HomeMy WebLinkAbout20040913Reconsideration Order No 29587.pdfOffice of the Secretary Service Date September 13, 2004 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE PETITION FILED BY IDAHO POWER COMPANY FOR APPROVAL OF MODIFICATIONS TO THE SECURITY PROVISIONS REQUIRED TO BE INCLUDED IN POWER PURCHASE AGREEMENTS BETWEEN ELECTRIC UTILITIES (IDAHO POWER, A VISTA CORPORATION DBA A VISTA UTILITIES, AND) ACIFICORP DBA UTAH POWER & LIGHT COMPANY) AND PURPA QUALIFYINGFACILITIES (QFS). CASE NO. IPC-O3- A VU-O3- PAC-O3- ORDER NO. 29587 On November 5, 2003, Idaho Power Company (Idaho Power; Company) filed a Petition with the Idaho Public Utilities Commission (Commission) requesting authority among other things to eliminate the second lien requirement as a risk mitigation measure in PURP Power Purchase Agreements containing levelized avoided cost rates. Idaho Power in reply comments represented that should the Commission continue with the second lien requirement the Company intended to outsource the legal work and requested that it be permitted to collect the estimated $1 000-500 cost directly from the QF or alternatively recover the lien expense as part of its annual Power Cost Adjustment (PCA) filing. On April 27, 2004, the Commission issued final Order No.29482 in Case Nos. IPC-03-, A VU-03-, and PAC-03-13. In its Order the Commission denied Idaho Power s request to eliminate the second lien requirement as a risk mitigation measure for PURP A Power Purchase Agreements containing levelized avoided cost rates. For new levelized contracts the Commission authorized the Company to recover its lien expense from the contracting QFs; or alternatively, permitted a QF to prepare the lien documentation and file the lien itself. On May 17, 2004, Idaho Power filed a Petition for Reconsideration (IDAP A 31.01.01.331) or in the alternative a Petition for Clarification (IDAP A 31.01.01.325) regarding the portion of Commission Order No. 29482 that provides the option for QFs to prepare and file the lien or security interest documentation. ORDER NO.29587 On June 9, 2004, the Comrnission issued Order No. 29515 granting reconsideration and establishing a schedule for comment. As part of its reconsideration, the Commission noted that its seminal decision to authorize recovery from QFs of Company legal expenses related to second liens is also at issue. In this Order on Reconsideration the Commission eliminates the second lien self- perfection option for QFs and eliminates the utility s right to directly recover the legal costs attendant to preparing second line documentation from the QF. Petition for Reconsideration The specific Order language of concern to Idaho Power in its Petition for Reconsideration is the following: The Commission continues to find value for ratepayers in the presence of a second lien to secure overpayment liability. We recognize that securing a lien may entail some expense. We assume the Company s decision to outsource is based on a determination that the utility has no in-house expertise or that the cost of outsourcing the task is less than performing the task itself. The Commission finds that it is inappropriate to recover this type of expense as part of the Company s PCA. We find it reasonable, however for the Company to assess this cost to QFs. Alternatively, we find reasonable that the QF be permitted to prepare the lien documentation and to file the lien itself. The procedure that we approve for recovery of lien expense is for new levelized PURP A contracts only. Order No. 29482, p. 12. Idaho Power states that it understands the Commission s desire to minimize QF transaction costs, however, the Company is concerned with the conflict of interest created by allowing QF developers to prepare and file the documents needed to secure Idaho Power security interest in the assets of their respective QF projects. Idaho Code, Title 28 , Chapter 9 the Company notes, sets out very precise documentation and filing requirements to protect security interests. If the requirements are not filed precisely, the security interest is not perfected and is subject to attack in the event of competing creditors seeking to foreclose on the QF' assets. The QF's failure to correctly document, perfect and maintain its security interest in QF project assets would jeopardize the Company s ability to maintain a priority creditor position on the assets covered by the security interest. Idaho Power maintains that QF developers do not have a proper incentive to do a thorough job of creating and perfecting Idaho Power s security interest. If the Commission still ORDER NO.29587 desires to provide this option to QF developers, Idaho Power requests that the Commission clarify Order No. 29482 by requiring that QF developers electing to prepare and file the lien documentation must permit the Company to review and approve all aspects of the creation of the security interest. The Company also requests that the Commission clarify that if the exercises this option to self file, Idaho Power will have no obligation to take remedial steps if the QF developer fails to adequately cover all project assets or fails to file any required continuation statements to maintain the viability of this security interest over the full-term of the contract. Idaho Power notes that the recommended review and approval procedure of the second lien documentation prepared by QFs will require the Company to incur additional legal expense. Nevertheless, Idaho Power believes the initial review and approval by Idaho Power is necessary to at least reduce the likelihood of potential problems if a QF project experiences financial problems. Of further concern to the Company, the Commission s final Order No. 29482 also contains the following language: . . . For existing levelized PURP A contracts, the Company is expected to administer its contracts in a responsible fashion and to require QF compliance with Commission -292 security requirements. For those levelized contracts without a second lien, the QF should be brought into compliance or the Company should require a posting of liquid security. The Commission expects the Company to follow Commission Orders. Reference Idaho Code ~ 61-706. If liquid security is required but not enforced, it is the Company and not its customers that are at risk for the foregone security. Order No. 29482, p. 12. Idaho Power believes that it is unreasonable for the Commission to require the Company to accept a security interest created by the QF developer and then put the Company at risk if those security interests are not enforceable or do not cover all of the assets associated with a project. If the Commission gives QF developers the option to prepare and file the documents needed to perfect Idaho Power s security interest in the QF's assets, the Company believes that it should be relieved of any liability, even if it has review and approval authority, if it is ultimately determined that the security interest provisions of the Commission s -292 security requirements do not cover all of the QF assets or cannot be enforced. ORDER NO.29587 Comments on Reconsideration Comments on reconsideration were filed by Idaho Power, A vista and Commission Staff. The comments can be summarized as follows: A. Second Lien Requirement - QF Option to Self-Perfect Idaho Power On Reconsideration Idaho Power presents two alternative options:(l) that the Commission eliminate the self-perfection option; or (2) provide Idaho Power the right to review and approve the QF's documentation and perfection option. For either a first or a second lien to have any value, upon default, the lien holder Idaho Power contends, must be able to step into the shoes of the QF developer-owner as soon as possible and take over operation and maintenance of the project. Property involved in the QF project generally involves several different types of property, i., real property, fixtures personal property, and other property such as property and equipment leases, fuel supply contracts, easements, rights-of-way, etc. In Order No. 29482, the Commission stated its assumption that the Company decision to outsource the preparation and perfection of its second lien was based either on a determination by the Company that it was not comfortable using its in-house legal counsel to prepare and perfect QF second liens or a determination by the Company that the cost of outsourcing the task was less than performing the task itself. Both assumptions, the Company states, were correct. Secured transactions involve specialized areas of the law that are constantly changing. Another major part of secured transactions laws is the effect of bankruptcy on loan security. Bankruptcy law, the Company states, is a very specialized legal practice and missteps often lead to loss of priority. For all of these reasons, the Company has concluded that outsourcing the legal work associated with QF second liens to legal counsel that specialize in secured transactions and bankruptcy law is a prudent course to follow to protect the interest of both the Company and its customers. Allowing the QF developer to self-perfect the second lien, Idaho Power contends presents a conflict of interest. Idaho Power understands the Commission s desire to reduce the transaction cost to the QF associated with the second lien process. It is not Idaho Power s intent to make the process more complicated or more expensive than is reasonably required to protect the Company and ultimately its customers. That being said, Idaho Power is concerned that ORDER NO.29587 giving the QF the option to document, prepare and perfect a second priority security interest to attach to the QF's own property, presumably on behalf of Idaho Power, presents an inherent conflict of interest. Mortgages, deeds of trust, and security agreements often include notice provisions, default provisions, representations, warranties and definitions that could place the drafting QF's interest at odds with those of Idaho Power. Security instruments deemed adequate by a debtor may justifiably be viewed as deficient by a secured creditor. Moreover, the priority of a security interest perfected by filing or recording, as is the case with security interests in real property, fixtures and most personal property, depends in large part on the date and time of filing/recording. Idaho Power is concerned that allowing QF developers to control the filing/recording of these security instruments may further jeopardize Idaho Power s position. Unfortunately, the Company states, the only time the quality of QF developer self- perfected second lien interest will be truly tested is when the QF project has defaulted. When the QF fails to perform the requirements of the Firm Energy Sales Agreement, defaults on various loans and other credit arrangements can occur. In that event, the filing of additional liens by other creditors, the filing of foreclosure actions associated with those liens, and ultimately the filing of bankruptcy by the QF are distinct possibilities. At any of those points and times, the validity of all of the liens is closely examined by the creditors, the bankruptcy trustee and others who have an interest in having higher priority security interests set aside so that their particular debt is more likely to be paid. If the lien is improperly documented or perfected or maintained and is set aside, or if its priority is compromised, the bankruptcy trustee and other potential junior creditors, including any equity participants in the QF project will benefit. If the Commission does not eliminate the QF self-perfection option, at a minimum Idaho Power states, that it should be permitted to review and approve the second lien instruments and confirm that the second lien interest was properly perfected in accordance with Idaho law and in a timely manner. The Company requests that the Commission bear in mind that this option will essentially double the legal expense associated with second lien transactions. The QF will be required to pay its legal counsel to prepare the second line documents and Idaho Power will be required to pay its legal counsel to review and approve the second lien documents. Commission Staff Staff concludes that the -292 Second Lien Security Requirement is not broken, continues to be of value and requires no elimination, adjustment, modification or fix. Staff recommends ORDER NO.29587 that the Commission rescind its earlier decision to permit QFs to self prepare and perfect second liens. Staff in comments notes that in response to a production request the Company identified 25 projects with levelized rates that are subject to the Commission s -292 Second Lien Security Requirements. All of the projects with the exception of one have an existing and filed second lien. The one exception elected to post liquid security in the form of a letter of credit. Staff believes that Idaho Power s arguments are compelling for eliminating the QF option to self-perfect second liens. By not allowing the self-perfection option, Idaho Power can avoid incurring additional legal expense that would otherwise be necessary for review and approval of second liens perfected by the QF. In addition, removing the self-perfection option will alleviate the Company s concern about risk if those security interests are not enforceable or do not cover all of the assets associated with a QF project. Avista Corporation Avista recommends that creation of second liens on QF projects be handled in a manner similar to common commercial and real estate transactions. In those transactions, the party receiving the benefit of the lien or mortgage may prepare and file the lien or mortgage documents, or select the attorney or closing agent who performs the required legal work. other situations , a person or law firm who is neutral to the seller and the buyer performs the legal work associated with creating the lien. Although the person whose property is to be encumbered is responsible for executing appropriate documents, only in the most exceptional circumstances is that person actually tasked with the responsibility of preparing and filing the appropriate documents that create the lien. Allowing QF developers to prepare and file the required documents, A vista contends, would be an unnecessary departure from usual commercial practice. B. Recovery of Second Lien Legal Expense Idaho Power Because QF developers obtain significant financial benefits from rate levelization Idaho Power believes that it is appropriate for the Company to receive reimbursement for legal expenses it incurs to secure the significant loan that rate levelization represents. Idaho Power states that it has negotiated a favorable rate for legal services associated with perfecting the second lien on QF assets. Unless the QF is uncooperative or is using some very exotic financing scheme, the legal expense will be in the $1 000 to $1 500 range. ORDER NO.29587 If the Commission elects the review and approval option, Idaho Power requests that the Commission acknowledge that the legal expenses that Idaho Power incurs to review and approve the documents prepared by the QF are not unusual or one-time expenses and the Commission should authorize the Company to defer those legal expenses for recovery in a future revenue requirement proceeding, preferably as a QF purchase power expense in the Company PCA. Commission Staff Regarding cost recovery of legal expenses incurred in preparing and perfecting second liens, Staff recommends that the Commission rescind its decision permitting Idaho Power to recover the cost of legal expenses incurred in preparing and perfecting second liens, directly from QFs, regardless of whether the legal work is performed in-house or outsourced. Staff contends that the legal expenses of preparing and perfecting a second lien, whether done in- house or outsourced, is a contract administration cost and has never been a cost directly billed to QFs. Staff opposes the direct billing of this cost to QFs. The legal costs attendant to securing a second lien are an operating expense appropriate for consideration in rate case revenue requirement calculations. Avista Corporation A vista concurs that a utility should recover in its rates costs relating to preparing and/or reviewing second liens. Alternatively, Avista contends that the costs of preparation and/or review of such liens should be directly reimbursed by the developer. C. Responsibility for Problems Arising Out of QF Self-Perfected Second Liens Idaho Power Idaho Power understands that it is responsible for acting prudently when it undertakes any action in compliance with the Commission s Orders. However, the Company believes it is unfair for the Commission to allow QFs to self-perfect security interests in their own property and then hold the Company responsible if those security interests are not sufficient to preserve the validity or priority of the lien. The same holds true, the Company maintains even if it has review and approval rights. A vista Corporation If QF developers are assigned the task of preparing, filing and perfecting a second lien for a utility, then the utility, A vista contends, should not be held responsible for the viability ORDER NO.29587 of that security. It would be unreasonable, it states, to require a utility to accept a security interest created by a QF and then hold the utility responsible, if the security interest is not ultimately effective, enforceable or sufficient to cover all of the assets. COMMISSION FINDINGS The Commission has reviewed the filings of record in Case Nos. IPC-03-, A VU- 03-and PAC-03-13 including final Order No.29482 dated April 27, 2004.The Commission has also reviewed Idaho Power s Petition for Reconsideration/Clarification of final Order No. 29482, the Commission s Order No.29515 granting reconsideration and the comments filed by Idaho Power, Avista and Commission Staff. Idaho Power Commission Staff and A vista in comments all recommend that the Commission eliminate the self-perfection option created in Order No. 29482. The Commission has reviewed the comments and finds them persuasive. Finding them persuasive, we find it reasonable on reconsideration to rescind that portion of our Order at page 12 where we state: Alternatively we find it reasonable that the QF be permitted to prepare the lien documentation and to file the lien itself. Having determined to grant Idaho Power s request to eliminate the self-perfection option, the Commission finds no reason to relieve the Company of the risk associated with the foregoing security should liquid security be required but not enforced. Order No. 29482 p. 12. Finally, in our Order granting reconsideration the Commission noted its desire to review its seminal decision to authorize recovery from QFs of Company legal expenses related to second liens. In reconsidering same, the Commission finds recovery in base rates is a better regulatory treatment for legal expenses related to the preparing of second lien documentation. The costs should not be direct billed to QFs nor should it be recovered as part of the Company PCA. This has never been a cost directly billed to QFs, it is a contract administration cost. It is an operating expense that can be presented to the Commission for consideration as part of the Company s rate case revenue requirement. Accordingly, we find it reasonable to rescind that part of Order No. 29482 page 12 which states: we find it reasonable, however, for the Company to assess this cost to QFs. ORDER NO.29587 CONCLUSIONS OF LAW The Idaho Public Utilities Commission has jurisdiction over Idaho Power Company, Avista Utilities, and PacifiCorp, electric utilities, pursuant to Title 61 of the Idaho Code Idaho Code ~~ 61-624 and 61-626 and the Commission s Rules of Procedure, IDAPA 31.01.01.000 seq. ORDER In consideration of the foregoing and as more particularly described above, IT HEREBY ORDERED and the Commission on reconsideration of final Order No. 29482 eliminates the second lien self-perfection option of QFs previously granted in Order No. 29482 page 12. IT IS FURTHER ORDERED and the Commission on reconsideration eliminates the utility s right to directly recover the legal costs attendant to preparing second lien documentation directly from the QF as previously authorized in Order No. 29482, page 12. We instead find the legal costs attendant to securing a second lien to be contract administration costs and an operating expense appropriate for consideration in utility rate case revenue requirement calculati ons. THIS IS A FINAL ORDER ON RECONSIDERATION. Any party aggrieved by this Order or other final or interlocutory Orders previously issued in these Case Nos. IPC-03- , AVU-03-9 and PAC-03-13 may appeal to the Supreme Court of Idaho pursuant to the Public Utilities Law and the Idaho Appellate Rules. See Idaho Code ~ 61-627. ORDER NO.29587 DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this /3 ';+'" day of September 2004. JS~ MARSHA H. SMITH, COMMISSIONER ATTEST: vld/O:IPCEO316 _A VUEO309 _P ACEO313 _sw3 ORDER NO.29587