HomeMy WebLinkAbout20110207final_order_no_32176.pdfOffce of the Secreta
Servce Date//Februar 7, 2011
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE JOINT )
PETITION OF IDAHO POWER COMPANY, ) CASE NO. GNR-E-I0-04
AVISTA CORPORATION, AND )
PACIFICORP DBA ROCKY MOUNTAIN )
POWER TO ADDRESS AVOIDED COST ) ORDER NO. 32176
ISSUES AND TO ADJUST THE PUBLISHED )
AVOIDED COST RATE ELIGIBILITY CAP. )
On November 5, 2010, Idaho Power Company, Avista Corporation, and PacifiCorp
dba Rocky Mountain Power filed a Joint Petition requesting that the Commission initiate an
investigation to address various avoided cost issues related to the Commission's implementation
of the Public Utility Regulatory Policies Act of 1978 (PURP A). PURP A was intended to
encourage the development of renewable energy technologies as alternatives to the use of fossil
fuels and the constrction of new generating facilties by electric utilties. Section 210 of
PURP A generally requires electric utilities to purchase power produced by qualifying facilities
(QFs) at "avoided cost" rates set by the Commission. "Avoided costs" are those costs which a
public utility would otherwse incur for electric power, whether that power was purchased from
another source or generated by the utilty itself. 18 C.F.R. § 292.101(b)(6).
While the investigation is underway, the Petitioners also moved the Commission to
"lower the published avoided cost rate eligibility cap from 10 aMW to 100 kW (to) be effective
immediately. . .." Petition at 7. Pursuant to PURA regulations issued by the Federal Energy
Regulatory Commission (FERC), this Commission must publish avoided cost rates for small QFs
with a design capacity of 100 kW or less. However, the Commission has the discretion to set the
published avoided cost rate at a higher capacity amount - commonly referred to as the
"eligibilty cap." 18 C.F.R. § 292.304(c)(1) and (2). When this case was initiated, the eligibilty
cap for the published avoided cost rate was set at 10 aMW. Order No. 30488. The avoided cost
rates for purchases from QFs larger than the eligibilty cap (10 aMW) must be individualy
negotiated by the QF and the public utility. In a negotiated contract, the utilty's avoided cost is
the staring point for rate negotiations.
As set out in greater detail below, the Commission grants in par and denies in par
the Petitioners' Motion to reduce the eligibilty cap. The Commission temporarily reduces the
ORDER NO. 32176 1
eligibility cap for published avoided cost rates from 10 aMW to 100 kW for wind and solar QFs
only.
BACKGROUND
A. The Joint Petition
The Petition states that Idaho Power currently has more than 208 MW of wind
generation and an additional 264 MW of Commission-approved QF wind contracts (many of
which are scheduled to be online by December 31, 20 i 0). The Petition asserts that Idaho Power
could have i, i 00 MW of wind-powered generation on its system in the near term that would
exceed the minimum loads experienced on Idaho Power's system this year. "Cumulatively, this
amount of generation would exceed any other single source of generation - hydro, coal, natural
gas, or renewables - that exists on Idaho Power's system." ¡d. at 4.
Rocky Mountain asserts that it is in a similar situation. The Petition declares that in
2005, Rocky Mountain had a single 20 MW wind QF contract and less than 50 MW of wind QF
requests in Idaho. "As of today, (Rocky Mountain) has 64 MW of wind QF contracts executed;
however, none have achieved commercial operation, and another 358 MW of standard wind QF
contracts are proposed." Rocky Mountain maintains that the majority of these proposed standard
wind QF contracts are configured to interconnect with the utility's Goshen substation "where
integration of the QF resource as a Network Resource for serving load could be impacted by
transmission constraints across Path C if the wind power is exported to RMP's northern Utah
load." ¡d. at 4.
The Petition states that many current QF projects are "large, utility-scale wind fars
that are broken up into 10 aMW increments in order to qualify for the published (avoided cost)
rates." ¡d. at 5. The Petition maintains that the typical wind developer is no longer
"unsophisticated" about the QF process and small projects (0.5-1.5 MW) "are no longer the
norm." ¡d. The Petitioners assert that it is "commonplace" for wind developers seeking QF
contracts with Idaho Power and Rocky Mountain to aggregate "six or more 'projects' totaling
100 to 150 MW of nameplate rating, and the multiple projects to all share interconnection
facilities to one common utilty delivery point." ¡d.
B. Procedural History
After the filing of the Joint Petition, the Commission received several Petitions to
Intervene. The following parties requested, and were granted, intervenor status: Cedar Creek
ORDER NO. 32176 2
Wind, LLC; Exergy Development Group of Idaho; Grandview Solar II; Idaho Windfars, LLC;
Interconnect Solar Development, LLC; the Northwest and Intermountain Power Producers
Coalition (NIPPC); Renewable Energy Coalition (Coalition); i Intermountain Wind, LLC; J.R.
Simplot Company; Board of Commissioners of Adams County (Adams County); Birch Power
Company; Dynamis Energy, LLC; North Side and Twin Falls Canal Companies (Canal
Companies); and Blue Ribbon Energy, LLC.
In addition to the Petitions to Intervene, the Commission also received four answers
to the Joint Petition. Answers were filed by NIPPC, the Coalition, Simplot, and the Milk
Producers of Idaho? The answers raise both procedural and substantive objections to the
Petitioners' request to lower the eligibility cap for the published avoided cost rate to 100 kW
nameplate capacity. The Milk Producers, Simplot and the Coalition also argue in their answers
that the lowering of the eligibility cap should not apply to non-wind QFs. Simplot asserts that
the Joint Petition does not refer to any "problems associated with biomass, cogeneration, solar,
small hydro, waste-to-energy projects or any other type of PURPA eligible QF resource. These
other types of (QF) resources have very different generating characteristics from wind and
should therefore not be caught in the overly broad sweep of the Joint Motion." Simplot Answer
at 3.
C. The Commission's Notice of Petition
On December 3,2010, the Commission issued an Order and Notice of Joint Petition.
After reviewing the Joint Petition and the answers, the Commission declined the Motion to
immediately reduce the eligibility cap. Instead, the Commission determined that it would
expeditiously consider the Petitioners' request to reduce the eligibility cap through the use of
Modified Procedure (written comments) and oral arguments. The Notice established an
intervention deadline of December 17, 20 i 0; set deadlines for initial comments and reply
comments of December 22, 2010, and January 19, 2011, respectively; and scheduled an oral
argument for January 27, 2011. Order No. 32131.
The Commission specifically requested comment and argument regarding: (1) the
advisability of reducing the published avoided cost eligibility cap; (2) if the eligibilty cap is
J The Coalition is an Oregon-based consortium of existing base load hydroelectric and biomass QFs located in the
Northwest.
2 The Milk Producers did not fie a Petition to Intervene and its "Answer" was a "letter in opposition." The Milk
Producers letter, therefore, wil been treated as a comment.
ORDER NO. 32176 3
reduced, the appropriateness of exempting non-wind QF projects from the reduced eligibilty
cap; and (3) the consequences of dividing larger wind projects into 10 aMW projects to utilize
the published rate.3 The Commission also determined that its decision regarding the Joint
Petitioners' Motion to reduce the published avoided cost eligibilty cap would become effective
on December 14,2010.
PROCEDURAL AND SUBSTANTIVE MOTIONS
Before and at the January 27, 2011 oral arguent, several paries made various
motions. The motions are addressed in greater detail below.
A. Motion to Strike
With its reply comments fied on Januar 19,2011, Rocky Mountain Power prefied
the direct testimony of Bruce Griswold. On Januar 21, 2011, NIPPC filed a Motion to Strike
Griswold's testimony. NIPPC renewed its Motion to Strike at oral argument. Given NIPPC's
Motion, Rocky Mountain Power withdrew Mr. Grswold's testimony. Tr. at 11.
B. Motionfor a Technical Hearing
In their initial comments and reply comments, both NIPPC and Adams County
requested that the Commission conduct a techncal hearng in order to allow the paries to
present witnesses. Several times durng oral argument NIPPC and Adams County referenced the
need for a technical hearing, but did not renew their Motion.
The Commission finds that the paries' positions have been adequately presented
through initial comments, reply comments and oral arguent, and that a technical hearng is not
necessar to resolve the question of whether the eligibilty cap should be reduced. We also find
that conducting a technical hearng would unecessarily delay the decision making process.
Consequently, the Commission denies the paries' requests for a technical hearing. We find that
the comments and oral arguent provide sufficient information to resolve the policy question of
temporarily reducing the eligibility cap.
e. Request to Take Offcial Notice
At oral argument, NIPPC distributed a document entitled "Request for Official
Notice" and asked the Commission to take offcial notice of a host of documents listed in the
"Request" including approximately 14 PUC Orders, several FERC orders, and the "Filings,
3 The Commission intends to consider the other avoided cost issues identified by the Petitioners and other interested
paries in subsequent proceedings.
ORDER NO. 32176 4
Testimony, Exhibits and Orders" in 24 different PUC dockets. In addition, NIPPC orally asked
that the Commission take offcial notice of "three documents related to coal costs that support
our comments": a settlement agreement of the Environmental Protection Agency; an Oregon
State Senate Natural Resources Committee report on greenhouse gas emissions; and
MidAmerican Holdings Company's comments from a coal combustion residual rulemaking. Tr..
at 7-8. The Commission acknowledged official notice of its own notices and orders. ¡d. at 9.
Pursuant to our Procedure Rule 263.01, the Commission may take official notice at
hearing and in its Orders of:
a. (l) Its own orders, notices, rules, certificates and permits, and (2) those of
any other regulatory agency, state or federal;
b. (l) matters of common knowledge, (2) technical, financial, or scientific
facts established and published in accepted authorities or in the
Commission's specialized knowledge, and (3) matters judicially
noticeable; and
c. Data contained in periodic reports of regulated utilities filed with the
Commission or federal regulatory agencies.
However, "( u)nless otherwise agreed to by the parties and approved by the presiding officer,
paries requesting the Commission to take offcial notice of documents must submit those
documents to the Commission in the manner prescribed for documents in Rule 262." Rule
263.02 (emphasis added). Although NIPPC presented the Commission with a list of citations to
documents, it did not actually provide copies of the requested documents to the Commission or
to the paries. NIPPC also advised the Commission that all of its requested documents met the
parameters of Rule 263.01. Tr. at 10. However, Rule 263.01 pertains to matters that the
Commission may offcially note. Parties requesting official notice must comply with Rule
263.02 and provide copies of the documents for which it seeks offcial notice. The purose of
providing copies to parties is to afford the paries an opportunity to review, and if necessary,
contest the offered materiaL. ¡d. Moreover, the majority of the "fiings, testimonies and
exhibits" from the 24 PUC dockets are not documents or information subject to official notice
per Rule 263. Notwithstanding the Commission's acknowledgement of taking official notice of
its own notices and orders, the Commission denies NIPPC's request to take offcial notice of the
remainder of its listed documents, including the three additional documents regarding coal costs.
ORDER NO. 32176 5
D. Motion to Dismiss
During oral argument, Blue Ribbon Energy asked the Commission to dismiss the
utilities' Joint Petition. Blue Ribbon articulated three bases upon which the Commission should
dismiss the Petition: (1) the utilities' failed to fie the Petition in good faith; (2) the utilties have
not presented a basis upon which relief can be granted; and (3) the utilities' Joint Petition
constitutes an effort by the utilities to terminate their obligations to enter into PURP A contracts.
Tr. at 74. The utilities responded that their Joint Petition was made in good faith and based on
verifiable evidence that large QF projects are receiving an avoided cost rate in excess of the
utilty's true avoided cost. ¡d. at 82. Rocky Mountain Power specifically pointed out that the
costs of QF contracts are borne by ratepayers and that the utilities were acting in the ratepayers'
interest. ¡d. at 83.
The Commission denied Blue Ribbon's request for dismissal of the Petition. The
Commission stated that the utilities' Petition was based on the Commission's authority to set the
eligibility cap for QF projects. ¡d. at 87. We reject Blue Ribbon's argument that a reduction in
the eligibility cap relieves utilities of their obligation to purchase QF power. Tr. at 76-77, 81.
Finally, Blue Ribbon's argument regarding the 80 MW maximum size of a QF is not relevant to
the cap size of the standard published rate. Cf 18 C.F.R. §§ 292.204(a) and 292.304(c).
COMMENTS AND ORAL ARGUMENT
Comments and arguments were presented by developers of QF facilities, Staff, each
of the Petitioners, and other interested persons. Idaho Power, Avista, and Rocky Mountain
Power all propose lowering the threshold for PURP A published avoided cost rates from 10 aMW
to 100 kW for all QF resources. The utilities argue that the number of QFs currently requesting
contracts under the published 10 aMW avoided cost rate is excessive and the utilities' ability to
continue to accept the QF energy without negatively impacting the electric system and the
utilties' customers is at risk. Specifically, the utilities cite large wind QFs as the source of their
curent predicament.
Idaho Power stated that "the current application of the (published rate) methodology,
including the 10 average megawatt cap, has several problems associated with it that have
potentially huge ramifications or implications for our customers. . .." Tr. at 13. Avista
maintained that reducing the eligibility cap to 100 k W "is the most practical, simplest, most
easily implemented and enforced solution to the issues" that the utilities are facing. ¡d. at 31.
ORDER NO. 32176 6
When addressing the disaggregation issue raised by the Petition, Rocky Mountain
Power argued that a disaggregated wind project "looks a lot like a large wind QF project. Except
for additional (electric) meters, the differences are almost purely legaL." ld. at 33. Rocky
Mountain Power explained that "the large QFs have an option and this option is valuable and that
value comes at the expense of ratepayers." ld. at 36. The Petitioners also maintain that it is
important that any change in the eligibilty cap be applied equally for all three utilties in order to
prevent a utilty not granted a reduction from disproportionately attracting a greater number of
QF project proposals.
Without exception, the Intervenors oppose reduction of the published avoided cost
rate eligibilty cap. The Intervenors generally contend that lowering the threshold is an
imposition on legally permissible QF projects that canot absorb the costs of negotiating with a
utilty and the increased difficulty of obtaining financing created by the uncertaity of the
payments they wil receive under PURP A contracts negotiated through use of the Integrated
Resource Plan (lRP) Methodology.
Dynamis, Adams County, Birch Power, Interconnect Solar, the Canal Companes, the
Coalition and Commission Staf urge the Commission to narowly apply any reduction in
eligibilty cap to the resource identified by the utilties as causing the immediate problem: wind
QFs. Interconnect Solar distinguishes its resource from wind by arguing that "( s )olar power is
not 'intermittent' and instead has a firm natue to its production that directly matches a utilty's
need for energy and capacity during heavy load hours." Interconnect Solar Comments at 2.
Even Intermountain Wind, a self-professed family operation, maintains that "(a)n overly broad
eligibilty reduction would har projects that are legitimately entitled access to PURP A
published avoided cost rates and would adversely affect the development of renewable energy in
Idaho." Intermountain Wind Comments at 5. Intermountain Wind also argues that, "(w)hether
PURP A published rates should be available to commercial scale projects may be fairly
debatable. Whether those rates should be available to paries such as Intermountain is not." ld.
at 4.
NIPPC maintains that a reduction in the published avoided cost rate eligibilty cap is
not waranted for any resource because the utilties have not demonstrated that the published
avoided cost rate is too high. NIPPC fuher argues that, although the utilties have identified
large wind projects as the immediate source of the problem, the utilties do not claim that they
ORDER NO. 32176 7
would be unable to integrate the amount of wind curently in the queue. NIPPC and Adams
County claim that disaggregation "is irrelevant and a non-issue, because if the avoided cost rates
are accurately set, the rates for an IRP methodology avoided cost project would be essentially the
same as the rates for a non-IRP methodology avoided cost project." Tr. at 49. They go on to
assert that "(n)o developer is going to go in for the IRP methodology knowing that it sets the
avoided cost rate under actual avoided cost rates if they're able to take advantage of the true
avoided cost rate. . . ." ¡d. at 51.
NIPPC and Intermountain Wind also oppose the Commission's decision to implement
a December 14, 2010, effective date. Intermountain Wind argues that the Commission "does not
have authority to look back in time and rearrange legal rights that existed on a certain day in the
past." Intermountain Wind Reply at 4. NIPPC contends that a December 14 effective date
"violates the filed rate doctrine and the prohibition against retroactive ratemaking." NIPPC
Comments at 8.
Commission Staff asserts that, although large wind projects are not inherently
undesirable, the disaggregation of multiple, affiiated QFs seeking to qualify for published rate
contracts raises concerns. Staff contends that "considering each 10 aMW QF individually for
purposes of eligibility for (published) avoided cost rates creates an artificial mismatch between
the method used to establish a project's avoided cost rates and the collective size of the project."
Staff Comments at 4. Staff emphasizes that, "(w)hen large QFs are added to a utilty's
renewable portfolio, but the QFs disaggregate in order to qualify for the published rate, the
avoided cost paid to the QF becomes inaccurate, because under the published rate methodology,
there's no mechanism to reflect the utility's reduced avoided cost." Tr. at 88. Staff fuher
maintains that obligating utilties to accept generation that they do not need unecessarily
increases the rates paid by the utilities' customers. Staff Comments at 5. Staff insists that the
problem described by the utilities is real and requires immediate attention.
DISCUSSION AND FINDINGS
The Idaho Public Utilities Commission has jurisdiction over this matter pursuant to
the authority and power granted it under Title 61 of the Idaho Code and the Public Utilty
Regulatory Policies Act of 1978 (PURPA). The Commission has authority under PURPA and its
implementing regulations of FERC to set avoided costs, to establish standard published avoided
ORDER NO. 32176 8
cost rates, to order electric utilities to enter into fixed-term obligations for the purchase of energy
from QFs, and to implement FERC regulations.
Based upon the record, the Commission finds that a convincing case has been made
to temporarily reduce the eligibility cap for published avoided cost rates from 10 aMW to 100
kW for wind and solar only while the Commission further investigates the implications of
disaggregated QF projects.4 We maintain the eligibility cap at 10 aMW for QF projects other
than wind and solar (including but not limited to biomass, small hydro, cogeneration,
geothermal, and waste-to-energy). The Petitioners have not convinced us that lowering the
eligibilty cap for these other QF technologies is necessary or in the public interest.
Wind and solar resources present unique characteristics that differentiate them from
other PURP A QFs. Wind and solar generation, integration, capacity and abilty to disaggregate
provide a basis for distinguishing the eligibility cap for wind and solar from other resources.
Furhermore, these intermittent resources must be "firmed" by ancilary services to assure system
reliability. Temporarily reducing the eligibility cap for wind and solar while we continue our
investigation, wil stil allow wind and solar projects larger than 100 k W to negotiate avoided
cost rates using the IRP Methodology.
Lowering the cap to 100 k W does not change the published avoided cost rates
established in Order No. 31025 (March 16, 2010). The published rate for wind and solar QFs
wil stil be available for projects 100 kW or smaller and as we have stated previously, will be
the starting point for negotiating an avoided cost rate for larger wind and solar QF projects.
At a minimum, FERC regulations require that standard or published rates be set for
purchases from QFs with a design capacity of 100 kW or less. These regulations also grant the
Commission the discretion to set the published rate eligibilty cap at a higher leveL. 18 C.F.R. §
292.304(c). Whether it is a published rate or a rate for a larger QF, FERC requires that the
avoided cost rates for all QF purchases be just and reasonable to utility customers and in the
public interest; and not discriminate against qualifying cogeneration and small power production
facilties. 18 C.F.R. § 292.304(a)(1). In establishing a published rate, the Commission may
differentiate among QFs using various technologies on the basis of supply characteristics of the
different technologies; the availability of capacity and energy during daily and seasonal peaks;
4 Other avoided cost issues identified in the Joint Petition, including utilization and/or modification of the IRP
Methodology, will be considered after a determination regarding disaggregation.
ORDER NO. 32176 9
dispatchability; reliabilty; and other factors. 18 C.F.R. § 292.304(c)(3); In re California PUC,
Order Granting Clarifcation and Dismissing Rehearing, 133 FERC il61,059 (October 21,2010)
at il23. Contrary to NIPPC's assertions, FERC rules insist that rates for purchases from QFs be
just and reasonable to ratepayers and in the public interest - not in the interest of the QFs.
This Commission established a clear and reasoned distinction between small and
large QFs in 1995 when it adopted the use of the IRP methodology for larger QFs. Order Nos.
25882, 25883, 25884. The Commission explained that requiring larger QF projects "to prove
their viabilty by market standards ensures that utilities wil not be required to acquire resources
priced higher than would result from a least cost planning (RFP) process. Ratepayers will not be
disadvantaged and QFs wil be treated fairly and consistently with the requirements and goals of
PURP A" Id. at 6. The purpose, then and now, of distinguishing between small and large QFs
with the application of the IRP methodology for large QF projects is to more precisely value the
energy being delivered - not encourage or discourage QF resources.
We note that parties have challenged the accuracy of the IRP Methodology. We
believe that the IRP Methodology appropriately assesses when the QF is capable of delivering its
resources against when the utility is most in need of such resources. The resultant pricing is
reflective of the value of QF energy to the utility. Unfortunately, the IRP Methodology is being
under-utilized because our Orders do not currently prevent QF developers from breaking up what
is truly a single, large project into several small QF projects in order to avail themselves of what
may sometimes be more favorable, published avoided cost rates.
Based on the foregoing, the Commission temporarily reduces the eligibility cap for
published avoided cost rates from 10 aMW to 100 kW for wind and solar resources only,
effective December 14,2010. Arguments that the Commission is without authority to implement
its eligibility cap reduction on December i 4 are unpersuasive for several reasons. First, the fied
rate doctrine and rule against retroactive ratemaking do not extend "to cases in which (paries)
are on adequate notice that resolution of some specific issue may cause a later adjustment to the
rate being collected at the time of service." Natural Gas Clearinghouse v. FERC, 965 F.2d
1066, 1075 (D.C.Cir.1992). "The goals of equity and predictability are not undermined when the
Commission warns all parties involved that a change in rates is only tentative and might be
disallowed." OXY USA, Inc. v. FERC, 64 F.3d 679, 699 (D.C.Cir.1995). The Commission
provided notice on December 3, 2010, that its decision regarding the published avoided cost rate
ORDER NO. 32176 10
eligibilty cap would become effective December 14, 2010. One need look no fuher than the
abundance of firm energy sales agreements filed with the Commission within that time frame to
realize that the paries took the Commission's notice of its effective date seriously.
Consequently, adequate notice was provided to all paries that the eligibilty cap was subject to
change.
Second, as previously mentioned, the published avoided cost rates established in
Order No. 31025 have not changed. What has temporarily changed is the availabilty of
published rates to wind and solar QFs. Wind and solar projects larger than 100 kW are stil
entitled to PURP A contracts and avoided cost rates that reflect the unque characteristics of their
resource.
This Commission is supportive of all small power producers contemplated by
PURPA, including wind and solar, and it is not the Commission's intent to push small wind and
solar QF projects out of the market. With ths goal in mind, the Commission is initiating
additional proceedings to investigate and determine in a finite timeframe requirements by which
wind and solar QFs can obtain a published avoided cost rate without allowing large QFs to
obtain a rate that is not an accurate reflection of a utilty's avoided cost for such projects. It is
just and reasonable and in compliance with the intent and mandate of PURPA tht large QF
projects avail themselves of economies of scale. Such an approach will assist the Commission in
fulfillng its obligations under PURP A.
The Commission directs the paries to meet informally withn 10 days of the issuance
of this Order to establish an expedited schedule, including dates for discovery, prefied direct
testimony and rebuttl that will accommodate a techncal hearng durng the week of May 9,
2011. Specifically, the Commission solicits information and investigation of a published
avoided cost rate eligibility cap structue that: (l) allows small wind and solar QFs to avail
themselves of published rates for projects producing 10 aMW or less; and (2) prevents large QFs
from disaggregating in order to obtain a published avoided cost rate that exceeds a utilty's
avoided cost.
ORDER
IT is HEREBY ORDERED that the Petitioners' Motion to reduce the eligibilty cap
for published avoided cost rates is granted in par and denied in par. The Commission
temporarly reduces the eligibilty cap for published avoided cost rates from 10 aMW to 100 kW
ORDER NO. 32176 11
for wind and solar QFs only, effective December 14, 2010. The Petitioners' Motion to reduce
the published eligibility cap for other QFs is denied.
IT is FURTHER ORDERED that NIPPC's request for the Commission to take
official notice of our Notices and Orders is granted and the request regarding the other
documents is denied as set out above.
IT is FURTHER ORDERED that the paries meet informally within 10 days of the
issuance of this Order to establish a schedule consistent with a techncal hearing to occur during
the week of May 9, 2011. The Commission directs the paries to address disaggregation, as more
fully described above.
THIS is A FINAL ORDER. Any person interested in this Order may petition for
reconsideration within twenty-one (21) days of the service date of this Order. Within seven (7)
days after any person has petitioned for reconsideration, any other person may cross-petition for
reconsideration. See Idaho Code § 61-626.
"7l4DONE by Order of the Idaho Public Utilties Commission at Boise, Idaho this
day of Februy 2011.
~~KEMPTON,~ÉÑT
~d~
MARSHA H. SMITH, COMMISSIONER
ATTEST:
~O.rtÆ
J D. Jewe
Commission Secretar
O:GNR-E-IO-04_ksJinal
ORDER NO. 32176 12