HomeMy WebLinkAbout20050907Answer to staff's reconsideration petition.pdf;:E'CEIVED
Dean J. Miller ISB #1968
McDEVITT & MILLER LLP
420 West Bannock Street
O. Box 2564-83701
Boise, ill 83702
Tel: 208.343.7500
Fax: 208.336.6912
ioe(8)mcdmtt - mi ller .com
fL. D L~l
ZO05 SEP - 7 PM 2: 36
i Ii ,; u P u fi L ; r;JTJL1TIES COi"ff1lSS10N
Attorneys for Magic Wind, LLC,
Cassia Wind Park LLC and
Cassia Wind LLC
OR\G\NAL
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE PETITION OF
IDAHO POWER COMPANY FOR AN
ORDER TEMPORARILY SUSPENDING
IDAHO POWER'S PURP A OBLIGATION TO
ENTER INTO CONTRACTS TO PURCHASE
ENERGY GENERATED BY WIND-
POWERED SMALL POWER PRODUCTION
FACILITIES.
Case No. IPC-O5-
ANSWER TO STAFF'S PETITION
FOR RECONSIDERATION
COME NOW Magic Wind LLC, Cassia Wind Park LLC, Cassia Wind LLC (collectively
Magic and Cassia ) and, pursuant to IPUCRP 331., Answer the Commission Staffs Petition
for Reconsideration dated August 31 , 2005 ("Staff Petition ) as follows, to wit:
Magic and Cassia concur, in part, in Staff s critique of the Windland Petition for
Reconsideration in so far as Windland contends current avoided costs are too high. Staff
correctly observes "that current rates are presumed just and reasonable, and remain the effective
avoided cost rates until determined otherwise by the Commission." (Staff Petition, pg. 3).
Windland's "self-serving belief' to the contrary does not make the current rates unreasonable.
(Staff Petition, pg. 2).
ANSWER TO STAFF'S PETITION FOR RECONSIDERATION -
Magic and Cassia disagree, however, with Staffs contention that the A. W Brown policy
regarding grandfathering should apply in this case. The policy adopted in A. W Brown and
similar cases having to do with changes to published PURP A rates was that there must either be
a signed contract or a meritorious complaint at the time of the proposed change in rates. See
A. W Brown v. Idaho Power 121 Idaho 812 828 P.2d 841 (1992).
In contrast, in the present case, the Commission adopted threshold criteria of either
submittal of a signed contract or submittal of an Application for Interconnection Study, coupled
with other evidence of project maturity. See Order No. 29839.
As discussed in Magic and Cassia s Answer to Windland's Petition for Reconsideration
the A. W Brown policy was a permissible, but not legally mandated policy for determining which
projects were entitled to older, higher PURP A rates and which projects would have to be content
with newer, lower rates. The Staff Petition correctly observes that the policy adopted in Order
No. 29839 is different from the A. W Brown standard, but the Staff Petition does not make a case
that the A. W Brown standard is legally required.
The present circumstance is different from the circumstance in A. W Brown and similar
cases, justifying a different exemption policy. In A. W Brown and similar cases the only matter
at issues was rates. Even if a project was only entitled to the newer lower rates, it was still
entitled to a contract and the other features of the PURP A regulatory structure remained in place.
Here, the circumstance is much different. By lowering the published rate eligibility cap to 100
kW from 10 mW the Commission has turned the regulatory structure on its head. Projects that
were currently in progress do not have a new, lower rate that they can accept if desired. Instead
they are not entitled to a published contract rate unless they reduce their size by 99% to qualify
ANSWER TO STAFF'S PETITION FOR RECONSIDERATION - 2
under the 100kW sized project. A different, broader, exemption policy is justified by this
different circumstance.
At the July 22, 2005 hearing in this matter, Staff itself recognized there were substantial
policy reasons favoring an exemption policy different from A. W Brown. Staff supported a policy
not identical to but similar that ultimately adopted by the Commission.
The following questions and answers of the Staff policy witness occurred:
First, Mr. Sterling, I take it that it's the Staffs view that starting in very
general terms that projects that have expended measurable or somewhat
considerable time, effort and money, in reliance on the Commission
current rules should be exempt from any suspension or modification of the
eligibility criterias; is that a generally true statement?
Yes, I generally would agree with that.
Have you had the opportunity to review the brief that was filed by Magic
and Cassia on July 15th
Yes, I have.
And in that brief, Magic and Cassia set forth a proposal to specifically
implement the general proposition we have just discussed, which is that
developers who have filed an interconnection application should be
exempt from any suspension or modification of the eligibility rules.
wanted to ask, what is Staff s reaction to that proposal?
I think it's a reasonable proposal. Staff made its proposal and Magic s is
also a reasonable proposal and Cassia.
ANSWER TO STAFF'S PETITION FOR RECONSIDERATION - 3
What would happen in your view if implementation of that proposal
somehow came into conflict with the Company s 200 megawatt RFP
desires?
Well, I think it's unfortunate that we have this conflict with the RFP;
however, I think we are where we are today and I think the fact that people
have relied on the existing rules and progressed with their contracts or
their interconnection applications, it may ultimately destroy Idaho Power
RFP and I think that's unfortunate, but I think that's where we are today. I
don t think that it would be fair to preserve Idaho Power s RFP at the
expense of people that have in good faith relied on the existing rules.
Having said that, though, I think that illustrates the very problem
that has caused this proceeding to happen in the first place and that is that
Idaho Power will be obligated or could be obligated, depending on how
the Commission decides this case, to purchase from PURP A projects at
prices that are considerably higher than they otherwise would purchase
comparable resources if they could proceed under an RFP, but again, I
don t think we can undo what's already happened.
(T. pgs. 135-136).
In its Order, the Commission correctly noted that several projects relied on the written
instructions of the IPCo Interconnection Application for pursuing a Purchase Power Agreement.
The Commission wisely chose to include submission of Interconnection Application and
1 As demonstrated in Magic and Cassia s Reply to Windland's Petition for Reconsideration a true comparison shows
that PURPA rates are not greatly, if at all, in excess of anticipated RFP prices. (See Magic and Cassia s Answer to
Petition for Reconsideration, August, 30 2005). Staffs concern on this point is not well founded. But, even if it
was, Staff s position at hearing was that fairness to those who relied on the Commission s policies outweighed
concerns about paying too much.
ANSWER TO STAFF'S PETITION FOR RECONSIDERATION - 4
payment of fees, as one of the two main criteria in determining which projects were sincerely
pursuing completion of the project. Projects that were willing to follow the directions of IPCo
and pay thousands of dollars for interconnection applications are just as sincere and committed
as those companies signing and submitting a Purchase Power Agreement.
Thus, the exemption policy established in Order No. 29839 strikes an appropriate balance
of competing interests in the circumstances of this case and should be retained.
CONCLUSION
Based on the reasons and authorities cited herein the Staff Petition should be denied.
DATED this day of September, 2005.
Respectfully submitted
CDEVITT & MILLER LLP
Dean J. Miller
McDevitt & Miller LLP
420 W. Bannock
Boise, ID 83702
Phone: (208) 343-7500Fax: (208) 336-6912
Counsel for Magic Wind LLC,
Cassia Wind Park LLC and
Cassia Wind LLC
ANSWER TO STAFF'S PETITION FOR RECONSIDERATION - 5
CERTIFICATE OF SERVICE
I hereby certify that on the 1J11-day of September, 2005, I caused to be served, via the
methodes) indicated below, true and correct copies of the foregoing document, upon:
Jean Jewell, Secretary
Idaho Public Utilities Commission
472 West Washington Street
O. Box 83720
Boise, ID 83720-0074
iiewell~puc.state.id. us
Hand Delivered
S. Mail I....A
Fax I....A
Fed. Express I....A
Email
Scott Woodbury
Idaho Public Utilities Commission
472 West Washington Street
O. Box 83720
Boise, ID 83720-0074
swoodbu(fYpuc. state. id
Hand Delivered
S. Mail
Fax
Fed. Express
Email
Barton L. Kline
Monica B. Moen
Idaho Power Company
1221 West Idaho Street
O. Box 70
Boise, ID 83707
BKline(fYidahopower .com
MMoen(fYidahopower. com
Hand Delivered
S. Mail
Fax
Fed. Express
Email
Linda Nordstrom
Pacifi Corp
825 NE Multnomah, Suite 1800
Portland, OR 97232
Fax: 503.813.7252
lisa.nordstrom~pacifi corp. com
Hand Delivered
S. Mail
Fax
Fed. Express
Email
Bob Lively
Pacificorp
One Utah Center, 23rd Floor
201 S. Main Street
Salt Lake City, UT 84140
Fax: 801.220.2798
bo b.Ii vel y~pacificorp. com
Hand Delivered
S. Mail
Fax
Fed. Express
Email
ANSWER TO STAFF'S PETITION FOR RECONSIDERATION - 6
I....A
I....A
I....A
I....A
I....A
I....A
I....A
William J. Batt
John R. Hammond, Jr.
Batt & Fisher, LLP
U S Bank Plaza, 5th Floor
101 South Capital Boulevard
O. Box 1308
Boise, ID 83701
Fax: 208.331.2400
i rh(fY battfisher. com
wi b(fYbattfi sher .com
Hand Delivered
S. Mail
Fax
Fed. Express
Email
Michael Heckler
Director of Marketing & Development
Windland Incorporated
7669 West Riverside Drive, Suite 102
Boise, ID 83714
Fax: 208.375.2894
mheckler(fYwindland. com
Hand Delivered
S. Mail
Fax
Fed. Express
Email
Peter J. Richardson
James T. Carkulis
Richardson & 0' Leary PLLC
99 East State Street
O. Box 1849
Eagle, ID 83616
Fax: 208.938.7904
peter(fYrichardsonandoleary.com
Hand Delivered
S. Mail
Fax
Fed. Express
Email
Glenn Ikemoto
Principal
Energy Vision, LLC
672 Blair Avenue
Piedmont, CA 94611
Fax: 510.217.2239
glenni~pacbell.net
Hand Delivered
S. Mail
Fax
Fed. Express
Email
ANSWER TO STAFF'S PETITION FOR RECONSIDERATION - 7
I....A
I....A
I....A
I....A
I....A
I....A
I....A
I....A
I....A
I....A
I....A
Richard L. Storro
Director, Power Supply
and David Meyer
1411 E. Mission Ave.
O. Box 3727, MSC- 7
Spokane, W A 99220-3727
Fax: 509.495.4272
dick. storro(fYavistacorp. com
davi d .meyer(fYavistacorp. com
Hand Delivered
S. Mail
Fax
Fed. Express
Email
R. Blair Strong
Paine, Hamblen, Coffin, Brooke &
Miller LLP
717 West Sprague Ave., Suite 1200
Spokane, WA 99201-3505
Fax: 509.838.0007
r. blair .strong(fYpainehamblen.com
Hand Delivered
S. Mail
Fax
Fed. Express
Email
J. R. Simp lot Company
Attn: David Hawk
Director, Energy Natural Resources
999 Main Street
P. O. Box 27
Boise, Idaho 83702
(208) 389-7306
Fax: (208) 389-7333
dhawk(fYsimplotcom
I....A
I....A
I....A
I...:A
I....A
I....A
Hand Delivered I....A
S. Mail I....A
Fax I....A
Fed. Express I....A
Email
R. Scott Pasley
Assistant General Counsel
J. R. Simp lot Company
999 Main Street
P. O. Box 27
Boise, Idaho 83702
(208) 389-7321
(208) 389-7464 telefax
~asley(fYsimplot.com
Hand Delivered I....A
S. Mail I....A
Fax I....A
Fed. Express I....A
Email
ANSWER TO STAFF'S PETITION FOR RECONSIDERATION - 8
William M. Eddie
Advocates for the West
O. Box 1612
Boise, ID 83701
billeddie(fYrmci.net
Hand Delivered
S. Mail
Fax
Fed. Express
Email
I....A
I....A
I....A
ANSWER TO STAFF'S PETITION FOR RECONSIDERATION - 9