HomeMy WebLinkAbout20060831notice_of_application.pdfOffice of the Secretary
Service Date
August 31 2006
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR
REVISION OF SCHEDULE 84 - NET
METERING NOTICE OF APPLICATION
CASE NO. IPC-O6-
NOTICE OF
MODIFIED PROCEDURE
NOTICE OF
COMMENT/PROTEST DEADLINE
YOU ARE HEREBY NOTIFIED that on August 17, 2006, Idaho Power Company
(Idaho Power; Company) filed an Application with the Idaho Public Utilities Commission
(Commission) requesting authority to revise net metering requirements in the Company
Schedule 84 - Net Metering tariff.
Background
On February 13 , 2002, the . Commission issued Order No. 29851 (Case No. IPC-
01-39) authorizing the net metering option for customers taking service under the Company
Schedule 1 - Residential Service (Rl), and Schedule 7 - Small General Service (R7).
On August 21 2002, the Commission issued Order No. 29094 (Case No. IPC-02-
4) authorizing other retail customers not receiving service under Schedules 1 and 7 (non-Rl/R7)
the option to also participate in a net metering program.
The Company s current net metering program credits residential and small general
service customers at full retail rates for all kilowatt hours (kWh) generated. This pricing, the
Company contends, pays customers more than the actual value of the generation itself. Net
metering, the Company states, allows Idaho Power to avoid some generation costs and perhaps
some transmission costs, but few, if any, other costs. Therefore, Idaho Power contends that the
Company does not recover its full costs of providing service from net metering customers.
Idaho Power contends that there is a major difference between the energy provided to
customers by the Company and energy provided to the Company by net metering customers.
Energy offered to customers by Idaho Power is firm, meaning that it is available at all times
whenever customers desire to make use of it. Net generation, on the other hand, is provided by
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
customers to Idaho Power on a non-firm basis, or on an "if and when available" basis. The
difference between the value of firm vs. non-firm energy, the Company states, is not recognized
under the Company s current net metering tariffs for Schedule 1 and Schedule 7 customers. In
its initial program offering, the Company recognized that its net metering proposal would result
in some subsidy to those residential and small general service customers that chose to develop
net-metered generation projects. However, the Company reasoned that as long as the eligibility
for net metering was limited to small projects utilizing watt-hour meters and capped at a
reasonable level, the subsidy would be small and would be partially offset by savings resulting
from simplification of the net metering program.
Idaho Power has now had the opportunity to examine over the last four years how its
customers have actually utilized the net metering option. As a result, the Company is proposing
some modifications to its net metering program to provide what it contends is a more equitable
result for its customers.
Modifications to Reduce Cost-Shifting
By accepting a net metering tariff for Residential and Small General Service
customer generation is credited at full retail rates; uncollected costs are shifted to the respective
customer classes. When the generation merely offsets usage, the dollar impacts, the Company
contends, are relatively small. However, when generation exceeds usage, the resultant cost-
shifting may become much more material.
Citing an example, Idaho Power states that in 2005 , one residential customer
averaged excess generation of 12 076 kilowatt hours every month. A small general service
customer also averaged excess generation of 15 913 kilowatt hours each month. In both cases
there was never a month when either customer registered positive net energy usage. Under
current net metering provisions, these customers received full retail rates for their generation.
The retail rate, the Company notes, includes recognition of generation, transmission and
distribution costs. All costs outside of the value of the generation received from net metering
customers, the Company contends, are being shifted to customers within the residential and
small general service customer classes.
Idaho Power believes the primary purpose of net metering is to allow customers to
realize the value of their generation by directing and immediately offsetting part or all of their
energy consumption. The net metering program s current provisions immediately compensate
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
customers for the generation. However, the Company contends that generation in excess of
consumption should be viewed differently.
Power purchased under net metering, the Company contends, is non-firm energy and
is of less value for meeting system loads than would be an alternative wholesale purchase of firm
energy. Net metering customers are frequently being paid higher prices for this non-firm energy
than Idaho Power would have otherwise paid for energy purchased on the wholesale market.
Idaho Power contends that generation in excess of consumption should not receive compensation
in excess of the value provided at the expense of customers who do not choose to develop
generation facilities.
Idaho Power requests that its Schedule 84 net metering provisions be revised to treat
all customers in a fair and equitable manner. Upon approval of the Company s proposal
Schedule 1 and Schedule 7 customers who generate electricity in excess of their usage will be
treated the same as non-Rl/R7 net metering customers who provide a non-firm energy product to
the Company. They would be credited an amount per kilowatt hour equal to 85% of the most
recently calculated monthly per kilowatt hour Avoided Energy Cost as defined in Schedule 84.
Furthermore, excess generation provided by Schedule 1 and Schedule 7 net metering customers
would be considered an energy resource with the cost to be spread to all retail customers through
the PCA mechanism, the same treatment as is currently afforded excess generation provided by
non-Rl/R7 customers.
Modifications to Eliminate a Financial Barrier
Currently, non-Rl/R7 customers are required to have a meter that is separate from
the retail load metering at the point of delivery. Some of these customers, the Company
contends, find the requirement for a separate meter to be a financial barrier to installing a small
net metering system. To encourage participation among non-Rl/R7 customers, the Company is
proposing to expand the options for these customers through changes to Schedule 84. If a non-
RlIR7 customer s generation facility has a total nameplate capacity rating which is no more than
2% of their Basic Load Capacity (BLC) and the system is 25 kW or smaller, the customer could
participate in net metering on the same basis as the Company s residential and small general
service customers. (Basic Load Capacity is the average of the two greatest non-zero monthly
billing demands established during the 12-month period which includes and ends with the
current billing period.) As proposed, all energy received and delivered by the Company could be
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
through the single existing retail meter. This one-meter option, the Company contends, would
make the installation of small net metering systems much easier for non-Rl/R7 customers. Since
one of the criteria is the generation facility s capacity cannot be more than 2% of the customer
BLC, Idaho Power contends that it is unlikely that a customer exercising this option would ever
have excess net generation. However, if such were the case, under the Company s proposal
excess energy would not receive any net metering program financial credits.
Alternatives to Net Metering
Net metering customers with significant generation in excess of usage, Idaho Power
notes, have other alternatives available under the Company s tariffs to develop small-renewable
energy projects. For non-firm energy generation, customers have the option to participate under
Schedule 86, Cogeneration and Small Power Production Non-Firm Energy. For firm energy
generation, qualifying facilities (QFs) are entitled to published avoided cost rates under the
Public Utility Regulatory Policies Act of 1978 ( PURP A).Therefore, if customers are not
satisfied with a credit they receive through the net metering option, Idaho Power contends that
the customers could apply to be a firm or non-firm PURP A QF project.
YOU ARE FURTHER NOTIFIED that the Commission has reviewed the filings of
record in Case No. IPC-06-17. The Commission has preliminarily found that the public
interest in this matter may not require a hearing to consider the issues presented and that issues
raised by the Company s filing may be processed under Modified Procedure , by written
submission rather than by hearing. Reference Commission Rules of Procedure IDAP A
31.01.01.201-204.
YOU ARE FURTHER NOTIFIED that the deadline for filing written comments or
protests with respect to Idaho Power s Application and the use of Modified Procedure in Case
No. IPC-06-17 is Friday, October 13, 2006. Persons desiring a hearing must specifically
request a hearing in their written protest or comments.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are
received within the deadline, the Commission may consider the matter on its merits and may
enter its Order without a formal hearing. If comments or protests are filed within the deadline
the Commission will consider them and in its discretion may set the matter for hearing or may
decide the matter and issue its Order based on the written positions before it. Reference IDAP
31.01.01.204.
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
YOU ARE FURTHER NOTIFIED that written comments concerning Case No. IPC-
06-17 should be mailed to the Commission and the Company at the addresses reflected below.
Commission Secretary Maggie Brilz
Idaho Public Utilities Commission Director, PricingPO Box 83720 Idaho Power Company
Boise, ID 83720-0074 PO Box 70
Boise, ID 83707-0070
E-mail: mbrilzrW,idahopower.comStreet Address for Express Mail:
472 W. Washington Street
Boise, ID 83702-5983
Barton L. Kline
Monica B. Moen
Idaho Power Company
PO Box 70
Boise, ID 83707-0070
E-mail: bkline0)idahopower.com
mmoen0)idahopower.com
All comments should contain the case caption and case number shown on the first page of this
document.Persons desiring to submit comments via e-mail may do so by accessing the
Commission s home page located at www.puc.idaho.gov. Click the "Comments and Questions
icon , and complete the comment form, using the case number as it appears on the front of this
document. These comments must also be sent to Idaho Power at the e-mail addresses listed
above.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are
received within the time limit set, the Commission will consider this matter on its merits and
enter its Order without a formal hearing. If written comments are received within the time limit
set, the Commission will consider them and, in its discretion, may the set the same for formal
hearing.
YOU ARE FURTHER NOTIFIED that the Application in Case No. IPC-06-
may be viewed at www.puc.idaho.gov by clicking on "File Room" and "Electric Cases " or can
be viewed during regular business hours at the Idaho Public Utilities Commission, 472 West
Washington Street, Boise, Idaho and at the general business office of Idaho Power Company,
1221 West Idaho Street, Boise, Idaho.
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
DATED at Boise, Idaho this 3 0 t-J..day of August 2006.
Co. ission Secretary
bls/N:IPC-06-17 _
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE