HomeMy WebLinkAbout20070808final_order_no_30398.pdfOffice of the Secretary
Service Date
August 8, 2007
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR
APPROVAL OF A FIRM ENERGY SALES
AGREEMENT FOR THE SALE AND
PURCHASE OF ELECTRIC ENERGY
BETWEEN IDAHO POWER COMPANY
AND HOT SPRINGS WINDFARM LLC
CASE NO. IPC-06-
ORDER NO. 30398
On July 11 , 2007, Idaho Power Company (Idaho Power; Company) submitted for
Commission approval an amendment (First Amendment) to the December 20, 2006, Firm
Energy Sales Agreement (Agreement) between Idaho Power and Hot Springs Windfarm LLC
(Hot Springs). The original Agreement was approved on February 20 2007, in Order No. 30246
(Order). Idaho Power and Hot Springs desire to amend the Agreement to (1) revise the wind
turbine manufacturer and specifications; (2) revise the scheduled operation date; and (3) provide
liquid security in the amount of estimated Delay Damages. The Commission in this Order
approves the First Amendment to the Idaho Power/Hot Springs Agreement.
BACKGROUND
In the original Agreement, Hot Springs selected December 31 , 2007 as the estimated
scheduled operation date for the Hot Springs Windfarm Project (Project). The Agreement
contains provisions that require the Project to pay Idaho Power liquidated damages if the Project
comes online after December 31 , 2007 (Delay Liquidated Damages). The Delay Liquidated
Damages will accrue for a period of up to ninety days. (Agreement Sections 5.3-6).
In the Order approving the original Agreement, the Commission noted that the Hot
Springs Windfarm Project had not signed an interconnection agreement at the time of the
Commission s approval of the Agreement. During the negotiation of the Agreement, Hot
Springs indicated to Idaho Power that it believed that the costs of interconnection would be
manageable and that the time required for interconnection studies would not adversely impact its
ability to meet the December 31 , 2007 scheduled operation date.
Hot Springs has now completed initial discussions with Idaho Power s delivery
business unit as required by the Agreement. As a result of those discussions, it has become
apparent that the Hot Springs Project will require network upgrades in order to accommodate the
Project's generation and that the time required for completion of necessary studies and the
ORDER NO. 30398
construction of necessary interconnection facilities and network upgrades will delay the Project'
online date beyond the December 31 , 2007 scheduled operation date. Such a delay will trigger
Delay Liquidated Damages.
Hot Springs is also now concerned about its ability to absorb all of the network
upgrade costs. Hot Springs has indicated that the type of settlement that is proposed in Case No.
IPC-06-21 (Cassia Case) will allow it to proceed with its Project. However, until Case No.
IPC-06-21 is resolved, Hot Springs is reluctant to proceed.
FIRST AMENDMENT
1. Wind Turbine Manufacturer and Specifications
The delay in interconnection of the Project has caused Hot Springs' investor and wind
turbine supplier to reallocate the project's turbines to another project. Hot Springs must now
wait for the next available turbines, which are due before the end of the year. One of the new
turbine options requires a modification of the type and size of wind turbines allowed under the
Agreement. The First Amendment reflects this change in turbine manufacturer and size. It also
recognizes that the turbine market is volatile and additional changes in turbine configuration may
be required in the future.
2. Scheduled Operation Date
In light of the foregoing, Hot Springs has requested that Idaho Power agree to amend
the Agreement to extend the scheduled operation date for a period of approximately one year.
Hot Springs believes this time is necessary to ensure that it will be able to meet the revised
scheduled operation date and give the Project the opportunity to avoid the payment of Delay
Liquidated Damages.
3. Liquid Security
Idaho Power states that it is willing to enter into the First Amendment for two
reasons. First, in exchange for this Amendment, Hot Springs is willing to provide Idaho Power
with liquid security in an amount sufficient to cover the Delay Liquidated Damages. This
provision is not currently included in this or other QF 1 contracts and Idaho Power believes that
the inclusion of this provision provides value for the Company and its customers. Second, Idaho
Power is aware of two other wind projects in the same area facing similar delays due to
unanticipated (by the developer) interconnection delays (Bennett Creek; Alkali Wind). If the
1 A qualifying small power production facility (QF) under ~ 292.203(a) of the Public Utility Regulatory Policies Act
of 1978 (PURPA), as amended.ORDER NO. 30398
Commission concurs, Idaho Power indicates that it will propose a similar resolution for those
projects.
The Hot Springs and the Bennett Creek contracts are the first with separate firm
energy sales agreements and interconnection agreements. When power sales agreements are
approved first, without signed transmission interconnection agreements, projects can be delayed
and necessitate later amendments to firm energy sales agreements.The Federal Energy
Regulatory Commission s (FERC' s) Standard of Conduct rules make it impossible , the Company
states, for Idaho Power s power supply business unit to independently confirm the
reasonableness of the QF developer s selection of a particular date for scheduled operation. To
address this problem in the future, Idaho Power states that it has implemented new contract
procedures. As a result, Idaho Power states that it will now be the policy of the power supply
business unit not to sign firm energy sales agreements until the QF project developer can
demonstrate that it has completed its interconnection application to the extent that the scheduled
operation date is unlikely to be modified due to delays in the interconnection study and
transmission construction process. This is the only way, Idaho Power states, that the Company
can be reasonably certain that the scheduled operation dates selected by the QF developer are
realistic.
Comments Of Idaho Winds LLC
Idaho Winds LLC is the developer of Alkali Wind Farm (IPC-06-36; Order No.
30253), a PURP A qualified facility with an Idaho Power power supply contract. The Alkali
project faces similar obstacles to meeting its online date due to unanticipated interconnection
delays. Idaho Winds is currently engaged in discussion with the Idaho Power delivery business
unit and, like Hot Springs and Bennett Creek, it has become apparent that Alkali will require
network upgrades in order to accommodate the project's generation and the time required for
completion of necessary studies and the construction of necessary interconnection facilities and
network upgrades will delay this project's online date beyond the December 31 , 2007 Scheduled
Operation Date, triggering Delay Liquidated Damages.
Idaho Winds believes that the Delay Liquidated Damages provIsIOn of Alkali
Project's contract is adequate to protect Idaho Power and its customers and objects to Idaho
Power s proposal to require Delay Security from Idaho Winds, or upon any other developer in a
similar situation.
ORDER NO. 30398
Analysis Of The Commission Staff
Staff apprises the Commission that it has no objection to amending the Idaho
Power/Hot Springs Agreement to revise the wind turbine manufacturer and specifications. The
particular turbine manufacturer and specifications are not critical, and do not change the energy
product Idaho Power will be purchasing under the Agreement.
As a condition of the one-year contract extension, the contract parties propose
extending the scheduled operating date by approximately one year. Because both Idaho Power
and Hot Springs are in agreement, Staff does not oppose the proposed changes. Unlike most of
~he other wind contracts wherein the projects have yet to come online, this Agreement contains
liquidated damages provisions in the event of delays in achieving the expected online date.
Staff believes strongly that approval of the First Amendment should not carry with it
either explicit or implicit approval of any terms of interconnection.The Interconnection
Agreement, which is yet to be signed, and the Firm Energy Sales Agreement, the Staff states, are
clearly two separate agreements. The Hot Springs project is not included in the "Twin Falls
cluster" and will not be included in a settlement stipulation in Cassia Case IPC-06-21;
therefore, whether any terms of the proposed settlement in the pending IPC-06-21 case relating
to QF interconnection can be applied to this Project is yet to be determined. Staff expects that a
separate interconnection agreement for this Project will be submitted for Commission approval at
a later date.
Hot Springs agrees to provide liquid security in the amount of estimated Delay
Liquidated Damages. Staff has no objection to this consensual change in security by the contract
parties. Idaho Power states that if the Commission concurs, Idaho Power would propose a
similar resolution for other wind projects in the same vicinity that are facing similar transmission
interconnection delays. Although Staff does not have any particular objections to proposals for
similar resolutions for other projects, Staff does not believe that Commission approval of the Hot
Springs First Amendment should be interpreted by the Company as blanket approval for any
other wind contracts.
Staff recommends that the Commission issue an Order: (1) approving the First
Amendment to the Firm Energy Sales Agreement (Attachment 1) without change or condition;
and (2) confirming that the costs associated with the Agreement as amended will be approved as
prudent expenditures for ratemaking purposes as originally provided in Order No. 30246. Staff
recommends that the Commission decline to comment on the Company s proposal to use the
ORDER NO. 30398
Liquid Security" amendment to the online delay damages provision agreed to by the contract
parties in this case as a template for other instances of QF failure to achieve scheduled operation
dates.
Commission Findings
The Commission has reviewed the filings of record in Case No. IPC-06-
including the underlying Agreement between Idaho Power and Hot Springs which we approved
on February 20 2007, in Order No. 30246 (Order). Idaho Power and Hot Springs desire in this
case to amend the Agreement to (1) revise the wind turbine manufacturer and specifications; (2)
revise the scheduled operation date; and (3) provide liquid security in the amount of estimated
Delay Damages. The Commission finds that the proposed amendment terms have been agreed to
by the parties and we find the proposed changes comprising the First Amendment to the Firm
Energy Sales Agreement between Idaho Power and Hot Springs Windfarm LLC to be
reasonable.
The Commission notes that Idaho Power proposes to use the "Liquid Security
amendment to the online Delay Liquidated Damages provision agreed to by the contract parties
in this case as a template for other instances of QF failure to achieve scheduled operation dates.
Idaho Winds LLC opposes the Company s template proposal. Staff contends that it is not
necessary for the Commission to address the Company s template proposal in this case docket
and advises the Commission that it has contacted both Idaho Power and Idaho Winds LLC with
its recommended treatment of the Company s template proposal. Neither party, it states, objects
to Staffs recommendation. The Commission finds that the First Amendment proposed in this
case can be approved without consideration of the Company s template proposal.
accordingly find it reasonable to not address the substance of the Company s template proposal
in this docket. We find that the respective positions of both Idaho Power and Idaho Winds LLC
regarding same can be raised later and are preserved and not waived.
CONCLUSIONS OF LAW
The Idaho Public Utilities Commission has jurisdiction over Idaho Power Company,
an electric utility, and the issues raised in Case No. IPC-06-34 pursuant to the authority and
power granted it under Title 61 of the Idaho Code and the Public Utility Regulatory Policies Act
of 1978 (PURPA).
The Commission has authority under PURP A and the implementing regulations of
the Federal E~ergy Regulatory Commission (FERC) to set avoided costs, to order electric
ORDER NO. 30398
utilities to enter into fixed term obligations for the purchase of energy from qualified facilities
(QFs) and to implement FERC rules.
ORDER
In consideration of the foregoing and as more particularly described above, IT IS
HEREBY ORDERED and the Commission does hereby approve the First Amendment to the
December 20, 2006 Firm Energy Sales Agreement between Idaho Power Company and Hot
Springs Windfarm LLc. Reference Order No. 30246.
THIS IS A FINAL ORDER. Any person interested in this Order may petition for
reconsideration within twenty-one (21) days of the service date of this Order. Within seven (7)
days after any person has petitioned for reconsideration, any other person may cross-petition for
reconsideration. See Idaho Code ~ 61-626.
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 'if--rL
day of August 2007.
Jk Jlh~L
MARSHA H. SMITH, COMMISSIONER
ATTEST:
~fJ
J e ~ D. Jewel I
fumission Secretary
bls/O:IPC-06-
ORDER NO. 30398