HomeMy WebLinkAbout20080104notice_of_oral_argument.pdfOffice of the Secretary
Service Date
January 4, 2008
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
EXERGY DEVELOPMENT GROUP OF
IDAHO LLC,CASE NO. IPC-O7-
PETITIONER,
NOTICE OF COMPLAINT
vs.AND MOTION TO COMPEL
IDAHO POWER COMPANY,NOTICE OF
ORAL ARGUMENT
RESPONDENT.
YOU ARE HEREBY NOTIFIED that on July 22 2007, Exergy Development Group
of Idaho LLC (Exergy) filed a "formal complaint" against Idaho Power Company (Idaho Power;
Company). Exergy owns and brings its complaint on behalf of five wind power generating
projects located within Idaho, each possessing an approved Firm Energy Sales Agreement with
Idaho Power. The subject matter of the complaint is Idaho Power s requirements for generation
interconnection for qualifying facilities (QFs) under the Public Utility Regulatory Policies Act of
1978 (PURPA). The five Exergy QF projects are part of the Twin Falls 138 kV interconnection
queue. The Company has determined that capacity and operational constraints on the
Company s transmission system in the Twin Falls area require upgrade to accept all the
generation being offered. All totaled, nearly 200 MW of new generation is being offered. The
sharing of transmission upgrade costs was addressed by the Commission in Idaho Power/Cassia
Case No. IPC-06-, Order No. 30414.
In multiple counts, Exergy contends that Idaho Power is failing to provide cost
estimates for interconnection pursuant to Schedule 72 (Interconnections to Non-utility
Generation), is charging unauthorized deposits as a precondition of providing cost estimates, is
threatening to remove Exergy s projects from the Company s transmission queue for failure to
pay the deposits, is failing to treat all interconnection customers in the same manner and is
operating under interconnection practices and policies that have not been approved by the
Commission.
NOTICE OF COMPLAINT
AND MOTION TO COMPEL
NOTICE OF ORAL ARGUMENT
Pursuant to Commission issued Summons, Idaho Power on August 21 , 2007, filed its
answer to Exergy s complaint recommending that the relief requested by Exergy be denied and
that the complaint be- dismissed with prejudice. On September 12, 2007, Exergy filed a Motion
(and Brief) to Compel Retention in Idaho Power s Interconnection Queue and to Prohibit Idaho
Power from Assessing Illegal Interconnection Study Deposits. By way of explicit clarification
Exergy states that it accepts full responsibility for paying Idaho Power all prudently incurred
interconnection costs. This case is not about cost responsibility, it contends, but rather it is about
the timing of those costs. Exergy maintains that Idaho Power s Schedule 72 governs the process
for interconnecting non-utility generators to the Company s system.
Schedule 72 provides in part
Unless specifically agreed otherwise in a written agreement between the
Seller and the Company, an initial cost estimate of Company-owned
interconnection Facilities will be provided to the seller. Payment of the
estimated cost will be required prior to the Company s ordering, installing,
modifying, upgrading, or performing in any other way work associated with
the Interconnection Facilities.
...
Exergy contends that Idaho Power puts the cart before the horse. The phrase "payment of the
estimated cost " Exergy states, necessarily assumes that there is an estimate of the costs. Exergy
contends "there is no provision in Schedule 72 for the pre-payment of interconnection costs, nor
is there any reference in Schedule 72 to the imposition of deposits in advance of the provision of
the 'actual cost estimate If the Commission had contemplated use of deposits, Exergy
contends it would surely have provided for a mechanism for collecting, refunding, and
accounting for such deposits. No utility, Exergy contends, may charge anything other than what
it is permitted to charge in its tariffs. Citing Idaho Code 9 61-313. Citing QF Power Purchase
Agreements, Appendix B Paragraph B-1 0, Exergy contends that the agreements approved by the
Commission contemplate reimbursement of Idaho Power costs, not pre-payment.
Without first implementing a ratemaking procedure or opening a docket to amend
Schedule 72, Exergy contends that Idaho Power and its QF customers are limited to the four
comers of Schedule 72 and nothing more.
On September 26, 2007, Idaho Power filed an answer to Exergy s Motion. Idaho
Power in its Answer describes FERC'four-step interconnection application process
(Application, Feasibility Study, System Impact Study, Facility Study). The Company states that
NOTICE OF COMPLAINT
AND MOTION TO COMPEL
NOTICE OF ORAL ARGUMENT
it applies the Federal Energy Regulatory Commission (FERC) rules for managing priority in the
interconnection queue and processing all interconnection requests to assure compliance with
FERC's regulations, and to ensure comparable treatment between QF and non-QF generation
developers. I Idaho Power contends that Exergy was in fact provided initial cost estimates for its
projects as part of project specific Generator Interconnection Feasibility Studies. Answer to
Motion, Exhibits 1-5. Having provided Exergy with an initial estimate of cost responsibility, the
Company contends it is authorized under Schedule 72 to request an additional deposit for further
interconnection studies. If Exergy wants to stay in the interconnection queue and continue with
the design and cost estimation process, it can pay the additional deposit. Idaho Power states that
the Company s request to Exergy is consistent with the process the Company follows for all
interconnection requests. Idaho Power notes that since year 2000 , the Company has received
more than 200 requests for interconnection. In each instance, the Company has requested and
received deposits to offset engineering and design expense and to ensure that customers have
some measure of protection if a developer decides to abandon its generation project in
midstream.
Exergy has already paid Idaho Power the following deposits. The additional
deposit requested is to proceed further in the interconnection study process.
QF Project Deposit Paid Additional Deposit Requested
Golden Valley $11 088 $35 000
Milner Dam $11 088 $100 000
Notch Butte $11 088 $100 000
Lava Beds $500 $10 000
Salmon Falls 324 $10 000
Idaho Power in its Answer to Motion states that the Company is not relying on
FERC's authority as justification for collecting deposits from Exergy. The Company states it
does not need to rely on FERC's authority. The plain language in Schedule 72, it states, provides
the Company with all the authority it needs to collect deposits to protect customers. The benefit
I In its Reply to Answer, Exergy contends that it is unreasonable to assume that FERC's interconnection rules are
appropriate for wholesale adoption in Idaho for QF interconnections. Many states, it argues, have adopted their own
comprehensive set of interconnection rules for QF interconnections that recognize the fact that most QFs
interconnect at distribution or subtransmission voltages.
NOTICE OF COMPLAINT
AND MOTION TO COMPEL
NOTICE OF ORAL ARGUMENT
of applying FERC's interconnection study process, the Company maintains, is the uniformity
and consistency that it provides. Using FERC's four-stage interconnection study process and the
FERC's rules for managing the QF interconnection queue , the Company contends, is completely
compatible and consistent with the terms of Schedule 72. Nothing in Schedule 72, Idaho Power
states, precludes the Company from taking payments for interconnection facilities in
installments. A pre-payment to be applied to a final bill, the Company contends, is a "deposit
regardless of what it is called.
Idaho Power recommends that Exergy s Motion be denied and that Exergy be
required to post the required deposits and that the Company be authorized to remove Exergy
projects from the interconnection queue for failure to do so. The costs of interconnection for all
participants in the Twin Falls queue, Idaho Power states, are dependent on whether or not other
projects ahead of them in the queue proceed for development. (Reference Idaho Power/Cassia
Case No. IPC-06-, Order No. 30414.) By remaining in the queue without providing
deposits in the same manner that other queue participants have provided them, the Company
contends that the Exergy projects have created uncertainty and have imposed a financial
disadvantage on other participants in the queue.
YOU ARE FURTHER NOTIFIED that pursuant to agreement of the parties and the
Commission Oral Argument of the parties on the issues raised in the filings in Case No. IPC-
07-13 is SCHEDULED TO COMMENCE AT 10:00 A.M. ON FRIDAY. JANUARY 18.
2008 AT THE COMMISSION HEARING ROOM. 472 WEST WASHINGTON STREET.
BOISE. IDAHO
YOU ARE FURTHER NOTIFIED that the oral argument in this matter will be held
III facilities meeting the accessibility requirements of the Americans with Disabilities Act
(ADA). Persons needing the help of a sign language interpreter or other assistance in order to
participate in or to understand testimony and argument at a public hearing may ask the
Commission to provide a sign language interpreter or other assistance at the hearing. The
request for assistance must be received at least five (5) working days before the hearing by
contacting the Commission Secretary at:
NOTICE OF COMPLAINT
AND MOTION TO COMPEL
NOTICE OF ORAL ARGUMENT
IDAHO PUBLIC UTILITIES COMMISSION
PO BOX 83720
BOISE, IDAHO 83720-0074
(208) 334-0338 (Telephone)
(208) 334-3762 (FAX)
E- Mail: secretary~puc.idaho. gov
YOU ARE FURTHER NOTIFIED that the initial complaint and subsequent filings
in Case No. IPC-07-13 have been filed with the Commission and are available for public
inspection during regular business hours at the Commission offices. The complaint and
subsequent filings ~e also available on the Commission s Website at www.puc.idaho.gov under
File Room" and then "Electric Cases.
DA TED at Boise, Idaho this i.j' f-J-day of January 2008.
~t0
D. Jewel
Commission Secretary
blsfN:IPC-07-I3 sw
NOTICE OF COMPLAINT
AND MOTION TO COMPEL
NOTICE OF ORAL ARGUMENT