HomeMy WebLinkAbout20191216notice_of_application_order_no_34506.pdfOffice of the Secretary
Service Date
December 16,2019
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION )CASE NO.AVU-E-19-13
OF AVISTA CORPORATION TO APPROVE )ELECTRIC DISTRIBUTION SERVICE )NOTICE OF APPLICATION
AGREEMENT WITH EAST GREENACRES )IRRIGATION DISTRICT )NOTICE OF
)MODIFIED PROCEDURE
)ORDER NO.34506
On November 12,2019,Avista Corporation dba Avista Utilities ("Avista"or
"Company")filed an Application requesting Commission approval of an Electric Distribution
Service Agreement ("Agreement")between the Company and the East Greenacres Irrigation
District ("East Greenacres").Application at 1.The Company requests the Application be
processed by Modified Procedure and that the proposed Agreement become effective on January
1,2020,or on the first day followingapproval by the Commission.Id.The Commission now
issues this Notice of Application and Notice of Modified Procedure setting comment and reply
deadlines and suspending the Company's proposed effective date.
BACKGROUND
East Greenacres has operated and maintained two Bureau of Reclamation-built
pumping facilities on the Rathdrum Prairie since December 31,1976,providing irrigation and
domestic water supply to approximately 5,300 acres of land.Id.at 2.To operate the pumping
facilities,East Greenacres receives electric power from the Bureau of Reclamation which is
delivered through Avista's transmission and distribution facilities.Id.Since March 1,2009,this
service has been separated into two service agreements to comply with federal and state authorities,
one for transmission and one for distribution.Id.at 2-3.The current electric distribution service
agreement between Avista and East Greenacres was approved by the Commission in 2014 and
remains in effect until terminated or replaced.See Order No.33145.
NOTICE OF APPLICATION
YOU ARE HEREBY NOTIFIED that Avista represents the Agreement was executed
on November 7,2019,and would become effective upon Commission approval.Id.at 3.The
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
ORDER NO.34506 1
Agreement provides for distribution service from Avista's Post Falls Substation over 13.2kV
feeders to East Greenacres'two pumping stations.Id.
YOU ARE FURTHER NOTIFIED that Avista states it has delivered approximately
3.8 million kilowatt-hours annuallyto East Greenacres'pumping facilities in recent years.Id.
Avista asserts the annual charge for distribution service under the existing agreement is $4,231.74
per month or $50,780.88 per year.Id.
YOU ARE FURTHER NOTIFIED that Avista asserts the charge for distribution
service under the new Agreement is $5,232.57 per month or $62,790.84 per year.Id.The
distribution charge is based on East Greenacres'peak demand-ratio share of Distribution Facilities
Costs derived from Avista's last cost of service study filed in Case No.AVU-E-17-01 updated for
both the settlement adjustments and 2019 revenue increase approved by Order No.33953 and tax
reform adjustments approved by Order No.34070.Id.at 3-4.
YOU ARE FURTHER NOTIFIED that Avista states it does not have a tariff for
customers who take service in a manner similar to East Greenacres.Id.Further,Avista represents
that East Greenacres is the only customer in the Company's service territory who receives its
power requirements from the Bureau of Reclamation.Avista asserts the service characteristics
involved in the Agreement are unique,and the distribution charge is based on Commission-
supported demand-based methodology,the Company believes this contractual relationship is not
unreasonably preferential.Id.
YOU ARE FURTHER NOTIFIED that the Application is available for public
inspection during regular business hours at the Commission's office.These documents are also
available on the Commission's web site at .Click on the "File Room"tab at
the top of the page,then select "Electric Cases"and click on the case number as shown on the
front of this document.
YOU ARE FURTHER NOTIFIED that all proceedings in this case will be held
pursuant to the Commission's jurisdiction under Title 61 of the Idaho Code and specifically Idaho
Code §§61-501,61-502 and 61-503.
YOU ARE FURTHER NOTIFIED that all proceedings in this matter will be conducted
pursuant to the Commission's Rules of Procedure,IDAPA 31.01.01.000et seq.
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
ORDER NO.34506 2
SUSPENSION
YOU ARE FURTHER NOTIFIED that Avista's Application requests a January 1,
2020,effective date.Due to the limited time remaining in the 2019 calendar year the Commission
finds it appropriate to suspend Avista's proposed effective date for the Agreement.Consequently,
the proposed effective is suspended for a period of thirty (30)days plus five (5)months from
January 1,2020,unless the Commission issues an earlier Order accepting,rejecting,or modifying
Avista's Application.Idaho Code §61-622(4).
NOTICE OF MODIFIED PROCEDURE
YOU ARE FURTHER NOTIFIED that the Commission has determined that the public
interest may not require a formal hearing in this matter,and that it will proceed under Modified
Procedure pursuant to Rules 201 through 204 of the Commission's Rules of Procedure,IDAPA
31.01.01.201 through .204.The Commission notes that Modified Procedure and written comments
have proven to be an effective means for obtaining public input and participation.
YOU ARE FURTHER NOTIFIED that any person desiring to state a position on this
Application may file a written comment in support or opposition with the Commission by no
later than twenty-one (21)days from the service date of this Notice.The written comment
must contain a statement of reasons supporting it.Persons desiring a hearing must specifically
request a hearing in their written comments.Written comments concerning this Application shall
be mailed to the Commission and the Company at the addresses reflected below:
For the Idaho Public Utilities For Avista Corporation:Commission
David J.Meyer,Esq.
Commission Secretary Vice President and Chief Counsel forIdahoPublicUtilitiesCommissionRegulatoryandGovernmentalAffairsPOBox83720AvistaCorporation
Boise,ID 83720-0074 1411 E.Mission Avenue,MSC-27
Spokane,WA 99220-3727StreetAddressforExpressMail:E-Mail:
11331 W.Chinden Blvd.,Patrick D.EhrbarBuilding8,Suite 201-A Director,Regulatory Affairs
Boise,ID 83714 Avista Corporation
1411 E.Mission Avenue,MSC-27
Spokane,WA 99220-3727
E-Mail:
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
ORDER NO.34506 3
These comments should contain the case caption and case number shown on the first page of this
document.Persons desiring to submit comments via e-mail may do so by accessing the
Commission's home page located at Click the "Consumers"tab then click
the "Case Comment or Question Form"and complete the comment form using the case number as
it appears on the front of this document.
YOU ARE FURTHER NOTIFIED that the Company shall file reply comments,if
necessary,by no later than twenty-eight(28)days from the service date of this Notice.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are received
within the time limit set,the Commission will consider this matter on its merits and enter its Order
without a formal hearing.If written comments are received within the time limit set,the
Commission will consider them and,in its discretion,may set the same for a formal hearing.
ORDER
IT IS HEREBY ORDERED that the proposed effective date for the Agreement is
suspended for a period of thirty (30)days plus five (5)months from January 1,2020,unless the
Commission issues an earlier Order accepting,rejecting,or modifying Avista's Application.
IT IS FURTHER ORDERED that the Application of the Company be processed by
Modified Procedure,Rule 201-204 (IDAPA 31.01.01.201-.204).Persons interested in submitting
written comments must do so by twenty-one (21)days from the service date of this Notice.The
Company may file reply comments by no later than twenty-eight(28)days from the service date
of this Notice.
H
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
ORDER NO.34506 4
DONE by Order of the Idaho Public Utilities Commission at Boise,Idaho this day of
December 2019.
PAUL KJELI AÑDER,PRESIDENT
KËÍÚINË RAPER,COM'MISSIONER
ERIC ANDERSON,COMMISSIONER
ATTE T:
Diane M.Hanian
Commission Secretary
I:\Legal\ELECTRIC\AVU-E-19-13\orders\AVUE1913_NtcofApp_jrh.docx
NOTICE OF APPLICATION
NOTICE OF MODIFIED PROCEDURE
ORDER NO.34506 5