Loading...
HomeMy WebLinkAbout20040827Notice of Rebuttal Testimony Deadline Order No 29574.pdfOffice of the Secretary Service Date August 27, 2004 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IDAHO POWER COMPANY Respondent. ) CASE NO. IPC-O4- ) NOTICE OF REBUTTAL ) TESTIMONY DEADLINE ) NOTICE OF AREA VIEWING ) ORDER NO. 29574 Complainant, CITY OF EAGLE, IDAHO, On February 11 , 2004, Idaho Power Company filed a complaint against the City of Eagle requesting that the Commission authorize the utility to construct a new 138- transmission line from the Eagle substation to a new substation in Star. Idaho Power filed its Complaint after the City denied two Idaho Power conditional use permit (CUP) applications to build the line through Eagle. The Complaint presents three primary issues: (1) the route of the new transmission line through or around the City; (2) the manner of construction (i.e., via aerial poles, underground or a combination of the two construction methods); and (3) should the City be responsible for any additional incremental costs associated with either underground construction or with construction over a more expensive alternate route. Following a prehearing conference, the Commission issued Order No. 29465 in April 2004 setting this matter for hearing. With the consent of the Parties, the original filing deadline for Idaho Power s rebuttal testimony was postponed. Now that settlement negotiations have proved unfruitful, the Commission resets Idaho Power s prefile rebuttal testimony date and gives notice of its intent to view the proposed area of impact prior to the public and technical hearings scheduled for September 9, 2004. NOTICE OF REBUTTAL TESTIMONY DEADLINE YOU ARE HEREBY NOTIFIED that Idaho Power s prefile rebuttal testimony deadline has been reset from the date identified in Order No. 29465. Idaho Power shall transmit its testimony via e-mail to the Parties of Record no later than Monday, September 6, 2004. NOTICE OF REBUTTAL TESTIMONY DEADLINE NOTICE OF AREA VIEWING ORDER NO. 29574 Because September 6 is a state holiday and the Commission s offices will be closed, Idaho Power shall file its rebuttal testimony with the Commission no later than Tuesday, September 7 2004. NOTICE OF VIEWING YOU ARE FURTHER NOTIFIED that in preparation for the hearings, the Commission intends to view the proposed area of impact. The Parties may presume that the Commission is familiar with the general layout of the existing electric system in Eagle. ORDER IT IS HEREBY ORDERED that Idaho Power transmit its prefile rebuttal testimony to the Parties of Record no later than September 6, 2004. Idaho Power shall file its rebuttal testimony with the Commission no later than September 7, 2004. DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this :l ')tk day of August 2004. JiW MARSHA H. SMITH, COMMISSIONER Commissioner Hansen Out of the Office DENNIS S. HANSEN, COMMISSIONER ATTEST: bls/O:IPCEO404 dh4 NOTICE OF REBUTTAL TES TIM 0 NY DEADLINE NOTICE OF AREA VIEWING ORDER NO. 29574