103.35
2028 76.58 129.14 106.53
2029 79.00 133.09 109.82
2030 81.49 137.16 113.21
2031 84.84 142.62 117.77
2032 87.77 147.41 121.76
2033 90.81 152.37 125.89
7.4 SUl1us Energy Pnce - For all Surplus Energy, Idaho Power shall pay to the Seller the curent
month's Market Energy Referece Prce or the All Hours Energy Price specified in
paragraph 7.3, whichever is lower.
7.5 Inadvertent Energy -
7.5. i Inadvertent Energy is electc energy produced by the Facilty, expressed in kWh,
which the Transmitting Entity(s) delivers on the Seller's behalf to Idaho Power at the
Point of Delivery that exceeds 10,000 kW multiplied by the hours in the specific
month in which the energy was delivered. (For example Januar contains 744 hours.
744 hours times 10,000 kW = 7,440,000 kWh. Energy delivered in Januar in excess
of1,440, 000 kWh in this example would be Inadverent Energy.)
7.5.2 Although Seller intends to design and operate the Facility to generate no more than
18
Draft: For Discnssion Purposes Only
10/28/2010
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 39 of 74
Draft: For Discussion Purposes Only
10 averge MW and therefore does not intend to genemte Inadverent Energy,
Idaho Power will accept Inadverent Energy that does not exceed the Maximum
Capacity Amount but wil not purchase or pay for Inadvertent Energy.
7.6 Payment Due Date - Undisputed Energy payments, less the Wind Energy Production Forecasting
Monthly Cost Allocation (MCA) described in Appendix E and any other payments due
Idaho Power, wil be disbursed to the Seller within 30 days of the date which Idaho Power
receives and accepts the docwnentation of the monthly Mechanical Available Guarantee and the
Net Energy actually delivered to Idaho Power as specified in Appendix A.
7.7 Continuing Jursdiction of the Commission This Agreement is a special contract and, as such, the
rates, ters and conditions contained in this Agreement wil be construed in accordance with
Idaho p'ower Company v. Idao ,Pblc Utilities Com.ien !;d Afon;E. Inc., 107 Idaho
781, 693 P.2d 427 (1984), IdaQPoWer Company v. Idao Public Utilities Commisson. 107
Idaho 1122, 695 P.2d 1 261 (1985), Afon Ener Inc. v. Idaho Power Coin 1 1 1 Idaho 925,
729 P.2d 400 (1986), Section 210 of the Public Utilties Regulatory Policies Act of 1978 and 18
CFR §292.303-308
ARTICLE VII: ENVIRONMENTAL ATTRIUTES
8.1 Seller retains ownership under this Agreement of Gren Tags and Renewable Energy Certificate
(RECs), or the equivalent environmental attributes, directly associated with the production of
energy from the Seller's Facility sold to Idaho Power.
ARTICLE IX: TRNSMISSION AGREEMENT
9.1 Transmission Agreement - The Seller will arrge and pay for the deliver of Net Energy and
Inadvertent Energy over the facilities of the Transmittng Entity(s) (XXX) to the Point of
Delivery. The deliver of Net Energy and Inadvertent Energy from the Facility to the
Idaho Power Point of Deliver shall be in accordance with the terms and conditions of a
Tmnsmission Agreement between the Seller and the Transmitting Entities. The Transmission
19
Draft: For Discussion
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 40 of 74
Draft: For Discussion Purposes Only
Agreement must provide for continuous firm transmission capacity on the Transmitting Entities
system for no less than the Maximum Capacity Amount and for the full Term of ths Agrement.
9.2 Acceptace of Transmission Agreement - This Agreement is expressly conditioned and
contingent upon Idaho Power's acceptance of the Transmission Agreement. Such acceptance wil
not be unreasonably withheld. A default by Seller under the Transmission Agreement will be a
Matenal Default under this Agreement.
9.3 Losses - Idaho Power wil only purchase the Net Energy that is deliverd by the Tranmitting
Entity to Idaho Power at the Point of Deliver. Losses wil be calculated as provided in
Appendix B of this Agreement.
9.4 Required Transmission Agrement provisions for Facilities not located within the Idaho Power
Electrical System Control Area -
If the Facility is not located within the Idaho Power Electrcal System Control Area, the
following requirements must be contained withn the Transmission Agreement (s);
9.41 Scheduling and delivery of Net Energy - The Transmission Agreement shall
include provisions that require the Transmittng Entity(s) to schedule and deliver
the Facility's energy to Idaho Power in accordance with industr standard
Wester Electricity Coordinating Council (WECC) scheduling processes and
procedures.
9.4.2 Energy Reserve Reguirements - The Trasmitting Entity(s) will provide all
generation reseres as required by the WECC and/or as required by any other
governing agency or industr standard to deliver the Net Energy to the specified
Point(s) of Deliver.
9.4.3 Documentation - Seller and/or the Transmitting Entity wil provide Idaho Power
with monthly documentation in a form acceptable to Idaho Power showing the
amount of energy scheduled and delivered to Idaho Power on an hourly bases.
If the Facility is located within the Idaho Power Electrcal System Control Area but not
20
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 41 of 74
Draft: For Discussion Purposes Only
within the Idaho Power serce tertory a combination of, energy scheduling, metering
and telemetr equipment meetig Idao Power stadas shall be requied to be in place
that wil provide Idaho Power accurte instataneous Net Energy deliveres being made
to Idaho Power at the Point of Deliver at any moment in tie as well as the capability to
record the Net Energy deliveres for an extended perod of time to provide the necessar
Net Energy deliver data to administer this Agreement. The Seller shall be responsible to
make all necessar arangements and cost of this process and equipment. The specific
equipment and schedule process shall be specified in more detail in Apendix XX of this
Agreement.
ARTICLE X - RECORDS
10.1 Maintence of Recor - Seller shall mantain at the Facility or such other location mutually
acceptable to the Paries adequate total generation, Net Energy, Station Use, Inadverent Energy
and maximum generation (kW) records in a form and content acceptable to Idaho Power.
10.2 Inpection - Either Par, after reasonable notice to the other Par, shall have the right, durng
normal business hours, to inspect and audit any or all generation, Net Energy, Station Use,
Inadvertent Energy and maximum generation (kW) records peraining to the Seller's Facilty.
ARTICLE XI: OPERATIONS
11.1 Communcations - Idaho Power, the Transmitting Entity(s) and the Seller shall maintain
approprate operating communications though Idaho Power's Designated Dispatch Facility in
accordance with Appendix A of ths Agreement.
11.2 Energy Acceptance -
12.2.1 Idaho Power shall be excused from acceting and paying for Net Energy or accepting
Inadvertent Energy which would have otherwse been produced by the Facility and
delivered by the Transmitting Entity(s) on behalf of the Seller to the Point of Deliver, if
it is prevented from doing so by an event of Force Majeure, Forced Outage or if
21
Draft: For Discussion
10/28/2010
Attchment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 42 of 74
Draft: For Discussion Purposes Only
Idaho Power deterines that cuailment, interption or reduction of Net Energy or
Inadvertent Energy delivenes is necessary because of line construction, electrcal system
maintenance requirements, emergencies, electrical system operating conditions, or
electrcal system reliability emergencies on its system or as otherise required by
Prdent Electrcal Practices. If, for reasons other than an event of Force Majeure or a
Forced Outage, a temporary disconnection that exceeds twenty (20) days, beginning with
the twenty-first day of such interrption, curtailment or reduction, Seller wil be deemed
to be delivering Net Energy at a rate equivalent to the pro rata daily average of the
amounts specified for the applicable month in paragraph 6.2. Idaho Power will notify
Seller when the interrption, curtailment or reuction is terinated.
11.2.2 Under no circumstances will the Transmitting Entity(s) on Seller's behalf deliver Net
Energy and/or Inadverent Energy from the Facilty to the Point of Delivery in an amount
that exceeds the Maximum Capacity Amount at any moment in time. Either the
Transmitting Entity(s) or Seller's failur to limit delivenes to the Maximum Capacity
Amount will be a Material Breach of this Agreement.
11.2.3 If Idaho Power is unable to accept the energy from this Facility and is not excused from
accepting the Facility's energy, Idaho Power's damages shall be limited to only the value
of the estimated energy that Idaho Power was unable to accept. Idaho Power will have
no responsibility to pay for any other costs, lost revenue or consequential damages the
Facility may incur.
11.3 Scheduled Maintenance - On or before Januar 31 of each calendar year, Seller shall submit a
wrtten proposed maintenance schedule of significant Facility and/or Transmitting Entity
maintenance for that calendar year and Idaho Power, Seller and Transmitting Entity shall
mutually agre as to the acceptability of the proposed schedule. The Pares determination as to
the acceptability of the Seller's timetable for scheduled maintenance will take into considertion
Prudent Electrcal Practices, Idaho Power system requirements and the Seller's preferd
22
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit"IPC
Page 43 of?4
Draft: For Discussion Purposes Only
schedule. Neither Part shall uneasonably withhold acceptance of the proposed maintenance
schedule.
11.4 Maintenance Coordination - The Seller, Idaho Power and the Transmitting Entity(s) shall, to the
extent practical, coordinate their respective line and Facility maintenance schedules such that they
occur simultaneously.
1 1.5 Contact Prior to Curtilment - Idaho Power wil mae a reasonable attempt to contact the Seller
and/or the Transmitting Entity prior to exercising its rights to curail, interrpt or reduce
deliveries from the Transmitting Entity from the Seller's Facility. Seller and the Transmittng
Entity understand that, in the case of emergency circumstances, real time operations of the
electrcal system, and/or unplanned events Idaho Power may not be able to provide notice to the
Seller or the Transmitting Entity pror to inteption, curtailment, or reduction of electrical
energy deliveries to Idaho Power.
ARTICLE XII: RELIAILITY MANAGEMENT SYSTEM
If the Facility is not located within the Idaho Power Electrcal System Control Area, the Seller will be
required to comply with the Reliabilty Management processes of the control area operator having control
of the specific location of the Facility and ths Aricle XII wil not apply. If the Facilty is located within
the Idaho Power Contrl Area, the Seller is required to comply with the following:
12.1 Purpose. In order to maintain the reliable operation of the trnsmission grd, the WECC
Reliability Criteria Agreement sets forth reliabilty critera adopted by the WECC to which Seller
and Idao Power shall be required to comply. Seller acknowledges receipt and understanding of
the WECC Reliability Criteria Agreement and how it perains to the Seller's Facility.
12.2 Compliance. Seller shall comply with the requirements of the WECC Reliability Criteria
Agreement, including the applicable WECC reliability critera set forth in Section IV of Anex A
thereof, and, in the event of failure to comply, Seller agrees to be subject to the sanctions
applicable to such failure. Such sanctions shall be assessed pursuant to the procedures contained
23
Dnft:For Discussion Purposes
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 44 of 74
Draft: For Discussion Purposes Only
in the WECC Reliability Critera Agreement. Each and all of the provisions ofthe WECC
Reliability Criteria Agreement are hereby incorporated by reference into this Aricle XII as
though set fort fully herein, and Seller shall for all puroses be considered a Participant, and
shall be entitled to all of the rights and prvileges and be subject to all of the obligations of a
Partcipant, under and in connection with the WECC Reliability Criteria Agreement, including,
but not limited to the rights, privileges and obligations set forth in Sections 5, 6 and 10 ofthe
WECC Reliability Criteria Agreement.
i 2.3 Payment of Sanctions. Seller shall be responsible for reimbursing Idaho Power for any monetar
sanctions assessed against Idaho Power by WECC due to the action or inaction of the Seller,
pursuant to the WECC Reliability Criteria Agreement. Seller also shall be responsible for
payment of any monetary sanction assessed against the Seller by WECC pursuant to the WECC
Reliability Critera Agreement. Any such payment shall be inade pursuant to the procedues
specified in the WECC Reliability Critera Agreement.
i 2.4 Transfer of Control or Sale of Generation Facilities. In any sale or transfer of control of any
generation facilities subject to this Agreement, Seller shall, as a condition of such sale or transfer,
require the acquiring party or transferee with respect to the trnsferred facilities either to assume
the obligations of the Seller with respect to this Agreement or to enter into an agrement with
Idaho Power imposing on the acquiring party or transferee the same obligations applicable to the
Seller pursuant to this Aricle XII.
12.5 Publication. Seller consents to the release by the WECC of information related to the Seller's
compliance with this Agreement only in accordance with the WECC Reliability Criteria
Agreement.
i 2.6 Third Pares. Except for the rights and obligations between the WECC and the Seller specified
in this Article XII, this Agreement creates contractual rights and obligations solely between the
Parties. Nothing in this Agreement shall create, as between the Pares or with respect to the
WECC: (a) any obligation or liabilty whatsoever (other than as expressly provided in this
24
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 45 of 74
Draft: For Discussion Purposes
Agreement), or (b) any duty or standad of care whatsoever. In addition, nothing in ths
Agreement shall create any duty, liability or standad of ca whatsoever as to any other pary.
Except for the rights, as a third-par beneficiary unde this Aricle XII, of the WECC against the
Seller for the Seller, no third pary shall have any rights whatsoever with respect to enforcement
of any provision of this Agreement. Idaho Power and the Seller expressly intend that the WECC
is a third-pary beneficiar to this Aricle XII, and the WECC shall have the right to seek to
enforce against the Seller any provision of this Arcle XII, provided that specific performance
shall be the sole remedy available to the WECC pursuant to Arcle XII of this Agreement, and
the Seller shall not be liable to the WECC pursuant to this Agreement for damages of any kind
whatsoever (other than the payment of sanctions to the WECC, if so constred), whether direct,
compensatory, special, indiect, consequential, or punitive.
12.7 Reserved Rights. Nothing in the Aricle XII of this Agreement or the WECC Reliability Criteria
Agreement shall affect the right of Idaho Power, subject to any necessar regulatory approval, to
take such other measures to maintan reliabilty, including disconnection that Idaho Power may
otherise be entitled to take.
12.8 Terination of Article XII. Seller may terminate its obligations pursuant to ths Aricle XII:
12.8.1 If after the effective date of this Aricle XII, the requirements ofthe WECC Reliability
Critera Agreement applicable to the Seller are amended so as to adverely affect the
Seller, provided that the Seller gives fifteen (15) days' notice of such terination to
Idaho Power and WECC within forty-five (45) days of the date of issuance of a FERC
order accepting such amendment for fiing, prvided fuer that the forty-five (45) day
period within which notice of termination is required may be extended by the Seller for
an additional forty-five (45) days if the Seller gives wrtten notice to Idaho Power of such
requested extension within the initial forty-five (45) day period; or
12.8.2 For any reason on one year's wrtten notice to Idaho Power and the WECC.
25
Draft: For Discussion
10/28/2010
Attachment NO.8
Case Nos, IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 46 of 74
For Discussion Purposes Only
ARTICLE XII: INEMNIFICATION AND INSURNCE
13.1 Indemification - Each Pary shall agree to hold harless and to indemify the other Par, its
officers, agents, affiiates, subsidiares, parent company and employees against all loss, damage,
expense and liability to third persons for injury to or death of person or injur to propery,
proximately caused by the indemnfying Pary's (a) constrution, ownership, opeation or
maintenance of, or by failure of, any of such Par's works or facilties used in connection with
this Agreement or (b) negligent or intentional acts, errors or omissions. The indemnifyg Par
shall, on the other Par's request, defend any suit asserting a claim covered by ths indemnity.
The indemnifyng Part shall pay all documented costs, including reasonable attorney fees that
may be incured by the other Par in enforcing this indemnity.
13.2 Insurance - During the term of this Agreement, Seller shall secure and continuously car the
following insurance coverage:
13.2.1 Comprehensive General Liability Inurance for both bodily injur and propery damage
with limits equal to $1,000,000, each occurence, combined single limit. The deductible
for such insurance shall be consistent with curt Insurce Industr Utility practices for
similar propert.
13.2.2 The above insurance coverage shall be placed with an insurance company with an A.M.
Best Company rating of A- or better and shall include:
(a) An endorsement naming Idaho Power as an additiona insured and loss payee as
applicable; and
(b) A provision stating that such policy shall not be canceled or the limits ofliability
reduced without sixty (60) days' prior wrtten notice to Idaho Power.
13.3 Seller to Provide Certficate of Insurance - As required in paragrph 4.1.6 herein and anually
therefter, Seller shall fuish Idaho Power a certificate of insurance, together with the
endorsements required therein, evidencing the coverage as set forth above.
26
Draft: ,For Discussion Purposes Only
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 47 of 74
Draft: For Discussion Purposes
13.4 Seller to Notify Idaho Power of Loss of Coverage - If the insurance coverage requied by
paragraph 13.2 shall lapse for any reason, Seller wil immediately notifY Idaho Power in wrting.
The notice will advise Idaho Power of the specific reason for the lapse and the steps Seller is
taking to reinstate the coverage. Failure to provide this notice and to expeditiously reinstate or
replace the coverage will constitute a Material Breach of ths Agreeent.
ARTICLE XN: FORCE MAEURE
14.1 As used in this Agreement, "Force Majeure" or "an event of Force Maeure" means any cause
beyond the control of the Seller or of Idaho Power which, despite the exercise of due diligence,
such Pary is unable to prevent or overcome. Force Majeure includes, but is not limted to, acts of
God, fire, flood, storms, wars, hostilities, civil strfe, strkes and other labor distubances,
earhquakes, fires, lightning, epidemics, sabotage, or changes in law or reguation occurrng after
the effective date, which, by the exercise of reasonable foresight such par could not reasonably
have been expected to avoid and by the exercise of due dilgence, it shall be unable to overcome.
If either Par is rendered wholly or in par unble to perform its obligations under this
Agreement because of an event of Force Majeure, both Paries shall be excused from whatever
performance is affected by the event of Force Majeure, provided that:
(l) The non-performng Party shall, as soon as is reasonably possible after the
occurence of the Force Majeure, give the other Par wrtten notice descrbing
the particulars of the occurce.
(2) The suspension of performance shall be of no greater scope and of no longer
duration than is required by the event of Force Majeure.
(3) No obligations of either Party which arose before the occurnce causing the
suspension of performance and which could and should have been fuly
performed before such occurence shall be excused as a result of such
occurrence.
27
Draft: l"or Discussion
10/28/2010
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 48 of 74
Draft: For Discussion Purposes Only
ARTICLE XV: LIAILITY; DEDICATION
15.1 Limitation of Liability. Nothing in this Agreement shall be constred to create any duty to, any
standard of car with reference to, or any liabilty to any person not a Par to this Agreement.
Neither pary shall be liable to the other for any indict, special, consequentil, nor puntive
damages, except as expressly authorized by this Agreement.
15.2 Dedication. No undertaking by one Party to the other under any provision of this Agreeent
shall constitute the dedication of that Par's system or any porton thereofto the Par or the
public or affect the status of Idao Power as an indepdent public utilty corporation or Seller as
an independent individual or entity.
ARTICLE XV: SEVE OBLIGATIONS
16.1 Except where specifically stated in this Agreement to be otherse, the duties, obligations and
liabilties of the Pares are intended to he several and not joint or collective. Nothing contained
in this Agreement shall ever he constred to create an association, trst, partership or joint
ventu or impose a trst or parerhip duty, obligation or liability on or with regard to either
Party. Each Part shall he individually and severally liable for its own obligations under ths
Agreement.
ARTICLE XVII: WAIVR
17.1 Any waiver at any time by either Part of its rights with respet to a default under this Agreement
or with respect to any other matter arsing in connection with this Agreement shall not be
deemed a waiver with respect to any subsequent default or other matter.
ARTICLE XVII: CHOICE OF LAWS AN VENUE
18.1 This Agreement shall be constred and intereted in accordace with the laws of the State of
Idaho without reference to its choice of law provisions.
18.2 Venue for any litigation arsing out of or related to this Agreement wil lie in the Distrct Cour of
28
Draft: For Discussion Purposes Only
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-1D-2
Allphin Affdavit, IPC
Page 49 of 74
Draft: For Discussion Purposes Only
the Fourh Judicial Distnct of Idaho in and for the County of Ada.
ARTICLE XI: DISPUTS AN DEFAULT
19.1 Disputes - All disputes related to or arsing under this Agrement, including, but not limited to,
the interpretation of the terms and conditions of this Agreement, will be submtted to the
Commission for resolution.
19.2 Notice of Default
19.2.1 Defaults. If either Pary fails to pedorm any of the term or conditions of this
Agreement (an "event of default"), the nondefaulting Par shall cause notice in
writing to be given to the defaulting Party, specifyng the maer in which such
default occured. If the defaulting Par shall fail to cure such default within the sixty
(60) days after servce of such notice, or if the defaulting Pary reasonably
demonstrates to the other Party that the default can be cured withi a commercially
reasonable time but not within such sixty (60) day perod and then fails to diligently
pursue such cure, then, the nondefaultig Par may, at its option, terminate this
Agreement and/or pursue its legal or equitable remedies.
19.2.2 Material Breaches - The notice and cure provisions in paragraph 19.2.1 do not apply
to defaults identified in this Agreement as Materal Breaches. Materal Breaches must
be cured as expeditiously as possible following occurence of the breach.
19.3 Security for Pedormance - Pror to the Option Date and thereafer for the full term of this
Agreement, Seller wil provide Idaho Power with the following:
19.3.1 Insurance - Evidence of compliance with the provisions of paragraph 13.2. If Seller
fails to comply, such failure wil be a Material Breach and may only be cured by
Seller supplying evidence that the required insurance coverage has been replaced or
reinstated;
19.3.2 Engineer's Certifications - Every three (3) years after the Opemtion Date, Seller will
supply Idaho Power with a Certification of Ongoing Opeations and Maintenance
29
Draft: For Discussion Purposes Only
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 50 of 74
For Discussion Purposes Only
(O&M) from a Registed Professional Engineer licensed in the State of Idaho, which
Certfication of Ongoing 0 & M shall be in the form specified in Appedix C. Seller's
failure to supply the required certificate wil be an event of default. Such a default
may only be cured by Seller providing the required cerificate; and
19.3.3 Licenses and Penits - During the full ten of this Agreement, Seller shall maintain
compliance with all penits and licenses described in paragraph 4.1. of this
Agreement. In addition, Seller will supply Idaho Power with copies of any new or
additional peits or licenses. At least every fifth Contract Year, Seller will update the
documentation described in paragraph 4.1.1. If at any time Seller fails to maintan
compliance with the perts and licenses described in paragraph 4.1.1 or to provide
the documentation required by ths paragraph, such failure wil be an event of default
and may only be cured by Seller submitting to Idaho Power evidence of compliance
from the penitting agency.
ARTICLE XX: GOVERNENTAL AUTORIZATION
20.1 Ths Agreement is subject to the jursdiction of those governenta agencies having control over
either Part of this Agreement.
ARTICLE XXI: COMMISSION ORDER
21. This Agreement shall become finally effective upon the Commission's approval of all terms and
provisions hereof without change or condition and declaration that all payments to be made to
Seller hereunder shall be allowed as prudently incured expenses for ratemaking purposes.
ARTICLE XXII: SUCCESSORS AND ASSIGNS
22. i This Agreeent and all of the tens and provisions herf shall be bindig upon and inure to the
benefit of the respective successors and assigns of the Paries hereto, except that no assignent
hereof by either Par shall become effective without the wrttn consent of both Paries being
30
Draft: l'or Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 51 of 74
Draft: For Discussion Purposes
first obtained. Such consent shall not be unreasonably withheld. Notwithstanding the foregoing,
any party which Idaho Power may consolidate, or into which it may merge, or to which it may
conveyor transfer substantially all of its electrc utilty assets, shal automatically, without fuer
act, and without need of consent or apprval by the Seller, succeed to all of Idaho Power's rights,
obligations and interests under ths Agrment. This Aricle shall not prevent a financing entity
with recorded or secured rights from exerising all rights and remedies available to it under law
or contract. Idaho Power shall have the right to be notified by the financing entity tht it is
exercising such rights or remedies.
ARTICLE XXII: MODIFICATION
23.1 No modification to this Agreeent shall be valid unless it is in wrting and signed by both Pares
and subsequently approved by the Commission.
ARTICLE XXIV: TAXS
24.1 Each Pary shall pay before delinquency all taxes and other goverental charges which, iffai1ed
to be paid when due, could result in a lien upon the Facility or the Interconnection Facilties.
ARTICLE XXV: NOTICES
25.1 All wntten notices under this Agreement shall be directed as follows and shall be
considered delivered when faxed, e-mailed and confrmed with deposit in the U.S. Mail,
fist-class, postage prepaid, as follows:
To Seller:
Original document to:
Telephone:
Cell:
31
For Discussion
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 52 of 74
Draft: For Discussion Purposes Only
FAX:
E-mal:
To Idaho Power:
Original document to:
Vice President, Power Supply
Idaho Power Company
POBox 70
Boise, Idaho 83707
Email: LGgrow€yidahopower.com
Copy of document to:
Cogenertion and Small Power Production
Idaho Power Company
POBox 70
Boise, Idaho 83707
E-mail: ralpl(£daqpweco
Either Pary may change the contact peron and/or address inoration listed above, by providing wrtten
notice from an authorize person represnting the Part.
ARTICLE XXVI: ADDITIONAL TERMS AND CONDITIONS
26.1 This Agreement includes the followi appendices, which are attached hereto and included by
reference:
Appendix A
AppendixB
AppendixC
AppendixD
AppendixE
Monthly Power Production and Availabilty Reprt
Facilty and Point of Deliver
Engieer's Cerfications
Forms of Liquid Securty
Wind Energy Production Forecasting
ARTICLE XXVII: SEVERILITY
27.1 The invalidity or unenforceabilty of any ter or proviion of this Agrement shall not affect the
validity or enforceabilty of any other terms or provisions and this Agreement shall be constred
in all other respects as if the invalid or unenforceable ter or provision were omitted.
32
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-1D-1 & IPC-E-10-62
Allphin Affdavit, IPC
Page 53 of 74
Draft: For Discussion Purposes Only
ARTICL XX: COUNRPARTS
28.1 This Agrent may be executed in two or more counterps, each of which shall be deemed an
origial but all of which together shal contitute one and the same instrent.
ARTICLE XXIX: EN AGREEN
29.1 Ths Agreement constitute the entire Ageeen of the Pares concerg the subjec matter
hereof and supered al prior or conteporeous or or wrtt agrents between the
Pares concerg the subject matter herof.
IN WISS WHREOF, The Partes hereto have caus ths Agrent to be exted
in thei respective naes on the dates set fort below:
Idaho Power Company
By By
Lisa A Grow
Sr. Vioø President. Power SUpply
Date Dated
"ldaoPowet "Seler"
33
Draft: For Discussion
101281010
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 54 of 74
Draft: For Discussion Purposes Only
APPENIXA
A -1 MONTHLY POWER PRODUCTION AN AV AIABILlT REPORT
At the end of each month the following reuire documentåtion wil be sUbmtted to:
Idaho Power Company
Attl:CQgêieratîon and Small Power Pruction
POBox 10
Boise, Idao 83707
The Metli redings require on this re will be the reding on the Meter Equipment meng the
Facilty's Net Ener delivlied by the Trasiittig Entity to the Idao Power electriClal sy.stem and/or
any other required energy measuremets to adeqately administli this Agreet. if the Meterig
Equipment is not located at the point which is able to measure the exact êiergydeliveesto the
Idao Power electrca system, then the metered energy amounts wil be adjused to account for eledcal
Løssesoçei.ng between the meerg poin and the point which the energy is delive to th
Idao Power eledcal system.
This re shall also include tlieSeller's calculation ofthe Meohaical Availabilty.
34
Draft: For Discussion Purposes Only
i 0128J201 0
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 55 of 74
Draft: For Discussion Purposes
Idaho Power Company
Cogeneration and Small Power Prducton
MONTHLY POWER PRODUCTION AN AVAILAILITY REPORT
Month Year
Project Name Project Number:
Address Phone Number:
City State Zip
Net Facilty
Output
Station
Usage
Station
Usage
Metered
Maximim Generation
Meter Number:
End of Month kWh Meter Reading:
Beginning of Month kWh Meter:
Difference:
Times Meter Constant:
kW
Net Generation
kWh for the Month:
Metered Demand:
Mechanical Availabilty Guarantee
Seller Calculated Mechanical Availabilty
As specifed in this Agreement, the Seller shall include with this monthly report a summary statement of the
Mechanical Availabilty of this Facilty for the calendar month. This summary shall include detals as to how
the Seller calculated this value and summary of the Facilty data used in the calculation. Idaho Power and
the Seller shall work together to mutually develop a summary report that provides the required data.
Idaho Power reserves the right to review the detailed data used in this calculation as allowed within the
Agreement.
Signature Date
35
Draft: For Discussion
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 56 of 74
Draft: For Discussion Purposes Only
A -2 MONTHLY POWER PRODUCTION AN SWITCHIG REPORT FOR PROJECTS
LOCATED OUTSIDE OF TH IDAHO POWER ELECTRICAL SYSTEM CONTROL ARA.
a.) The Transmitting Entity wil schedule and deliver the Facility's Net Energy to the
Idaho Power electrcal system at the Point of Deliver in accordance with the electrcal
industry stadard WECC scheduling and delivery processes. As specfied in pargrph 9.4
the Seller and/or the Transmitting Entity shall provide Idaho Power with monthly
documentation indicating the hourly energy scheduled and delivered to Idaho Power. Ths
documentation will be reconciled with Idaho Power recors of energy scheduled and received
from this Facility. In the event a discrepancy exists between the Idaho Power records and the
Seller / Tranmitting Entity documents, Idaho Power records wil be considered to be
accurate until such tie as Idao Power, the Seller and the Transmitting Entity mutually
agree on an adjustment to the Idaho Power records.
b.) The Seller shall submit to Idao Power a Monthly Power Production and Switching Report as
specified in Appendix A-I of this Agreement. The meter readings on this reprt shall be the
meter readings at the actul Facility measurng the actual energy deliveres to Transmitting
Entity at the Facility.
A-4 ROUTIN REORTING FOR PROJECTS OUTSIDE OF THE IDAHO POWER
ELECTRCAL SYSTEM CONTROL AR.
The Seller and Transmitting Entity shall maintain apprpnate communications with the
Idaho Power Designed Dispatch Facilty in compliance with electrc industr standard WECC energy
scheduling processes and procedures.
36
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 57 of 74
For Discussion Purposes
Seller1s Contat Infonation
24-Hout Projec Operational COntat
Nam:
Telephone Nube:
Cell Phone:
Proect On-site Contat informtion
Telephone Ni.ber:
37
1012010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 58 of 74
Draft: For Discussion Purposes Only
APPENDIXB
FACILITY AN POIN OF DELIVERY
Project Name:
Project Number:
B-1 DESCRIPION OF FACILITY
(Must include the Nameplate Capacity rating and VAR capabilty (both leading and lagging) of all
generation units to be included in the Facility.)
Var Capabilty (Both leading and lagging) Leading is _ Laggig is _
B-2 LOCATION OF FACILITY
Near:
Sections: _ Township: _ Range:County:il.
Description of Interconnection Location:
Nearest Idaho Power Substation:
B-3 SCHDULED FIRST ENRGY AN OPERATION DATE
Seller has selected as the Scheduled First Energy Date.
Seller has selected as the Scheduled Opration Date.
In mang these selectons, Seller recognizes that adequate testing of the Facilty and completion
of all requrements in paragrph 5.2 of this Agreement must be completed prior to the project
being granted an Opeation Date.
38
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 59 of 74
Draft: For Discussion Purposes Only
B-4 MAMUM CAPACITY AMOUNT:
This value will be MW which is consistent with the value provided by the Seller to
Idaho Power in accordance with Schedule 72. Ths value is the maximum energy (MW) that
potentially could be delivered by the Seller's Facility to the Idaho Power electrcal system at any
moment in time.
B-5 POINT OF DELIVERY
at the point on the Idaho Power electrcal system where
the Sellers Facility's Net energy is delivered by the Transmitting Entity to the Idaho Power
electrical system.
B-6 LOSSES
For Facilities within the Idaho Power Electrcal System Control area - If the Idaho Power
Metering equipment is capable of measurig the exact energ deliveres by the Transmitting
Entity on behalf of the Seller to the Idaho Power electrcal system at the Point of Delivery, no
Losses will be calculated for this Facility. If the Idaho Power Metering is unable to measure the
exact energy deliveries by the Transmitting Entity on behalf of the Seller to the Idaho Power
electrical system at the Point of Delivery, a Losses calculation wil be established to measure the
energy losses (kWh) between the Seller's Facility and the Idaho Power Point of Delivery. Ths
loss calculation wil be initially set at 2% (or any other reasonably detennined value by Idaho
Power) of the kWh energy production recorded on the Facility generation metering equipment.
At such time as Seller provides Idaho Power with the electrcal equipment specifications
(transformer loss specifications, conductor sizes, etc) of all of the electrical equipment between
the Facilty and the Idaho Power electrical system, Idaho Power wil configue a revised loss
calculation formula to be agreed to by both paries and used to calculate the kWh Losses for the
remaining term of the Agreement. If at any time durng the term of this Agreement, Idaho Power
deterines that the loss calculation does not corrctly reflect the actual kWh losses attrbuted to
the electrical equipment between the Facility and the Idaho Power electrcal system, Idaho Power
39
Draft: For Discnssimi
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 60 of 74
Draft: For Discussion Purposes Only
may adjust the calculation and retroactively adjust the previous months kWh loss calculations.
For Facilities outside of the Idaho Power Electrcal Control area - Idaho Power wil only
pay for Net Energy that is scheduled and delivered by the Transmitting Entity to the Point
of Delivery. All energy Losses between the Facilty and the Point of Deliver wil be
borne by either the Transmittng Entity or the Seller.
B-7 INTERCONNCTION FACILITIES
The Seller and Transmittng Entity shal constrct, operate and maintain the Facility and all
interconnection and protection equipment in accordance with Prdent Electrcal Practices, the
National Electrc Safety Code and any other applicable local, state and federal codes
B-8 METERING AN TELEMETRY
For Facilties located within the Idaho Power Electcal System Contrl Area
Metering Equipment - At the minimum the Meterig Equipment and Telemetr equipment
must be able to provide and record hourly energy deliveries by the Transmittng Entity to the
Point of Deliver and any other energy measurements required to admiister this Agreement.
Telemetr Equipment - At the minimum the Telemetr Equipment must be able to provide
Idaho Power with continuous instantaeous telemet of the Facility's energy deliveres to
the Transmitting Entity. The Seller wil arnge for and make available at Seller's cost, a
communications circuit acceptable to Idao Power, dedicated to Idaho Power's use to be used
for load profiling and another communications circuit dedicated to Idaho Power's
communication equipment for continuous telemeterig of the Facility's energy deliveres to
the Transmittng Entity to Idaho Power's Designated Dispatch Facility.
40
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 61 of 74
Draft: For Discussion Purposes Only
All costs including but not limited to actu equipment, installation, engieerng, monthly
communication circuit fees, operations and maintenance will be the responsibilty of the
Seller.
Exact details of the Metering and Telemetr equipment and specifcations wil need to be
added to this appendix once more inforlln becomes available in regards to the physical
and electrical configuration at this site and the configuratin of the interconnection at the
Point of Delivery.
For Facilties located outside of the Idaho Power Electrcal System Control Area
Meterng Equipment - At the minimum the Metering Equipment must be able to provide and
record hourly energy deliveres by the Facilty to the Trasmittg Entity and any other
energy measurements reuired to adminster ths Agreement.
Telemetr Eguipment - If Telemetr Equipment is required by the Transmittg Entity and
the Trasmitting Entity and Idao Power deterine that it is reuired that Idao Power have
access to the automated data. The Seller shall be responsible for all costs associated with
providing the automated telemetry data to Idaho Power.
Exact details of the Metering and Telemetr equipment and specificatns wil need to be added
to this appendix once more information becomes available in regards to the physical and
electrical configuration at this site and the configuration of the interconnection at the Point of
Delivery.
B-8 NETWORK RESOURCE DESIGNATION
Idaho Power canot accept or pay for generation from this Facility until a Netork Resource
Designation ("NR") application has been accepted by Idaho Power's deliver business unt.
41
Draft:F or Discussion
10/28/2010
Attachment No.8
Case Nos, IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 62 of 74
Draft: For Discussion Purposes Only
Feder Energy Regatory Commssion ("FERC") Rules requì Idaho Power to prep an
submt the NR. Because much of the informaton Idao Power needs to prear the NR is
specific to the Seller's Facilty, Idao Power',li abilty to fie the NR in a tiely maner is
continget upon tiely reeipt of the reui infonntion fr th Seller. Pror to Idao Power
beginning the process to enle Ido Powe to submt a request for NR statu for this Facilty,
the Seller shal have completed all requients as spcifed in Pargraph 5.7 of th Agrt.
Seller's faiure to provide complet and accurate informatin in a timely maner ca
iìigcantly impact Idaho Powe's abil and cost t,o attai the NR desation for the
Seller's Facil and the Seller shall bear th~ costs of any of these delays that are a result of
any aetion or inacon by the Seller.
42
Purpse Omy
10122010
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 63 of 74
Draft: For Discussion Purposes
APPENDIXC
ENGINER'S CERTIFICATION
OF
OPERATIONS & MAINENANCE POLICY
The undersigned . on behalf of himself/herself and
, hereinafter collectively refered to as "Engieer," hereby states and certifies to the Seller
as follows:
1. That Engineer is a Licensed Professional Engineer in good standing in the State of Idaho.
2. That Engineer has reviewed the Energy Sales Agrement, hereinafter "Agrement," between
Idaho Power as Buyer, and as Seller, dated
3. That the cogeneration or small power production project which is the subject of the Agreement
and this Statement is identified as IPCo Facilty No.and is hereinafter refered to as
the "Project."
4.That the Project, which is commonly known as the Project, is located in
Section _ Township Rage . Boise Merdian,County, Idaho.
5. That Engineer reognzes that the Agreement provides for the Project to fuish electrcal energy
to Idaho Power for a year period.
6. That Engineer has substantial experence in the design, constrction and operation of electrc
power plants of the same tye as ths Project.
7. That Engineer ha no economic relationship to the Design Engineer of this Project.
8. That Engineer has reviewed and/or supersed the review of the Policy for Operation and
Maintenance ("O&M") for this Project and it is his professional opinion that, provided said Project has
bee designed and built to approprate standards, adherence to said O&M Policy will result in the
43
Draft:lior Discussion
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 64 of 74
Draft: For Dfieumou Purpse Only
Prect's prucingat or nea the desgn electrca output, effciency and plat factor for a _ ye
perod.
9, Thát Engieeregnie tht I(bo Power, m accordce with pargrph 5.2 of the Agrent,
is reiyi~ on Entiees repestations and øpmiotl cotamed in this Statemnt.
10. That Enginer eerñes tht the above statements ar éomplete, tr and aèCurte to th be of
hisler knowlc:ge and therfore sets hisler ha and seal below.
By
(p.E. Stap)
Date
44
Draft: For Discussion Purposes Onl
1012812010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 65 of 74
Draft: For Discussion Purposes Only
APPENDIXC
ENGINER'S CERTIFICATION
OF
ONGOING OPERATIONS AND MAINTENANCE
The undersigned , on behalf of himselflerself
and hereiaf collectively referred to as "Engineer," hereby states and
cerifies to the Seller as follows:
1. That Engineer is a Licensed Professional Engineer in good standing in the State of Idao.
2. That Engineer has reviewed the Energy Sales Agreement, hereinafter "Agreement," between
Idaho Power as Buyer, and as Seller, dated
3. That the cogeneration or small power production project which is the subject of the Agreement
and this Statement is identified as IPCO Facilty No.and hereinafter referd to as the
"Project".
4.That the Project, which is commonly known as the Project, is located in
Section _ Township Rage , Boise Meridian,COWlty, Idaho.
5. That Engineer recognizes that the Agreement provides for the Project to fush electrcal energy
to Idaho Power for a year period.
6. That Engineer has substantial experence in the design, constrction and operation of electrc
power plants of the same type as this Project.
7. That Engineer has no economic relationship to the Design Engineer of ths Project.
45
Dnft: For Discussion
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 66 of 74
Di,eDøiOD Porpose
8. Tht Engifieeha made a physical insion of said Project, its opertions and maintenan~
reords since the last previous certifed inson. 1t is Engineer's profesiona opinon. bas on the
Project's appece. tht its ongaing O&Mha beensubstatily in accor with sad O&MPollcy;
that it is in røaribly god opetingcol1dition; and that if adherce to sad O&M PQ1icyçoptinu~, th
Projec will èofitiue prucing at or ne. its design electrcal output. efciency and plant factor for the
reining year of the Agrent.
9. Tht Rngineerrecogze tht Idao Power, in accornce withpangrph 5.2 of th Agrent,
relyipg on Engieer's tetitions and opnio CQntaied in ths Stateent.
10. That Enginee cees thåt the above stateneIts ar ooplete, tre and accurate to the bet of
biiØer knowledge and therfore se~hisêr hand and seal below.
By
(P.E. Sta)
Date
46
Draft FOr'Dliulln Pus Ony
101281010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 67 of 74
Draft: For Discussion Purposes Only
APPENIXC
ENGINER'S CERTIFICATION
OF
DESIGN & CONSTRUCTION ADEQUACY
The undersigned , on behalf of himselflerself and
hereinfter collectively referred to as "Engineer", hereby states and
certifies to Idaho Power as follows:
1.That Engineer is a Licensed Professional Engineer in good standing in the State of Idao.
2.That Engineer has reviewed the Fir Energy Sales Agreement, hereinafter "Agrment",
between Idaho Power as Buyer, and Seller, dated
3.That the cogeneration or small power production project, which is the subject of the
Agreement and this Statement, is identified as IPCo Facility No and is hereinafter
refered to as the "Project".
4.That the Project, which is commonly known as the is located in
Section _ Township Rage , Boise Meridian,County, Idaho.
5.That Engineer reognizes that the Agreement provides for th Project to furish electrcal
energy to Idaho Power for a year period.
6.That Engineer has substantial experence in the design, constrction and operation of
electrc power plants of the same tye as this Project.
7.That Engineer has no economic relationship to the Design Engineer of this Project and
has made the analysis of the plans and specifications independently.
8.That Engineer has reviewed the engineerng design and constrction of the Project,
including the civil work, electrcal work, generating equipment, prime mover conveyance system, Seller
fuished Interconnection Facilities and other Project facilities and equipment.
47
Draft: );~or Discussion
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 68 of 74
9.
Draft: For DiKoB Purpmi Only
That the Prjeá has been eonstied in at.(rcce with saidplar and spfications, aU
applicable cooesanâ consistent with Prent Electrcal Practccas that teo is desbe in the
Agrent.
10.That the deign and constion of the Project is such that with reasonable and prudeit
opeation and rnintealle praçtice 1)y Seller, the Prject is capable of peroning in accorce with the
ten of the Agent and withP: Eleeeal Practces for a ye perod.
1 i.Tht Enginee recgnize tbtldaoPower, in accoce with pagraph 5.2 of the
Agreit, in internnectig the Project with its system is relying on Engi~s rerestation and
opinons contane in this Statement.
12.that Engineer cefies th the above statemeits ar cóinplete, tr and accurte to the
bist ofhist knwledge and therore se hisl hand and sea below.
By
(p.E. Sta)
Date
48
Draft: For Discussion Purposes Only
1012SaOlO
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 69 of 74
Draft: 11'01" Discussion Purposes Only
APPENDIXD
FORMS OF LIQUID SECUR
The Seller shall provide Idao Power with commercially resonable secunty instrents such as
Cash Escrow Secunty, Guarantee or Letter of Credit as those term are defined below or other
forms of liquid financial secunty that would prvide reily avalable cash to Idaho Power to
satisfy the Delay Secunty reuirement and any other secunty requiement within this Agreement.
For the purose ofthis Appdix D, the ter "Credit Requirements" shall mean acceptable
financial creditworthiness of the entity providing the secunty instrment in relation to the ter of
the obligation in the reasonable judgment ofIdaho Power, provided that any guarantee and/or
letter of credt issued by any other entity with a short-ter or long-term investment grade credit
rating by Standard & Poor's Corporation or Moody's Investor Servces, Inc. shall be deemed to
have acceptable fiancial creditwortiness.
1. Cash Escrow Secunty - Seller shal deposit fuds in an escrow account established by the
Seller in a bankng institution acceptable to both Parties equal to the Delay Secunty or any
other required secunty amount(s). The Seller shall be responsible for aU costs, and receive
any interest eaed associated with establishing and mantaining the escrow account(s).
2. Guaantee or Letter of Credit Security - Seller shall post and maintain in an amount
equa to the Delay Securty or other requied security amount(s): (a) a guarnty from
a pary that satisfies the Credit Requirements, in a form acceptable to Idaho Power at
its discretion, or (bl.an irevocable_Letter of Credit in a form acceptable to Idaho
Power, in favor of Idao Power. The Letter of Credit wil be issued by a financial
49
DiscIHision
10/28/2010
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 70 of 74
Draft: For Discussion Purposes Only
institution acceptable to both parties", The Seller shall be responsible for all costs
associated with establishing and maintaining the Guarantee(s) or Letters) of Credit.
50
Draft: For Discussion Purposes Only
10/28/2010
Attachment NO.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 71 of 74
Draft: For Discussion Purposes Only
APPENDIXE
WIN ENEGY PRODUCTION FORECASTING
As specified in Commission Order 30488, Idaho Power shal make use of a Wind Energy Production
Forecasting model to forecast the energy production from this Facilty and other Qualifyng Facility wind
generation resources. Seller and Idaho Power wil shar the cost of Wind Energy Production Forecasting.
The Facility's share of Wind Energy Production Forecastig is detenned as specified below. Sellers
share will not be greater than 0.1 % of the total energy payments made to Seller by Idaho Power durng the
previous Contract Year.
a. For ever month of this Agreement beginnng with the first full month after the
First Energy Date as specified in Appendix of this Agrement, the Wind Energy
Production Forecasting Monthly Cost Allocation (MCA) wil be due and payable
by the Seller. Any Wind Energy Production Forecasting Monthly Cost
Allocations (MCA) that ar not reimbured to Idaho Power shall be deducted
from energy payments to the Seller.
. As the value of the 0.1 % cap of the Facilties total energy payments will not
be known until the first Contract Year is complete, at the end of the first
Contract Year any prior allocations that exceeded the 0.1 % cap shall be
adjusted to reflect the 0.1 % cap and if the Facility has paid the monthy
allocations a refund will be included in equal monthly amounts over the
ensuing Contract Year, If the Facilty has not paid the monthly allocations
the amount due Idaho Power will be adjusted accordingly and the unpaid
balance will be deducted frm the ensuing Contract Year's energy payments.
b. During the first Contract Year, as the value ofthc 0.1% cap of the Facilities total
51
Draft: For Discussion
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 72 of 74
Draft: For Discussion Purposes Ouly
energy payments will not be known until the fist Contrct Year is complete,
Idaho Power will deduct the Facility's calculated share of the Wind Energy
Production Forecasting costs specified in item d each month durig the fit
Contract Year and subsequently refud any overayment (payments that exceed
the cap) in equal monthly amounts over the ensuing Contract Year.
c. The cost allocation formula described below will be reviewed and revised if
necessar on the last day of any month in which the cumulative MW nameplate
of wind projects having Commission approved agreements to deliver energy to
Idaho Power has been revised by an action of the Commssion.
d. The monthly cost allocation will be based upon the following forula:
Where: Total MW (TM is equal to the total nameplate rating of all QF wind
projects that ar under contract to provide energy to Idaho Power
Company.
Faciity MW fFMW is equal to the nameplate ratng of this Facility as
specified in Appendix B.
Anual Wind Energy Production Forecastng Cost (AFCost) is equal
to the total anual cost Idaho Power incurs to provide Wind Energy
Production Forecasting. Idaho Power will estimate the AFCost for the
curent year based upon the previous year's cost and expected costs for
the curent year. At year-end, Idaho Power will compar the actual costs
to the estimated costs and any differences between the estimated AFCost
and the actual AFCost wil be included in the next year's AFCost.
Annual Cost Alocation (ACA) = AFCost X (F 1 TMW
And
Monthly Cost Allocation (MCA) = ACA 112
e. The Wind Energy Production Forecstig Monthly Cost Allocation (MCA) is
52
Draft: For Discussion Purposes Only
10/28/2010
Attachment No.8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 73 of 74
Dra: For DiJeunioD Purpses
due and payable to Idao Power. The MeA will fir be need aganst an
tnonthlyener payments owed to the Seller. If the netting of the MeA against
the monthly energy payments reults in a balance being due Idao Power, the
Facilty sbàll pay this amount within 1 S days of the date of the payment invoice.
53
l012I2()10
Attachment No. 8
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 74 of 74
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO.9
~hin, Randy
From:
Sent:
To:
Cc:
Subject:
Importance:
Tracking:
AJlphin, Randy
Thursday, No~ember 04,201010:25 AM
peter~richardsorlándoreary.com
Walker, Donovan
Wasatch wind - Grouse Creek I and Grouse Creek Ii transmisssion requests
High
Rec:ipie"l
peter!lrichardsonandoleary.co
Walker, Dønøn
Read
Read: 11/412010 10:26 AM
peter, as I indic¡ited in our letter to you dated November 1, 2010. 1 proceeded with filing transmission service requests
(TSR) for both of these projectS. Upon review of the information I submitted the application was rejected by the Idaho
Power transmission group due to the fact that information did not sync up with the project's transmission requests on
the aPA system.
The information prOvided by the projects in the Idaho Power transmission Capacity application questionnaire indicated
an on line date 12/1/2012, whereas the BPA transmission information indicates the earliest aPA Would have
transmission capacity would be available on the BPA system is June 2013.
The BPA transmission application indicates ,a 21 MWand a 30 MW project, based on the last information Wastach
provided to Idaho Power you requested two 21 MW projects.
In order for the Idaho Power transmiSSion group to accept my transmission applications we must have our information
consistent with the project's request for transmission on the aPA system. Please submit a revised Transmission
Capacity Application Questionnaire for both the Grouse Creek I and Grouse Creek II project as soon as possible. I wil
wait to file the Idaho power TSR until you have provided the revised information that is consistent with the BPA
transmission requests.
Ancillary Services - it is also very important to note that 8PA wil not be supplying ancilary services for your project.
You will be required to secure these ¡inciUary services from someone. As the proje.ct is not in the Idaho Power service
territory, Idaho POWEr is not required to supply ancilary services. if you want Idaho Power to provide the.se services, you
wil need to send in a written request and Idaho PoWer will review the request to determine our ability and cost to
provide these services. These services and costs woUld be in addition to any transmission costs incurred to provide
transmission capacity for this project on the Idaho Power electrical system.
In summary - I must have ,a revised transmission questionnaire from the projects that is consistent with the BPA
transmission requests to be able to file an Idaho Power transmission serviCe request.
Randy
1 Attachment No. 9
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 1 of9
a
DONOVAN E. WALKER
S.nror Counsel~~.Q~m
November 24,2010
VIAE-MAIL
Peter J. Richardson
RICHARDSON & O'LEARY, PLLC
515 North 27th Street
P.O. Box 7218
Boise., IdahO 83702
Re: Grouse Creek Wind Park, LLC, and Grouse Creek Wind Park II, LLC
Mr. Richardson:
Please let this confirm receipt of your November 23, 2010, letter regarding the
abave~reterenced proposed projects subsequent to our November 19, 2010. meeting,
With that Jetter you confirm, on behalf of your client, that Idaho Power had previousiy
sent YOll draft contracts containing the "standard" terms and conditions for a PURPA,
le$$ than 1 o average megawatts, published avoided cost rate Firm Energy Sales
Agreement ("FESAlJ). With this lelter IdaM Power acknowledges that Idaho Power and
your client are fully engaged in the referred to PURPA contracting process.
Your letter also confIrms and acknowledges that your client wishes to move
forward with the FESA, Including the standard, Idaho Public Utilìties Commission
("CommissionlJ) approved $45 per kilowatt of project .capacity delay security. prior to
completIon of the interconnection and transmission studies and processes. Further,
that your client understands it Is their responsibìlty to work with Idaho Power's Delivery
business unit to ensure that suffcient time and resources wil be àvallable for Delivery to
construct the lnterconnectlon facilties, and transmission upgrades if required, in time to
allow the projects to achieve the Scheduled Operation Date that the projects wil commit
themselves to in the FESA. In addition, your client has been advised, and accepts the
risk, that delays in thelnferconnectlon or transmission process do not constitute
excusable delays in achieving the Scheduled Operation Date, and if the projects fail to
achieve the Scheduled Operation Date at the time,s specified in the FESA, delay
damages wlU be assessed, and delay security applied. Please allow me to suggest that
special consideration be giiien to the Scheduled Operation Date selected by the
proJects fot Inclusion in tile FESA, such that with the information available at this time a
date is ohosen that has a good probabilty of providing time for the anticipated
interoonnection ånd possible transmission upgrades to be completed.
Affidavit of Ch ristin~, M~I~elL '.,
Exhibit J 1(.
Case Nos. IPC-E-IO~6ï'; W~j¡.iO.62
Page 1
Attachment NO.9
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of9
Peter J. Riohardson
November 24,2010
Page2of7
Additionally, given 1h.e VtJl) large amount of PURPA genei'ation projects that ara
proposed for Integration Into Idaho Power's system, as well as the issues raised in the
November 5, 2010, Joint Petition filed with the Commission, Idaho Power WOUld like to
call yor attention to some of the existing terms and conditions that are part of the
CommIssIon-approved standard PURPA FESA, as well as part of the Company's
approved Tariff Sohedule 72, and make certin that both Idaho Powr and your cllents
have a common understanding and meeting of the minds as to the meaning of these
terms and conditions prior to exeoutlng the FE$As and submittng thesame to the
Commission for approvaL.
Accrding to the standard provisions of the FESA (included below for your
reference), curfailment without compensatIon may occur if there Is an event of Force
Majeure, a, Forced Outage, or a temporary disconnection of the Facillty in accordanC$
with Tariff Schedule 72. If the gerieratlon from your client's facilty wil have an adverse
affect upon Idaho PQwets service to its customers, Idaho Power may temporarily
disconnect the facilty frm Idaho Powets transmission/distribution system as specified
within Schedule 72, or take such other reasonable steps as Idaho Power deems
appropriate. Idaho Powets intent and understanding Is that nonøoorrpensated
curtailment would be exercised when the generation being provided by facilties
conne,cted to Its system in certain operating coditions exceeds or approaohes the
mJnimum load levels of the Company's system such that It may have a detrimental
effect upon the Company's abilty to manage Its thermal, hydro, and other resources In
order to meet its obligation to reliably serve loads on Its system.
Idaho Power trusts that these provisions are acceptable to you and your clients,
as they have been part of the Commisslon..appmved standard FESA, as well as part of
the Commission-approved Tariff Schedule 72 for quite some time. Signing and
submiting the FESAs to the CommissiOn will evidence your specific acknowledgment
that both parties have â common understanding as set out above with regard to the
possible curtailment, without compensation, that may occur In certn operating
conditions on Idaho Power's system.
Please review the previously provIded draft contract: fllHn or corrct any of the
project specific, factual information contained thereIn; and return the draft to Idaho
Power so that the Company can then initiate the Sarbanes-Oxley contract approval
process and generate ane.xecutable draft for signatures.
Sincerely,
eb, (llrz~,\_Donovan E. Wall(er
DEW:C"Jb
co: Randy Allphin (via a-mall)
Affdavit of CliliStíl10 Mikell
Exhibit J
Case Nos. IPC-E-I0-61 , IPC-E-I0-62
Page 2
Attachment No.9
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 3 of9
Peler J. RIchardson
Nove~r 24, 2010
Page 30f7
Artcle XU; Opertions. from the FESA states as follos:
12 .1CommuhlcaUons - Idaho Power and the Seller shall maintaIn
lpproprllte oplJratlng cømmunlcations thrqogb Idaho Power's
PesiOn_te DiSatch Facilty In aocordlnce with Ap~ndix A of thi&
Agrement.
12.2 Energy Accptànèe -
12.2.1
12.2..2
12.2.3
Idaho Po shall be excuse from acpting and
paying for Net Energ or aocepting Inadvertent
Energy which would have otherwise ben produced
bythè Facllty and deUvered by the Seller to the Point
of Delivery, If It Is prevented from doing $0 by an
e~rlt ofF!arC8 Mljure. Forcd Oute or temporary
dieconne(lon of the FactUty In accrdance wit
Sch6(ule 12. If, for reasons other lh.n an event of
Forc M...re or a Forçed Outae. a temporary
d!scoMecon under Schedule 72 exceeds twenty
(20) days, beginning wîth the twenty-first day of such
Interr, curtilmnt Gr reuçtlon, Seller wil be
deeme to be delivring Net Energy at a rate
eqlAlvàlent to the pro rlta dally aVerage of the
amounts specifd for the applicable month In
para9,raph 6.2. Idaho POWêr will notify Seller when
the interrupton, curtllment or reduction Is terminate.
If, In. the reasonable oplrílon of Idaho Power.Seller'$
operatlol' 'of the Faoill or Innecon F8C1l l&
unsafe or may othelw ad aff ldlho
Power's equipment, pennel orserv to It
custOl'fS, Idaho Powr ma te dlnnot
the Facility from Idaho Power's
trnsmisIon/distributio system as specl witin
Setedule 72 or take such other reasonable steps..
Idaho Power deems appropriate.
Under no circmstances wil the Seiter deliver Net
Enel'Y and/or Inadvertent Energy from the Facíll to
the Point of De In an amount that exceds the
MIX Cap Amount at any , moment In time.
SeWs fa to limit deliveries to the Maximum
Capaçly Amount wil be å Material Breach of this
Agreement.
Affidavit of Christine Mikell
ExhibitJ
Case Nos. IPC-E..io-6l, IPC-E-I0-62
Page 3
Attachment No.9
Case Nos. fPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, fPC
Page 4 of9
Peter J. Richardson
Novembèr24,2010
Page4of7
12.2.4 If Idaho Power is unable to accpt the energ frm
this FaciDly and is not excused frm accpUri the
Facilty', energy, Idaho Power's damages shall be
limited to only the vllue of the estmatedønergy that
Idaho Powr was unable to accpt. Idaho Power will
have no reponllibilily to pay for.ny other taita, lost
revenuø or conseuential damaes the Fadllly may
Incur..
12.3 Scheduled Maintenance - On, or bafore Januaiy 31 of each
calendar year, Seifer shall submIt a wrttn prposed mafntenance
schedule of signifloa,nt Facility maintenance for that calendar year
and Idaho Powr and Seller shaJJ mutually agree as to the
accptabØity of thè proposed schedule. The Parties deterination
as to the aecptainty of the Seller's timetable for scheduled
maintenance will take into constderatlon Prudent Electrical
Practcas, Idaho Power systern tèquitè.rents and the Seller'S
preferred schedule. Neither Party shall unresonably withhotd
acceptance of the proposed maintenance scmedule.
12.4 Malntenance Coofdination - The Seller and Idaho Power shall, to
the extnt practica, coordinate their repeet line and facilty
maintenanc schedules such that they ooor simultaneously.
12.5Contaet Prior to CurtaRment .. Idaho Powr wilt make a rea$Onable
attempt to oontact the Seller prior to éxerclslng It, riQhts to Interupt
interconnection or cortn deliveries from the Seller's FacUlty. Seiler
understands that In the case of ~mergl1CY cfrcumstancøs. real time
operations of the elerical system, andlor unplanned event Idaho
Power may not bé able to provjde notice to the Seller prior to
interruption, curtffment, or reducton of electrical energy deliveries
to Idaho Power.
Idaho Power's Schedule 72, Interconnections to Non~Utilty Generation, states in
pertinent part:
5.3 Temporary Disconnection. Tel1orary dlsconnecton shall continue
only fqr so Iòng as reasonably necessary under Í1GC)od Utilit
Practice." Good UUity Practice means any of thEt practices.
methods and acts engaged In or approed by a significant portion
of theeleetrlc. Industr during the relevant time period, or àny of the
practices, methods and acts which, In th exercise of reasonable
judgment In light of the fact known at the time the declslon was
made, could have been eXPitd to accomplish the desired result
ata reasonable cost consIstent wi QOod business practIces,
rellabllty, safety and expedition. Good Utfllty Practce Is not
Affdavit of Christine Mikell
ExhibitJ
Cas Nos.IPC-E..iO-61, IPC.E-l0-62
Page 4
Attachment No. 9
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 50f9
Peter J. Richardson
November 24, 2010
Page50f7
intended to be ßmlte to the optimum practde, method, or act to the
exclusion of all others, but rather to be açcptable practices,
meods, or acl generall accpted in the rfgion. Good Utility
PractIce inclUdes copliance with WECC or NERC requirements..
Payment of 100t l'venue rellng from temprary dlsconneotlon
shall be govrne by the power purchase agreement.
5.3.1 Emergncv CgngltlOl' UEmergenc Condition"
means a condition or .sltuation; (1) that In the
judgment of the Part making the cllm Is Imminently
likely to endanger life or propert; or (2) that, In the
ctse Of the COmpany, Is Imminently likely (,$
determIned In a non-dj$criminatory numner) to ciusea materf advers effct on the securit of, or
d8 to th Company's trnsll~n~.., the Còpany's Intnne F8C orth eqUi of the com)" cuete.,; or (3)th In th oa of th se, illmnll ik (Ddermine In a noat n1nnt) to ca_ a
maærlal advers effec on the rellabiHty and securiof. or ~ to, th Oera Fa. or th
Sø Inlnec FìCes. Under Emenc
OOl élr th Compan or the seler mayimdi sq lnníseic end
te 41snn the Generallon F8c1. Th
Cony shaD nOf th Seller .pr, whn I
bee. .- of en Emeen Con tht may
re,.1I be ~ to af. th seleø
op of th Ge Fådit. The Se ahnoir thø Co pr when It be awarof an Emrpnoy Codl that R1Y rena b&
exp to af th COmps ~Irt orseic to th Coy'. Gustra. To.Ch extlntoll II kn. th noUti sh ~
th em~ Conitio, the extet of the dll
or dlfcleoy,th .-ec eff en thopertln Of
bo Part' ~ an opeUon, if ancipadura, and th ne core. aøn.
6.3.2 Boul MWDJ QøØì an ßt. The
COmpny may Intt Iaeã S8ce or
cu th outt of th seWs Gera f.i
.. l$rø dfnti th GeneraFacfr th Conf ~nttr .sy
wh nety for roin mainnanc,con. end ref.. on thCotl
Affdavit or Chiistine Mikell
ExhibitJ
Case Nös. IPC-E..IU.6!, IPC.E-l0-62
PageS
Attachment No.9
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 6 of9
Peter J. Ricardson
November 241 201Q
Pige6of1
ttansmisslonldisrlbutlon syst$m. The Company will
make a reasonable tUempt to contact the Seller prior
to exerci8ngitš rights to interrupt intercnnecion. or
curtil deliverIes from th Sellets FaciDly. Seller
undel'tands lh. In the case of emrgncy
cfl'l1fånces, real tie operations of the eieetrlca8Ytem. and unpl evts. Ut Co .yno be able to pro no to Ut $e ptto(ht. CU or reuo of eIØl døll tolh C~an. nie Co_aU U88 re ef toeørnfe such
reduction or temporary disconnection wit the Seller.
5.3.3 SCØU Ma!nOn or l*re JanllIY 31 of
eaoh oar ye. Sell .. eua wr
pr nt~ 8Cle of slgt Fac~ce to tht CU ye an th Coy
and Seller shall matually agree as to the accpl$bHit
of the proed schec;uJe. The Partie determnatIon
al to the aCCplâblllty of the. Sellêrs timetable for
schedUle maintnance wil take Into consideration
Good unity Practices, Idaho Power sytem
requirements and the Sellets preferr sèhedule.
Neither Part shlilI unreasoniibly withhold accptance
of the propos maintenance schedule.
5.3.4 Ma CoIn'. Th Seifer llnd the
Coman Ibal. to ih ,øx pr, coordnate
thir .re ~Ut system and
Generation FacUity maintenance schedules such that
they occur simultiineousy. Seller shall prciide and
maintain adequate prctive e.uipment suffent to
prevent damage to the Generation Facility and Seller.
furnished 'nl$rccneolQn FacUltes. In some cases.
sotreof Seller, protect refaYJ wU' provide back-up
protection for Idaho Power's facHities. In that event,
Idaho Powr will test stich relays annuållY and Seller
wil pay the actual cost of such annuilitesting.
5.3.5 Force Ouges. During any forced oute, the
Oompany may suspend interconnection seNC8 to
effect immediate re.palrs on the Companys
trnsmISsion/distrbutin syste. The Company shill
Use reasonable effort to provide the Seller with prior
notie. Ifprior notice Is not given, the Company shall.
upon réquest, provide the Seller wren
Affdavit of Christine Mikell
ExhibitJ
Case Nos. IPC..E..iO-61, IPC-E-10-62
Page 6
Attachment No. 9
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 7 of9
P~r J. FUchanjson
November 24, 2010
Pige7of7
documentation aftr the fact explaining the
cLrcurnstanCèof the disconneotlon.
5.3.6 Myerse Operating Efct. The Company shàll notify
the Seller as soon as práctlCâble If, ba$ed on Good
UUlty Practic, operàlfon of the Seller's Generation
Facility may cause dIsruption or deterioration of
servce to oter cU8tomera served from the same
electc systef1 or If operating the Generation Facllit
could cause damage to the Company's
transission/distribution sY$t.m or other affected
.ystems. Supportng documentation used to reach
the desion to disconnect shall be prOVided to the
sellêr upon request. If, after notlc, the Seller fails to
remedy the adverse operating effct within a
reasonable time, the Company may, disconnect the
Genertion Facility. The Company shall provide the
Seller wfth resonable noti of suCh discnnection.
unless the prol&ona of Anicle 5.3.1 apply.
5.3.7 MoUo of .. Otgetl Fac.The Seiter
mat re wr aut from the Companybere ma any change to th GetJn Facl
that ma have a ma Imct on th i.rely orrebil øf U1 COmpl& tnlodlipt Suc auton shl not be unrelbwi. Molftlons"'lI.be c:l' In aonc
wltGood Utility Practice. If the Seller makes such
rrodltltion without the COMpany's prior wrillén
authorization. the lattr shall have the right to
temporarily di$Cnnect the Generatlcm FacRlty.,
5.3.8 Reconnecton. Thè Panlesshall cooperate with eaoh
other to restore the Generation Faoilit,
Internnection Facilities, and the Company's
transmision/distributIon system to theIr normal
operating state as soon as reasnebly practioable
foiiowing a temporary disconnection.
Afídavit ofChrilitiiiøMikell
Exhibit J
Case Nos. IPC-E-10-61,lPC-E-i0-61
Page 7
Attachment No. 9
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 80f9
~hin, Randy
From:
Sent:
To:
Cc:
Subject:
~etêl'.Rf(;tirqsQri (peter~richardsonandoleary.coml
'. Monday, November.29, 201() 10:46 AM
Kris Sass.er
Walker, DOIovan;Grêg Adams; Allphin, Randy
Grouse Creek Complaint Dockets
Krs, as we discussed ths morng on the telephone, we have tentatively reached a settlement with
Idaho Power and respectflly request that the Commission not serve a summons on idaho Power at this
time. We believe we wil have a final setement within approximately two to thee weeks and we will
at that time fo:ra1ly request a dismissal that would be contingent upon Comiission approval ofthe
finl settlement agre,ement and power purchas,e agreeent. Please referce Docket Nos. IPC-E-10-29
and IPC-E-1O-30.
Peter Richaron
Richardson & O'Lea
515 N. 27th Street
Boise, Idaho 83702
(208) 938-7901
1 Attachment NO.9
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 90f9
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO. 10
Allphin, Randi
From:
Sent:
To:
Cc:
Subject:
Attachments:
Gr~~)~øaft$IGreg(grièharasQnandoleatY.comirhursda~,p~mberQZ.;2Ò1 04;42 PM
Walker, Donovan
Peter Richardson; Allphin, Randy
Grouse Creek Projects
12-2-10 Walker Letter GCWPs.pdf; Grouse Creek PPA Draft -12-2-10.doc; Grouse Creek II
PPA Draft 12-2-10.doc
Donovan,
Please see the attached letter from Peter Richardson and completed draftFESAs for these projects. Please contact us
with any questions.
Greg
Greg Adams
Richardson & O'Lear PLLC
515 N. 27th Street, 83702
P.O. Box 7218, 83707
Boise, Idaho
Voice: 208.938.2236
Facsimìle: 208.938.7904
Inormtion contained in ths electronic message and in any atthments heeto may contain informtion tht isconfdentìal, protected
by the attorey/client privilege and/or attorney work product doctre. Ths emal is intended only fo th use of the invidua or
entity naed above. Inadvernt disclosure of the contents of ths email or its attchments to unnteded recipiets is not inteded to
and does not constitute a waiver of the attorney/client prvilegeanor attrney work prduct doctre. This trnsmission is fuer
covered by the Electrnic Communcation Privacy Act, is U.S.C. §§ 2510-2521.
If you have received this email in eror, imediately notifY the sender of the erneous re.eipt and destoy this emil and any
attchments of the sae either electronic or prnted. Any disclosur, dissemination, distribution, copyig or us of the contents or
informtion received in error is strctly prohibited.
Than you.
1 Attachment No. 10
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of 3
IHIlÐ8ÐN It OLE, PU
ATTORNEYS AT LAW
Pctcr Richardson
Tel: 208-938.1901 FlO, 208.938.1904
pcrc,.rldii,duai ndolci 'y. com
P.O. 80s 1218 BOÎf. ID U707 . SU N. 27m Si, lui.e. ID 83702
2 Decembe 2010
Vitz U.S. Mtzt1 and Electronlc Mail
Donavon Walker
Legal Deparent
Idaho Power Compay
1221 West Idaho Stret
Boise, IO 83702
RE: IPC-E-IO-29, IPC-ElO-30-0rouse Creek LLC and Grouse Creek II LLC
Complaints
Dear Donova;
Than you for your letter of November 24, 201 0, regaring the above,.referenced projects
and complaint actions. As we agreed, we have taken the steps necessary to stay the
pending complaint actions regarding these projects in response to your letter. Wasateh
Wind is fully aware oithe contacts' provisions you highlighted in, your letter. Wasatch
Wind is also fulJy aware of the transnssion an interonnection risks, as weI i as the
liquid security provision.
As we discussed earlier today, the dtft agreements you sent contain a requirement in
Aricle S.7 to complete certain internnection and trmisson processes prior to
execution of the Firm Energy Sales Agreement, but you agree to remove this requirement
from the final agreement. I also would like to point out that Wasatcb Wind ha not
included line losses in the schedule of Monthly Net Energy for theñrst year of the
agement contained in Aricle 6.2.1. Wasatch Wind understands tht it wil only be pa.id
for output delivered to Idaho Power's system per the provisions of Appendix ß.6.
Additionally, beaus there wa some confuon earlier, pleas provide me with
confrmtion tht Idaho Power ha initiated the tranmission capacity applications to
secure Netork Resource designations for these projects. The requests should be for two
21 MWprojeet, each with a First Energy date ofDeçember 31,2012, and Scheduled
Operation date of Lune 1, 2013.
Wasatch Wind is prpaed to execute the agreements and we appreciate the fact that
Idao Power is processing them as quickly as possible, s.ubject only to your stdard
Attachment No. 10
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of3
Mr. Doovan Walker
Debe 2,2010
Pag 2
SarbaOxey contract apPval proce. To tht en enclose you wi fid th ñdly
filled ou cont for ea of the aboe..refed prec.
Sínøely,
'A J 'g 11- )~ .~Petr J. Rich
Richdson &; O'Le PLLC
Attachment No. 10
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 30f3
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO. 11
,
~hin,RandY
From:
Sent:
To:
Co:Subje:Alments:
Traking:
Peter,
;JtØ1:50PMTIPeter
Walker. Donoan
VVasah wtnd .energyWash wtndenlet 1i..1-2010,pd
Repint
'Pet Rlc'
Walk, Doova
Attached is a leer in regrdtö theWasatc Wfnd èl'èê projects.
Randy Allphin
Idaho Power COmpany
1
Read
Rl;d: 1211210 1:S PM
Attachment No. 11
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 1 of3
ø_.AAii:~~
December 7, 2010
Wasatch Wind
C/O Peter Richardson
Richardson &, O'Leary
515 N 27th Street,
Boise, ID 83702
Original: U SMail
E~mail copy: Peter Richardon pete~richardsonandoleary.com
Re: Gruse Creek I and Grouse Creek II wind project transission reuests
Mr. Richardson,
Idaho Power is in receipt of your letter dated December 2, 20 i 0 and the draft purchas power
agrents YOu provided for these two projects. Idaho Power is reviewing the infonnation
provided and wil coordinate the completion ofthese agreements in a prompt manner.
In addition, in this letter you provided clarfication of the project sizes and have asked for
confinnation that Idaho Power has fied the necessary documentation to initiate the transmission
capacity acquisition process.
As was discussed in our meeting of November 19. 2010, the project have provided Idaho
Power with differng details of the projec such as project sizes, proposed online dates, third party
transmission infonnation. etc. In October and early November 2010, Idaho Power received
confirmation frm the project of e.nough specific details to enable Idaho Power to request
transmission capacity for these projects. On November 4,2010, Idaho Power fied a transmission
service request application with the Idaho Power transmission grup for these projects. At that
time, the Idaho Power transmissioti grup returned the application communicatmg back that they
wer unable to process the application due to the fact that the BP A transmission requests noted on
the information provided by the projects were not consistent with the infonntiøti provided by the
project to Idaho Power for the Idaho Power trnsmission request.
P.O, Box 70 (&3107)
AttachmeMtN'ßI~t St.
Case Nos.ol¡se~~1!ß-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of3
On Deber 6, 2010, we once aga filed a trsson sece reuest with th Ida
Power trssion group. We will communicae to you all infòaion regaing ths reues as
we receve it back fr the trsmisson grup.
If you have any questions pleae do not hestate to cotact me.
Sicetly,
lit~'
Rady C. Allphi
Senor Engy Contrct Cordintor
(208) 388-2614E-ir:ra(idabOJ,o
cc Donò Walke (lPCo)
1'0 b 70 (imon'lt IN kI'S1Il(l II imz
Attachment No. 11
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 30f3
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO. 12
~hiniRandy
From:
Sent:
To:
Co:
Subject:
Attachments:
d
Walker, Donovan
Grouse creek draft contracts
Grouse Creek wind Park II Idaho Power draft agrement 12-07-2010.docx; Grouse Creek
wind Park IdahO Powr draft agreement 12-o7-2010.docx
Tracking:Recipient
'Peter Rîchardson'
Walker. Donovan
Read
Read: 121712010 7:ti6 PM
Peter,
Attached are draft agreements for the Grouse Creek wind park and the Grouse Creek wind park II.
In reviewing the drafts you had previously provided we discovered numerous problems with document formatting,
fonts, etc. Therefore we have copied the project specific information you provided in those drafts into new draft
agreements. Please use these draft agreements for all new comments etc.
One key piece of information that wa.s missing from both agreements . the aCcurate 10catiOn dèscription. The locations
provided are identical and the section information was hOt filed in. Bàsed on this information that has been provided,
there is no abilty to determine if the projects are at least 1 mile apart from each other.
Please review these draft agreements, add the additional information and return your comments ASAP so that we can
continue to move forWard with these agreements.
Randy Allphin
Idaho Power Company
1 Attachment No. 12
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of2
.chin, Randy
Fro:Se
To:
Co:Subje:
Per Richardson (petertmrichardsonandoleary.co)
Thursay, Dembe 09,20103:18 PM
Walker, Donovan; Allphin, Randy
Greg Adams
Grouse Oreek On Une Date
Donovan and Randy,
Ou clíent hii a.grd to the delay secty provisions, and in lookig at our on line da.te requet, what
would be your reaction if we moved the on line dates from fist energy 121l2a. COD 6113 to fit
energy 6/13 and COD 12113? Would we sti be o.k. in the prcess you have going? Tha, -Pete
Pet Richarson
Richardson & O'Lea
515 N. 27th Street
Boise, Idaho 83702
(208) 938-7901
1 Attachment No. 12
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of2
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO. 13
Darrington, Michael
From:
Sent
To:
Cc:
Subjec:
',e¡;r Ql1.MtetaelT' ,D~mtær.1i4,20,1Ö,9:55AM
'Peter Richardsõn'
'bWOodard(§wasatchwind.com'¡ Allphin, Randy; Walker, Donovan; Snyder, Carlene
Grouse Creek Wind Park Final Agreements - information need
Mr. Richardson:
In order to complete the final executable contracts for the Grouse Creek wind proje.cts we need the following
information:
ARTICLE IX: TRANSMISSION AGREEMENT
9.1 Transmission Agreement - The Seller wil arrange and pay for the delivery of Net Energy and Inadvertent Energy over
the facilities of the Transmitting Entity(s) ( ) to the Point of Delivery.
Please tist the transmitting entity(s) for each project.
APPENDIX 8
8-2 LOCATION OF FACILITY
Near: Lynn, UT
Sections: _ Township: 14 N Range: 17 W County: Box Elder, UT
Please list the Section for each project.
Once we have this information, we can finalize the Energy Sales Agreement for signature.
Michael Darrington
Sr. Planning Analyst
Power Supply
Idaho Power Company
PO Bo)(70
1221 W. Idaho St.
Boise, 10 83709
(208)388-5946
1 Attachment No. 13
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of 1
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO. 14
~hinJ Randy
From:
Sent:
To:
Cc:
Subjec:
AlI~bí?, R~ntlyWednesday,geêerroer 15,20107:49 AM
'Peter Richardson'; Walker, Donovan
Greg Adams; D8r'rington, Michael
RE: Grouse Creek On Line Date
Tracking:Recipient
'Peter Richardson'
Walker. Donovan
Greg Adms
Darringtn, Mich
Read
Read: 12115t2()'0 8:52 AM
Mr. Richardson
Idaho Power has reviewed your request to alter the First Energy date and the Operation Dates within the
Grouse Creek I and II proposed agreements and can accépt your r'equest. We wil insert these new dates in thé
draft agreements
On Tuesday, Dec 14 Michael Darrington emailed you a request for additional information requirements to
complete these draft agreements - in general the information required is name of the Transmitting Entity(s) and
completion ofthe location description for these projects. Please reference his e-mail for complete details.
After receipt of this additional information required to complete the agreements we wil resume the processing
of these proposed agreements.
Randy Allphin
Idaho Power Company
From: Peter Richardsn (n;:~and,gxl
Sent: Tuesday, December 14, 20104:36 PM
To: Peter Richardson; Walker, Donovan; Allphin, Randy
Cc: Greg Adams
Subject: RE:Grouse Creek On Une Date
Donovan an Randy:
Any thoughts on the below question.
Peter Richardson
Richa.dson & O'Le
1 Attachment No. 14
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of 5
515 N. 27th Str
Roìse, Idaho 83702
(208) 938-7901
From: Peer Richardson
sent: Thursay, Deber 09, 2010 3: 18 PM
To: Walker, Donovan; 'Allphin, Randy'
Cc Greg Adams
Subjec: Grous Crek On Line Date
Donovan and Ray~
Our clien ha agr to the delay sety prviions, and in lOôkiat our on line dâte
reqest, what would be your retion if we moved the on tie date frm first energy
12112 and COD 611:3 to fu energy 6113 and COD 121137 Would we stl be o.k. in the
prs you have gomg? Than -Pete
Peter Richason
Richardson & O'Lear
515 N. 27th Str
Boise, idao 83702
(208)938-7901
2 Attachment No. 14
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 20f5
~hin, Randy
From:
Sent:
To:
Cc:
Subject:
~t,~Adar;~l~~g(§richard~onariQle.ary.comJ
Wedne$day,Oeci:per15¡ 20103:41 PM
Allphin, Randy; Peter Richardson; Walker, Donovan
Darrington, Michael
RE: Grouse Creek On Line Date
Randy an Michael,
Than you for accetance ofthe new dates. Here is the additional data requested for the Grouse Creek
Wind Park an Grouse Creek Wind Park II. The legal descriptions ar differet for the two projects, but
the trsmssion prvider is the same. Please let us know if you have any additional questionst and
please copy me as Pete is out of the offce fòr a feW days.
GCWP: T14N R17W Sections 8,16,17
GCWP II: T14N R17W Sections 21, 27, 28
Trasmission Provider: BPA
Greg Adams
Richardson & O'LearPLLC
515 N. 27th Street, 83702
P.O. Box 7218,83707
Boise,. Idaho
Voice: 208.938.2236
Facsimìle: 208.938.7904
Inforntion contained in this electronic message and in any attaehmetrs hereto may cont infottation tht is c,onfdential,
proteted by the attmey/clientpriviege anor ãttomey workproduct doctre. This enail is intended only for the use of th
individua or entity naed above. Inaverent dislosur of the contents of ths email or its attchments to umntended
recipients is not intened to and does not constitute a waiver of the attrney/client prvilegeandlor attrney work product
doctre. Th trission is fuer cover by the Electrnic. Communication Privacy Act, 18 U.S.C. §§ 2510-2521.
If you have reeived this email in error, iiediately noti the sede of th eroneous receipt and destry this enail an any
attchments of the same either electrnic or prited. Any disclosur, dissemination, distribution, copying or us of the
contents or infttatión received in error is strctly prhibited.
Thayou.
From: Allphin, Randy ÜJ:ßAlRtn_l).CÐl
set: Wednesday, December 15, 2010 7:49 AM
i Attachment No. 14
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 3 of 5
To: Peter Richardson; Walker, DOnovan
Cc: Gre Adams; Darrington,Mic~el
Subject: RE: Grouse Crek On Line Date
Mr. Richardson
Idaho Power has reviewed your request to alter the Firt Energy date and the Operation Dates within the
Grouse Creek I and II proposed agrements and ca accept your request. We will inser these new
dates in the draft agreeents
On Tuesday, Dec 14 Michael Darngton emailed you a request for additional information requiements
to complete these draft agreements - in general the infonnation requite is name of the Tranmitting
Entity(s) and completion of the location description for these projects. Please reference his e~mail for
complete detaìls.
After receipt of this additional information required to complete the agreements we wil rèsue the
processing of these proposed agreements.
Randy Allphin
Idaho Power Company
From: Peter Richadson r mailto:peterrgchardsonadolear.com L
Sent: Tuesday, .December 14, 2010 4:36 PM
To: Peter Richardson; Walker, Donovan; Allphin, Randy
Ce: Greg Adams
Subje.e: RE: Grouse Creek On Line Date
Donovan and Randy:
Any thoughts on the below question.
Peter Richardson
Richarson & O'Leay
515 N. 27th Street
Boise, Idaho 83702
(208) 938-7901
2 Attachment No. 14
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 4 of5
From.: Peter Richardson
Sent: Thursday, December 09, 2010 3:18 PM
To: Walker, Donovan; 'Allphin, Rady'
Cc: Greg Adams
Subject: Grouse Creek On Line Date
Donovan and Randy,
Our client has agree to the delay secrity provisions, and in looking at our on line date
request, what would be your reaion if we moved the on line dates from fist energy
12/12 and COD 6/13 to fist energy 6/13 and COD 12/137 Would we stll be o.k. in the
process you have going? Tha, -Pete
Peter Richarson
Ri,chadson & O'Leary
SISN. 27th Street
Boise, Idaho 83702
(208) 938-7901
_~i.jj-~
This trinission ¡nay contain infoation that is privileged, confidetial and/or exçmpt fr discloure vnde applicle law. If you are not the ined recÇl
you are herby notifed that any disclosure, copying, distrbution, or use of the ùifonatiòn contained herin (ìncluding any reliane ther) is STRC1Y
PROHIBITED. If you receive this tl'siilion ùi eror, plea immediately contat the sender and desro the mateal in its entirety, whether ùi electric or bard
copy fotmL 1ñ)'.
3 Attachment No. 14
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 5 of5
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION .
CASE NO. IPC-E-10-61
CASE NO. IPC-E-10-62
IDAHO POWER COMPANY
ATTACHMENT NO. 15
.chin, Randy
From:
Sent:
To:
Cc:
Subject:
Gré, Adams (Gr ichardsonandoleary.com)
ThufsdáY, O~ec 16, 2010 8: 19 AM
Darrington, Michael
Allphin, Randy; Peter Richardson; Walker, Donovan
RE: Grouse Creek On Line Date
Yes, those are the correct dates.
June 1,2013 as first energy date.
Decem ber 1 J 2013 as Scheduled Operation date.
Thanks for checking.
Greg Adans
Richardson & O'Leary PLLC
sis N. 27th Stree, 83702
P.O. Box 7218, 83707
Boise, Idaho
Voice: 208.938.2236
Facsimile: 208.938.7904
Informtion contained in this electronic message and in any attchments hereto may contain informtion that is cofidential,
protected by the attrney/client prvilege and/or attorney work product doctre. Ths emil is intede only for the use of the
individual or entity named above. Inadverent discIosure of the contents of this email or its attachments to witended
recipients is not inteded to and does not constitute a waiver of the attrney/client privilege and/or attrney work prduct
doctre. This trinission is fuer covered by the Electronic Communication Privacy Act, 18 U.S.C. §§ 2510-2521.
If you have received this email in error, imediately notify the sender of the eroneous reeipt and destroy ths emil and any
attachmts of the same either electronic. or printed. Any disclosur, dissemintion, distrbution, copying or use of th
contents or infonnation received in errr is stctly prhibited.
Th you.
From: Darrington, Michael (mailt:MDarrington(gidahopower.com)
Sent: Wednesday, December 15, 2.0104:17 PM
To: Gre Adams
Cc: Allphin, Randy; Peter Richardson; Walker, Donovan
Subjec: RE:Grouse Creek On Une Date
Greg:
1 Attachment No. 15
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 1 of8
I want to make sure I understand the requested dates (as requested in the first email of this strng) for the
First Energy Date and Scheduled Operation Date for the Grouse Creek Wind prjects.
The currnt dates~ as found in Appendix B-3 ar:
B-3 SCHEDULED FIRST ENERGY AN OPERATION DATE
Seller has selected December 31, 2012 as the Scheduled Fir Energy Date..
Seller has selected June 1. 2013 as the Scheuled Opation Date.
My interretation of the dates you have requested (first energy 6/13 and COD 12/13) would change
Appendix B-3 as foIlows:
B-3 SCHEDULED FIRST ENERGY AN OPERATION DATE
Seller has selected June 1, 2013 as the Scheduled Firs Energy Date.
Seller has selected December 1, 2013 as the Scheduled Operation Date.
Ar these the correct dates that you would like in Appendix B-3 of the Firm Energy Sales Agreement?
Thans~
Michael Dargton
Sr. Planng Analyst
Power Supply
Idaho Power Company
POBox 70
1221 W. Idaho St.
Boise. ID 83709
(208)388-5946
From: Greg Adams (mailto:Greg~richardsonandoleary.com)
Sent: Wednesay, December 15~ 2010 3:41 PM
To: Allphin, Randy; Peter Richardson; Walker, Donovan
Ce: Dargton~ Michael
Subject: RE: Grouse Creek On Line Date
2 Attachment No. 15
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 2 of8
Randy and Michael,
Than you for acceptance of the new dates. Here is the additional data requested for the Gruse Creek
Wind Park and Grouse Creek Wind Park II. The legal descriptions ar different for the two projecs, but
the transmission provider is the same. Please let us know if you have any additional questions~ and
please copy me as Pete is out of the offce for a few days.
GCWP: T14N R17W Sections 8~16,17
GCWP II: T14N R17W Sections 21, 27, 28
Transmission Provider: BP A
Grg Adams
Richardson 8t O'Leay PLLC
515 N. 27th Stree 83702
P.O. Box 7218,83707
Boise, Idao
Voice: 208.938.2236
Facsimile: 208.938.7904
Informtion contained in ths electrnio messge and in any atthmts hereto may contan informtion tht is cofidentl,
protected by the attomey/client privilege and/or attorney work product doctre. This email is inteded only for the use of the
individual or entity naed above. Inadvertnt disclosur of the contents of ths emal or its atthments to uninteded
recipients is not intended to and does not constitute a waiver of the attorney/client privilege and/or attorney work product
doctrne. Ths trmission is fu cover by the Electrnic Communication Privacy Act, 18 U. S.C. § § 251 Q.2521.
If you hae reeive ths email in errr, immediately notify the sende of the erroneous receipt an destry ths em and any
attohments of the same either electrnic or prted. Any dìsclosure, disemination, dìstrbution, copying or use of the
contents or inonnation received in error is strctly prohibited.
Th you.
From: Allphin, Randy (niai1to:RAllphin~idahopower.C(ml
Sent: Wednesday, December 15, 2010 7:49 AM
To: Peter Richarson; Walker, Donovan
Cc: Greg Adams; Darngton, Michael
Subjeet: RE: Grouse Crek On Line Date
Mr. Richardson
3 Attachment No. 15
Case Nos. IPC-E-10-61 & IPC-E-10-2
Allphin Affdavit, IPC
Page 3 ofB
Idaho Power has reviewed your request to alte the First Energy date and the Operation Dates withn the
Grouse Creek I and II proposed agreements and can accet your request. We wi inser these new
dates in the draft agreements
On Tuesday, Dec 14 Michael Dargtn emailed you a request for additional information requirements
to complete these draft agreements - in general the information requied is name of the Transmittng
Entity(s) and completion of the location descrption for these projecs. Please reference his e-maîl for
complete detals.
After receipt of this additional information required to complete the agreements we wil resume the
processing of these proposed agreements.
Randy Allphin
Idaho Power Company
From: Peter Richadson (maîlto:peter(qchardsonandoleary.com J
Sent: Tuesday, Deceber 14,2010 4:36 PM
To: Peter Richardson; Walker, Donovan; Allphin, Randy
Cç: Greg Adams
Subjeçt: RE: Grouse Creek On Line Date
DonOVan and Randy:
Any thoughts on the below question.
Peter Richardson
Richardson & O'Leay
515 N. 27th Street
Boise, Idaho 83702
(208) 938-7901
From: Peter Richardson
Sent: Thursday, Deceber 09,20103:18 PM
To: Waler, Donovan; 'Allphin, Randy'
Cc: Greg Adams
Subject: Grouse Creek On Line Date
4 Attachment No. 15
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 4 of8
Donovan and Randy~
Our client has agr to the delay securty provisions, and in looking at our on line date
reques what would be your reaction if we moved the on line dates from first energy
12/12 and COD 6/13 to first energy 6/13 and COD 12/131 Would we still be o.k. in the
process you have going? Thans, .Pete
Peter Richardson
Richarson & O'Lear
515 N. 27th Street
Boise~ Idao 83702
(208) 938-7901
-_.il__
This trsmission may c,onlain infonnon thai is prvilege. confidentia andor exempt frm disclosur un applicable law, If you ar noi tle inend reien,
you are heby notifed that any disclosur, copying, distrbution, or use ,of th informtion cotaned lin (including any reliace thereon) is STRICTLYPROHIITE. If you reved this tranmisson Í1 er, plClC iimedaiely contat the seder and desoy the mateial in it enre, whether in e1enic or hard
copy foimt. Thk you.
5 Attchment No. 15
Case Nos. IPC-E-1Q-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 50f8
Allphin, Randy
From:
Sent:
To:
eei
Subjeçt:
A1lphin tflr'(l
l'b~~~¡Darnbet6,,~U1 09:53 AM
'petet(;richafdsonanclolear.com'; 'Greg(;rtohard$onandoleary.com'
Darrington, Michael
Grouse Crek agreements
Gentlemen,
We have the two Grouse Creek agreements ready for you, would you like to pick them up at our front desk or do you
wish us to mail them. If mailng is desired please provide the address. If you wish to pick them up we can have them at
the front desk at noon.
Randy
1 Attachment No. 15
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affdavit, IPC
Page 6 of8
Darrngton, Miçhael
From:
S.ent:
To:
Subjec:
~rtiñgtn.Michael
Thursday, ~, 1612010 10:41 AM
'Greg Adams'; Allp ,Randy; Peter Richardson
RE: Grouse Creek agreements
Greg:
Yes, we wil have the Grouse Creek Agreements ready to pick up at noon, along with the Shell and Exergy Agreements.
Michael Darrington
Sr. Planning Analyst
Power Supply
Idaho Power Company
PO Box 70
1221 W.ldaho St.
Boise, JD 83709
(208)388-5946
From: Greg Adams (mallto:Greg(ârlchardsonandoleaiy.co)
Sent: Thursay, December 16, 2010 10:36 AM
To: Allphin, Randy; Peter Richardson
eei Darrington, Michael
Subjec: RE: Grouse Creek agreements
We wil pick these up as well. Wil they be ready with the Exergy and Shell PPAs at noon?
Thanks,.
Greg Adams
Richardson &. O'Lea PLLC
sis N. 27th Street 83702
P.O. Box 7218,83707
Boise, Idaho
Voice: 208.938.2236
Facsimile: 208.938.7904
Informtion contaed in ths electrnic mesage and in any atthments hereto may conta infortion that is confidential, proteted
by the attrney/client privilege anor attorney work product doctrne. Ths email is intended only for the use of the indidual or
entity named above. Inadverent disclosure of the contents oftms email or its attachments to unintended recipient is not intended to
and does not constitute a waiver of the attoey/client prvilege anor attorneyworkproduct doctrine. Ths trsmission is fuer
covered by the Electrc Communcation Privacy Act, 18 U.S.C.§§ 2510-2521.
If you have received ths einl in error, inedately notify the sender of the erreous receìpt and destroy ths em an any
athments of the same either electronic or printed. Any dìsclosue, dissemintin, ditrbution, copyig or use of the contets or
infurmtion received in eror is strctly prombited.
Thnk you.
1 Attachment No. 15
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affidavit, IPC
Page 7of8
Fro: Allphin, RandY (mailto:RAlphln(§ldahoDöwer.col
Set: Thursay, Dembe 16,20109:53 AM
To: Petr Richardson; Gre Adams
Ce:: Darrngtn, Michael
Subjec Grous Creek agreeents
Gentlemeni
We have the two Grouse Creek agreements. ready for you, would you like to pick them up at our front desk or do you
wIsh us to mall them. IfmaUing is desIred please provide the address. If you wish to piCk them up we can have them at
the front desk at noon.
Rìndy-_.AA~~
~ ~mi1llt~ønfl .prMlqcol:llor~ hli4iliiidet.iUale ia.'I',ytii~1l lI ~ ~,i~l:yIlØled flll1d~ .coor_ ofl1iidlmuall eoli (Ii ~ mlll th)ÙI STRY MQFllBrm. If)'reYl tbia~ fnem". . ooth~lI~thma fnìt\ly, ,,_erfn ~orbiço Di 11yo
2
Attachment No. 15
Case Nos. IPC-E-10-61 & IPC-E-10-62
Allphin Affd.avit, IPC
Page 8of8