HomeMy WebLinkAbout20230202Veolia to Staff 159-162(Sixth Set).pdfVEOLIA WATER IDAHO, INC.’S RESPONSES TO SIXTH PRODUCTION
REQUEST OF THE COMMISSION STAFF PAGE 1 OF 3
16596950_1.DOCX (30-235)
Preston N. Carter, ISB No. 8462
Blake W. Ringer, ISB N. 11223
Givens Pursley LLP
601 W. Bannock St.
Boise, ID 83702
Telephone: (208) 388-1200
Facsimile: (208) 388-1300
prestoncarter@givenspursley.com
blakeringer@givenspursley.com
Attorneys for Veolia Water Idaho, Inc.
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF VEOLIA WATER IDAHO, INC. FOR A
GENERAL RATE CASE
Case No. VEO-W-22-02
VEOLIA WATER IDAHO, INC.’S
RESPONSES TO SIXTH PRODUCTION
REQUEST OF THE COMMISSION STAFF
In response to the Sixth Production Request of the Commission Staff to Veolia Water
Idaho, Inc. dated January 25, 2023, Veolia Water Idaho, Inc. (“Veolia” or “Company”), submits
the non-confidential responses contained below. Documents are available for download at the
link provided in the transmittal email. Confidential responses and documents will be provided
separately under the terms of the Protective Agreement. An updated response to Request No. 42
of the Commission Staff is also available at the same link.
DATED: February 1, 2023.
By:_____________________________
Preston N. Carter
Givens Pursley LLP
Attorneys for Veolia Water Idaho, Inc.
RECEIVED
Wednesday, February 1, 2023 4:44:14 PM
IDAHO PUBLIC
UTILITIES COMMISSION
VEOLIA WATER IDAHO, INC.’S RESPONSES TO SIXTH PRODUCTION
REQUEST OF THE COMMISSION STAFF PAGE 2 OF 3
16596950_1.DOCX (30-235)
CERTIFICATE OF SERVICE
I certify that on February 1, 2023, a true and correct copy of the foregoing was served
upon all parties of record in this proceeding via electronic mail as indicated below:
Commission Staff Via Electronic Mail
Jan Noriyuki, Commission Secretary
Idaho Public Utilities Commission
11331 W. Chinden Blvd., Bldg. 8, Suite 201-A
Boise, ID 83714
jan.noriyuki@puc.idaho.gov
Dayn Hardie
Deputy Attorney General
Idaho Public Utilities Commission
11331 W. Chinden Blvd., Bldg. 8, Suite 201-A
Boise, ID 83714
dayn.hardie@puc.idaho.gov
Lorna K. Jorgensen
Meg Waddel
Ada County Prosecuting Attorney’s Office
Civil Division
200 W. Front Street, Room 3191
Boise, ID 83702
civilpafiles@adacounty.id.gov
Sharon M. Ullman, pro se
5991 E. Black Gold St.
Boise, ID 83716
sharonu2013@gmail.com
Austin Rueschhoff
Thorvald A. Nelson
Austin W. Jensen
Holland & Hart, LLP
555 17th Street, Suite 3200
Denver, CO 80202
darueschhoff@hollandhart.com
tnelson@hollandhart.com
awjensen@hollandhart.com
aclee@hollandhart.com
kdspriggs@hollandhart.com
Jim Swier
Micron Technology , Inc.
8000 South Federal Way
Boise, ID 83707
jswier@micron.com
VEOLIA WATER IDAHO, INC.’S RESPONSES TO SIXTH PRODUCTION
REQUEST OF THE COMMISSION STAFF PAGE 3 OF 3
16596950_1.DOCX (30-235)
Mary Grant
Deputy City Attorney
Boise, City Attorney’s Office
150 N. Capitol Blvd.
PO Box 500
Boise, ID 83701-0500
BoiseCityAttorney@cityofboise.org
mrgrant@cityofboise.org
Preston N. Carter
VEO-W-22-02
IPUC DR 159
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-22-02
SIXTH PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: Cooper
REQUEST NO. 159:
Please identify any procurement starting October 1, 2022, through the period up to the
current date, where the procurement was not compliant with the SUEZ North American Inc.
Procurement Policy (Revised July 2020). In each case, please explain why it was not compliant
and provide all Company documentation used to justify moving forward with the procurement
even though it was not compliant.
RESPONSE NO. 159:
None.
VEO-W-22-02
IPUC DR 161
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-22-02
SIXTH PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: Njuguna
REQUEST NO. 161:
For the following items included in the Company's rate base calculations, please
provide the balances for the months ended December 31, 2021; January 31, 2022; and
February 28, 2022.
a.Accumulated Deferred Income Taxes
b.Deferred Charges
c.Regulatory Liability - TCJA
d.Working Capital
RESPONSE NO. 161:
Please see the attachment for the information requested.
VEO-W-22-02
IPUC DR 162
Page 1 of 1
VEOLIA WATER IDAHO, INC.
CASE VEO-W-22-02
SIXTH PRODUCTION REQUEST OF THE COMMISSION STAFF
Preparer/Sponsoring Witness: Njuguna
REQUEST NO. 162:
Please update the Deferred Power with actual power costs to December 31, 2022.
RESPONSE NO. 162:
Please see the attachment.