HomeMy WebLinkAbout20050808Petition for reconsideration.pdfWilliam J. Batt
John R. Hammond, Jr.
BATT & FISHER, LLP
U S Bank Plaza, 5th Floor
101 South Capitol Boulevard
O. Box 1308
Boise, Idaho 83701
(208) 331-1000
(208) 331-2400 facsimile
EC:EiVED
~. ; t~ E
t71L...J
"'"
-'-'I
Lw.,
.."
1UO5AUG - Pr" 4: 5 I
to JIO PUBLIC
Ii!I....., ..J U. I I
Attorneys for Windland Incorporated
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE PETITION OF
IDAHO POWER COMPANY FOR AN ORDER
TEMPORARILY SUSPENDING IDAHO
POWER'S PURP A OBLIGATION TO ENTER
INTO CONTRACTS TO PURCHASE ENERGY
GENERATED BY WIND- POWERED SMALL
POWER PRODUCTION FACILITIES
Case No. IPC-O5-
WIND LAND
INCORPORATED'S PETITION
FOR RECONSIDERATION OF
COMMISSION ORDER NO.
29839
Introduction
Windland Incorporated ("Windland") hereby requests, pursuant to Idaho Code ~ 61-626
and RP 331 , that the Commission reconsider Order No. 29839 (the "Suspension Order ) issued
in this case on August 4, 2005.
The Commission issued the Suspension Order yesterday, and Windland is still
considering the likely effects of the Order on future viability of wind energy in Idaho, including
the major project that Wind I and has bid into the Idaho Power Wind RFP. Nevertheless, given
the time-sensitivity of the issues in this case, and their importance to the direction of public
energy policy in Idaho, Windland has immediately filed this Petition for Reconsideration.
Windland intends to expeditiously file a brief in support of this Petition for
Reconsideration, together with a request for stay of the Suspension Order pending a decision on
Windland's Petition for Reconsideration, and entry or continued stay of the Suspension Order
WINDLAND INCORPORATED'S PETITION FOR RECONSIDERATION OF COMMISSION ORDER NO.
29839 OR' GIN A l
during the pendency of Windland's request for review of the Suspension Order by the Idaho
Supreme Court, should such a request be filed.
Windland requests that the Commission reconsider the Suspension Order on the
following grounds:
The Order requires Idaho Power to enter into contracts at rates exceeding avoided
cost, contrary to law.
The Order sets criteria for "grandfathering" certain proposed QF projects that do
not have established contractual rights to old, clearly outdated avoided cost rates
contrary to law.
1. The rate established in Order No. 29646 does not accurately reflect cost of
alternative energy
The evidence introduced in the record demonstrates that the current avoided cost rate is
too high, at least for wind powered QFs. Section 210 of the PURP A requires that the rates paid
to QFs should not "exceed the incremental cost to the electric utility of alternative electric
energy . 1 In its testimony and pleadings, Idaho Power asserted that the RFP produced an
average price of $55 per MWh. This and other testimony shows that the incremental cost of
wind-generated alternative electric energy in the Idaho Power service territory is well below the
avoided costs of nearly $61 per MWh established in Order No. 29646.2 Indeed, Idaho Power
witness, John R. Gale testified that the current avoided cost rate "deserves to be reexamined"
because the Company thought it "would acquire wind resources closer to $43.00" in its RFP.
Testimony of John R. Gale Tr. at p. 71 1. 25, p. 72, 11. 11-20. Additionally, the Company
1 Public Utilities Regulatory Policy Act of 1978 , 210(b)(2).
2 Indeed Windland's bid for selling the output of the Cotterrel wind farm is lower than both the avoided cost rate of
$61 per MWh for PURP A projects and the Idaho Power claimed $55 per MWh price, fact which further
demonstrates that using the current avoided cost rate for wind powered QFs is unjust and unreasonable. Heckler
Testimony.
WINDLAND INCORPORATED'S PETITION FOR RECONSIDERATION OF COMMISSION ORDER NO.
29839, P. 2
believed that "integration issues" made applying the current avoided cost rate to wind QFs
questionable. ld. Staff witness Rick Sterling agreed in his testimony that there were sufficient
reasons to question whether the current avoided cost rates as applied to wind QFs were to high.
See Testimony of Rick Sterling, Tr. at pp. 110, 111 & 117. Thus, the Commission correctly
found that avoided cost rates are set to high for wind QFs:
Based on the record established in this case the Commission finds reason to
believe that wind generation presents operational integration costs to a utility
different form other PURP A qualified resources. We find that the unique supply
characteristics of wind generation and the related integration costs provide a basis
for adiustment to the published avoided cost rates, a calculated figure that may be
different for each regulated utility.
Order No. 29839 at p. 8 (emphasis added). This being the case, the current avoided cost
rate is unjust and unreasonable as applied to the parties and matters before the
Commission in the instant case. The Commission correctly stated: "In moving forward
with this case we do so in recognition that no utility is required to pay more than its
avoided cost for QF purchases." Suspension Order, p. 9.
Nevertheless, the effect of the Suspension Order is to require Idaho Power to enter
into new contracts under PURP A at a rate that clearly exceeds the avoided cost rate for
QF purchases. In so doing, the Commission erred.
2. The Commission has ordered grandfathering of QFs contrary to law
In the Suspension Order the Commission stated:
(TJhis Commission finds it reasonable to establish the following criteria to
determine the eligibility of PURP A qualifying wind generating facilities for
contracts at the published avoided cost rates. For purposes of determining
eligibility we find it reasonable to use the date of the Commission s Notice in this
case, i., July 1 , 2005. For those QF projects in the negotiation queue on that
date, the criteria that we will look at to determine project eligibility are: (1)
submittal of a signed power purchase agreement to the utility, or (2) submittal to
the utility of a completed Application for Interconnection Study and payment of
fee. In addition to a finding of existence of one or both of the preceding threshold
WINDLAND INCORPORATED'S PETITION FOR RECONSIDERATION OF COMMISSION ORDER NO.
29839, P. 3
criteria, the QF must also be able to demonstrate other indicia of substantial
progress and project maturity, e., (l) a wind study demonstrating a viable site
for the project, (2) a signed contract for wind turbines, (3) arranged financing for
the project, and/or (4) related progress on the facility permitting and licensing
path.
Suspension Order, pp. 9-10.
In so doing, the Commission requires Idaho Power to enter into contracts with
which it has no legal obligation under contract law. Idaho law provides otherwise. Thus
the Supreme Court has stated:
In A.W. Brown Co., this Court ruled that IPUC has authority, under state and
federal law, to require that before a developer can lock in a certain rate, there
must be either a signed contract to sell at that rate or a meritorious complaint
alleging that the project is mature and that the developer has attempted and failed
to negotiate a contract with the utility; that is, there would be a contract but for the
conduct of the utility. 121 Idaho at 816 828 2d at 845
Rosebud Enterprises, Inc., v. Idaho Public Utilities Commission, and Idaho Power Company,
131 Idaho at , 951 2d 521 (1997) (emphasis added). Other than the wind QF projects
which the Commission has previously approved and the Arrow Rock project, Idaho Power
Company has not entered into any further contracts. As such, the "grandfathering" criteria that is
provided for in the Commission Suspension Order is in error.
Conclusion
For the foregoing reasons, Windland requests that the Commission reconsider its decision
regarding "grandfathering" in Order No. 29839. After such reconsideration, Windland
respectfully requests that the Commission amend Order No. 29839 to prohibit the
grandfathering" of any wind QF projects into the avoided cost rate established by Order No.
29646 because such rate is unjust and unreasonable.
WINDLAND INCORPORATED'S PETITION FOR RECONSIDERATION OF COMMISSION ORDER NO.
29839, P. 4
DATED this 5th day of August, 2005.
Respectfully Submitted
Jo R. ammond, Jr.
Wi ia J. Batt
BA T FISHER, LLP
101 South Capital Blvd., Suite 500
O. Box 1308
Boise, ID 83701
(208) 331-1000
WINDLAND INCORPORATED'S PETITION FOR RECONSIDERATION OF COMMISSION ORDER NO.
29839 , P. 5
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on this 5th day of August, 2005, I served the foregoing upon
all parties of record in this proceeding as indicated below.
Barton L. Kline
Monica B. Moen
IDAHO POWER COMPANY
O. Box 70
Boise, ID 83707-0070
bk 1 ine(~jdahopower. com
mmoen~idahopower. COIn
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
Peter J. Richardson
RICHARDSON & O'LEARY PLLC
515 N. 2ih Street
Boise, ID 83702
peter~ri chrdsonando eary. com
J Certified Mail
J First Class Mail
J Hand Delivery
J F acsimil e
( x J Electronic Mail
Richard L. Storro
Director, Power Supply
A VISTA CORPORATION
1411 E. Mission Ave
O. Box 3727, MSC- 7
Spokane, WA 99220-3727
di ck. storro~a vistacorp. com
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
R. Blair Strong
PAINE, HAMBLEN, COFFIN
BROOKE & MILLER LLP
717 West Sprague Avenue, Suite 1200
Spokane, W A 99201-3505
r. blair. strong~painehamb len. com
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
Scott Woodbury
Deputy Attorney General
IDAHO PUBLIC UTILITIES COMMISSION
424 W. Washington Street
O. Box 83720
Boise, ID 83720-0074
scott. woodbury~puc. idaho. gov
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
WINDLAND INCORPORATED'S PETITION FOR RECONSIDERATION OF COMMISSION ORDER NO.
29839, P. 6
Michael Heckler
Director of Marketing and Development
WIND LAND INCORPORATED
7669 West Riverside Drive, Suite 102
Boise, ID 83714
Telephone: (208) 377-7777
Facsimile: (208) 375-2894
mheckler~windland. com
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
Dean J. Miller
McDEVITT & MILLER LLP
420 W. Bannock
Boise, ID 83702
oe~mcdevitt -miller .com
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
Jared Grover
CASSIA WIND LLC
CASSIA GULCH WIND PARK LLC
3635 Kingswood Drive
Boise, ID 83701
J Certified Mail
( x J First Class Mail
J Hand Delivery
J Facsimile
J Electronic Mail
Armand Ecker
MAGIC WIND LLC
716- BEast 4900 North
Buhl, ID 83316
J Certified Mail
( x J First Class Mail
J Hand Delivery
J Facsimile
J Electronic Mail
Glenn Ikemoto
Principal
ENERGY VISION LLC
672 Blain Avenue
Piedmont, CA 94611
glenni~pacbell.net
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
Bob Lively
P ACIFICORP
One Utah Center, 23rd Floor
201 S. Main Street
Salt Lake City, UT 84140
bob .li vel y~pacifi corp. com
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
WIND LAND INCORPORATED'S PETITION FOR RECONSIDERATION OF COMMISSION ORDER NO.
29839, P. 7
Lisa Nordstrom
P ACIFICORP
825 NE Multnomah, Suite 1800
Portland, OR 97232
lisa. nordstrom~pacifi corp. com
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
David Hawk
Director, Energy Natural Resources
J .R. SIMPLOT COMPANY
999 Main Street
O. Box 27
Boise, ID 83707-0027
dhawk~simplot. com
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
R. Scott Pasley
Assistant General Counsel
J .R. SIMPLOT COMPANY
999 Main Street
O. Box 27
Boise, ID 83707-0027
spasley~simplot.com
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
William M. Eddie
ADVOCATES FOR THE WEST
1320 W. Franklin Street
O. Box 1612
Boise, ID 83701
billeddie~rmci.net
J Certified Mail
J First Class Mail
J Hand Delivery
J Facsimile
( x J Electronic Mail
Troy Gagliano
917 SW Oak Street, Suite 303
Portland, OR 97205
J Certified Mail
( x J First Class Mail
J Hand Delivery
J Facsimile
J Electronic Mail
WINDLAND INCORPORATED'S PETITION FOR RECO SIDERATION OF COMMISSION ORDER NO.
29839, P. 8