HomeMy WebLinkAbout20140609_4384.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER KJELLANDER
COMMISSIONER REDFORD
COMMISSIONER SMITH
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: KRISTINE SASSER
DEPUTY ATTORNEY GENERAL
DATE: JUNE 6, 2014
SUBJECT: IDAHO POWER’S APPLICATION FOR APPROVAL OR REJECTION
OF A PPA WITH NORTH SIDE ENERGY, CASE NO. IPC-E-14-07
On April 30, 2014, Idaho Power Company filed an Application requesting that the
Commission accept or reject an Agreement between Idaho Power and North Side Energy
Company (North Side), Inc., for the sale and purchase of electric energy generated by the Head
of U Canal Project. On May 27, 2014, Idaho Power filed an Amendment to its Application that
included a summary of terms and conditions contained in the proposed Agreement that are
different from prior agreements approved by this Commission.
THE APPLICATION
On April 23, 2014, Idaho Power and North Side entered into an Agreement pursuant
to the terms and conditions of various Commission Orders applicable to PURPA agreements for
seasonal hydro projects. Idaho Power states that North Side proposes to operate and maintain a
1.28 megawatt (MW) seasonal hydro energy facility to be located near Jerome, Idaho. The
Company maintains that the project will be a qualified facility (QF) under the applicable
provisions of the Public Utility Regulatory Policies Act (PURPA).
Under the terms of the Agreement, North Side elected to contract with Idaho Power
for a 20-year term using the non-levelized other published avoided cost rates as currently
established by the Commission in Order No. 32817 for energy deliveries of less than 10 average
MW (aMW). As defined in paragraphs 1.20 and 4.1.4 of the Agreement, North Side will be
required to provide data on the facility that Idaho Power will use to confirm that under normal
and/or average conditions, the facility will not exceed 10 aMW on a monthly basis. As described
in paragraph 7.5 of the Agreement, should the facility exceed 10 aMW on a monthly basis, Idaho
DECISION MEMORANDUM 2
Power will accept the inadvertent energy that does not exceed the maximum capacity amount,
but will not purchase or pay for inadvertent energy.
North Side has selected May 1, 2015, as the project’s Scheduled Operation Date.
Various requirements have been placed upon North Side in order for Idaho Power to accept
energy deliveries from this facility. Idaho Power will monitor compliance with these
requirements. Idaho Power will continue to monitor the ongoing requirements throughout the
term of the Agreement.
The Agreement provides that all applicable interconnection charges and monthly
operational or maintenance charges under Schedule 72 will be assessed to North Side. A
Schedule 72 Generator Interconnection Agreement (GIA) between North Side and Idaho Power
was executed on July 29, 2013. Idaho Power states that PURPA QF generation must be
designated as a network resource (DNR) to serve Idaho Power’s retail load on its system. In
order for the facility to maintain its DNR status and maintain compliance with Idaho Power’s
non-discriminatory administration of its Open Access Transmission Tariff (OATT) and FERC
requirements there must be a power purchase agreement (PPA) associated with its transmission
service request.
Article 21 of the Agreement provides that the PPA will not become effective until the
Commission has approved all terms and conditions and declared that all payments Idaho Power
makes to North Side for purchases of energy will be allowed as prudently incurred expenses for
ratemaking purposes.
Idaho Power filed an Amendment to its initial Application on May 27, 2014. The
Amendment provides a summary of terms and conditions contained in the proposed Agreement
that are different from prior agreements approved by this Commission. In its Amendment, Idaho
Power explains that the recent hydro agreements are the first hydro-based agreements submitted
for approval “that contain revised terms and conditions subsequent to the Commission’s final
and reconsideration orders from Case No. GNR-E-11-03. As such, the form of the [Agreement]
has several terms and conditions that vary from previously approved agreements in order to
comply with the Commission’s recent orders.” Amendment at 5.
Idaho Power and North Side also agreed to changes in some standard provisions that
the parties now propose for Commission approval. Idaho Power identifies that major changes as
follows:
Change to the definition of “Mid-Columbia Market Energy Cost” to
replace reference to the Dow Jones index with reference to the
DECISION MEMORANDUM 3
Intercontinental Exchange (ICE) index and formula consistent with the
proposed settlement in Case No. IPC-E-13-251;
Addition of definitions and provisions, paragraphs 1.29, 1.38, 1.39, 3.4
and 7.6 to incorporate definitions of “non-seasonal hydro facility” and
“seasonal hydro facility” as well as “seasonal hydro facility test periods”
to incorporate and maintain separate rates for seasonal and non-seasonal
hydro projects and to ensure that seasonal hydro projects perform within
the requirements of generating 55 percent of their annual generation in the
months of June, July and August;
Removal of the provisions providing for delay liquidated damages and
maintained provisions to provide for delay security and actual delay
damages as provided for by the Commission’s adoption of the partial
stipulation in Commission Order No. 32697;
Change to Article VIII, “Environmental Attributes,” to indicate that North
Side owns all Environmental Attributes or Renewable Energy
Credits/Certificates;
Change to paragraph 6.2 to allow Mr. Arkoosh to adjust the “Initial Year
Monthly Net Energy Amounts” on a monthly, rather than quarterly, basis;
Revision to paragraph 12.4 relating to Scheduled Maintenance; and
Several other minor revisions in an attempt to add clarity.
Idaho Power requests that its Application be processed by Modified Procedure.
STAFF RECOMMENDATION
Staff recommends that the case be processed by Modified Procedure with at least a
28-day comment period and opportunity for reply.
COMMISSION DECISION
Does the Commission wish to process this case under Modified Procedure with a 28-
day comment period and opportunity for reply?
M:IPC-E-14-07_ks
1 This change is relevant to the 90/110 performance requirement.