HomeMy WebLinkAbout20090413_2530.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER KEMPTON
COMMISSIONER SMITH
COMMISSIONER REDFORD
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: NEIL PRICE
DEPUTY ATTORNEY GENERAL
DATE: APRIL 9, 2009
SUBJECT: AVISTA CORPORATION’S APPLICATION FOR APPROVAL OF AN
ELECTRIC DISTRIBUTION SERVICE AGREEMENT WITH EAST
GREENACRES IRRIGATION DISTRICT, CASE NO. AVU-E-09-02
On February 2, 2009, Avista Corporation (“Avista” or “Company”) filed an
Application with the Commission seeking approval of its Electric Distribution Service
Agreement with East Greenacres Irrigation District (“Greenacres”).
On March 4, 2009, the Commission issued a Notice of Application and Notice of
Modified Procedure and established a 21-day open comment period. Order No. 30739.
Commission Staff was the only party to file written comments within the established comment
period.
THE AGREEMENT
The Electric Distribution Service Agreement (“Agreement”) entered into between
Avista and Greenacres provides for the continuation of “United States Bureau of Reclamation
(“Bureau” or “Bureau of Reclamation”) energy over Avista owned and operated distribution
facilities from Avista’s Post Falls Substation to certain delivery points on the Greenacres
system.” Application at 1. The effective date of the Agreement is March 1, 2009 or the first day
following an Order by the Commission granting approval of the Agreement. Id.
The Application stated that the Agreement is “unique, and therefore more
appropriately provided under a special contract rather than a filed tariff.” Id. at 2. Avista stated
that the distribution rate charged by the Company is “consistent with distribution charges
embedded in current Idaho retail rates” and the net revenues generated via the Agreement will
DECISION MEMORANDUM 2
serve as an offset to the Company’s fixed costs. Id. In recent years, Avista has delivered
approximately 3.1 million kWhs to Greenacres’ pumping facilities at an annual rate of $8,157.
Id. at 3.
The parties entered into the Agreement on January 30, 2009. Id. The Agreement
does not contain a fixed termination date. Id. However, the parties contemplate that the
Agreement will terminate contemporaneously with the occurrence of either of the following
conditions: (1) the termination of the parties’ Transmission Agreement; or (2) one year prior
written notice submitted by either party. Id. The distribution charge recited in the Agreement is
$3,622.77 per month, or $43,473.24 per year. Id. The Application stated that the charge was
“derived from Avista’s last cost of service study” and subsequent settlement adjustments and
revenue increases associated with Case No. AVU-E-08-01 and Commission Order No. 30647.
Id. at 3-4.
Avista stated that “the contract is non-discriminatory and is not unreasonably
preferential.” Id. at 4. The Company requested that its Application be processed under the
Commission’s Modified Procedure rules. Id. at 2.
STAFF COMMENTS
Staff reviewed the Agreement by utilizing Avista’s cost-of-service study approved in
its last general rate case, AVU-E-08-01, to verify the Company’s rate calculations. Staff
Comments at 2. Staff stated that Greenacres’ annual distribution charge of $43,473 is calculated
by determining its “Load Ratio Share” (Greenacres’ annual energy consumption ÷ Idaho’s
normalized annual energy consumption) and applying that ratio, 0.0978%, to the cost of Idaho’s
distribution facilities, $44,451,166. Id.
Staff mentioned that the jurisdictional energy methodology employed by Avista is
just “one of several methodologies that can be used to establish a facilities charge.” Id. While it
does not oppose the Company’s use of an energy allocation methodology, Staff believes that
“allocation of distribution facilities used by the irrigation district based on demand is more
appropriate” because “the cost of distribution facilities is driven by demand rather than energy.”
Id. Staff discussed this issue with Avista and the Company agreed to work with Staff “to
develop a demand-based rate calculation methodology for use in the future.” Id. Staff also
added that the necessary data for applying Avista’s energy allocation methodology was more
prevalent than demand data. Id. at 3.
DECISION MEMORANDUM 3
Staff acknowledged that the energy based distribution agreement was mutually agreed
upon and approved by both the parties. Id. Further, Staff believes that the general body of
ratepayers will not be harmed by approval of this agreement and therefore recommends that the
Commission approve the Agreement. Id.
COMMISSION DECISION
Does the Commission wish to approve Avista’s Application for approval of its
Electric Distribution Service Agreement with East Greenacres Irrigation District?
M:AVU-E-09-02_np2