Loading...
HomeMy WebLinkAbout20090619Harms Direct.pdfiOß9..IUll '9 PM 1: 46 ~~ 1~:',1 tfriIDAHO PUBLIC UTILITIES CO.M"".. l(~'~1r~SIO¡\'l IJ. .lT! n11ï¡l¡t., S' 'C)"r,~ ",. '", ,¡-.. BEFORE THE ,. r: 1\1 ': 1" R,c" ç: a ,C"i \( L '\;.J. ,',""'h_ "";'''' IN THE MATTER OF IDAHO POWER ) COMPANY'S APPLICATION FOR A ) CASE NO.IPC-E-09-3 CERTIFICATE OF PUBLIC CONVENIENCE ) AND NECESSITY FOR THE LANGLEY )GULCH POWER PLANT ) ) DIRECT TESTIMONY OF PATRICIA HARMS IDAHO PUBLIC UTILITIES COMMISSION JUNE 19, 2009 1 2 record. Q.Please state your name and address for the 3 A.My name is Patricia Harms. My business address 4 is 472 West Washington Street, Boise, Idaho. 5 6 Q.By whom are you employed and in what capacity? A.I am employed by the Idaho Public Utili ties 7 Commission (Commission) as a Principal Financial 8 Specialist/Senior Auditor. 9 Q.Please give a brief description of your 10 educational background and experience. 11 I graduated from Boise State University, Boise,A. 12 Idaho in 1981 with a B.A. degree in Business 13 Administration, emphasis in Accounting. I am a Certified 14 Public Accountant licensed by the State of Idaho. Prior 15 to joining the Commission Staff in 2000, I was employed 16 by the State of Alaska as an In Charge Auditor and 17 performed both financial and performance audits of 18 governmental agencies. I have attended many seminars and 19 classes involving auditing and accounting. While at the 20 Commission I have audited a number of utilities including 21 water, electric, gas and telephone utilities and provided 22 comments and testimony in a number of cases that dealt 23 with general rates, hook-up fees, accounting issues, and 24 other regulatory issues. I have also completed the 25 National Association of Regulatory Utility Commissioners' CASE NO. IPC-E- 09-306/19/09 HAS, P. (Di) 1 STAFF 1 (NARUC) annual regulatory studies program at Michigan 2 State University. I also regularly attend meetings of 3 NARUC's Staff Subcommittee on Accounting and Finance and 4 at selected meetings serve as secretary for the 5 Subcommittee. 6 Q.What is the purpose of your testimony? 7 A.The purpose of my testimony is to present 8 Staff's recommendations regarding the treatment of 9 depreciation for the Langley Gulch Proj ect. 10 My testimony in this case also describes 11 Staff's position regarding the Allowance for Funds Used 12 During Construction (AFUDC) and Construction Work in 13 Progress (CWIP) as it relates to projects in general and 14 Langley Gulch specifically. Staff witness Sterling's 15 testimony recommends that the actual amount of AFUDC 16 incurred be recoverable, but that it be considered an 17 addition to both the Soft Cap and Hard Cap amounts for 18 the Langley Gulch Proj ect. 19 My testimony also describes capitalized taxes 20 and Staff's recommended treatment of those costs. Staff 21 recommends that the actual amount of taxes relating to 22 project costs be capitalized and recovered based upon 23 Staff's proposed Langley Gulch Proj ect amount. 24 DEPRECIATION 25 Q.What is Staff's recommendation regarding the CASE NO. IPC-E-09-306/19/09 HARMS, P. (D i) 2 STAFF 2 1 treatment of depreciation for the Langley Gulch Proj ect? A.Staff recommends that the Langley Gulch Project 3 be depreciated in accordance with the depreciation rates 4 that are in effect at the time the Proj ect is placed into 5 service. This recommendation is similar to the return on 7 6 equity treatment that the Company is requesting for the 8 Staff also recommends that a new depreciation study that Project.(Gale, Supplemental Direct, page 4, lines 1-4) . 9 includes the Project with economic lives no shorter than 10 35 years for the production plant and 45, years for the 11 related transmission plant be completed and filed when, 12 or shortly after, the Proj ect is placed into service 13 (likely during 2013). This timeframe is consistent with 14 the historical periodic depreciation filings of the 15 Company. 16 Q.How were the depreciation rates currently used 18 17 by the Company approved by the Commission? A.The depreciation rates currently in use by the 19 Company were approved by the Commission in Case No. 20 IPC-E-08-6 (08-6 case) in Order No. 30639 dated 21 September 12, 2008. The depreciation rates were based on 22 the results of a detailed depreciation study of the 23 Company's electric plant in service as of December 31, 24 2006. The depreciation rates were based on a straight 25 line, average service life procedure for all electric CASE NO. IPC-E-09-306/19/09 HAS, P. (Di) 3 STAFF 1 plant. In that case, the proposed changes in 2 depreciation rates resulted in a decrease of the 3 Company's total annual depreciation expense. The parties 4 to the 08-6 Case filed a Stipulation setting forth 5 agreed-upon depreciation rates. The Stipulation 6 identified changes to the Company's proposal agreed to by 7 the parties, primarily increases in the service life and 8 life span of a steam generation plant and hydraulic 9 production plants. The parties also agreed to a detailed 10 review in the next depreciation case of accrual rates for 11 several plant assets, including Bridger Assets, Bennett 12 Mountain, Clear Lake Hydraulic Production Plant, Meters, 13 Computers and Corporate Aircraft. 14 Q.What depreciation rates were approved in Case 15 No. IPC-E- 08 - 6 for production plant and how do those 16 rates compare to the depreciable life of 35 years (2.86%) 17 requested by the Company for the Langley Gulch production 18 plant? .19 A.The Commission-approved accrual rates for 20 selected production plant accounts according to the 21 Attachment to Order No. 30639 are stated in the following 22 table (Table No.1) . 23 24 25 CASE NO. IPC-E- 09-306/19/09 HAS, P. (Di) 4 STAFF 1 Table No. 1 2 Account and Description Accrual 3 6 340.00 341. 00 342.00343.00344.00345.00346.00 Land Structures & Improvements Fuel Holders Prime MoversGenerators Accessory Electric Equipment Misc. Power Plant Equipment Non-depreciable 2.75-3.16% 2.75-2.80% 2.76-3.25% 1.93-3.30% 2.75-7.22% 2.52-7.17% 4 5 7 Q.Why do the listed accrual amounts vary so 8 greatly by account? 9 A.In the Attachment to Order No. 30639, accrual 10 rates and composite remaining life for production plant 11 are listed by Federal Energy Regulatory Commission (FERC) 12 account and within that account by plant. For example, 13 the accrual rates for Account 344.00 Generators range 14 from a low of 1.93% and a composite remaining life of 15 29.5 years for Evander Andrews to a high of 3.30% and a 16 composite remaining life of 34.5 years for Bennett 17 Mountain. Similarly, the accrual rates for Account 18 345.00 Accessory Electric Equipment range from a low of 19 2.75% and a composite remaining life of 34.5 years for 20 Bennett Mountain to a high of 7.22% and a composite 21 remaining life of 10.5 years for Salmon Diesel. 22 Q.Was Langley Gulch part of the depreciation 23 study filed in Case No. IPC-E-08-6? 24 A.No. The depreciation study only relates to 25 plant in service at the time of the study. CASE NO. IPC-E-09-306/19/09 HAS, P. (Di) 5 STAFF 1 Q.What Commitment Estimate dollars for the 2 Langley Gulch production plant relate to the above 3 accounts and what is its related depreciable life? 4 A.Staff asked the Company in the discovery 5 process to provide all studies, life cycle analyses and 6 other information used to derive a depreciable life of 35 7 years for the production plant and 45 years for the 8 transmission plant. The Company was asked to include 9 within its response the Commitment Estimate dollars as it 10 relates to production and transmission plant by electric 11 plant in service account number (3XX. xx) and the related 12 depreciable life. The Company's response to Production 13 14 15 16 17 18 19 20 21 22 23 24 25 Request No. 83 referred Staff to the depreciation study that was the basis of Case No. IPC-E- 08 - 6 and stated the following: "While Idaho Power believes that its Commitment Estimate is reasonable, it cannot predict with precision the specific Commitment Estimate amounts that will close to each FERC electric plant account upon placing the project in-service. The requested allocation of Commitment Estimate dollars will be made upon final unitization of the work order (s). However, there are portions of the power plant Commitment Estimate that will likely close to specific accounts. The property and water rights acquired for the plant will close to plant account 340. The amounts for the gas turbine, steam turbine, and heat recovery steam generator ("HRSG") will close to plant accounts 343 and 344. The remainder of CASE NO. IPC-E-09-306/19/09 HAS , P . (D i) 6 STAFF 1 2 3 4 5 6 the power plant investment will close to plant accounts 341, 342, 345, and 346. Accounts 340-346 currently all have approximately the same overall depreciable life. The current Idaho Power investment in these accounts has a composite remaining life ofapproximately 30 years." Q.What depreciation rates were approved in Case 7 No. IPC-E-08-6 for transmission plant and how do those 8 rates compare to the depreciable life of 45 years (2.22%) 9 requested by the Company for Langley Gulch transmission 10 plant? 11 A.The Commission-approved accrual rates for 12 selected transmission accounts according to the 13 Attachment to Order No. 30639 are stated in the following 14 table (Table No.2) . 15 Table No. 2 16 17 18 19 20 21 Account and Description 350.20 350.21 352.00 353.00 354.00 355.00 356.00 Land Rights and Easements Rights of Way Structures & Improvements Station Equipment Towers and Fixtures Poles and Fixtures Overhead Conductors and Devices Accrual 1. 51% 1. 50% 1. 68% 2.06% 1.96% 2.81% 1.92% Q.What are the composite remaining lives for the 24 23 30639? 22 above accounts as stated in the Attachment to Order No. A.The composite remaining lives for the above 25 accounts according to the Attachment to Order No. 30639 CASE NO. IPC-E-09-306/19/09 HAS, P. (Di) 7 STAFF 1 are stated in the following table (Table No.3) . 3 2 Table No. 3 Account and Description 4 350.20350.21352.00 353.00 354.00 355.00 356.00 5 6 7 8 Remaining Life Land Rights and Easements Rights of Way Structures & Improvements Station Equipment Towers and FixturesPoles and Fixtures Overhead Conductors and Devices 54.2 Years 63.7 Years 47.3 Years 35.4 Years 48.6 Years 36.7 Years 48.3 Years Q.What Commitment Estimate dollars for the 9 Langley Gulch transmission plant relate to the above 11 10 accounts and what is its related depreciable life? A. 12 the discovery process to provide all studies, life cycle As noted previously, Staff asked the Company in 13 analyses and other information used to derive a 14 depreciable life of 35 years for the production plant and 15 45 years for the transmission plant. The Company was 16 asked to include within its response the Commitment 17 Estimate dollars as it relates to production and 18 transmission plant by electric plant in service account 19 number (3XX. xx) and the related depreciable life. The 20 Company's response to Production Request No. 83 referred 21 Staff to the depreciation study that was the basis of 22 Case No. IPC-E-08-6 and stated the following: 23 "While Idaho Power believes that its Commitment Estimate is reasonable, it24 cannot predict with precision the specific Commitment Estimate amounts25 that will close to each FERC electric CASE NO. IPC-E-09-306/19/09 HAS, P. (Di) 8 STAFF 1 2 3 4 5 6 plant account upon placing the proj ect in-service. The requested allocation of Commitment Estimate dollars will be made upon final unitization of the workorder (s) ... The transmission lines portion of the proj ect will close to plant accounts 354-356 and the transmission station portion will close to accounts 350,352, and 353." Q.Do you have a schedule of the Langley Gulch 7 Commitment Estimate dollars by account and its related 8 depreciable life? 9 A.No, the Company did not provide such a schedule 10 in support of its request for the depreciable life of 35 11 years for production plant and 45 years for transmission 13 12 plant. Q.How frequently has the Company filed cases 15 14 requesting approval of its depreciation rates? A.The Company filed its most recent depreciation 16 case in 2008 (Case No. IPC-E-08-6). The previous 17 depreciation case was filed in October 2003 (Case No. 19 18 IPC-E-03-7) . 20 21 22 23 24 Q.Is this timing the basis of your recommendation that the Company file a depreciation case during 2013 when,or shortly after,the Project is placed into service? A.Yes.However,another consideration is the size (in dollars)of the plant and the other issues 25 identified in Case No. IPC-E-08-6 that were identified CASE NO. IPC-E-09-306/19/09 HAMS, P. (D i) 9 STAFF 1 for further review by the parties to the Stipulation. 2 This leads to Staff's expectation that another 3 depreciation study will be forthcoming within five years 4 of the last filed depreciation case. 5 Q.Is there anything else that might influence 6 depreciation in 2013 when the plant is expected to close 7 to plant in service? 8 A.Yes. The Securities and Exchange Commission 9 (SEC) has published a roadmap associated with 10 implementation of International Financial Reporting 11 Standards (IFRS). This roadmap sets forth several 12 milestones that, if achieved, could lead to the required 13 use of IFRS by U. S. issuers in 2014 if the SEC believes 14 it to be in the public interest. Current international 15 standards treat depreciation differently than most u. S. 16 utilities. 17 Q.How are assets depreciated under current 18 International Accounting Standards (lAS)? 19 A.While there are many different aspects of 20 depreciation under lAS, the most significant one that the 21 Company can currently prepare the Langley Gulch Project 22 for is componentization. 23 lAS 16, paragraph 43 states: 24 "Each part of an item of property, plant and equipment with a cost that is25 significant in relation to the total CASE NO. IPC-E-09-306/19/09 HAS, P. (Di) 10 STAFF 1 cost of the item shall be depreciatedseparately. " 2 3 This may be a physical component or a non- 4 physical component such as an inspection or an overhaul. 5 Q.How does this differ from current depreciation 6 methods? 7 A.Utilities currently use mass/group asset 8 depreciation. It has been recognized that mass/group 9 asset depreciation cannot be accommodated under IFRS. 10 Q.What is Staff's recommendation to the Company 11 regarding lAS 16 ? 12 A.Staff recommends that the Company create and 13 retain documentation associated with the Langley Gulch 14 Project that would allow the Company to comply with 15 component depreciation when IFRS are adopted. Staff 16 expects this detail will also be utilized in the next 17 depreciation study. 18 AFC AN CWIP 19 Q.What is Staff's recommendation for the recovery 20 of AFUDC in this case? 21 A.Staff recommends that the Company accrue actual 22 AFUDC based upon the monthly cash balance of actual 23 expenditures as the production and transmission plant is 24 under construction. The monthly expenditures would be 25 subj ected to a prudency review of the amounts to which CASE NO. IPC-E-09-306/19/09 HAMS, P. (D i) 11 STAFF 1 the AFUDC rate is applied except for those plant amounts 2 approved in this proceeding. Absent specific ratemaking 3 authority, AFUDC will cease when the plant is placed in 4 service. 5 Q.What is Staff's recommendation regarding CWIP 6 in this case? 7 A.Based upon the evidence at this time, Staff 8 does not believe that including CWIP in rate base before 9 the related plant is used and useful is appropriate. The 10 Company has not made a CWIP request in this case. 11 Q.What has the Company included for AFUDC in this 12 case? 13 A.The Company's Commitment Estimate includes an 14 estimated AFUDC of $49 million associated with the 15 production plant and almost $1 million for the 16 transmission portion of the proj ect. 17 Q.How has the Company calculated those amounts? 18 A.According to the Company's responses to 19 discovery, it used a 7% AFUDC rate and applied it to 20 estimated monthly cash flows for the production plant to 21 derive the $49 million. The 7 percent rate used to 22 estimate AFUDC on the power plant portion of the project 23 was not based on an exact capital structure or exact 24 financing cost (s) at a particular point in time. It was 25 a high level estimate derived from the average annual CASE NO. IPC-E-09-306/19/09 HAS, P . (D i) 12 STAFF 1 AFUDC rates the Company applied to construction work in 2 progress over the last four years according to the 3 Company. 4 The $1 million included within the Commitment 5 Estimate for transmission was not calculated in the same 6 manner. Instead it was an estimate from the bid process 8 7 and does not have a supporting schedule. The Company's 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 response to Production Request Nos. 80 and 64 explained the AFUDC amounts as follows: "The monthly cash flow estimates for the Langley Gulch power plant were derived from preliminary payment schedules/estimates for the gas turbine, steam turbine, and EPC (Engineering, Procurement and Construction) contract. The cash flow amounts for the remainder of theproj ect were based on Idaho Power'sproj ected timing of construction and planned work activities." "Payment schedules for the construction of the gas turbine, steam turbine, and overall construction of the Langley Gulch plant are not available at this time because contract terms have not been finalized. Idaho Power estimated monthly cash construction expenditures for the power plant portion of theproj ect for purposes of proj ecting AFUDC... The proj ected transmission cost of $31. 5M includes a high level AFUDCestimate of approximately $991,000. A projected cash flow and AFUDC schedule is not available at this time for the transmission portion of the proj ect due to the preliminary nature and scope of the overall design and cost estimate." Q.What are the historical AFUDC percentages that CASE NO. IPC-E-09-306/19/09 HAS, P. (Di) 13 STAFF 1 have been applied to plant? 2 A.According to the last general rate case for 3 Idaho Power (Case No. IPC-E-08-10), the monthly AFUDC 4 rates January 2008 through October 2008 ranged from 5 3.016% to 6.585%. (Case No. IPC-E-08-10, Miller Direct 6 Rebuttal, page 5). According to the Company's responses 7 to discovery, the monthly AFUDC rates for January through 8 April 2009 have ranged from 3.27% to 8.26% (response to 9 Production Request No. 82). 11 10 Table No. 4 12 13 14 15 16 17 18 19 20 21 Month and Year Rate in Effect January 2008 February 2008 March 2008 April 2008 May 2008 June 2008 July 2008 August 2008 September 2008 October 2008 November 2008 December 2008 January 2009 February 2009 March 2009 April 2009 6.352% 5.592% 4.111% 4.136% 3.696% 3.016% 4.894% 6.271% 6.240% 6.585% 6.660% 6.793% 5.24% 4.11% 3.27% 8.26% Q.How do the rates above compare to that used to 22 calculate the $49 million estimated AFUDC for the Langley 23 Gulch production plant? 24 A.As can be seen above, the historical rates vary 25 widely compared to the 7% used for the production plant CASE NO. IPC-E-09-306/19/09 HAS, P. (Di) 14 STAFF 1 AFUDC included in the Langley Gulch Commitment Estimate. 2 Q.How does Idaho Power calculate the AFUDC rate? 3 A.On a monthly basis the Company's AFUDC rate is 4 calculated consistent with the AFUDC formula established 5 in the FERC Uniform System of Accounts/General 6 Instructions (18 CFR 1.101). Idaho Power uses semi- 7 annual compounding as allowed in FERC Order 561. 8 Q.What are AFUDC and CWIP? 9 A.AFUDC is an accounting mechanism which 10 recognizes capital costs associated with financing 11 construction. Generally, the capital costs recognized by 12 AFUDC include interest charges on borrowed funds and the 13 cost of equity funds used by a utility for purposes of 14 construction. The main purposes of AFUDC are to 15 capitalize with each project the costs of financing that 16 construction; separate the effects of the construction 17 program from current operations; and to allocate current 18 capital costs to future periods when these capital 19 facilities are in service, useful and producing revenue. 20 AFUDC represents the cost of funds used during the 21 construction period before plant goes into service. When 22 it is placed in service, the entire cost of the plant, 23 including AFUDC, is added to rate base, where it earns a 24 rate of return and is depreciated over the life of the 25 plant. CASE NO. IPC-E- 09-3 06/19/09 HAS, P. (Di) 15 STAFF 1 CWIP is the accumulation of all costs 2 associated with the construction of an asset, including 3 the cost of financing construction (AFUDC) expenditures. 4 Utilities record these costs in Account 107. This 5 account includes the total of the balances of work orders 6 for electric plant in process of construction. Work 7 orders are to be cleared from this account and closed to 8 plant in service as soon as practicable after completion 9 of the proj ect . CWIP has not been included in rate base 10 on a current basis (before a proj ect is complete and its 11 costs closed to plant in service) historically in Idaho. 12 ALTERNATIVES PROPOSED BY THE COMPANY 13 Q.What two alternatives to a plant filing with 14 the assurances described in the Company's testimony does 15 Company witness Smith describe in her testimony? 16 A.Company witness Smith describes "CWIP in Rate 1 7 Base" and "AFUDC: Pay Currently" in her testimony and 18 compares this to the ratemaking assurances described in 19 Company witness Gale's direct testimony. "CWIP in Rate 20 Base" is described as the Company recovering CWIP 21 expenditures (including AFUDC) the Company incurs as it 22 constructs the Proj ect in current rates on an annual 23 basis. "AFUDC: Pay Currently" is similar to Hells Canyon 24 Relicensing AFUDC granted in Order No. 30722 where 25 customers would pay AFUDC in annual rate increases from CASE NO. IPC-E- 09-306/19/09 HAS, P. (Di) 16 STAFF 2 1 2010 through 2013. 3 Smith's Exhibit No.7 for the two alternatives to Q.Do the percentages shown in Company witness 4 traditional ratemaking and the third alternative of 5 placing in service at the end of the construction period 6 the entire CWIP balance including AFUDC represent the 7 rate increases that could be expected using those 8 methods? 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 A.No. According to the Company's response to Production Request No. 102, the spreadsheet that was used to develop this Exhibit was: "...to demonstrate the potential to reduce rate shock by employing either AFUDC Pay Currently or CWIP in Rate Base versus the third alternative to place in service at the end of construction the entire CWIP balance, including AFUDC of the Langley Gulch Power Plant. The analysis is for illustrative purposes only and does not predict the future impact of thesealternatives. " And, "The assumption in the illustrative example that revenues would grow 1 percent each year was not intended to portray any expectation by Idaho Power. This was a simplifying assumption for the hypothetical illustration of the annual differences between the regulatory treatments of AFUDC Pay Currently, CWIP in Rate Base and Traditional Ratemaking." (Emphasis Added. ) Q.What is Staff's position regarding AFUDC and CASE NO. IPC-E-09-306/19/09 HARMS, P. (D i) 1 7 STAFF 1 CWIP? 2 A.Staff's position regarding AFUDC was most 3 recently presented by Staff witness Vaughn in Idaho 4 Power's last General Rate Case, Case No. IPC-E-08-10 and 5 remains largely the same today. 6 In Case No. IPC-E-08-10 the Company requested 7 recovery of the currently accruing AFUDC for the Hells 8 Canyon relicensing proj ect (AFUDC component of CWIP). 9 Staff agreed in large part with the Company's proposal 10 because the amount of AFUDC expected at the end of 2012 11 would be larger than the actual direct relicensing costs 12 assuming no additional expenses were incurred during the 13 relicensing proj ect. Staff stated that this enormous 14 growth in AFUDC for the Hells Canyon relicensing proj ect 15 provided the basis for an explicit finding that it was in 16 the public interest to include AFUDC in base rates before 17 the proj ect was closed to plant in service. 18 Although there are limited situations where the 19 public is served by placing CWIP in rate base according 20 to Staff's testimony in Case No. IPC-E-08-10, the Hells 21 Canyon relicensing project is different from other 22 construction proj ects for several reasons. First, 23 "proj ect completion" is determined when the FERC grants a 24 permanent license. Because of the large number of 25 stakeholders involved in relicensing and because of the CASE NO. IPC-E-09-306/19/09 HAS, P. (Di) 18 STAFF 1 ever-shifting political environment, project completion 2 is largely beyond the Company's direct control. A 3 permanent license could be granted as early as January 4 2009 or it could be delayed for many years. Second, it 5 is unlikely that the permanent license will not be 6 granted. At the present time, Idaho Power is operating 7 the Hells Canyon dam complex under annual licensing. 8 Because the Hells Canyon complex is fully operational and 9 power generation is not curtailed, Staff argued that the 10 relicensing investment is essentially used and useful. 11 Q.What did the Commission find in Case No. 12 IPC-E-08-10? 13 A.The Commission found in Order No. 30722, pages 14 13 and 14, as follows: 15 "... that the Hells Canyon relicensing proj ect is unlike a typical16 construction proj ect, and establishes circumstances that support a finding17 that including AFUDC in rates will serve the public interest. The unique18 circumstances include: (1) the proj ect process has already been under way for19 nearly ten years, and Idaho Power has little control over the completion20 date; (2) the Company is able to use the generating facilities during the21 relicensing process, and they currently provide a significant amount of the22 Company's total generating capacity and energy; (3) the lengthy duration of the23 project, and an as yet unknown completion date, mean that AFUDC is24 already significant and will continue to accumulate to alarming levels.25 Other considerations, not unique to the CASE NO. IPC-E-09-306/19/09 HARS, P. (D i) 19 STAFF 1 2 3 4 5 6 7 8 Hells Canyon project, also support a finding the public interest is served by including a portion of AFUDC in rates. The amount of AFUDC included inrates now will reduce the total proj ect costs that ultimately will be included in rate base, thereby reducing future rate increases. Idaho Power's cash flow will improve, which will help maintain its credit strength and ability to access funds for ongoingconstruction projects." Q.Do any of the three attributes described in the 9 Commission's finding in Case No. IPC-E-08-10 apply to the 10 Langley Gulch Project? 11 A.No. The proj ect has not been under way for 12 nearly ten years and Idaho Power has substantial control 13 over the completion date as the Proj ect is a self -build 14 Proj ect. The Proj ect is not currently used and useful 15 nor is AFUDC growing at "an alarming rate" as described 16 in Case No. IPC-E-08-10 for the Hells Canyon relicensing 17 project. The Company's ability to obtain financing for 18 the Langley Gulch Proj ect and cash flow is described in 19 Staff witness Carlock's testimony. 20 22 21 AFUDC in base rates? Q.What authorizes the inclusion of CWIP and/or A.The potential inclusion of CWIP/AFUDC in base 23 rates is an option the Commission may utilize based on a 24 2006 change in Idaho Code. 25 In 1984 the Idaho Legislature enacted Idaho CASE NO. IPC-E-09-306/19/09 HAS, P. (Di) 20 STAFF 1 Code § 61-502A to read 2 "Except upon its finding of an extreme emergency, the (Public Utilities)3 Commission is hereby prohibited in any order issued after the effective date4 of this act, from setting rates for any utility that grants a return on5 construction work in progress... or property held for future use and which6 is not currently used and useful in providing utility service." 7 8 However, in 2006 this section was amended to read 9 "Except upon its explici t finding thatthe public interest will be served--10 thereby, the Commission is hereby prohibi ted in order issued after the11 effective date of this act, from setting rates for any utility that12 grants a return on construction work in progress or property held for future13 use and which is not currently used and useful in providing utility service."14 (Emphasis indicates amended language.) 15 CWIP including AFUDC may be considered in the 16 determination of rates upon a finding that the public 17 interest will be served. 18 Q.Has the Company stated as its preferred 19 ratemaking treatment that CWIP and/or AFUDC should be 20 included in rates before the plant is used and useful and 21 closed to plant in service? 22 A.No. Company witness Gale states that the 23 Company prefers that the Commission issue an Order under 24 the provisions of Senate Bill 1123 (Gale Supplemental 25 page 6, line 20-22) . CASE NO. IPC-E-09-306/19/09 HARS, P. (Di) 21 STAFF 2 1 CAITALIZED TAXS Q.What are the capitalized taxes the Company has 3 included in its Commitment Estimate for the Langley Gulch 4 Project? 5 A.The Company has included an estimate of 6 capitalized property taxes in its Commitment Estimate. 7 The Company has estimated the year-end plant balance 8 (exclusive of AFUDC) for each year during construction, 9 deri ved on estimated assessed value and multiplied that 10 estimated assessed value by the levy rate estimate for 12 11 each year including 2009 through 2012. Q.Is it appropriate for the Company to include 13 capitalized property taxes in its Project costs? 14 A.Yes. Property taxes are a cost that the 15 Company will incur during the period the Langley Gulch 16 plant is under construction and should be included within 17 the cost of the Proj ect. Once the Proj ect is completed 18 and closed to plant in service property tax becomes an 20 19 annual expense of operating the plant. Q.What amount does Staff recommend be included 22 21 within the Project's cost? A.Staff witness Sterling recommends that actual 23 property taxes capitalized for this Project be included 24 in its costs. For those plant amounts not approved by 25 this Commission, any related capitalized property taxes CASE NO. IPC-E-09-306/19/09 HAS , P. (D i) 22 STAFF 2 1 would also be excluded pending a prudency review. Q.Does this conclude your direct testimony in 4 3 this proceeding? 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 A.Yes, it does. CASE NO. IPC-E-09-306/19/09 HAMS, P. (Di) 23 STAFF CERTIFICATE OF SERVICE I HEREBY CERTIFY THAT I HAVE THIS 19TH DAY OF JUE 2009, SERVED THE FOREGOING DIRECT TESTIMONY OF PATRICIA HARMS, IN CASE NO. IPC-E-09-3, BY ELECTRONIC MAIL AND MAILING A COpy THEREOF, POSTAGE PREPAID, TO THE FOLLOWING: BARTON L KLINE LISA D NORDSTROM IDAHO POWER COMPANY PO BOX 70 BOISE ID 83707-0070 E-MAIL: bklinetmidahopower.com Inordstromtmidahopower .com PETER J RICHARDSON RICHARDSON & O'LEARY 515 N 17TH STREET PO BOX 7218 BOISE ID 83702 E-MAIL: peter(ßrichardsonandoleary.com DR DON READING 6070 HILL ROAD BOISE ID 83703 E-MAIL: dreading(ßmindspring.com KEN MILLER CLEAN ENERGY PROGRAM DIRECTOR SNAKE RIVER ALLIANCE PO BOX 1731 BOISE ID 83701 E-MAIL: kmiler(ßsnakeriverallance.org ANTHONY Y ANKEL 29814 LAKE ROAD BAY VILLAGE OH 44140 E-MAIL: tonytmyankel.net ERIC L. OLSEN RACINE, OLSON, NYE, BUDGE & BAILEY, CHARTERED PO BOX 1391 POCATELLO ID 83204-1391 E-MAIL: elotmracinelaw.net BETSY BRIDGE IDAHO CONSERVATION LEAGUE 710 N SIXTH ST (83702) PO BOX 844 BOISE ID 83701 E-MAIL: bbridgetmwildidaho.org SUSAN K. ACKERMAN 9883 NW NOTTAGE DR PORTLAND OR 97229 E-MAIL: susan.k.ackermantmcomcast.net BRAD M. PURDY ATTORNEY AT LAW 2019 N. 17TH STREET BOISE, ID 83702 E-MAIL: bmpurdy(ßhotmail.com 1 CERTIFICATE OF SERVICE