SCHEDULE 75
FIXED COST ADJUSTMENT MECHANISM - ELECTRIC
PURPOSE:
This Schedule establishes balancing accounts and implements an annual Fixed
Cost Adjustment ('FCA') rate mechanism that separates the recovery of the
Company's Commission authorized revenues from kilowatt-hour sales to
customers served under the applicable electric service schedules.
TERM:
The FCA mechanism wil! remain in effect through March 31,2025
APPLICABLE:
To Customers in the State of ldaho where the Company has electric service
available. This schedule shall be applicable to all retail customers taking service
under Schedules 1, 11, 12, 21, 22, 31, and 32. This Schedule does not apply to
Extra Large General Service Schedule 25, Extra Large General Service to
Clearwater Paper Schedule 25P, or to Street and Area Light Schedules 41 through
49.
Applicable Customers will be segregated into two (2) distinct Rate Groups:
Group 1-Schedule 1
Group 2 - Schedules 1 1, 12, 21, 22, 31, 32
Note - the recovery of incremental revenue related to fixed production and
fransmission cosfs will be excluded for new naturalgas cusfomers added after the
FCA Base test year.
MONTHLY RATE:
Group 1 - ($O.OO+05) per kWh
Group 2 - ($0.00034) per kWh
lssued July 29,2022 Effective October1,2022
Patrick Ehrbar, Director of Regulatory Affairs
IDAHO PUBLIC UTILITIES COMMISSION
Approved Effective
Sept. 29, 2022 Oct. 1, 2022
Per ON 35540