Janua 15,2007
Ms. Jean D. Jewell
Secretary
Idaho Public Utilities Commission
PO Box 83720
Boise, ID 83720-0074
Subject: IPC-E-06-09 - Quarerly Update on Danskin CTI Construction Project
Dear Ms. Jewell:
Enclosed please find the quaerly update on the Danskin CTI Constrction Project for
the fourh quarer of 2007. Total project costs through December 31, 2007 are $61,896,439.
Very truly yours,
Attchments
c: Ric Gale
Greg Said
Bart Kline
Legal Files
P.O. Box 70 (B3707)
1221 W.ldaho St.
Boise. 10 83702
Danskin CT1 Construction Project B~~i~"iJan. 10,2007 \ b 8: \ 0
Construction of the new combustion turbine at the Evander Andre~~~~~MW~~ií,1fearing
completion. Commercial operation is scheduled for Feb. 17, 20ÕSLWhìeWil'a1iead of schedule.
Siemens Power Generation has begun the important commissioning phase of the project.
Notices have been filed with the EPA in anticipation of "first fire" on Feb. 2, 2008. Although the
project will be operational in February, the project is scheduled for Provisional Acceptance from
Siemens on April 1 for completion. This will insure that punch list items are complete and final
site grading can be done in better weather.
The back feed power is available at the new 230 KV substation and the combustion turbine is
scheduled to be placed on "turning geat' Jan. 14. This important process is the first time that the
combustion turbine rotor shaft is turned at the project. The final gas line connections are
complete and commissioned. The new 230 KV line from Evander Andrews to Bennett Mountain
is complete. Current focus is the final check out of the computerized control system and operator
stations in the control room. Siemens contractor, INCa Construction has reduced its staff at the
site.
Below are the expenditures to date:
Idaho Power Company
Danskin CT1 Construction Project
Expenses
Through 12-31-07
Siemens Turnkey Contract
Change Orders
Sales Tax
Other Idaho Power Costs
$42,499,150
493,386
1,311,727
1,351,957
Subtotal: Plant Costs $45,656,220
Transmission Interconnection & Network Upgrades 16,240,219
Total Project Costs:$61,896,439
Note: AFUDC is not included