BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF VEOLIA WATER IDAHO, INC. FOR
APPROVAL OF WATER MAIN
INSTALLATION AGREEMENT
Case No. VEO-W-23-01
VEOLIA WATER IDAHO, INC.’S
RESPONSES TO FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF
Veolia Water Idaho, Inc. (“Veolia” or “Company”) in response to the First Production
Request of the Commission Staff to Veolia Water Idaho, Inc. dated June 15, 2023, submits the
following responses.
DATED June 28, 2023.
GIVENS PURSLEY LLP
By
Preston N. Carter
Attorneys for Veolia Water Idaho, Inc.
RECEIVED
2023 JUNE 28, 2023 12:29PM
IDAHO PUBLIC
UTILITIES COMMISSION
VEOLIA WATER IDAHO, INC.’S RESPONSES TO FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF PAGE 2 OF 2
CERTIFICATE OF SERVICE
I hereby certify that on June 28, 2023, I caused to be served a true and correct copy of the
foregoing document to the person(s) listed below by the method indicated:
Jan Noriyuki, Commission Secretary
Idaho Public Utilities Commission
11331 W. Chinden Blvd., Bldg. 8, Suite 201-A
Boise, ID 83714
U.S. Mail, postage prepaid
Express Mail
Hand Delivery
Facsimile
Email jan.noriyuki@puc.idaho.gov
_________________________________________
Preston N. Carter
VEO-W-23-01
IPUC Staff PR 1
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-23-01
FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: C. Cooper
REQUEST NO. 1:
Please provide the estimated cost for construction for the proposed main line extension.
RESPONSE NO. 1:
We estimate construction cost for the proposed main line extensions between $3,000,000
and $3,500,000.
VEO-W-23-01
IPUC Staff PR 2
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-23-01
FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: C. Cooper
REQUEST NO. 2:
Please provide the approximate annual maintenance costs for the proposed main line
extension.
RESPONSE NO. 2:
Maintenance costs will be minimal and could include pipeline flushing, valve exercising,
and hydrant maintenance. Estimated total maintenance cost per year of not more than $3,000.
VEO-W-23-01
IPUC Staff PR 3
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-23-01
FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: Preston Carter /
Marshall Thompson
REQUEST NO. 3:
The second request in the Company’s Prayer for Relief is for the Commission to enter an
Order “Approving the Agreement, and Veolia’s performance under the Agreement.” Application
at 3. Please clarify what the Company means regarding its “performance under the Agreement.”
RESPONSE NO. 3:
The intent of the quoted language is to clarify that Veolia requests that the Commission
approve both the Agreement itself, as well as the actions that Veolia will take pursuant to the
Agreement, which are identified in the Agreement itself. Veolia does not view this language as
materially different from standard language in a prayer for relief, and does not expect that this
language would result in an order from the Commission that is materially different from orders
in other similar cases.
VEO-W-23-01
IPUC Staff PR 4
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-23-01
FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: C. Cooper
REQUEST NO. 4:
Please clarify if the scope of the main line extension will include service lines and
hookups to each affected home. If not, how will service be extended to them? Who will pay the
expense to connect each resident?
RESPONSE NO. 4:
The scope of the main line extension will not include service lines and hookups to each
affected home. Veolia will pay for each service line from the main to the meter box, and the
customer meter. The individual property owner will pay the cost of any service line from the
back leg of the meter to their home.
VEO-W-23-01
IPUC Staff PR 5
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-23-01
FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: C. Cooper
REQUEST NO. 5:
Please provide the number of new service connections the Company anticipates from the
main line extension.
RESPONSE NO. 5:
We believe there will be a minimum of 30 service connections initially, this is the
approximate number of homeowners in the planned construction area who have contacted Ada
County with immediate well concerns. In the future, additional individual property owners that
front the main would likely request service. There are 173 properties that the proposed mains
will front.
VEO-W-23-01
IPUC Staff PR 6
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-23-01
FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: C. Cooper
REQUEST NO. 6:
Please provide a map showing the planned and main line extension and the Company’s
service boundary in the vicinity.
RESPONSE NO. 6:
The attached map shows the planned main line extension areas in relation to the
Company’s service area boundary.
BOGUS BASIN
SHAW MOUNTAIN
SUNSET PEAK
§¨¦I-84
§¨¦I-84
§¨¦I-84
§¨¦I-84
MERIDIAN
BOISE
GARDENCITY
EAGLE
KUNA
BOISE BOISE
KUNA
EAGLE
W Cherry Ln
W Ustick Rd
N Orchard St
S Five
Mile Rd
W Chinden Blvd
N Ten
Mile Rd
E Lake Hazel Rd
W Franklin Rd
S Vista Ave
E Gowen Rd
N Meridian Rd
S Federal Way
W Overland Rd
E Hwy 21
E Kuna Mora Rd
N Five
Mile Rd
S Capitol
Blvd
W Overland Rd
S Cole Rd
W Fairview Ave
N Cole Rd
W State St
E Overland Rd
S Meridian Rd
E ChindenBlvd
S Broadway Ave
S Orchard St
W Lake Hazel Rd
W Fairview Ave
N Meridian Rd E Fairview Ave
W Franklin Rd
E Front St
W Chinden Blvd W State St
S Ten Mile Rd
E Ustick Rd
E ChindenBlvd
W Lake Hazel Rd
E Franklin Rd
N Glenwood St
S Eagle Rd
N Hwy 55
N Eagle Rd
E State St
S Eagle Rd
W Hwy 44
E Parkcenter Blvd
E Hwy 44
N Hwy 55
E KunaMora Rd E KunaMora Rd W Kuna Mora Rd
Print Date: 5/6/2022 No Scale
WATER DISTRIBUTION SYSTEM
±
Service Area
VEO-W-23-01
IPUC Staff PR 7
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-23-01
FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: J. Cary
REQUEST NO. 7:
Please provide the expected tax effects of this project.
RESPONSE NO. 7:
Because the property is to be contributed as CIAC, which is treated as exempt for
income-tax purposes, there should be no income tax effects from the project for ratemaking
purposes.