HomeMy WebLinkAbout20110706_3385.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER KJELLANDER
COMMISSIONER REDFORD
COMMISSIONER SMITH
COMMISSION SECRETARY
COMMISSION STAFF
FROM: KRISTINE SASSER
DEPUTY ATTORNEY GENERAL
DATE: JULY 1, 2011
SUBJECT: IDAHO POWER’S APPLICATION FOR A DETERMINATION
REGARDING THE FIRM ENERGY SALES AGREEMENT WITH
INTERCONNECT SOLAR DEVELOPMENT LLC, CASE NO. IPC-E-11-
10
On June 17, 2011, Idaho Power Company filed an Application with the Commission
requesting acceptance or rejection of a 25-year Firm Energy Sales Agreement (Agreement)
between Idaho Power and Interconnect Solar Development LLC (Interconnect Solar) dated June
7, 2011. The Application states that Interconnect Solar would sell and Idaho Power would
purchase electric energy generated by the Interconnect Solar photovoltaic solar generating
facility (Facility) located near Murphy, Idaho.
THE AGREEMENT
The Application states that Interconnect Solar proposes to construct, own, operate and
maintain a 20 MW (maximum capacity, nameplate) photovoltaic solar generating facility.
Application at 2. The Facility will be a QF under the applicable provisions of PURPA. The
Agreement is for a term of 25 years and contains avoided cost rates established pursuant to the
Commission’s approved Integrated Resource Plan (IRP) avoided cost methodology as currently
required by the Commission for solar QFs with a design capacity of more than 100 kilowatts
(kW). Order No. 32262. Idaho Power asserts that the 25-year contract term was the result of
negotiations that attempted to balance the parties’ interests in a manner that was favorable to
Idaho Power customers and to Interconnect Solar. Id. at 3.
Interconnect Solar selected June 1, 2012, as its Scheduled First Energy Date and July
1, 2012, as its Scheduled Operation Date. Id. at 3. Idaho Power asserts that various
requirements have been placed upon the Interconnect Solar Facility in order for Idaho Power to
DECISION MEMORANDUM 2
accept the Facility’s energy deliveries. Idaho Power states that it will monitor the Facility’s
compliance with initial and ongoing requirements through the term of the Agreement.
Interconnect Solar and Idaho Power have agreed to liquidated damage and security
provisions of $45 per kW of nameplate capacity. Agreement ¶¶ 5.3.2, 5.8.1. Delay Liquidated
Damages shall apply if Interconnect Solar fails to bring the Facility on-line by the Scheduled
Operation Date. Interconnect Solar is responsible to complete a Generation Interconnection
Agreement (GIA) and is responsible for all costs associated with interconnection of the Facility
to Idaho Power’s system and any necessary transmission upgrades for its generation to serve
load. Idaho Power states that, at the time this Application was filed, the GIA has not yet been
signed and the required payment for interconnection and transmission upgrades has not been
paid. Idaho Power estimates that, after payment is made, 18 months is required for Idaho Power
to complete the interconnection and transmission facilities. Idaho Power maintains that
Interconnect Solar has been expressly advised in writing that the Scheduled Operation Date it
selected was prior to such time that the interconnection/transmission facilities are scheduled to
be constructed and completed. Application at 8. Idaho Power states that Interconnect Solar has
acknowledged and expressly agreed to accept all risk associated with not meeting the Scheduled
Operation Date, including forfeiture of the Delay Security, and potential termination of the
Agreement. Id.
The parties have agreed to terms providing for each party’s 50% ownership of any
environmental attributes, including RECs, generated by the Facility for the full 25-year term of
the Agreement.
Energy prices in this Agreement are derived from Idaho Power’s AURORA
economic dispatch model for this Facility’s estimated energy shape as specified by Commission
requirements for the IRP-based avoided cost methodology. Id. at 5. The energy prices contain
the previously approved differentiation between heavy load and light load pricing, as well as
different seasonal prices. Id. This Agreement adds heavy load peak pricing to the months of
July and August. The energy price identified by the IRP methodology for this Facility is
equivalent to a 20-year levelized price of $105.15 per MWh. Id. However, Idaho Power states
that the actual energy pricing stream varies throughout the term of the contract based upon the
month and time of day during which the energy is delivered to Idaho Power. Id.
By its own terms, the Agreement will not become effective until the Commission has
approved all of the Agreement’s terms and conditions and declares that all payments made by
DECISION MEMORANDUM 3
Idaho Power to Interconnect Solar for purchases of energy will be allowed as prudently incurred
expenses for ratemaking purposes. Agreement ¶ 21.1.
Idaho Power requests that its Application be processed by Modified Procedure
pursuant to Commission Rules of Procedure 201-204. IDAPA 31.01.01.201-.204.
STAFF RECOMMENDATION
Staff recommends that the case be processed by Modified Procedure.
COMMISSION DECISION
Does the Commission wish to process this case under Modified Procedure?
M:IPC-E-11-10_ks