HomeMy WebLinkAbout20121023order_no_32669.pdfOffice of the Secretary
Service Date
October 23,2012
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
GROUSE CREEK WIND PARK,LLC AND )
GROUSE CREEK WIND PARK!!,LLC,)
)SUPREME COURT
Petitioners-Appellants,)DOCKET NO.31951-2011
)
v.)
)IPUC CASE NOS.IPC-E-10-61
IDAHO PUBLIC UTILITIES COMMISSION,)!PC-E-10-62
)
Respondent-Respondent on Appeal,)
)
and )
)
IDAHO POWER COMPANY,)IPUC ORDER NO.32669
)
Respondent-Intervenor/Respondent )
on Appeal.)
On September 7,2011,Grouse Creek Wind Park,LLC and Grouse Creek Wind Park
II,LLC (“Grouse Creek”)filed a timely Notice of Appeal from Order Nos.32257 and 32299 in
Case Nos.IPC-E-10-61 and WC-E-10-62.Idaho Power Company was granted intervention by
the Idaho Supreme Court on November 7,2011.On October 19,2012,Grouse Creek filed an
Amended Notice of Appeal.
Idaho Appellate Rule (I.A.R.)6 provides that the Commission “may by order correct
the title of an appeal or cross-appeal at any time before the ...agency’s record is lodged”with
the Supreme Court.Pursuant to I.A.R.6,the Commission issues this Order correcting the title of
the case on appeal.We find that the amended title appropriately reflects the positions of the
parties on appeal.
ORDER
IT IS HEREBY ORDERED that the title of the appeal in this matter shall be
corrected as reflected above to show the Idaho Public Utilities Commission as Respondent
Respondent on Appeal and Idaho Power Company as Respondent-Intervenor/Respondent on
Appeal.
ORDER NO.32669 1
IT IS FURTHER ORDERED that the Commission Secretary shall file a copy of this
Order changing the title of the appeal with the Supreme Court.
DONE by Order of the Idaho Public Utilities Commission at Boise,Idaho this
day of October 2012.
,,‘,/
PAUL KJELLANDER,PRESIDENT
MARSHA H.SMITH,COMMISSIONER
ATTEST:
n D.Jewel(/
immission Secretary
0:Supreme Court Case:IPC-E-10-6 1_62_dh_Appeal_Fitle Change
ORDER NO.32669 2