Loading...
HomeMy WebLinkAbout20181026IPC Rep to MSJ 38.pdfDEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] Steven B. Andersen (ISB 2618) sba@aswblaw.com Wade L. Woodard (ISB 6312) wlw@aswblaw.com ANDERSEN SCHWARTZMAN WOODARD BRAILSFORD, PLLC 101 South Capitol Boulevard, Suite 1600 Boise, ID 83702-7720 Telephone: 208.342.4411 Facsimile: 208.342.4455 Donovan E. Walker (ISB 5921) dwalker@idahopower.com IDAHO POWER COMPANY 1221 West Idaho Street (83702) P. O. Box 70 Boise, ID 83707 Telephone: 208.388.5317 Facsimile: 208.388.6936 Attorneys for Defendant-Intervenor Idaho Power Company IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF IDAHO FRANKLIN ENERGY STORAGE ONE, LLC, FRANKLIN ENERGY STORAGE TWO, LLC, FRANKLIN ENERGY STORAGE THREE, LLC, FRANKLIN ENERGY STORAGE FOUR, LLC, Plaintiffs, vs. PAUL KJELLANDER, KRISTINE RAPER and ERIC ANDERSON, in their official capacity as Commissioners of the IDAHO PUBLIC UTILITIES COMMISSION, Defendants, and, IDAHO POWER COMPANY, Defendant-Intervenor. Case No.: 1:18-cv-00236-REB DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 1 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - i TABLE OF CONTENTS I. INTRODUCTION .......................................................................................................... 1 II. FACTUAL AND PROCEDURAL BACKGROUND.................................................... 2 A. Facts regarding PURPA, FERC’s Regulations and the IPUC’s Implementation Thereof ...................................................................................................................... 2 B. Facts Regarding Idaho Power ................................................................................... 5 C. Facts Regarding Plaintiffs’ QF Applications ............................................................ 5 D. Facts Regarding the Underlying Administrative Actions and Orders ...................... 7 III. ARGUMENT .................................................................................................................. 9 A. Plaintiffs’ Motion Must be Denied Because Their Claim is Time-Barred ............... 9 B. Plaintiffs’ Motion Must be Denied Because Their Untimely Challenge of the IPUC’s Orders Constitute an Improper Collateral Attack on Final Orders That Have Preclusive Effect ............................................................................................ 11 C. Plaintiffs’ Motion Must be Denied Because Their Challenge is an As-Applied Challenge that Falls Exclusively Within the State’s Jurisdiction ........................... 13 D. Plaintiffs’ Motion Must be Denied Because the IPUC Did Not Determine Plaintiffs’ QF Status, Nor Are Plaintiffs Entitled to a Certain Rate or Term ......... 16 1. The IPUC Did Not Determine Plaintiffs’ QF Status ...................................... 17 2. PURPA Does Not “Vest” in Plaintiffs or Entitle Them to Any Specific Rate or Contract Term ................................................................................................. 19 E. Contrary to Plaintiffs’ Claim, the IPUC’s Orders Do Not Create Any Irreconcilable Conflict Between State and Federal Law ............................................................... 20 IV. CONCLUSION ............................................................................................................. 20 Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 2 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - ii TABLE OF AUTHORITIES Cases A.W. Brown Co., Inc. v. Idaho Power Co., 121 Idaho 812 (1992) ................................................. 4 Afton Energy, Inc. v. Idaho Power Co., 107 Idaho 781 (1984) .................................................. 3, 4 Allco Renewable Energy Ltd. v. Mass. Elec. Co., 875 F.3d 64 (1st Cir. 2017) ............ 2, 13, 14, 19 Cal. Pub. Utils. Comm’n, 133 FERC ¶ 61,059 (2010) ............................................................. 3, 19 Crossroads Cogeneration Corp. v. Orange & Rockland Utils., Inc., 159 F.3d 129 (3d Cir. 1998) ................................................................................................................................................... 12 Dias v. Elique, 436 F.3d 1125 (9th Cir. 2006) .............................................................................. 12 Empire Lumber Co. v. Wash. Water Power Co., 114 Idaho 191 (1987) ........................................ 4 Exelon Wind 1, L.L.C. v. Nelson, 766 F.3d 380 (5th Cir. 2014) ......................... 2, 3, 13, 14, 15, 19 FERC v. Mississippi, 456 U.S. 742 (1982) ................................................................................. 2, 3 Greensboro Lumber Co. v. Georgia Power Co., 643 F.Supp. 1345 (N.D. Ga. 1986) ..... 14, 15, 16 Idaho Power Co. v. Idaho Pub. Utils. Comm’n, 155 Idaho 780 (2013) ..................................... 3, 4 Independent Energy Productions Association, Inc. v. California Public Utilities Commission, 36 F.3d 848 (9th Cir. 1994) ............................................................................................... 17, 18, 19 J & J Contractors/O.T. Davis Const., A.J.V. v. State, 118 Idaho 535 (1990) .............................. 12 Luz Dev. & Fin. Corp., 51 FERC ¶ 61,078 (1990). .................................................................. 4, 18 Mass. Inst. of Tech. v. Mass. Dept. of Pub. Utils., 941 F.Supp. 233 (D. Mass. 1996) ........... 15, 16 N.Y. State Elec. & Gas Corp. v. Saranac Power Partners, LP, 117 F.Supp.2d 211 (N.D.N.Y. 2000) ............................................................................................................................... 9, 10, 11 Neal v. Harris, 100 Idaho 348 (1979) ........................................................................................... 10 Niagara Mohawk Power Corp. v. FERC, 306 F.3d 1264 (2d Cir. 2002) ..................................... 10 Portland Gen. Elec. Co. v. FERC, 854 F.3d 692 (D.C. Cir. 2017)................................................. 3 Power Res. Grp. v. Pub. Util. Comm’n of Tex., 422 F.3d 231 (5th Cir. 2005) ........................ 3, 15 Power Res. Grp., Inc. v. Pub. Util. Comm’n, 73 S.W.3d 354 (Tex.App.-Austin 2002) ............... 15 Power Resource II, No. 1:03-CV-762-HLH, Dkt. No. 44 ............................................................ 15 Roche Prods., Inc., et al., 29 FERC ¶ 61,098 (1984) ................................................................... 14 Rosebud Enters., Inc. v. Idaho Pub. Utils. Comm’n, 128 Idaho 609 (1996) .................................. 4 Silkwood v. Kerr-McGee Corp., 464 U.S. 238 (1984) .................................................................. 20 Snow Mountain Pine Co. v. CP Nat’l Corp., 30 FERC ¶ 61,293 (1985) ..................................... 14 Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 3 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - iii Ticor Title Co. v. Stanion, 144 Idaho 119 (2007) ......................................................................... 13 Utah-Idaho Sugar Co. v. Intermountain Gas Co., 100 Idaho 368 (1979). ............................. 12, 13 Welch v. Del Monte Corp., 128 Idaho 513 (1996) ........................................................................ 11 Statutes 16 U.S.C. § 824a ............................................................................................................................. 9 16 U.S.C. § 824a-3(a)(1)........................................................................................................... 2, 19 16 U.S.C. § 824a-3(a)(2)........................................................................................................... 2, 19 16 U.S.C. § 824a-3(a) ..................................................................................................................... 2 16 U.S.C. § 824a-3(b) ..................................................................................................................... 2 16 U.S.C. § 824a-3(b) ..................................................................................................................... 2 16 U.S.C. § 824a-3(d) ..................................................................................................................... 2 16 U.S.C. § 824a-3(f) ............................................................................................................ 2, 3, 13 16 U.S.C. § 824a-3(g) ................................................................................................................... 13 16 U.S.C. § 824a-3(g)(2) .............................................................................................................. 14 16 U.S.C. § 824a-3(h) ................................................................................................................... 14 16 U.S.C. § 824a-3(h)(2)(A) ......................................................................................................... 13 16 U.S.C. § 824a-3(h)(2)(B) ................................................................................................... 11, 13 18 C.F.R. § 292.101 ........................................................................................................................ 9 18 C.F.R. § 292.304(b)(2) ......................................................................................................... 2, 19 18 C.F.R. § 292.304(c)(1) ........................................................................................................... 3, 4 18 C.F.R. § 292.304(c)(2) ........................................................................................................... 3, 4 18 C.F.R. § 292.304(c)(3)(ii) ................................................................................................ 3, 4, 19 18 C.F.R. § 292.304(e)(2)(iii) ......................................................................................................... 3 I.C. §§ 61-502 ................................................................................................................................. 4 I.C. §§ 61-503 ................................................................................................................................. 4 I.C. § 61-625 ................................................................................................................................. 11 I. C. § 61-626 ................................................................................................................................ 12 I.C. § 61-627 ............................................................................................................................. 8, 12 Idaho Public Utilities Commission Orders Order No. 32262 (2011) ..................................................................................................................................... 5 Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 4 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - iv Order No. 32697 (2012) .................................................................................................................. 4 Order No. 33357 (2015) .................................................................................................................. 5 Rules I.A.R. 14(b). .............................................................................................................................. 8, 10 I.A.R. 21 ........................................................................................................................................ 11 Other Policy Statement Regarding the Commission's Enforcement Role Under Section 210 of the Public Utility Regulatory Policies Act of 1978, 23 FERC § 61, 304 (1983) ...................... 14, 16 Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 5 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 1 Defendant-Intervenor Idaho Power Company (“Idaho Power”), by and through its counsel of record, hereby submits this Response to Plaintiffs’ Motion for Summary Judgment [Dkt. 29]. I. INTRODUCTION Plaintiffs’ motion, which is replete with factual and legal inaccuracies and wholly unsupported contentions, should not only be denied, but summary judgment should be granted against them and in favor of Defendants.1 This entire case is based upon Plaintiffs’ fundamentally flawed and blatantly erroneous claim that the allegedly offending party, the Idaho Public Utilities Commission (“IPUC”), has repeatedly and explicitly disavowed. According to Plaintiffs, in ruling upon Idaho Power’s Petition for Declaratory Relief (“Petition”) regarding the rates and terms of any contracts it must enter into with Plaintiffs under the Public Utility Regulatory Policies Act of 1978 (“PURPA”), the IPUC determined Plaintiffs’ Qualifying Facility (“QF”) status, thereby intruding upon the exclusive jurisdiction of the Federal Energy Regulatory Commission (“FERC”). Contrary to Plaintiffs’ claim, not only did Idaho Power assume Plaintiffs’ QF status for purposes of its Petition, but so too did the IPUC in ruling upon that Petition. In fact, the IPUC expressly stated as such in both orders at issue in this matter and described Plaintiffs’ argument to the contrary as “a frivolous effort to contrive a legal basis for reconsideration.” (Ex. 12, p. 3.2) Therefore, because the IPUC did not determine Plaintiffs’ QF status, their motion must be denied. Plaintiffs’ motion must also be denied because their claim (1) is time-barred; (2) constitutes an improper collateral attack on the IPUC’s final orders that have preclusive effect; and (3) is an as-applied claim over which this Court lacks jurisdiction. Consequently, as discussed more fully below, Plaintiffs’ motion must be denied in its entirety. 1 Idaho Power files concurrently herewith its cross Motion for Summary Judgment. 2 All exhibits cited to herein are attached to the Declaration of Donovan E. Walker (“Walker Decl.”) filed concurrently herewith. Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 6 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 2 II. FACTUAL AND PROCEDURAL BACKGROUND A. Facts Regarding PURPA, FERC’s Regulations and the IPUC’s Implementation Thereof Congress enacted PURPA “to reduce the dependence of electric utilities on foreign oil and natural gas and to control consumer costs.” Exelon Wind 1, L.L.C. v. Nelson, 766 F.3d 380, 384 (5th Cir. 2014); also FERC v. Mississippi, 456 U.S. 742, 745 (1982) (“Mississippi”). To accomplish these goals, PURPA directs FERC to promulgate rules mandating that electric utilities purchase energy from cogeneration and small power production facilities, which are known as QFs. Id.; also Allco Renewable Energy Ltd. v. Mass. Elec. Co., 875 F.3d 64, 67 (1st Cir. 2017); 16 U.S.C. § 824a-3(a), (b). Despite seeking to promote energy generation by QFs, Congress did not intend to do so at the expense of American consumers and, as such, PURPA strikes a balance between these two interests. Exelon, 766 F.3d at 384. For example, “PURPA requires utilities to purchase power generated by [QFs], but also mandates that the rates that utilities pay for such power ‘shall be just and reasonable to the electric consumers of the electric utility and in the public interest.’” Id. (citing 16 U.S.C. § 824a-3(a)(2), (b)(1)). Additionally, the rates utilities are to pay QFs for their power cannot exceed the “incremental cost to the electric utility of alternative electric energy.” Allco, 875 F.3d at 67; 16 U.S.C. § 824a-3(b). PURPA defines “incremental cost” as “the cost to the electric utility of the electric energy which, but for the purchase from such cogenerator or small power producer, such utility would generate or purchase from another source.” 16 U.S.C. § 824a-3(d). In accordance with PURPA’s directive, “FERC promulgated regulations requiring utilities to purchase electricity from QFs ‘at a rate equal to the utility’s full avoided cost.’” Allco, 875 F.3d at 67; 18 C.F.R. § 292.304(b)(2). PURPA also requires state regulatory authorities to implement FERC’s rules. Mississippi, 456 U.S. at 751; also 16 U.S.C. § 824a-3(f). A state commission such as the IPUC can comply Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 7 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 3 with its implementation obligations by “issuing regulations, by resolving disputes on a case-by- case basis, or by taking any other action reasonably designed to give effect to FERC’s rules.” Id. FERC provides state agencies “great latitude in determining the manner of implementation of [FERC’s] rules, provided that the manner chosen is reasonably designed to implement the requirements” of FERC’s regulations. Exelon, 766 F.3d at 385. Given this substantial latitude, FERC is “reluctant to second guess the state commission’s determinations.” Cal. Pub. Utils. Comm’n, 133 FERC ¶ 61,059, at P 24 (2010) (“CPUC”). Under PURPA and FERC’s regulations, states are responsible for regulating and authorizing agreements under which a utility purchases energy from a QF, including “determin[ing] the specific parameters” of any such agreement. Power Res. Grp. v. Pub. Util. Comm’n of Tex., 422 F.3d 231, 238 (5th Cir. 2005); also Idaho Power Co. v. Idaho Pub. Utils. Comm’n, 155 Idaho 780, 786-89 (2013). As part of this responsibility, states calculate the avoided cost rates, determine if and when a legally enforceable obligation is established and determine the length and terms of any agreement. Id.; also Portland Gen. Elec. Co. v. FERC, 854 F.3d 692, 695 (D.C. Cir. 2017); Afton Energy, Inc. v. Idaho Power Co., 107 Idaho 781, 785-86 (1984); 18 C.F.R. § 292.304(c)(1), (2). With respect to determining avoided cost rates, one factor to be considered is “the terms of any contract including the duration of the obligation.” CPUC, 133 FERC ¶ 61,059, at P 23; also 18 C.F.R. § 292.304(e)(2)(iii). Also, avoided cost rates may “differentiate among qualifying facilities using various technologies on the basis of the supply characteristics of the different technologies.” Id.; also 18 C.F.R. § 292.304(c)(3)(ii). To date, FERC has only considered battery storage QFs in one decision, finding that: [T]he primary energy source of the battery system is not the electro- chemical reaction. Rather, it is the electric energy which is utilized to initiate that reaction, for without that energy, the storage facility could not store or produce the electric energy which is to be Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 8 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 4 delivered at some later time. Since this energy is the primary energy source of the facility, it is necessary to look to the source of this energy as the ultimate primary energy source of the facility. Luz Dev. & Fin. Corp., 51 FERC ¶ 61,078, at 61,171 (1990). Idaho has implemented PURPA consistent with federal and state law. The IPUC has the authority and is the appropriate state forum to establish avoided cost rates, to set standard/published rate eligibility caps that exceed the 100 kilowatt (“kW”) minimum, to review and approve contracts and to resolve disputes between QFs and electric utilities. I.C. §§ 61-502, 61-503; Idaho Power Co., 155 Idaho at 786-89; A.W. Brown Co., Inc. v. Idaho Power Co., 121 Idaho 812, 816 (1992); Empire Lumber Co. v. Wash. Water Power Co., 114 Idaho 191, 192 (1987); Afton Energy, 107 Idaho at 785-86. The IPUC has implemented PURPA by issuing general procedures and engaging in case-by-case analysis. Rosebud Enters., Inc. v. Idaho Pub. Utils. Comm’n, 128 Idaho 609, 615 (1996). Of relevance, FERC’s regulations require state commissions to set “standard rates for purchases from [QFs] with a design capacity of 100 kilowatts or less,” and permit them to set “standard rates for purchases from [QFs] with a design capacity of more than 100 kilowatts.” 18 C.F.R. § 292.304(c)(1), (2). Consistent with these regulations, the IPUC has established two methods for calculating avoided cost rates that depend upon the QF’s size: (1) the surrogate avoided resource (“SAR”) method; and (2) the integrated resource plan (“IRP”) method. See IPUC Order No. 32697, pp. 7-8 (2012). Similarly consistent with FERC’s regulation that standard rates “[m]ay differentiate among [QFs] using various technologies…,” 18 C.F.R. § 292.304(c)(3)(ii), the IPUC has set the eligibility cap for wind and solar QFs to access published avoided cost rates at 100 kilowatts (kW). IPUC Order No. 32697, p. 13 (2012). Published avoided cost rates are available for QFs of all other resource types with a design capacity of up to 10 average megawatts Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 9 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 5 (aMW). Id. at pp. 7-8. The IPUC established these eligibility caps while investigating “disaggregation” – the breaking up of one large project “into smaller projects ‘in order to obtain published avoided cost rates that exceed a utility’s actual avoided cost’” – by solar and wind QFs. IPUC Order No. 32262, p. 3 (2011). As for the length of PURPA contracts, the IPUC has established 20-year terms for standard published rate contracts. See IPUC Order No. 33357, pp. 1, 7 (2015). For non-standard, IRP- based contracts, the IPUC found that a two-year term was reasonable, consistent with PURPA’s intent and FERC’s regulations and appropriately balanced the competing interests of protecting ratepayers and developing QF power generation. Id. at p. 25. B. Facts Regarding Idaho Power Idaho Power is a vertically integrated electric utility engaged in the business of generating, purchasing, transmitting and distributing electrical energy. Idaho Power is subject to the provisions of PURPA, as implemented by the rules and regulations of the IPUC and FERC. C. Facts Regarding Plaintiffs’ QF Applications In January 2017, Plaintiffs each filed a Form 556, entitled “Certification of Qualifying Facility (QF) Status for a Small Power Production or Cogeneration Facility” (“Form 556”), with FERC, in which they each self-certified themselves to be battery storage QFs. (Dkt. 37, Stipulated Fact [“SF”] 4; Exs. 1-4.) Pursuant to the Form 556s, each of Plaintiffs’ battery storage facilities has a nameplate design capacity of 32,000 kW, is located on the same site and is being developed by Alternative Power Development, LLC. (Dkt. 37, SF 1; Exs. 1-5.) Additionally, the primary energy source for each battery storage facility is solar. (Id.) Specifically, not only does each QF’s hourly generation output profile generally match the shape, timing and output of a solar generation Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 10 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 6 profile, (Walker Decl., ¶ 17; Exs. 1-4, Generation Profile), but Plaintiffs’ respective Form 556s describe each facility’s power source as follows: The energy storage system that comprises the energy storage Qualifying Facility is designed to, and will, receive 100% of its energy input from a combination of renewable energy sources such as wind, solar, biogas, biomas, etc. The current initial design utilizes solar photovoltaic (PV) modules mounted to single-axis trackers to provide the electric energy input to the Qualifying Facility’s battery storage system. The PV modules are planned to be connected in series/parallel combinations to solar inverters, rated approximately 2.5 MWac each, (subject to change). (Exs. 1-4, Form 556, p. 9, emphasis added.) In late January 2017, Plaintiffs submitted to Idaho Power their respective Schedule 73 Qualifying Facility Energy Sales Agreement Request (“Schedule 73”), along with their Form 556 and a generation output profile. (Dkt. 37, SF 5; Exs. 1-4.) In their Schedule 73 applications, Plaintiffs each requested published avoided cost rates and a 20-year contract from Idaho Power. (Id.) Idaho Power responded to Plaintiffs’ applications with a letter dated February 9, 2017.3 (Dkt. 37, SF 6; Ex. 6.) In that letter, Idaho Power notified Plaintiffs’ counsel that the applications were incomplete, identified several deficiencies and stated that “it does not appear that your proposed projects qualify for Rate 4 Option – Non-Levelized Non-Fueled Rates and a twenty (20) year contract term.” (Ex. 6.) Plaintiffs’ counsel responded by letter dated February 10, 2017, purporting to address the deficiencies in Plaintiffs’ applications and demanding that Idaho Power proffer 20-year, published avoided cost rates for each facility. (Dkt. 37, SF 7; Ex. 7.) By letter 3 Plaintiffs disingenuously claim that “Idaho Power did not respond directly to [Plaintiffs’] requests for standard offer twenty-year contracts” and, instead, “sought a declaratory ruling from the IPUC.” (Dkt. 29-1, p. 6.) Such a contention is blatantly false as evidenced by Exhibits 6 and 8. In fact, Plaintiffs directly contradict this misrepresentation through Contract Facts 2 and 4, which are stated in Plaintiffs’ very own “Concise Statement of Facts in Support of Motion for Summary Judgment.” (Dkt. 29-4, pp. 3, 4.) Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 11 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 7 dated February 27, 2017, Idaho Power responded, stating that it did not agree that Plaintiffs were eligible for published rates and 20-year contracts and notifying Plaintiffs’ counsel that it had filed its Petition with the IPUC that same day. (Dkt. 37, SF 8; Ex. 8.) D. Facts Regarding the Underlying Administrative Actions and Orders On February 27, 2017, Idaho Power filed its Petition, in which it asked the IPUC for a determination of Plaintiffs’ proposed battery storage projects’ eligibility for published avoided cost rates and 20-year contract terms. (Dkt. 37, SF 9; Ex. 9.) In its Petition, Idaho Power argued that Plaintiffs’ proposed facilities’ eligibility for published rates should be limited to the 100kW available to solar QFs based upon the facilities’ fuel source. (Ex. 9.) Idaho Power did not dispute Plaintiffs’ QF self-certification as battery storage facilities and, in fact, it asked the IPUC to assume the validity of these self-certifications without prejudice to Idaho Power’s ability to separately challenge them before FERC, the proper authority to determine QF status. (Id. at p. 6.) On July 13, 2017, the IPUC issued Order No. 33785, in which it issued its ruling on Idaho Power’s Petition. (Dkt. 37, SF 10; Ex. 10.) In this Order, the IPUC acknowledged that Idaho Power had not and was not challenging Plaintiffs’ asserted QF status and confirmed that “[t]he battery storage facilities’ QF status is a matter within FERC’s jurisdiction and is not at issue in this case.” (Ex. 10, pp. 3, 11.) In this Order, the IPUC also determined that, because the primary energy source of Plaintiffs’ battery storage facilities is solar and their design capacities exceed 100 kW, Plaintiffs are not entitled to published avoided cost rates and 20-year contracts and, instead, are entitled to negotiate two-year contracts that use Idaho’s IRP-based avoided cost methodology, identical to solar and wind QFs. (Id. at pp. 12-13.) On August 3, 2017, Plaintiffs filed a Petition for Reconsideration of Order No. 33785. (Dkt. 37, SF 11; Ex. 11.) Plaintiffs’ only basis for error was that the IPUC improperly determined Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 12 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 8 Plaintiffs’ QF status. (Ex. 11.) On August 29, 2017, the IPUC issued Order No. 33858, in which it denied Plaintiffs’ Petition for Reconsideration and stated in pertinent part as follows: [Plaintiffs] assert[] that, contrary to Indep. Energy Producers, we determined the QF status of battery storage facilities in the Final Order. We did not. [Plaintiffs’] mischaracterization of our Final Order is a frivolous effort to contrive a legal basis for reconsideration. (Dkt. 37, SF 12; Ex. 12, p. 3.) Plaintiffs had 42 days from the date of Order No. 33858 to file a Notice of Appeal to the Idaho Supreme Court under Idaho Code § 61-627 and Idaho Appellate Rule 14(b). See I.C. § 61- 627; I.A.R. 14(b). Plaintiffs, however, never filed any such appeal and, in fact, to date they have not appealed either IPUC Order No. 33785 or 33858 to any state court in Idaho. (Dkt. 37, SF 13.) Instead, on December 14, 2017, two months after the time within which Plaintiffs had to file an appeal of the IPUC’s decision had expired, they filed a Petition for Declaratory Order and Petition for Enforcement Pursuant to Section 210(h) of the Public Utility Regulatory Policies Act of 1978 with FERC (“FERC Petition”). (Dkt. 37, SF 14; Ex. 13.) On February 15, 2018, FERC issued a Notice of Intent Not to Act, in which it declined to initiate an enforcement action pursuant to Section 210(h)(2)(A) of PURPA as requested by Plaintiffs. (Dkt. 37, SF 15, Ex. 14.) In light of FERC’s refusal to act, on May 30, 2018, Plaintiffs commenced the instant lawsuit against the IPUC by filing their Complaint for Violation of the Federal Power Act, the Public Utilities Regulatory Policies Act of 1978, and Federal Energy Regulatory Commission Regulations. (Dkt. 1.) Two days later, on June 1, 2018, Plaintiffs filed their First Amended Complaint in which they substituted three IPUC’s Commissioners in as party defendants. (Dkt. 2.) In their operative complaint, Plaintiffs again allege, as they did before the IPUC and FERC, that, in making its ruling as to the rates and contract terms that Plaintiffs are eligible for with Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 13 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 9 respect to their proposed battery storage facilities, the IPUC improperly determined Plaintiffs’ QF status. (Exs. 11, 13; Dkts. 1, 2.) To rectify this allegedly improper action by the IPUC, Plaintiffs ask this Court to find that IPUC Order Nos. 33785 and 33858 are erroneous and that, instead of being limited to two-year contracts that use Idaho’s IRP-based avoided cost methodology, they are entitled to published avoided cost rates and 20-year contracts. III. ARGUMENT A. Plaintiffs’ Motion Must Be Denied Because Their Claim is Time-Barred As with any other claim, Plaintiffs’ instant challenge to the IPUC’s orders must be brought within the applicable limitations period. Neither PURPA nor FERC’s regulations contain any such period. See 16 U.S.C. § 824a et seq.; 18 C.F.R. § 292.101 et seq. As a result, and because there is no federal limitations period directly applicable to PURPA enforcement actions under Section 210(h), courts addressing this issue have applied the “well-settled” rule that “if Congress fails to include a statute of limitations in a statute, courts should – with few exceptions – impose a state limitations ‘most closely analogous’ to the federal act in need.” N.Y. State Elec. & Gas Corp. v. Saranac Power Partners, LP, 117 F.Supp.2d 211, 246 (N.D.N.Y. 2000) (“NYSEG”). An exception to this rule is when applying a state limitations period would “frustrate or interfere with the implementation of national policies or be at odds with the purpose or operation of federal substantive law.” Id. PURPA enforcement actions, however, “fall[] squarely inside the rule, not the exception.” Id. at 247. In NYSEG, when the Northern District of New York addressed this issue, it determined that the most closely analogous state limitations period was the one applicable to the appeal of final agency actions. See id. at 246-47. It further held that, because the plaintiff failed to commence its PURPA enforcement proceeding within this limitations period, the claim was time-barred. Id. Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 14 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 10 Under Idaho law, any IPUC decision must be appealed within 42 days of the date any application for rehearing is denied. I.A.R. 14(b); see Neal v. Harris, 100 Idaho 348, 350 (1979) (noting that Idaho Appellate Rule 14 limits the time to appeal IPUC decisions). Specifically, Idaho Appellate Rule 14(b) provides in pertinent part as follows: (b) Appeals From an Administrative Agency. An appeal as a matter of right from an administrative agency may be made only by physically filing a notice of appeal with the Public Utilities Commission…within 42 days from the date evidenced by the filing stamp of the clerk or secretary of the administrative agency on any decision, order or award appealable as a matter of right. … The time for an appeal from such decision, order or award of the public utilities commission begins to run when an application for rehearing is denied, or, if the application is granted, after the date evidenced by the filing stamp on the decision on rehearing. Here, the IPUC issued Order No. 33858 denying Plaintiffs’ Motion for Reconsideration on August 29, 2017. (Dkt. 37, SF 12; Ex. 12.) Pursuant to Idaho Appellate Rule 14(b), Plaintiffs had 42 days therefrom – until October 10, 2017 – to appeal that order and, in turn, the IPUC’s Order No. 33785 that was the subject of Plaintiffs’ Motion for Reconsideration. I.A.R. 14(b). Plaintiffs failed to comply with this limitations period and, in fact, to date they have not appealed either of the IPUC’s orders to any state court in Idaho. (Dkt. 37, SF 13.) Instead, the first attempt Plaintiffs made to challenge the orders was when they filed their FERC Petition on December 14, 2017, over two months after the limitations period had already expired. (Dkt.37, SF 13, 14.) The timely filing of a petition with FERC is a jurisdictional prerequisite to Plaintiffs’ current attempt to seek relief from the instant Court. See NYSEG, 117 F.Supp.2d at 246-47 (PURPA enforcement actions not filed within the state limitations period for appealing agency orders are time-barred); Niagara Mohawk Power Corp. v. FERC, 306 F.3d 1264, 1269-70 (2d Cir. 2002) (a district court lacks subject matter jurisdiction if a plaintiff fails to exhaust its administrative remedy by petitioning FERC to bring an enforcement action prior to suing in federal Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 15 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 11 court); I.A.R. 21 (the failure to file a timely notice of appeal is jurisdictional and requires automatic dismissal of the appeal); see also 16 U.S.C. § 824a-3(h)(2)(B). Therefore, because Plaintiffs failed to challenge the IPUC’s orders until after the applicable limitations period set forth in Idaho Appellate Rule 14(b) had expired, their claims are time-barred and this Court lacks subject matter jurisdiction over them. As a result, Plaintiffs’ motion must be denied. B. Plaintiffs’ Motion Must Be Denied Because Their Untimely Challenge of the IPUC’s Orders Constitute an Improper Collateral Attack on Final Orders That Have Preclusive Effect As noted, Plaintiffs never appealed IPUC Order Nos. 33785 or 33858 to any Idaho state court, nor did they challenge those orders in any other court or administrative agency within the applicable 42 day limitations period set forth in Idaho Appellate Rule 14(b). (See Section III.A, supra.) As a result, these orders became final, conclusive and beyond this Court’s jurisdiction to review. See e.g., I.A.R. 21 (the failure to file a timely notice of appeal is jurisdictional and requires automatic dismissal of the appeal); Welch v. Del Monte Corp., 128 Idaho 513, 516 (1996) (holding that failing to timely appeal an order of the Idaho Industrial Commission results in the findings of fact and conclusions of law contained therein becoming conclusive and precluding further adjudication of those facts and issues). As a result, Plaintiffs are now barred from attacking those orders collaterally through the instant federal action. NYSEG, 117 F.Supp.2d at 247-48; also I.C. § 61-625 (“All orders and decisions of the commission which have become final and conclusive shall not be attacked collaterally”). The strong public policy considerations supporting the rule prohibiting collateral attacks on final orders has long been recognized by the Idaho Supreme Court: The legislature has afforded the orders of the [Idaho Public Utilities] Commission a degree of finality similar to that possessed by judgments made by a court of law. I.C. s 61-625 reads as follows: … “All orders and decisions of the commission which have become final and conclusive shall not be attacked collaterally.” … Final orders of the Commission should ordinarily be challenged either by Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 16 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 12 petition to the Commission for rehearing or by appeal to this Court as provided by I.C. ss 61-626 and -627; Id. Const. Art. 5, s 9. A different rule would lead to endless consideration of matters previously presented to the Commission and confusion about the effectiveness of Commission orders. Utah-Idaho Sugar Co. v. Intermountain Gas Co., 100 Idaho 368, 373-74 (1979). Not only does the final and conclusive nature of the IPUC’s orders bar collateral attacks like Plaintiffs’ instant lawsuit, but it also results in those orders having preclusive effect in any subsequent proceedings, including the instant one. For example, the Third Circuit held that federal common law rules of preclusion give preclusive effect to the factual findings and legal conclusions contained in an unreviewed state utility commission’s decision to the same extent as would the state courts. Crossroads Cogeneration Corp. v. Orange & Rockland Utils., Inc., 159 F.3d 129, 135 (3d Cir. 1998); see also Dias v. Elique, 436 F.3d 1125, 1128 (9th Cir. 2006) (“Federal courts give the same preclusive effect to the decisions of state administrative agencies as the state itself would”). Of importance, in Crossroads the Third Circuit found that there is “no provision of PURPA that seeks to limit common law rules of preclusion from applying to state agency decisions relating to utility regulation” and concluded that, “[g]iven the substantial role given state utility agencies by Congress in enacting PURPA, … Congress did not intend to prevent application of common law rules of preclusion.” Id. As such, the Third Circuit gave preclusive effect to the state agency’s decision “to the same extent as would the [state’s] courts.” Id. Based upon this law, the factual findings and legal conclusions in the IPUC’s orders are entitled to preclusive effect before this Court to the same extent that they would be in Idaho’s state courts. Id.; see also J & J Contractors/O.T. Davis Const., A.J.V. v. State, 118 Idaho 535, 537 (1990) (“The doctrine of claim preclusion, or res judicata, applies to the effect of administrative decisions”). As already discussed, under Idaho law, IPUC orders receive “a degree of finality Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 17 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 13 similar to that possessed by judgments made by a court of law.” Utah-Idaho Sugar, 100 Idaho at 373. Additionally, as the record shows (1) Plaintiffs had a full and fair opportunity to litigate whether the IPUC improperly determined their QF status through their prior Motion for Reconsideration (see Ex. 11); (2) that issue is the identical issue Plaintiffs now raise in the present lawsuit, (see Ex. 11; Dkts. 2, 29); and (3) the IPUC issued a final order on the merits via Order No. 33858, (see Ex. 12), that is now final and conclusive. See Ticor Title Co. v. Stanion, 144 Idaho 119, 124 (2007) (delineating the elements of issue preclusion and claim preclusion). Consequently, under the foregoing law, Plaintiffs’ motion must be denied because their current claim constitutes an improper collateral attack on final orders that have preclusive effect. C. Plaintiffs’ Motion Must Be Denied Because Their Challenge is an As-Applied Challenge That Falls Exclusively Within the State’s Jurisdiction Section 210 of PURPA creates “an overlapping scheme of federal and state judicial review of state regulatory actions taken pursuant to PURPA.” Allco, 875 F.3d at 67. Specifically, Section 210 authorizes the following three types of enforcement actions through which a QF can challenge the actions of a state regulatory agency such as the IPUC: (1) implementation challenges by FERC against states in federal court, 16 U.S.C. § 824a-3(h)(2)(A); (2) implementation challenges by QFs against states in federal court, 16 U.S.C. § 824a-3(h)(2)(B); and (3) as-applied challenges by QFs against states or unregulated utilities in state court. 16 U.S.C. § 824a-3(g); also Allco, 875 F.3d at 67-69. While federal district courts have exclusive jurisdiction over implementation challenges, state courts have exclusive jurisdiction over as-applied challenges. Exelon, 766 F.3d at 388. “Implementation challenges involve claims that a state agency has failed to properly implement FERC’s regulations governing the purchase of energy from QFs.” Allco, 875 F.3d at 68; also Exelon, 766 F.3d at 388 (“An implementation claim involves a contention that the state agency…has failed to implement a lawful implementation plan under § 824a-3(f) of PURPA….”); Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 18 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 14 Policy Statement Regarding the Commission’s Enforcement Role Under Section 210 of the Public Utility Regulatory Policies Act of 1978, 23 FERC ¶ 61,304, at 61,644 (1983) (“1983 Policy Statement”) (implementation challenges under 16 U.S.C. § 824a-3(h) address claims that the state agency has “promulgated regulations which are inconsistent with or contrary to [FERC’s] regulations”). As-applied challenges, on the other hand, “involve claims that a utility has failed to abide by a state’s regulations implementing PURPA.” Allco, 875 F.3d at 68; also Exelon, 766 F.3d at 388 (an as-applied claim “involves a contention that the state agency’s…implementation plan is unlawful, as it applies to or affects an individual petitioner”). Stated differently, implementation challenges are limited to those involving claims that a state agency or nonregulated utility “failed to comply with [its] obligation under § 210(f)(2) of PURPA to devise an implementation plan…that is consistent on its face with FERC’s regulations,” while as-applied challenges are those alleging that such an agency or utility “failed to adhere to its own implementation plan in its dealings with a particular qualifying facility.” Greensboro Lumber Co. v. Georgia Power Co., 643 F.Supp. 1345, 1374 (N.D. Ga. 1986). These latter, as applied claims, “must be brought in state court, which has exclusive jurisdiction ‘to enforce any requirement’ of a nonregulated utility’s [or State regulatory authority’s] implementation plan.” Id.; also 16 U.S.C. § 824a-3(g)(2). “That this is the FERC’s interpretation of PURPA’s enforcement mechanism is clear.” Id.; see Snow Mountain Pine Co. v. CP Nat’l Corp., 30 FERC ¶ 61,293, at 61,589 (1985) (“As the commission has previously noted, complaints regarding an alleged refusal to purchase power from a qualifying facility and the rates for such purchases are matters properly brought in a State forum”); Roche Prods., Inc., et al., 29 FERC ¶ 61,098, at 61,184 (1984) (“matters of application of [a utility’s] rules…are properly brought before State judicial forums”). Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 19 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 15 As-applied claims include questions on whether a specific state agency’s order, as opposed to a particular state rule, properly implement FERC’s regulations and whether a state agency properly interpreted its own rules. See Exelon n, 766 F.3d at 389-91 (discussing Power Res. Grp., 422 F.3d 231; Power Resource II, No. 1:03-CV-762-HLH, Dkt. No. 44, at 17-18; Power Res. Grp., Inc. v. Pub. Util. Comm’n, 73 S.W.3d 354, 356-57 (Tex.App.-Austin 2002)). As-applied claims also include questions on whether the rates established under a state’s implementation plan are “non-discriminatory, just and reasonable” as required by FERC’s regulations and whether a state agency’s adoption of a certain charge to be levied on a particular class of customers complies with FERC’s regulations. See Greensboro Lumber, 643 F.Supp. at 1374-75; Mass. Inst. of Tech. v. Mass. Dept. of Pub. Utils., 941 F.Supp. 233, 236-38 (D. Mass. 1996) (“MIT”). In this case, the gravamen of Plaintiffs’ challenge is that the IPUC improperly applied its own PURPA implementation plan when it determined that Plaintiffs are not entitled to 20-year contracts with standard/published avoided cost rates and, instead, are only entitled to negotiate two-year contracts using Idaho’s IRP-based avoided cost methodology. For example, in their First Amended Complaint, Plaintiffs allege that “Defendants’ ruling deprives [Plaintiffs] of their right to the Idaho Commission’s more favorable contract terms and rates available to all ‘other’ QFs and instead restricts them to the less favorable contract terms and rates that are available, under the Idaho Commission’s implementation of PURPA, to just solar and wind QFs.” (Dkt. 2, ¶ 13, emphasis added; also Dkt. 2, ¶¶ 44-58.) Similarly, in their motion Plaintiffs ask this Court to enter summary judgment in their favor “declaring and requiring the Defendants honor Plaintiff’s ‘other QF’ status and require Idaho Power Company to tender twenty (20) year contracts at published rates consistent with their status as ‘other QFs’ pursuant to established IPUC requirements….” (Dkt. 29, pp. 1-2, emphasis added.) As these pleadings show, Plaintiffs’ argument is that, because Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 20 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 16 they are not self-certified solar or wind QFs and, instead, are “other” QFs under Idaho’s PURPA implementation scheme, they are not subject to the limitations imposed upon such solar and wind QFs and, therefore, are entitled to the more favorable rates and contract terms previously established by the IPUC. (Dkt. 2, ¶¶ 13, 44-58; Dkt. 29, pp. 1-2; Dkt. 29-1.) While Plaintiffs argue that their challenge relates to the IPUC’s implementation of PURPA, presumably in an effort to manufacture jurisdiction where none exists, their challenge is unequivocally an as-applied challenge. As already noted, merely a cursory review of their allegations proves that Plaintiffs’ challenge is not an implementation challenge because they are not arguing that the IPUC “promulgated regulations which are inconsistent with or contrary to [FERC’s] regulations.” 1983 Policy Statement, at 61,644. For example, Plaintiffs do not claim that the IPUC’s two methods for calculating avoided costs are unlawful, or that the IPUC’s eligibility caps for solar and wind QFs, on the one hand, and all “other” QFs, on the other hand, are unlawful. (See e.g., Dkt. 2, ¶ 13; Dkt. 29, pp. 1-2; Dkt. 29-1.) Instead, Plaintiffs claim that the IPUC, in ruling upon Idaho Power’s Petition, failed to adhere to its own implementation plan in its dealings with Plaintiffs by refusing to grant them the contract rate and terms applicable to “other” QFs. (See id.) Thus, as in Greensboro Lumber, Plaintiffs’ challenge is “properly regarded as a challenge to the application of an implemented plan, and not a challenge to the implementation of the plan itself” and, as such, jurisdiction lies with the state court. MIT, 941 F.Supp. at 237-38 (citing Greensboro Lumber, 643 F.Supp. at 1374-75). Consequently, because Plaintiffs’ claim is an as-applied challenge, this Court lacks jurisdiction. D. Plaintiffs’ Motion Must Be Denied Because the IPUC Did Not Determine Plaintiffs’ QF Status, Nor Are Plaintiffs Entitled to a Certain Rate or Term Plaintiffs’ entire lawsuit and motion is based upon the allegation that, in ruling upon Idaho Power’s Petition and finding that Plaintiffs are not entitled to standard/published avoided cost rates Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 21 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 17 and 20-year contracts, the IPUC improperly determined Plaintiffs’ QF status and denied them “rights [that] are vested in them under PURPA.” (Dkt. 29-1, p. 2; also Dkts. 2, 29, 29-1.) Plaintiffs’ claim misrepresents both the facts and the law and is entirely meritless. 1. The IPUC Did Not Determine Plaintiffs’ QF Status In its Petition, Idaho Power explicitly stated that it was not challenging Plaintiffs’ QF status and that, for purposes of its Petition, it wanted the IPUC to assume the validity of Plaintiffs’ QF status and determine, based upon the facts presented in Plaintiffs’ Schedule 73 applications and Form 556s, whether Plaintiffs are entitled to published avoided cost rates and 20-year contracts. (Ex. 9, pp. 6-7.) In ruling upon that Petition, the IPUC did as Idaho Power asked and did not question, let alone determine, Plaintiffs’ QF status. (Ex. 10, pp. 3, 10-11.) The IPUC plainly stated this fact in its order, when it acknowledged that “[t]he battery storage facilities’ QF status is a matter within FERC’s jurisdiction and is not at issue in this case.” (Id. at p. 11, emphasis added.) The IPUC confirmed this in its order denying Plaintiffs’ Motion for Reconsideration, in which Plaintiffs, as they currently do, argued that the IPUC improperly determined their QF status: [Plaintiffs] argue[] that the Final Order is “unreasonable, unlawful, erroneous or not in conformity with the law” and should be reconsidered because it infringed on FERC’s jurisdiction to determine QF status. [Plaintiffs’] only legal authority for its argument is Indep. Energy Producers, 36 F.3d at 856, in which the Ninth Circuit Court of Appeals opined that the authority to make QF status determinations belongs to FERC, not the states. [Plaintiffs] assert[] that, contrary to Indep. Energy Producers, we determined the QF status of battery storage facilities in the Final Order. We did not. [Plaintiffs’] mischaracterization of our Final Order is a frivolous effort to contrive a legal basis for reconsideration.4 4 In an egregious misrepresentation of the IPUC’s order, Plaintiffs claim that “[t]he IPUC characterized [Plaintiffs’] reliance on the Ninth Circuit’s precedent in Independent Energy Producers v. CPUC as a ‘frivolous attempt to contrive a legal basis for reconsideration.’” (Dkt. 29-1, p. 12.) As is evident from the IPUC’s order, that comment was made in response to Plaintiffs’ mischaracterization of its ruling, i.e., that it determined Plaintiffs’ QF status, and not its Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 22 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 18 [Plaintiffs] contend[] we determined that the primary energy source behind a battery storage QF is the QF, based on a misreading of FERC’s decision in Luz Development and Finance Corporation, 51 FERC ¶ 61,078. Franklin Petition at 9. This Commission did not find that the primary energy source behind a battery is the QF, nor did we assert that Luz stands for such a proposition. In the Final Order, we explicitly recognized that “battery storage facilities’ QF status is a matter within FERC’s jurisdiction” and we acknowledged the self-certifications of [Plaintiffs’] QFs. Final Order No. 33785 at 3, 10-11. Consistent with FERC’s analysis in Luz, we looked to the primary energy source of [Plaintiffs’] battery storage QFs to determine the projects’ eligibility to particular avoided cost rates and contract terms. (Ex. 12, pp. 2-3, emphasis added.) As shown, the record speaks for itself that, contrary to Plaintiffs’ claim, the IPUC did not determine Plaintiffs’ QF status and, instead, simply determined which rates and terms Plaintiffs were eligible for in their contracts with Idaho Power, something the IPUC undeniably has the responsibility and authority to decide.5 (See Section II.A., supra.) Unfazed by the utter lack of support for their position, Plaintiffs forge ahead in their motion with a second baseless argument. In particular, Plaintiffs claim that, under Independent Energy Productions Association, Inc. v. California Public Utilities Commission, 36 F.3d 848 (9th Cir. 1994) (“Independent Energy”), a state agency like the IPUC cannot inquire into or “look under the hood” at a QF’s energy source for any reason, including for use in determining the contract rates and terms for which it is eligible under PURPA. (Dkt. 29-1, pp. 5-12.) reliance upon Independent Energy Producers, although that case does not support Plaintiffs’ position at all. (See Ex. 12, pp. 2-3.) 5 Throughout their motion, Plaintiffs couch this position using different language, including that the IPUC determined “the nature of the QF,” “questioned the validity of the QF’s assertion that it is, in fact, a QF” and “inquir[ed] as to the energy inputs necessary to qualify a facility as a QF,” (Dkt. 29-1, pp. 8-9, 10.) As already discussed and shown, however, the IPUC did nothing of the sort. It never questioned, analyzed or determined whether or not Plaintiffs were QFs or anything relating to its status as a QF and, instead, it unambiguously assumed that each of Plaintiffs’ four facilities was, as stated in their Form 556s, a self-certified battery storage facility. (E.g., Exs. 10, 12.) Thus, Plaintiffs’ argument fails regardless of the varying terms it uses to couch that argument. Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 23 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 19 There are two fatal deficiencies with this argument. First, Independent Energy does not even remotely stand for the broad proposition for which Plaintiffs claim it stands. Instead, all Independent Energy holds is that FERC has exclusive jurisdiction to certify and decertify QFs and that a state regulation or program that allows anybody other than FERC to evaluate whether a QF remains in compliance with the operating and efficiency standards that facilities must comply with to be certified as and/or remain certified as a QF infringes upon that exclusive jurisdiction. Indep. Energy, 36 F.3d at 853-59. Second, state agencies such as the IPUC unequivocally can look to a QF’s energy source in determining contract rates or terms. CPUC, 133 FERC ¶ 61,059, at P 23; also 18 C.F.R. § 292.304(c)(3)(ii). For these reasons, Plaintiffs’ motion must be denied. 2. PURPA Does Not “Vest” in Plaintiffs or Entitle Them to Any Specific Rate or Contract Term Through their framing of the issue, Plaintiffs appear to believe that PURPA “vests” in them or entitles them to 20-year contracts and standard avoided cost rates. (See Dkt. 29-1, p. 2.) Tellingly, Plaintiffs fail to cite to any legal authority supporting this position, presumably because no such authority exists. The only thing that Plaintiffs are “entitled” to as self-certified QFs under PURPA is the triggering of its provisions mandating that Idaho Power agree to purchase Plaintiffs’ power at “just and reasonable rates” that do not exceed the “incremental cost to [Idaho Power] of alternative electric energy.” E.g., Exelon, 766 F.3d at 384; Allco, 875 F.3d at 67; 16 U.S.C. § 824a-3(a)(2), (b)(1); 18 C.F.R. § 292.304(b)(2). The First Circuit recently confirmed this fact: “Section 210 of PURPA does not create a contract. Rather, it merely creates an obligation to enter into a contract at a regulation-specified rate.” Allco, 875 F.3d at 70-71. As already discussed, the setting of this rate, i.e., the avoided cost rate, is left to the IPUC, as is the determination of the length of any contract and other terms thereof. Consequently, contrary to Plaintiffs’ contention, Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 24 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 20 neither PURPA nor FERC’s regulations entitle them to or vest in them any right to 20-year contracts with Idaho Power at standard avoided cost rates. E. Contrary to Plaintiffs’ Claim, the IPUC’s Orders Do Not Create Any Irreconcilable Conflict Between State and Federal Law Plaintiffs’ conflict preemption argument is baseless and rests upon a faulty premise – that the IPUC determined that a QF’s “primary energy source determines [its] QF status.” (Dkt. 29-1, p. 14.) As already discussed, the IPUC did not make this determination and, in fact, it did not make any determinations on Plaintiffs’ QF status. (See Section III.D.1, supra.) Moreover, a state law is preempted only when “it is impossible to comply with both state and federal law” or where it “stands as an obstacle to the accomplishment of the full purposes and objectives of Congress.” Silkwood v. Kerr-McGee Corp., 464 U.S. 238, 248 (1984). Here, however, Plaintiffs do not challenge a state law; instead, they challenge the IPUC’s decision addressing the contract terms to which Plaintiffs are eligible for under its PURPA implementation scheme. Even if such a decision can serve as the basis of a preemption claim, Plaintiffs do not identify a single federal law that is in conflict with the IPUC’s decisions, nor can they. The IPUC’s orders do not affect whether a facility is or is not certified or decertified as a QF under federal law. (See Exs. 10, 12.) All those orders do is address the contract terms applicable to Plaintiffs’ specific battery storage QFs based upon the information they provided to FERC and Idaho Power. (Id.) Thus, there is not any conflict between state and federal law. IV. CONCLUSION Based upon the foregoing, Idaho Power respectfully requests that this Court deny Plaintiffs’ Motion for Summary Judgment in its entirety. Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 25 of 26 DEFENDANT-INTERVENOR’S RESPONSE TO PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT [DKT. 29] - 21 DATED this 26th day of October, 2018. ANDERSEN SCHWARTZMAN WOODARD BRAILSFORD, PLLC /s/ Steven B. Andersen Steven B. Andersen Attorneys for Defendant-Intervenor Idaho Power Company CERTIFICATE OF SERVICE I hereby certify that on this 26th day of October, 2018, I caused a true and correct copy of the foregoing document to be electronically filed with the Clerk of the Court using the CM/ECF system, which sent a Notice of Electronic Filing to the following persons: Peter J. Richardson peter@richardsonadams.com Robert C. Huntley rhuntely@huntleylaw.com Brandon Karpen brandon.karpen@puc.idaho.gov Scott Zanzig scott.zanzig@ag.idaho.gov /s/ Steven B. Andersen Steven B. Andersen Case 1:18-cv-00236-REB Document 38 Filed 10/26/18 Page 26 of 26