HomeMy WebLinkAbout20060531intervention_order_no_30057.pdfOffice of the Secretary
Service Date
May 31, 2006
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER
COMPANY'S APPLICATION FOR A
CERTIFICATE OF PUBLIC CONVENIENCE
AND NECESSITY FOR THE EV ANDER ANDREWS POWER PLANT
CASE NO. IPC-06-
ORDER NO. 30057
The Industrial Customers of Idaho Power petitioned to intervene in this case on May
, 2006, pursuant to Rules of Procedure 71 through 75 of the Idaho Public Utilities
Commission, IDAPA 31.01.01.071-075.
FINDINGS OF FACT
We find that no party timely opposed this Petition to Intervene.
We further find that based on the pleadings and other documents filed in this case
intervention by this party would serve the purposes of intervention as described by Rule 74 of the
Rules of Procedure and should be granted.
ORDER
IT IS THEREFORE ORDERED that the Petition to Intervene filed by the Industrial
Customers of Idaho Power is hereby granted.
IT IS FURTHER ORDERED that all parties in this proceeding serve all papers
hereafter filed in this matter on all parties of record. This Intervenor is represented by the
following for purposes of service:
Peter J. Richardson
Richardson & O'Leary
515 N. 27th Street
PO Box 7218
Boise, ID 83702
E-mail: petercq?richardsonandolearv.com
Dr. Don Reading
6070 Hill Road
Boise, ID 83703
E-mail: dreadingcq?mindspring.com
ORDER NO. 30057
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this
t"'-
day of May 2006.
MARSHA H. SMITH, COMMISSIONER
ENNIS S. HANSEN, CO MISSIONER
ATTEST:
~~~1l
Commission Secretary