HomeMy WebLinkAbout20060110final_order_no_29950.pdfOffice of the Secretary
Service Date
January 10, 2006
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR
APPROVAL OF A FIRM ENERGY SALES
AGREEMENT FOR THE SALE AND
PURCHASE OF ELECTRIC ENERGY
BETWEEN IDAHO POWER COMPANY
AND NOTCH BUTTE WIND PARK LLC
ORDER NO. 29950
CASE NO. IPC-05-
On October 20, 2005 , Idaho Power Company (Idaho Power; Company) filed an
Application with the Idaho Public Utilities Commission (Commission) requesting approval of a
20-year Firm Energy Sales Agreement (Agreement) between Idaho Power and Notch Butte Wind
Park LLC (Notch Butte) dated October 14, 2005. Under the Agreement, Notch Butte will sell
and Idaho Power will purchase electric energy generated by Notch Butte, a project located near
Notch Butte, Idaho, which is between Twin Falls and Shoshone, Idaho, in an area more
particularly described as Section 36, Township 6 S, Range 16 E, Boise Meridian, Jerome
County, Idaho; Sections 3 , 4, 5 , 6, 8 and 9, Township 7 S, Range 17 E, Boise Meridian, Jerome
County, Idaho; and Section 3 , 4, 5, 8 and 9, Township 7 S, Range 17 E, Boise Meridian, Lincoln
County, Idaho. The project will consist of twelve (12) 1.5 MW GE wind turbines. The
nameplate rating of the project is 18.0 MW. Under normal and/or average conditions, the project
will not exceed 10 aMW on a monthly basis. If energy in excess of this amount (Inadvertent
Energy) is accidentally generated, Idaho Power will accept Inadvertent Energy that does not
exceed the 19.2 MW Maximum Capacity Amount, but will not purchase or pay for it.
Agreement ~ 7.3.2; Appendix B-
The Notch Butte project will be a qualified small power production facility (QF)
under the applicable provisions of the Public Utility Regulatory Policies Act of 1978 (PURP A).
As represented by Idaho Power, the Agreement comports with the terms and conditions of
Commission Order No. 29632 (Us. Geothermal et al v. Idaho Power), avoided cost Order No.
29646 and Commission Order Nos. 29839, 29851 and 29872 in Case No. IPC-05-22. The
Agreement is for a 20-year term and contains the non-Ievelized published avoided cost rates set
forth in Order No. 29646.
ORDER NO. 29950
In interlocutory Order No. 29839 issued in Case No. IPC-05-22 the Commission
reduced the size cap for QF wind generation facilities entitled to receive the published avoided
cost rates from 10 aMW to 100 kW. In its Order, the Commission further identified several
criteria that it would consider to determine whether a particular QF wind generation facility in
the negotiation queue was sufficiently mature so as to justify "grandfathering" the project to
entitlement to the published rates. These criteria are as follows:
(1) Submittal of a signed power purchase agreement to the utility, or(2) Submittal to the utility of a completed Application for Interconnection
Study and payment of fee.
In addition to a finding of existence of one or both of the preceding threshold
criteria, the QF must also be able to demonstrate other indicia of substantial
progress and project maturity, e.
(1) A wind study demonstrating a viable site for the project
(2) A signed contract for wind turbines(3) Arranged financing for the project, and/or(4) Related progress on the facility permitting and licensing path.
Order No. 29839, p. 10, August 4, 2005; final Order No. 29851. In reconsideration Order No.
29872 issued on September 21 , 2005 in the same case, the Commission reaffirmed the
grandfathering criteria and changed the "grandfathering" eligibility deadline from the previously-
ordered July 1 2005 , to August 4 2005 , the date of interlocutory Order No. 29839.
Considering and weighing all of the Commission-identified criteria, Idaho Power
believes that the Notch Butte project is sufficiently far enough along the development path that it
should be "grandfathered" to the published rates. Notch Butte has selected November 2006 as
the scheduled first energy date and May 2007 as the scheduled operation date.
As reflected in Agreement Section 24, the Agreement will not become effective until
the Commission has approved all the Agreement's terms and conditions and declares that all
payments that Idaho Power makes to Notch Butte for purchases of energy will be allowed as
prudently incurred expenses for ratemaking purposes.
On November 7 2005 , the Commission issued a Notice of Application and Modified
Procedure in Case No. IPC-05-32. The deadline for filing written comments was November
, 2005. Comments were filed by Commission Staff and Windland Incorporated. Staff has
reviewed the submitted Agreement and finds that it comports with the terms and conditions of
Commission Order No. 29632 (Us. Geothermal, et at. v. Idaho Power), avoided cost Order No.
ORDER NO. 29950
29646 and Commission Order Nos. 29839 , 29851 and 29872 in Case No. IPC-05-22. The
Agreement is for a 20-year term and contains the non-Ievelized published avoided cost rates set
forth in Order No. 29646. Staff recommends approval of the Agreement with an effective date
of October 14 2005.
Windland Incorporated expresses concern that the presence of "signed but not yet
built" wind PURPA contracts limits Idaho Power Company s options to procure other wind
energy resources. If projects are approved but not built on schedule, Windland contends that
there is a significant financial risk to Idaho ratepayers. Windland contends that Exergy
Development Group has been late meeting target dates for three approved projects to date. The
United Materials Horseshoe Bend Wind Park project near Great Falls, Montana is now almost a
year late in meeting its scheduled on-line date. The Fossil Gulch project near Hagerman, Idaho
is on-line but did not achieve the status by its January 1 , 2005 milestone target. The Burley
Butte project near Burley, Idaho did not meet its October 30, 2005 first energy date. Windland
does not expect the Thousand Springs, Pilgrim Stage, Oregon Trail and Tuana Gulch projects to
meet their December 31 , 2005 scheduled operation dates. If Exergy fails to bring Notch Butte
and three other proposed projects on-line by the scheduled May 2007 date, Windland contends
that it will be too late for Idaho Power to procure alternate wind resources from another source
before the federal production tax credit expires at the end of 2007. Reference Milner Dam (IPC-
05-30), Lava Beds (IPC-05-31), and Salmon Falls (IPC-05-33). Windland requests that
the Commission examine the totality of facts associated with these four contracts and only
approve them if Exergy provides adequate assurances that the projects will be timely built.
Exergy by way of reply contends that Windland raises issues of generic applicability
to PURP A contracts relative to penalties or damage calculations for delay in achieving the first
operation date for QF projects. Exergy contends that such issues are beyond the scope of the
instant proceeding. Exergy further contends that it is black letter law in Idaho that when the
Commission makes changes in a utility s rates or the terms and conditions of service, that such
changes may only be made on a prospective basis. Citing Utah Power Light v. IPUC 107
Idaho 47 685 P.2d 276 (1984).
Idaho Power in reply comments addresses Exergy contract performance, notes the
default provisions of the Agreement and cites prior QF contract policy regarding the
inappropriateness of liquidated damage provisions in small QF published rate contracts. Idaho
ORDER NO. 29950
Power contends that the Notch Butte project satisfies the Commission s grandfathering eligibility
criteria and requests that the Commission approve the Firm Energy Sales Agreement. Idaho
Power agrees that the template contract the Company currently utilizes for small QF published
rate contracts provides essentially a "free option" to the QF developer to sign a contract, lock-
a rate, and then go see if it can actually put together a project. Windland is correct in its
assessment, the Company concurs, that should multiple QF projects entitled to the published
rates fail to meet the scheduled operation dates, the collective impact could adversely affect the
Company s resource planning process. Should the Commission find the performance and
liquidated damage issues raised by Windland to be worthy of further consideration, Idaho Power
contends that the suggested changes are appropriate only for prospective application and
recommends that the appropriate procedure would be to open a separate docket.
COMMISSION FINDINGS
The Commission has reviewed and considered the filings of record in Case No. IPC-
05-, including the underlying Agreement, the comments and recommendations of
Commission Staff and Windland Incorporated, and the reply comments of Exergy and Idaho
Power. We have also reviewed public comments filed in support of the project.
The Commission Staff recommends that the Notch Butte Agreement be approved.
Windland Incorporated recommends that the Commission require adequate assurances from the
developer that the project will be timely built. Idaho Power notes the default provisions of the
Agreement and suggests that the generic performance and liquidated damage issues raised by
Windland be addressed, if at all, in a separate docket for prospective application in future
contracts.
The Commission has considered the concerns raised by Windland regarding the
ramifications of an approved QF project failing to come on-line. While the identified risks exist
we find the risk to be small. There is always a risk that QF projects will not come on-line at the
time projected. In addition, prices of resources are always changing. The Company s planning
process is flexible enough to accommodate the risk associated with small QF projects. We have
no developed record of upfront project failure to justify the imposition of a performance bond
requirement assuring that small projects qualifying for published rates will be timely built. Until
the facts are demonstrated to be otherwise we do not find a performance bond requirement in this
case or an investigation to be warranted.
ORDER NO. 29950
Idaho Power has presented a Firm Energy Sales Agreement with Notch Butte for
Commission consideration and approval. The nameplate rating of the wind facility is 18.0 MW.
The contract is for a 20-year term and contains non-Ievelized published avoided cost rates for
energy deliveries not exceeding 10 aMW on a monthly basis. The Commission finds that the
Agreement submitted in this case contains acceptable contract provisions and comports with the
terms and conditions of Order Nos. 29632 and 29682 in Case Nos. IPC-04-8; 04-10. The
Commission finds that the project satisfies the grandfathering eligibility criteria established in
Order Nos. 29839 and 29872 in Case No. IPC-05-22.
The Commission finds it reasonable that the submitted Agreement be approved
without further notice or procedure. IDAPA 31.01.01.204. We further find it reasonable to
allow payments made under the Agreement as prudently incurred expenses for ratemaking
purposes.
CONCLUSIONS OF LAW
The Idaho Public Utilities Commission has jurisdiction over Idaho Power Company,
an electric utility, pursuant to the authority and power granted it under Title 61 of the Idaho Code
and the Public Utility Regulatory Policies Act of 1978 (PURP A).
The Commission has authority under PURP A and the implementing regulations of
the Federal Energy Regulatory Commission (FERC) to set avoided costs , to order electric
utilities to enter into fixed term obligations for the purchase of energy from qualified facilities
and to implement FERC rules.
ORDER
In consideration of the foregoing, IT IS HEREBY ORDERED and the Commission
does hereby approve the October 14, 2005 Firm Energy Sales Agreement between Idaho Power
Company and Notch Butte Wind Park, LLC.
THIS IS A FINAL ORDER. Any person interested in this Order may petition for
reconsideration within twenty-one (21) days of the service date of this Order. Within seven (7)
days after any person has petitioned for reconsideration, any other person may cross-petition for
reconsideration. See Idaho Code ~ 61-626.
ORDER NO. 29950
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 01i'
day of January 2006.
.J~
MARSHA H. SMITH, COMMISSIONER
ATTEST:
bls/O:IPC-05-32 sw
ORDER NO. 29950