HomeMy WebLinkAbout20020829Order No 29103.pdfOffice of the Secretary
Service Date
August 29, 2002
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR AN
ORDER APPROVING THE COSTS TO BE
INCLUDED IN THE 2002/2003 PCA YEAR
FOR THE IRRIGATION LOAD REDUCTION
PROGRAM AND AST ARIS LOAD REDUCTION AGREEMENT.
CASE NO. IPC-01-
ORDER NO. 29103
In the spring of 2001 , the Commission approved Idaho Power Company s Irrigation
Load Reduction Program ("Program ), authorizing the Company to pay large irrigation
customers to reduce their electric consumption by at least 100 000 kilowatt hours ("kWh"
between March 1 , 2001 and November 30, 2001 (the "irrigation season l Order Nos. 28676
and 28699 (Case No. IPC-01-3). The Program was implemented in response to two unique
conditions: the second worst drought on record and unprecedented wholesale power costs.
On October 19, 2001 , the Company filed an Application requesting that the
Commission authorize it to recover two components it claimed were Program costs as part of the
2002/2003 Power Costs Adjustment ("PCA"). Case No. IPC-01-34. The first component is
the direct costs of the Program, i.e., the actual payments made to irrigation customers for
reducing their energy consumption. Order No. 28699 at 21. The second component is the "lost
revenue" which represents a calculated amount of revenue the Company might have received
from the sale of power to irrigation customers had the Program not been in operation.
On April 15, 2002, the Commission issued Order No. 28992 granting Idaho Power
request to recover the Program s direct costs, which at its conclusion totaled nearly $74 million
in payments made to irrigators for reducing their electrical consumption.However, the
Commission denied the Company s request to recover approximately $12 million of lost
revenue, i., the revenue the Company might have earned if irrigators had not reduced their
consumption.
Idaho Power filed a timely Petition for Reconsideration requesting that the
Commission reconsider its decision regarding lost revenue. Idaho Power did not seek
1 The Program was a temporary and voluntary program only for the 200 I irrigation season.
ORDER NO. 29103
reconsideration of the Commission s decision to grant it recovery of a quantified amount of its
direct costs. The Company did not request a hearing to submit additional evidence and asked the
Commission merely to reconsider its decision based upon the existing record. No party filed a
response to the Company s Petition. On May 30, 2002, the Commission granted reconsideration
so that it could "thoroughly review the record. . . and render our decision." Order No. 29040 at
As a preliminary matter we acknowledge that the Load Reduction Program, Case No.
IPC-01-, and the present case, Case No. IPC-01-, are inextricably linked. Idaho Power
recognized this fact by citing the record from Case No. IPC-01-3 in its Application and
Petition for Reconsideration in this case. We have reviewed and relied upon the records from
both cases to resolve the issues raised in Idaho Power s Petition for Reconsideration. Having
reviewed this matter fully, the Commission denies Idaho Power s Petition for Reconsideration.
BACKGROUND
A. Historical Context
Prior to implementing the Program and during its operation, Idaho was experiencing
its second worst drought conditions in about 75 years. See generally, Order Authorizing
Temporary Increase in Generation in Light of Electricity Exigencies in Western United States
Project No. 18-063 at 8, 95 FERC,-r 61 181 (May 8, 2001). See also Order No. 28722. In a
normal water year Idaho Power generates about 60% of its power system requirement from its
hydropower facilities. Because of the drought conditions, Idaho Power was forced to purchase
more power than usual from the regional wholesale market. In December 2000, the Commission
ordered Idaho Power and other Idaho utilities to cease off-system sales of hydropower and
conserve critical water supplies. Order No. 28605 at 3; Order No. 28665 at 4. At the same time
as Idaho and the West were experiencing severe drought, western power prices were extremely
volatile and at unprecedented highs due in large part to chronic supply shortages in California
and poor hydro conditions throughout the West. Monthly average wholesale prices were ten
times higher than normal prices. Order No. 28722 at 21. To address these difficulties the
Company initiated several load reduction programs in early 2001 to reduce its power needs and
to mitigate against possible rate increases. As the Commission recognized in the 200112002
PCA Order issued May 1 , 2001
, "
(i)n granting the rate increase authorized by this Order, the
Commission recognizes that consumers need avenues to reduce their consumption. Conservation
ORDER NO. 29103
and DSM programs are powerful tools Idahoans can use to mitigate the impact of this rate
increase as well as ones that may occur in the future." Order No. 28722 at 21. Simply put, Idaho
Power and the Commission were actively seeking ways to reduce customer consumption and
mitigate against possible customer rate increases. It was under these circumstances that the
Commission approved Idaho Power s Irrigation Load Reduction Program.
B. Case No. IPC-01-
The extreme drought conditions in 2001 drastically reduced Idaho Power
hydro generation of energy. Consequently, the Company was faced with the reality of needing to
purchase large amounts of power on the regional wholesale power market to supply its customers
with electricity. At the same time the prices for power in the regional market were at an all time
high. Consequently, implementation of Idaho Power s Program was meant to significantly
reduce electrical consumption and the need to purchase high priced power from the market.
Reducing off-system purchases was critical not only to the Company but to all
ratepayers as the cost of power in the market was at unprecedented high levels and could result
in severe increases in customer utility rates. These purchase power costs were also much higher
than paying irrigation customers to reduce their consumption of energy. Case No. IPC-01-
Order No. 28699 at 11-12. Thus, the Program was meant to cost effectively reduce the amount
and total expense of Idaho Power s off-system purchases of power during 2001 it would have to
make to serve its system load.
In approving the implementation of this Program the Commission found:
Idaho Power s Irrigation Buy-Back Program will serve the public interest by
providing the opportunity for the Company s customers to receive positive
benefits if it is successful. Allowing Idaho Power to pay irrigators for energy
reductions rather than purchasing power on the wholesale market will have a
positive impact on Idaho s economy in general by retaining those dollars in
the state of Idaho.
Order No. 28699 at 11; see also Order No. 28676 at 2. The Commission also found that:
(T)he direct costs and lost revenue impacts of this Program may be treated as
a purchased power expense in the Company s Power Cost Adjustment
PCA") mechanism. Idaho Power and the parties shall develop and present a
proposal to the Commission recommending a procedure to calculate the
amount of revenue impact that should be passed through the Company s PCA
mechanism. Idaho Power shall record the purchase cost paid to irrigators and
any calculated lost revenue in separate purchased power subaccounts. The
ORDER NO. 29103
separate subaccount detail with all supporting documentation should be such
that the costs for the Buy-Back Program and any lost revenue amounts will be
easily identified for audit. The PCA filing should also include a separate line
to identify these costs.
Order No. 28699 at 12 (emphasis added); see also Order No. 28676 at 2-
C. Case No. IPC-01-
In October 2001, Idaho Power requested that the Commission authorize the Company
to include the costs of the Irrigation Load Reduction Program in the 200212003 Power Cost
Adjustment ("PCA") case. The Company sought to recover $73 941 839.42 in direct costs from
the Irrigation Program through its PCA mechanism. See Order No. 29026, Case No. IPC-02-
(authorizing recovery of this amount through the PCA). Idaho Power also sought Commission
authorization to recover lost revenue. The total amount of lost revenue the Company sought was
$11 589 179 without interest.2 Case No. IPC-02-2 and -, Tr. at 424; Staff Exh. 4, p. 2 , line
14.
On April 15, 2002, the Commission issued Order No. 28992 granting in part and
denying in part Idaho Power s Application. The Commission granted Idaho Power s request to
recover the direct costs resulting from this Program. Order No. 28992 at 6-7. However, the
Commission rejected the Company s request for recovery of lost revenue. Order No. 28992 at 7-
8. In its findings the Commission stated:
In Order No. 28699 we stated
, "
direct costs and lost revenue impacts of this
Program may be treated as a purchased power expense in the Company
Power Cost Adjustment ("PCA") mechanism.Order No. 28699 at p.
(emphasis added). This Commission finding did not guarantee that Idaho
Power was entitled to recovery of alleged reduced/lost revenues that resulted
from this Program. Rather, the Commission merely recognized that the issue
of recovery of these amounts would be considered. Thus, any amount of
reduced revenue for which the Company would later seek recovery had to be
properly accounted for and subsequently reviewed by the Commission. This
issue has been thoroughly addressed and argued by Idaho Power and
supported by the Commission Staff. However, the Commission remains
unconvinced that Idaho Power should recover reduced revenues in this case.
At the time this Program was approved, volatility in the regional power
market and below normal streamflows had pushed the market price of power
to unprecedented levels. This Program was intended to allow Idaho Power to
cost-effectively reduce its total purchase power expense during 2001 , thereby
2 Including interest the total amount sought to be recovered by the Company is $12 015 461.25.
ORDER NO. 29103
benefiting all of its customers. The Commission finds that in the context of
the market situation that existed at the time this Program was approved, it was
the prudent if not required action for the Company to take and that further
incentives, such as the recovery of reduced revenues, to develop and utilize a
program of this type were not needed . Finally, in general, the
Commission rejects the "no losers test." The societal viewpoint dictates that
Idaho is best served by not permitting the "no losers" price to be a ceiling on
load reduction programs or conservation measures costs.
Order No. 28992 at 7-8. (emphasis added).
THE PETITION FOR RECONSIDERATION
Idaho Power presents several arguments why the Commission should reconsider its
decision in final Order No. 28992. The Company generally asserts that denying the recovery of
lost revenue is unreasonable, unlawful, erroneous, unduly discriminatory, and not in conformity
with the facts of record or applicable law. In addition, the Company maintains that the Order
results in confiscation, and ultimately rates that are confiscatory. These arguments are discussed
in greater detail below.
First, Idaho Power alleges the Commission s denial of the recovery of lost revenue
results in confiscation and ultimately rates that are confiscatory. Petition at 2-3. Second, Idaho
Power argues that the Commission s denial of the recovery of lost revenue in Order No. 28992 is
not in conformity with the facts in the record of Case No. IPC-01-3 or the Orders issued in that
case. Specifically, the Company alleges that Order No. 28699 authorized it to recover lost
revenue. !d. at 3-4. Third, the Company contends that denial of the recovery of lost revenue in
Order No. 28992 is an unlawful collateral attack on Order No. 28699 in Case No. IPC-01-
which the Company contends authorized their recovery. Id. at 4. Finally, Idaho Power alleges
that Order No. 28992 or any other Order that requires the implementation of conservation or
demand-side management ("DSM,,)3 programs that does not allow the Company to recover all its
costs, including lost revenue, is unreasonable, unlawful and confiscatory. Id. at 5.
Idaho Power did not offer to provide additional evidence and contends that the
evidentiary record in Case No. IPC-01-3 and in this proceeding, Case No. IPC-01-, is
sufficient for the Commission to make a determination on its Petition. Based on the foregoing,
3 Demand-side management programs are used to encourage consumers to modify patterns of electricity usage
including the timing and level of electricity demand.
ORDER NO. 29103
Idaho Power requests that the Commission reconsider Order No. 28992 and upon
reconsideration, issue an Order that would authorize the Company to recover the total amount of
lost revenue ($12.015 million). Idaho Power also requests that the Commission modify Order
No. 28992 to provide that in determining the cost effectiveness of any conservation or DSM
program, the Company is entitled to recover all costs that it would incur as a result of the
implementation of any particular program.
COMMISSION FINDINGS AND DISCUSSION
A. Standard for Reconsideration
Reconsideration provides an opportunity for an aggrieved person to bring to the
Commission s attention any issue previously determined and provides the Commission with an
opportunity to rectify any mistake or omission. Idaho Code ~ 61-626; Washington Water Power
v. Kootenai Environmental Alliance 99 Idaho 875, 591 P.2d 122 (1979). In those instances
where an aggrieved person asks the Commission to reconsider its decision based upon the
record, it may simply do so. The Commission s Procedural Rule 331.01 requires that petitions
for reconsideration must include "a statement of the nature and quantity of evidence or argument
that the petitioner will offer if reconsideration is granted." IDAPA 31.01.01.331.01.
Commission Rule 331.03 provides that petitions for reconsideration must state whether the
petitioner requests reconsideration by evidentiary hearing, written briefs, comments, or
interrogatories. IDAPA 31.01.01.331.03. Idaho Power stated in its Petition that the record(s) in
this matter is sufficient to make a determination on this matter without the need for further
proceedings.
On May 30, 2002, the Commission issued Order No. 29040 and determined the
record in this proceeding was sufficient by itself for us to render a decision on the Company
Petition for Reconsideration. Order No. 29040 at 2. Accordingly, we granted Idaho Power
Petition for the limited purpose of examining the record to determine whether Order No. 28992
should be amended to allow the Company to recover lost revenue that may have resulted from
operation of the Irrigation Load Reduction Program in 2001. Id.
B. The Record in Case No. IPC-01-3 and "May" vs. "Shall"
Idaho Power s Petition for Reconsideration rests largely on its mistaken belief that the
Commission specifically approved the recovery of lost revenue in Order No. 28699 (Case No.
IPC-01-3) issued May 25 2001. No such approval was given in that Order or any other Order
ORDER NO. 29103
involving this issue. In that case we explicitly stated that the Company may treat these amounts
as a purchased power expense for the purposes of booking the amounts properly. Actual
recovery of the booked lost revenue was to be decided in the subsequent case, Case No. IPC-
01-34. Our use of the word "may" was not intended to authorize the recovery of the yet to be
determined lost revenue. See Rife v. Long, 127 Idaho 841 , 848, 908 P.2d 143, 150 (1995) (the
meaning of the word "may," when appearing in legislation means or expresses the right to
exercise discretion. When used in a statute, the word "may" is permissive rather than the
imperative or mandatory meaning of "must" or "shall.
In Order No. 28699 we recognized that recovery of lost revenue was an issue that
would be preserved for review in the annual 2002/2003 PCA case. Accordingly, Order No.
28699 required that the parties develop a mechanism to calculate the amount of lost revenue and
that the Company properly account for the amount so that it could be easily identified for audit.
The Order contemplated that in March 2002, during review of the Company s next PCA filing,
we would determine whether any lost revenue should be recovered and if so what amount was
prudent and reasonable. Accordingly, our Orders in Case No. IPC-01-3 did not grant Idaho
Power the authorization to recover lost revenue from implementing this Program. Rather, the
Commission determined that the issue would be preserved for later review. On further review, in
Order No. 28992 issued April 15, 2002, we found that the recovery of lost revenue was
inappropriate. Based on the foregoing, the Commission finds that this argument is without merit
and is not a basis for amending Order No. 28992.
C. Collateral Attack
Idaho Power next alleges that Order No. 28992 is an unlawful collateral attack on our
prior Order No. 28699 in Case No. IPC-01-, that it contends authorized the recovery of lost
revenue. Idaho Power contends that the plain meaning of the word "may" in the context of
Order No. 28699 is that the Company was permitted to recover lost revenue. Thus, the Company
argues that Order No. 28992 denying their recovery is in direct contradiction to Order No. 28699
and amounts to a collateral attack in violation of Idaho Code ~ 61-625. The Company
argument is misplaced. Idaho Code ~ 61-625 provides
, "
(a)ll orders and decisions of the
commission which have become final and conclusive shall not be attacked collaterally.
We find that Order No. 28992 is not an unlawful collateral attack on Order No. 28699
for three reasons. First, as stated previously, we did not authorize the recovery of lost revenue in
ORDER NO. 29103
Order No. 28699; we established an accounting mechanism to track and preserve the issue for
later review. This was the "plain meaning" of our usage of the word "may" in Order No. 28699.
Rife 127 Idaho at 848, 908 P.2d at 150.Second, Order No. 28699 did not "finally and
conclusively" determine an exact amount, if any, that Idaho Power could recover. Neither did it
specify the rates to produce the amount to be recovered. Indeed, the irrigation season had just
begun. Order No. 28699 only authorized the Program to be implemented and established a
tracking or booking mechanism. Thus, it was also not "final and conclusive" as to any amount
that Idaho Power might be allowed to recover. See Rosebud Enterprises v. Idaho P. U , 131
Idaho 1 , 5 , 951 P.2d 521 525 (1997). Accordingly, the Commission s denial of the recovery of
lost revenue does not in any way contradict Order No. 28699 and does not constitute a collateral
attack on that Order.
Idaho Power has also misconstrued and misapplied !daho Code ~ 61-625. This
statute bars persons from collaterally attacking final Commission Orders. Even had we approved
the recovery of lost revenue in Order No. 28699 which we did not the Commission retains the
authority to rescind, alter or amend a prior Order or decision made by it. Idaho Code ~ 61-624.
D. Lost Revenue Is Not a Recoverable Cost in this Case
The Company argues that the Commission without evidentiary or legal support
denied recovery of lost revenue. Furthermore, Idaho Power contends that by not allowing the
recovery of lost revenue results in confiscation and ultimately rates that are confiscatory.
1. Exercise of Lawful Authority
Our decision to deny the recovery of lost revenue implicates the Commission
ratemaking functions as delegated by the Idaho Legislature. The Commission s decision on this
matter undeniably has had an effect on the rates that customers pay for electric service from
Idaho Power.
The function of ratemaking is legislative and not judicial. Industrial Customers of
Idaho Power v. Idaho Public Utilities Commission 134 Idaho 285, 289, 1 P.3d 786, 790 (2000).
The Commission, as an agency of the legislative department of government, exercises delegated
legislative power to make rates. Id. So long as it regularly pursues its authority and remains
within constitutional limitations, the courts have no jurisdiction to interfere with its
determinations. Id. Thus, the Commission s rate setting Order carries with it the presumption of
validity. See Application of Utah of Power Light Co.107 Idaho 446, 448-, 690 P.2d 901
ORDER NO. 29103
903-04 (1984). The Commission is vested with the power to supervise and regulate every public
utility in the state and to do all things necessary to carry out the spirit and intent of the Public
Utilities Law. See Idaho Code ~ 61-501.
Before the Commission can increase rates, it must first make a finding that such
increase is justified. Idaho Code ~ 61-622. Section 61-622 provides in relevant part:
The commission shall have power, and is hereby given authority, either upon
complaint or upon its own initiative ... to enter upon a hearing concerning the
propriety of such rate, fare, . . . rule or regulation. . . . On such hearing, the
commission shall establish the rates, fares, . . . rules or regulations proposed
, .
. . which it shall find to be just and reasonable.
Idaho Code ~ 61-622.
Idaho Power requested that the Commission allow it to recover and pass on to
ratepayers through the PCA mechanism the lost revenue it claims it would have earned but for
the implementation of the Program. Based on the Commission s ratemaking authority we are
empowered to determine whether the Company should recover the lost revenue that allegedly
resulted from this Program. Nothing in the record indicates that the Commission departed from
regularly pursuing its statutory authority when it decided to deny the recovery of lost revenue.
Accordingly, we find that Idaho Power s argument that we were without a legal basis to deny the
recovery of lost revenue is without merit.
2. It Is Not Appropriate for the Company to Recover Lost Revenue
The Commission finds that lost revenue is not a recoverable "expense" to be
recovered from ratepayers like the direct costs from this Program (i., the payments to
irrigators). In general, the Commission finds that rates should accurately reflect the actual costs
incurred to provide service. Given the unique context that caused this Program to be
implemented, we find that lost revenue does not constitute an actual cost of providing service
that should be borne by ratepayers. To allow Idaho Power to recover lost revenue would at least
partially destroy the goal of reducing overall energy costs to all ratepayers at a time when energy
costs were at all time highs. To charge ratepayers for lost revenue is unreasonable in the context
of the crisis that existed because of the drought and the unprecedented prices in the regional
power market at that time. Requiring ratepayers to pay for energy they did not consume, but
avoided due to this Program, is also unreasonable. The Commission did, however, allow the
ORDER NO. 29103
Company to recover its actual costs (including interest) for purchasing load reductions from its
irrigation customers ($74 million).
Our finding is also consistent with our prior conservation and DSM Orders that deny
the recovery of lost revenue. See Order Nos. 25062, 25122 & 25640. The Commission also
finds that in the context of the electric power market crisis that existed at the time, it was the
prudent if not required action for the Company to develop programs to conserve and reduce
consumption of expensive power. In fact, the Commission has always believed that cost-
effective DSM resources are generally least-cost resources and they are of significant value to
the Company, its shareholders, its customers and to the general community. To not acquire such
resources merely because the Company may lose some sales of power might constitute
imprudence. Accordingly, we expect Idaho Power and all utilities in this State to operate
efficiently in the long-term best interests of their shareholders and customers.
3. Confiscation
Idaho Power argues that Order No. 28992 results in confiscation and ultimately rates
that are confiscatory. However, the Company does not articulate how our Order is confiscatory.
We affirm our decision that it is not appropriate for Idaho Power to recover revenue
for energy it did not sell to its customers in this Program. In general, though, the question is
whether our denial of the recovery of lost revenue causes rates currently in place to be
confiscatory. On this question the complainant has the burden of proof. Petition of the
Mountain States Telephone and Telegraph Company, 76 Idaho 474, 480, 284 P.2d 681 , 683-
(1955) citing Los Angeles Gas Electric Corp. v. Rail Commission 289 U.S. 287, 53 S.Ct. 637
643 , 77 LEd. 1180 (1933). In Duquesne Light Co. v. Barasch 488 U.S. 299, 109 S.Ct. 609, 102
LEd.2d 646 (1989) the Supreme Court restated the constitutional parameters of ratesetting for
public utilities under the Takings Clause of the Fifth Amendment of the United States
Constitution:
The guiding principle has been that the Constitution protects utilities from
being limited to a charge for their property serving the public, which is so
unjust" as to be confiscatory. If the rate does not afford sufficient
compensation, the State has taken the use of utility property without paying
just compensation and so violated the Fifth and Fourteenth Amendments.
4 Indeed the Company did not offer evidence that the Commission
s decision on the single issue of lost revenue
resulted in the Company s failure to earn its authorized rate of return.
ORDER NO. 29103
288 US. at 307-, 109 S.Ct. at 615-, 102 LEd.2d at 657. See also Hayden Pines Water
Company v. Idaho Public Utilities Commission 122 Idaho 356 358 834 P.2d 873 (1992).
If the Company s confiscation argument rests solely on the mistaken belief that we
previously approved the recovery of lost revenue it must fail. As stated previously, we did not
through any Order approve the recovery of these alleged costs. Furthermore, we must reiterate
that it would be unreasonable to allow the Company to recover these amounts in the context of
the drought and crisis in the regional power market that existed at that time. We must also find
that the Company has failed to specifically allege on what grounds Order No. 28992 violates
either the Takings Clause of the Idaho or United States Constitutions. Accordingly, we find the
Company s confiscation argument without merit.
D. Demand-Side Management Programs and Recovery of all Costs
Finally, Idaho Power requests that the Commission modify Order No. 28992 to
provide that in determining the cost effectiveness of any future DSM program, the Company is
entitled to recover all costs that it would incur, including lost revenue.
We find that the Company s request is beyond the scope of this case and has been
raised for the first time by the Company s Petition for Reconsideration. The Company
Application did not request this authorization as shown in the concluding paragraph:
WHEREFORE, Idaho Power Company respectfully requests (1) that the
Commission issue its order approving the methodology for the calculation of
the reduced revenue as a result of the Irrigation Load Reduction Program, and
(2) for an order approving the costs to be included in the 200212003 PCA year
for the Irrigation Load Reduction Program. . . . The Company further requests
authority to supplement its filing in this proceeding as additional costs are
incurred in the year 2002 for the Irrigation Load Reduction Program(.
Application at 5-6. Thus, in both cases, Case No. IPC-01-34 and Case No. IPC-01-, we
were only examining the Irrigation Program and its costs. We were not requested to nor did we
consider the broader question that Idaho Power now raises in its Petition-the treatment of costs
(including lost revenue) from the operation of future DSM and conservation programs.5 Our
decision was limited to the facts and circumstances of this case. Thus, our decision to deny the
Company s request to recover lost revenue does not predetermine that recovery of lost revenue is
5 However, in Case No. IPC-01-34 we did authorize Idaho Power to recover the direct costs associated with the
Astaris Load Reduction Program. See Order No. 28992 at 8-
ORDER NO. 29103
never appropriate in future DSM and conservation programs.Furthermore, because this
argument was not raised in the Company s Application interested persons and parties were not
properly given notice that this would be an issue in this case.6 Thus, we find that to consider this
argument without providing notice to all possible interested persons and parties might constitute
a violation of due process. Based on these reasons, we find that Idaho Power s argument is
without merit.
In the alternative, we find Idaho Power s position on this issue fundamentally
inconsistent with the regulatory scheme under which it operates. The Company essentially
requests that we prejudge the reasonableness and prudency of the costs that it alleges will be
incurred through any future DSM or conservation program.Granting such approval would
eliminate our review of costs and give the Company a "blank check" to recover them, whether
prudently incurred or not. The Commission will not tie its hands by granting such a request. To
do so would ignore our duties as delegated to us by the Idaho Legislature. We must evaluate
each case and DSM program with its associated benefits and costs on its own merits. This can
only be done at the time a particular program is brought to the Commission for its review.
Based on the foregoing, the Commission denies Idaho Power s request to amend our
Order No. 28992. Our finding is consistent with the Commission s position on this matter in the
past. See Order No. 22299.
CONCLUSION
Based on the foregoing, we find that our decision in Order No. 28992 to deny Idaho
Power the authorization to recover lost revenue from operation of the Irrigation Load Reduction
Program during 2001 was not unreasonable, unlawful, erroneous or unduly discriminatory. We
also find that Order No. 28992 conforms with the facts of record and/or applicable law.
Furthermore, the Commission does not find that the denial of the recovery of lost revenue results
in confiscatory rates. The Commission also finds that Order No. 28992 is not an unlawful
collateral attack on Order No. 28699. Finally, we decline to modify our Order to provide that
6 As this case was processed by Modified Procedure the Commission must provide notice of the issues presented in
the proceeding and a summary of the moving party s justification for the proposed changes and its position. IDAP
31.01.01.202. Notice of Idaho Power s new argument was not issued to all interested persons and parties through
Order No. 28893.
7 Idaho Power s argument assumes that we consider lost revenue to be a cost. As we stated previously, at least for
purposes of this case we do not consider lost revenue to be an actual cost in this case.
ORDER NO. 29103
Idaho Power is entitled to recover all "costs" that it would incur as a result of the implementation
of any demand-side management program.
ORDER
IT IS HEREBY ORDERED that Idaho Power Company Petition for
Reconsideration is denied.
THIS IS A FINAL ORDER ON RECONSIDERATION. Any party aggrieved by this
Order or other final or interlocutory Orders previously issued in this Case No. IPC-01-34 may
appeal to the Supreme Court of Idaho pursuant to the Public Utilities Law and the Idaho
Appellate Rules. See Idaho Code ~ 61-627.
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this :;"9
day of August 2002.
i2LAUL KJi L DER, PRESIDENT
~4-~~J f/.
~: ~
ARSHA H. SMITH, COMMISS'rbNER
ATTEST:
Commission Secretary
O:IPCEO 134 jh4
ORDER NO. 29103