BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR
APPROVAL OF A FIRM ENERGY SALES
AGREEMENT FOR THE SALE AND
PURCHASE OF ELECTRIC ENERGY
BETWEEN IDAHO POWER COMPANY
AND BENNETT CREEK WINDF ARM LLC
CASE NO. IPC-O6-
NOTICE OF APPLICATION
NOTICE OF
MODIFIED PROCEDURE
NOTICE OF
COMMENT/PROTEST DEADLINE
YOU ARE HEREBY NOTIFIED that on December 26, 2006, Idaho Power
Company (Idaho Power; Company) filed an Application with the Idaho Public Utilities
Commission (Commission) requesting approval of a 20-year Firm Energy Sales Agreement
between Idaho Power and Bennett Creek Windfarm LLC (Bennett Creek) dated December 20
2006 (Agreement).
Background
On August 4, 2005 , the Idaho Public Utilities Commission (Commission) in Case
No. IPC-05-, Order No. 29839, reduced the eligibility cap for avoided cost published rates
for non-firm wind projects from 10 aMW to 100 kW, required individual negotiation for larger
wind qualifying facilities (QFs), and established criteria for assessing QF contract entitlement.
Reference Public Utility Regulatory Policies Act of 1978 (PURP A). By Commission Order No.
29872 the date for grandfathering eligibility was changed from July 1 , 2004, the Notice of
Petition date, to August 4 2005 , the date oflnterlocutory Order No. 29839.
Agreement
The Bennett Creek facility will be located within Sections 22, 23, 26 (less southeast
quarter) and 27, Township 4 S , Range 8 E, Boise Meridian, Elmore County, Idaho. Bennett
Creek warrants the facility will be a qualified small power production facility (QF) under the
applicable provisions of the Public Utility Regulatory Policies Act of 1978 (PURPA). The
facility will consist of 12 Vestas wind turbines with individual nameplate ratings of 1.65 MW for
each unit, for a total facility nameplate generator rating of 19.8 MW. The Agreement contains
the non-Ievelized, published avoided cost rates set forth in Order No. 29391. Under normal
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
and/or average operating conditions, Bennett Creek will not generate more than 10 aMW on a
monthly basis. Energy delivered in excess of this monthly amount is Inadvertent Energy. Idaho
Power will accept Inadvertent Energy that does not exceed the Maximum Capacity Amount (20
MW) but will not purchase or pay for Inadvertent Energy. Agreement ~ 7.
Based on Idaho Power Company s review of the information provided by the
developer and in light of the procedure the Commission accepted in Cassia Wind Order No.
29954, Case No. IPC-05-, Idaho Power has determined that it would be reasonable to
grandfather the Bennett Creek facility based on satisfaction of the following criteria identified by
the Commission in Order No. 29839, Case No. IPC-05-
Primary criteria:
Prior to August 5, 2005 , the developer had tendered a signed Firm Energy
Sales Agreement to Idaho Power for the facility. This satisfies one of the two
primary criteria for grandfathering.
Secondary criteria:
As of August 5 , 2005, the facility did not have a signed contract for turbines.
Idaho Power has reviewed the information provided by the developer and
determined that this developer believed that obtaining financing was the
highest priority on the critical path to project development and directed its
resources to that goal rather than turbine acquisition. As a result, prior to
August 4, 2005, the developer had entered into binding commitments to
obtain financing. The Company has also confirmed that as of August 4
2005 , the facility had made substantial progress on the other secondary
criteria, except for acquisition of turbines. As in the case of Cassia Wind, the
developer has now obtained a firm commitment for turbines for the facility
and filed the necessary applications for interconnection to satisfy the second
primary criteria.
Idaho Power notes that there are three provisions the Commission should be aware of
in its consideration of the Agreement:
1. In the negotiations of this project, Idaho Power and Bennett Creek agreed
that an on-line date of December 2007 is crucial to demonstrate that the
project was a viable project in August of2005. This Agreement contains
delay damage provisions that require the project pay Idaho Power
damages if the project comes on-line after December 31 , 2007. The
delay damages will accrue for a period of up to 90 days.
2. The Agreement contains the methodology for computing shortfall energy
payments the Commission approved in the Firm Energy Sales Agreement
between Idaho Power and Fossil Gulch Wind Park, LLC (Case No. IPC-
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
04-, Order No. 29630) and recently approved for Magic Wind Park
in Order No. 30206 issued in Case No. IPC-06-26. Bennett Creek has
voluntarily selected the Fossil Gulch Method. Use of the Fossil Gulch
methodology is a negotiated term of the Agreement and is mutually
acceptable to Idaho Power and Bennett Creek.
3. The Agreement reflects the changes to Idaho Power s Schedule 72
(Uniform Interconnection Agreement) approved in Order No. 30179
issued on November 17, 2006 in Case No. IPC-06-18.
Bennett Creek has selected March 31 , 2007 as the Scheduled First Energy Date and
December 31 , 2007 as the Scheduled Operation Date
Section 24 of the Agreement provides that the Agreement will not become effective
until the Commission has approved all of the Agreement's terms and conditions and declared
that all payments Idaho Power makes to Bennett Creek for purchases of energy will be allowed
as prudently incurred expenses for ratemaking purposes.
YOU ARE FURTHER NOTIFIED that the Commission has reviewed the filings of
record in Case No. IPC-06-35. The Commission has preliminarily found that the public
interest in this matter may not require a hearing to consider the issues presented and that issues
raised by the Company s filing may be processed under Modified Procedure, i., by written
submission rather than by hearing. Reference Commission Rules of Procedure, IDAP A
31.01.01.201-204.
YOU ARE FURTHER NOTIFIED that the deadline for filing written comments or
protests with respect to Idaho Power s Application and the use of Modified Procedure in Case
No. IPC-06-35 is Friday, January 26, 2007.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are
received within the deadline, the Commission may consider the matter on its merits and may
enter its Order without a formal hearing. If comments or protests are filed within the deadline
the Commission will consider them and in its discretion may set the matter for hearing or may
decide the matter and issue its Order based on the written positions before it. Reference IDAP
31.01.01.204.
YOU ARE FURTHER NOTIFIED that written comments concerning Case No. IPC-
06-35 should be mailed to the Commission and the Company at the addresses reflected below.
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
Street Address for Express Mail:
Barton L. Kline, Senior Attorney
Monica B. Moen, Attorney II
Idaho Power Company
PO Box 70
Boise, ID 83707-0070
E-mail: bkline~idahopower.com
mmoen~idahopower.com
Commission Secretary
Idaho Public Utilities Commission
PO Box 83720
Boise, ID 83720-0074
472 W. Washington Street
Boise, ID 83702-5983 Ric Gale
Vice President Pricing and Regulatory
Idaho Power Company
PO Box 70
Boise, ID 83707-0070
E-mail: rgale~idahopower.com
Street Address for Express Mail:
1221 W. Idaho Street
Boise, ID 83702
All comments should contain the case caption and case number shown on the first page of this
document.Persons desiring to submit comments via e-mail may do so by accessing the
Commission s home page located at www.puc.idaho.gov. Click the "Comments and Questions
icon, and complete the comment form, using the case number as it appears on the front of this
document. These comments must also be sent to Idaho Power at the e-mail addresses listed
above.
YOU ARE FURTHER NOTIFIED that the Application in Case No. IPC-06-
may be viewed at www.puc.idaho.gov by clicking on "File Room" and "Electric Cases " or can
be viewed during regular business hours at the Idaho Public Utilities Commission, 472 W.
Washington Street, Boise, Idaho and at the general business office of Idaho Power Company,
1221 West Idaho Street, Boise, Idaho.
DATED at Boise, Idaho this '-/ fit.day of January 2007.
~j~r~Co mission Secretary