HomeMy WebLinkAbout20220222_rn1.pdf
DECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER ANDERSON
COMMISSIONER CHATBURN
COMMISSIONER HAMMOND
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: RILEY NEWTON
DEPUTY ATTORNEY GENERAL
DATE: FEBRUARY 22, 2022
SUBJECT: IN THE MATTER OF IDAHO POWER COMPANY’S APPLICATION FOR
APPROVAL OR REJECTION OF AN ENERGY SALES AGREEMENT
WITH SHINGLE CREEK LLC, FOR THE SALE AND PURCHASE OF
ELECTRIC ENERGY FROM THE SHINGLE CREEK HYDRO PROJECT;
IPC-E-22-02.
On February 4, 2022, Idaho Power Company (“Company”) applied to the Commission
for an order approving an Energy Sales Agreement (“ESA”) between the Company and Shingle
Creek LLC, (“Seller”) for the purchase of electric generation from the Shingle Creek Hydro Project
(“Facility”) located near Riggins, Idaho. The ESA is a new contract with the same Qualifying
Facility (“QF”) for a new term and current terms and conditions. The Company requests its
Application be processed by Modified Procedure.
STAFF RECOMMENDATIONS
Staff recommends the Commission issue Notice of Application and Notice of Modified
Procedure and establish a March 31, 2022, public comment deadline and an April 7, 2022,
Company reply deadline.
COMMISSION DECISION
Does the Commission wish to issue Notice of Application and Notice of Modified
Procedure establishing a March 31, 2022, public comment deadline and an April 7, 2022, reply
deadline?
Riley Newton
Deputy Attorney General
I:\Legal\ELECTRIC\IPC-E-22-02 Shingle Creek\memos\IPCE2202_memo_rn.docx