HomeMy WebLinkAbout20080924Answer.pdfLISA D. NORDSTROM
Senior Counsel
E.iJ esIDA~POR(I
An IDACORP Company
September 23, 2008
VIA HAND DELIVERY
Jean D. Jewell, Secretary
Idaho Public Utilities Commission
472 West Washington Street
P.O. Box 83720
Boise, Idaho 83720-0074
Re: Case No. IPC-E-08-18
Gibbs v. Idaho Power Company
Dear Ms. Jewell:
Enclosed please find for filing an original and seven (7) copies of Idaho Power's
Answer in the above matter.
I would appreciate it if you would return a stamped copy of this letter for my file in
the enclosed stamped, self-addressed envelope.
Very truly yours,
X~/lvj1~
Lisa D. Nordstrom
Senior Counsel for Idaho Power Company
LDN:csb
Enclosures
P.O. Box 70 (83707)
1221 W. Idaho St.
Boise, 10 83702
LISA D. NORDSTROM, ISB # 5733
BARTON KLINE, ISB # 1526
Idaho Power Company
1221 West Idaho Street
P.O. Box 70
Boise, Idaho 83707
Telephone: (208) 388-5825
Facsimile: (208) 388-6936
Inordstrom~idahopower.com
bkline~idahopower.com
REceiVED
zoos SEP 23 PM~: 48
IDAHO PUBLIC
UTILITIES COMMISSION
Attorneys for Idaho Power Company
Street Address for Express Mail:
1221 West Idaho Street
Boise, Idaho 83702
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
JONATHAN GIBBS,
Respondent.
)
)
) Case No. IPC-E-08-18
)
)
) ANSWER
)
)
)
)
Complainant
vs.
IDAHO POWER COMPANY,
Respondent, Idaho Power Company ("Idaho Powet' or the "Company"), hereby
answers the Complaint of Jonathan Gibbs in the above-entitled case as follows:
FACTUAL BACKGROUND
Mr. Jonathan Gibbs owns a lot in Van Dorn Estates located in New Meadows,
Idaho, a residential subdivision recorded with the Adams County recorder on September
ANSWER -1
18, 2006, as document 112649. Mr. Gibbs' propert is generally known by the property
address 3742 Van Dorn Drive.
In May 2008, Mr. Gibbs made a Service Request (Attachment No.1) for installation
of an underground primary line extension from an existing sector to a new padmount
transformer. The resulting Customer Cost Quote (Attachment No.2) 'includedline
installation cost, line installation allowances, engineering charges, and a charge for
Unusual Conditions. The Cost Quote was calculated under the provisions of the
Company's Rule H tariff, "New Service Attachments and Distribution Line Installations or
Alterations" (Attachment No.3). On May 20, 2008, Mr. Gibbs paid the full cost of the Cost
Quote and signed an Unusual Conditions Acknowledgement (Attachment No.4).
On June 5, 2008, Idaho Power's contractor, 4 T Construction, installed an
underground primary line extension from an existing sector to a new padmount transformer
as set out in the Work Order and Work Order Map (Attachment No.5). The contractor dug
a 180-foot trench from the sector to the padmount transformer, as indicated in the notes
section of the Daily Progress Report (Attachment No.6). Of this distance, 160 feet was
"rocky trench" that required "hammering basalt with hoe bucket to break up and dig." The
contractor then set the pad box and temporary pedestal, pulled 194 feet of 1/0 primary
underground cable, set the padmount transformer, and backfilled the trench with dirt.
Idaho Power received the contractor's Change Order (Attachment No.7) for the 160 feet of
rock trenching on July 8, 2008, and paid the invoice on July 15, 2008. The Company then
refunded the difference between the Unusual Conditions estimate and the amount charged
by the contractor to Mr. Gibbs on July 22, 2008.
ANSWER -2
On July 23, 2008, Jonathan Gibbs came to the McCall Operations Center and
wished to discuss the amount of the Unusual Conditions Charge. Because the Idaho
Power Delivery Area Leader assisting Mr. Gibbs did not have the Work Order information
available, he told Mr. Gibbs that he would research the Work Order and contacthim. Idaho
Power's McCall Delivery Area Leader attempted to call Mr. Gibbs on July 25, 2008, but
received no answer. The Delivery Area Leader called Mr. Gibbs again on July 28, 2008,
and advised him that the Unusual Conditions Charge resulted from 160 feet of rock
trenching and that this was the amount it cost Idaho Power to have its subcontractor dig
the trench through the rock. Mr. Gibbs indicated that he intended to file a complaint with
the Idaho Public Utilities Commission.
UNUSUAL CONDITIONS CHARGE
At the time the Cost Quote was prepared in May 2008, the Company's Distribution
Design Representative estimated that an unusual cost of $4,000 would be incurred for rock
trench digging and added that amount to the Cost Quote. This estimate was based on the
designer's experience, conversations with other designers, and the fact that two rock
quarries are located adjacent to Mr. Gibbs' subdivision. Although identified and paid
u pfro nt, charges for Unusual Conditions are eligible for refund if the conditions are not
encountered.
In this case, the Company's contractor encountered 160 feet of rock trench digging
(see attached photos and Daily Progress Report, Attachment No.6) and billed the
Company $3,918.40 ($24.49 per foot x 160 feet) through a Change Order (Attachment No.
7) for the Unusual Condition. Although the contractor's backhoe bucket had new teeth
when it started digging Mr. Gibbs' trench, the rock was so difficult to break up that the
ANSWER -3
bucket teeth had to be replaced at the end of the job. The 20 feet closest to the sector and
road were not unusually rocky and thus were not included in the Unusual Conditions
Charge. The Company accordingly refunded Mr. Gibbs $81, the difference between the
estimated Unusual Conditions and those actually encountered. This result is in keeping
with the Unusual Conditions Acknowledgement (Attachment No.4) signed by Mr. Gibbs on
May 20, 2008.
Unusual Conditions as defined by Section 1 of the Company's Rule H tariff are
"construction conditions not normally encountered." Normal conditions pertain to.
conditions most commonly encountered throughout the Company's service territory and
are not representative of specific areas or regions. As specifically set out in the definition
of "Unusual Conditions," rock digging is not a normal construction condition encountered
throughout the Company's service territory. Consequently, Mr. Gibbs was required to pay
an Unusual Conditions Charge.
Although Mr. Gibbs argues to the contrary, Idaho Power believes the amount paid to
its contractor for the project is reasonable. As is its customary practice, Idaho Power uses
a bidding process to award a multi-year contract to a subcontractor in each of Idaho
Power's operational areas for the installation of electrical facilities. Contracts are awarded
based on the subcontractor's qualifications and bid prices. Idaho Power currently has a
three-year contract for electric facilties installation in the McCall/Payette Operations Area
with 4 T Construction. 4 T Construction has a proven track record of providing facility
installation and trenching in accordance with Idaho Power's specifications, and satisfies
Idaho Power's training and insurance requirements. Idaho Power's inspector verified that
160 feet of rock trench had in fact been dug by 4 T Construction for Mr. Gibbs' primary line
ANSWER -4
extension, as evidenced on the Change Order (Attachment No.7). The Unusual
Conditions Charge for rock trenching was calculated on the per unit ($24.49 perfoot) basis
that resulted from the contract bidding process; Idaho Power's Unusual Conditions Charge
was the pass-through cost that it paid its contractor and nothing more.
CUSTOMER-PROVIDED TRENCHING
Mr. Gibbs also contends that he was told that he could not provide his own trench.
The Company's Distribution Design Representative does not recall tellng Mr. Gibbs that he
could not provide his own trench, and to do so would have been unusuaL. Idaho Power
often permits customers (usually subdivision developers with the requisite equipment) to
trench for primary service but does not generally encourage it. However, either result is
permissible according to Rule H Section 2(1):
The Company wil at its discretion allow an Applicant,
Additional Applicant or subdivider to provide trench digging and
backfilL. In a joint trench, backfill must be provided by the
Company. Costs of Customer-provided trench and backfil wil
be removed or not included in the Work Order Costs and will
not be subject to refund.
It is the Representative's standard practice to provide customers a "Reduced
Charge Option for Underground Electrical Service" brochure 1 (Attachment No.8), which
explains the Company's requirements for customers providing their own trench. The
Reduced Charge Option for Customer Provided Trench & Conduit found in Rule H Section
4(c) covers "underground electrical service" (i.e., lower voltage secondary service from the
transformer to the meter base), not primary service trenching from the sector to the
transformer.
11n addition to other documents and FAQs related to New Construction Electric Service, the Reduced
Charge Option brochure can be found under the Construction link on Idaho Powets website at:
http://ww.idahopower.com/pdfs/customerservice/newConstruction/DFEO71 ReducedChargeOption. pdf.
ANSWER -5
At the time he signed and paid the Cost Quote, Mr. Gibbs discussed the customer-
provided trench option with Idaho Power's Distribution Design Representative and
indicated that he planned to use this Reduced Charge Option. Mr. Gibbs' intent is
evidenced by the notation and customer signature at the bottom of the Service Request
(Attachment No.1) indicating: "CUSTOM TO PROVIDE 3" CONDUIT FOR FUTURE
UNDERGROUND SERVICE." If Idaho Power were to instead provide the trench for
secondary service, it would also provide conduit as part of the cost for Company Installed
Facilities set by Rule H. Thus, Mr. Gibbs was aware that customers may provide their own
trenching.
In some construction situations, particularly when primary service is being installed,
the Company may spend additional time explaining the logistical, safety, and cost
ramifications of customer-provided trenching. This discussion may discourage customers
from providing their own trench because of the lack of cost savings to the customer and/or
scheduling difficulties with excavators and inspectors. When a customer provides the
trench, the customer must dig the trench to the proper depth (42" for primary service, 36"
for secondary service), backfill of the trench after the conduit is installed, and compact the
trench in accordance with certain specifications. Idaho Power requires that the trench be
open when its representatives arrive at the job site to install conduit so that the Company
can inspect the depth. The customer must then have someone at the job site to backfill as
soon as Idaho Power installs the conduit so that it can start pullng cable through conduit
secured by the dirt. It is also the customer's responsibility to "shade" the conduit with dirt
or sand around and on top of the conduit before backfillng to protect the conduit from
rocks as the material is pushed into the trench. The customer must also find and repair the
ANSWER -6
conduit if the conduit is damaged during backfllng such that Idaho Power cannot pull
cable through the conduit. In short, there is considerable coordination that must take place
in order to complete the work in a timely manner.
Idaho Power's experience with customer-provided trenching is that it often results in
time spent waiting on others to complete their portion of the work. Either the excavator
is waiting on the conduit to be placed or the Idaho Power crew that is doing the job is
waiting on the excavator to dig and backfill so they can finish their work. The customer is
required to pay for this down time, whether it is the excavator's.time or the time of Idaho
Power's crew. While the idea of customer-provided trench is that Idaho Power would not
have to bring a backhoe to the job site, Idaho Power often needs a backhoe to finish the
job, which again adds cost to the customer.
Additional safety issues arise when customers attempt to provide trenching for the
higher voltage primary service line as they dig around the sector device that the power wil
be coming from as it is energized. The customer is responsible for the primary service
trench to the transformer location and the backfil, but Idaho Power crews must place the
gravel and compact the transformer pad.
In sum, Idaho Power does not encourage customers to dig their primary service
trench given the number of logistical and safety issues that can arise. In the Company's
experience, customers digging primary trenches do not save much money and sometimes
pay more than what Idaho Power would have charged. In Mr. Gibbs' situation the
Company's representative may have discouraged Mr. Gibbs from providing his own
primary trenching, but Mr. Gibbs was not told that he could not provide his own primary
trench.
ANSWER -7
COMPANY POSITION
The Company contends that the trenching provided for Mr. Gibbs' primary service
line installation required rock digging and was properly identified and charged as an
Unusual Condition under the Company's Rule H "New Service Attachments and
Distribution Line Installations or Alterations." The Company also contends that the Unusual
Conditions amount charged was reasonable given the work required. Finally, Idaho Power
maintains that it did not tell Mr. Gibbs he could not provide his own primary trench -
particularly given Mr. Gibbs' stated intent to provide his own secondary service trench.
COMMUNICATIONS AND SERVICE OF PLEADINGS
Service of pleadings and communications with reference to this case should be sent
to the following:
Lisa Nordstrom
Barton L. Kline
Idaho Power Company
1221 West Idaho Street
Boise, Idaho 83702
Inordstrom~idahopower.com
blkine~idahopower.com
Ric Gale
Scott Sparks
Idaho Power Company
1221 West Idaho Street
Boise, Idaho 83702
rgale~idahopower.com
ssparks~idahopower.com
REQUESTED RELIEF
For the reasons stated above, Idaho Power requests that the Commission deny Mr.
Gibbs' Complaint and uphold the reasonableness of the Unusual Conditions Charge in
accordance with Idaho Power's approved Rule H tariff.
Dated this 23rd day of September 2008.
.
LISA D. NORDST
Attorney for Idaho
ANSWER - 8
CERTIFICATE OF MAILING
I HEREBY CERTIFY that on the 23rd day of September 2008 I served a true and
correct copy of the within and foregoing ANSWER upon the following named parties by the
method indicated below, and addressed to the following:
Weldon Stutzman
Deputy Attorney General
Idaho Public Utilties Commission
472 West Washington Street
P.O. Box 83720
Boise, Idaho 83702
-2 Hand Delivered
U.S. Mail
_ Overnight Mail
FAX
-2 Email Weldon.stutzman~puc.idaho.gov
Jonathan Gibbs
9502 Scorpio
Boise, Idaho 83709
Hand Delivered
-2 U.S. Mail
_ Overnight Mail
FAX
Email
~l)~Lisa D. Nordstrom .
ANSWER -9
BEFORE THE
IDAHO PUBLIC UTiliTIES COMMISSION
CASE NO. IPC-E-08-18
IDAHO POWER COMPANY
ATTACHMENT NO.1
!4H1~PO
An lDACI/ cov
Idao Powei. Company
Service Request
"':1
Dat 5/161
Service Reuest Number: 009395
GIBBS, JONATHAN-URn LINE EX FROM SEClERDD4 TO NEW PMT
Work Orde Number: 172188
Reues Ty: RS
Rate Sch: 1
Reply By:
Feeder: NWMS41A
Serce Locaon: NEW MEOWS,ID 83654
Requir in Servce Date:1017/Z007
Planing Centerfleam: MC CA
Eng Hour: 0011
Eng Fee Amount (Att 98): SSo.OO
Eng Fee Amount (Att 16):
En Fee Serice Agmet No:
En Fee Service Agrmet Date:
Cutomer No: 18769491
Centaet DeIl:
2S2R JONATH GmBS
!)2 SCORPIO ST" BOISE ID 8370
CUST JONATHAN GmBS
9501 SCORPIO ST" BOIS ID 83709
IPO FLIN
"
Attbute Informatin
RES/COM
Service Voltage:
No. OfPl:
KW Motor Load:
Largest Motor:
i Phase KW Demd:
3 Phase KW Demand:
Connecte KW Lod: 25
Com~æi De~n Anum:
No. of Meters: 1
Mfr. Lac:
CtLoc:
Pr OHlG: UG
Serice OHlG: UG
SIV.Ownr:
Panl Amp Siz: 200
~
NEED PRIY LIN EXION FROM EXISTIG SEC TO NEW PADMOUN TRSFORMR
AN UNERGROUN EAEM is NEEDED FROM CUSTOME TO ACCOMPLISH LIN EXTENTION
UNERGROUN SERVICE CHGES IS NOT INCLUDED INTffS WORK ORDER
CUTOM TO PROVIE 3" CONDUI FOR FU UNERGROUN SERVICE.
IPCO WILL BE DIGGING ALONG EDGE OF CUSTOMES DRIWAY, BUT DRIWAY is NOT
THE YE, SO NO PROVISIONS TO REPAI DRlVEWAY IS IN TIS WORK ORDER.
I undertad that the information provided above is accurate to the best of my knowledge. Changes to load; voltage; location; etc.
may, result in additional engineering chaes.
L~L.' ~ jJ-¡l~;n ¡
l.Client Signature Date asf!Facilty Rep. Signat
5/'~1 gf ,
Date Attachment No. 1
Case No. IPC-E-08-18
Idaho Power Company
Page 1 of 1
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-08-18
IDAHO POWER COMPANY
ATTACHMENT NO.2
!!IDA~PO..
An IDARP company
CUSTOMER COST QUOTE
IDAHO
Customer or Projec Name:
GIBBS, JONATHAN.URD UNE EXT FROM SECTR DD4 TO NE
Prepaid Fee
Deign Numbe
0000071192
Creit
Work Order ft
27284188
1. Line InstaIIationlUpgrade Costs
2. Company Bettrment
3. Line Installation Allownces
a. Custome Cash Allownce
b. Terminal Facilites Allownce
c. Salvage Taxable - Creit
4. Line Instllaon Credit (Customer Proided Tronch)
5. Veste Interet Work Order #
6. Bank Leer of Credit (for Unusual Conditions over $10,00)
7. Unusual Conditions
6161
Debit
4,8401
Total .
~t:I 01
I 01
1,8331
01
4,0001
5,8331
4.0001
1.831
8. Net Consction Cost
9. Net Vested OR Refundable Constrcton Cos (Lmited to 5 years or 4 additonal applica)
10. Construction Cost Not Available for Vesng or Reund
11. Right of Way Permits (NSR)
12. Bilable Engineering Charges (NSR) (11 Hrs (l $50 per Hr)
13. Underground Service Charg (NSR)
14. Relocation or Removal Charges (NSR)
a. Reloction or removal wilh new load. (412)
b. Relocll or reval wilh NO ne load (415)
Co Non-Taxble Salvage Crdit on Relocation or Removal
I
I
I
01
5501
01
01
01
01
01
5501
01
15. Other Charges
16. Feeder Charge
17. Sub-Total Non.Refundable Charges
18. Engineering Fees
19. Right of Way Permits (NSR)
20. Temporary Service Chae (NSR)
21. Total Preid Cuser Charges
$01
I $01~~
$3.0071
$ 9.3901
$ 6,3831
22. Idaho Power Co. ContrbutIon & Bank Lettr of Credit
23. Total Work Order Charges
24. Total Cusomer Payment Due (Una 8 + Una 17)
Notes:
Notice: This Wrn quotaon shall be binding on the Company for a period of sixt days (60) from th date below IndIcated.
subjec to changes In informaion provide by the Customer or changes in Ihe Companys abilit to obtn Satfactor
rights-of-w or to comply wi govrnmental regulations. Incuding but not limid to the rule, reulations. and tariff of the Idaho
Public Utilities Commission. The Customer must make payent of the quote amount not les thn Ihrrt (30) days prior to the
start of constrction. but the Company does not reprent tht constructon will commence within 30 das of recept of payment
The sta of constrcton will be subject to th Compas abill to obtan the nesary labo. materis and equipmentustome Signatre Date
,;:;Zi' - b Z
uotatlon Date ~
0.2
Case No. IPC-E-08-18
Idaho Power Company
Page 1 of 1
CC 2 REfH200
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-08-18
IDAHO POWER COMPANY
ATTACHMENT NO.3
Idaho Power Company
RULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INS:TALLATIONS OR
ALTERATIONS
IDAHO PUBLIC UTILITIES COMMISSION. . Approved EffectiveOnginal Sheet No. H-1 Feb. 29, 2008 March 1,2008
Per O.N. 30508
Jean D. Jewell Secretary
I.P.U.C. No. 29. Tariff No. 101
This rule applies to requests for electric service under Schedules 1,4,5, 7, 9,19,24,45, and 46
that require the installation, alteration, relocation, removal, or attachment of Company-owned
distribution facilties. New construction beyond the Point of Delivery for Schedule 9 or Schedule 19 is
subject to the provisions for facilties charges under those schedules. This rule does not apply to
transmission or substation facilties, or to requests for electric service that are of a speculative nature.
1. Definitions
Additional Applicant is a person or entity whose Application requires the Company to provide
new or. relocated service from an existing section of distribution facilties with a Vested Interest.
. Applicant is a person or entity whose Application requires the Company to provide new or
relocated service from distribution facilties that are free and clear of any Vested Interest.
Application is a request by an Applicant or Additional Applicant for new electric service from the
Company. The Company, at its discretion, may require the Applicant or Additional Applicant to sign a
written application.
Company Betterment is that portion of the Work Order Cost of a Line Installation, alteration,
and/or Relocation that provides a benefit to the Company not required by the Applicant o~ Additional
Applicant. Increases in conductor size and work necessitated by the increase in conductor size are
considered a Company Betterment if the Connected Load added by the Applicant or Additional
Applicant is less than 100 kilowatts. If, however, in the Company's discretion, it is determined that the
additional Connected Load added by the Applicant or Additional Applicant, even though less than 100
kilowatts, is (1) located in a remote location, or (2) a part of a development or project which wil add a
load greater than 100 kilowatts, the Company wil not consider the work necessitated by the load
increase to be a Company Betterment.
Connected Load is the total nameplate kW rating of the electric loads connected for commercial,
industrial, or irrigation service. Connected Load for residences is considered to be 25 kW for
residences with electric space heat and 15 kW for all other residences.
Fire Protection Facilties are water pumps and other fire protection equipment, served
separately from the Applicant's other electric load, which operate only for short periods of time in
emergency situations and/or from time to time for testing purposes.
Line Installation is any installation of new distribution facilities (excluding Relocations or
alteration of existing distribution facilties) owned by the Company.
IDAHO
Issued per Order No. 30508
Effective - March 1, 2008
Attachment NO.3
Case No. IPC-E-08-18
Idaho Power Company
Page 1 of 16
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise, ID
Idaho Power Company
I.P.U.C. No. 29. Tariff No. 101 Original Sheet No. H-2
IDAHO PUBLIC UTILITIES COMMISSIONApproved Effective
Feb. 29, 2008 March 1, 2008
Per O.N. 30508
Jean D. Jewell SecretaryRULEH
NEW SERVICE AlTACHMENTS
AND DISTRIBUTION LlNE
INSTALLATIONS OR
ALTERATIONS
(Continued)
1. Definitions (Continued)
Line Installation Allowance is the portion of the estimated cost of a Line Installation funded by
the Company.
Line Installation Charge is the partially refundable charge assessed an Applicant or Additional
Applicant whenever a Line Installation is built for that individuaL.
Local Improvement District is an entity created by the appropriate city or county goveming body,
as provided by Idaho Code §50~2503, whose purpose is to provide for the study, financing and
construction of a Distribution Line Installation or alteration. The governing body shall assess propert
owners to recover the cost of the distribution Line Installation or alteration. A Local Improvement
District has discernible propert boundaries.
Multiple Occupancy Projects are project that are intended to be occupied by more than four
owners or tenants. Examples include. but are not limited to, condominiums and apartments.
Relocation is a change in the location of existing distribution facilities.
Residence is a structure built primarily for permanent domestic dwellng. Dwellngs where
tenancy is typically less than 30 days in length, such as hotels, motels, camps, lodges, clubs, and
structures built for storage or parking do not qualify as a Residence.
Subdivision is the division of a lot, tract, or parcel of land into two or more parts for the purpose
of transferring ownership or for the construction of improvements thereon, that is lawfully recognized
and approved by the appropriate governmental authorities.
Temporary Line Installation is a Line Installation for electric service of 18 calendar months or
less in duration.
Temporary Service Attachment is a service attachmentto a Customer-provided temporary pole
which typically fumishes electric service for construction.
Terminal Facilties include transformer, meter, service cable. and underground conduit (where
applicable).
Underground Service Attachment Charge is the non-refundable charge assessed an Applicant
or Additional Applicant whenever new single phase underground service is required by a Schedule 1, 4,
5, or 7 customer attaching to the Company's distribution system.
Attachment NO.3
Case No. IPC-E-08-18
Idaho Power Company
Page 2 of 16
IDAHO
Issued per Order No. 30508
Effective - March 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affirs
1221 West Idaho Street, Boise, 10
Idaho Power Company
I.P.U.C. No. 29. Tariff No. 101 Original Sheet No. H-3
IDAHO PUBLIC UTILITIES COMMISSIONApproved Effective
Feb. 29, 2008 March 1,2008
Per O.N. 30508
Jean D. Jewell SecretaryRULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
AL TERA TIONS
(Continued)
1. Definitions (Continued)
Unusual Conditions are construction conditions not normally encountered. These conditions
may include, but are not limited to: frost, landscape replacement, road compaction, pavement
replacement, chip-sealing, rock digging, boring, nonstandard facilties or construction practices, and
other than available voltage requirements.
Vested Interest is the right to a refund that an Applicant or Additional Applicant holds in a
specific section of distribution facilties when Additional Applicants attach to that section of distribution
facilties.
Vested Interest Charge is an amount collected from an Additional Applicant for refund to a
Vested Interest Holder. .
Vested Interest Holder is an entity that has paid a refundable line Installation Charge to the
Company for a Line Installation. A Vested Interest Holder may also be an entity that has paid a
refundable charge to the Company under the provisions of a prior rule or schedule.
Vested Interest Refund is a refund payment to an existing Vested Interest Holder resulting from
a Vested Interest Charge to an Additional Applicant.
Vested Interest Portion is that part of the Company's distribution system in which a Vested
Interest is held.
Work Order Cost is a cost estimate penormed by the Company for a specific request for service
by an Applicant or Additional Applicant. The Work Order Cost wil include general overheads limited to
1.5 percent. General overheads in excess of 1.5 percent will be funded by the Company.
2. General Provisions
a. Cost Information. The Company wil provide cost information as reflected in the
charges contained in this rule, to potential Applicants and/or Additional Applicants. This
preliminary information wil not be considered a formal cost quote and wil not be binding on the
Company or Applicant but rather wil assist the Applicant or Additional Applicant in the decision
to request a formal cost quote. Upon receiving a request for a formal cost quote, the Applicant
or Additional Applicant will be required to prepay non-refundable engineering costs to the
Company.
b. Ownership. The Company wil own all distribution Line Installations and retain allrights to them. . Attchment NO.3
Case No. IPC-E-08-18
Idaho Power Company
Page 3 of 16
IDAHO
Issued per Order No. 30508
Effective - March 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise, ID
Idaho Power Company
I.P.U.C. No. 29. Tariff No. 101 Original Sheet No. H--
IDAHO PUBLIC UTILITIES COMMISSIONApproved Effective
Feb. 29, 2008 March 1, 2008
Per O.N. 30508
Jean D. Jewell SécretaryRULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
2. General Provisions (Continued)
c. Rights-of-Way. The Company wil construct, own, operate, and maintain lines
only along public streets, roads, and highways that the Company has the legal right to occupy,
and on public lands and private property across which rights-of-way satisfactory to the Company
may be obtained at the Applicant's or Additional Applicant's expense.
d. Removals. The Company reserves the right to remove any distribution facilties
that have not been used for one year. Facilties shall be removed only after providing 60 days
written notice to the last Customer of record and the owner of the property served, giving them a
reasonable opportunity to respond.
e. Property Specifications. Applicants or Additional Applicants must provide the
Company with final propert specifications as required and approved by the appropriate
governmental authorities. These specifications may include but are not limited to: recorded plat
maps, utilty easements, final construction grades, and propert pins.
f. Undeveloped Subdivisions. When electric service is not provided to the
individual spaces or lots within a Subdivision, the Subdivision wil be classified as undeveloped.
g. Mobile Home Courts. Owners of mobile home courts wil install, own, operate,
and maintain all termination poles, pedestals, meter loops, and conductors from the Point of
Delivery.
h. Conditions for Start of Constructon. Construction of the Line Installations and/or
Relocations wil not be scheduled until the Applicant or Additional Applicant pays the
appropriate charges to the Company.
i. Terms of Payment. All payments listed under this section wil be paid to the
Company in cash, a minimum of 30 days and no more than 120 days, prior to the start of
Company construction, unless mutually agreed otherwise.
j. Interest on Payment. If the Company does not start construction on a Line
Extension and/or Relocation within 30 days after receipt of the construction payment, the
Company wil compute interest on the payment amount beginning on the 31 st day and ending
once Company construction. actually begins. Interest wil be computed at the rate applicable
under the Company's Rule L. If this computation results in a value of $10.00 or more, the
Company will pay such interest to the Applicant, Additional Applicant, or subdivider.
Attachment NO.3
Case No. IPC-E-08-18
Idaho Power Company
Page 4 of 16
IDAHO
Issued per Order No. 30508
Effective - March 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affirs
1221 West Idaho Street, Boise, ID
Idaho Power Company
I.P.U.C. No. 29, Tariff No. 101 Original Sheet No. H-S
IDAHO PUBLIC UTILITIES COMMISSIONApproved Effctive
Feb. 29, 2008 March 1, 2008
Per O.N. 30508
Jean D. Jewell SecretaryRULEH
NEW SERVICE ATIACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
AL TERA TIONS
(Continued)
2. General Provisions (Continued)
k. Fire Protection Facilities. The Company wil provide service to Fire Protection
Facilities when the Applicant pays the full costs of the Line Installation including Terminal
Facilties, less Company Betterment. These costs are not subject to a Line Installation
Allowance, but are eligible for Vested Interest Refunds under Section 6.a.
i. Customer Provided Trench Digging and BackflL. The Company will at its
discretion allow an Applicant, Additional Applicant or subdivider to provide trench digging and
backfll. In a joint trench, backfll must be provided by the Company. Costs of Customer-
provided trench and backfill wil be removed or not included in the Work Order Costs and wil not
be subject to refund.
3. Line Installation Allowances
The Company wil contribute an allowance for the Terminal Facilties necessary for service
attachments and/or Line Installations. A Line Installation Allowance wil be applied to the Line
Installation costs for a Subdivision as outlined in Section 4,a.i. Subdividers may recoup their payments
only through the refunding provisions under Section 6 of this rule.
Schedules 1, 4, or S
Non-Electric Heat Residence
All-Electric Residence
Non-Residence
Multiple Occupancy Projects
Single Phase
Three Phase
Schedule 7
Single Phase
Three Phase
Schedule 9
Single Phase
Three Phase
Schedule 24
Single Phase
Three Phase
Schedule 19
Case-By-Case
Maximum Allowance
Overhead Terminal Facilties + $1,000
Overhead Terminal Facilties + $1,300
Cost of Meter Only
Overhead Terminal Facilties
80% of Terminal Facilities
Overhead Terminal Facilties
80% of Terminal Facilties
$1,726
80% of Terminal Facilities
$1,726
Overhead Terminal Facilties
Attachment No. 3
Case No. IPC.E.08.18
Idaho Power Company
Page 5 of 16
IDAHO
Issued per Order No. 30508
Effective - March 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise, ID
Idaho Power Company
I.P.U.C. No. 29. Tariff No. 101 Original Sheet No. H-6
IDAHO PUBLIC UTILITIES COMMISSIONApproved Effective
Feb. 29, 2008 March 1, 2008
Per O.N. 30508
Jean D. Jewell SecretaryRUlEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
4. Charges for Line Installations and Additional Charges for Underground Service
Attachments
An Applicant or Additional Applicant wil pay the Company for construction of Line Installations
and/or underground service attachments, less Line Installation Allowances, based upon the charges
listed in this section.
a. Line Installation Charge. If a Line Installation is required, the Applicant or
Additional Applicant wil pay a partially refundable Line Installation Charge equal to the Work
Order Cost less applicable Line Installation Allowances.
i. Une Installation Charges Inside Subdivisions. Inside a Residential
Subdivision, the Line Installation Charges are calculated using the Work Order Cost less
Terminal Facilities. The maximum refund wil be the total per lot refund amount as
specified in Section 6.b., but not more than the Work Order Cost less Terminal Facilties.
Costs of new facilties outside Subdivisions are subject to Vested Interest Refunds.
Inside a non-Residential Subdivision, the Line Installation Charges are calculated
as follows:
Schedule 7
Single Phase ......................................................................... Overhead Terminal Facilties
Three Phase........................................................... ....................80% of Terminal Facilties
Schedule 9
Single Phase ............."........................................................... Overhead Terminal Facilties
Three Phase............................................................................ ...80% of Terminal Facilties
Maximum Allowance
b. Underground Service Attachment Charge. Each Applicant or Additional
Applicant wil pay a non-refundable Underground Service Attachment Charge for attaching new
Terminal Facilties to the Company's distribution system. The Company wil determine the
location and maximum length of service cable.
Attachment No. 3
Case No. IPC-E-08-18
Idaho Power Company
Page 6 of 16
IDAHO
Issued per OrderNo. 30508
Effective - March 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise,ID
Idaho Power Company First Revised Sheet No. H-7
Cancels
Original Sheet No. H-7I.P.U.C. No. 29. Tariff No. 101
RULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
IDAHO PUBLIC UTILITIES COMMISSIO~Approved EffctivE
May 30.2008 June 1, 2001
Per O.N. 30558
Jean D. Jewell Secretary
4. Charges for Line Installations and Additional Charges for Underground Service
Attachments (Continued)
Schedules 1. 4. 5 and 7. Single Phase (Limited to a maximum of 400 Amps)
Underground Service Cable (Base charge plus Distance Charge)
Base Charge
from underground
from overhead including 2" riser
from overhead including 3" riser
$40.00
$395.00
$520.00
Distance Charge (per foot)
Company Installed Facilties (per foot)
with 1/0 underground cable $6.90
with 4/0 underground cable $7.50
with 350 underground cable $9.60
Customer Provided Trench & Conduit (per foot)
with 1/0 underground cable $2.15
with 4/0 underground cable $3.60
with 350 underground cable $4.65
c. Vested Interest Charge
Additional Definitions for Section 4.c. and Section 6.a.:
Original Investment - Work Order Cost less Terminal Facilities Allowance.
Vested Interest Holdets Contribution - Customer Payment plus Line Installation
Allowances other than Terminal Facilties.
Vested Interest - Amount potentially subject to refund.
Load Ratio - Additional Applicant load divided by the sum of Additional
Applicant's load and Vested Interest Holder's load.
Distance Ratio - Additional Applicant distance divided by original distance.
i. The initial Applicant will pay the original investment cost less any
allowances. An Additional Applicant connecting to a Vested Interest Portion wil have
two options:
Option One - An Additional Applicant may choose to pay the current
Vested Interest Holdets Vested Interest, in which case the Additional Applicant
wil become the Vested Interest Holder and, as such, wil be9QOOfi~ili~ to
receive Vested Interest Refunds up to that new Vestedaslrel-E.Jller's
contribution less 20 percent of the original investment Idaho Power Company. Page70f16
IDAHO
Issued Per IPUC Order No. 30558
Effective - June 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affirs
1221 West Idaho Street, Boise, ID
Idaho Power Company First Revised Sheet No. H-8
Cancels
Original Sheet No. H-8
IDAHO PUBLIC UTILITIES COMMISSIOriApproved EffectivE
May 30, 2008 June 1, 200t
Per O.N. 30558
Jean D. Jewell Secretary
I.P.U.C. No. 29. Tariff No. 101
RULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
4. Charges for Line Installations and Additional Charges for Underground Service
Attachments (Continued)
Option Two - An Additional Applicant may choose to pay an amount determined
by this equation:
Vested Interest Payment = Load Ratio x Distance Ratio x Vested Interest
Holders unrefunded contribution.
If Option Two is selected, the Additional Applicant has NO Vested Interest and
the previous Vested Interest Holder remains the Vested Interest Holder. The Vested
Interest Holder's Vested Interest wil be reduced by the newest Additional Applicant's
payment.
ii. The Vested Interest Charge wil not exceed the sum of the Vested
Interests in the Vested Interest Portion.
ii. If an Additional Applicant connects to a Vested Interest Portion which was
established under a prior rule or schedule, the Vested Interest Charges of the previous
rule or schedule apply to the Additional Applicant.
5. Other Charges
All charges in this section are non-refundable.
a. Relocation and Removal Charges. If an Applicant or Additional Applicant
requests a Relocation or removal of Company facilties, the Applicant or Additional Applicant wil
pay a non-refundable charge equal to the Work Order Cost.
b. Engineering Charge. Applicants or Additional Applicants wil be required to
prepay all engineering costs for Line Installations, and/or Relocations greater than 16 estimated
hours. Estimates equal to or less than 16 hours wil be biled to the Applicant or Additional
Applicant as part of the construction costs, or after the engineering is completed in instances
where construction is not requested. Engineering charges wil be calculated at $50.00 per hour.
Attachment No. 3
Case No. IPC-E-08-18
Idaho Power Company
Page 8 of 16
IDAHO
Issued Per IPUC Order No. 30558
Effective - June 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise, ID
Idaho Power Company First Revised Sheet No. H-9
Cancels
Original Sheet No. H-9
IDAHO PUBLIC UTILITIES COMMISSIOflApproved EffectivE
May 30, 2008 June 1, 200f
Per O.N. 30558
Jean D. Jewell Secretary
I.P.U.C. No. 29. Tariff No. 101
RULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
5. Other Charges (Continued)
c.' Engineering Charges for Agencies and Taxing Districts of the State of'ldaho.
Under the authority of Idaho Code Section §67 -2302, an agency or taxing district of the State of
Idaho may invoke its right to decline to pay engineering charges until the engineering" services
have been performed and biled to the agency or taxing district. Any state agency or taxing
district that claims it falls within the provisions of Idaho Code §67-2302 must notify Idaho Power
of such claim at the time Idaho Power requests prepayment of the engineering charges. Idaho
Power may require that the state agency or taxing districts claim be in writing. If the state
agency or taxing district that has invoked the provisions of Idaho Code Section §67 -2302 does
not pay the engineering charges within the 60-day period as provided in that statute, all the
provisions ofthat statute wil apply.
d. Right of Way Charge. Applicants or Additional Applicants wil be responsible for
any costs associated with the acquisition of right-of-way.
e. Temporary line Installation Charge. Applicants or Additional Applicants wil pay
the installation and removal costs of providing Temporary Line Installations.
f. Temporarv Service Attachment Charge. Applicants or Additional Applicants wil
pay for Temporary Service Attachments as follows:
i. Underground - $140
The Customer-provided pole must be set within two linear feet of the Company's
existing transformer or junction box.
ii. Overhead - $120
The Customer-provided pole shall be set in a location that does not require more
than 100 feet of #2 aluminum service conductor that can be readily attached to the
permanent location by merely relocating it.
The electrical facilties provided by the Customer on the pole shall be properly
grounded, electrically safe, and ready for connection to Company facilities.
The Customer shall obtain all permits required by the applicable state, county, or
municipal governments and wil provide copies or verification to the Company as
required. The above conditions must be satisfied before the service wil be attached.
Attachment No. 3
Case No. IPC-E-08-18
Idaho Power Company
Page 9 of 16
IDAHO
Issued Per ¡PUC Order No. 30558
Effective - June 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affirs
1221 West Idaho Street, Boise, ID
Idaho Power Company
I.P.U.C. No. 29, Tariff No. 101
First Revised Sheet No. H-10
Cancels . IDAHO PUBLIC UTILITIES COMMISSIOf\Original Sheet No. H-10 Approved Effectiv.May 30, 2008 June 1, 200l
Per O.N. 30558
RULE H Jean D. Jewell Secretary
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
g. Temporarv Service Return Trip Charge. If the conditions stated in Section S.f. of
this rule are not satisfied prior to the Customets request for temporary service, a Temporary
Service Return Trip Charge ot$35.00 wil be assessed each time Company personnel are
dispatched to the job site, but are unable to connect the service. The charge wil be biled after
the conditions have been satisfied and the connection has been made.
h. Unusual Conditions. Applicants, Additional Applicants, and subdividers wil pay
the Company the additional costs associated with any Unusual Conditions included in the Work
Order Cost related to the construction of a Line Installation or Relocation. This payment, or
portion thereof, wil be refunded to the extent that the Unusual Conditions are not encountered.
Unusual Conditions payments for Line Installations wil also be refunded, under the provisions of
Section 6, if the Unusual Conditions are encountered.
In the event that the estimate of the Unusual Conditions included in the Work Order Cost
exceeds $10,000, the Applicant, Additional Applicant or subdivider may either pay for the Unusual
Conditions, or may furnish an Irrevocable Letter of Credit drawn on a local bank or local branch offce
issued in the name of Idaho Power Company for the amount of the Unusual Conditions. Upon
completion of that portion of the project which included an Unusual Conditions estimate, Idaho Power
Company wil bil the Applicant, Additional Applicant or subdivider for the amount of Unusual Conditions
encountered up to the amount established in the Irrevocable Letter of Credit. The Applicant, Additional
Applicant or subdivider wil have 15 days from the issuance of the Unusual Conditions billng to make
payment. If the Applicant, Additional Applicant or subdivider fails to pay the Unusual Conditions bil
within 15 days, Idaho Power wil request payment from the bank. .
i. Joint Trench. Applicants. Additional Applicants, and subdividers wil pay the
Company for trench and backfll costs included in the work order prepared for an unshared
trench. In the event that the Company is able to defray any of the trench and backfll costs
included in the work order through the sharing of the trench with other utilties, the trench and
backfll cost savings wil be refunded.
j. Underground Service Return Trip Charge. When a residential Customer agrees
to supply the trench, backfll, conduit, and compaction for an underground service, an
Underground Service Return Trip Charge of $50.00 wil be assessed each time the Company's
installation crew is dispatched to the job site at the Customer's request, but is unable to
complete the cable installation.
Attachment No. 3
Case No. IPC-E-08-18
Idaho Power Company
Page 10 of 16
IDAHO
Issued Per IPUC Order No. 30558
Effective - June 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President. Regulatory Affairs
1221 West Idaho Street, Boise, ID
Idaho Power Company
I.P.U.C. No. 29, Tariff No. 101
First Revised Sheet No. H-11
Cancels
Original Sheet No. H"11
IDAHO PUBLIC UTILITIES COMMISSIOF\Approved EffectivE
May 30, 2008 June 1, 200l
Per O.N. 30558
Jean D. Jewell SecretaryRULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
AL TERA TIONS
(Continued)
6. Refunds
a. Vested Interest Refunds. The initial Applicant wil be eligible to receive up to 80
percent of the original investment as a Vested Interest Refund in accordance with Section 4.c.
Refunds wil be funded by the Additional Applicant.s Vested Interest Charge as calculated in
accordance with Section 4.c. A Vested Interest Holder and the Company may agree to waive
the Vested Interest payment requirements of Additional Applicants with loads less than an
agreed upon leveL. Waived Additional Applicants would not be considered Additional Applicants
for purposes of Secton 6.a.i.(1).
i. Vested Interest Refund Limitations
(1). Except for Rule 6.c, Vested Interest Refunds wil be funded by no
more than four Additional Applicants during the 5-year period following the
completion date of the Line Installation for the initial Applicant.
(2). In no circumstance wil refunds exceed 100 percent of the
refundable portion of any party.s cash payment to the Company.
b. Subdivision Refunds
i. A subdivider wil be eligible for Vested Interest Refunds for payments for
Line Installations outside the subdivision.
ii. A subdivider wil be eligible for a refund from the Company on the' Line
Installation Charge inside the Subdivision when a permanent Residence connects for
service and occupies a lot inside the Subdivision within 5 years from the construction
completion date of the line Installation for the Subdivision.
iii. The amount refunded to subdividers of residential Subdivisions wil be
$800 per lot, less any additional Line Installation costs required to provide connected
service to the lot.
c. Special Rule for Undeveloped Subdivisions Platted Prior to January 1. 1997
i. For an undeveloped Subdivision which has been platted prior to January
1, 1997, and which has not been amended after January 1, 1997, refunds wil be made
for connections inside the Subdivision during the first 10 years following the completion
date of the line Installation.
Attachment No. 3
Case No, IPC-E-08-18
Idaho Power Company
Page 11 of 16
IDAHO
Issued Per IPUC Order No. 30558
Effective - June 1, 2008
Issued by IDAHO POWER COMPANY
John,R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise, ID
Idaho Power Company First Revised Sheet No. H-12
Cancels
Original Sheet No. H-12
IDAHO PUBLIC UTILITIES COMMISSIOi\Approved EffectivE
May 30, 2008; June 1, 200l
Per O.N. 30558
Jean D. Jewell Secretary
I.P.U.C. No. 29, Tariff No. 101
RULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
6. Refunds (Continued)
ii. The subdivider wil not be entitled to refunds under Sections B.b.H. and
6.b.iii. Connections within the undeveloped Subdivision wil be treated as individual
Applicants or Additional Applicants for payment, extension allowance, and refunding
purposes.
iii. The individual requesting the 10-year refund date wil have the burden of
demonstrating that the Line Installation is to a Subdivision which has been platted and is
undeveloped.
iv. Special Arrangements Permitting Deviation from Rule H Refund
Provisions - An Applicant and/or Applicants and the Company may mutually agree that
a deviation from Rule H refund provisions is reasonable and does not adversely affect
other Customers of the Company. A written agreement to deviate from Rule H refund
provisions wil be prepared and submitted to the Commission. The agreement wil not
be effective until approved by the Commission.
7. Line Installation Agreements
When the Line Installation Allowance paid by the Company under the provisions of this rule
equals or exceeds $75,000, the Applicant wil be required to contract to pay. for a period of 5 years
following the completion date of the Line Installation, an annual payment equal to the greater of the
bilings determined by application of the appropriate schedule or:
a. Eighty percent of the Applicant's total annual bil as determined by application of
the appropriate schedule; plus;
b. Twenty percent of the Line Installation Allowance granted the Applicant.
Each Line Installation, for which the Line Installation Allowance paid equals or exceeds
$75,000, will require a separate Uniform Distribution Line Installation Agreement between the
Applicant and the Company.
Developers of multi-family residential dwellngs in which each unit is separately metered
wil be exempt from the requirement to enter into an agreement with the Company if the Line
Installation Allowance paid equals or exceeds $75,000.
IDAHO
Issued Per IPUC Order No. 30558
Effective - June 1, 2008
Attachment No. 3
Case No. IPC-E-08-18
Idaho Power Company
Page 12 of 16
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise, ID
Idaho Power Company First Revised Sheet No. H-13
Cancels
Onginal Sheet No. H-13
IDAHO PUBLIC UTILITIES COMMISSIOllApproved EffectivE
May 30,2008 June 1, 200f
Per O.N. 30558
Jean D. Jewell Secretary
I.P.U.C. No. 29. Tariff No. 101
RULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
AL TERA TIONS
(Continued)
8. Existing Agreements
This rule shall not cancel existing agreements, including refund provisions, between the
Company and previous Applicants, or Additional Applicants. All Applications wil be governed and
administered under the rule or schedule in effect at the time the Application was received and dated by
the Company.
9. Locallrnprovement Distncts
Unless specifically provided for under this paragraph, a Local Improvement Distnct wil be
provided service under the general terms of, this rule.
The Company wil provide a cost estimate and feasibilty study for a Local Improvement District
within 120 days after receiving the resolution from the requesting governing body. The cost estimate
wil be based on Work Order Costs and wil not be considered binding on the Company if construction
is not commenced within 6 months of the submission of the estimate for reasons not within the control
of the Company. The governing body issuing the resolution wil pay the Company for the costs of
prepanng the cost estimate and feasibilty study regardless of whether the Line Installation or the
conversion actually takes place.
Unless specifically provided for under this paragraph, a Local Improvement Distnct wil be
provided service under the general terms of this rule.
The Company wil provide a cost estimate and feasibility study for a Local Improvement District
within 120 days after receiving the resolution from the requesting governing body. The cost estimate
wil be based on Work Order Costs and wil not be considered binding on the Company if construction
is not commenced within 6 months of the submission of the estimate for reasons not within the control
of the Company. The governing body issuing the resolution wil pay the Company for the costs of
preparing the cost estimate and feasibilty study regardless of whether the Line Installation or the
conversion actually takes place.
After passage of the Local Improvement District ordinance, the Company wil construct the Line
Installation or conversion. Upon completion of the project, the Company wil submit a bil to the Local
Improvement District for the actual cost of the work performed, including the costs of preparing the cost
estimate and feasibilty study. If the actual cost is less than the estimated cost, the Local Improvement
District wil pay the actual cost. If the actual cost exceeds the estimated cost, the Local Improvement
District wil pay only the estimated cost. The governing body wil pay the Company within 30 days after
the bil has been submitted.
Attachment No. 3
Case No. IPC-E-08-18
Idaho Power Company
Page 13 of 16
IDAHO
Issued Per IPUC Order No. 30558
Effective - June 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise, ID
Idaho Power Company First Revised Sheet No. H-14
Cancels
Original Sheet No. H-14I.P.U.C. No. 29. Tariff No. 101
RULEH
NEW SERVICE ATIACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
IDAHO PUBLIC UTILITIES COMMISSIOf\Approved EffectivE
May 30, 2008 June 1, 200(
Per O.N. 30558
Jean D. Jewell Secretary
9. . Local Improvement Districts (Continued)
A Local Improvement District wil be eligible for a Line Installation Allowance for any new load
connecting for service upon the completion of the Line Installation. A Local Improvement District wil
retain a Vested Interest in any Line Installation to the Local Improvement District. A Local Improvement
District may waive payments for Vested Interest from Additional Applicants within the Locl
Improvement District.
Attachment No. 3
Case No. IPC-E-08-18
Idaho Power Company
Page 14 of 16
IDAHO
Issued Per IPUC Order No. 30558
Effective - June 1,2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise, ID
Idaho Power Company
I.P.U.C. No. 29. Tariff No. 101
First Revised Sheet No. H-15
Cancels
Original Sheet No. H-15
IDAHO PUBLIC UTILITIES COMMISSIO~Approved EffectivE
May 30,2008 June 1, 200i
Per O.N. 30558
Jean D. Jewell SecretaryRULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
Idaho Power Company
Uniform Distribution Line Installation Agreement
DISTRICT
THIS AGREEMENT Made this , 20_, between
, whosebilling address is hereinafter called
Customer, and Idaho Power Company, A corporation with its principal offce located at 1221 West
Idaho Street, Boise, Idaho, hereinafter called Company:
ACCOUNT NO.
day of
NOW THEREFORE, The parties agree as follows:
1. The Company will agree to provide facilties to supply
Service for the Customer's facilties located at or near , County of
Idaho.
volt, _ phase Electric
, State of
2. The Customer wil agree to:
a. Make a cash advance to the Company of $
Customer's share of the investment in service facilties;
as the
b. . Provide rights-of-way for the line extension at no cost to the Company, in a form
acceptable to the Company;
c. Pay an annual minimum charge during the first 60 months following the Initial
Service Date. The annual minimum charge wil be the greater of (1) the total of the schedule
bilings for the year or (2) $ plus 80 percent of the total schedule billngs for
the year. The total schedule billngs wil be computed in accordance with the rates and
provisions of the schedules under which the Customer received service for that year.
3. This Agreement wil not become binding upon the parties until signed by both parties.
4. The initial date of delivery of power and energy is subject to the Company's abilty to
obtain required labor, materials, equipment, satisfactory rights-of-way and comply with governmental
regulations.
5.
thereof.
The term of this Agreement wil be for 5 years from and after the Initial Service Date
Attachment NO.3
Case No. IPC-E-08-18
Idaho Power Company
Page 15 of 16
IDAHO
Issued Per IPUC Order No. 30558
Effective - June 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affirs
1221 West Idaho Street, Boise, 10
fdaho Power Company
I.P.U.C. No. 29. Tariff No. 101 Original Sheet No. H-16
IDAHO PUBLIC UTILITIES COMMISSIOltApproved EffectivE
May 30, 2008 June 1, 200l
Per O.N. 30558
Jean D. Jewell SecretaryRULEH
NEW SERVICE ATTACHMENTS
AND DISTRIBUTION LINE
INSTALLATIONS OR
ALTERATIONS
(Continued)
Idaho Power Company
Uniform Distribution Line Installation Agreement
(Continued)
6. This Agreement wil be binding upon the respective succssors and assigns of the
Customer and the Company, provided however, that no assignment by the Customer wil be effective
without the Company's prior written. consent. The Company's consent wil not be unreasonably
withheld.
7. This Agreement is subject to valid laws and to the regulatory authority and orders, rules
and regulations of the Idaho Public Utilities Commission and such other administrative bodies having
jurisdiction as well as Idaho Power Company's Rules and Regulations as now or may be hereafter
modified and approved by the Idaho Public Utilties Commission.
8. The Company's Rule H, any revisions to that rule, and/or any successor rule is to be
considered as part of this Agreement.
9. .In any action at law or equity commenced under this Agreement and upon which
judgment is rendered, the prevailng part, as part of such judgment, wil be entitled to recover all costs,
including reasonable attorneys fees, incurred on account of such action.
W.o. No.
Initial Service Date
(APPROPRIATE SIGNATURES)
Attachment No. 3
Case No. IPC-E-08-18
Idaho Power Company
Page 16 of 16
IDAHO
Issued Per IPUC Order No. 30558
Effective - June 1, 2008
Issued by IDAHO POWER COMPANY
John R. Gale, Vice President, Regulatory Affairs
1221 West Idaho Street, Boise, 10
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-08-18
IDAHO POWER COMPANY
ATTACHMENT NO.4
Custome or Proect Name:
GIBBS, JONATHAN.URD LINE EXT FROM SEeTER DD4 TO NE
Deign Number:
0000071192
Work Ord #:
27284188
~IDA~PO.AIlÐRPC:~
Unusual Conditions Acknowledgement.
Unusual Conditions ar constrction conditions not nonnaly encountered.
These conditions may include, but are not limted to: frost, landscape
replacement, road compaction, pavement replacement, chip-sealig, rock
digging, boring, nonstadard facilities or constrction pratices, and other than
available voltage requirements.
I have read and understand the above definition of Unusual
Conditions as set forth in Idaho Power Company's Line Installation
tariff, Rule H. I further understand that Idaho Power Company wil
determine the type and extent of the Unusual Conditions encountered.
Unusual Conditions charged for on the Customer Cost Quote sheet, but
not encountered, wil be refunded to the Customer by Idaho Power
Company after the completion of construction.
Signed: ~ø7;.~
Customer Signare
Date: 5--.z ¡: -r ~ %
Attachment NO.4
Case No. IPC-E-08-18
Idaho Power Company
Page 1 of 1
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-08-18
IDAHO POWER COMPANY
ATTACHMENT NO.5
;B.
AA IOACRPtompany
Idao Power Company
Contrctor WO Conscton Report ."~
P.:LDi SI
272188 - 02
Work Order: 17284188-02 -GmBS, JONAT~-URD LINE EXT FROM SECTR DD4 TO NE
Work Order Type: 45 / . ftÆ!J Designer: FLI MCDANIEL
Feeder: NW1&; ,?i¡i. J~'¡1JølJ''Vi(j¡; # Priority: 4
Service Addre: ~l"MEADOWS ID 8365
Cuomer Requested In Serice Dat,
WorkStDa Ó G -oS". 01(
0'0' 05'. o~
Foren', Jiitil
Righ of Way
Job Sta
Dig Lin fI
DaComplete Date
Cuomer Prvided Trenc Y N
Desig Descrption:
NEED PRIYLIBXTESIONFROM EXG SE TO NB PADMOUNTRSFORMR
AN UNERGROUN EA IS NEBDED FROM æSTOME TO ACCMPLIH LIN EXTETION
UNERGROUN SERVICB CHAGBS is NOTlNCLED IN THS WORK ORDER
CUSTOM TO PROVIE 3" CONDUI FOR FU UNERGROUN SEVICE.
Work Orer Directions:
Contact
CUST JONATIJAN GIBBSIPCO FLlN
Outside Services:
EquipltasOt
~
Flagger Gravel
BlasngIoc Crew:
~ ~MN_
~
~
~
~
Z
~~ ~Z ..~ ... E-l" ::= ~
5 t~ z
~ ~
~ ¡ontrneted Required Start Dale:R t:¿14,tJK Contrcted nequirc Finished Date:
Paving
& iS ,ô3
Attachment NO.5
Case No. IPC-E-08-18
Idaho Power Company
Page 1 of2
~284188. GIBBS, JONATHN.UR LlNEEX FROM SE DD4 TO NEW'PMTTR
;'Z
'
2
.
:
.
;
:
:
!
~
~
;
,
_
:
:
.
:
:
.
.
t
:
t
t
.
:
;
'
:
;
t
C
i
-
7
'
.
'
~
;
;
C
~
:
;
~
~
;
¿
5
-
'
:
,
;
:
:
~
~
~
~
'
~
-
:
'
g
~
.-
-
.
.
_
-
'
"
.
"
.
_
-
--
"
.
"
-
'
'
'
-
-
-
-
_
.
.
_
-
_
.
.
-
.
_
.
.
:
1
¡¡
:¡
IIIIII
;:
I
Ij
'/
(!
--
--
-
-
-
-
//
/
/
(!
PO
I
N
T
NU
M
B
E
R
12
ST
A
T
I
O
N
UN
D
E
R
G
R
O
U
N
D
C
A
B
L
E
N
O
T
E
S
i
C
A
B
L
E
C
A
B
L
E
T
R
E
N
C
H
C
O
N
D
U
I
T
C
O
N
D
U
I
T
.
S
I
Z
E
L
E
N
G
T
H
L
E
N
G
T
H
S
I
Z
E
L
E
N
G
T
H
60
2
"
6
0
1I
0
-
C
2
0
0
1
8
0
1
-
2
'
1
8
0
CO
M
P
A
C
T
I
O
N
LE
N
G
T
H
~C
O
M
E
O
U
T
T
H
E
B
A
C
K
O
F
S
E
C
T
E
R
A
T
A
N
A
N
G
L
E
F
O
R
P
R
I
M
A
R
Y
.
L
I
N
E
E
X
T
E
N
S
I
O
N
~
2
"
S
T
U
B
Ó
U
T
F
O
R
L
O
T
3
·
I
N
S
T
A
L
L
2
5
K
V
A
P
M
T
T
R
F
WI
T
H
3
"
S
T
U
B
F
O
R
S
E
R
V
I
C
E
A~
m
e
n
t
N
o
o
5
ca
N
o
.
I
P
C
-
E
-
0
1
8
Id
a
h
o
P
o
*
r
C
o
m
n
y
-
r
-
P
a
g
2
o
f
2
PR
I
M
A
R
Y
S
T
U
B
L
O
T
3
DD
4
T
O
D
D
4
4
30
rS
l
..
Cu
s
t
o
m
e
r
:
Do
t
e
:
Ad
d
i
t
i
o
n
a
l
D
e
s
c
r
i
p
t
i
o
n
.
St
O
l
e
10
Go
u
n
t
y
AD
A
M
S
Su
r
v
e
y
e
d
o
r
G
P
S
:
G
P
S
Jo
i
n
t
U
s
e
A
t
t
a
c
h
m
e
n
t
s
:
N
O
Pr
e
-
B
u
i
l
t
D
o
t
e
:
O
S
/
2
1
/
0
8
Bu
i
l
t
a
s
D
e
s
i
g
n
e
d
:
Co
n
s
t
r
u
c
t
i
o
n
O
a
t
o
e
:
Oo
e
r
a
t
i
n
o
V
o
l
t
a
g
e
:
7
.
2
k
Y
I
~
~
"
-
-
-
t
¡
-
l
l
r
F
M
B
y
Do
t
e
:
_
WO
R
K
O
R
D
E
R
M
A
P
S
C
,
t
,
L
E
o
De
s
i
g
n
e
r
:
F
R
M
0
5
6
4
Jo
b
T
i
t
l
e
.
GI
B
B
S
.
J
O
N
A
T
H
A
N
-
U
R
D
L
I
N
E
E
X
T
F
R
O
M
S
E
C
T
E
R
0
0
4
T
O
N
E
W
P
M
T
Ad
d
i
t
i
o
n
a
l
D
e
s
c
r
i
p
t
i
o
n
.
Fe
e
d
e
r
M
o
p
f
i
l
e
N
o
m
e
:
N
W
M
S
4
1
0
2
Qu
a
T
w
n
I
R
n
g
M
e
r
1
1
9
N
O
l
E
B
M
"
"
"
'
9
'
"
"
0
.
0
0
0
0
0
7
1
1
9
2
Wo
r
k
O
r
d
e
r
I
~
"
:
2
7
2
8
4
1
8
8
ID
A
H
O
P
O
W
E
R
C
O
.
'i
"
=
"
i
5
0
:,
h
S
¿
\
í
~
i
)
f
~
\'
,
~
$
M
"
f
i
l
S
'
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-08-18
IDAHO POWER COMPANY
ATTACHMENT NO.6
,
''"'''T Construction
~iI 'Progrss Reprt lìJ ~~ 3. Date:, 'O=OQ =
6-k-ks FOI'taD "'~ De.~v'.
Employe Name Postin n.e Tie Tota naif or Desripton ToWStartStHours.." ,"~e.¡Ç ¡""¿¡6 A I¿J?.:GO ~e:'~ '"..CJ.-f AnIJ 7;.(,7';~I;,.f: '....
..~t;A l..A"U'.Ot\,:'c."?,
,
-
..dplT,UIlN..Aet Mi Mi TotaHoursStart:St Miesfl~.l 1C:..:r-,I~,. b. &..0 J Cì:: L .I;;r:.L. ~..¿: ,I;)
.
Attac hment No. €.
e No. IPC-E.08-H
4T .J # ~7 . c.~Cuer#
Cas
-
("n- '- ~.'¡'..
No.1: Solid rock.Sifting required.
No.2: Solid rock trench walls. Broken up with backhoe pounding.
Attachment NO.6
Case No. IPC-E-08-18
Idaho Power Company
Page 2 of3
No.3: Broken basalt rock, no clean backfil present.
No.4: Trench length, depth.
Attachment No. 6
Case No. IPC-E-08-18
Idaho Power Company
Page 3 of 3
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-08-18
IDAHO POWER COMPANY
ATTACHMENT NO.7
611. M IOP Ccmny //1, I f-II I"
Change Order
Delivery Business Unit
9 -O.=
WOi Orde Number
, -~~
- c:d'AS
Pursuant to the coditons of the Constrion Agreeent reference aboe, the Contrct Docments are hereby amended as follos:
Description of Change (e.g., Addltioiis. Deletions, Revisions)
,
4 ¡r,'JJlb£ "-ßt:Ul rÆúi
inls Sup th Chnge
Bais of Compenstion
Pursuantto the General Conditons, Artcfe C.11, "Change in \h Worf: th
Contrar shall be copensaed for the chang descbe abov as folow:
o No aditioal compensation is applicble for this chnge.
¡;ay unit price applicable to the changed wor (pursantto General Conditions
C-11(a)). Th unit and quantites are desabed in 'Descrption of Change"
abve.
o By lump sum adjutmt to the chaged work (puruant to Geeral Conditions
C-11(b)). Th lump sum doll adjustnt is $
o On a time and materials basis (puuant to General Conditions e-11 (c)).
Estmated labor class and man-hours:
Esmate equipment type and hours:
Estimate subcntract or direc costs:
Time of Copletion Adjustment
Pursuant to th Gera Conditins. Aric C-2. "Time
and Orde of Completi: and Aricl C.11, 'Changes in
the Work,. the Time of Completion shall be adjuste as
follow:
o Tme of completi remains unchanged.
o TIme of completion date is incrased by _calendar days to . ~OO_'
o Other (Decrbe the time of completion adjustmnt)
This Chage Order represnts an acrd an satisfcton for all oost and/or time involved in completing the additional work described above
in the -Desciption of Change: Except as proyided herein, all terms and condiions of the Contract Documents. as heretofore modifed, remar
unchanged.
Prepare By:¥IT CtJtI
Ida POWIl Copany, Owne
~tÇlX(CY Attachment No. 7
Case No. IPC-E-08~18
Idaho Power Company
Page 1 of 1
Contractors Sigatur~(; 77
Approved By: Idaho Power Company. Owner~~Authozed Idaho PCM Signatre
DEL 00 (2i)
L, ...; ;?.£r i /l S/tPL r,r ,Oat. ~nD 7-ý"'l)j'
Date
DD ~7/ql¡p(
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-08-18
IDAHO POWER COMPANY
ATTACHMENT NO.8
Reduced Charge Option for
Underground Electrical Service
Revised June 2008
*
An IDACOR l' Company
Program Explanation
The Reduced Charge Option is available for new
1-0 underground electrical services and allows
the customer to install the conduit for the service
cable. When the installation is complete,
inspected, and all requirements have been met,
Idaho Power wil then install the cable and meter
at a reduced charge.
Be sure to connect to the proper equipment.
Refer to the Definitions section or contact Idaho
Power for clarification.
Call Dig-Line for locations
at least 2 business days before digging.
Dial~811
Know what's below.
Call before you dig.Nationwide
Conformance
Each installation is subject to review and
inspection at any time by Idaho Power for
conformance to these specifications.
If a non-conformance is discovered such as the
conduit length, route, depth, etc., or if you are not
ready when the installation crew arrives, the
cable WILL NOT BE INSTALLED and you wil be
charged $50.00 for each return trip. After the
non-compliance is corrected, contact Idaho
Power to reschedule the installation.
Contact Idaho Power if:
. This is your first time using this program.
. Your service exceeds any of the design
limits.
. A conduit stub cannot be found.
. You require service from a pole.
Reduced Charge Option, DFE 071
Revised June 2008
Design Limitations
200 Amp. For self-contained meter bases up
through 200 amps that meet the following
limitations, you do not need to contact Idaho
Power until you are ready for your service to be
installed.
. Use 2" gray, UL listed, Schedule 40 PVC
Use 2" conduit, bends, and fittings unless
Idaho Power specifically tells you to use 3".
. 125' maximum service length
This is the horizonta distance measured
along the service route between Idaho
Power's equipment and the meter.
. Up to 135° of conduit bends.
Don't include the bends at the meter or
Idaho Power's equipment in the 135° limit.
400 Amp. For larger self-contained meter
bases up through 400 amps, you must contact
Idaho Power for approval in advance to ensure
a proper design.
. 3" conduit
All services to meter bases larger than 200
amps require 3" conduit, bends, and fittings.
Additional Requirements
Conduit bends. Only
use gray colored
manufactured bends with
a radius of at least 24".
Do not form your own
bends!
+" :724" Ra;,,, /:
Trench and Backfll.
Backfill Material
No rocs larger than 2"
No trsh or rubbish
Conduit
Attachment NO.8 Page 1 of 5
Case No. IPC-E-08-18
Idaho Power Company
Page 1 of 5
Reduced Charge Option Revised June 2008
WARNING!
Non-conformances may have to be
corrected at the builder's expense.
Important Information
DON'T heat the conduit in any way to shape it
or to form bends.
DON'T leave open trenches. Any open trench
must be adequately barricaded or protected to
ensure public safety as required by local,
state, or federal rules and regulations. Keep
open trenches to a minimum.
DON'T change conduit sizes in the run.
DO compact the trench particularly near the
meter where settling could pull the conduit
down and damage the meter base. Although
compacting the trench is the builder's
responsibilty, the homeowner is responsible
for any future settling.
DO make square conduit cuts. Remove burrs
from the inside and outside edges.
DO glue conduit joints. All joints must be
completely seated and permanently glued
with PVC cement.
DO keep dirt and debris out of the conduit.
DO keep proper trench separations. Keep a
12" horizontal and vertical clearance between
the electrical conduit and all other utilities
and any structures.
DO keep proper meter separations.
The electric and
gas meters must
be separated as
shown.
M¡r;"',C.(.'ofCc'l'tp~",-¡
Ownership and Maintenance
Idaho Power assumes ownership of the builder-
installed conduit when the electrical service
cable is installed. However, the builder is
responsible for the condition of the conduit and
trench until the ownership of the home is
transferred to the first buyer.
After the cable has been installed, Idaho Power
wil own and maintain:
. All conduit and fittings installed below the
finished grade.
. The entire length of electric cable and the
connections at Idaho Power's equipment.
. The meter.
NOTE. Idao Power wil connect the cable
to the meter base but the homeowner wil
own and maintain the connections.
After the cable has been installed, the builder
or homeowner wil own and maintain:
. All conduit and fittings installed above the
finished grade.
. The trench and any landscaping.
. The meter base and its connections to the
electric cable.
. All wiring and electrical connections on the
customer's side of the meter.
Meter Base Guidelines
Refer to the Meter Base Identifcation
Guidelines located on www.idahopower.com.
Meter Base Requirements
The meter base must accept 3" conduit if 3"
conduit is used for the service.
The meter base and conduit must be on the
outside of an outside structure wall and remain
accessible to Idaho Power.
Exceptions must be approved in advance!
Attachment NO.8
Case No. I PC-E-08-18 Page 2 of 5
Idaho Power Company
Page 2 of 5
Reduced Charge Option Revised June 2008
Locate the meter on the side of the house toward
the front.
. Don't place the meter behind a fence.
. Don't put the meter at the back of the house.
Don't put the meter here
NOTE. Placing the meter in
front of the fence wil keep the
meter reader out of the back yard.
The center ofthe meter must be 5'-6" (+/- 6")
above the finished grade.
Meters installed on a pedestal require a minimum
height of 3'-0".
WARNING!
Any conduit above
ground must meet
applicable electrical
code requirements,r Slip Coupling
Support
Bracket5'-6"
(+/- 6")
Keep this
conduit straight
30" min
7
Suggestion. Block out a
section of the footing for
an easier installation.
.4n nt.~~ i' Cc.nrq,1
OK NOT PERMITTED
Keep the riserstright Don't form the PVC
conduit with heat or
add ext bends
Transformers
Most transformers have 2" or 3" conduit stubs
as shown below. Expose the end of the stub and
connect your new conduit. If the stub marker
cannot be found, contact your Idaho Power
representative.
Don't dig under the transformer!
Street-cr
Idaho Power's
Conduit Stub
Transformer
Street
Conduit
Stub
Marker
c:
Idaho Power's Builder's
Conduit Stub Conduit
Attachment NO.8
Case No. I PC-E-08-18 Page 3 of 5
Idaho Power Company
Page 3 of 5
Reduced Charge Option Revised June 2008
Handholes
Most handholes do not have conduit stubs.
. Plumb the conduit into the nearest comer of
the handhole using a 45° or 90° bend with the
end 2" above the handhole floor.
. Plug or cap the open end of the conduit to
keep out dirt and debris.
If there is a conduit stub, expose the end and
connect your conduit to it.
Street--
Street-- Handhole
Builder's
Conduit
Street-- Handhole
Builder's
Conduit
WARNING!
Call Dig-Line for locations
at least 2 business days before digging.~ Dial
~ 811Know what's below.
Call before you dig.Nationwide
!V f;l~(;a ~ (.C~"lXW.v
Contact Idaho Power
if your service involves a pole.
Special Requirements for Poles
You must meet with an Idaho Power
representative prior to digging the trench to
determine:
1. If the pole is adequate for your service.
2. Which side of the pole you must route the
conduit toward.
Trench all the way to the base of the pole.
If the pole becomes unstable, contact Idaho
Power immediately! When backfilling the
trench, leave 6' to 8' open adjacent to the pole.
Any open trench must be adequately baricaded
or protected for public safety.
After Idaho Power connects the pole riser and
conduit, it is the builder's responsibilty to
backfll and compact any remaining trench.
Call Idaho Power to detennine which
side of pole to route the conduit toward
11\~;! . . i 1/¡ ¡ i \ i T/~\!ìi 30"min 1//1 ¡ ! i 36" max / .
/Ì (¡\ 1- 18" -- I .'11de'. :'"';/1/%/7////'1,-.......\.)
Leave 6' to 8'
of Open Trench -i
Barricade as Needed I
Seal the End
of the Conduit
Attachment NO.8
Case No. I PC-E-08-18 Page 4 of 5
Idaho Power Company
Page 4 of 5
Reduced Charge Option Revised June 2008
Important Idaho Cost Information
The cost information below has been extracted from the "Rule H Line Installation Tarffs". You may view
the tariffs on http://idahopower.com/aboutus/regulatoryinfo/tariffPdf.asp?id=32&.pdf . Copies are available
by contacting Idaho Power or the respective Public Utilties Commission.
Underground Services (400 amp max.)
The non-refundable charge for a new Schedule 1
or Schedule 7, underground l-Ø service consists
of a Base Charge plus a Distace Charge. These
costs do not apply to services with meter bases
larger than 400 amps.
Base Charge
From underground .....................................$40.00
From overhead (2" pole riser) ........... ....... $395.00
From overhead (3" pole riser) .................. $520.00
Distance Charge
With 1/0 service cable ............................... $2.15/ft
With 4/0 service cable. ............. ....... ....... ... $3.60/f
With 350 service cable................. .... ..... .... $4.65/f
NOTE. Use the following Distance Charges if Idaho
Power provides the trench and conduit:
Distance Charge (IPCo trench & conduit)
With 1/0 cable ...........................................$6.90/ft
With 4/0 cable ...........................................$7.50/ft
With 350 cable...................................... .... $9.60/ft
There may also be additional charges for unusual
trenching conditions.
Temporary Services
The non-refundable charge for installing a l-Ø
temporary service is:
From underground ................................. $140.00
The customer-provided meter pole must be
securely set within 2' of the hand hole or
padmounted transformer.
From overhead ....................................... $120.00
The customer-provided meter pole must be
securely set in a location that wil allow the
temporary service conductor to be attached to
the permanent meter location by merely
relocating it. A maximum of 100' of #2 Tx
conductor is allowed.
TEMPORARY SERVICE NOTES.
. Electrical facilties provided by the customer
must be properly grounded, electrically and
structurally safe, provide adequate clearances,
and ready for connection.
. The customer must obtain all permits required
by the applicable state, county, or municipal
governments before callng Idaho Power and
provide copies or verifcation, as required.
. The site must be inspected, if required.
. All conditions must be met before the service wil
be connected. (If any condition is not met, the
service wil not be connected and the customer
wil be biled $35.00 per trip each time Idaho
Power dispatches personnel to connect it.)
NOTE. These costs are subject to change.
Call Idaho Power for curent pricing.
Contact Idaho Power for Oregon Cost Information
M!:;A(;';W:' Ct'l":'f.-mv
Attachment NO.8
Case No. IPC-E-08-18 Page50f5
Idaho Power Company
Page 5 of 5