HomeMy WebLinkAbout20160412_4944.pdfDECISION MEMORANDUM TO;COMMISSIONER KJELLANDER COMMISSIONER RAPER COMMISSIONER ANDERSON COMMISSION SECRETARY LEGAL WORKING FILE FROM:CURTIS THADEN DATE:April 6,2016 RE:IDAHO POWER COMPANY TARIFF ADVICE NO.16-01 REVISIONS TO THE GENERAL RULES AND REGULATIONS INDEX, SCHEDULE INDEX,AND CANCELLATION OF SHEET NO.23-Il On March 22,2016,Idaho Power submitted Tariff Advice 16-01 to revise Idaho Power’s Electric General Rules and Regulations Index,Schedule Index,and cancelling Sheet No.23-Il.Over time,changes have been made to the titles and page numbers of tariff schedules and rules.Because of the changes,the indexes for the tariff need to be updated.In addition,Schedule 23 was updated when Advice No.15-16 was filed.The page numbers changed when wording was moved,resulting in Sheet No.23-Il being eliminated.In addition to the housekeeping changes,3 new schedules are added to the index: Schedule 73 —Cogeneration and Small Power Production Schedule —Idaho Schedule 82—Flex Peak Program Schedule 87—intermittent Generation Integration Charges Idaho Power requests that the proposed revisions become effective April 22,2016. STAFF RECOMMENDATION Staff reviewed the revisions to the General Rules and Regulations index.Schedule Index,and Schedule 23.Based on its review,Staff recommends approval of Idaho Power’s proposed changes to its tariff. DECISION MEMORANDUM 1 APRIL 6,2016 COMMISSION DECISION Does the Commission wish to approve the changes set forth in this Tariff Advice with an effective date of April 22,2016? Curtis Thaden Udmemos/Idaho Power TaritTAdvice 16-01 dec memo DECISION MEMORANDUM 2 APRIL 6,2016 I Idaho Power Company SeeendThird Revised Sheet No.H Cancels l.P.U.C.No.29.Tariff No.101 gcetSecond Revised Sheet No.H GENERAL RULES AND REGULATIONS INDEX SHEET RULE TITLE NUMBER Title Page Index Page H --iii Rule A Introduction A-i Rule B Definitions B-i —B-2 Rule C Service and Limitations C-i —C-2 Rule D Metering D-i —D-3 Rule 2 Master Metering Standards E-1 --E-2 Rule F Service Establishment and Discontinuance F-i Rule G Billings G-i --G-2 Rule H New Service Attachments and Distribution Line Installations or Alterations H-I --H46i4 Rule I Budget Pay Plans I-i --1-2 Rule J Continuity,Curtailment and Interruption of Electric Service J-i Rule K Customer’s Load and Operations K-i --K-2 Rule L Deposits L-1 --L-2 Rule M Facilities Charge Service M-1 --M-3 IDAHO Issued by IDAHO POWER COMPANY Issued —per Order No.32l26March 22,201 6Grcgor W.SaidTimothy 2.Tatum,Vice President,Regulatory Affair Effective —Januecy-1,-2G42ApriI 22,2016 1221 West Idaho Street,Boise,ID Advice No.16-01 Idaho Power Company ThirdFourth Revised Sheet No.iB Cancels I I.P.U.C.No.29,Tariff No.101 SeeendThird Revised Sheet No.Hi SCHEDULE INDEX SHEET SCHEDULE TITLE NUMBER 1 Residential Service Standard Plan 1-1 —1-2 3 Master-Metered Mobile Home Park Residential Service 3-1 —3-2 4 Residential Service Energy Watch Pilot Plan (Optional)(Suspended)4-1 —4-3 5 Residential Service Time-of-Day Pilot Plan (Optional)5-1 —5-3 7 Small General Service 7-1 —7-2 9 Large General Service 9-1 —9-4 15 Dusk to Dawn Customer Lighting 15-1 —15-2 19 Large Power Service 19-1 —1 9Z 23 Irrigation Peak Rewards Program (Optional)23-1 —234j 24 Agricultural irrigation Service 24-1 —24-6I40Non-mMetered General Service 40-1 —40-2 41 Street Lighting Service 41-1 —41-8 42 Traffic Control Signal Lighting Service 42-1 45 Standby Service 45-1 —45-5 46 Alternate Distribution Service 46-1 —46-4 54 Fixed Cast Adjustment 54-1 —54-2 55 Power Cost Adjustment 55-1 —5523 60 Solar Photovaltaic Service Pilot Program 60-1 —60-6 61 Payment for Home Wiring Audit 61-1 62 Green Energy Purchase Program Rider (Optional)62-1 66 Miscellaneous Charges 66-1 —66-4 72 Interconnections to Non-Utility Generation 72-1 —7229 73 Cogeneration and Small Power Production Schedule —Idaho 73-1 —73-10 79 Weatherization Assistance for Qualified Customers 79-1 81 Residential Air Conditioner Cycling Program (Optional)81-1 —81-3 82 Flex Peak Program (Optional)82-1 —82-5 84 Customer Energy Production Net Metering Service 84-1 —84-5 85 Cogeneration and Small Power Production Non-Firm Energy 86-1 —85-7 87 Intermittent Generation Integration Charges 87-1 —87-15 89 Unit Avoided Energy Cost for Cogeneration and Small Power Production 89-1 91 Energy Efficiency Rider 91-1 95 Adjustment for Municipal Franchise Fees 95-1 —95-2I98ResidentialandSmallFarmEnergyCredit98-1 —98-2 IDAHO Issued by IDAHO POWER COMPANY Issued —January 19,2Ol2March 22,2ol6Crogory W.SaidTimothy E.Tatum,Vice President,Regulatory Affair Effective —March 1,2Ol2April 22,2016 1221 West Idaho Street,Boise,ID Advice No.12 0216-01