HomeMy WebLinkAbout20071024Idaho Windfarms comments.pdfGlenn Ikemoto
Idaho Windfarms, LLC
672 Blair Avenue
Piedmont, California 94611
Tel: 510-655-7600
Fax: 510-217-2239
glenni~pacbell.net
Idaho Public Utilities Commission
Office of the SecretaryRECEIVED
OCT 2 ~ 2007
Boise, Idaho
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE PETITION OF
IDAHO POWER COMPANY TO MODIFY
THE METHODOLOGY OF DETERMINING
FUEL COSTS TO ESTABLISH
PUBLISHED RATES
COMMENTS OF
IDAHO WINDFARMS, LLC
CASE NO. IPC-E-O7 -
Idaho Windfarms, LLC (IWF) hereby respectfully submits its Comments on
Idaho Power's Petition in the subject proceeding.
INTRODUCTION
IWF is an active greenfield wind energy developer in Idaho. It has
successfully developed the Bennett Creek and Hot Springs Windfarms near Mountain
Home, which are currently under construction. The principals of IWF have developed
and financed wind energy projects for over 20 years and completed projects in seven
countries. In addition , we have substantial expertise in utility resource planning and
economic analyses, having previously worked as senior planners in Pacific Gas and
Electric Company s Generation Planning and Corporate Planning Departments.
WHAT, AGAIN?
This Petition represents the single most important decision on the future of
renewable energy in Idaho that the Commission will face for the next several years.
Since it issued Order No. 29029 on May 21 , 2002, which re-established long term
contracts for PURPA projects, the wind industry has had to fight one regulatory battle
after another. It has addressed the issues of firm energy (90/110 Performance Band),
integration costs and transmission system upgrades. In the more than five years since
the Commission s decision to move forward with PURPA projects, wind projects have
effectively only had access to Published Prices for six months.
Now, on the eve of completing the latest two year suspension to resolve the
integration cost issue, Idaho Power raises yet another new issue. The continuous
regulatory delays are simply killing the wind industry in Idaho and costing the ratepayers
real money. IWF hopes the Commission sees through this attempt to continue the
suspension of PURPA wind projects by using multiple price reductions.
., ..
THIS IS A SETTLED ISSUE
The Commission s Order No. 29124 issued on September 26, 2002 in Case
No. GNR-02-1 settled the issue of which fuel forecast to use for avoided cost
purposes and how to model it. Idaho Power made its objections known at the time and
the Commission made its decision. This Case was heavily contested by numerous
parties. The Commission cannot allow Idaho Power to cherry pick a single issue for
reconsideration years after the Case has been closed.
It would be just as valid for the renewable energy industry to question why we
should use a gas forecast that is lower than the ones used by every Idaho utility in their
own IRPs. Why should we use a 20 year average price when the SAR is a 30 year
resource? Why should we only assess integration costs for the uncertainty of wind
deliveries and ignore the uncertainty of natural gas costs? Both have an equivalent
impact on ratepayers. Clearly, if we are to revisit one issue in calculating avoided costs,
it is fair and reasonable to revisit them all.
IDAHO POWER'S PRICE IS WRONG
The fundamental principle in resource planning is to compare (and price) all
options with the same assumptions. This requires that the PURPA prices determined by
the SAR methodology should at least be comparable to the individual cost of power
estimates for similar generation resources in the utilities' own IRPs. Idaho Power's
proposal does not pass this mandatory "smell test". The following is a comparison of the
costs of combined cycle generation in each of the three utilities' IRPs. The original utility
estimates are adjusted to a uniform monetary measure (2008, 20 year levelized nominal
dollars) and the SAR's capacity factor:
Comparison of CCCT IRP Cost of Power Estimates ($/MWh)
(Tilted Capital Method)
2007 SAR Update
Current IPC
IPC PAC AVU Method Proposal
Cost Estimate Year (SAR -non fuel)2006 2006 2007 2000 2000
Utility CCCT Cost of Power from IRPs 78.74.65.
Type of Levelized Dollars Nominal Real Real Nominal Nominal
IRP Capacity Factor 85%56%
Adjust to SAR Capacity Factor (92%)
Delete Environmental Adders
2006 Real Dollars 66.63.
Escalate Nominal $ to 2008
2008 20-Yr Nominal Levelized $75.78.77.73.68.
The table above clearly demonstrates that Idaho Power's proposal
undervalues PURPA energy and will result in fewer indigenous, secure, clean and
economic renewable energy projects in Idaho. By contrast, the current SAR method
produces results that are low, but comparable to the current utility estimates for IRP
resources. The lower SAR costs are due to the outdated cost estimates and lower fuel
price forecast.
The utilities report their IRP cost of power (COP) estimates using different
base dollars. Idaho Power uses levelized nominal dollars. Pacificorp and Avista use
levelized real dollars. The revised estimates above, for Pacificorp, uses the economic
assumptions in their IRP. For Idaho Power and Avista, a 5.1 % real weighted average
cost of capital and 2% general inflation rate were assumed. Those are the only two
assumptions needed to convert between the two base dollars. The 20 year levelized
capital costs are based on using the tilted capital method to adjust the plant life specified
in the utility's IRP to a 20 year estimate. In other words, the capital costs are not fully
recovered over the 20 year period and do not artificially increase the cost of power.
THE COST OF UNCERTAINTY
As noted above, the wind industry has just suffered through more than two
years of delay as the issue of integration costs were debated. The parties were trying to
reconcile the differences between renewable resources, which tap a flow of energy and
fossil fuels, which tap a store of energy. Wind energy has uncertain energy deliveries
but highly certain costs. Fossil fuel projects have certain deliveries but highly uncertain
costs. From a ratepayer's perspective , there is no difference between these risks. Yet
the uncertainty of wind deliveries is likely to get priced into PURPA contracts and the
uncertainty of fossil fuel prices will continue to be ignored.
Yet, the fuel price risk has harmed ratepayers time and time again. In its
current Rate Case (IPC-07-08) Idaho Power's witness, Greg Said , testified that wind
projects reduced power supply costs by $10.1 million. He points out that the savings
would be partially offset by integration costs. The Commission is now addressing that
issue and may place the full integration cost burden on future PUPRA wind projects.
, the Commission must recognize that the economic scales are unbalanced. The fuel
price forecast is based on the short term market and contains massive price uncertainty.
Also, approving Idaho Power's Petition will likely delay the implementation of additional
wind energy in Idaho for years. This will undoubted cause the loss of more ratepayer
savings as the natural gas forecasts prove themselves to be low again. The following
table is from Idaho Power's 2007 IRP. It documents the history of low natural gas
forecasts, each of which unnecessarily delayed renewables to the detriment of Idaho
ratepayers. Apparently the natural gas forecasters are working in the State of Denial.
Natural G.. For""ast Comparison
$lMMBTU (Nominal)
011CC
Oi-""
..---........... """..---
I--
---
c--'"L---
------ - -. -
J=rl...
-.----
2006 IRP
010.
",,
!i.CC 2004 IRP
07,
CE,2002 IRP
..,
2000 IRP
"'co
oz."":!II" """ :!lICE :!II" 2010 20" ~12 """ "",. "'" 20'E ""17 'C1E :!II"
= ""
~'" "'" '02' =5
CONCLUSION
Idaho Power's Petition in this proceeding should be denied. It is inappro-
priate to rehear a single issue from a comprehensive decision. Should the Commission
decide to investigate the method for modeling the natural gas forecast, it should institute
a full and fair investigation of all components of avoided costs. In addition , Idaho
Power's proposal doesn t pass the simplest test of reasonableness. It produces a result
which is not comparable to similar generation alternatives in any of the IRPs filed by the
three Idaho utilities. These IRPs are the basis for all supply-side and demand-side
resource allocation decisions. A published price as low as Idaho Power s proposal will
delay or cancel otherwise economic renewable energy projects in favor of increased
higher cost, market purchases. Finally, since the cost of fuel price uncertainty is
currently ignored in the SAR methodology, the Commission should recognize that
PURPA renewables are already significantly under-priced. Denying Idaho Power
Petition will allow wind energy developers to get back to work producing clean energy
instead of regulatory filings.
Respectfully submitted this 24th day of October, 2007:
CERTIFICATE OF SERVICE
I hereby certify that on the 24th day of October, 2007 , true and correct copies of
the COMMENTS OF IDAHO WINOFARMS , LLC were delivered by U.S. Mail to:
Barton L. Kline, Senior Attorney
Lisa O. Nordstrom , Attorney II
Idaho Power Company
PO Box 70
Boise, 10 83707
bkline~idahopower.com
Inordstrom~idahopower.com
Ric Gale, Vice President
Regulatory Affairs
Idaho Power Company
PO Box 70
Boise, 10 83707
rgale~idahopower.com
bz;'
ann Ikemot
Principal
EnVision Systems, LLC