BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER
COMPANY'S PETITION TO MODIFY THE
METHODOLOGY FOR DETERMINING
FUEL COSTS USED TO ESTABLISH
PUBLISHED RATES FOR PURP A
QUALIFYING FACILITIES
CASE NO. IPC-O7-
NOTICE OF PETITION
NOTICE OF
MODIFIED PROCEDURE
NOTICE OF
COMMENT /PROTEST DEADLINE
Pursuant to the Public Utility Regulatory Policies Act of 1978 (PURPA) and the
implementing regulations of the Federal Energy Regulatory Commission (FERC), the Idaho
Public Utilities Commission (Commission) has approved a methodology for calculation of the
avoided cost rates paid to PURP A qualifying cogeneration and small power production facilities
(QFs) by Idaho Power Company, Avista Corporation and PacifiCorp. Avoided cost rates are the
purchase price paid to QFs for purchases of QF capacity and energy.
YOU ARE HEREBY NOTIFIED that on September 10, 2007 , Idaho Power
Company (Idaho Power; Company) filed a Petition with the Idaho Public Utilities Commission
(Commission) to modify the methodology for determining fuel costs used to establish published
rates for PURP A QFs. Idaho Power contends that use of the current method to set the fuel cost
component in the surrogate avoided resource (SAR) methodology will result in published
avoided cost rates that are not representative of the costs Idaho Power is likely to avoid by
purchasing energy from QFs.
BACKGROUND
In Order No. 29124 issued September 26, 2002 in Case No. GNR-02-, the
Commission established the methodology currently used to compute the fuel cost component of
the surrogate avoided resource (SAR) methodology. For QF projects generating less than 10
aMW, the avoided cost rates determined by the SAR methodology are commonly referred to as
the published rates. The current SAR is a natural gas-fired combined cycle combustion turbine.
The method the Commission adopted in Order No. 29124 to calculate the fuel cost
component starts with an arithmetic average of the nominal prices for natural gas for the first 3
NOTICE OF PETITION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
years of the Northwest Power Planning and Conservation Council's (NWPCC) median 20-year
forecast of natural gas prices. In Order No. 29124, the first 3 years of the 20-year forecast were
2000-2002. These three years consist of the current year s forecasted price, plus the previous
two years' forecasted prices. The average three-year price set in 2002 was $3.75. The SAR
methodology then escalates that 3-year average natural gas price at a uniform percent per year
over 20 years. The escalation rate is also calculated from the NWPCC 20-year natural gas
forecast. In 2002 the escalation rate was 2.6%.
In 2004, the NWPCC revised the 20-year natural gas price forecast. In Order No.
29646, the Commission revised the fuel cost component for the SAR methodology utilizing the
average of the NWPCC's natural gas price forecast for the 3-year period 2004 through 2006.
This change in the three-year average price revised the fuel cost component in the SAR
methodology to $5.10. The fuel escalation rate was changed to 2.3%. As a result of these two
changes, in 2004, the levelized published rate for a QF project estimated to come on-line in 2007
(20-year term) went from 53.67 millslkWh in 2002 to 62.40 millslkWh in 2004.
IDAHO POWER PROPOSAL
On July 31 , 2007, the NWPCC released a draft of its next forecast of natural gas
pnces. Petition, Attachment 1.1 Idaho Power contends that there exists an extreme divergence
between NWPCC's forecast of natural gas prices and the assumed cost of fuel for the SAR. The
principal reason for the divergence between the assumed cost of fuel for the SAR under the
current methodology and the NWPCC's 20-year forecast in natural gas prices is the use of the 3-
year average starting point and the linear escalation from that starting point. By starting the fuel
cost assumption at the highend of the range of prices shown in the NWPCC forecast and
escalating prices from that point in a linear profile, the current methodology fails to recognize the
expected downward trend in fuel prices apparent in NWPCC's 20-year forecast. Failing to
recognize the non-linear shape of the NWPCC's 2007 forecast, the Company contends, will
cause the published rates to be much higher than they otherwise would be.
Idaho Power proposes that the Commission utilize the average of all 20 years of the
NWPCC's final 2007 median 20-year natural price forecast as the fuel cost component in the
SAR methodology. Because Idaho Power proposes to use the 20-year average price, no
I The draft fuel price forecast was approved by the NWPCC on September II , 2007.
http://www.nwcouncil.org/library/2007/2007-14.htm.
See
NOTICE OF PETITION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
escalation forecast is needed. (Utilizing assumptions in the NWPCC 2007 draft forecast, the
calculated escalation rate is 1.10%.
Petition Attachment 4 depicts three sets of published avoided cost rates for Idaho
Power: (1) the current published avoided cost rates; (2) the published avoided cost rates that will
go into effect if the NWPCC accepts its 2007 draft natural gas price forecast as its final forecast
and the 3-year average natural gas price method remains unchanged; and (3) the Idaho Power
proposal - the fuel cost component is computed using the average of the 20 years of natural gas
prices from the NWPCC' s draft 2007 median gas price forecast:
Using NWPCC Gas Forecast
Update Fuel Only Update Fuel Only
Published Rate Calculation Model Current Pricing Using Established Using a 20 yr Avg
Method
NWPCC 2004 Fuel NWPCC 2007 Fuel NWPCC 2007 Fuel
3 yr avg 3 yr avg 20 yr avg
2002-2004 2005-2007 2008-20027
20-yr levelized rate, on-line date:
2007 62.40 72.67.
2008 63.73.68.
2009 65.31 74.68.
Idaho Power believes that its Petition presents a limited policy question to the
Commission. The Company does not believe that its proposal presents a factual dispute
requiring a technical proceeding to effectuate a resolution. The Company proposes to retain the
fundamental SAR methodology. The assumptions for all components of the SAR methodology
remain the same except for the fuel cost assumption. All of the data required to analyze Idaho
Power s proposal to change the fuel cost assumption are contained in the NWPCC's 2007 natural
gas price forecast in the current SAR methodology model. The Company is not requesting a stay
of the implementation of the new published rates while this case is pending.
Idaho Power requests that the Commission issue an Order changing the method for
determining the fuel cost component of the SAR methodology to utilize the average of all 20
years set out in the NWPCC's 2007 final median forecast of natural gas prices rather than the
escalated average of the first 3 years of the same forecast.
YOU ARE FURTHER NOTIFIED that the Commission has reviewed the filings of
record in Case No. IPC-07-15. The Commission has preliminarily found that the public
NOTICE OF PETITION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
interest in this matter may not require a hearing to consider the issues presented and that issues
raised by the Company s filing may be processed under Modified Procedure, i., by written
submission rather than by hearing. Reference Commission Rules of Procedure IDAP A
31.01.01.201-204.
YOU ARE FURTHER NOTIFIED that the deadline for filing written comments or
protests with respect to Idaho Power s Petition and the use of Modified Procedure in Case No.
IPC-07-15 is Tuesday, October 23, 2007. Persons desiring a hearing must specifically
request a hearing in their written protest or comments.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are
received within the deadline, the Commission may consider the matter on its merits and may
enter its Order without a formal hearing. If comments or protests are filed within the deadline
the Commission will consider them and in its discretion may set the matter for hearing or may
decide the matter and issue its Order based on the written positions before it. Reference IDAP
31.01.01.204.
YOU ARE FURTHER NOTIFIED that written comments concerning Case No. IPC-
07-15 should be mailed to the Commission and the Company at the addresses reflected below.
Commission Secretary
Idaho Public Utilities Commission
PO Box 83720
Boise, ID 83720-0074
Street Address for Express Mail:
Barton L. Kline, Senior Attorney
Lisa D. Nordstrom, Attorney II
Idaho Power Company
1221 W. Idaho Street (83702)
PO Box 70
Boise, ID 83707-0070
E-mail: bkline~idahopower.com
lnordstrom~idahopower .com472 W. Washington Street
Boise, ID 83702-5983
All comments should contain the case caption and case number shown on the first page of this
document.Persons desiring to submit comments via e-mail may do so by accessing the
Commission s home page located at www.puc.idaho.gov. Click the "Comments and Questions
icon, and complete the comment form, using the case number as it appears on the front of this
document. These comments must also be sent to Idaho Power at the e-mail addresses listed
above.
NOTICE OF PETITION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
YOU ARE FURTHER NOTIFIED that the Petition in Case No. IPC-07-15 may be
viewed at www.puc.idaho.gov by clicking on "File Room" and "Electric Cases " or can be
viewed during regular business hours at the Idaho Public Utilities Commission, 472 W.
Washington Street, Boise, Idaho and at the general business office of the Idaho Power Company,
1221 West Idaho Street, Boise, Idaho.
DATED at Boise, Idaho this :27 ~day of September 2007.
Je D. Jewell
Commission Secretary
blslN:IPC-07-15 sw
NOTICE OF PETITION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE