Loading...
HomeMy WebLinkAbout20230131_TariffAdvice22-05_msmd1.pdfDECISION MEMORANDUM TO:COMMISSIONER ANDERSON COMMISSIONER LODGE COMMISSIONER HAMMOND COMMISSION SECRETARY LEGAL WORKING FILE FROM:MATTHEW E.SUESS MICHAEL DUVAL DATE:JANUARY 26,2023 RE:IDAHO POWER'S ANNUAL COMPLIANCE FILING TO UPDATE THE SUBSTATION ALLOWANCE UNDER SCHEDULE 19,LARGE POWER SERVICE,TARIFF ADVICE NO.22-05 BACKGROUND On December 28,2022,Idaho Power ("Company")filed the Tariff Advice No.22-05 proposing an update to the Substation Allowance outlined in Schedule 19,Large Power Service, required by Idaho Public Utilities Commission Order Nos.32893 and 32914.The Company requested that the updates to the allowance be approved with an effective date of February 1, 2023. STAFF ANALYSIS Staff recommends approval of the Company's proposed allowance amount as filed.The overall increase of 38 percent is a result of a 40 percent direct cost increase mitigated by a general overhead decrease of 2.06 percent resulting in an overall allowance increase from $57,640 per MW to $79,444 per MW. The allowance is a credit given to a Schedule 19 customer against the total cost of a substation upgrade,with the difference being directly charged to that customer for an upgrade needed to provide them with service.As will be discussed,the increase in this year's allowance is subject to abnormal inflationarypressure.However,because the allowance is credited against the total cost of the project,which is also subject to the same inflationarypressure,the increases are offsetting,thereby keeping the impact to customers consistent. DECISION MEMORANDUM -1 -JANUARY 31,2023 Staffreviewed the Company's cost adjustment and methodology used to determinethe proposed allowance and believes it conforms with Order Nos.32893,32914,32982,and 34576 from Case Nos.IPC-E-13-09 (Glanbia Foods Petition for Allowance to Rule H),IPC-E-14-01 (Schedule 19 Update),and IPC-E-19-40 (Update to Substation Allowance Under Schedule 19), respectively.Under the current methodology,the Company determines the per Megawatt ("MW")substation allowance by dividing the estimated fully loaded costs for constructing a transformer substation by 44.8 Megavoit Amperes ("MVA"),which is the rating of the transformer commonly used by the Company for this type of service.I Staff validated the Company's direct costs for labor,material,and vehicles and found them to be reasonable given current inflation rates.Prior to the adjustment for overhead cost, substation direct cost increased by 40%from the previous year.The increase in costs affecting labor,material,and vehicles is attributed to pandemic-relatedsupply chain issues and shortages in the labor market,which are beyond the control of the Company.The two biggest contributors to the increase were the 44.8 MVA transformer (average cost increase of 12%)and the 4-unit metal-clad switchgear (average cost increase of 88%).Project labor costs also went up 10 percent. Staff believesthe proposed overhead rate is reasonable and recommends approval as filed,Staff verified the Company's inputs and calculation of general overheads associated with substations.The Schedule 19 general overhead rate represent capital costs that cannot be directly assigned to a specific asset or individualproject,and are applied to all vehicle,labor,and direct material costs.The proposed general overhead rate for the 12-months ending October 31, 2022,was 6.57 percent,which decreased from the current authorized rate of 8.63 percent. STAFF RECOMMENDATION Staffrecommends the Company's proposed update to Schedule 19 be approved as filed with an effective date of February 1,2023. 'MVA and MW are equivalent for purposes of determining the cost per MW of the Substation Allowance. DECISION MEMORANDUM -2 -JANUARY 31,2023 COMMISSION DECISION Does the Commission wish to approve the Company's proposed update to Schedule 19 as filed with an effective date of February 1,2023? Matthew E.uess DECISION MEMORANDUM -3 -JANUARY 31,2023