HomeMy WebLinkAbout20101116Application.pdfeslDA~POR~ An IDACORP company DONOVAN E. WALKER Senior Counsel dwalkerc.idahopower.com November 16,2010 VIA HAND DELIVERY Jean D. Jewell, Secretary Idaho Public Utilities Commission 472 West Washington Street P.O. Box 83720 Boise, Idaho 83720-0074 Re: Case No. IPC-E-10-39 IN THE MATTER OF THE APPLICATION OF IDAHO POWER COMPANY FOR APPROVAL OF A FIRM ENERGY SALES AGREEMENT FOR THE SALE AND PURCHASE OF ELECTRIC ENERGY BETWEEN IDAHO POWER COMPANY AND DESERT MEADOW WINDFARM, LLC Dear Ms. Jewell: Enclosed for filing please find an original and seven (7) copies of Idaho Power Company's Application in the above matter. DEW:csb Enclosures 1221 W. Idaho St. (83702) P.O. Box 70 Boise, ID 83707 DONOVAN E. WALKER (ISB No. 5921) LISA D. NORDSTROM (ISB No. 5733) Idaho Power Company P.O. Box 70 Boise, Idaho 83707 Telephone: (208) 388-5317 Facsimile: (208) 388-6936 dwalkerCcidahopower.com InordstromCcidahopower.com R ;",~: t 2Dm NOV l 6 PM 2= S4 Attorneys for Idaho Power Company Street Address for Express Mail: 1221 West Idaho Street Boise, Idaho 83702 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION ) OF IDAHO POWER COMPANY FOR ) CASE NO. IPC-E-10-39 APPROVAL OF A FIRM ENERGY SALES ) AGREEMENT FOR THE SALE AND ) APPLICATION PURCHASE OF ELECTRIC ENERGY ) BETWEEN IDAHO POWER COMPANY ) AND DESERT MEADOW WINDFARM, LLC. ) ) Idaho Power Company ("Idaho Powet' or "Company"), in accordance with RP 52 and the applicable provisions of the Public Utilty Regulatory Policies Act of 1978 ("PURPA"), hereby respectfully applies to the Idaho Public Utilties Commission ("I PUC" or "Commission") for an Order approving the Firm Energy Sales Agreement ("FESA") between Idaho Power and Desert Meadow Windfarm, LLC ("Desert Meadow" or "Sellet') under which Desert Meadow would sell and Idaho Power would purchase electric energy generated by the Desert Meadow Windfarm ("Facilty") located near Mountain Home, Idaho. In support of this Application Idaho Power represents as follows: APPLICATION - 1 I. BACKGROUND 1. Sections 201 and 210 of PURPA, and pertinent regulations of the Federal Energy Regulatory Commission ("FERC"), require that regulated electric utilities purchase power produced by cogenerators or small power producers that obtain qualifying facilty ("OF") status. The rate a OF receives for the sale of its power is generally referred to as the "avoided cost" rate and is to reflect the incremental cost to an electric utilty of electric energy or capacity or both, which, but for the purchase from the OF, such utilty would generate itself or purchase from another source. The Commission has authority under PURPA Sections 201 and 210 and the implementing regulations of the FERC, 18 C.F.R. § 292, to set avoided costs, to order electric utilities to enter into fixed-term obligations for the purchase of energy from OFs, and to implement FERC rules. 2. Desert Meadow proposes to design, construct, install, own, operate, and maintain a 23 megawatt ("MW") (Maximum Capacity Amount) wind generating facilty to be located near Mountain Home, Idaho. The Facilty wil be a OF under the applicable provisions of PURPA. II. THE FIRM ENERGY SALES AGREEMENT 3. On November 12, 2010, Idaho Power and Desert Meadow entered into a FESA pursuant to the terms and conditions of the various Commission Orders applicable to this PURPA agreement for a wind resource. See Order Nos. 30415, 30488, 30738, and 30744. A copy of the FESA is attached to this Application as Attachment NO.1. Under the terms of this FESA, Desert Meadow elected to contract with Idaho Power for a 20-year term using the non-Ievelized published avoided cost APPLICATION - 2 rates as currently established by the Commission for energy deliveries of less than 10 average megawatts ("aMW"). Although Idaho Power filed a Joint Petition on November 5, 2010, seeking a reduction in the published avoided cost rate eligibility cap from 10 aMW to 100 kilowatts ("kW") , the Company does not believe that this FESA should be impacted by that filng. This FESA was final and executed by Desert Meadow on November 2, 2010, prior to the filing of the Joint Petition. The FESA was subsequently executed by Idaho Power on November 12, 2010, and now filed for approval with the Commission on November 16, 2010. 4. The nameplate rating of this Facilty is 23.0 MW. As defined in paragraph 1.17 and paragraph 4.1.3 of the FESA, Desert Meadow wil be required to provide data on the Facilty that Idaho Power wil use to confirm that under normal and/or average conditions, the Facility wil not exceed 10 aMW on a monthly basis. Furthermore, as described in paragraph 7.5 of the FESA, should the Facilty exceed 10 aMW on a monthly basis, Idaho Power wil accept the energy (Inadvertent Energy) that does not exceed the Maximum Capacity Amount, but wil not purchase or pay for this Inadvertent Energy. 5. This PURPA wind agreement includes the Mechanical Availability Guarantee ("MAG"), Wind Integration Cost reduction, and Wind Forecasting cost sharing as required in Commission Order No. 30488. In addition, Desert Meadow and Idaho Power have agreed to Delay Liquidated Damages and associated Delay Security provisions of $45 per kW of nameplate capacity within this FESA that have previously been approved as reasonable by the Commission in several PURPA FESAs. See Case APPLICATION - 3 Nos. IPC-E-10-02, IPC-E-10-05, IPC-E-10-15, IPC-E-10-16, IPC-E-10-17, IPC-E-10-18, IPC-E-1 0-19, and IPC-E-10-22. 6. Desert Meadow has elected December 31, 2011, as the Scheduled First Energy Date and December 31,2012, as the Scheduled Operation Date for this Facilty. See Appendix B. Various requirements have been placed upon Desert Meadow in order for Idaho Power to accept energy deliveries from this Facilty. Idaho Power wil monitor compliance with these initial requirements. In addition, Idaho Power wil monitor the ongoing requirements through the full term of this FESA. Should the Commission approve this FESA, Idaho Power intends to consider the Effective Date of the FESA to be November 12, 2010. 7. The FESA, as signed and submitted by the parties thereto, contains non- levelized published avoided cost rates in conformity with applicable IPUC Orders. All applicable interconnection charges and monthly operation and maintenance charges under Schedule 72 wil be assessed to Desert Meadow. 8. The FESA provides that all applicable interconnection charges and monthly operational or maintenance charges under Schedule 72 wil be assessed to Seller. The Facility is currently in good standing with the generator interconnection process. Assuming that Seller continues to provide necessary technical information and make payments for interconnection materials and studies in a timely manner, Idaho Power's Delivery business unit anticipates providing a "Facilty Study Report" to Seller no later than January 7, 2011. Following review of the Facilty Study Report, the next step is for Seller and Idaho Power Delivery to enter into a Generator Interconnection Agreement, or "GIA." Idaho Power - Power Supply submitted Transmission Service APPLICATION - 4 Requests ("TSR") on behalf of the Facility to Idaho Power Delivery. Delivery responded that a System Impact Study was required and one was subsequently performed. The Study analysis indicates that the existing transmission system can accommodate the requested 120 MW without transmission network upgrades. The TSRs wil be accepted providing completion of the GIA and valid network resource designation. 9. Seller has selected December 31, 2011, for the Scheduled First Energy Date and December 31, 2012, as the Scheduled Operation Date. Desert Meadow has been advised that it is Desert Meadow's responsibilty to work with Idaho Powets Delivery business unit to ensure that sufficient time and resources wil be available for Delivery to construct the interconnection facilties, and transmission upgrades if required, in time to allow the Facility to achieve the December 31, 2012, Scheduled Operation date. Seller has been further advised that delays in the interconnection or transmission process do not constitute excusable delays in achieving the Scheduled Operation date and if Seller fails to achieve the Scheduled Operation date at the times specified in the FESA, delay damages wil be assessed. The developer of the Facility has advised Idaho Power that it is aware of these requirements and is confident of its abilty to meet the schedule. 10. Section 21 of the FESA provides that the FESA wil not become effective until the Commission has approved all of the FESA's terms and conditions and declared that all payments Idaho Power makes to Desert Meadow for purchases of energy wil be allowed as prudently incurred expenses for ratemaking purposes. II. MODIFIED PROCEDURE 11 . Idaho Power believes that a hearing is not necessary to consider the issues presented herein and respectfully requests that this Application be processed APPLICATION - 5 under Modified Procedure, i.e., by written submissions rather than by hearing. RP 201 et seq. If, however, the Commission determines that a technical hearing is required, the Company stands ready to present its testimony and support the Application in such hearing. IV. COMMUNICATIONS AND SERVICE OF PLEADINGS 12. Communications and service of pleadings, exhibits, orders and other documents relating to this proceeding should be sent to the following: Donovan E. Walker, Senior Counsel Lisa Nordstrom, Lead Counsel Idaho Power Company 1221 West Idaho Street P.O. Box 70 Boise, Idaho 83707 dwalkerCcidahopower.com InordstromCcidahopower.com Randy C. Allphin Energy Contract Administrator Idaho Power Company 1221 West Idaho Street P.O. Box 70 Boise, Idaho 83707 rallphinCcidahopower.com V. REQUEST FOR RELIEF 13. Idaho Power Company respectfully requests that the Commission issue an Order: (1) authorizing that this matter may be processed by Modified Procedure; (2) approving the Firm Energy Sales Agreement between Idaho Power Company and Desert Meadow Windfarm, LLC, without change or condition; and (3) declaring that all payments for purchases of energy under the firm Energy Sales Agreement between Idaho Power Company and Desert Meadow Windfarm, LLC, be allowed as prudently incurred expenses for ratemaking purposes. Respectfully submitted this 16th day of November 2010. ~ Attorney for Idaho Power Company APPLICATION - 6 CERTIFICATE OF MAILING I HEREBY CERTIFY that on the 16th day of November 2010 I served a true and correct copy of the within and foregoing APPLICATION upon the following named parties by the method indicated below, and addressed to the following: Desert Meadow Windfarm, LLC Dean J. Miler McDEVITT & MILLER LLP 420 West Bannock Street P.O. Box 2564 Boise, Idaho 83701 Mauriæ Miler, Authorized Manager 3145 Geary Boulevard, #723 San Francisco, California 94118 APPLICATION - 7 Hand Delivered -2 U.S. Mail _ Overnight Mail FAX -2 Email joeCcmcdevitt-miller.com Hand Delivered -2 U.S. Mail _ Overnight Mail FAX -2 Email mauriCcenvisionwind.com ~ BEFORE THE IDAHO PUBLIC UTiliTIES COMMISSION CASE NO. IPC-E-39 IDAHO POWER COMPANY ATTACHMENT NO.1 Aricle 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 FIR ENERGY SALES AGREEMENT BETWEEN IDAHO POWER COMPAN AN DESERT MEADOW WINF AR, LLC TABLE OF CONTENTS TITLE Definitions No Reliance on Idaho Power Waranties Conditions to Acceptance of Energy Term and Operation Date Purchase and Sale of Net Energy Purchase Price and Method of Payment Environmental Attributes Facilty and Interconnection Meterig and Telemetry Records Operations Indemnification and Insurance Force Majeure Liabilty; Dedication Several Obligations Waiver Choice of Laws and Venue Disputes and Default Governental Authorization Commission Order Successors and Assigns Modification Taxes Notices Additional Terms and Conditions Severabilty Counterpars Entire Agreement Signatures Appendix A AppendixB AppendixC AppendixD AppendixE 11/1/2010 FIR ENERGY SALES AGREEMENT (10 aMW or Less) Project Name: Deser Meadow Windfar Project Number:21615120 THIS AGREEMENT, entered into on this -J day of ¡Vt? b¡tt' 2010 between DESERT MEADOW WINFAR, LLC (Seller), and IDAHO POWER COMPANY, an Idaho corporation (Idaho Power), hereinafter sometimes referred to collectively as "Parties" or individually as "Pary." WITNESSETH: WHEREAS, Seller wil design, construct, own, maintain and operate an electrc generation facility; and WHEREAS, Seller wishes to sell, and Idaho Power is wiling to purchase, firm electrc energy produced by the Seller's Facility. THEREFORE, In consideration of the mutual covenants and agreements hereinafter set forth, the Parties agree as follows: ARTICLE I: DEFINTIONS As used in this Agreement and the appendices attached hereto, the following terms shall have the following meanings: 1.1 "Availability Shortfall Price" - The curent month's Mid-Columbia Market Energy Cost minus the current month's All Hours Energy Price specified in paragraph 7.3 of this Agreement. If this calculation results in a value less than 15.00 Mils/kWh the result shall be 15.00 Mils/Wh. 1.2 "Business Days" - means any calendar day that is not a Satuday, a Sunday, or a NERC recognized holiday. -1- 11/1/2010 1.3 "Calculated Net Energy Amount" - A monthly estimate, prepared and documented after the fact by Seller, reviewed and accepted by the Buyer that is the calculated monthly maximum energy deliveries (measured in kWh) for each individual wind turbine, totaled for the Facility to determine the total energy that the Facility could have delivered to Idaho Power durng that month based upon: (1) each wind tubine's Nameplate Capacity, (2) Suffcient Prie Mover available for use by each wind tubine during the month, (3) incidents of Force Majeure, (4) scheduled maintenance, or (5) incidents of Forced Outages less Losses and Station Use. If the duration of an event characterized as item 3, 4 or 5 above (measured on each individual occurence and individual wind turbine) lasts for less than 15 minutes, then the event wil not be considered in this calculation. The Seller shall collect and maintain actual data to support this calculation and shall keep this data for a minimum of 3 years. 1.4 "Commission" - The Idaho Public Utilties Commssion. 1.5 "Contract Year" - The period commencing each calenda year on the same calendar date as the Operation Date and ending 364 days thereafter. 1.6 "Delay Liquidated Damages" - Damages payable to Idaho Power as calculated in paragraph 5.3, 5.4, 5.5 and 5.6. 1.7 "Delay Period" - All days past the Scheduled Operation Date until the Seller's Facility achieves the Operation Date. 1.8 "Delay Price" - The curent month's Mid-Columbia Market Energy Cost minus the current month's All Hours Energy Price specified in paragraph 7.3 of this Agreement. If this calculation results in a value less than 0, the result of this calculation will be O. 1.9 "Designated Dispatch Facility" - Idaho Power's Systems Operations Group, or any subsequent group designated by Idaho Power. 1.10 "Effective Date" - The date stated in the opening paragraph of this Fir Energy Sales Agreement representing the date upon which this Fir Energy Sales Agreement was fully executed by both Paries. 1.11 "Facilty" - That electrc generation facility described in Appendix B of ths Agreement. -2- 111112010 1.12 "First Energy Date" - The day commencing at 00:01 hours, Mountain Time, following the day that Seller has satisfied the requirements of Aricle IV and the Seller begins delivering energy to Idaho Power's system at the Point of Delivery. 1.13 "Forced Outage" - a partial or total reduction of a) the Facilty's capacity to produce and/or deliver Net Energy to the Point of Delivery, or b) Idaho Power's abilty to accept Net Energy at the Point of Delivery for non-economic reasons, as a result ofIdaho Power or Facility: 1) equipment failure which was not the result of negligence or lack of preventative maintenance, or 2) responding to a transmission provider curailment order, or 3) unplaned preventative maintenance to repair equipment that left unrepaired, would result in failure of equipment prior to the planed maintenance period, or 4) planed maintenance or construction of the Facilty or electrical lines required to serve this Facility. The Paries shall make commercially reasonable efforts to perform this unplaned preventative maintenance durg periods of low wind availabilty. 1.14 "Heavy Load Hours" - The daily hours begining at 7 :00 am, ending at 11 :00 pm Mountain Time, (16 hours) excluding all hours on all Sundays, New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving and Chrstmas. 1.15 "Inadvertent Energy" - Electric energy Seller does not intend to generate. Inadvertent energy is more paricularly described in paragraph 7.5 of this Agreement. 1.16 "Interconnection Facilities" - All equipment specified in Idaho Power's Schedule 72. 1.17 "Initial Capacity Determination" - The process by which Idaho Power confirs that under normal or average design conditions the Facility wil generate at no more than 10 average MW per month and is therefore eligible to be paid the published rates in accordance with Commssion Order No. 29632. 1.18 "Light Load Hours" - The daily hours beginning at 11 :00 pm, ending at 7:00 am Mountain Time (8 hours), plus all other hours on all Sundays, New Years Day, Memorial Day, Independence Day, Labor Day, Thansgiving and Chrstmas. -3- 111112010 1.19 "Losses" - The loss of electrical energy expressed in kilowatt hours (kWh) occurrng as a result of the transformation and transmission of energy between the Meterg Point and the point the Facilty's energy is delivered to the Idaho Power electrical system. The loss calculation formula wil be as specified in Appendix B of this Agreement. 1.20 "Market Energy Reference Price" - Eighty-five percent (85%) of the Mid-Columbia Market Energy Cost. 1.21 "Material Breach" - A Default (paragraph 19.2.1) subject to paragraph 19.2.2. 1.22 "Maximum Capacity Amount" - The maximum capacity (MW) of the Facility wil be as specified in Appendix B of this Agreement. 1.23 "Mechancal Availabilty" - The percentage amount calculated by Seller within 5 days after the end of each month of the Facility's monthly actual Net Energy divided by the Facility's Calculated Net Energy Amount for the applicable month. Any damages due as a result of the Seller fallng short of the Mechancal Availability Guarantee for each month shall be determined in accordance with paragraph 6.4.4. 1.24 "Mechanical Availabilty Guarantee" shall be as defined in paragraph 6.4. 1.25 "Meterig Equipment" - All equipment specified in Schedule 72, this Agreement and any additional equipment specified in Appendix B required to measure, record and telemeter bi- directional power flows from the Seller's Facilty at the Metering Point. 1.26 "Metering Point" - The physical point at which the Metering Equipment is located that enables accurate measurement of the Test Energy and Net Energy deliveries to Idaho Power at the Point of Delivery for this Facility that provides all necessary data to administer this Agreement. 1.27 "Mid- Columbia Market Energy Cost" - The monthly weighted average of the daily on-peak and off-peak Dow Jones Mid-Columbia Index (Dow Jones Mid-C Index) prices for non-firm energy. If the Dow Jones Mid-Columbia Index price is discontinued by the reporting agency, both Paries wil mutually agree upon a replacement index, which is similar to the Dow Jones Mid-Columbia Index. The selected replacement index wil be consistent with other similar agreements and a commonly used index by the electrical industry. -4- 11/112010 1.28 "Nameplate Capacity" -The full-load electrical quatities assigned by the designer to a generator and its prie mover or other piece of electrical equipment, such as transformers and circuit breakers, under standardized conditions, expressed in amperes, kilovolt-amperes, kilowatts, volts or other appropriate units. Usually indicated on a nameplate attached to the individual machine or device. 1.29 "Net Energy" - All of the electric energy produced by the Facility, less Station Use, less Losses, expressed in kilowatt hour (kWh) delivered to Idaho Power at the Point of Delivery. Subject to the terms of this Agreement, Seller commits to deliver all Net Energy to Idaho Power at the Point of Delivery for the full term of the Agreement. Net Energy does not include Inadvertent Energy. 1.30 "Operation Date" - The day commencing at 00:01 hours, Mountain Time, following the day that all requirements of paragraph 5.2 have been completed. 1.31 "Point of Delivery" - The location specified in Appendix B, where Idao Power's and the Seller's electrical facilties are interconnected and the energy from this Facilty is delivered to the Idaho Power electrcal system. 1.32 "Prudent Electrical Practices" - Those practices, methods and equipment that are commonly and ordinly used in electrical engineerig and operations to operate electric equipment lawfully, safely, dependably, effciently and economically. 1.33 "Scheduled Operation Date" - The date specified in Appendix B when Seller anticipates achieving the Operation Date. It is expected that the Scheduled Operation Date provided by the Seller shall be a reasonable estimate of the date that the Seller anticipates that the Seller's Facilty shall achieve the Operation Date. 1.34 "Schedule 72" - Idao Power's Tariff No 101, Schedule 72 or its successor schedules as approved by the Commission. The Seller shall be responsible to pay all costs of interconnection and integration of this Facilty into the Idaho Power electrical system as specified within Schedule 72 and this Agreement. 1.35 "Season" - The three periods identified in paragraph 6.2.1 of this Agreement. -5- 111112010 1.36 "Special Facilties" - Additions or alterations of transmission and/or distribution lines and transformers as described in Schedule 72. 1.37 "Station Use" - Electrc energy that is used to operate equipment that is auxiliar or otherwise related to the production of electricity by the Facility. 1.38 "Suffcient Prie Mover" means wind speed that is (1) equal to or greater than the generation unit's manufactuer-specified minimum levels required for the generation unt to produce energy and (2) equal to or less than the generation unit's manufacturer-specified maximum levels at which the generation unit can safely produce energy. 1.39 "Surplus Energy" - All Net Energy produced by the Seller's Facility and delivered by the Facility to the Idaho Power electrical system prior to the Operation Date. 1.40 "Total Cost of the Facility" - The total cost of strctures, equipment and appurenances. 1.41 "Wind Energy Production Forecast" - A forecast of energy deliveries from this Facility provided by an Idao Power administered wind forecasting modeL. The Facilty shall be responsible for an allocated portion of the total costs of the forecasting model as specified in Appendix E. ARTICLE II: NO RELIANCE ON IDAHO POWER 2.1 Seller Independent Investigation - Seller warrants and represents to Idaho Power that in entering into this Agreement and the undertaking by Seller of the obligations set forth herein, Seller has investigated and determined that it is capable of performing hereunder and has not relied upon the advice, experience or expertise of Idaho Power in connection with the transactions contemplated by this Agreement. 2.2 Seller Independent Experts - All professionals or experts including, but not limited to, engineers, attorneys or accountants, that Seller may have consulted or relied on in underaking the transactions contemplated by this Agreement have been solely those of Seller. ARTICLE II: WARIES 3.1 No Warranty by Idaho Power - Any review, acceptance or failure to review Seller's design, specifications, equipment or facilities shall not be an endorsement or a confiration by Idao -6- 111112010 Power and Idao Power makes no waranties, expressed or implied, regarding any aspect of Seller's design, specifications, equipment or facilities, including, but not limited to, safety, durability, reliabilty, strength, capacity, adequacy or economic feasibilty. 3.2 Qualifyng Facilty Status - Seller warts that the Facility is a "Qualifyng Facilty," as that term is used and defined in 18 CFR 292.201 et seq. After initial qualification, Seller wil take such steps as may be required to maintain the Facility's Qualifyng Facility status durng the term of this Agreement and Seller's failure to maintain Qualifying Facilty status wil be a Material Breach of this Agreement. Idaho Power reserves the right to review the Facilty's Qualifyg Facility status and associated support and compliance documents at anytime durig the term of this Agreement. ARTICLE IV: CONDITIONS TO ACCEPTANCE OF ENERGY 4.1 Prior to the First Energy Date and as a condition of Idaho Power's acceptance of deliveries of energy from the Seller under this Agreement, Seller shall: 4.1.1 Submit proof to Idaho Power that all licenses, permits or approvals necessar for Seller's operations have been obtained from applicable federal, state or local authorities, including, but not limited to, evidence of compliance with Subpart B, 18 CFR 292.201 et seq. as a certified Qualifying Facility. 4.1.2 Opinion of Counsel- Submit to Idaho Power an Opinon Letter signed by an attorney admitted to practice and in good standing in the State of Idaho providing an opinion that Seller's licenses, perits and approvals as set forth in paragraph 4.1.1 above are legally and validly issued, are held in the name of the Seller and, based on a reasonable independent review, counsel is of the opinion that Seller is in substantial compliance with said permits as of the date of the Opinion Letter. The Opinon Letter wil be in a form acceptable to Idaho Power and wil acknowledge that the attorney renderig the opinion understands that Idaho Power is relying on said opinion. Idao Power's acceptace of the form wil not be unreasonably withheld. The Opinion Letter wil be governed by and -7- 111112010 shall be interpreted in accordance with the legal opinon accord of the American Bar Association Section of Business Law (1991). 4.1.3 Intial Capacity Determination - Submit to Idaho Power such data as Idao Power may reasonably require to perform the Initial Capacity Determination. Such data wil include but not be limited to, Nameplate Capacity, equipment specifications, prime mover data, resource characteristics, normal and/or average operating design conditions and Station Use data. Upon receipt of this information, Idaho Power wil review the provided data and if necessary, request additional data to complete the Initial Capacity Determination withi a reasonable time. 4.1.3.1 If the Maximum Capacity specified in Appendix B of this Agreement and the cumulative manufacture Nameplate Capacity rating of the individual generation units at this Facilty is less than 10 MW. The Seller shall submit detailed, manufacturer, verifiable data of the Nameplate Capacity ratings of the actual individual generation units to be installed at this Facility. Upon verification by Idaho Power that the data provided establishes the combined Nameplate Capacity rating of the generation units to be installed at this Facility is less than 10 MW, it wil be deemed that the Seller has satisfied the Initial Capacity Deterination for this Facility. 4.1.4 Nameplate Capacity - Submit to Idaho Power manufactuer's and engineerig documentation that establishes the Nameplate Capacity of each individual generation unit that is included within this entire Facilty. Upon receipt of this data, Idao Power shall review the provided data and determine if the Nameplate Capacity specified is reasonable based upon the manufactuer's specified generation ratings for the specific generation units. 4.1.5 Engineer's Certifications - Submit an executed Engieer's Certification of Design & Construction Adequacy and an Engineer's Certification of Operations and Maintenance (O&M) Policy as described in Commission Order No. 21690. These certificates wil be -8- 111112010 in the form specified in Appendix C but may be modified to the extent necessar to recognize the different engineerig disciplines providing the certificates. 4.1.6 Insurance - Submit written proof to Idaho Power of all insurance required in Aricle XIII. 4.1.7 Interconnection - Provide written confiration from Idao Power's delivery business unit that Seller has satisfied all interconnection requirements. 4.1.8 Network Resource Designation - The Seller's Facility has been designated as a network resource capable of deliverig firm energy up to the amount of the Maximum Capacity. 4.1.9 Written Acceptance - Request and obtain written confiration from Idaho Power that all conditions to acceptance of energy have been fulfilled. Such written confiration shall be provided within a commercially reasonable time following the Seller's request and wil not be uneasonably withheld by Idaho Power. ARTICLE V: TERM AN OPERATION DATE 5.1 Term - Subject to the provisions of paragraph 5.2 below, this Agreement shall become effective on the date first written and shall continue in full force and effect for a period of 20 Contract Years from the Operation Date. 5.2 Operation Date - The Operation Date may occur only after the Facility has achieved all of the following: a) Achieved the First Energy Date. b) Commission approval of this Agreement in a form acceptable to Idaho Power has been received. c) Seller has demonstrated to Idaho Power's satisfaction that the Facility is complete and able to provide energy in a consistent, reliable and safe manner. d) Seller has requested an Operation Date from Idao Power in a written format. e) Seller has received written confiration from Idao Power of the Operation Date. This confirmation wil not be unreasonably withheld by Idao Power. 5.3 Operation Date Delay - Seller shall cause the Facility to achieve the Operation Date on or before -9- 111112010 the Scheduled Operation Date. Delays in the interconnection and trasmission network upgrade study, design and constrction process that are not Force Majeure events accepted by both Paries, shall not prevent Delay Liquidated Damages from being due and owing as calculated in accordace with this Agreement. 5.3.1 If the Operation Date occurs after the Scheduled Operation Date but on or prior to 90 days following the Scheduled Operation Date, Seller shall pay Idaho Power Delay Liquidated Damages calculated at the end of each calenda month after the Scheduled Operation Date as follows: Delay Liquidated Damages are equal to ((Curent month's Initial Year Net Energy Amount as specified in paragraph 6.2.1 divided by the number of days in the curent month) multiplied by the number of days in the Delay Period in the current month) multiplied by the curent month's Delay Price. 5.3.2 If the Operation Date does not occur within ninety (90) days following the Scheduled Operation Date, the Seller shall pay Idaho Power Delay Liquidated Damages, in addition to those provided in pargraph 5.3.1, calculated as follows: Forty five dollars ($45) multiplied by the Maximum Capacity with the Maximum Capacity being measured in kW. 5.4 If Seller fails to achieve the Operation Date withi ninety (90) days following the Scheduled Operation Date, such failure wil be a Materal Breach and Idaho Power may terminate this Agreement at any time until the Seller cures the Material Breach. Additional Delay Liquidated Damages beyond those calculated in 5.3.1 and 5.3.2 wil be calculated and payable using the Delay Liquidated Damage calculation described in 5.3.1 above for all days exceeding 90 days past the Scheduled Operation Date until such time as the Seller cures this Material Breach or Idaho Power terminates this Agreement. 5.5 Seller shall pay Idaho Power any calculated Delay Liquidated Damages within 7 days of when Idaho Power calculates and presents any Delay Liquidated Damages bilings to the Seller. Seller's failure to pay these damages within the specified time wil be a Material Breach of this -10- 111112010 Agreement and Idaho Power shall draw fuds from the Delay Securty provided by the Seller in an amount equal to the calculated Delay Liquidated Damages. 5.6 The Paries agree that the damages Idao Power would incur due to delay in the Facility achieving the Operation Date on or before the Scheduled Operation Date would be difficult or impossible to predict with certainty, and that the Delay Liquidated Damages are an appropriate approxiation of such daages. 5.7 Prior to the Seller executing this Agreement, the Seller shall have agreed to and executed a Letter of Understanding with Idaho Power that contains at minimum the following requirements: a) Seller has fied for interconnection and is in compliance with all payments and requirements of the interconnection process b) Seller has received and accepted an interconnection system impact study for this Facility. c) Seller has provided all information required to enable Idao Power to file an initial transmission capacity request. d) Results of the initial transmission capacity request are known and acceptable to the Seller. e) Seller acknowledges responsibilty for all interconnection costs and any costs associated with acquirng adequate firm transmission capacity to enable the project to be classified as an Idao Power designated firm network resource. f) If the Facilty is located outside of the Idaho Power servce terrtory, in addition to the above requirements, the Seller must provide evidence that the Seller has acquired firm transmission capacity from all required transmitting entities to deliver the Facility's energy to an acceptable point of delivery on the Idaho Power electrcal system. 5.8 Within thirty (30) days of the date of a finl non-appealable Commission Order as specified in Aricle XXI approving this Agreement; Seller shall post liquid securty ("Delay Securty") in a form as described in Appendix D equal to or exceeding the amount calculated in paragraph 5.8.1. -11- 111112010 Failure to post this Delay Securty in the time specified above will be a Material Breach of this Agreement and Idaho Power may terminate this Agreement. 5.8.1 Delay Security The greater of forty five ($45) multiplied by the Maximum Capacity with the Maximum Capacity being measured in kW or the sum of three month's estimated revenue. Where the estimated three months of revenue is the estimated revenue associated with the first three full months following the estimated Scheduled Operation Date, the estimated kWh of energy production as specified in paragraph 6.2.1 for those three months multiplied by the All Hours Energy Price specified in paragrph 7.3 for each of those three months. 5.8.1.1 In the event (a) Seller provides Idaho Power with cerification that (1) a generation interconnection agreement specifyng a schedule that wil enable this Facility to achieve the Operation Date no later than the Scheduled Operation Date has been completed and the Seller has paid all required interconnection costs or (2) a generation interconnection agreement is substantially complete and all material costs of interconnection have been identified and agreed upon and the Seller is in compliance with all terms and conditions of the generation interconnection agreement, the Delay Security calculated in accordace with paragraph 5.8.1 wil be reduced by ten percent (10%). 5.8.1.2 If the Seller has received a reduction in the calculated Delay Securty as specified in paragraph 5.8.1.1 and subsequently (1) at Seller's request, the generation interconnection agreement specified in paragraph 5.8.1.1 is revised and as a result the Facilty wil not achieve its Operation Date by the Scheduled Operation Date, or (2) if the Seller does not maintain compliance with the generation interconnection agreement, the full amount of the Delay Securty as calculated in paragraph 5.8.1 wil be subject to reinstatement and wil be due and owing within 5 business days from the date Idaho Power requests reinstatement. Failure to timely reinstate the Delay Securty wil be a Material Breach of this Agreement. -12- 111112010 5.8.2 Idaho Power shall release any remaining security posted hereunder afer all calculated Delay Liquidated Damages are paid in full to Idaho Power and the earlier of: 1) 30 days after the Operation Date has been achieved, or 2) 60 days after the Agreement has been terminated. ARTICLE VI: PURCHASE AND SALE OF NET ENERGY 6.1 Deliveiy and Acceptance of Net Energy - Except when either Par's performance is excused as provided herein, Idaho Power wil purchase and Seller wil sell all of the Net Energy to Idaho Power at the Point of Delivery. All Inadvertent Energy produced by the Facilty wil also be delivered by the Seller to Idaho Power at the Point of Delivery. At no time wil the total amount of Net Energy and/or Inadvertent Energy produced by the Facilty and delivered by the Seller to the Point of Delivery exceed the Maxmum Capacity Amount. 6.2 Net Energy Amounts - Seller intends to produce and deliver Net Energy in the following monthly amounts. These amóunts shall be consistent with the Mechanical Availabilty Guaantee. 6.2.1 Initial Year Monthly Net Energy Amounts: Month Season 1 March April May Season 2 July August November December Season 3 June September October Januar Februar kWh 4,036,000 4,042,000 4,727,000 3,392,000 3,775,000 4,348,000 5,022,000 4,150,000 5,082,000 5,918,000 3,275,000 3,675,000 6.3 Unless excused by an event of Force Majeure, Seller's failure to deliver Net Energy in any Contract Year in an amount equal to at least ten percent (10%) of the sum of the Initial Year Monthly Net Energy Amounts as specified in paragraph 6.2 shall constitute an event of default. -13- 111112010 6.4 Mechanical Availability Guarantee - Afer the Operational Date has been established, the Facility shall achieve a minimum monthly Mechanical Availability of 85% for the Facilty for each month during the full term of this Agreement (the "Mechancal Availabilty Guarantee"). Failure to achieve the Mechanical Availability Guarantee shall result in Idao Power calculating daages as specified in paragraph 6.4.4. 6.4.1 At the same time the Seller provides the Monthly Power Production and Availabilty Report (Appendix A), the Seller shall provide and certify the calculation of the Facilty's current month's Mechanical Availability. The Seller shall include a sumar of all information used to calculate the Calculated Net Energy Amount including but not limited to: (a) Forced Outages, (b) Force Majeure events, (c) wind speeds and the impact on generation output, and (c) scheduled maintenance and Station Use information. 6.4.2 The Seller shall maintain and retain for three years detailed documentation supporting the monthly calculation of the Facilty's Mechancal Availabilty. 6.4.3 Idaho Power shall have the right to review and audit the documentation supporting the calculation of the Facility's Mechanical Availabilty at reasonable times at the Seller's offces. 6.4.4 If the current month's Mechanical Availabilty is less than the Mechanical Availability Guarantee, damages shall be equal to: ((85 percent of the month's Calculated Net Energy Amount) mius the month's actual Net Energy deliveries) multiplied by the Availabilty Shortfall Price. 6.4.5 Any damages calculated in paragraph 6.4.4 wil be offset against the curent month's energy payment. If an unpaid balance remains after the damages are offset against the energy payment, the Seller shall pay in full the remaining balance within 30 days of the date of the invoice. -14- 111112010 ARTICLE VII: PURCHASE PRICE AN METHOD OF PAYMENT 7.1 Heayy Load Purchase Price - For all Net Energy received durng Heavy Load Hours, Idaho Power wil pay the non-levelized energy price in accordance with Commission Order 31025 adjusted in accordace with Commission Order 30415 for Heavy Load Hour Energy deliveries, adjusted in accordance with Commission Order 30488 for the wind integration charge, and with seasonalization factors applied: Year Season 1 - (73.50 %) Mils/kWh Season 2 - (120.00 %) Mils/kWh Season 3 - (100.00 %) Mils/kWh 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 40.52 42.80 45.32 47.71 50.29 53.05 54.64 56.20 57.90 59.57 61.29 63.33 65.46 67.67 69.97 72.35 74.38 76.62 78.96 81.38 83.87 87.22 90.15 93.19 66.15 69.87 74.00 78.18 82.74 87.64 90.46 93.23 96.25 99.21 102.27 105.90 109.67 113.59 117.66 121.90 125.49 129.20 133.03 136.97 141.04 146.51 151.30 156.26 55.12 58.24 61.66 64.92 68.42 72.17 74.34 76.61 79.12 81.59 84.14 87.16 90.31 93.57 96.97 100.50 103.49 106.58 109.77 113.06 116.45 121.01 125.00 129.13 7.2 Light Load Purchase Price - For all Net Energy received during Light Load Hours, Idaho Power wil pay the non-levelized energy price in accordance with Commission Order 31025 adjusted in accordance with Commission Order 30415 for Light Load Hour Energy deliveries, adjusted in accordance with Commission Order 30488 for the wind integration charge, and with -15- 111112010 seasonalization factors applied: Season 1 - (73.50 %)Season 2 - (120.00 %)Season 3 - (100.00 %) Year Mils/kWh Mils/kWh Mils/kWh 2010 35.59 58.1 1 48.42 2011 37.88 61.84 51.54 2012 40.40 65.95 54.96 2013 42.79 69.86 58.22 2014 45.37 74.06 61.72 2015 48.13 78.91 65.48 2016 49.72 81.73 67.64 2017 51.28 84.50 69.76 2018 52.97 87.51 72.07 2019 54.65 90.47 74.35 2020 56.37 93.53 76.86 2021 58.41 97.16 79.88 2022 60.54 100.93 83.03 2023 62.74 104.85 86.29 2024 65.04 108.92 89.69 2025 67.43 113.16 93.22 2026 69.45 116.76 96.21 2027 71.55 120.47 99.30 2028 73.70 124.29 102.49 2029 76.03 128.24 105.78 2030 78.52 132.31 109.1 7 2031 81.87 137.77 113.73 2032 84.80 142.56 117.72 2033 87.84 147.52 121.85 7.3 All Hour Energy Price - The price to be used in the calculation of the Surlus Energy Price and Delay Price shall be the non-levelized energy price in accordance with Commission Order 31025 adjusted in accordance with Commssion Order 30488 for the wind integration charge, and with seasonalization factors applied: Year Season 1 - (73.50 %) Mils/kWh Season 2 - (120.00 %) Mils/kWh Season 3 - (100.00 %) Mils/kWh 2010 2011 2012 2013 2014 2015 38.33 40.61 43.13 45.52 48.10 50.86 62.57 66.30 70.42 74.33 78.85 83.75 52.14 55.26 58.68 61.93 65.44 69.19 -16- 111112010 2016 52.45 86.58 71.36 2017 54.01 89.35 73.48 2018 55.71 92.36 75.88 2019 57.37 95.32 78.35 2020 59.10 98.38 80.90 2021 61.14 102.01 83.92 2022 63.27 105.78 87.07 2023 65.48 109.70 90.33 2024 67.78 113.77 93.73 2025 70.16 118.01 97.26 2026 72.18 121.60 100.25 2027 74.28 125.31 103.35 2028 76.58 129.14 106.53 2029 79.00 133.09 109.82 2030 81.49 137.16 113.21 2031 84.84 142.62 117.77 2032 87.77 147.41 121.76 2033 90.81 152.37 125.89 7.4 Surlus Energy Price - For all Surplus Energy, Idaho Power shall pay to the Seller the curent month's Market Energy Reference Price or the All Hours Energy Price specified in pargraph 7.3, whichever is lower. 7.5 Inadvertent Energy - 7.5.1 Inadvertent Energy is electric energy produced by the Facility, expressed in kWh, which the Seller delivers to Idaho Power at the Point of Delivery that exceeds 10,000 kW multiplied by the hours in the specific month in which the energy was delivered. (For example Januar contains 744 hours. 744 hours times 10,000 kW = 7,440,000 kWh. Energy delivered in January in excess of 7,440, 000 kWh in this example would be Inadvertent Energy.) 7.5.2 Although Seller intends to design and operate the Facilty to generate no more than 10 average MW and therefore does not intend to generate Inadvertent Energy, Idaho Power wil accept Inadvertent Energy that does not exceed the Maximum Capacity Amount but wil not purchase or pay for Inadvertent Energy. 7.6 Payment Due Date - Undisputed Energy payments, less the Wind Energy Production Forecasting Monthly Cost Allocation (MCA) described in Appendix E and any other payments due Idao -17- 111112010 Power, wil be disbursed to the Seller withi 30 days of the date which Idaho Power receives and accepts the documentation of the monthly Mechanical Available Guarntee and the Net Energy actully delivered to Idaho Power as specified in Appendix A. 7.7 Continuing Jurisdiction of the Commission - This Agreement is a special contract and, as such, the rates, ters and conditions contained in this Agreement wil be construed in accordance with Idaho Power Company v. Idaho Public Utilties Commission and Afton Energy Inc., 107 Idaho 781, 693 P.2d 427 (1984), Idaho Power- Company v. Idao Public Utilties Commission, 107 Idaho 1122,695 P.2d 1 261 (1985), Afton Energy, Inc, v. Idao Power Company, 111 Idao 925, 729 P .2d 400 (1986), Section 210 of the Public Utility Regulatory Policies Act of 1978 and 18 CFR §292.303-308. ARTICLE VII: ENVIRONMENTAL ATTRIUTES 8.1 Seller retains ownership under this Agreement of Green Tags and Renewable Energy Certificates (RECs), or the equivalent environmental attributes, directly associated with the production of energy from the Seller's Facility sold to Idaho Power. ARTICLE IX: FACILITY AN INERCONNCTION 9.1 Design of Facility - Seller wil design, construct, install, own, operate and maintain the Facility and any Seller-owned Interconnection Facilities so as to allow safe and reliable generation and delivery of Net Energy and Inadvertent Energy to the Idaho Power Point of Delivery for the full term of the Agreement. 9.2 Interconnection Facilties - Except as specifically provided for in this Agreement, the required Interconnection Facilities wil be in accordance with Schedule 72, the Generation Interconnection Process and Appendix B. The Seller is responsible for all costs associated with this equipment as specified in Schedule 72 and the Generation Interconnection Process, including but not limited to initial costs incurred by Idaho Power for equipment costs, installation costs and ongoing monthly Idaho Power operations and maintenance expenses. -18- 111112010 ARTICLE X: METERIG AND TELEMETRY 10.1 Metering - Idaho Power shall, for the account of Seller, provide, install, and maintain Meterg and Telemetry Equipment to be located at a mutually agreed upon location to record and measure power flows to Idaho Power in accordace with this Agreement and Schedule 72. The Meterng Equipment wil be at the location and the type required to measure, record and report the Facility's Net Energy, Station Use, Inadvertent Energy and maximum energy deliveries (kW) at the Point of Delivery in a maner to provide Idaho Power adequate energy measurement data to administer this Agreement and to integrate this Facility's energy production into the Idaho Power electrical system. 10.2 Telemetry - Idaho Power wil install, operate and maintain at Seller's expense meterig, communications and telemetry equipment which wil be capable of providing Idaho Power with continuous instataneous telemetry of Seller's Net Energy and Inadvertent Energy produced and delivered to the Idaho Power Point of Delivery to Idaho Power's Designated Dispatch Facilty. ARTICLE XI - RECORDS 11.1 Maintenance of Records - Seller shall maintain at the Facility or such other location mutually acceptable to the Paries adequate total generation, Net Energy, Station Use, Inadvertent Energy and maximum generation (kW) records in a form and content acceptable to Idaho Power. 11.2 Inspection - Either Party, after reasonable notice to the other Pary, shall have the right, durg normal business hours, to inspect and audit any or all generation, Net Energy, Station Use, Inadvertent Energy and maximum generation (kW) records pertaining to the Seller's Facilty. ARTICLE XII: OPERATIONS 12.1 Communications - Idaho Power and the Seller shall maintain appropriate operating communications through Idaho Power's Designated Dispatch Facility in accordace with Appendix A of this Agreement. 12 .2 Energy Acceptance - -19- 111112010 12.2.1 Idaho Power shall be excused from accepting and paying for Net Energy or accepting Inadvertent Energy which would have otherwise been produced by the Facilty and delivered by the Seller to the Point of Delivery, if it is prevented from doing so by an event of Force Majeure, Forced Outage or temporar disconnection of the Facilty in accordance with Schedule 72. If, for reasons other than an event of Force Majeure or a Forced Outage, a temporary disconnection under Schedule 72 exceeds twenty (20) days, beginning with the twenty-first day of such interption, curailment or reduction, Seller wil be deemed to be delivering Net Energy at a rate equivalent to the pro rata daily average of the amounts specified for the applicable month in paragraph 6.2. Idaho Power wil notify Seller when the interrption, curailment or reduction is terminated. 12.2.2 If, in the reasonable opinion of Idaho Power, Seller's operation of the Facility or Interconnection Facilities is unsafe or may otherwise adversely affect Idao Power's equipment, personnel or service to its customers, Idao Power may temporarly disconnect the Facility from Idaho Power's transmission/distribution system as specified within Schedule 72 or take such other reasonable steps as Idaho Power deems appropriate. 12.2.3 Under no circumstances wil the Seller deliver Net Energy and/or Inadvertent Energy from the Facility to the Point of Delivery in an amount that exceeds the Maximum Capacity Amount at any moment in time. Seller's failure to limit deliveries to the Maximum Capacity Amount wil be a Material Breach of this Agreement. 12.2.4 If Idaho Power is unable to accept the energy from this Facility and is not excused from accepting the Facilty's energy, Idaho Power's damages shall be limited to only the value of the estimated energy that Idao Power was unable to accept. Idaho Power wil have no responsibilty to pay for any other costs, lost revenue or consequential damages the Facilty may incur. 12.3 Scheduled Maintenance - On or before Januar 31 of each calendar year, Seller shall submit a written proposed maintenance schedule of significant Facility maintenance for that calenda year -20- 111112010 and Idao Power and Seller shall mutually agree as to the acceptability of the proposed schedule. The Paries determination as to the acceptabilty of the Seller's timetable for scheduled maintenance wil take into consideration Prudent Electrical Practices, Idaho Power system requirements and the Seller's preferred schedule. Neither Pary shall uneasonably withhold acceptance of the proposed maintenance schedule. 12.4 Maintenance Coordiation - The Seller and Idao Power shall, to the extent practical, coordinate their respective line and Facilty maintenance schedules such that they occur simultaneously. 12.5 Contact Prior to Curailment - Idaho Power wil make a reasonable attempt to contact the Seller prior to exercising its rights to interrpt interconnection or curail deliveries from the Seller's Facilty. Seller understands that in the case of emergency circumstances, real time operations of the electrical system, and/or unplaned events Idaho Power may not be able to provide notice to the Seller prior to interrption, curtailment, or reduction of electrical energy deliveries to Idaho Power. ARTICLE XII: INEMNIFICATION AN INSURCE 13.1 Indemnification - Each Party shall agree to hold harless and to indemnify the other Party, its officers, agents, affliates, subsidiares, parent company and employees against all loss, damage, expense and liabilty to third persons for injury to or death of person or injur to property, proximately caused by the indemnifying Pary's (a) construction, ownership, operation or maintenance of, or by failure of, any of such Pary's works or facilties used in connection with this Agreement or (b) negligent or intentional acts, errors or omissions. The indemnifying Pary shall, on the other Pary's request, defend any suit asserting a claim covered by this indemnty. The indemnifying Party shall pay all documented costs, including reasonable attorney fees that may be incurred by the other Pary in enforcing this indemnity. 13.2 Insurance - Durng the term of this Agreement, Seller shall secure and continuously car the following insurce coverage: 13.2.1 Comprehensive General Liability Insurance for both bodily injury and property daage -21- 111112010 with limits equal to $1,000,000, each occurrence, combined single limit. The deductible for such insurance shall be consistent with current Insurance Industr Utilty practices for similar property. 13.2.2 The above insurance coverage shall be placed with an insurance company with an A.M. Best Company rating of A- or better and shall include: (a) An endorsement naming Idaho Power as an additional insured and loss payee as applicable; and (b) A provision stating that such policy shall not be canceled or the limits of liabilty reduced without sixty (60) days' prior wrtten notice to Idaho Power. 13.3 Seller to Provide Certificate of Insurance - As required in paragraph 4.1.6 herein and anually thereafter, Seller shall fuish Idao Power a certificate of insurance, together with the endorsements required therein, evidencing the coverage as set forth above. 13.4 Seller to Notify Idaho Power of Loss of Coverage - If the insurance coverage required by paragraph 13.2 shall lapse for any reason, Seller wil imediately notify Idao Power in writing. The notice wil advise Idaho Power of the specific reason for the lapse and the steps Seller is taking to reinstate the coverage. Failure to provide this notice and to expeditiously reinstate or replace the coverage wil constitute a Material Breach of this Agreement. ARTICLE XIV: FORCE MAJUR 14.1 As used in this Agreement, "Force Majeure" or "an event of Force Majeure" means any cause beyond the control of the Seller or of Idaho Power which, despite the exercise of due diligence, such Pary is unable to prevent or overcome. Force Majeure includes, but is not limited to, acts of God, fire, flood, storms, wars, hostilties, civil strife, strikes and other labor disturbances, earthquakes, fires, lightning, epidemics, sabotage, or changes in law or regulation occurrng after the Effective Date, which, by the exercise of reasonable foresight such pary could not reasonably have been expected to avoid and by the exercise of due dilgence, it shall be unable to overcome. If either Pary is rendered wholly or in par unable to perform its obligations under this -22- 111112010 Agreement because of an event of Force Majeure, both Paries shall be excused from whatever performance is affected by the event of Force Majeure, provided that: (l) The non-performing Pary shall, as soon as is reasonably possible after the occurrence of the Force Majeure, give the other Part wrtten notice describing the paricular of the occurence. (2) The suspension of performance shall be of no greater scope and of no longer duration than is required by the event of Force Majeure. (3) No obligations of either Party which arose before the occurrence causing the suspension of performance and which could and should have been fully performed before such occurence shall be excused as a result of such occurence. ARTICLE XV: LIAILITY; DEDICATION 15.1 Limitation of Liabilty. Nothing in this Agreement shall be construed to create any duty to, any standard of care with reference to, or any liabilty to any person not a Pary to this Agreement. Neither pary shall be liable to the other for any indirect, special, consequential, nor puntive damages, except as expressly authorized by this Agreement. 15.2 Dedication. No undertakg by one Pary to the other under any provision of this Agreement shall constitute the dedication of that Pary's system or any portion thereof to the Party or the public or affect the status of Idaho Power as an independent public utilty corporation or Seller as an independent individual or entity. ARTICLE XVI: SEVERA OBLIGATIONS 16.1 Except where specifically stated in this Agreement to be otherwise, the duties, obligations and liabilties of the Paries are intended to be several and not joint or collective. Nothing contained in this Agreement shall ever be construed to create an association, trst, parership or joint venture or impose a trst or parnership duty, obligation or liabilty on or with regard to either Party. Each Pary shall be individually and severally liable for its own obligations under this -23- 111112010 Agreement. ARTICLE XVII: WAIER 17.1 Any waiver at any time by either Party of its rights with respect to a default under this Agreement or with respect to any other matters arsing in connection with this Agreement shall not be deemed a waiver with respect to any subsequent default or other matter. ARTICLE XVII: CHOICE OF LAWS AN VENU 18.1 This Agreement shall be construed and interpreted in accordance with the laws ofthe State of Idaho without reference to its choice of law provisions. 18.2 Venue for any litigation arsing out of or related to this Agreement wil lie in the Distrct Cour of the Four Judicial District ofIdaho in and for the County of Ada. ARTICLE XIX: DISPUTES AN DEFAULT 19.1 Disputes - All disputes related to or arsing under this Agreement, including, but not limited to, the interpretation of the terms and conditions of this Agreement, wil be submitted to the Commission for resolution. 19.2 Notice of Default 19.2.1 19.2.2 Defaults. If either Party fails to perform any of the terms or conditions of this Agreement (an "event of default"), the non-defaulting Pary shall cause notice in writing to be given to the defaulting Pary, specifyng the manner in which such default occured. If the defaulting Pary shall fail to cure such default within the sixty (60) days after servce of such notice, or if the defaulting Party reasonably demonstrates to the other Pary that the default can be cured within a commercially reasonable time but not within such sixty (60) day period and then fails to dilgently pursue such cure, then, the non-defaulting Pary may, at its option, termate this Agreement and/or pursue its legal or equitable remedies. Material Breaches - The notice and cure provisions in paragraph 19.2.1 do not apply -24- 111112010 to defaults identified in this Agreement as Material Breaches. Material Breaches must be cured as expeditiously as possible following occurrence of the breach. 19.3 Security for Performance - Prior to the Operation Date and thereafter for the full term of this Agreement, Seller wil provide Idao Power with the following: 19.3.1 19.3.2 19.3.3 Insurance - Evidence of compliance with the provisions of paragraph 13.2. If Seller fails to comply, such failure wil be a Material Breach and may only be cured by Seller supplying evidence that the required insurce coverage has been replaced or reinstated; Engineer's Certifications - Every three (3) years after the Operation Date, Seller wil supply Idaho Power with a Certification of Ongoing Operations and Maintenance (O&M) from a Registered Professional Engieer licensed in the State of Idaho, which Certification of Ongoing 0 & M shall be in the form specified in Appendix C. Seller's failure to supply the required certificate wil be an event of default. Such a default may only be cured by Seller providing the required certificate; and Licenses and Permits - Durig the full term of this Agreement, Seller shall maintai compliance with all permits and licenses described in paragraph 4.1.1 of this Agreement. In addition, Seller wil supply Idaho Power with copies of any new or additional permits or licenses. At least every fifth Contract Year, Seller wil update the documentation described in Paragraph 4.1.1. If at any time Seller fails to maintain compliance with the permits and licenses described in paragraph 4.1.1 or to provide the documentation required by this paragraph, such failure wil be an event of default and may only be cured by Seller submitting to Idaho Power evidence of compliance . from the permitting agency. ARTICLE XX: GOVERNENTAL AUTHORIATION 20.1 This Agreement is subject to the jurisdiction of those governental agencies having control over either Pary of this Agreement. -25- 111112010 ARTICLE XXI: COMMISSION ORDER 21.1 This Agreement shall become finally effective upon the Commission's approval of all terms and provisions hereof without change or condition and declartion that all payments to be made to Seller hereunder shall be allowed as prudently incured expenses for ratemakng purposes. ARTICLE XXII: SUCCESSORS AN ASSIGNS 22.1 This Agreement and all of the terms and provisions hereof shall be binding upon and inure to the benefit of the respective successors and assigns of the Parties hereto, except that no assignent hereof by either Party shall become effective without the written consent of both Parties being first obtained. Such consent shall not be unreasonably withheld. Notwithstanding the foregoing, any pary which Idaho Power may consolidate, or into which it may merge, or to which it may conveyor transfer substantially all of its electric utilty assets, shall automatically, without fuher act, and without need of consent or approval by the Seller, succeed to all ofIdaho Power's rights, obligations and interests under this Agreement. This article shall not prevent a financing entity with recorded or secured rights from exercising all rights and remedies available to it under law or contract. Idaho Power shall have the right to be notified by the financing entity that it is exercising such rights or remedies. ARTICLE XXII: MODIFICATION 23.1 No modification to this Agreement shall be valid unless it is in writing and signed by both Paries and subsequently approved by the Commission. ARTICLE XXIV: TAXES 24.1 Each Pary shall pay before delinquency all taxes and other governental charges which, if failed to be paid when due, could result in a lien upon the Facility or the Interconnection Facilities. ARTICLE XXV: NOTICES 25.1 All written notices under this Agreement shall be directed as follows and shall be considered -26- 111112010 delivered when faxed, e-mailed and confirmed with deposit in the U.S. Mail, first-class, postage prepaid, as follows: To Seller: Original document to: Desert Meadow Windfar, LLC Attention: Maurice Miler, Authorized Manager 3145 Gear Blvd., #723 San Francisco, CA 94118 E-mail: maur(£envisionwind.com To Idaho Power: Original document to: Vice President, Power Supply Idaho Power Company POBox 70 Boise, Idaho 83707 Email: Lgrow(£idahopower.com Copy of document to: Cogeneration and Small Power Production Idaho Power Company POBox 70 Boise, Idaho 83707 E-mail: rallphi(gidaopower.com Either Pary may change the contact person and/or address information listed above, by providing wrtten notice from an authorized person representing the Par. ARTICLE XXVI: ADDITIONAL TERMS AN CONDITIONS 26.1 This Agreement includes the following appendices, which are attached hereto and included by reference: Appendix A AppendixB AppendixC AppendixD AppendixE Monthly Power Production and Availability Report Facility and Point of Deliver Engineer's Certifications Forms of Liquid Security Wind Energy Production Forecasting -27- 111112010 ARTICLE XXVII: SEVERAILITY 27.1 The invalidity or unenforceabilty of any term or provision of this Agreement shall not affect the validity or enforceability of any other ters or provisions and this Agreement shall be constred in all other respects as if the invalid or unenforceable term or provision were omitted. ARTICLE XXVII: COUNERPARTS 28.1 This Agreement may be executed in two or more counterparts, each of which shall be deemed an original but all of which together shall constitute one and the same instrument. ARTICLE XXIX: ENTIR AGREEMENT 29.1 This Agreement constitutes the entire Agreement of the Paries concering the subject matter hereof and supersedes all prior or contemporaneous oral or wrtten agreements between the Parties concernng the subject matter hereof. IN WITNESS WHEREOF, The Paries hereto have caused this Agreement to be executed in their respective names on the dates set forth below: Idaho Power Company Desert Meadow Windfar, LLC By YAisaj Û. &0- BY/~2eLD V Lisa A Grow ~ G eon S. IkemotoSr. Vice President, Power Supply Authorized Manager Dated I ¡. It:. 10 Dated // - 2, -, ¿ D / 0 "Idaho Power""Seller" -28- 111112010 APPENDIX A A -1 MONTHLY POWER PRODUCTION AN AVAIABILITY REPORT At the end of each month the following required documentation wil be submitted to: Idaho Power Company Attn: Cogeneration and Small Power Production POBox 70 Boise, Idaho 83707 The meter readings required on this report wil be the readings on the Idaho Power Meter Equipment measurng the Facility's total energy production delivered to Idaho Power and Station Usage and the maximum generated energy (kW) as recorded on the Meterg Equipment and/or any other required energy measurements to adequately administer this Agreement. This document shall be the document to enable Idaho Power to begin the energy payment calculation and payment process. The meter readings on this report shall not be used to calculate the actual payment, but instead wil be a check of the automated meter reading information that wil be gathered as described in item A-2 below: Ths report shall also include the Seller's calculation of the Mechanical Availabilty. -29- 111112010 Idaho Power Company Cogeneration and Small Power Producton MONTHLY POWER PRODUCTION AND AVAIABILITY REPORT Month Year Project Name Project Number: Address Phone Number: City State Zip Net Facilty Output Station Usage Station Usage Metered Maximum Generation Meter Number: End of Month kWh Meter Reading: Beginnng of Month kWh Meter: Difference: Times Meter Constant: kW Net Generation kWh for the Month: Metered Demand: Mechanical Availabilty Guarantee Seller Calculated Mechanical Availabilty As specified in this Agreement, the Seller shall include with this monthly report a summary statement of the Mechanical Availabilty of this Facilty for the calendar month. This summary shall include details as to how the Seller calculated this value and summary of the Facilty data used in the calculation. Idaho Power and the Seller shall work together to mutually develop a summary report that provides the required data. Idaho Power reserves the right to review the detailed data used in this calculation as allowed withi the Agreement. Signature Date -30- 111112010 A-2 AUTOMATED METER READING COLLECTION PROCESS Monthly, Idaho Power wil use the provided Metering and Telemetry equipment and processes to collect the meter reading information from the Idaho Power provided Metering Equipment that measures the Net Energy and energy delivered to supply Station Use for the Facilty recorded at 12:00 AM (Midnight) of the last day of the month.. The meter information collected wil include but not be limited to energy production, Station Use, the maximum generated power (kW) and any other required energy measurements to adequately admnister this Agreement. A-3 ROUTIN REPORTING Idao Power Contact Information Daily Energy Production Reporting Call daily by 10 a.m., 1-800-356-4328 or 1-800-635-1093 and leave the following information: · Project Identification - Project Name and Project Number . Current Meter Reading · Estimated Generation for the current day · Estimated Generation for the next day Planed and Unplaned Project outages Call 1-800-345-1319 and leave the following information: · Project Identification - Project Name and Project Number . Approximate time outage occurred Estimated day and time of project coming back online Seller's Contact Information 24-Hour Project Operational Contact Name: Telephone Number: Cell Phone: Glenn Ikemoto 510 655-7600 510 384-0671 Project On-site Contact information Telephone Number: -31- 111112010 APPENDIXB FACILITY AN POIN OF DELIVERY Project Name: Deser Meadow Windfar Project Number: 21615120 B-1 DESCRIPTION OF FACILITY (Must include the Nameplate Capacity rating and V AR capability (both leading and lagging) of all generation units to be included in the Facilty.) The Facilty wil be comprised of approximately 10 wind tubines with a cumulative nameplate rating that wil not exceed the Maximum Capacity Amount as specified in item B-4 and not less than 18 MW. At the time this Agreement was executed, selection of the turbine manufacturer had not been finalized by the Seller. No later than 60 days prior to the Facility achieving its First Energy Date, the Seller shall provide Idaho Power a precise, detailed description of the wind turbines selected and quantity. The Facility is curently considering use of up to 11 REpower MM92 wind turbines (Nameplate Capacity rating up to 2.05MW/turbine, 0.95 leadlO.95 lag power factor), or up to 10 Siemens SW 101 wind turbines (Nameplate Capacity rating up to 2.30MW /turbine, 0.90 leadlO.90 lag power factor), or other wind turbine models. B-2 LOCATION OF FACILITY Near: Mountain Home, ID T4S R8E SEC 24, 25, 26 T4S R9E SEC 19 County: Elmore, ID. Description of Interconnection Location: The Facility wil interconnect to the Idaho Power transmission system at 230 kV with a tap at T4S, R9E, SEC 21, Elmore County, ID, or other location specified in the interconnection agreement. Nearest Idao Power Substation: King Substation, Elmore County, ID -32- 111112010 B-3 SCHEDULED FIRST ENERGY AN OPERATION DATE Seller has selected December 31,2011 as the Scheduled First Energy Date. Seller has selected December 31, 2012 as the Scheduled Operation Date. In making these selections, Seller recognizes that adequate testing of the Facility and completion of all requirements in paragraph 5.2 of this Agreement must be completed prior to the project being granted an Operation Date. B-4 MAXIMUM CAPACITY AMOUN: This value wil be 23 MW which is consistent with the value provided by the Seller to Idao Power in accordance with Schedule 72. This value is the maximum energy (MW) that potentially could be delivered by the Seller's Facility to the Idao Power electrical system at any moment in time. At the time this Agreement was executed the Seller had requested only 20 MW of capacity in the interconnection and transmission capacity process. Prior to the project delivering energy that exceeds 20 MW, the Seller must request and be granted additional capacity up to but not exceeding 3 MW in both interconnection and transmission capacity by Idaho Power. The Seller must make this additional capacity request using the routine Idaho Power interconnection and transmission capacity process and shall be responsible for all costs associated with this additional capacity request. Under no circumstances wil the Nameplate Capacity of this Facility exceed 23 MW. If the installed capacity is less than the Maximum Capacity Amount at the end of the first Contract Year, the Maximum Capacity Amount wil be adjusted downward to reflect the actual nameplate rating of the wind tubines installed. This revised Maximum Capacity Amount wil then remain in effect for the remaining term of this Agreement. B-5 POIN OF DELIVERY "Point of Delivery" means, unless otherwise agreed by both Paries, the point of where the Sellers Facility's energy is delivered to the Idaho Power electrical system. Schedule 72 wil determine -33- 111112010 the specific Point of Delivery for this Facilty. The Point of Delivery identified by Schedule 72 wil become an integral part of this Agreement. B-6 LOSSES If the Idaho Power Metering equipment is capable of measurng the exact energy deliveries by the Seller to the Idaho Power electrical system at the Point of Delivery, no Losses wil be calculated for this Facility. If the Idaho Power Meterig equipment is unable to measure the exact energy deliveries by the Seller to the Idaho Power electrical system at the Point of Delivery, a Losses calculation wil be established to measure the energy losses (kWh) between the Seller's Facility and the Idaho Power Point of Delivery. This loss calculation wil be initially set at 2% of the kWh energy production recorded on the Facility generation metering equipment. At such time as Seller provides Idaho Power with the electrical equipment specifications (trsformer loss specifications, conductor sizes, etc.) of all of the electrcal equipment between the Facilty and the Idaho Power electrical system, Idaho Power wil configure a revised loss calculation formula to be agreed to by both paries and used to calculate the kWh Losses for the remaining term of the Agreement. If at any time durg the term of this Agreement, Idaho Power determines that the loss calculation does not correctly reflect the actual kWh losses attributed to the electrical equipment between the Facilty and the Idaho Power electrical system, Idaho Power may adjust the calculation and retroactively adjust the previous months kWh loss calculations. B-7 METERIG AN TELEMETRY Schedule 72 wil determine the specific meterig and telemetry requirements for this Facility. At the minimum, the Metering Equipment and Telemetry equipment must be able to provide and record hourly energy deliveries to the Point of Delivery and any other energy measurements required to administer this Agreement. These specifications wil include but not be limited to equipment specifications, equipment location, Idaho Power provided equipment, Seller provided equipment, and all costs associated with the equipment, design and installation of the Idaho Power provided equipment. Seller wil arrange for and make available at Seller's cost -34- 111112010 communication circuit(s) compatible with Idaho Power's communications equipment and dedicated to Idaho Power's use terminating at the Idaho Power facilities capable of providing Idaho Power with continuous instantaneous information on the Facilities energy production. Idaho Power provided equipment wil be owned and maintained by Idao Power, with total cost of purchase, installation, operation, and maintenance, including administrative cost to be reimbursed to Idaho Power by the Seller. Payment of these costs wil be in accordace with Schedule 72 and the total metering cost wil be included in the calculation of the Monthly Operation and Maintenance Charges specified in Schedule 72. B-8 NETWORK RESOURCE DESIGNATION Idaho Power canot accept or pay for generation from this Facilty until a Network Resource Designation ("NR") application has been accepted by Idaho Power's delivery business unt. Federal Energy Regulatory Commission ("FERC") rules require Idaho Power to prepare and submit the NR. Because much of the information Idaho Power needs to prepare the NR is specific to the Seller's Facilty, Idao Power's abilty to fie the NR in a timely manner is contingent upon timely receipt of the required information from the Seller. Prior to Idaho Power begining the process to enable Idaho Power to submit a request for NR status for this Facility, the Seller shall have completed all requirements as specified in Paragraph 5.7 of this Agreement. Seller's failure to provide complete and accurate information in a timely manner can significantly impact Idaho Power's abilty and cost to attain the NRD designation for the Seller's Facilty and the Seller shall bear the costs of any of these delays that are a result of any action or inaction by the Seller. -35- 11/112010 APPENDIXC ENGINER'S CERTIFICATION OF OPERATIONS & MAIENANCE POLICY The undersigned , on behalf of himselflerself and , hereinafter collectively referred to as "Engineer," hereby states and certifies to the Seller as follows: 1. That Engineer is a Licensed Professional Engineer in good standing in the State of Idao. 2. That Engineer has reviewed the Energy Sales Agreement, hereinafter "Agreement," between Idaho Power as Buyer, and as Seller, dated 3. That the cogeneration or small power production project which is the subject of the Agreement and this Statement is identified as IPCo Facilty No. and is hereinafter referred to as the "Project." 4. That the Project, which is commonly known as the Project, is located in Section _ Township Range , Boise Meridian, County, Idaho. 5. That Engineer recognizes that the Agreement provides for the Project to fush electrical energy to Idao Power for a year period. 6. That Engineer has substantial experience in the design, construction and operation of electric power plants of the same type as this Project. 7. That Engineer has no economic relationship to the Design Engineer of this Project. 8. That Engineer has reviewed and/or supervised the review of the Policy for Operation and Maintenance ("O&M") for this Project and it is his professional opinion that, provided said Project has been designed and built to appropriate standards, adherence to said O&M Policy wil result in the -36- 111112010 Project's producing at or nea the design electrical output, effciency and plant factor for a year period. 9. That Engineer recognizes that Idaho Power, in accordance with paragraph 5.2 of the Agreement, is relying on Engineer's representations and opinions contained in this Statement. 10. That Engineer certifies that the above statements are complete, true and accurte to the best of his knowledge and therefore sets his!her hand and seal below. By (P .E. Stap) Date -37- 111112010 APPENDIXC ENGINER'S CERTIFICATION OF ONGOING OPERATIONS AN MAIENANCE The undersigned , on behalf of himself/erself hereinafter collectively referred to as "Engineer," hereby states andand certifies to the Seller as follows: 1. That Engineer is a Licensed Professional Engineer in good standig in the State of Idaho. 2. That Engineer has reviewed the Energy Sales Agreement, hereinafter "Agreement," between Idaho Power as Buyer, and as Seller, dated 3. That the cogeneration or small power production project which is the subject of the Agreement and this Statement is identified as IPCo Facility No. and hereinafter referred to as the "Project" . 4. That the Project, which is commonly known as the Project, is located in Section _ Township Range , Boise Meridian, County, Idaho. 5. That Engineer recognizes that the Agreement provides for the Project to fush electrical energy to Idaho Power for a year period. 6. That Engineer has substantial experience in the design, construction and operation of electric power plants of the same type as this Project. 7. That Engineer has no economic relationship to the Design Engineer of this Project. -38- 111112010 8. That Engineer has made a physical inspection of said Project, its operations and maintenance records since the last previous certified inspection. It is Engineer's professional opinon, based on the Project's appearance, that its ongoing O&M has been substantially in accordance with said O&M Policy; that it is in reasonably good operating condition; and that if adherence to said O&M Policy continues, the Project wil continue producing at or near its design electrical output, efficiency and plant factor for the remaining years of the Agreement. 9. That Engineer recognizes that Idao Power, in accordance with pargraph 5.2 of the Agreement, is relying on Engineer's representations and opinions contained in this Statement. 10. That Engineer certifies that the above statements are complete, true and accurate to the best of his knowledge and therefore sets his!her hand and seal below. By (P .E. Stap) Date -39- 111112010 APPENDIXC ENGINER'S CERTIFICATION OF DESIGN & CONSTRUCTION ADEQUACY The undersigned , on behalf of himself/herself and hereinafter collectively referred to as "Engineer", hereby states and certifies to Idaho Power as follows: 1. 2. That Engineer is a Licensed Professional Engineer in good standing in the State ofIdao. That Engineer has reviewed the Fir Energy Sales Agreement, hereinafter "Agreement", between Idao Power as Buyer, and as Seller, dated 3. That the cogeneration or small power production project, which is the subject of the Agreement and this Statement, is identified as IPCo Facility No and is hereinafter referred to as the "Project". 4. That the Project, which is commonly known as the Project, is located in Section _ Township Range , Boise Meridian, County, Idao. 5. That Engineer recognizes that the Agreement provides for the Project to fuish electrcal energy to Idaho Power for a year perod. 6.That Engineer has substantial experience in the design, constrction and operation of electric power plants of the same type as this Project. 7. That Engineer has no economic relationship to the Design Engineer of this Project and has made the analysis of the plans and specifications independently. 8. That Engineer has reviewed the engineering design and construction of the Project, including the civil work, electrical work, generating equipment, prime mover conveyance system, Seller furnshed Interconnection Facilities and other Project facilties and equipment. -40- 111112010 9. That the Project has been constructed in accordance with said plans and specifications, all applicable codes and consistent with Prudent Electrical Practices as that term is described in the Agreement. 10. That the design and construction of the Project is such that with reasonable and prudent operation and maintenance practices by Seller, the Project is capable of performing in accordance with the terms of the Agreement and with Prudent Electrical Practices for a year period. 11.That Engineer recognzes that Idaho Power, in accordance with paragraph 5.2 of the Agreement, in interconnecting the Project with its system, is relying on Engineer's representations and opinions contained in this Statement. 12. That Engineer certifies that the above statements are complete, true and accurte to the best of his/her knowledge and therefore sets his hand and seal below. By (P .E. Stamp) Date -41- 111112010 APPENDIXD FORMS OF LIQUID SECURY The Seller shall provide Idaho Power with commercially reasonable securty instruments such as Cash Escrow Security, Guarantee or Letter of Credit as those ters are defined below or other forms of liquid financial security that would provide readily available cash to Idaho Power to satisfy the Delay Security requirement and any other security requirement within this Agreement. For the purose of this Appendix D, the term "Credit Requirements" shall mean acceptable financial creditworthiness of the entity providing the security instruent in relation to the term of the obligation in the reasonable judgment ofIdaho Power, provided that any guarantee and/or letter of credit issued by any other entity with a short-term or long-term investment grade credit rating by Standard & Poor's Corporation or Moody's Investor Services, Inc. shall be deemed to have acceptable financial creditwortiness. 1. Cash Escrow Securty - Seller shall deposit fuds in an escrow account established by the Seller in a baning institution acceptable to both Paries equal to the Delay Security or any other required securty amount(s). The Seller shall be responsible for all costs, and receive any interest earned associated with establishing and maintaining the escrow account(s). Guarantee or Letter of Credit Security - Seller shall post and maintain in an amount equal to the Delay Security or other required security amount(s): (a) a guaranty from a party that satisfies the Credit Requirements, in a form acceptable to Idaho Power at its discretion, or b) an irevocable_Letter of Credit in a form acceptable to Idaho Power, in favor of Idaho Power. The Letter of Credit wil be issued by a financial institution acceptable to both paries. The Seller shall be responsible for all costs associated with establishing and maintaining the Guarantee(s) or Letter(s) of Credit. -42- 111112010 APPENDIXE WIN ENERGY PRODUCTION FORECASTING As specified in Commission Order 30488, Idaho Power shall make use of a Wind Energy Production Forecasting model to forecast the energy production from this Facilty and other Qualifyng Facilty wind generation resources. Seller and Idaho Power wil share the cost of Wind Energy Production Forecasting. The Facility's share of Wind Energy Production Forecasting is determined as specified below. Sellers share wil not be greater than 0.1 % of the total energy payments made to Seller by Idao Power durg the previous Contract Year. a. For every month of this Agreement beginnng with the first full month after the First Energy Date as specified in Appendix of this Agreement, the Wind Energy Production Forecasting Monthly Cost Allocation (MCA) wil be due and payable by the Seller. Any Wind Energy Production Forecasting Monthly Cost Allocations (MCA) that are not reimbursed to Idao Power shall be deducted from energy payments to the Seller. . As the value of the 0.1 % cap of the Facilities total energy payments wil not be known until the first Contract Year is complete, at the end of the first Contract Year any prior allocations that exceeded the 0.1 % cap shall be adjusted to reflect the 0.1 % cap and if the Facility has paid the monthly allocations a refud wil be included in equal monthly amounts over the ensuing Contract Year. If the Facility has not paid the monthly allocations the amount due Idaho Power wil be adjusted accordingly and the unpaid balance wil be deducted from the ensuing Contract Year's energy payments. b. Durng the first Contract Year, as the value of the 0.1 % cap of the Facilities total energy payments wil not be known until the first Contract Year is complete, -43- 111112010 Idaho Power wil deduct the Facility's calculated share of the Wind Energy Production Forecasting costs specified in item d each month durng the fist Contract Year and subsequently refud any overpayment (payments that exceed the cap) in equal monthly amounts over the ensuing Contract Year. c. The cost allocation formula described below wil be reviewed and revised if necessar on the last day of any month in which the cumulative MW nameplate of wind projects having Commission approved agreements to deliver energy to Idaho Power has been revised by an action of the Commission. d. The monthly cost allocation wil be based upon the following formula: Where: Total MW (TMW is equal to the total nameplate rating of all QF wind projects that are under contract to provide energy to Idao Power Company. Facilty MW (¥W) is equal to the nameplate rating of this Facilty as specified in Appendix B. Annual Wind Energy Production Forecasting Cost (AFCost) is equal to the total annual cost Idao Power incurs to provide Wind Energy Production Forecasting. Idaho Power wil estimate the AFCost for the current year based upon the previous year's cost and expected costs for the current year. At year-end, Idaho Power wil compare the actual costs to the estimated costs and any differences between the estimated AFCost and the actual AFCost wil be included in the next year's AFCost. Annual Cost Allocation (ACA) = AFCost X (FMW / TMW) And Monthly Cost Allocation (MCA) = ACA / 12 e. The Wind Energy Production Forecasting Monthly Cost Allocation (MCA) is due and payable to Idaho Power. The MCA wil first be netted against any monthly energy payments owed to the Seller. If the netting of the MCA against -44- 111112010 the monthly energy payments results in a balance being due Idaho Power, the Facility shall pay this amount within 15 days of the date of the payment invoice. -45- 111112010