HomeMy WebLinkAbout200207032002 IRP.pdf
Idaho Power Company
2002 Integrated Resource Plan
June 2002
Idaho Power Company
2002 Integrated Resource Plan
Table of Contents
1. Integrated Resource Plan Summary ..........................................................................................1
Introduction ...............................................................................................................................................1
Risk Management......................................................................................................................................1
Load Forecast ............................................................................................................................................2
Resource Adequacy...................................................................................................................................2
Future Resource Options...........................................................................................................................4
Near-Term Action Plan .............................................................................................................................5
2. Load Forecast............................................................................................................................9
Load Growth .............................................................................................................................................9
Term Off-System Sales ...........................................................................................................................11
Energy Efficiency and Demand-Side Management ................................................................................11
3. Existing and Planned Resources.............................................................................................. 15
Hydroelectric Generating Resources.......................................................................................................15
Thermal Generating Resources ...............................................................................................................18
Purchased & Exchanged Generating Resources......................................................................................18
Transmission Resources..........................................................................................................................19
4. Adequacy of Existing and Planned Resources.........................................................................25
Water Planning Criteria for Resource Adequacy ....................................................................................26
Planning Scenarios ..................................................................................................................................27
5. Future Resource Options.........................................................................................................35
Purchased and Exchanged Generation ....................................................................................................35
Generating Resources..............................................................................................................................38
Hydroelectric Generating Resources.......................................................................................................39
Thermal Generating Resources ...............................................................................................................39
Thermal Technologies.............................................................................................................................42
Advanced Technologies ..........................................................................................................................43
Demand-Side Measures and Pricing Options..........................................................................................46
Societal Costs ..........................................................................................................................................47
6. Ten-Year Resource Plan ..........................................................................................................49
Overview .................................................................................................................................................49
Resource Strategies .................................................................................................................................49
Strategy Selection....................................................................................................................................54
Least-Cost Resource Plan........................................................................................................................57
7. Near-Term Action Plan............................................................................................................61
Introduction .............................................................................................................................................61
Near-Term Action Plan ...........................................................................................................................61
Market Purchases ....................................................................................................................................61
Generation Resources..............................................................................................................................62
Transmission Resources..........................................................................................................................62
Demand-Side Management, Energy Conservation, and Pricing Options ...............................................63
Green Energy...........................................................................................................................................63
Appendices:
Appendix A 2002 Economic Forecast
Appendix B 2002 Sales and Load Forecast
Appendix C 2002 Conservation Plan
Technical Appendix
Glossary of Acronyms
AEO – Annual Energy Outlook
AIR – Additional Information Requests
aMW – Average Megawatt
APS – Arizona Public Service
BPA – Bonneville Power Administration
CCCT – Combined-Cycle Combustion Turbine
CO2 – Carbon Dioxide
CT – Combustion Turbine
DOE – Department of Energy
DG – Distributed Generation
DSM – Demand-Side Management
EA – Environmental Assessment
EIA – Energy Information Administration
FERC – Federal Energy Regulatory Commission
HP/IP – High Pressure/Intermediate Pressure
IOU – Investor-Owned Utility
IPC – Idaho Power Company
IPUC – Idaho Public Utilities Commission
IRP – Integrated Resource Plan
kV – Kilovolt
kWh – Kilowatt hour
LIWA – Low-Income Weatherization Assistance
MMBTU – Million British Thermal Units
MW – Megawatt
MWh – Megawatt hour
NEEA – Northwest Energy Efficiency Alliance
NWPPC – Northwest Power Planning Council
NOx – Nitrogen Oxides
NYMEX – New York Mercantile Exchange
OPUC – Oregon Public Utility Commission
PM&E – Protection, Mitigation and Enhancement
PV – Photovoltaic
QF – Qualifying Facility
RFP – Request for Proposal
RTO – Regional Transmission Organization
SCCT – Simple-Cycle Combustion Turbine
SO2 – Sulfur Dioxide
SWIP – Southwest Intertie Project
TSP – Total Suspended Particulates
WACC – Weighted Average Cost of Capital
WEFA – Wharton Econometrics Forecast Associates
WECC – Western Electricity Coordinating Council
1. Integrated Resource Plan Summary
2. Ensure that resources selected are
cost-effective, low risk, and meet the
increasing electrical energy demands
of our customers.
Introduction
The 2002 Integrated Resource Plan
(IRP) is Idaho Power Company’s (IPC or
the Company) sixth resource plan prepared
to fulfill the regulatory requirements and
guidelines established by the Idaho Public
Utilities Commission (IPUC) and the
Oregon Public Utility Commission (OPUC).
The number of households in the
Idaho Power Company service territory is
expected to increase from around 310,000
today to nearly 380,000 by the end of the
planning period in 2011. Population growth
in Southern Idaho is an inescapable fact, and
IPC will need physical resources to meet the
electrical energy demands of the additional
customers.
Prior to submission of the 2002
Integrated Resource Plan, two sets of public
meetings were held. The first set of
meetings solicited comments regarding
water-planning criterion. Previous IRPs
used median, or normal, stream flows for
resource planning. The second set of public
meetings followed the release of the draft
version of the plan. In addition, written
comments were solicited from the public at
both stages.
Idaho Power Company has an
obligation to serve customer loads
regardless of the water conditions that may
occur. In light of public input to the
planning process, IPC will emphasize a
resource plan based upon a worse-than-
median level of water. In the 2002 resource
plan, IPC is emphasizing the 70th percentile
water conditions and 70th percentile load
conditions for resource planning. The
water-planning criteria are discussed further
in Chapter 4.
Based on legislative actions in
Oregon and Idaho, the 2002 Integrated
Resource Plan assumes that during the
planning period, from 2002 through 2011,
Idaho Power will continue to be responsible
for acquiring sufficient resources to serve all
of its customers in its Idaho and Oregon
certificated service areas and will continue
to operate as a vertically-integrated electric
utility. It is the intent that neither the
Company nor its customers will be
disadvantaged by decisions made in
accordance with the 2002 Integrated
Resource Plan.
Risk Management
Idaho Power, in conjunction with
the IPUC staff and interested customer
groups, developed a risk management policy
during 2001 to protect against severe
movements in the Company’s Power Cost
Adjustment (PCA) balance. The risk
management policy is primarily aimed at
managing short-term market purchases and
hedging strategies. The policy is intended to
supplement the existing IRP process. In
summary, the IRP will be the forum for
making long-term resource decisions while
the risk management policy will address the
The two primary goals of the 2002
Integrated Resource Plan are to:
1. Maintain Idaho Power’s ability to
reliably serve the growing demand
for electricity within the service
territory throughout the 10-year
planning period.
Chapter 1 1 Plan Summary
short-term resource decisions that arise as
resources, loads, costs of service, market
conditions, and weather vary.
Load Forecast
The 2002 Sales and Load Forecast
includes three forecasts defining possible
load conditions in the Idaho Power service
territory during the 2002 through 2011
planning period.
The expected load forecast assumes
median temperatures and median
precipitation. Since actual loads can vary
significantly dependent upon weather
conditions, two alternative scenarios are also
considered.
A 70th percentile load forecast and
90th percentile load forecast were prepared
to address the weather risk and uncertainty
inherent in forecasting loads. The 70th
percentile load assumes a level of monthly
loads that are not likely to be exceeded 70
percent of the time. However, the 70th
percentile load forecast is expected to be
exceeded 3 out of 10 years, or 30 percent of
the time.
The 90th percentile load forecast
assumes monthly loads that are not likely to
be exceeded 90 percent of the time.
However, the 90th percentile load forecast is
expected to be exceeded in 1 out of 10 years,
or 10 percent of the time.
The three forecasts are discussed
further in Chapter 2 and in Appendix B,
2002 Sales and Load Forecast.
Resource Adequacy
In the Integrated Resource Plan
modeling process, monthly demand and
energy requirements from the 2002 Sales
and Load Forecast are compared throughout
the planning period against the generating
capability of Idaho Power’s power supply
system. The comparison reveals Idaho
Power’s future need for additional capacity
and energy resources.
Idaho Power has determined that
existing resources, as described in Chapter
3, are likely to be insufficient to meet
expected peak energy requirements under
the 70th percentile load and water conditions
as early as 2003. Under the 70th percentile
water and load conditions, projected peak-
hour loads may cause peak-hour
transmission overloads from the Pacific
Northwest presenting significant difficulties
during the summers of 2003 and 2004. A
combination of purchases from the east side,
demand reduction programs, and temporary
generation resources may be required to
meet the projected summer peak-hour loads
in 2003 and 2004.
Idaho Power Company recognizes
that capacity constraints may present
significant difficulties during the summer
peak-hour conditions. IPC is addressing the
potential difficulties (transmission
overloads) projected for the summers of
2003 and beyond by pursuing several
strategies that will enhance IPC’s ability to
serve projected loads without encountering
transmission overloads from the Pacific
Northwest. The strategies include:
1. Making firm purchases for the
system (possibly sourced from areas
other than the Pacific Northwest)
while simultaneously making a non-
firm off-system sale. This provides
Idaho Power with the ability to
interrupt the non-firm sale during
critical peak-hour conditions.
2. Accelerating construction of the
Brownlee to Oxbow Number 2
transmission line. The transmission
deficiencies illustrated in Figure 17
Chapter 1 2 Plan Summary
assume the line is available summer
of 2005. IPC is considering
accelerating construction of the
project to have the transmission
available summer of 2004.
3. Idaho Power plans to continue
investigating opportunities for cost-
effective power exchanges as a
method to manage projected
surpluses and deficiencies. For
example, the existing Montana
exchange ends in December of 2003
– if an agreement similar to the
current agreement was in place for
summer 2004, the projected
transmission overload from the
Pacific Northwest projected for July
would be reduced by 75 MW. Idaho
Power has already contacted
Northwestern Energy to discuss this
opportunity.
In addition to the above strategies,
Idaho Power has some short-term peaking
capability at C.J. Strike, Bliss and Lower
Salmon hydro plants that was not modeled
in the monthly peak-hour surplus and
deficiency, or the monthly peak-hour NW
transmission deficit analyses. For these
analyses, the three hydro plants were
assumed to operate at the monthly average
generation values. While the assumption
simplifies the analysis, it also understates
the important peaking capability of the
projects.
The combined peaking capacity of
these projects that is not accounted for in the
above-mentioned analyses is approximately
100 MW for a 1-hour period. The dispatch
of the plant capacity presents a complex
modeling problem. Because of the
complexity, the peaking capacity of the
plants was not included in the resource
model. However, Idaho Power Company
intends to continue to use the peaking
capacity of these plants in actual operations.
An additional 100 MW of term
market purchases in June, July, November,
and December to supplement the existing
IPC resources are planned to meet the
monthly average energy requirements
through the summer of 2011.
Contingency Plans
The energy crisis of 2001 was a
learning experience for Idaho Power.
Several of the demand reduction programs
developed during the energy crisis are
considered to be active contingency plans,
capable of being utilized again. One
example is the Energy Exchange Program.
The Energy Exchange Program enabled
industrial customers to reduce load during
certain hours in exchange for a payment
from Idaho Power. While the program is
currently inactive, the Energy Exchange
Program could be reactivated on short
notice, if necessary to respond to extreme
conditions. Other demand reduction
programs, such as the Irrigation Voluntary
Load Reduction Program can be
implemented on short notice if deemed
necessary.
Garnet Delayed
In the 2000 Integrated Resource
Plan, Idaho Power identified a need for
additional generating resources located close
to the Treasure Valley load center beginning
in June of 2004. The identified need was the
basis upon which Idaho Power issued the
request for proposals (RFP), specifying an
on-line date of June 1, 2004. The Garnet
Energy LLC proposal was selected. A
Power Purchase Agreement (PPA) between
Idaho Power Company and Garnet Energy
Chapter 1 3 Plan Summary
Market Purchases LLC was negotiated and filed with the IPUC
in December 2001. Section 4.4 of the PPA
provides Idaho Power with an option to
delay the guaranteed commercial operation
date of the Garnet facility from the currently
scheduled date of June 1, 2004 until June 1,
2005. The option exercise date was April
15, 2002.
In the 2002 IRP, Idaho Power
Company plans to use term market
purchases from the Pacific Northwest
throughout the planning period to
supplement company resources in June,
July, November, and December. The
market purchases are placed in the resource
plan in 100 MW increments. A term market
purchase implies the purchase of a specific
quantity of energy and capacity during a
specific time period. Term market
purchases are usually made prior to actual
need and not during real-time system
operation. Additionally, term market
purchases are usually for longer time periods
than are the hourly market purchases made
during real-time system operations.
To assess the cost, benefits and
prudence of the PPA for Idaho Power rate-
making purposes, the IPUC has scheduled
technical hearings in Case No. IPC-E-01-42
for late July 2002. Considering the nature of
Idaho Power’s projected deficiencies for
2004, and the hearing schedule that
commences after the Garnet delay option
expires, Idaho Power has determined that it
is prudent to delay the guaranteed
commercial operation date of the Garnet
facility until June 1, 2005. To not rely solely on long-term
market purchases beyond 2004 was
determined to be the optimum strategy
because the delivery of increased market
purchases from the Pacific Northwest would
require substantial investments in additional
transmission facilities to relieve constraints
on Idaho Power’s transmission system.
However, term market purchases remain an
important aspect of resource planning,
allowing efficient timing of new resources
as well as efficient use of existing resources.
Transmission constraints are discussed more
thoroughly in Chapter 3.
Idaho Power’s decision to delay the
commercial operation date of the Garnet
facility until June 1, 2005, will present
several near-term challenges that will need
to be addressed if a low-water and high-load
condition occurs in 2004.
Future Resource Options
Beginning in June 2005, additional
permanent resources will be required to
meet Idaho Power Company’s service
territory load requirements. Idaho Power
Company has three options available to meet
the projected resource requirements:
Generation and Transmission
Resources
Generic generating resources using
currently available technologies, including
gas-fired and coal-fired thermal generation,
renewable resource technologies such as
hydropower, solar, geothermal, wind power,
and generation from fuel cells, were
considered as potential resources for
inclusion in the 2002 Integrated Resource
Plan. One of the technologies, a 100 or 200
MW simple-cycle gas-fired combustion
1. Market purchases.
2. Generation and transmission
resources.
3. Targeted demand-side management,
targeted conservation measures, and
pricing options.
Chapter 1 4 Plan Summary
turbine, was selected as the core supply-side
resource for the third and fourth resource
strategies in the final evaluation. A 64 MW
upgrade to the Shoshone Falls plant is part
of each resource strategy.
The 2002 Integrated Resource Plan
incorporates the planned addition of a new
10-mile 230 kV transmission line between
Brownlee and Oxbow. The Brownlee-
Oxbow upgrade is expected to add 100 MW
of transmission capacity. The transmission
upgrade is planned to be in service by the
fall of 2004.
Demand-Side Management and
Targeted Conservation Measures
Due to the nature and timing of
projected energy deficits and transmission
overloads, conservation and demand-side
measures must be carefully targeted to cost-
effectively address the projected deficits. If
the Idaho PUC approves the Company’s
proposed conservation rider, Idaho Power
Company anticipates the addition of targeted
demand-side management and targeted
energy conservation programs.
Idaho Power Company plans to
continue supporting regional and local
conservation efforts, including NEEA.
Participation in regional and local
conservation efforts is contingent upon
committed funding. Idaho Power Company
will also proceed with plans to improve
energy efficiency at other company
facilities. Although not specifically
identified in the Resource Strategies or the
Near-Term Action Plan, Idaho Power will
continue cost-effective incremental
efficiency upgrades to existing generation
facilities.
Four Resource Strategies Analyzed
Idaho Power’s resource options for
the planning period are described in Chapter
5. To meet the forecast loads in a cost-
efficient manner throughout the 10-year
planning period, IPC considered multiple
resource acquisition strategies. The
strategies included increased monthly
energy and capacity purchases from the
Pacific Northwest power market to meet
seasonal deficiencies and the acquisition of
additional generating capability from a
portfolio of various generation technologies.
Each resource strategy includes upgrading
the Oxbow to Brownlee transmission path
adding 100 MW of import capacity from the
Pacific Northwest. Four strategies are being
considered for final analysis and review:
1. The first resource strategy is a long-
term limited-quantity market
purchase strategy.
2. The second resource strategy is a
combination of long-term market
purchases of varying quantities and a
64 MW facility upgrade to the
existing Shoshone Falls hydro plant.
3. The third resource strategy is a
combination of short-term limited-
quantity market purchases, the
acquisition of 200 MW of peaking
resources and a 64 MW facility
upgrade at Shoshone Falls.
4. The fourth resource strategy is a
combination of long-term limited-
quantity market purchases, the
acquisition of 100 MW of peaking
resources and a 64 MW facility
upgrade at Shoshone Falls.
The portfolio of resources is fully described
in the Near-Term Action Plan (Chapter 7).
Near-Term Action Plan
Customer growth is the primary
driving force behind Idaho Power
Company’s need for additional resources.
Population growth throughout Southern
Chapter 1 5 Plan Summary
Idaho and, specifically, in the Treasure
Valley requires additional measures to meet
both peak and electrical energy needs.
Over the past 85 years, Idaho Power
Company has developed a portfolio of
generation resources. The Company
believes that a blended approach based on a
portfolio of options is the most cost-
effective and least-risk method of addressing
increasing energy demands of Idaho Power
customers.
Because of the short duration of the
forecast peak load conditions, Idaho Power
has identified a resource strategy using both
supply-side and demand-side measures.
Idaho Power believes that the following
plan, which outlines a balanced approach,
has a high probability of being the least
expensive for Idaho Power’s customers.
The plan is based on Strategy 4, a
combination of limited long-term market
purchases and generation additions. The
plan also calls for a transmission upgrade,
along with an investigation into demand
reduction measures suitable to address the
short duration of projected peak-hour
transmission overloads.
In summary, Idaho Power has
identified six items to address the resource
needs in the Near-Term Action Plan:
First, Idaho Power Company plans to
continue to make seasonal market purchases
of 100 aMW in the months of June, July,
November and December throughout the
planning period.
Second, Idaho Power Company
plans to integrate demand-side measures,
where economical, to address the short
duration peaks of the system load.
Third, Idaho Power Company plans
to solicit proposals and initiate the siting and
permitting for approximately 100 MW of a
utility-owned and operated peaking resource
to be available beginning in 2005.
Fourth, assuming the Idaho PUC
approves the Garnet Power Purchase
Agreement, Idaho Power will purchase up to
250 MW of capacity and associated energy
during periods of peak need beginning June
1, 2005.
Fifth, Idaho Power Company plans
to proceed with the Brownlee to Oxbow
transmission line, expecting the project to be
in-service in 2005 and increasing the import
capabilities from the Pacific Northwest.
Sixth, Idaho Power Company plans
to proceed with the Shoshone Falls upgrade
project, expecting the upgrade to be in-
service in 2007.
Finally, Idaho Power Company plans
to informally reassess the deficiencies that
remain in 2008 though 2011 prior to 2004.
The deficiencies will be formally assessed in
the 2004 IRP.
Additional Steps
Idaho Power Company supports the
Green Power Program. In order to meet the
needs of customers desiring Green Energy,
IPC has identified two specific near-term
actions to be initiated during the next two
years:
1. Idaho Power anticipates participating
in several educational and
demonstrational energy projects with
a focus on green resources.
2. Idaho Power intends to dedicate up to
$50,000 to explore the feasibility of
constructing a pilot anaerobic
digester project within the IPC
service territory.
Idaho Power Company and the
Commissions must agree on mechanisms
that insure prompt recovery of prudent costs
Chapter 1 6 Plan Summary
incurred for the pilot and demonstration
projects.
Although not specifically identified
in the Four Resource Strategies or in the
Near-Term Action Plan, Idaho Power will
continue to pursue cost-effective
incremental upgrades at existing generation
facilities.
Consistent with the final Risk
Management Policy under review in Case
No. IPC-E-01-16, Idaho Power Company
will continue to use the short-term regional
market to balance system load and
generation, as well as take advantage of the
long-term energy market to secure energy at
reasonable prices.
Idaho Power Company continually
works to improve the resource planning
process. Idaho Power has recently made
organizational changes to further improve
integrated resource planning. The Company
agrees with the IPUC that integrated
resource planning will continue to be an
important and ongoing activity at Idaho
Power Company.
Chapter 1 7 Plan Summary
Chapter 1 8 Plan Summary
2. Load Forecast
Load Growth
Future demand for electricity by
customers in Idaho Power Company’s
service territory is represented by three load
forecasts, which reflect a range of load
uncertainty. Table 1 summarizes the three
forecasts of Idaho Power’s annual total load
growth during the planning period. The
forecast 10-year average annual growth rate
in the expected load forecast is 2.3 percent.
The expected load forecast
represents the most probable projection of
service territory load growth during the
planning period. The forecast for total load
growth is determined by summing the load
forecasts for individual classes of service, as
more particularly described in Appendix B,
2002 Sales and Load Forecast. For
example, the expected total load growth of
2.3 percent is comprised of residential loads
growth of 2.4 percent, commercial loads
growth of 4.1 percent, irrigation loads
growth of 0.4 percent, industrial loads
growth of 2.4 percent, and additional firm
loads growth of 2.2 percent.
Economic growth assumptions
influence the individual customer-class
forecasts. The number of households and
employment projections, along with
customer consumption patterns, are used to
form load projections. Economic growth
information for Idaho and its counties can be
found in Appendix A, 2002 Economic
Forecast.
The number of households in the
State of Idaho is projected to grow at an
annual average rate of 2.1 percent during the
10-year forecast period. Growth in the
number of households within individual
counties in Idaho Power’s service area
differs from statewide household growth
patterns. Service area household projections
are derived from individual county
household forecasts. Growth in the number
of households within the Idaho Power
service territory, combined with reduced
consumption per household, results in the
previously mentioned 2.4 percent residential
load growth rate.
The expected case load forecast
assumes median temperatures and median
precipitation; i.e., there is a 50 percent
chance that loads will be higher or lower
than the expected forecast loads due to
colder-than-median or hotter-than-median
temperatures or wetter-than-median or drier-
than-median precipitation.
Since actual customer loads can
vary significantly dependent upon weather
conditions, two alternative scenarios were
considered that address load variability due
to weather. IPC has generated load forecasts
for 70th percentile weather and 90th
percentile weather. 70th percentile weather
means that in seven out of 10 years, the load
is expected to be less than the forecast and
in three out of 10 years, the load is expected
to exceed the forecast. 90th percentile load
has a similar definition.
Cold winter days create high heating
load. Hot, dry summers create both high-
cooling and high-irrigation loads. In the
winter, maximum load occurs with the
highest recorded levels of heating degree
days (HDD). In the summer, maximum load
occurs with highest recorded levels of
cooling and growing degree days (CDD and
GDD). Heating degree days, cooling degree
days, and growing degree days are used by
IPC to quantify the weather and estimate a
load forecast.
Chapter 2 9 Load Forecast
Table 1 Idaho Power Company
Range of Load Growth Forecasts
Average Megawatts
Forecast 2002 2004 2006 2008 2010 2012 Avg Annual
Growth Rate
90th Percentile Load 1,818 1,889 2,003 2,091 2,174 2,261 2.2%
70th Percentile Load 1,753 1,821 1,933 2,018 2,099 2,183 2.2%
50th Percentile Load
(Expected or Median)
1,714 1,781 1,892 1,976 2,056 2,139 2.2%
Idaho Power loads are highly
dependent upon weather. The three
scenarios allow careful examination of load
variability and how the load variability may
impact resource requirements. It is
important to understand that the
probabilities associated with the load
forecasts apply to any given month and that
an extreme month may not necessarily be
followed by another extreme month. In fact,
a normal year likely contains extreme
months as well as mild months.
For example, at the Boise Weather
Service Office, the median number of HDD
in December over the 1964-2000 time
period is 1,039 HDD. The coldest
December over the same time period was
December 1995 when there were 1,619
HDD recorded at Boise.
For December, the 70th percentile
HDD is 1,079 HDD. The 70th percentile
value is likely to be exceeded in three out of
10 years on average. The 90th percentile
HDD is 1,278 HDD and is likely to be
exceeded in one out of 10 years on average.
Percentile estimation was used in each
month throughout the year for the weather-
sensitive customer classes - residential,
commercial, and irrigation - to forecast load.
Astaris Load
The Astaris elemental phosphorous
plant temporarily ceased production at the
end of 2001. Because of the change in its
business situation, Astaris is expected to
only require 10 MW per month for on-going
maintenance. The 10 MW is included as a
firm load requirement of Idaho Power. The
Astaris special contract with Idaho Power
will expire in March 2003, at which time
Astaris is expected to become a Schedule 19
industrial customer. The Astaris contract
allows for up to 240 MW of load and, until
Astaris notifies Idaho Power of changes to
the contract, IPC must consider the
possibility of up to 240 MW of Astaris load.
Until recently, Astaris had been IPC’s
largest individual customer.
In the 70th percentile residential and
commercial load forecasts, temperatures in
each month were assumed to be at the 70th
percentile of HDD in winter and at the 70th
percentile of CDD in the summer. In the
70th percentile irrigation load forecast, GDD
were assumed at the 70th percentile and
precipitation was assumed to be at the 70th
percentile, reflecting weather that is both
hotter and drier than median weather. The
90th percentile irrigation load forecast was
similarly constructed using weather values
measured at the 90th percentile.
Chapter 2 10 Load Forecast
Table 2 Idaho Power Company
Term Off-System Sales
Contract Expiration 2002 Average Load
Washington City June 2002 2 aMW
City of Weiser December 2002 6 aMW
Utah Associated Municipal Power Systems December 2003 40 aMW
City of Colton May 2005 3 aMW
Raft River Rural Electric Cooperative September 2006 6 aMW
Total Term Sales 57 aMW
Term Off-System Sales
Idaho Power currently has five term
off-system sales contracts. Most of the five
contracts were entered into in the late 1980s
or early 1990s when Idaho Power had an
energy and capacity surplus. The contracts,
expiration dates, and average sales amounts
are shown in Table 2.
The term sales contract with the
City of Weiser is a full-requirements
contract with Idaho Power. Under a full-
requirements contract, Idaho Power is
responsible for supplying the entire load of
the City. The City of Weiser is located
entirely within Idaho Power’s load-control
area.
A term sales contract with Raft
River Rural Electric Cooperative Inc. was
established as a full-requirements contract
after being approved by the Federal Energy
Regulatory Commission (FERC) and the
Public Utilities Commission of Nevada.
Raft River Rural Electric Cooperative Inc. is
the electric distribution utility serving Idaho
Power’s former customers in the State of
Nevada. Idaho Power sold the transmission
and distribution facilities, along with the
rights-of-way that serve about 1,250
customers in Northern Nevada and 90
customers in Southern Owyhee County, to
Raft River Rural Electric Cooperative Inc.
The closing date of the transaction was April
2, 2001. The area sold to Raft River Rural
Electric Cooperative Inc. is located entirely
within Idaho Power’s load-control area.
Idaho Power Company recently
notified the City of Colton that IPC intends
to terminate the contract at the end of May
in 2005. Contract termination requires
three-year advance notification and can be
initiated by either party. Peak and energy
forecasts used in the IRP assumed
termination of the Colton contract at the end
of June 2004.
As shown in Table 2, most of the
term off-system sales contracts are
scheduled to end by the end of 2003. Idaho
Power will continue to evaluate the value of
term off-system sales, but with the
exceptions of the City of Weiser and Raft
River Rural Electric Cooperative Inc., Idaho
Power has not included the renewal of any
term off-system sales contracts in its load
projections.
Energy Efficiency and Demand-
Side Management
In response to IPUC Order No.
28722, Idaho Power filed a comprehensive
Demand-Side Management (DSM) program
on July 31, 2001. The filing proposed a ½
Chapter 2 11 Load Forecast
percent charge applied to all customer
classes to fund new DSM programs. The
proposed charge was to be included as a
rider on customer bills. A list of program
options that could be implemented with
DSM funding was included as part of the
filing. Idaho Power Company also proposed
developing an Energy Efficiency Advisory
Group to assist with selecting and evaluating
DSM programs if the rider charge for
conservation funding is approved. On
November 21, 2001, in Order No. 28894,
the Idaho Commission postponed
consideration of DSM funding until the
2002 PCA filing in April 2002.
The energy conservation
improvements attributable to past
participation in Idaho Power’s DSM
programs are reflected in the actual
measured loads of recent years and
throughout the forecast of projected loads
for future years in the planning period.
Idaho Power Company’s most
current reports to the IPUC and the OPUC
regarding DSM programs are attached
hereto as Appendix C, 2002 Conservation
Plan.
Northwest Energy Efficiency Alliance
The Northwest Energy Efficiency
Alliance mission is to promote market
transformation to energy efficient products
and services in the Pacific Northwest. Idaho
Power is one of six investor-owned utilities
and eight public utilities that provide
funding in the region. Idaho Power’s
continuing commitment to the Alliance is
dependent upon regulatory approval of cost
recovery.
The Northwest Energy Efficiency
Alliance conducts activities such as market
research, technology assessment, planning,
and brokering collaborations. In addition,
the Alliance administers demonstration
programs, targets market interventions,
develops infrastructures to assist market
transformations, and disseminates
information. To ensure the effectiveness of
its efforts, the Alliance conducts a
comprehensive evaluation of each of the
projects.
Idaho Power has entered into a
Memorandum of Agreement to fund the
Northwest Energy Efficiency Alliance
through 2004. For that period, Idaho
Power’s system-wide contribution is
estimated to be $1.3 million annually out of
an annual Alliance budget of $20 million.
The $1.3 million requested contribution is
less than the $1.7 million annually that
Idaho Power was previously contributing to
the Alliance. Idaho Power Company is
hopeful that the public utility commissions
of Idaho and Oregon will support the
funding request.
Idaho Power supports and
complements the Alliance activities in its
retail service territory in the states of Oregon
and Idaho. Due to the small size of the
Oregon retail service territory compared to
the Idaho retail service territory, most of the
costs for participation in the Alliance have
been allocated to the Idaho retail service
territory. For the same reason, the Idaho
Public Utilities Commission has been the
primary agency that the Company has
looked to for authorization to participate in
the Northwest Energy Efficiency Alliance.
Idaho Power Company has recently obtained
approval from the IPUC for continued
participation in the Alliance through the year
2004. The OPUC has consistently
expressed its support of the Company’s
participation in the Alliance by providing
funding from Idaho Power’s Oregon
customers.
Chapter 2 12 Load Forecast
Public-Purpose Programs Northwest Power Planning Council
Regional Efficiency
Low-Income Weatherization Assistance The Northwest Power Planning
Council (NWPPC) has a conservation goal
of 300 aMW within three years. The
NWPPC suggests that IPC can contribute
80,160 MWh, or just over 9 aMW, to the
effort. Idaho Power Company intends to
meet the NWPPC goal through a
combination of customer and company
conservation. Idaho Power Company has a
variety of large facilities, including offices,
maintenance shops, generation facilities, and
distribution and transmission facilities.
Conservation at the various IPC facilities is
expected to make a significant contribution
to the Northwest Power Planning Council
conservation goal.
Low-Income Weatherization
Assistance (LIWA) is a public-purpose
program to make weatherization services
more affordable for low-income customers.
Payments are made to local non-profit
agencies participating in state-run
weatherization programs in Idaho and
Oregon to supplement federal funding. In
Idaho, the program is fuel-blind and allows
payments for some health and safety
measures, as well as weatherization. In
Oregon, all dwellings must be electrically
heated and all measures must provide cost-
effective electricity savings to be eligible for
funding. Idaho Power typically contributes
50 percent of the cost for qualifying
measures, plus a $75 administration fee, per
dwelling. The program also funds
weatherization of buildings occupied by tax-
exempt organizations.
BPA Conservation and Renewable
Discount Program
Under the Bonneville Power
Administration (BPA) residential exchange
program, Idaho Power is eligible to
participate in the Conservation and
Renewable Discount Program (C&RD).
The C&RD is a credit that is made available
to Idaho Power in order to further
conservation and renewable development in
the region. Idaho Power can spend up to
$525,000 per year on qualified expenditures
through 2004. Qualified expenditures are
specified by BPA.
Oregon Commercial Audit Program
The Oregon Commercial Audit
Program is a statutory program specifying
that all commercial building customers be
notified every year that information
regarding energy-saving operations and
maintenance measures is available and that
commercial energy-audit services can be
provided. The audit services are normally
provided at no charge to the customer.
Customers using more than 4,000 kWh per
month may receive a more detailed audit but
may be required to pay a portion of the cost.
Idaho Power allocates the C&RD
credit to residential conservation programs.
During the winter of 2001-2002, 14,000
energy efficiency packets were distributed to
lower income or high electrical usage
customers. Each packet included energy
efficiency information and an Energy Star
compact fluorescent bulb as an example of
energy conservation. Future programs using
C&RD funding are in planning stages.
Oregon Residential Weatherization
The Oregon Residential
Weatherization Program is a statutory
requirement program specifying annual
notification to all residential customers
informing them how to obtain energy audits
and financing for energy conservation
Chapter 2 13 Load Forecast
measures. To qualify for an Idaho Power
audit or financing, customers must have
electric space heat.
Energy Efficiency Promotion
Activities
Idaho Power continues to promote
the wise, efficient, and safe use of electricity
by providing information and education at
workshops and conferences. Idaho Power
offers informational material, consulting
services, energy audits, power quality
assistance, audits, and financing to help
customers avoid energy problems.
Chapter 2 14 Load Forecast
3. Existing and Planned Resources
Hydroelectric Generating
Resources
Idaho Power operates 17
hydroelectric generating plants located on
the Snake River and its tributaries.
Together, these hydroelectric facilities
provide a total nameplate capacity of 1,707
MW and median water annual generation
equal to approximately 1,071 aMW.
The backbone of the Company’s
hydroelectric system is the Hells Canyon
Complex in the Hells Canyon reach of the
middle Snake River. The Hells Canyon
Complex consists of the Brownlee, Oxbow
and Hells Canyon dams and associated
generating facilities. The three plants
provide approximately 70 percent of IPC’s
annual hydroelectric generation and nearly
40 percent of the total energy generation.
Water storage in the Brownlee reservoir also
enables the Hells Canyon Complex to
provide the major portion of IPC’s peaking
and load-following capability.
Idaho Power’s hydroelectric
facilities upstream from Hells Canyon
include the American Falls, Milner, Twin
Falls, Shoshone Falls, Clear Lake, Thousand
Springs, Upper and Lower Malad, Upper
and Lower Salmon, Bliss, C.J. Strike, Swan
Falls and Cascade generating plants. Water
storage reservoirs at Lower Salmon, Bliss
and C.J. Strike provide for peaking
capabilities at these plants. All of the other
upstream plants utilize run-of-river stream
flow for generation.
Federal Energy Regulatory
Commission Relicensing Process
Idaho Power Company’s
hydroelectric facilities, with the exception of
the Clear Lake and Thousand Springs plants,
operate under federal licenses regulated by
the FERC. The process of relicensing Idaho
Power’s hydroelectric projects at the end of
their initial 50-year license periods is well
under way. A license renewal was granted
by FERC in 1991 for the Twin Falls project.
Applications to relicense the Company’s
three mid-Snake facilities (Upper Salmon,
Lower Salmon and Bliss) were submitted to
FERC in December 1995. The application to
relicense the Shoshone Falls project was
filed in May 1997. The application to
relicense the C.J. Strike project was filed in
November 1998. Relicensing applications
for the remaining hydroelectric facilities,
including Swan Falls, the Upper and Lower
Malad plants, and the Hells Canyon
Complex, will be prepared and submitted
during the current ten-year planning period.
The relicensing schedule for hydroelectric
projects is shown in Table 3.
Failure to relicense existing
hydropower projects at a reasonable cost
would create upward pressure on the current
low rates available to Idaho Power
customers. The relicensing process may
potentially decrease available capacity and
increase the cost of a project’s generation
through additional operating constraints and
requirements for environmental protection,
mitigation and enhancement (PM&E)
imposed as a condition for relicensing.
Idaho Power Company’s goal in relicensing
is to maintain the low cost of generation at
the hydroelectric facilities while
implementing non-power measures designed
to protect and enhance the river
environment. No reduction of the available
capacity of hydroelectric plants to be
relicensed was assumed as part of the 2002
Integrated Resource Plan. If capacity
reductions occur as a result of the process,
Chapter 3 15 Existing and Planned Resources
Table 3 Idaho Power Company
Hydropower Project Relicensing Schedule
FERC Nameplate Current File FERC
Project License Capacity License License
Number (MW) Expires Application
Bliss 1975 75 Dec 1997 Dec 1995
Lower Salmon 2061 60 Dec 1997 Dec 1995
Upper Salmon 2777 34.5 Dec 1997 Dec 1995
Shoshone Falls 2778 12.5 May 1999 May 1997
C.J. Strike 2055 82.8 Nov 2000 Nov 1998
Upper/Lower Malad 2726 21.8 July 2004 July 2002
Hells Canyon Complex 1971 1166.9 July 2005 July 2003
Swan Falls 503 25 June 2010 June 2008
then Idaho Power Company would be forced
to add other capacity resources in order to
maintain reliability.
− Involve resource agencies and the public
throughout the relicensing process for
Idaho Power’s hydroelectric projects.
Collaborative Process − Foster open exchange of views among
participants. Idaho Power is seeking to address
concerns regarding hydro generation by
working with various public and private
agencies and organizations and pursuing a
collaborative approach to the relicensing of
the hydro generation facilities. Discussions
with state and federal agencies have been
initiated to investigate ways in which the
low costs and flexibility of existing hydro
generation can be retained for the benefit of
Idaho Power customers.
− Facilitate well-defined and focused study
plans.
− Encourage agreements among
participants on the content of
applications for relicensing, on PM&E
plans and on conditions of new licenses.
− Ensure efficient use of resources and
avoid unnecessary study and process
costs.
Idaho Power has established a
collaborative team consisting of federal and
state resource agencies, tribes, regional and
local governments, non-governmental
organizations, industrial and commercial
customers, regulatory bodies and other
interested entities to actively participate with
Idaho Power by exchanging information and
providing input on components of new
license applications, including Idaho
Power’s PM&E proposals. The goals of the
collaborative process are to:
− Provide participants with more control
and certainty in the relicensing process
through better relationships with affected
entities and the public.
− Reduce the likelihood and extent of
potential litigation.
The FERC has expressed
encouragement for the collaborative process,
and FERC representatives routinely attend
the collaborative team meetings.
Chapter 3 16 Existing and Planned Resources
Salmon Recovery Program Environmental Analysis
In recent years, the movement of
water through the hydroelectric system to
assist spawning and migration of salmon has
substantially impacted the amount and
timing of hydroelectric generation. For that
reason, IPC actively monitors and
participates in regional efforts to develop a
program of actions to assist the recovery of
the endangered salmon populations.
The National Environmental Policy
Act requires that FERC perform an
environmental assessment (EA) of each
hydropower license application to determine
whether federal action will significantly
impact the quality of the natural
environment. If so, then an environmental
impact statement (EIS) must be prepared
prior to granting a new license. As part of
the EA for Idaho Power’s mid-Snake and
Shoshone Falls applications, FERC visited
Idaho during July 1997 to receive public and
agency input through scoping meetings.
FERC issued additional information requests
(AIRs) in 1998 for the mid-Snake project.
FERC also visited Idaho to receive public
and agency input at a scoping meeting held
in September 1999. FERC issued AIRs for
the C.J. Strike project in 1999. A draft EIS
was issued on the mid-Snake projects in
January 2002, and the FERC was in Idaho in
February 2002 to receive public and agency
comment. Completion of the final EIS
regarding the mid-Snake projects is
expected later in 2002.
Hydroelectric Relicensing
Uncertainties
Idaho Power Company is optimistic
that the hydro project relicensing will be
completed in a timely fashion. However,
prior experience indicates that the
relicensing process will probably result in an
increase in the costs of generation from the
relicensed projects. The increased costs are
usually associated with the requirements
imposed on the projects as a condition of
relicensing. As previously described in the
discussion of the ongoing FERC
collaborative process, Idaho Power is
currently discussing relicensing issues with
the collaborative team. Initial discussions
with members of the collaborative team
have begun concerning proposed changes in
project operations that would impact the
availability of electric energy from the
relicensed projects. Once complete, Idaho
Power will be able to better estimate the
potential impacts of the proposed
requirements on energy-generating
capability. The FERC relicensing process
then provides IPC with time to assess
proposed requirements and to develop and
present responses to the proposals. As a
result, Idaho Power cannot reasonably
estimate at this time the impact of the
relicensing process on the generating
capability of the relicensed projects. At the
time of the 2004 IRP, Idaho Power will have
FERC is currently developing an
approach to a cumulative environmental
analysis of the Snake River from Shoshone
Falls through the Hells Canyon Complex.
Once the analysis is complete, FERC will
consider recommendations from affected
state and federal agencies and issue license
orders for the affected projects, including
required PM&E measures. The process may
take from two to five years in the case of the
Shoshone Falls, Upper Salmon, Lower
Salmon and Bliss projects. Opportunity for
additional public comment will occur before
the license orders are issued. If a project’s
current license expires before a new license
has been issued, annual operating licenses
are issued by FERC pending completion of
the licensing process.
Chapter 3 17 Existing and Planned Resources
better information regarding the power
generation impacts of relicensing.
Thermal Generating Resources
Bridger
Idaho Power Company owns a one-
third share of the Jim Bridger (Bridger)
coal-fired plant located near Rock Springs,
Wyoming. The plant consists of four nearly
identical generating units. Idaho Power’s
one-third share of the generating capacity of
Bridger currently stands at 707 MW after
the upgrade of the high-
pressure/intermediate-pressure (HP/IP)
turbines on all four generating units. The
fourth unit HP/IP upgrade was completed in
June of 2000. After adjustment for
scheduled maintenance periods and
estimated forced outages and de-ratings, the
annual energy-generating capability of Idaho
Power’s share of the Bridger plant is
approximately 627 aMW.
Valmy
Idaho Power Company owns a 50
percent share, or approximately 261 MW of
capacity of the 521 MW Valmy plant
located east of Winnemucca, Nevada. The
plant, which consists of one 254 MW unit
and one 267 MW unit, is owned jointly with
Sierra Pacific Power Company. After
adjustment for scheduled maintenance
periods and estimated forced outages and
de-ratings, the annual energy-generating
capability of Idaho Power’s share of the
Valmy plant is approximately 231 aMW.
Boardman
Idaho Power owns a 10 percent
share of the 552 MW coal-fired plant near
Boardman, Oregon, operated by Portland
General Electric Company. After
adjustment for scheduled maintenance
periods and estimated forced outages and
de-ratings, the annual energy-generating
capability of Idaho Power’s share of the
Boardman plant is approximately 47 aMW.
Evander Andrews Power Complex
In addition to the three coal-fired
steam-generating plants, Idaho Power owns
and operates the Evander Andrews Power
Complex, a 90 MW natural gas-fired
combustion turbine plant and the associated
switchyard. The 12-acre complex,
constructed during the summer of 2001, is
located northwest of Mountain Home,
Idaho. The complex was named in honor of
Air Force Master Sergeant Evander
Andrews, a member of a civil engineering
squadron from Mountain Home Air Force
Base. Master Sergeant Andrews was the first
U.S. casualty of Operation Enduring
Freedom.
The Andrews Complex will operate
as needed to support system load or in
response to favorable market conditions.
Salmon Diesel
Idaho Power owns and operates two
diesel generation units located at Salmon,
Idaho. The Salmon diesels produce 5.5 MW
and are primarily operated during
emergency conditions.
Purchased & Exchanged
Generating Resources
Garnet Purchased-Power Contract
Idaho Power Company has entered
into an agreement to purchase up to 250
MW of capacity and associated energy
during periods of peak need from the Garnet
Energy LLC facility. As proposed, the
Chapter 3 18 Existing and Planned Resources
Under a similar agreement, 126,000
MWh are delivered to Seattle City Light
from November through February and
returned to Idaho Power from July through
September. Deliveries to Seattle City Light
are assumed to be 25 aMW in November
and 50 aMW in December, January and
February. Power receipts are assumed to be
100 aMW in July, 54 aMW in August and
16 aMW in September. The last transfer of
energy in the Seattle agreement occurs in
September 2002 and the last transfer of
energy in the Montana agreement occurs in
December 2003.
facility would be a nominal 250 MW natural
gas-fired combined-cycle combustion
turbine electrical generation facility capable
of expansion to a nominal 500 MW project.
The planned site for the Garnet
facility is be located in Canyon County
about 1 mile south of Middleton, Idaho, on
30 acres east of Middleton Road, south of
the south channel of the Boise River. The
location is approximately 1.25 miles north
of the future Locust Grove-Caldwell
transmission line and about 3 miles west of
the Williams Northwest natural gas pipeline.
Public Utility Regulatory Policies Act Idaho Power plans to continue
investigating opportunities for cost-effective
power exchanges as a method to manage
projected surpluses and deficiencies –
especially with the Montana Exchange
ending in December 2003. Idaho Power has
contacted Northwestern Energy to discuss
continuing an energy exchange between the
companies.
Idaho Power purchases energy from
independent power producers operating as
qualifying facilities (QF) under the Public
Utility Regulatory Policies Act of 1978, at
avoided cost rates established by the public
utility commissions of Idaho and Oregon.
The Technical Appendix lists the various QF
projects. As of December 2001, the various
QF projects were delivering 93 aMW of
power to IPC and its customers.
Additionally, properly timed
seasonal exchanges or wholesale purchases
delivered to the east side of the IPC system
will result in a direct reduction in the
number of hours of transmission deficit from
the Pacific Northwest. East side deliveries
can directly reduce the load and congestion
on the Brownlee East transmission path. For
these reasons, IPC continues to pursue cost
effective exchanges delivered to the east
side of the Idaho Power system.
Exchanges
In the past, seasonal load diversity
between Idaho Power and the rest of the
region has enabled IPC to make term power
exchanges with other regional utilities,
maximizing the utilization of IPC’s existing
generation and transmission resources.
An exchange agreement with
Montana Power Company (Northwestern
Energy) provides for the delivery to
Montana of 108,000 MWh during the three-
month period from December through
February. Deliveries are assumed to be
constant at 50 aMW. In return, Montana
Power Company delivers to Idaho 118,000
MWh during the three-month June through
August period. Power receipts are assumed
to be 10 aMW in June and 75 aMW in July
and August.
Transmission Resources
Description
The Idaho Power transmission
system is a key element serving the needs of
its retail customers. The 230 kilovolt (kV)
and higher voltage main grid system is
essential for the delivery of bulk power
supply. Figure 1 shows the principal grid
Chapter 3 19 Existing and Planned Resources
elements of Idaho Power’s high-voltage
transmission system.
Capacity and Constraints
Idaho Power Company’s
transmission connections with regional
utilities provide paths over which off-system
purchases and sales are made. The
transmission interconnections and the
associated power transfer capacities are
identified in Table 4. The capacity of a
transmission path may be less than the sum
of the individual circuit capacities. The
difference is due to a number of factors,
including load distribution, potential outage
impacts, and surrounding system limitations.
In addition to the restrictions on
interconnection capacities, there are other
internal transmission constraints that may
limit IPC’s ability to access specific energy
markets. The internal transmission paths
needed to import resources from other
utilities and their respective potential
constraints are shown in Figure 1 and Table
4.
Brownlee East Path
The Brownlee East transmission
path is on the east side of the Northwest
Interconnection shown in Table 4.
Brownlee East is comprised of the 230 kV
and 138 kV lines east of the
Brownlee/Oxbow/Quartz area and the
Summer Lake-Midpoint 500 kV line. The
constraint on the Brownlee East
transmission path is within Idaho Power’s
main transmission grid and located in the
area between Brownlee and Boise on the
west side of the system.
The Brownlee East path is most
likely to face summer constraints. The
summer constraints result from a
combination of Hells Canyon Complex
hydro generation flowing east into the
Treasure Valley, concurrent with term
transmission wheeling obligations and
purchases from the Pacific Northwest. The
term transmission also flows southeast into
and through Southern Idaho. Significant
congestion affecting southeast energy
transmission flow from the Pacific
Northwest also occurs during the months of
November and December.
The Brownlee East constraint is the
primary restriction on imports of energy
from the Pacific Northwest. If new
resources are sited west of this constraint,
additional transmission capacity will be
required to remove the existing Brownlee
East transmission constraint and deliver the
energy from the additional resources to the
Boise/Treasure Valley load area.
A new 10-mile, 230 kV line
between Brownlee and Oxbow is planned to
relieve the operating limitations at Oxbow
and Hells Canyon. The transmission
upgrade will increase the Brownlee East
capacity by approximately 100 MW, thereby
increasing IPC’s ability to import additional
energy from the Pacific Northwest for native
load use. The transmission upgrade is
expected to be completed and in service by
the fall of 2004.
Brownlee North Path
The Brownlee North path is a part of
the Northwest Interconnection and consists
of the Hells Canyon-Brownlee and Oxbow-
Brownlee 230 kV double circuit line. The
Brownlee North path is most likely to face
constraints during the summer months when
high southeast energy flows and high hydro
production levels coincide. Congestion on
the Brownlee North path also occurs during
the winter months of November and
December due to large southeast energy
transfers.
Chapter 3 20 Existing and Planned Resources
Northwest Path
The Northwest path consists of the
500 kV Summer Lake-Midpoint line, the
three 230 kV lines between the Northwest
and Brownlee, and the 115 kV
interconnection at Harney. Deliveries of
purchased power from the Pacific Northwest
often flow over these lines. During low
water conditions, total purchased power
needs may exceed the capability of the path.
If new resources are sited west of this
constraint, additional transmission capability
will be needed to transmit the energy into
the IPC control area.
Borah West Path
The Borah West transmission path is
within Idaho Power’s main grid
transmission system located west of the
Eastern Idaho, Utah Path C, Montana and
Pacific (Wyoming) interconnections shown
in Table 4. The Borah West path consists of
the 345 kV and 138 kV lines west of the
Borah/Brady/Kinport area. The Borah West
path will be of increasing concern because
the capacity of this path is fully utilized by
existing term obligations. If new resources
are constructed or acquired from sites east of
the Borah West constraint, additional
transmission facilities will need to be
constructed to transmit the energy to
customers in the Treasure Valley and Magic
Valley.
Chapter 3 21 Existing and Planned Resources
Chapter 3 22 Existing and Planned Resources
Fi
g
u
r
e
1
Id
a
h
o
P
o
w
e
r
C
o
m
p
a
n
y
T
r
a
n
s
m
i
s
s
i
o
n
S
y
s
t
e
m
Table 4 Idaho Power Company Transmission Interconnections
Transmission
Interconnections
To
Idaho
From
Idaho
Line or Transformer Connects Idaho Power To
Northwest 1,100 to 2,400 MW Oxbow - Lolo 230 kV Washington Water Power
1,200 MW Midpoint - Summer
Lake 500 kV
PacifiCorp (PPL Division)
Hells Canyon -
Enterprise 230 kV
PacifiCorp (PPL Division)
Quartz Tap -
LaGrande 230 kV
Bonneville Power
Administration
Hines - Harney
138/115 kV
Bonneville Power
Administration
Sierra 262 MW 500 MW Midpoint - Humboldt
345 kV
Sierra Pacific Power
Eastern Idaho1 Kinport - Goshen 345
kV
PacifiCorp (UPL Division)
Bridger - Goshen 345
kV
PacifiCorp (UPL Division)
Brady - Antelope 230
kV
PacifiCorp (UPL Division)
Blackfoot - Goshen
161 kV
PacifiCorp (UPL Division)
Utah (Path C)2 775 to 830 to Borah - Ben Lomond
345 kV
PacifiCorp (UPL Division)
950 MW 870 MW Brady - Treasureton
230 kV
PacifiCorp (UPL Division)
American Falls -
Malad 138 kV
PacifiCorp (UPL Division)
Montana3 79 MW 79 MW Antelope - Anaconda
230 kV
Montana Power Company
87 MW 87 MW Jefferson - Dillon 161
kV
Montana Power Company
Pacific (Wyoming) 600 MW 600 MW Jim Bridger 345/230kV PacifiCorp (Wyoming
Division)
Power Transfer Capacity for Idaho Power Company Interconnections
1 The Idaho Power-PacifiCorp interconnection total capacities in Eastern Idaho and Utah include Jim Bridger resource
integration. 2 The Path C transmission path also includes the internal PacifiCorp Goshen-Grace 161 kV line. 3 The direct Idaho Power-Montana Power schedule is through the Brady-Antelope 230kV line and through the Blackfoot-Goshen 161 kV line
that are listed as an interconnection with PacifiCorp. As a result, Idaho-Montana and Idaho-Utah capacities are not independent.
Chapter 3 23 Existing and Planned Resources
Transmission Uncertainties
FERC Order 2000
On December 15, 1999, the FERC
issued Order 2000 to encourage voluntary
membership in regional transmission
organizations (RTO). The order required all
public utilities that own, operate or control
interstate transmission facilities to file by
October 15, 2000 a proposal for an RTO.
Idaho Power Company has been an active
participant in efforts to determine an
appropriate structure for RTO West, a RTO
for the Pacific Northwest. While the
proposed restructuring changes will not alter
the physical capability of the transmission
system, it is uncertain how an RTO structure
will affect Idaho Power’s use of its
transmission system.
FERC Order 888
On May 10, 1996, FERC issued
Order 888. The FERC intent of Order 888
was to promote the use of transmission
facilities for competitive markets at the
wholesale level. Because of the geographic
location of Idaho Power’s transmission
facilities, Idaho Power anticipates that
multiple entities may request transmission
capacity in Idaho Power’s main grid
transmission system to transport power from
the Pacific Northwest to the Desert
Southwest. Under the auspices of FERC
Order 888, utilities can be compelled to
construct additional transmission facilities to
increase capacity if the party seeking to use
the increased capacity pays the cost of
adding the capacity. In fact, use of Idaho
Power’s transmission facilities has already
been the subject of litigation before the
FERC brought by Arizona Public Service
(APS) against Idaho Power relating to
APS’s desire to use Idaho Power’s
transmission system for term transactions.
In light of the FERC support for open access
facilitating transactions at the wholesale
level, planning for future transmission
resources must anticipate additional
regulatory requirements being placed on the
transmission system as a result of FERC
Orders 888 and 2000.
FERC Docket No. RM01-12-000
On April 10, 2002, in Docket No.
RM01-12-000, entitled Electricity Market
Design and Structure, the FERC issued a
Notice of Options paper to initiate
discussions on proposed rule making to
address standardized transmission service
and wholesale market design. While the
rule making is in the very early stages, an
initial review indicates that it could have
considerable impact on Idaho Power’s
transmission operations and recovery of
costs for transmission service. Idaho Power
Company is working with the other RTO
West participants to respond to the rule
making.
Western Electricity Coordinating Council
Operating Transfer Capability Process
Since the transmission disturbances
of the summer of 1996, transmission system
capabilities have come under increasing
scrutiny. The Western Electricity
Coordinating Council (WECC) has adjusted
the transfer capability on many transmission
lines. A transmission operator no longer has
the assurance that all of the line capability
will be fully usable in the future. New
interactions with other existing transmission
paths, previously unidentified, can force
reductions in existing transmission
capability.
Chapter 3 24 Existing and Planned Resources
Chapter 4 25 Resource Adequacy
4. Adequacy of Existing and Planned Resources
Idaho Power Company is committed
to generate and deliver reliable, low-cost
power for its customers. Reliability and
quality of service are directly impacted by
the adequacy of IPC’s electric supply.
Idaho Power has specified a
resource adequacy criterion requiring new
resources be acquired at the time that the
resources are needed to meet forecast energy
growth, assuming a water condition at the
70th percentile for hydroelectric generation.
Idaho Power is proposing to change from
the previous median water-planning
criterion. The change is discussed in greater
detail later in this chapter.
The 70th percentile means that Idaho
Power plans generation based on stream
flows that occur in seven out of 10 years on
average. Stream-flow conditions are
expected to be worse than the planning
criteria 30 percent of the time. Idaho Power
plans to meet WECC criteria for reserves.
The WECC criteria currently requires Idaho
Power to maintain 330 MW of reserves
above the forecast peak load to cover an
unexpected loss equal to Idaho Power’s
share of two Bridger generation units.
A 70th percentile monthly water
planning differentiates Idaho Power from
other Northwest utilities, which typically
plan resources based upon having annual
generating capability sufficient to meet
forecast annual energy requirements under
critical water conditions. Critical water
conditions are generally defined to be the
worst, or nearly worst, annual water
conditions based on historical stream flow
records.
Using the 70th percentile water-
planning criterion produces capacity and
energy surpluses whenever stream flows are
greater than the 70th percentile. Temporary
off-system sales of surplus energy and
capacity provide additional revenue and
reduce the costs to IPC customers. During
months when Idaho Power faces an energy
or capacity deficit because of low stream
flow, excessive demand, or for any other
reason, Idaho Power plans to purchase off-
system energy and capacity on a short-term
basis to meet system requirements.
Low-water (90th percentile)
scenarios have been evaluated and included
in the 2002 Integrated Resource Plan to
demonstrate the viability of IPC’s plan to
serve peak and energy loads under low-
water conditions. The evaluations include
consideration of IPC’s transmission
capability at times of lower stream flows.
Impact of Salmon Recovery Program
on Resource Adequacy
The December 1994 Amendments
to the Northwest Power Planning Council’s
fish and wildlife program and the biological
opinions issued under the Endangered
Species Act (ESA) for the four lower Snake
River federal hydroelectric projects call for
427,000 acre-feet of water to be acquired by
the federal government from willing lessors
upstream of Brownlee Reservoir. The
acquired water is then to be released during
the spring and summer months to assist
ESA-listed juvenile salmonids (spring,
summer, fall Chinook and steelhead)
migrating past the four federal hydroelectric
projects on the lower Snake River. In the
past, water releases from Idaho Power’s
hydroelectric generating plants have been
modified to cooperate with the federal
efforts. Idaho Power also adjusts flows in
the late fall of each year to assist with the
spawning of fall Chinook below the Hells
Canyon Complex.
Because of the practical, physical,
and legal constraints that federal interests
must deal with in moving 427,000 acre-feet
of water out of Idaho, Idaho Power has pre-
released, or shaped, a portion of the acquired
water with water from Brownlee Reservoir
and later refilled the reservoir with water
leased under the federal program. At times,
Idaho Power has also contributed water from
Brownlee to assist with the federal efforts to
improve salmonid migration past the lower
Snake federal projects.
Idaho Power’s cooperation with the
federal programs has been pursuant to an
agreement with the BPA that provided for
an energy exchange which reimbursed Idaho
Power for any energy or generating capacity
lost by the shaping or modification of flows.
The BPA agreement insured that Idaho
Power customers were not adversely
affected by Idaho Power’s cooperation with
federal efforts.
The agreement with the BPA
expired on April 15, 2001, and has not been
renewed. As such, the energy exchange
with the BPA that was modeled in the 2000
IRP is not included in the 2002 IRP. Idaho
Power does not intend to modify or
otherwise shape flows from its hydroelectric
projects to address federal responsibilities in
the lower Snake River in the absence of an
appropriate agreement with the BPA or
other federal interests. While such an
agreement may be negotiated in the future,
Idaho Power Company does not intend to
enter into any such agreement that would
adversely affect Idaho Power customers or
require the construction of additional
resources.
Water Planning Criteria for
Resource Adequacy
Idaho Power Company has an
obligation to serve customer loads
regardless of the water conditions that may
occur. In the past, when water conditions
were at low stream-flow levels, IPC relied
on market purchases to serve customer
loads. Historically, IPC’s plan has been to
acquire or construct resources that will
eliminate expected energy deficiencies in
every month of the forecast period whenever
median or better water conditions exist,
recognizing that when water levels are
below median, IPC historically relied on
market purchases to meet any deficits.
In connection with the recent market
price movements to historical highs during
the summer of 2001, IPC has reevaluated the
planning criteria. The public, the Idaho
Public Utilities Commission, and the Idaho
legislature all have suggested that Idaho
Power may place too great a reliance on
market purchases based upon the IRP
planning criteria. Greater planning reserve
margins or the use of more conservative
water planning criteria have been suggested
as methods requiring IPC to acquire more
firm resources and reduce the likelihood of
market purchases.
Due to the public input to the
planning process, IPC is proposing a
resource plan based upon a lower-than-
median level of water. In the current
resource plan, IPC is using the 70th
percentile water conditions and load
conditions for resource planning. However,
IPC will continue to evaluate resource
adequacy under a median water condition
and include that evaluation as part of the
Integrated Resource Plan.
Idaho Power will continue to
analyze its ability to serve customers’ peak
and energy needs under a low-water
condition (90th percentile) as well. Based on
the low-water analyses, IPC believes that it
will be difficult to acquire and deliver short-
term resources from the Pacific Northwest in
Chapter 4 26 Resource Adequacy
Chapter 4 27 Resource Adequacy
amounts sufficient to satisfy peak-hour
deficiencies during low-water conditions.
Historically, Idaho Power has been
able to reasonably plan for the use of short-
term power purchases to meet temporary
water-related generation deficiencies on its
own system. Short-term power purchases
have been successful because Idaho Power
customers typically have summer peaking
requirements while the other utilities in the
Pacific Northwest region have winter
peaking requirements.
Although Idaho Power has
transmission interconnections to the
Southwest, the Northwest market is the
preferred source of purchased power. The
Northwest market has a large number of
participants, high transaction volume, and is
very liquid. The accessible power markets
south and east of Idaho Power’s system tend
to be smaller, less liquid, and have greater
transmission distances.
Under the low water and high-load
conditions, projected peak-hour loads are
likely to cause peak-hour transmission
overloads from the Pacific Northwest. The
transmission overloads may present
significant difficulties as early as the
summers of 2003 and 2004 (transmission
adequacy is discussed later in this chapter).
Recent experiences indicate that, even when
Northwest power is available, the short-term
prices can be quite high and volatile.
Recent market price events
demonstrate that while IPC has been able to
rely on market purchases, the price can be
high. The price risk has led to the
development of the Risk Management
Policy discussed in the Introduction. The
Risk Management Policy represents
collaboration of Idaho Power, the IPUC
staff, and interested customers in
Commission Case IPC-E-01-16.
The primary uncertainties associated
with planned short-term power purchases
are the availability of adequate Northwest to
Idaho transmission capacity to allow imports
at the times when needed, and uncertainty
concerning the market prices of the
purchases.
Planning Scenarios
Median Water, Median Load (Energy)
Figure 2 shows the monthly energy
surpluses and deficiencies associated with
median water and the most probable or
expected future load scenario. With median
water, median loads, and the additional
generation from both the Evander Andrews
Power Complex near Mountain Home and
Garnet in 2005, IPC will experience energy
deficiencies in the winter months starting in
December 2006. Winter deficiencies are
expected to increase from approximately 38
aMW in 2006 to approximately 190 aMW in
2011. Additionally, IPC will experience
summer energy deficiencies starting in July
2008. Summer deficiencies are expected to
increase from approximately 28 aMW in
2008 to approximately 178 aMW by 2011.
Median Water, Median Load (Peak)
At the time of the peak monthly
system load, additional energy is required to
satisfy the peak demand. Figure 3 shows
that, for the median water and median load
scenario, additional resources must be
purchased in the summer beginning in June
2002 and in the winter starting in December
2004. Under the median water and median
load scenario, deficiencies are generally
limited to June, July, November, and
December; however, peak-hour energy
deficiencies do begin to occur in other
months starting in 2010.
70th Percentile Water, 70th Percentile
Load (Energy)
When below-normal water and
higher-than-expected load conditions occur,
a greater number of months are expected to
have deficiencies than in the median water
and median load scenario. Figure 4 shows
that winter deficiencies begin in December
2002 with initial deficiencies of
approximately 10 aMW increasing to
approximately 277 aMW by November
2011. Summer deficiencies in June and July
are expected to increase from approximately
45 aMW in 2004 to approximately 293
aMW in 2011. Initial surpluses in August,
September and October are expected to
become deficiencies starting in August
2006, at 5 aMW and increasing to 200 aMW
by September 2011.
70th Percentile Water, 70th Percentile
Load (Peak)
Figure 5 illustrates that with 70th
percentile water and 70th percentile load
conditions, summer peak-hour energy
deficiencies occur starting in June 2002 at
161 MW and increase to 610 MW in July
2011. Winter peak-hour deficiencies occur
beginning in December 2002 at 107 MW
and increase to 314 MW in November 2011.
Peak-hour energy deficiencies are limited to
June, July, November and December until
2006, when deficiencies begin to occur in
other months. By 2011, deficiencies occur
in 11 of 12 months.
90th Percentile Water, 70th Percentile
Load (Energy)
Figure 6 illustrates that under the
90th percentile water, 70th percentile load
scenario, summer deficiencies occur in all
years starting in June 2002, with 164 aMW,
and increasing to 429 aMW in July 2011.
Winter deficiencies also occur in all years
starting in December 2002 at 101 aMW and
increasing to 316 aMW by December 2011.
By 2005, deficiencies occur in 9 of 12
months; by 2010, all months are deficit.
90th Percentile Water, 70th Percentile
Load (Peak)
The pattern of deficiencies for the
90th percentile water, 70th percentile load
scenario is similar to the pattern of
deficiencies for the 70th percentile water,
70th percentile load scenario. Deficiencies
in the peak months are typically 40 to 60
MW greater because of changes in water
conditions. Monthly surpluses and
deficiencies for the 90th percentile water,
70th percentile load growth are shown in
Figure 7.
Chapter 4 28 Resource Adequacy
Chapter 4 29 Resource Adequacy
Figure 2 Monthly Energy Surplus / Deficiency
Median Water, Median Load, Existing Resources with Garnet
-400
-200
0
200
400
600
800
1000
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
aM
W
Figure 3 Monthly Peak-hour Surplus / Deficiency
Median Water, Median Load, Existing Resources with Garnet
-800
-600
-400
-200
0
200
400
600
800
1000
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
MW
Figure 4 Monthly Energy Surplus / Deficiency
70th Percentile Water and Load, Existing Resources with Garnet
-400
-300
-200
-100
0
100
200
300
400
500
600
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
aM
W
Figure 5 Monthly Peak-hour Surplus / Deficiency
70th Percentile Water and Load, Existing Resources with Garnet
-800
-600
-400
-200
0
200
400
600
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
MW
Chapter 4 30 Resource Adequacy
Figure 6 Monthly Energy Surplus / Deficiency
90th Percentile Water, 70th Percentile Load, Existing Resources with Garnet
-600
-500
-400
-300
-200
-100
0
100
200
300
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
aM
W
Figure 7 Monthly Peak-hour Surplus / Deficiency
90th Percentile Water, 70th Percentile Load, Existing Resources with Garnet
-800
-600
-400
-200
0
200
400
600
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
MW
Chapter 4 31 Resource Adequacy
Transmission Adequacy
Prior to 2000, Integrated Resource
Plans have emphasized construction or
acquisition of generating resources to satisfy
load obligations. Transmission limitations
were not viewed as a major impediment to
Idaho Power’s purchasing power to meet its
service obligations. The 2002 edition of the
IRP, as well as the 2000 IRP, recognizes that
transmission constraints have begun to place
limits on purchased power supply strategies.
To better assess the adequacy of the power
supply and the transmission system, IPC
analyzed peak-hour transmission conditions.
The transmission adequacy analysis
reflects IPC’s contractual transmission
obligations to serve BPA loads in Southern
Idaho. The BPA loads are typically served
with energy and capacity from the Pacific
Northwest. Analyzing the transmission
limitations during the peak hour of each
month allows IPC to assess the adequacy of
the transmission system to serve IPC
customers and BPA customers with energy
from the Pacific Northwest.
The results of the transmission
analyses indicate that the Brownlee East
path is most likely to face transmission
constraints. The transmission analysis
shows monthly peak-hour transmission
deficiencies when the IPC resource
deficiencies are met by energy purchases
from the Pacific Northwest at the same time
the transmission system is delivering energy
to BPA customers in Southern Idaho.
Figure 8 represents the monthly
peak-hour transmission deficiencies for a
median water and median load condition.
The magnitude of the transmission
deficiency is 21 MW in July 2003 and 84
MW in July 2004. Assuming that Garnet is
available in June 2005, the next transmission
deficiency occurs in July of 2006 and has a
magnitude of approximately 45 MW. July
peak transmission deficiencies for
subsequent years increase by approximately
70-80 MW per year.
Figure 9 represents the monthly
peak-hour transmission deficiencies for a
70th percentile water and 70th percentile load
condition. The magnitude of the
transmission deficiency is 86 MW in July
2003 and 180 MW in July 2004. Assuming
that Garnet is available in June 2005, then
the July 2005 transmission deficiency is
reduced to 25 MW. Transmission
deficiencies for subsequent July peaks
increase by approximately 75-90 MW per
year. By 2010, transmission deficiencies
begin to appear in December.
Figure 10 represents the monthly
peak-hour transmission deficiencies for a
90th percentile water and 70th percentile load
condition. The magnitude of the
transmission deficiencies is 141 MW in July
2003 and 225 MW in July 2004. Assuming
that Garnet is available in June 2005, the
July 2005 deficiency is 92 MW.
Transmission deficiencies for subsequent
July peak conditions increase by
approximately 75-90 MW per year. By the
winter season of 2010-2011, transmission
deficiencies begin to appear in December
and January.
Chapter 4 32 Resource Adequacy
Figure 8 Monthly Peak-hour NW Transmission Deficit
Median Water / Median Load
-800
-600
-400
-200
0
200
400
600
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
MW
Figure 9 Monthly Peak-hour NW Transmission Deficit
70th Percentile Water, 70th Percentile Load, Existing Resources with Garnet
-800
-600
-400
-200
0
200
400
600
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
Chapter 4 33 Resource Adequacy
Chapter 4 34 Resource Adequacy
Figure 10 Monthly Peak-hour NW Transmission Deficit
90th Percentile Water, 70th Percentile Load, Existing Resources with Garnet
-800
-600
-400
-200
0
200
400
600
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
MW
5. Future Resource Options
Idaho Power’s primary resource
options for the planning period include
purchases of power from the wholesale
market, the acquisition of additional
generating resources and, to a lesser extent,
pricing options and demand-side
management programs. The information
about each resource option required for
resource planning includes capacity and
energy capability, expected resource life,
seasonal availability, dispatchability,
investment and operating costs, and fuel
cost.
Identification of the resource
options themselves does not constitute a
resource plan, but the specification of
resource options is a first step in the
resource planning process. Included in the
first step is a cost analysis of potential
generating resources sited at generic
locations. The cost analysis assists in the
initial economic ranking of all resources
under consideration.
After the cost of each resource is
determined for generic locations, a more
focused analysis of selected resources is
performed to establish resource costs based
specifically on Idaho or Pacific Northwest
regional data. Resource costs associated
with Northwest- and Idaho-sited
technologies are discussed in greater detail
later in this chapter, as well as in Chapter 6.
Purchased and Exchanged
Generation
Market Purchases
In the 1997 IRP, Idaho Power chose
supplemental seasonal energy and capacity
purchases as the near-term strategy to
optimize the use of company-owned
resources and meet customer loads at the
least cost. That strategy had been successful
and was continued in the 2000 IRP. Idaho
Power had been able to take advantage of
abundant supplies of off-system surplus
energy and available transmission access to
supplement the Company’s own low-cost
generation resources. In 2001, IPC and
many other Northwest utilities experienced
low-water conditions and once again relied
on the market place to satisfy deficiencies.
During that spring and summer, market
prices moved to unprecedented levels, often
in the hundreds of dollars per MWh. While
power was available for purchase, the cost to
IPC and its customers was extremely high.
Idaho Power plans to continue
using, but much less frequently, seasonal
energy and capacity purchases to optimize
utilization of Company-owned resources.
By emphasizing a 70th percentile water
planning criteria, the Company plans to have
adequate resources available to satisfy all of
its customers’ monthly energy needs in 7 out
of 10 years. In only 3 years out of 10 would
IPC expect monthly energy deficiencies to
occur based upon low-water conditions.
Market-based transactions of both hourly
and term energy will continue to be used
under deficit conditions.
Hourly Energy Purchases
The market price of hourly energy is
based on the output of the marginal
generation resources in the interconnected
region offered for sale in the short-term.
Historically, the hourly market in the WECC
has been very reliable and robust, allowing
hourly spot-purchases to be a viable
component of the Company’s short-term
resource planning strategy.
Chapter 5 35 Future Resource Options
Term Energy Purchases
Term energy purchases are for
specific quantities of energy during specific
periods of time that are typically longer than
time periods for hourly energy purchases.
Term energy contracts may be entered into
directly with other utilities or may be
established through local markets.
The New York Mercantile
Exchange (NYMEX) is currently in the
process of reconfiguring its electricity
strategy to incorporate both futures and
over-the-counter (OTC) instruments that are
more flexible and address changes in the
way the electricity industry does business
today. The previous futures contracts traded
at Palo Verde and the California-Oregon
Border (COB) were recently delisted in
anticipation of the new products that
NYMEX plans to introduce.
An exchange serves to guarantee
contracts by requiring collateral (margin)
from traders for each obligation they hold.
The exchange also sets standard terms for
quantity, quality, and location for delivery.
The mechanisms of the exchange and the
futures contracts allow price discovery and
push prices to a market-clearing price.
Standardized futures contracts, together with
options based on futures, allow buyers and
sellers to manage price risk.
The current lack of NYMEX
contracts limits the regional electricity
market. In all likelihood, individual bilateral
contracts with utilities and other generation
owners will continue to be the principal
source of term energy transactions for the
foreseeable future.
Market Purchase Prices
Idaho Power’s estimated market
price during the planning period is best
represented by a combination of the forward
price curve and a price forecast. The
forward price curve was used for the first
five years of the planning period, and a price
forecast was used for the remaining five
years to represent the full cost of market
purchases. The estimated market prices
used in the IRP are shown in the Technical
Appendix.
Gas Price Forecast
One of the primary variables
affecting the costs of energy from either a
simple-cycle or combined-cycle combustion
turbine is the price of natural gas. Forward
market prices and gas price forecasts
produced by national forecasting
organizations have been examined as part of
the process to determine the appropriate gas
prices used to estimate market prices for
electricity.
IPC relies on a combination of
forward market prices and the WEFA long-
range forecast to estimate future gas prices
for the IRP. The price forecasts which were
examined are: (1) the November-adjusted
2001 WEFA Group long-range forecast of
the price for natural gas delivered to electric
utilities in the Mountain region, and (2) the
November 2001 PIRA Energy Group
forecast of prices at Sumas (a major gas
trading hub serving the Western United
States). The long-term gas market in the
Northwest is typically thinly traded, causing
forward pricing data to be less reliable.
For the year 2002, a nominal
delivered price of $2.69 per MMBTU, based
on forward market prices, was used in the
IRP. For subsequent years, the WEFA
forecast was used for the IRP.
The gas price forecast used to
develop the estimate of market prices
contained in this 2002 IRP is shown in the
Technical Appendix.
Chapter 5 36 Future Resource Options
Coal Price Forecast
The IRP coal price forecast is a
composite of Idaho Power’s spot coal
forecasts for its three existing thermal
plants. The plant forecasts are created using
current coal and rail transportation market
information and then escalated based on the
2001 WEFA long-range forecasts. The
resulting $/MMBTU cost estimate
represents the delivered cost of coal
including rail cost, coal cost, and use taxes.
Transmission Resources
Upgrades
Adequate transmission capacity is
critical to the success of a strategy that
utilizes purchases from the wholesale
market to supplement and optimize the IPC-
owned and purchased generation resources.
Transmission alternatives do not generate
additional energy or capacity, but the
transmission system does provide access to
energy markets.
Traditionally, it has been a generally
accepted proposition among electric utilities
in the West that it is less expensive and
faster to construct new transmission
facilities than to construct new generation.
However, in recent times, the regulatory
analyses and other right-of-way
requirements associated with new
transmission facilities construction have
resulted in much longer lead times and
substantially higher costs for new
transmission facilities when compared to
prior time periods. Typically, the permitting
and construction lead times are five to eight
years, depending on transmission distance
and the voltage level.
The costs and impacts of potential
transmission upgrade alternatives are
investigated as part of the IRP. The portion
of the Company’s transmission system that
would provide the most immediate benefit
would be the upgrade of the transmission
lines between the Pacific Northwest region
and the Boise area. Transmission
construction alternatives for the Pacific
Northwest lines would be significantly long
(between 170 and 400 miles). Analyses of a
range of transmission alternatives, including
substation additions, show construction
costs of approximately $400,000 to
$700,000 per mile and incremental
transmission costs between $45 and $90/kW
per year for additional Pacific Northwest
transmission connections.
The projected Pacific NW
transmission upgrade costs are
approximately 500 percent higher than
Idaho Power’s embedded transmission costs.
Assuming a 50 percent annual load factor
(typical for interconnections) and further
assuming that all project capacity is
subscribed, construction of new
transmission lines results in 10 to 20
mills/kWh added to Pacific Northwest
purchased energy prices. If some of the
transmission capacity is unsubscribed, then
the estimated transmission upgrade
estimates are further increased.
Transmission upgrades across the
Borah West path located west of American
Falls, Idaho, are estimated to cost about
$15/kW per year. Upgrades to the Borah
West Path would be necessary for network
resource developments east of Borah.
New Transmission Projects
Southwest Intertie Project (SWIP)
Idaho Power has obtained the
necessary right-of-way permits to construct
the Southwest Intertie Project, a 500-kV
transmission line to connect the Company’s
Midpoint Substation with Southwest
transmission lines at a location near Las
Vegas, Nevada. Uncertainties associated
Chapter 5 37 Future Resource Options
with implementation of FERC Orders 888
and 2000 have halted development of the
SWIP Project.
Brownlee to Oxbow 230 kV
Transmission Line Number 2
To improve reliability of the
Brownlee to Oxbow transmission line and
increase the transfer capacity, IPC plans to
build a new 10-mile, 230 kV transmission
line between Brownlee and Oxbow. The
project would increase Brownlee East
capacity by approximately 100 MW. Idaho
Power Company is presently siting the
transmission facilities. The transmission
upgrade is expected to cost $18 million and
to be completed and in service by the fall of
2004.
Borah West Transmission Upgrade
The Borah West path is a fully-
subscribed transmission path and is a known
constraint within the IPC main grid
transmission system. Idaho Power Supply
has submitted a study request to the Idaho
Power Transmission Group to determine the
feasibility and cost of upgrading the Borah
West transmission line and increasing the
transmission capacity by 150 MW.
LaGrande Upgrade
Idaho Power Company has submitted
a study request to determine the feasibility
and cost of upgrading the transmission line
from Brownlee to LaGrande, increasing the
transmission capacity by 154 MW.
Generating Resources
Background
The following discussion of the
costs associated with various non-hydro
generating technologies is based on the
technology descriptions, capital costs,
operational and maintenance cost and heat-
rate data derived from the Department of
Energy/Energy Information Administration,
(DOE/EIA) 2002 Annual Energy Outlook
(AEO) report. The government data were
combined with specific IPC financial
factors, such as cost of capital, interest on
funds used during construction, and tax
rates, to further refine costs used for
comparisons. Use of data taken from a
common source like the AEO report allows
Idaho Power to make a consistent first
comparison of the costs of the selected
technologies at generic locations. The initial
cost comparison is shown in Figure 11. The
fuel cost estimates are described earlier in
this chapter.
Idaho Power selected several
generation technologies for investigation at
specific Idaho locations. The selected
generation technologies were estimated
using plant-sizing, capital costs, operational
costs, and capacity factors that were more
consistent with known and expected
operational assumptions for generation
within the Idaho Power service territory.
While the average load continues to
increase in the Idaho Power service territory,
the near-term problem is serving the peak
load. Figure 4 shows that under the 70th
percentile water and 70th percentile load
planning scenario, the monthly energy
deficiencies are expected to be less than 100
MW until December 2005. However, under
the same planning scenario, peak-hour
deficits exceed 200 MW in 2003, 2004 and
again in 2006. The peak-hour deficiency
drops below 200 MW in 2005 when Garnet
comes on-line, but deficiencies exceed 200
MW in 2006 and increase to over 600 MW
by 2011. The near-term requirements
indicate the need for a peak-hour resource.
The generation resources are ranked in
Figure 11 through Figure 14.
Chapter 5 38 Future Resource Options
Chapter 5 39 Future Resource Options
Hydroelectric Generating
Resources
Efficiency Improvement Projects
Idaho Power continually
investigates and evaluates opportunities to
economically improve efficiency and
generating capacity at existing hydroelectric
facilities. Each improvement opportunity is
technically and economically considered on
an individual project basis. Proposed
capacity upgrades are evaluated by
standards for cost effectiveness of long-term
resource investments, including uncertainty
in environmental impact.
New Hydro Projects
Idaho Power is proposing a
significant hydro capacity upgrade at the
Shoshone Falls facility. The existing
Shoshone Falls Hydroelectric facility was
completed in 1921 and has a generating
capacity of 12.5 MW. Idaho Power is
proposing a 64 MW expansion at the
Shoshone Falls facility.
With the expiration of Shoshone
Falls FERC License No. 2778, Idaho Power
filed an application to relicense the facility
in 1997. As part of the license preparation,
a facility expansion was identified and
investigated. At the time of license
submittal, Idaho Power determined it was
not economical to expand the facility. Re-
examination of the facility expansion
investigation following the recent energy
crisis has led IPC to propose the Shoshone
Falls upgrade. The Shoshone Falls upgrade
must be considered within the Shoshone
Falls relicensing process. If Idaho Power
Company receives positive feedback
concerning the proposal then IPC will begin
the environmental and regulatory process
involved in licensing and permitting the
Shoshone Falls upgrade.
If Idaho Power does not proceed
with the Shoshone Falls upgrade, there is no
guarantee that the upgrade will be available
for IPC customers in the future. Therefore,
the project has been designated as non-
deferrable.
Thermal Generating Resources
Efficiency Improvement Projects
Idaho Power Company, in
conjunction with its operating partners, is
continually looking for economic efficiency
and capacity improvements at the thermal
generation facilities. The Company is
presently considering efficiency upgrades at
both the Boardman and Valmy generation
facilities.
Boardman
A high pressure/intermediate
pressure turbine modification is being
evaluated. The modification would add
approximately 2.5 MW of capacity (Idaho
Power would receive 10 percent of the 25
MW increase) at a levelized cost of
approximately 8 mills per kWh.
Valmy
A low-pressure turbine modification
is being evaluated for both Units 1 and 2.
The modifications are projected to add
approximately 7 MW of capacity (Idaho
Power would receive 50 percent of the 14
MW increase) at a levelized cost of
approximately 11 mills per kWh.
Figure 11 30-Year Nominally Levelized Cost of Production
For Economic Ranking at a Generic Location (excluding transmission costs)
0 20 40 60 80 100 120 140 160 180 200 220
Photovoltaic (5 MW)
Solar Thermal (100 MW)
Fuel Cells (10MW)
Wind (50 MW)
Conventional Combustion
Turbine (160 MW)
Advanced Combustion
Turbine (120 MW)
Conventional Gas/Oil
Combined Cycle (250 MW)
Geothermal (50 MW)
Integrated Coal Gasification
Combined Cycle (428 MW)
Scrubbed Coal (400 MW)
$/MWh
Capacity
Non Fuel O&M
Fuel
80% Capacity Factor
28% Capacity Factor
42% Capacity Factor
80% Capacity Factor
32% Capacity Factor
80% Capacity Factor
80% Capacity Factor
80% Capacity Factor
87% Capacity Factor
80% Capacity Factor
Figure 12 30-Year Nominally Levelized Cost of Production
For Economic Ranking at an Idaho Location (excluding transmission costs)
0 20 40 60 80 100 120 140 160 180 200 220
Idaho Wind (10 MW)
Idaho - Conventional Combustion
Turbine V64.3 (61.2 MW)
Idaho - Advanced Combustion
Turbine LM 6000 (2ea) (78.52 MW)
Idaho - Conventional V64.3
Combined Cycle (88.6 MW)
Boardman Unit 2 (56 MW)
Danskin CC Expansion
Incremental (38.96 MW)
Valmy Unit 3 (130 MW)
Shoshone Falls Upgrade (64 MW)
$/MWh
Capacity
Non Fuel O&M
Fuel
47% Capacity Factor
23% Capacity Factor
59% Capacity Factor
59% Capacity Factor
91% Capacity Factor
84.1% Capacity Factor
91% Capacity Factor
88.4% Capacity Factor
Chapter 5 40 Future Resource Options
Figure 13 30-Year Nominally Levelized Fixed Costs of Operation
For Economic Ranking at a Generic Location (excluding transmission costs)
0 5 10 15 20 25 30 35 40 45
Photovoltaic (5 MW)
Solar Thermal (100 MW)
Geothermal (50 MW)
Fuel Cells (10 MW)
Integrated Coal Gasification
Combined Cycle (428 MW)
Scrubbed Coal (400 MW)
Wind (50 MW)
Conventional Gas/Oil
Combined Cycle (250 MW)
Advanced Combustion
Turbine (120 MW)
Conventional Combustion
Turbine (160 MW)
$/kW Month
Capacity
Non Fuel O&M
Figure 14 30-Year Nominally Levelized Fixed Costs of Operation
For Economic Ranking at an Idaho Location (excluding transmission costs)
0 5 10 15 20 25 30 35 40 45
Danskin CC Expansion
Incremental (38.96 MW)
Boardman Unit 2 (56 MW)
Valmy Unit 3 (130 MW)
Idaho Wind (10 MW)
Shoshone Falls Upgrade (64 MW)
Idaho - Conventional V64.3
Combined Cycle (88.6 MW)
Idaho - Advanced Combustion Turbine
LM 6000 (2ea) (78.52 MW)
Idaho - Conventional Combustion
Turbine - V64.3 (61.2 MW)
$/kW Month
Capacity
Non Fuel O&M
Chapter 5 41 Future Resource Options
Thermal Technologies
Conventional Steam Turbine Plant
Conventional coal-fired steam
turbine technology is well developed. The
standard configuration has a conventional
steam boiler generating steam, which is then
used to drive a turbine to generate
electricity. The emissions from the
combustion of coal are treated (scrubbed) to
meet applicable clean-air standards.
For a 400 MW unit, the 2002 AEO
assumes a capital cost of $1,148 per kW of
plant capacity. Using an 80 percent capacity
factor, a levelized cost of approximately
43.6 mills per kWh at a generic location is
projected (Figure 11).
Advanced Coal Technologies
The AEO uses integrated coal
gasification combined-cycle technology to
address the cleaner-burning coal
technologies under development. The
primary benefit of advanced coal technology
plants is the ability to achieve lower
emissions of sulfur dioxide and nitrogen
oxides without the need for add-on emission
control equipment.
Integrated coal gasification
combined-cycle plant capital costs from the
2002 AEO were $1,373 per kW for a 428
MW plant. The derived levelized cost of
generation at a generic location is
approximately 44.4 mills per kWh,
operating at an 80 percent capacity factor.
Simple-Cycle Combustion Turbine
(SCCT)
Combustion turbines (CT), either
simple-cycle or combined-cycle, burn
natural gas or fuel oil distillate to create hot
exhaust gas, which is allowed to expand
through a turbine to turn an electric power
generator. Compared to coal-fired steam
plants, CTs burn more expensive fuel and
typically have higher heat rates. Compared
to coal-fired generation, the principal
advantages of a CT are lower capital costs
per kW of generating capacity and shorter
lead times for siting and construction.
SCCTs also have relatively lower
environmental impacts than do coal-fired
plants and possess the ability to more
rapidly adjust the level of generation over
the output range. Consequently, SCCTs are
often selected for peaking and other low-
capacity factor requirements. After
installation, a SCCT may be converted to a
combined-cycle unit for more efficient
operation at higher capacity factors by
adding a heat recovery boiler and steam
turbine generator.
The 2002 AEO report estimates that
capital costs of a 160 MW simple-cycle
combustion turbine plant are $348 per MW.
The levelized cost of generation at a generic
location is approximately 55.9 mills per
kWh, operating at an 80 percent capacity
factor (Figure 11).
Idaho Power has estimated the cost
of simple-cycle technology sited in Idaho.
Both a conventional combustion turbine and
an advanced aero-derivative combustion
turbine were estimated. Both of these
turbines are smaller in capacity than the 160
MW SCCT used in the AEO report. The
smaller sized SCCTs were chosen because
of the operating hour limitations a 160 MW
plant would have under state emission
regulations unless the unit was equipped
with selective catalytic reduction emissions
controls. Although the smaller capacity
SCCTs have a higher capital cost per kW
installed, the smaller size allows greater
Chapter 5 42 Future Resource Options
operating flexibility and a higher capacity
factor.
Combined-cycle Combustion Turbine
(CCCT)
The CCCT adds a heat recovery
boiler and steam turbine generator to the
simple-cycle combustion turbine to decrease
the effective heat rate and increase overall
generating efficiency. The heat recovery
system uses the residual hot exhaust gas
from the combustion turbine to create steam,
which is then used to drive a secondary
turbine to generate electricity. The
increased capital cost of the CCCT, coupled
with increased fuel efficiency, tends to make
the CCCT more cost-effective at higher
capacity factors than the SCCT.
Construction costs and operating
characteristics for a new 250 MW CCCT
based on the 2002 AEO show an estimated
capital cost for the unit of $468 per kW of
capacity. Operating at an 80 percent
capacity factor, the CCCT has a levelized
cost of generation at a generic location of
approximately 44.8 mills per kWh (Figure
11).
Idaho Power has estimated the cost
of a specific CCCT sited in Idaho in contrast
to the more generic AEO cost data. The
simple-cycle combustion turbine estimated
in the previous section was expanded to a
CCCT plant sited in Idaho.
Micro-Turbines
Micro-turbines are scaled-down
versions of the larger combustion turbine
generators. Micro-turbines range in size
from 25 to 100 kW and are applicable to
small commercial facilities, acting as either
backup power sources or as generators that
run in parallel with the utility system.
Banks of the machines have been set up to
provide power to larger commercial
facilities and some industrial facilities.
Micro-turbine commercialization is limited,
with only a few manufacturers offering the
products. At this time, there are no micro-
turbine generators operating on the Idaho
Power system.
Diesel and Natural Gas Internal
Combustion Generators
Diesel- and gas-fueled generators
are one of the most common forms of
distributed electric generation. Based on the
internal combustion engine, the generators
provide reliable electrical service in many
diverse locations. Diesel generator
capacities range from a few kW to beyond
10 MW. Idaho Power owns two 2.5 MW
diesel engine-generators in Salmon, Idaho,
that are primarily used for backup power.
Many industrial and large commercial
facilities have internal combustion engine
generators used for backup power. Nearly
every hospital in Idaho has an emergency
internal combustion engine generator.
Many diesel generators were
deployed throughout the Northwest last
summer when the market price of electricity
made distributed diesel generation profitable
to operate. When market prices returned to
historical norms, use of the diesel generators
declined significantly. Idaho Power’s own
trial with diesel generators in the Treasure
Valley in the summer of 2001 was, at best,
problematic.
Advanced Technologies
Fuel Cells
Fuel cells are electrochemical
devices that convert the chemical energy of
a fuel, such as natural gas, into low-voltage
electricity. In a typical fuel cell, hydrogen
extracted from the fuel is oxidized at an
anode using oxygen supplied from the
Chapter 5 43 Future Resource Options
cathode. Ion flow across the fuel cell is
accompanied by flow of electricity through
the external circuit. The by-products of the
chemical process are carbon dioxide, water
and heat.
Fuel cells are thought by many to be
the future of distributed generation. Fuel
cells are highly reliable and can provide
backup power in critical facilities. The
present cost for a fuel cell system is
extremely high, but improvements in
manufacturing and design innovation are
expected to reduce fuel cell costs. Fuel cells
are expected to sell commercially for $1,000
to $1,500 per kW when the systems are in
production. At this time, commercial fuel
cell systems are just becoming available and
are limited in size from a few watts to 250
kW.
An individual fuel cell has fairly
low output so multiple fuel cells are usually
connected together in a battery
configuration, forming power modules. The
power modules are then combined to meet
the power application requirement.
The fuel cell technology selected in
the 2002 AEO for cost projection purposes
was a 10 MW molten carbonate system. A 2
MW molten carbonate demonstration unit
was built and operated in Santa Clara,
California. The unit was a limited success
and operated for several months on a
restricted basis during 1996.
The AEO capital assumption is
$2,145 per kW for fuel cells. The resulting
levelized cost of generation at a generic
location is about 70 mills per kWh,
operating at an 80 percent capacity factor
(Figure 11).
Biomass
Production of power from biomass
has declined in Idaho Power’s service
territory in the past few years due to the
closing of Boise’s (formerly Boise Cascade)
Emmett lumber mill. However, interest in
using animal waste or municipal sewage to
produce methane for power production is
increasing, and IPC anticipates that some
farms and feedlots may bring anaerobic
digesters on-line during the IRP planning
period.
Solar Photovoltaic
The cost of photovoltaics (PV) has
decreased significantly in the past decade,
even though PV cost is still quite high when
compared to conventional generation. In
some regions of the country with high utility
costs, there has been some PV capacity
installed in the last few years. Photovoltaic
generation continues to be used in remote
off-grid locations.
The building block of the solar
photovoltaic (PV) system is a solid-state
solar cell that converts solar radiation
directly into electrical energy. A number of
solar cells are interconnected to form a solar
module. PV systems range in size from
small, single-module systems to large
systems with many hundreds of solar
modules.
The 2002 AEO uses a capital cost of
$3,931 per kW for a 5 MW station with a 28
percent capacity factor. The cost estimate
yields a levelized cost of about 210.1 mills
per kWh for generation at a generic location
(Figure 11).
Solar Thermal Generation
Solar thermal power plants convert
solar energy to electricity by concentrating
sunlight to produce heat and then electricity.
The systems are similar to typical generating
plants in that the heat is converted into
electricity via a turbine generator using
conventional steam-cycle technology.
Chapter 5 44 Future Resource Options
Idaho Power participated in the
Solar Two demonstration project near
Barstow, California, along with several
other utilities and government agencies.
The 10 MW Solar Two demonstration
project is now over.
The 2002 AEO uses a capital cost of
$2,605 per kW for a 100 MW station at a
generic location yielding a levelized cost of
approximately 111.0 mills per kWh at a 42
percent capacity factor (Figure 11).
Windpower
Most wind generation being
installed today is in the form of large wind
farms where multiple wind turbines are
placed at one site and the aggregate power is
delivered to the electric grid. Wind
generation facilities range in size from 10
MW to over 100 MW. Additionally, a few
companies market small, home-sized wind
turbine generators, although the cost of the
small generators remains high. Some
companies are also trying to market used,
mid-sized wind turbines. Mid-size wind
turbines range in size from 25 kW to 200
kW and would be applicable to large
residences and farms.
Wind turbines currently being
deployed have improved aerodynamics, are
less costly, and more reliable than earlier
versions. Using 2002 AEO capital costs of
$1,008 per kW, the levelized cost at a
generic location would be approximately
59.7 mills per kWh for a 50 MW wind plant
having a 32 percent capacity factor (Figure
11).
Because the wind intensity at a
given location is inconsistent, the energy
produced from wind turbines is less useful
than energy produced from resources that
can be dispatched to meet system load
requirements. However, due to the
generation and storage flexibility of Idaho
Power’s hydroelectric system, a moderately-
sized wind project may be feasible as part of
the generation portfolio.
Idaho Power believes it would be
prudent to pursue a pilot wind generation
project to more accurately define the costs
and benefits of such a project. If the pilot
project meets acceptable goals for costs and
benefits, then the project could be expanded
at a later date, contingent upon continued
public support and Commission approval.
Geothermal
Geothermal power plants convert
geothermal heat to electricity by using the
earth’s heat to produce steam, which is then
used to drive a steam turbine. The
technology has always produced some
interest because of the potential low-cost
electricity that could be produced at a high-
quality geothermal field.
Because of the remote locations and
relatively low temperature, the known
geothermal areas within Idaho Power’s
service territory have limited potential. The
2002 AEO cost and performance data
represent the best site that could be
developed in the Pacific Northwest. An
optimal location yields a 50 MW project
with costs of $1,791 per kW, a levelized cost
of approximately 44.5 mills per kWh and an
87 percent capacity factor (Figure 11). It
must be noted that the AEO data do not
assume any cost for the use of geothermal
fluid.
In addition, the AEO data do not
include the exploration and development
cost of the geothermal resource, nor are the
costs of purchasing geothermal fluid from
the owner of the resource considered. The
AEO cost information assumes that the
geothermal fluid resource exists and can be
utilized at zero cost. In most cases, the
royalty cost of geothermal fluid would be
significant.
Chapter 5 45 Future Resource Options
Energy Storage
An effective energy storage system
could enhance existing generation and
transmission resources. Presently, energy
storage systems with a capacity greater than
1 MW are limited to pumped storage,
hydroelectric generation, and compressed air
technologies. Each technology is site-
specific. The operating flexibility of the
existing Idaho Power hydro system already
provides a significant amount of energy
storage.
Distributed Generation
The term “Distributed Generation”
(DG) refers to small- or intermediate-sized
generation resources typically placed near
the load. DG ranges in size from less than a
kW up through 50 MW and beyond.
Distributed generators are
commonly operated as stand-alone units.
Distributed generation is usually not
operated for the benefit of the entire power
system, but for the benefit of the individual
DG operators.
Idaho Power Company currently
purchases approximately 100 average
megawatts of energy generated by 68
different cogeneration and small power
producers (CSPP). These CSPP projects are
small (20 kW to 9 MW) and are distributed
throughout the Idaho Power Company
service territory. In response to news of
higher wholesale electric prices and longer
contract terms, the Company has received
numerous inquiries from potential
developers requesting information
concerning the appropriate interconnection
processes and the various contract options
available for new DG projects.
Solar, wind, small hydro, wood
waste, methane (animal waste, landfill gas,
waste water treatment plants), and
geothermal are some of the various fuel
sources that are being considered by various
distributed generation plant developers.
In negotiating a contract with a
potential developer of distributed
generation, Idaho Power Company adheres
to Federal and State regulations and
considers the benefits of the project's
physical location, dependability, flexibility
and any other characteristics that may
influence the value of the energy to the
Idaho Power Company system. A report
outlining the role that distributed generation
could play in Idaho Power’s future resource
portfolio was filed with the Oregon Public
Utility Commission in January 2002. A
copy of the report can be found in the
Technical Appendix.
Small Hydro
Small, or low-head hydro facilities
are installed throughout the IPC service
territory. The extensive system of irrigation
canals is ideally suited to small hydro
applications. Developers continue to
propose new hydroelectric projects on
Idaho’s many irrigation canals. Most of the
recently proposed projects are under 1 MW
in size. Each small hydro project is
analyzed individually for financial
feasibility. Successful small hydro
applications are limited due to high capital
costs, the seasonal nature of canal flows, and
existing market prices for energy.
Demand-Side Measures and
Pricing Options
Demand-side measures and energy
conservation measures are often seen as
synonymous. Unfortunately, generic energy
conservation programs are unlikely to be
sufficient to meet the peak deficiencies
facing Idaho Power during the term of this
resource plan. Demand-side measures and
pricing options that target peak-hour
demand reduction are more likely to address
Chapter 5 46 Future Resource Options
Table 5 Idaho Power Company
Externality Cost Adder Ranges for Thermal Plant Emissions
Combinations of NOx, TSP and CO2 Adder Levels in Dollars per Ton
Emission Level 1 Level 2 Level 3 Level 4 Level 5 Level 6
NOx $2,640 $2,640 $2,640 $6,600 $6,600 $6,600
TSP $2,640 $2,640 $2,640 $5,280 $5,280 $5,280
CO2 $13.20 $33.00 $52.80 $13.20 $33.00 $52.80
the peak deficiencies facing Idaho Power
Company.
Power generation costs vary hour by
hour depending on a variety of factors
including aggregate demand and the
availability of generation resources.
Economic theory indicates that accurate
prices are necessary for an efficient
allocation of resources. Accurate price
signals for electricity are based on market
conditions, reflect the true production and
distribution costs of service, and vary
depending on the aggregate demand and
availability of generation resources.
Idaho Power Company implemented
a Time-of-Use Pilot Program for irrigation
customers in April 2001. The purpose of the
Pilot Program is to gather meaningful
information regarding irrigation customers’
ability to shift energy consumption from
higher-cost peak hours to lower-cost off-
peak periods. The data collected during the
pilot program is expected to provide Idaho
Power Company, the customers of Idaho
Power, and the Idaho PUC with the
information necessary to evaluate the
impacts costs, and benefits of time-of-use
pricing. The irrigation pilot program
continues until October 1, 2002. Idaho
Power Company will analyze the pilot
program’s impact after the program data
becomes available in late 2002.
Idaho Power Company’s Voluntary
Irrigation Load Reduction program was very
effective in reducing summer demand
during 2001. Similar demand-side measures
targeting peak reduction may also be
effective.
Due to the nature and timing of the
projected peak deficits and transmission
overloads, conservation, demand-side
measures, and pricing options must be
carefully designed and targeted to cost-
effectively address the projected deficits.
Societal Costs
All electric power resources have
costs, benefits, and impacts beyond the
construction and operating costs that are
included in the price of electricity. The non-
internalized costs include the air pollution
and natural resource depletion associated
with thermal generation, the effects on
aquatic life and recreation associated with
hydroelectric dams, and the aesthetic and
bird mortality impact associated with
renewable wind power.
Order 93-695 from the Oregon
Public Utility Commission specified cost
adders associated with the level of sulfur
dioxide (SO2), carbon dioxide (CO2),
nitrogen oxides (NOx), and total suspended
particulate (TSP) emissions from new
thermal generating plants. SO2 emission
costs are included in the calculation of direct
utility costs through modeling of the
emission allowance system established by
Chapter 5 47 Future Resource Options
the Clean Air Act. The sensitivity of the
choice of least cost adders for CO2, NOx
and TSP emissions has been investigated for
the six levels of cost adders specified by the
OPUC in Order 93-695.
Table 5 shows the six specified
combinations of externality cost adders for
CO2, NOx and TSP emissions. Each
emission has been assigned a low- and a
high-level of cost adder, and the different
possible combinations of cost adders for the
individual emissions represent the range of
total emission cost adders. The low end of
the range is produced by the low adder
values for each emission, and the high end
of the range by the high adders for each
emission.
Chapter 5 48 Future Resource Options
6. Ten-Year Resource Plan
Overview
Development of the ten-year
resource plan involves the selection of
resources from Idaho Power’s future
resource options (described in Chapter 5)
that are well-suited to meet the forecasted
deficiencies identified in Chapter 4. Idaho
Power has selected four strategies to analyze
as the Company’s 2002 resource plan. A
cost comparison of the resource strategies
was used to determine the single strategy
that is most likely to meet expected loads at
the lowest expected cost. The four strategies
were also analyzed in the context of their
relative sensitivity to various uncertainties.
Uncertainties included external cost adders
for emissions from thermal generation and
discount rate variations. The result of the
analytical comparisons led to the selection
of Idaho Power’s 10-year resource plan.
Unless noted otherwise in this
section, references to forecasted energy
surpluses or deficiencies are based on a 70th
percentile stream flow and 70th percentile
load-planning criterion. Peak-hour
deficiencies and transmission overloads are
based on a 90th percentile stream flow and
70th percentile load-planning criterion.
Each of the four strategies selected
for evaluation in the 2002 Integrated
Resource Plan assumes that the Garnet
Power Purchase Agreement is approved and
that the Garnet Energy Facility is capable of
providing energy and capacity in June 2005.
If the Garnet Power Purchase Agreement is
not approved, or if the facility is not
constructed for any reason, Idaho Power will
need to replace the energy and capacity that
Garnet is expected to provide. If Garnet
were canceled, Idaho Power would most
likely combine the projected deficiencies
currently identified in this IRP with the
additional deficits created by canceling
Garnet, and reassess the options available
for supplying the combined deficiency.
In addition, the 2000 IRP assumed a
continuation of seasonal market purchases
from the Pacific Northwest during the entire
planning period. The seasonal purchases
consisted of 250 aMW of energy during July
and August and 200 aMW of energy during
November and December. The addition of
the 90 MW Evander Andrews Power
Complex in 2001, combined with changes in
the load forecast, have permitted Idaho
Power to reduce the planned seasonal
purchases that were assumed in the 2000
IRP. However, all of the resource strategies
considered in the 2002 IRP include some
level of market purchases.
Resource Strategies
The first resource strategy
considered is a long-term limited quantity
market purchase strategy.
The second resource strategy
considered is a combination of long-term
market purchases of varying quantities and a
64 MW facility upgrade to the existing
Shoshone Falls hydro plant.
The third strategy considered is a
combination of short-term limited-quantity
market purchases, the addition of a new 200
MW peaking resource and a 64 MW facility
upgrade at Shoshone Falls.
The fourth resource strategy
considered is a combination of long-term
limited-quantity market purchases, the
addition of a new 100 MW peaking
resource, and a 64 MW facility upgrade at
Shoshone Falls.
Chapter 6 49 Ten-Year Resource Plan
Chapter 6 50 Ten-Year Resource Plan
Three of the four resource strategies
include the Shoshone Falls upgrade. The
actual increase in output at Shoshone Falls
will vary by month and will be determined
by water conditions. An average increase in
output of 30 MW was used in the energy
analysis, although the amount varies by
month. During median water conditions, the
Shoshone Falls upgrade will provide 33
aMW, and, under 70th percentile water
conditions, the Shoshone Falls upgrade will
provide 16 aMW. Peak nameplate
generation from the Shoshone Falls upgrade
is expected to be 64 MW.
As noted earlier in this plan, Idaho
Power is proposing to pursue the Shoshone
Falls upgrade as a non-deferrable project.
The levelized cost of energy from the
upgrade project is shown in Figure 12.
Energy produced from the Shoshone Falls
upgrade is competitive when the Shoshone
Falls levelized costs are compared to the
costs of the other resources shown in Figure
12. Considering levelized cost, and the fact
that the project increases the efficiency and
output of an existing hydro project, Idaho
Power plans to proceed with the upgrade.
Idaho Power does not anticipate permitting
or environmental issues to adversely affect
the Shoshone Falls upgrade.
The four resource strategies are
outlined in Table 6.
Strategy 1
The first resource strategy
considered is a long-term limited quantity
market purchase of energy and capacity.
The strategy includes long-term market
purchases of 100 MW during June, July,
November and December in years 2002
through 2011. While the strategy is similar
to the market purchase strategy included in
the 2000 IRP, the magnitude of the
purchases is significantly less than the 200
MW to 250 MW considered in 2000.
Strategy 1 is capable of supplying
projected energy needs through November
of 2005. In Strategy 1, peak-hour
transmission overloads from the Pacific
Northwest in excess of 100 MW occur in
July of 2003, July 2004, and again in July
2006. Strategy 1 is an alternative for
meeting forecast energy deficiencies in the
near term. In Strategy 1, the decision to add
additional resources, including the Shoshone
Falls upgrade, is deferred until the next IRP,
or an interim assessment.
Chapter 6 51 Ten-Year Resource Plan
Table 6 Resource Strategies
Strategy Years Quantity Description
1
2002-11 100 MW Term Market purchase in June, July, November and
December; sources include NW, SE, NE and/or Garnet during
non-contract months. Reassess deficiency in 2004 IRP.
2 2002-04
2005-11
2007-11
100 MW
200 MW
30 aMW
Term Market purchase in June, July, November and
December; sources include NW, SE, and NE. Reassess
deficiency in 2004 IRP.
Term Market purchase in June, July, November and
December.
Shoshone Falls upgrade
3 2002-04
2005-11
2007-11
100 MW
200 MW
30 aMW
Term market purchase in June, July, November and
December; sources include NW, SE, and NE.
Peaking resource (simple-cycle CT or equivalent)
Shoshone Falls upgrade
4 2002-04
2005-11
2005-11
2007-11
100 MW
100 MW
100 MW
30 aMW
Term market purchase in June, July, November and
December; sources include NW, SE, and NE.
Peaking resource (simple-cycle CT or equivalent)
Term Market purchases in June, July, November and
December.
Shoshone Falls upgrade
Strategy 2
The second resource strategy utilizes
a combination of market purchases of
varying quantities and the Shoshone Falls
upgrade. Like Strategy 1, the second
strategy includes long-term market
purchases of 100 MW during June, July,
November and December from 2002
through 2004. Beginning in 2005, the
market purchases increase to 200 MW in the
same months. The final component of the
second resource strategy is the Shoshone
Falls upgrade, which is expected to be
available in 2007. Under Strategy 2, a peak-
hour transmission overload from the Pacific
Northwest in excess of 100 MW is forecast
in July 2003, July 2004, and again in July
2006 – the same as Strategy 1. From an
energy perspective, the second resource
strategy is capable of meeting monthly
energy deficiencies through July of 2009.
Although the second strategy offers
enhanced reliability and a reasonably low
cost for meeting the monthly energy
deficiencies, peak-hour deficiencies and
transmission overloads are still present.
Strategy 3
The third resource strategy
considered is a combination of short-term
market purchases, a 200 MW peaking
resource and the Shoshone Falls upgrade. In
the third strategy, the market purchases are
short-term, providing a bridge until Garnet
capacity is available in 2005. Strategy 3
adds a 200 MW peaking resource in 2005
and the Shoshone Falls upgrade in 2007.
The third strategy assumes that the peaking
resource is located between the Brownlee
Chapter 6 52 Ten-Year Resource Plan
East and Borah West constraints, thereby
reducing the need to transmit power across
those constraints.
The Strategy 3 combination of
resources is capable of meeting monthly
energy deficiencies through October of
2009. Under Strategy 3, peak-hour
transmission overloads from the Pacific
Northwest in excess of 100 MW occur in
July 2003, July 2004, and again in July
2008. Under expected market prices,
Strategy 2 is less expensive that Strategy 3.
However, under the high market price
scenario, Strategy 2 is more expensive for
two reasons – first, purchases are being
made at a higher price and, second, there is
no peaking resource available to make
profitable surplus sales when market prices
are high. The addition of a peaking
resource in Strategy 3 provides increased
reliability, security and an opportunity to
generate profitable surplus sales during
times of high market prices or when not
needed for system load during the later
portion of the planning period.
Strategy 4
The fourth resource strategy is a
combination of long-term market purchases,
a 100 MW peaking resource and the
Shoshone Falls upgrade. The fourth strategy
is very similar to Strategy 3; however,
instead of adding a 200 MW peaking
resource in 2005, Strategy 4 adds a 100 MW
peaking resource and 100 MW of market
purchase in 2005. The net effect is
substituting 100 MW of peaking resource
for 100 MW of market purchase. The
combination of resources in Strategy 4 is
capable of meeting monthly energy
deficiencies through August of 2009. Peak-
hour transmission overloads from the Pacific
Northwest in excess of 100 MW occur in
July 2003, July 2004, and again in July
2007. Under expected market prices, the
cost of Strategy 4 is between the costs of
Strategies 2 and 3.
The fourth resource strategy balances
market purchases with the addition of 100
MW internal generation. During times of
high market prices, there is less generation
available to produce profitable surplus sales
than is available under Strategy 3.
Conversely, under low market prices,
Strategy 4 is preferable to Strategy 3
because of less-expensive market purchases
and lower fixed costs associated with a
smaller peaking resource in Strategy 4.
Cost Comparison of Resource
Strategies Including Emission Cost
Adders
A cost analysis was performed for
each of the four resource strategies with the
emission adders identified in OPUC Order
93-695. Cost estimates of the generating
resources assumed a 30-year operating life;
the results are summarized in Table 7. As
shown in Table 7, Strategy 1 is the lowest
cost and Strategy 3 is the most expensive.
The relative ordering of the strategies is the
same for Zero, Level 1 or Level 6 emission
adders.
Chapter 6 53 Ten-Year Resource Plan
Table 7 Cost Comparison of Resource Strategies
Over the Range of Emission Cost Adders Assuming Expected Market Prices
($ Millions)
10 Year Plan with Emission Adders Resource Strategy
Zero Level 1 Level 6
Strategy 1 – LT Market Purchase (MP) 43 99 243
Strategy 2 – LT MP, Shoshone Falls upgrade 94 151 295
Strategy 3 – ST MP, 200 MW Peaking
Resource plus Shoshone Falls upgrade
146 203 347
Strategy 4 – LT MP, 100 MW Peaking
Resource plus Shoshone Falls upgrade
129 185 329
To meet Idaho Power Company’s
projected deficiencies and generate
profitable surplus sales when market prices
permit, the peaking resources and Shoshone
Falls upgrade were dispatched against an
expected market price. Capacity factors for
the peaking resources varied from nearly
zero under the low-price scenario to full
load under the high-price scenario. The
market purchase strategy was quantified
using a combination of forward prices at
Mid-Columbia (Mid-C) for the first five
years and a Northwest market price forecast
for the last 5 years of the planning period.
The costs of the resource plan for each
strategy are progressively increased by the
costs of the minimum applicable emission
adders.
Discount Rate
The discount rate used to determine
the present value of the future costs of
potential resources can influence which of
the resources are chosen for the plan. A
high discount rate tends to favor resources
having low initial investment cost, but high
future operating costs such as gas-fired
generation. A low discount rate tends to
favor resources with high investment costs
but low operating costs, such as
hydroelectric generation. Low discount
rates tend to favor resources with a high
percentage of total costs occurring in the
early years of the resource life.
Idaho Power’s after-tax weighted
average cost of capital (WACC) was used as
the discount rate for determining resource
plan costs in the 2002 IRP. The current
after-tax WACC value is 7.6 percent. Other
discount rates are sometimes proposed to
reflect other risks or costs considered
appropriate for resource planning. For
example, a lower discount rate can be used
as a societal rate to emphasize the long-term
costs to society of nonrenewable energy
resource depletion. Conversely, a risk
premium may be added to an after-tax
WACC to reflect higher than normal risk,
such as that inherent in making long-term
resource acquisition commitments.
The sensitivity of the resource
strategies to different WACC/discount rates
has been investigated over a range of rates
from 5.6 percent to 9.6 percent. The
resulting range of present value costs for the
resource strategies is shown in Table 8.
The values presented are influenced not only
by the varying discount rates but also by the
Chapter 6 54 Ten-Year Resource Plan
Table 8 Cost Comparison of Resource Strategies
Over a Range of Discount Rates Assuming Expected Market Prices
($ Millions)
Resource Strategy Discount Rate
5.6% 7.6% 9.6%
Strategy 1 – LT Market Purchase (MP) 49 43 38
Strategy 2 – LT MP, Shoshone Falls upgrade 101 94 88
Strategy 3 – ST MP, 200 MW Peaking
Resource plus Shoshone Falls upgrade
140 146 149
Strategy 4 – LT MP, 100 MW Peaking
Resource plus Shoshone Falls upgrade
130 129 126
associated financing cost assumptions.
Higher financing costs will be offset to a
degree by the higher WACC and the higher
corresponding discount rates. Conversely,
strategies with lower-cost financing
assumptions will be discounted to a lesser
degree when determining the present value
cost.
First, for the generation resources
(Shoshone Falls and the peaking resource)
the financial analysis utilized the levelized
costs shown in Figure 12 and Figure 14.
The peaking resources were assumed to be
simple-cycle combustion turbines. The
costs associated with two peaking facilities
were derived from the estimated $/kW costs,
shown in Figure 14, for the conventional
combustion turbine unit located in Idaho,
and then increasing the size to either 100
MW or 200 MW. The size choices are not
exact and are not based on a specific turbine
or grouping of turbines. In Strategies 3 and
4, final sizing of the peaking resource would
be determined during the project design
phase.
Although the present value
measurement of resource plan costs are
sensitive to the discount rate assumptions,
the discount rate effects over the range of
discount rates analyzed were insufficient to
influence the final selection of a resource
strategy.
Strategy Selection
Since the peaking resources are
long-lived assets with a service life
extending beyond the planning period, a
terminal value was assigned to each resource
strategy to account for remaining asset life
at the end of the planning period.
Table 9 provides a summary of the
net present value of the costs associated with
each of the four resource strategies under
three different market price scenarios - low,
expected and high.
It is important to note that Strategy 1
is not equal to the others in terms of
resources added or deficiency covered, so
the lowest cost strategy is not necessarily the
preferred choice. Details of the financial
analysis are outlined below.
Based on the input received from
the state commissions and the public during
the last year, there is an expressed interest in
Idaho Power becoming more energy-
independent by reducing the reliance on
market purchases, especially at high prices,
Chapter 6 55 Ten-Year Resource Plan
Table 9 10-Year Plan Costs with Market Sales
Low Market Prices Expected Market Prices High Market Prices
Strategy 1 $28,000,000 $43,000,000 $86,000,000
Strategy 2 $76,000,000 $94,000,000 $148,000,000
Strategy 3 $208,000,000 $146,000,000 -$219,000,000
Strategy 4 $143,000,000 $129,000,000 -$6,000,000
and moving away from the median stream-
flow planning criterion. Another concern is
that Idaho Power should own generation
assets, thereby providing customers an
opportunity to receive the benefits of any
profitable surplus sales through the power
cost adjustment (PCA) mechanism. Idaho
Power Company customers have also
expressed an interest in conservation and
green resource development. The public
also recognizes that the regional market
independence and improved reliability
provided by additional generation resources
come with a cost.
While the market purchase strategy
has the lowest cost of the four under several
price scenarios, the market purchase does
not cover the same amount of deficiency
that the other strategies do. Furthermore,
the market purchase strategy does not
increase reliability, initiate the process for
future generation resources, eliminate
forecast transmission overloads or
significantly reduce price risk for IPC
customers.
Strategy 2 is a combination of
market purchases and the Shoshone Falls
upgrade. Except for the addition of the
Shoshone Falls upgrade, Strategy 2 is
primarily a market-based solution. Under
expected market prices, Strategy 2 is $52M
less expensive than Strategy 3. Under the
low-price scenario, Strategy 2 is about
$48M less expensive than Strategy 3.
However, when the high-price scenario is
considered, Strategy 2 is about $367M more
expensive than Strategy 3. The high-priced
market purchases made under Strategy 2 and
the profitable surplus sales during non-
deficit months from the Strategy 3 peaking
resource create the $367M difference.
Strategy 1, the market purchase
strategy, was eliminated from further
consideration primarily because it is not a
viable long-term solution under the 70th
percentile planning criterion. In essence, the
market purchase strategy defers the decision
to add additional resources until the next
IRP.
Under the 70th percentile planning
criterion, additional resources or
transmission is inevitable. Even under a
median water planning criterion, peak-hour
transmission overloads from the Pacific
Northwest are forecast in 2006. Strategy 3 considers a combination
of short-term market purchases, the addition
of 200 MW of capacity and the Shoshone
Falls upgrade. Strategy 3 eliminates
transmission overloads from the Pacific
Northwest until June of 2007.
Considering the number of issues
associated with siting a generation facility,
Idaho Power prefers to begin resource
acquisition sooner, rather that later. If the
decision is deferred until the 2004 IRP, at
least two years of valuable time is lost which
may compromise system reliability. Beginning in July 2007, the
projected transmission overloads from the
Chapter 6 56 Ten-Year Resource Plan
Pacific Northwest increase from 41 MW in
2007 to 336 MW in July 2011. The addition
of 200 MW of capacity between the
Brownlee East and Borah West constraints
provides a significant improvement in
reliability, and reduces Idaho Power’s
dependence on market purchases. Table 9
shows the costs associated with Strategy 3.
The total cost for Strategy 3 ranges from a
cost of $208M under the low-price scenario
to a $219M cost savings under the high-
price scenario. Under the expected market
price scenario, the expected cost is $146M.
The potential benefits of internal
generation under the high-price scenario are
significant. When Strategy 3 is compared to
Strategy 4, the benefits of internal
generation under the high prices become
apparent.
Strategy 4 considers a combination
of long-term market purchases, the addition
of 100 MW of capacity, and the Shoshone
Falls upgrade. However, instead of adding
200 MW of capacity, Strategy 4 adds 100
MW of capacity and 100 MW of firm
market purchases. The net effect is
substituting 100 MW of capacity for 100
MW of firm long-term market purchase.
The total cost for Strategy 4 ranges
from a cost of $143M under the low-price
scenario to a $6M savings under the high-
price scenario. Under the expected market
price scenario, the expected cost is $129M -
about $18M less expensive than Strategy 3.
However, under the high-price scenario,
Strategy 3 generates an extra $213M in
savings due to profitable surplus sales of the
additional 100 MW from the peaking
resource during non-deficit months and
avoids high-priced market purchases.
Price Probability and Strategy Selection
Of the four strategies investigated,
there is no clearly-defined optimum choice.
Each strategy has advantages and
disadvantages. It is very difficult to
determine a least-cost strategy given the
uncertainty in market prices; different
market prices lead to different strategies.
To further analyze the strategies,
probabilities were assigned to each of the
three market scenarios considered. Since
price is unknown, the high-price and the
low-price scenario were both assumed to
have an equal probability of occurrence.
The probability distribution in each price
scenario was assumed to be symmetric
around the expected price. For example, the
probability of the low-price scenario
occurring is 5%; the probability of the high-
price scenario occurring is 5%, and the
probability of the expected-price scenario
occurring is 90%.
The estimated costs under each price
scenario were then multiplied by the
assigned probabilities and summed to
calculate a probability-weighted cost for
each scenario. It was further assumed that
each price scenario was equally likely to
occur. It is assumed to be equally likely for
the distribution to be 1-98-1 (low, expected,
high) as it is to be 20-60-20. In all of the
price scenarios considered, it is assumed
that, in the long run, prices will be closer to
the expected price scenario. The price
scenarios ranged from 0-100-0 to 20-60-20
in which the costs were calculated for each
of the three resource strategies under the
differing price probabilities. The costs for
each strategy were summed over the various
price distribution probabilities to identify the
preferred choice.
For price distribution probabilities
between 0-100-0 and 20-60-20, Strategy 2 is
the least cost. However, Strategy 2 does
nothing to increase reliability or to reduce
market purchases.
For all price distribution probabilities
between 0-100-0 and 19-62-19, Strategy 4 is
less expensive than Strategy 3. If the low-
Chapter 6 57 Ten-Year Resource Plan
or high-price scenarios receive weights of 20
percent or greater, then Strategy 3 is
preferred over Strategy 4. The greater the
likelihood of high market prices, the better it
is to have a generation resource to avoid
high-priced market purchases and make
profitable surplus sales when the resource is
not needed to support native load.
Least-Cost Resource Plan
As noted above, given the
uncertainty in market prices, it is difficult to
identify a least-cost plan because the
assessment of least cost is dependent on the
probabilities assigned to the low-, expected-
and high-market price scenarios.
While Idaho Power can plan to have
sufficient resources to meet the monthly
average energy requirements, it is apparent
that projected peak-hour loads, and,
ultimately, peak-hour transmission
overloads, will drive the need for additional
internal generation and targeted demand-
side measures that focus on peak reduction.
It is appropriate to consider the duration of
the expected peak-hour loads and the
transmission overloads from the Pacific
Northwest. While the magnitude of the
transmission overloads is significant, the
number of hours that the overloads are
projected to occur is limited.
Before implementation of Strategy 4
or the Brownlee to Oxbow Number 2
transmission line project, the projected total
number of Pacific Northwest transmission
overload hours estimated under the 90th
percentile water and 70th percentile load
scenario range from 13 hours in 2003 to 114
hours in 2011 – a total of 402 expected
hours over the planning period (see Figure
10). Under a 70th percentile water and 70th
percentile load scenario, 289 hours of
transmission overload from the Pacific
Northwest are estimated (see Figure 9).
The limited duration of the overloads
illustrates the needle-peak nature of serving
the last increment of load.
Because of the nature of the forecast
peak load conditions, Idaho Power has
identified a blended strategy to meet the
resource needs. Idaho Power believes that
the following plan, which outlines a
balanced approach, has a high probability of
being the least cost for Idaho Power’s
customers.
The plan is based on Strategy 4, a
combination of market purchases and
generation additions, and includes a
transmission upgrade together with an
investigation into demand reduction
measures that are suitable to address the
short duration of projected transmission
overloads.
First, Idaho Power Company plans to
continue to make seasonal market purchases
of 100 aMW in the months of June, July,
November and December throughout the
planning period.
Second, Idaho Power Company
plans to integrate demand-side measures
where economically feasible, to address the
short duration peaks of the system load.
Third, Idaho Power Company plans
to solicit proposals and initiate the siting and
permitting for approximately 100 MW of a
utility owned and operated peaking resource
to be available beginning in 2005.
Fourth, assuming the Idaho PUC
approves the Garnet Power Purchase
Agreement, Idaho Power will purchase up to
250 MW of capacity and associated energy
during periods of peak need beginning June
1, 2005.
Fifth, Idaho Power Company plans
to proceed with the Brownlee to Oxbow
transmission line, expecting the project to be
in service in 2005, increasing the import
capabilities from the Pacific Northwest.
Chapter 6 58 Ten-Year Resource Plan
Sixth, Idaho Power Company plans
to proceed with the Shoshone Falls upgrade
project, expecting the upgrade to be in
service in 2007.
Finally, Idaho Power Company plans
to informally reassess the deficiencies that
remain in 2008 though 2011 prior to 2004.
The deficiencies will be formally assessed in
the 2004 IRP.
A blend of supply-side resources
and demand reduction measures has distinct
advantages for Idaho Power customers.
However, the issue of customer funding for
DSM must be resolved for further progress
to be made. Idaho Power is committed to
cost effective demand-side management
measures so long as the funding is available
prior to initiating the measures
Under the 70th percentile stream
flow and 70th percentile load planning
criteria, the strategy outlined above is
expected to eliminate energy deficiencies
through August 2009 (assuming the peaking
resource is in place by 2005).
Under the 90th percentile stream
flow and 70th percentile load planning
criteria, peak-hour transmission overloads
from the Pacific Northwest in excess of 100
MW occur in July 2003, July 2004, and
again in July 2008. No credit has been
assumed for demand-side measures.
Figure 15 shows the monthly energy
surplus/deficiencies for the 10-year planning
period, assuming that the proposed plan is
implemented under 70th percentile water and
load conditions. Figure 16 shows monthly
peak-hour surplus/deficiency under 90th
percentile water and 70th percentile load
conditions. Figure 17 shows the monthly
peak-hour transmission deficiency from the
Pacific Northwest under the same
conditions.
Impacts on Rates
Impacts on customer’s rates are
derived from changes in capital investments
and expenses. Generally, a $10 million
increase in the Company’s total system rate
base results in a general rate increase of 0.3
percent, while a $10 million increase in
expenditures results in a rate increase of
approximately 1.8 percent.
The least-cost resource plan in the
2002 IRP proposes increases in both
physical plant and purchase power
expenditures from 2002-2011. As
previously mentioned, the plan calls for a
peaking resource in 2005, a hydro plant
upgrade in 2007, and market purchases
throughout the planning period.
Considering investments only and
excluding associated expenses, the addition
of a 100 MW peaking resource ($89 million)
and the Shoshone Falls upgrade ($41
million) would result in a capital investment
of approximately $130 million, or a 3.9
percent rate increase.
The least-cost plan also calls for
purchase power expenses totaling $54
million (at forecasted market prices), or a
9.7 percent rate increase. As a result, an
overall rate increase of approximately 13.6
percent over the planning period can be
estimated for the proposed least-cost
resource plan.
Actual rate impacts would not take
place until the new resources are on-line, or
annually, when market purchases were
made. However, it is important to recognize
that if power is purchased based on meeting
loads under a 70th percentile water and load
conditions and actual conditions turn out to
be more favorable than the 70th percentile,
any surplus energy would be sold and the
sale proceeds would be handled via the PCA
mechanism, helping reduce rates.
Figure 15 Monthly Energy Surplus / Deficiency
70th Percentile Water and Load, Strategy 4 Resources with Garnet
-800
-600
-400
-200
0
200
400
600
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
aM
W
Figure 16 Monthly Peak-hour Surplus / Deficiency
90th Percentile Water, 70th Percentile Load, Strategy 4 Resources with Garnet
-800
-600
-400
-200
0
200
400
600
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
MW
Chapter 6 59 Ten-Year Resource Plan
Figure 17 Monthly NW Transmission Deficit - 90th Percentile Water, 70th Percentile
Load, Strategy 4 Resources with Garnet and Brownlee-Oxbow Transmission Upgrade
-800
-600
-400
-200
0
200
400
600
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
MW
Chapter 6 60 Ten-Year Resource Plan
7. Near-Term Action Plan
Introduction
Customer growth is the primary
driving force behind Idaho Power
Company’s need for additional resources.
Population growth throughout Southern
Idaho, and specifically in the Treasure
Valley, requires additional measures to meet
both peak and energy needs.
Over the past 85 years, Idaho Power
Company has developed a portfolio of
generation resources. IPC believes that a
blended approach based on a portfolio of
options is the most cost-effective and least-
risk method to address the increasing energy
demands of our customers.
Supply-side generation resources are
likely to be the primary method to meet the
increasing energy demands of Idaho Power
Company customers. However, IPC
customers have expressed an interest that all
generation resources be financially,
environmentally, and socially responsible.
Near-Term Action Plan
First, Idaho Power Company plans to
continue to make seasonal market purchases
of 100 aMW in the months of June, July,
November and December throughout the
planning period.
Second, Idaho Power Company
plans to integrate demand-side measures
where economically feasible, to address the
short duration peaks of the system load.
Third, Idaho Power Company plans
to solicit proposals and initiate the siting and
permitting for approximately 100 MW of a
utility owned and operated peaking resource
to be available beginning in 2005.
Fourth, assuming the Idaho PUC
approves the Garnet Power Purchase
Agreement, Idaho Power will purchase up to
250 MW of capacity and associated energy
during periods of peak need beginning June
1, 2005.
Fifth, Idaho Power Company plans
to proceed with the Brownlee to Oxbow
transmission line, expecting the project to be
in service in 2005, increasing the import
capabilities from the Pacific Northwest.
Sixth, Idaho Power Company plans
to proceed with the Shoshone Falls upgrade
project, expecting the upgrade to be in
service in 2007.
Finally, Idaho Power Company plans
to informally reassess the deficiencies that
remain in 2008 though 2011 prior to 2004.
The deficiencies will be formally assessed in
the 2004 IRP.
Market Purchases
Idaho Power customers, the state
legislature, and the IPUC have all
recommended that Idaho Power Company
rely less on the short-term regional power
market to meet long-term energy
deficiencies. IPC agrees with this
assessment. However, the Company
believes that participation in the short-term
market produces distinct financial
advantages for IPC customers. Therefore,
IPC will continue to use the short-term
regional market to balance the system load
and generation, as well as to take advantage
of the short-term market to secure low-cost
energy at a reasonable risk as described in
the Least-Cost Resource Plan.
Purchasing energy and capacity from
the Pacific Northwest long-term market will
continue to be the preferred source of supply
Chapter 7 61 Near-Term Action Plan
Idaho Power Company intends to
initiate a request for proposals (RFP) to
construct approximately 100 MW of simple-
cycle combustion peaking capacity between
the Brownlee East and Borah West
transmission constraints. The RFP process
ensures that the resource will be constructed
at a competitive price for Idaho Power’s
customers.
for a portion of Idaho Power’s incremental
resource needs throughout the planning
period. Idaho Power expects that, for the
remainder of 2002 through 2004 under
adverse water and load conditions, adequate
transmission capability does not exist to
allow all of the required purchases to be
delivered to the Idaho Power system from
the Pacific Northwest.
An important aspect of the ongoing
relicensing process for Idaho Power’s
hydroelectric facilities is identifying the
present and future value of power generation
from the relicensed facility. The integrated
resource planning process will provide an
ongoing basis and methodology to evaluate
the IPC hydroelectric generating facilities
for relicensing consistent with other
resource options. Any proposed
modifications or expansions of generating
capacity at existing hydroelectric facilities,
such as the Shoshone Falls upgrade, will be
evaluated within the IRP methodology.
A combination of purchases from
utilities to the northeast or southeast,
targeted demand reduction measures, and
temporary generation resources may be
necessary to fulfill any remaining
requirements. However, there is some
degree of uncertainty regarding the
availability of both generation and
transmission from the utilities to the
northeast and southeast.
Generation Resources
Population growth in Southern
Idaho is an inescapable fact. IPC will need
physical resources, such as the Evander
Andrews Power Complex near Mountain
Home, Idaho, to meet the energy demands
of the additional customers. Idaho Power
Company will continue to analyze resource
additions and select resources that
responsibly meet the needs of our
customers.
Transmission Resources
Idaho Power Company is currently
pursuing the Brownlee to Oxbow
transmission upgrade and expects to begin
construction in 2004. The project has been
identified as the most cost-effective
alternative to expand transmission capacity
and import electrical power from other
generation sources through the
interconnected transmission line grid in the
Western United States.
Idaho Power will continue with
cost-effective incremental efficiency
upgrades to existing generation facilities,
including possible turbine upgrades at the
Boardman and Valmy plants and the
Shoshone Falls upgrade.
The Brownlee to Oxbow project will
increase the reliability of Idaho Power’s
transmission system, and increase the
Brownlee East transmission capacity by
approximately 100 MW. The expected
service date is November 2004.
In recognition of seasonal peak
deficiencies and recognizing the limitations
of the transmission system to allow the
deficits to be covered solely by off-system
purchases, Idaho Power will need to acquire
additional peaking resources.
Chapter 7 62 Near-Term Action Plan
Demand-Side Management,
Energy Conservation, and
Pricing Options
Socially responsible conservation
and energy efficiency means doing more
with less, rather than doing without. Idaho
Power Company will continue to support
energy efficiency at our facilities and our
customers’ facilities. Idaho Power
Company plans to continue active
participation in regional conservation
efforts.
Due to the nature and timing of the
projected energy deficits and transmission
overloads, conservation and demand-side
measures must be carefully designed and
targeted to cost-effectively address the
projected peak deficits. Idaho Power
Company anticipates the addition of targeted
demand-side management, targeted pricing
options, and targeted energy conservation
programs.
Idaho Power will also proceed with
plans to improve energy efficiency at
company facilities, including office
buildings, local offices, maintenance yards,
small buildings, and power plants.
Green Energy
Idaho Power Company is supportive
of the Green Power Program (Schedule 62).
To meet the needs of customers desiring this
product, Idaho Power plans to include
additional green energy in the IPC
generation portfolio. In addition, IPC has
identified two specific near-term actions to
be initiated during the next two years:
1. Idaho Power Company anticipates
participating in educational and
demonstrational energy projects with
the focus on green resources.
2. Idaho Power intends to dedicate up
to $50,000 to explore the feasibility
of constructing a pilot anaerobic
digester project within the IPC
service territory.
In addition to the near-term actions,
Idaho Power anticipates adding a utility
scale (50 to 100 MW) wind project within
its service territory. The exact timing,
location, and size of the wind project will be
determined by events listed below. Idaho
Power anticipates using an RFP process to
develop a wind project.
Because of the intermittent nature of
wind generation, Idaho Power views wind
generation primarily as an energy resource
and not a peaking resource. Considering the
seasonal and peak nature of Idaho Power’s
projected deficiencies, Idaho Power does not
anticipate adding a wind project to address
seasonal energy and capacity needs.
However, the addition of a wind project
could be triggered at any time by any of the
following events:
1. Increased customer demand for
green energy as measured through
Idaho Power’s existing Green Power
Program. If Idaho Power customers’
demand for Green Power increases
to 15 aMW, then Idaho Power will
initiate a RFP for a wind project
sized to meet this need (a 50 MW
project operating at a 30 percent
capacity factor would provide 15
aMW).
2. Public Utility Commission or
Legislative action (either unsolicited
or in response to an Idaho Power
proposal) for Idaho Power to add a
wind project to its generation
portfolio and regulatory approval to
add the project into ratebase for cost
recovery.
3. A change in Idaho Power’s projected
surplus/deficiency that indicates the
need to add an energy resource.
Chapter 7 63 Near-Term Action Plan
Idaho Power Company and the
Commissions must agree on mechanisms
that ensure prompt recovery of prudent costs
incurred for the pilot and demonstration
projects.
Idaho Power Company continually
works to improve its resource planning
process and has recently made
organizational changes to further improve
integrated resource planning. Idaho Power
Company agrees with the Idaho Public
Utility Commission that integrated resource
planning will continue to be an important
and ongoing activity at Idaho Power
Company.
Chapter 7 64 Near-Term Action Plan