BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION OF
IDAHO POWER COMPANY FOR AUTHORITY
TO IMPLEMENT A POWER COST
ADJUSTMENT (PCA) RATE FOR ELECTRIC
SERVICE FROM MAY 16, 2003 THROUGH
MAY 15, 2004.
CASE NO. IPC-03-
ERRATA NOTICE TO
ORDER NO. 29243
On May 15 , 2003 , IPUC Order No. 29243 was issued by this Commission. The
following change(s) should be made to that Order:
Page 7, Commission Findings Paragraph, last sentence
READS:
We calculate this true-up rate to be 6039~per kWh and find that these
interim PCA rates are reasonable, recognizing that there are additional issues
yet to be decided.
SHOULD READ:
We calculate this true-up rate to be 3579~per kWh and find that these
interim PCA rates are reasonable, recognizing that there are additional issues
yet to be decided.
DATED at Boise, Idaho this llQ~L-- day of May 2003.
~~~
~LUlAj
arbara Barrows
Assistant Commission Secretary
bls/O:IPCE0305 _1n2 _errata