HomeMy WebLinkAbout20230711_PACE2317_cs.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER ANDERSON
COMMISSIONER HAMMOND
COMMISSIONER LODGE
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: CLAIRE SHARP
DEPUTY ATTORNEY GENERAL
DATE: JULY 11, 2023
SUBJECT: IN THE MATTER OF ROCKY MOUNTAIN POWER’S APPLCIATION
TO COMPLETE THE STUDY REVIEW PHASE OF THE STUDY OF
THE COSTS AND BENEFITS OF ON-SITE CUSTOMER GENERATION;
CASE NO. PAC-E-23-17
On June 29, 2023, Rocky Mountain Power, a division of PacifiCorp, (“Rocky Mountain
Power” or “Company”) applied to the Idaho Public Utilities Commission (“Commission”)
requesting the Commission complete the study review phase of the costs and benefits for on-site
customer generation. Application at 1. Commission Order No. 34753 defined the scope of the
Company’s study. Id. at 6. The Company attached its on-site generation study (“Study”) and
requested a timeline for intervention, public review and comment, as well as a finding that the
Study’s scope satisfied Order No. 34753. Id. at 1.
STAFF RECOMMENDATION
Staff recommends the Commission issue a Notice of Application and a Notice of
Intervention Deadline establishing a 21-day intervention deadline.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and a Notice of Intervention
Deadline establishing a 21-day intervention deadline?
_____________________________
Claire Sharp
Deputy Attorney General