HomeMy WebLinkAbout20210706_dh1.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER KJELLANDER
COMMISSIONER RAPER
COMMISSIONER ANDERSON
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: DAYN HARDIE
DEPUTY ATTORNEY GENERAL
DATE: JUNE 30, 2021
SUBJECT: IN THE MATTER OF IDAHO POWER COMPANY’S APPLICATION FOR
APPROVAL OF ITS LOAD CURTAILMENT AND INTERRUPTION
PLAN; CASE NO. IPC-E-21-13.
On May 11, 2021, Idaho Power Company (“Company”) applied for approval of its 2021
Load Curtailment and Interruption Plan (“LCIP”) and for authority to update its Electric Service
Rule J—Continuity, Curtailment, and Interruption of Electric Service. The Company requests its
Application be processed by Modified Procedure.
STAFF RECOMMENDATION
Staff recommends the Commission issue a Notice of Application and Notice of 21-day
intervention deadline.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of 21-day
intervention deadline?
__________________________
Dayn Hardie
Deputy Attorney General
I:\Legal\ELECTRIC\IPC-E-21-13\memos\IPCE2113_dec1_dh.docx