HomeMy WebLinkAbout20050819Notice of application.pdfOffice of the Secretary
Service Date
August 19 2005
BEFORE THE IDAHO PUBLIC UTILITIES COl\'IMISSION
IN THE l\'IATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR CASE NO. IPC-O5-
APPROVAL OF A FIRM ENERGY SALES
AGREEMENT FOR THE SALE AND NOTICE OF APPLICATION
PURCHASE OF ELECTRIC ENERGY
BETWEEN IDAHO POWER COMPANY NOTICE OF MODIFIED
AND ARROW ROCK WIND, INC.PROCEDURE
NOTICE OF
COMMENT/PROTEST
DEADLINE
YOU ARE HEREBY NOTIFIED that on July 28, 2005, Idaho Power Company
(Idaho Power; Company) filed an Application with the Idaho Public Utilities Commission
(Commission) requesting approval of a Firm Energy Sales Agreement (Agreement) between
Idaho Power and Arrow Rock Wind, Inc. (Arrow Rock) dated July 28 , 2005. Under the
Agreement, Arrow Rock will sell and Idaho Power will purchase electric energy generated by
the Arrow Rock Wind Generating Project, located near Billings Montana, in an area more
particularly described as located approximately 100 miles northwest of Billings, Montana in
Wheatland County on the west side of Highway 191 in the NW 1/4 of Section 36, Township
, Range 15 E. The nameplate rating of the wind facility is 19.5 MW. Under normal and/or
average conditions, the project will not exceed 10 aMW on a monthly basis.
As represented, Arrow Rock will be a qualified small power production facility (QF)
under the applicable provisions of the Public Utility Regulatory Policies Act of 1978 (PURP A).
Idaho Power contends that the Agreement comports with the terms and conditions of
Commission Order No. 29632 (US. Geothermal et al v. Idaho Power) and avoided cost Order
No. 29646. The Agreement is for a 20-year term and contains the published non-Ievelized
avoided cost rates set forth in Order No. 29646. Arrow Rock has selected December 1 , 2005 as
the scheduled Operation Date for this facility.
Arrow Rock has made arrangements with NorthWestern Energy to deliver the net
energy from its Montana facility to the Idaho Power electrical system. The transmission
arrangement with NorthWestern Energy means that the Company will receive firm energy from
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENTIPROTEST DEADLINE
the facility rather than the intermittent energy generally associated with a wind-generating
project. Energy deliveries from the Arrow Rock project are for nine months out of the year and
exclude deliveries during the spring months of March, April and May when the value of energy
on the Company s system is the lowest.
Idaho Power acknowledges the Company s Petition in Case No. IPC-05-22 and
represents that Arrow Rock was in the final stages of negotiations with Idaho Power immediately
prior to the Petition filing and that prior to that date Arrow Rock had submitted an executed
Agreement to the Company. It is Idaho Power s contention that Arrow Rock is appropriate for
exempting from the temporary suspension requested by the Company in Case No. IPC-05-22.
Section 22 of the Agreement provides that the Agreement will not become effective
until the Commission has approved all the Agreement's terms and conditions and declared that
all payments that Idaho Power makes to Arrow Rock for purchases of energy will be allowed as
prudently incurred expenses for ratemaking purposes.
YOU ARE FURTHER NOTIFIED that the Commission has reviewed the filings of
record in Case No. IPC-05-24. The Commission has preliminarily found that the public
interest in this matter may not require a hearing to consider the issues presented and that issues
raised by the Company s filing may be processed under Modified Procedure Le., by written
submission rather than by hearing. Reference Commission s Rules of Procedure, IDAPA
31.01.01.201-204.
YOU ARE FURTHER NOTIFIED that the deadline for filing written comments or
protests with respect to Idaho Power s Application and the use of Modified Procedure in Case
No. IPC-05-24 is Friday, September 9 2005.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are
received within the deadline, the Commission may consider the matter on its merits and may
enter its Order without a formal hearing. If comments or protests are filed within the deadline,
the Commission will consider them and in its discretion may set the matter for hearing or may
decide the matter and issue its Order based on the written positions before it. Reference IDAP A
31.01.01.204.
YOU ARE FURTHER NOTIFIED that written comments concerning Case
No. IPC-05-24 should be mailed to the Commission and the Company at the addresses
reflected below.
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
Commission Secretary
Idaho Public Utilities Commission
PO Box 83720
Boise, ID 83720-0074
Street Address for Express Mail:
Monica B. Moen, Attorney II
Barton L. Kline, Senior Attorney
Idaho Power Company
PO Box 70
Boise, ID 83707-0070
Mail: mmoen(fYidahopower.com
bkl ine(fYitillhQpower. com
472 W. Washington Street
Boise, ID 83702-5983 Randy C. Allphin, Contract Administrator
Idaho Power Company
PO Box 70
Boise, ID 83707-0070
E-mail: nillPhin(fYidahopower.com
Street Address for Express Mail:
1221 W. Idaho Street
Boise , ID 83702
All comments should contain the case caption and case number shown on the first page of this
document. Persons desiring to submit comments via e-mail may do so by accessing the
Commission s home page located at www.puc.idaho.gov. Click the "Comments and Questions
icon, and complete the comment form, using the case number as it appears on the front of this
document. These comments must also be sent to Idaho Power at the e-mail addresses listed
above.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are
received within the time limit set, the Commission will consider this matter on its merits and
enter its Order without a formal hearing. If written comments are received within the time limit
set, the Commission will consider them and, in its discretion may set the same for formal
hearing.
YOU ARE FURTHER NOTIFIED that the Application in Case No. IPC-05-
may be viewed at www.puc.idaho.gov by clicking on "File Room" and "Electric Cases " or can
be viewed during regular business hours at the Idaho Public Utilities Commission, 472 W.
Washington Street, Boise, Idaho and at the general business office of Idaho Power Company,
1221 West Idaho Street, Boise, Idaho.
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE
DATED at Boise, Idaho this qf"day of August 2005.
bls/N:IPC-O5-24 sw
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
NOTICE OF COMMENT/PROTEST DEADLINE