HomeMy WebLinkAbout20220419_cb1.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER ANDERSON COMMISSIONER CHATBURN COMMISSIONER HAMMOND COMMISSION SECRETARY COMMISSION STAFF LEGAL FROM: CHRIS BURDIN DEPUTY ATTORNEY GENERAL DATE: APRIL 19, 2022 SUBJECT: IN THE MATTER OF ROCKY MOUNTAIN POWER’S APPLICATION REQUESTING APPROVAL OF $28.4 MILLION ECAM DEFERRAL; CASE NO. PAC-E-22-05 On March 30, 2022, PacifiCorp dba Rocky Mountain Power (“Company”) applied for
Commission authorization to adjust its rates under the Energy Cost Adjustment Mechanism
(“ECAM”). Specifically, the Company seeks an order approving approximately $28.4 million in
ECAM deferral and a 4.5 percent increase to Electric Service Schedule No. 94, Energy Cost
Adjustment.
The Company requests that its proposed adjustment to the Electric Service Schedule
No. 94 be processed by Modified Procedure and become effective on June 1, 2022.
STAFF RECOMMENDATION
Staff recommends that the Commission issue a Notice of Application and Notice of
Modified Procedure, setting a May 13, 2022, public comment deadline and a May 19, 2022,
Company reply deadline.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of Modified
Procedure setting a May 13, 2022, public comment deadline, and a May 19, 2022, Company reply
deadline?
Chris Burdin
Deputy Attorney General
I:\Legal\ELECTRIC\PAC-E-22-05 ECAM\memos\PACE2205_Dec_cb.docx