HomeMy WebLinkAbout20070730_1998.pdfDECISION MEMORANDUM
TO:CO MMISSI 0 NER KJELLAND ER
COMMISSIONER SMITH
COMMISSIONER REDFORD
COMMISSION SECRETARY
LEGAL
WORKING FILE
FROM:RICK STERLING
DATE:JULY 25, 2007
RE:CASE NO. IPC-06-34 (Idaho Power)
FIRST AMENDMENT TO HOT SPRINGS WINDFARM FIRM ENERGY
SALES AGREEMENT
On July 11 , 2007, Idaho Power Company (Idaho Power; Company) submitted for
Commission approval an amendment (First Amendment) to the December 20, 2006, Firm
Energy Sales Agreement (Agreement) between Idaho Power and Hot Springs Windfarm LLC
(Hot Springs). The original Agreement was approved on February 20 2007, in Order No. 30246
(Order). Idaho Power and Hot Springs desire to amend the Agreement to (1) revise the wind
turbine manufacturer and specifications; (2) revise the scheduled operation date; and (3) provide
liquid security in the amount of estimated Delay Damages.
BACKGROUND
In the original Agreement, Hot Springs selected December 31, 2007 as the estimated
scheduled operation date for the Hot Springs Windfarm Project (Project). The Agreement
contains provisions that require the Project to pay Idaho Power liquidated damages if the Project
comes online after December 31 2007 (Delay Damages). The Delay Damages will accrue for a
period of up to ninety days. (Agreement Sections 5.6).
In the Order approving the original Agreement, the Commission noted that the Hot
Springs Windfarm Project had not signed an interconnection agreement at the time of the
Commission s approval of the Agreement. During the negotiation of the Agreement, Hot
Springs indicated to Idaho Power that it believed that the costs of interconnection would be
DECISION MEMORANDUM - 1 -JULY 25, 2007
manageable and that the time required for interconnection studies would not adversely impact its
ability to meet the December 31 , 2007 scheduled operation date.
Hot Springs has now completed initial discussions with Idaho Power s delivery business
unit as required by the Agreement. As a result of those discussions, it has become apparent that
the Hot Springs Project will require network upgrades in order to accommodate the Project'
generation and that the time required for completion of necessary studies and the construction of
necessary interconnection facilities and network upgrades will delay the Project's online date
beyond the December 31 , 2007 scheduled operation date. Such a delay will trigger Delay
Damages.
Hot Springs is also now concerned about its ability to absorb all of the network
upgrade costs. Hot Springs has indicated that the type of settlement that is proposed in Case
No. IPC-06-21 (Cassia Case) will allow it to proceed with its Project. However, until Case
No. IPC-06-21 is resolved, Hot Springs is reluctant to proceed.
FIRST AMENDMENT
1. Wind Turbine Manufacturer and Specifications
The delay in interconnection of the Project has caused Hot Springs' investor and wind
turbine supplier to reallocate the project's turbines to another project. Hot Springs must now
wait for the next available turbines, which are due before the end of the year. One of the new
turbine options requires a modification of the type and size of wind turbines allowed under the
Agreement. The First Amendment reflects this change in turbine manufacturer and size. It also
recognizes that the turbine market is volatile and additional changes in turbine configuration may
be required in the future.
2. Scheduled Operation Date
In light of the foregoing, Hot Springs has requested that Idaho Power agree to amend the
Agreement to extend the scheduled operation date for a period of approximately one year. Hot
Springs believes this time is necessary to ensure that it will be able to meet the revised scheduled
operation date and give the Project the opportunity to avoid the payment of Delay Damages.
3. Liquid Security
Idaho Power states that it is willing to enter into the First Amendment for two reasons.
First, in exchange for this Amendment, Hot Springs is willing to provide Idaho Power with
DECISION MEMORANDUM - 2 -JULY 25 , 2007
liquid security in an amount sufficient to cover the liquidated Delay Damages. This provision is
not currently included in this or other QF contracts and Idaho Power believes that the inclusion
of this provision provides value for the Company and its customers. Second, Idaho Power is
aware of two other wind projects in the same area facing similar delays due to unanticipated (by
the developer) interconnection delays (Bennett Creek; Alkali Wind). If the Commission concurs
Idaho Power indicates that it will propose a similar resolution for those proj ects.
The Hot Springs and the Bennett Creek contracts were the first wherein the firm energy
sales agreements will be separate from the interconnection agreements. When power sales
agreements are approved first, without signed transmission interconnection agreements, projects
can be delayed and necessitate later amendments to firm energy sales agreements. FERC'
Standard of Conduct rules make it impossible for the Company s power supply business unit to
independently confirm the reasonableness of the QF developer s selection of a particular date for
scheduled operation. To address this problem in the future, Idaho Power states that it has
implemented new contract procedures. As a result, Idaho Power states that it will now be the
policy of the power supply business unit not to sign firm energy sales agreements until the QF
project developer can demonstrate that it has completed its interconnection application to the
extent that the scheduled operation date is unlikely to be modified due to delays in the
interconnection study and transmission construction process. This is the only way that the
Company can be reasonably certain that the scheduled operation dates selected by the QF
developer are realistic.
COMMENTS OF IDAHO WINDS LLC
Idaho Winds LLC is the developer of Alkali Wind Farm (IPC-06-36; Order No.
30253), a PURP A qualified facility with an Idaho Power contract. The Alkali project (Project)
faces similar obstacles to meeting its online date due to unanticipated interconnection delays.
Idaho Winds is currently engaged in discussion with the Idaho Power delivery business unit and
like Hot Springs and Bennett Creek, it has become apparent that Alkali will require network
upgrades in order to accommodate the Project's generation and the time required for completion
of necessary studies and the construction of necessary interconnection facilities and network
upgrades will delay this Project's online date beyond the December 31 , 2007 Scheduled
Operation Date, triggering Delay Liquidated Damages.
DECISION MEMORANDUM - 3 -JULY 25, 2007
Idaho Winds believes that the Delay Liquidated Damages provision of Alkali Project's
contract is adequate to protect Idaho Power and its customers and objects to Idaho Power
proposal to require Delay Security from Idaho Winds and its PP , or upon any other developer
in a similar situation.
STAFF ANALYSIS
Staffhas no objection to amending the Agreement to revise the wind turbine
manufacturer and specifications. The particular turbine manufacturer and specifications are not
critical, and do not change the energy product Idaho Power will be purchasing under the
Agreement.
As a condition of the one-year contract extension, the parties propose extending the
scheduled operating date by approximately one year. Because both Idaho Power and Hot
Springs are in agreement, Staff does not oppose the proposed changes. Unlike most of the other
wind contracts wherein the projects have yet to come online, this Agreement contains liquidated
damages provisions in the event of delays in achieving the expected online date.
Staff believes strongly that approval of the First Amendment should not carry with it
either explicit or implicit approval of any terms of interconnection. The Interconnection
Agreement, which is yet to be signed, and the Firm Energy Sales Agreement are clearly two
separate agreements. The Hot Springs project is not included in the "Twin Falls" cluster and will
not be included in a settlement stipulation in Case IPC-06-24; therefore, whether any terms of
the proposed settlement in the pending IPC-06-24 case relating to QF interconnection can be
applied to this project is yet to be determined. Staff expects that a separate interconnection
agreement for this project will be submitted for Commission approval at a later date.
Hot Springs agrees to provide liquid security in the amount of estimated Delay Damages.
Staffhas no objection to this change in security. Idaho Power states that if the Commission
concurs, Idaho Power would propose a similar resolution for other wind projects in the same
vicinity that are facing similar transmission interconnection delays. Although Staff does not
have any particular objections to proposals for similar resolutions for other projects, Staff wishes
to make it clear that it does not believe that Commission approval of the Hot Springs First
Amendment should be interpreted by the Company as blanket approval for any other wind
DECISION MEMORANDUM - 4 -JULY 25 , 2007
contracts. Staff recommends that the Commission decline to comment on this proposal of the
Company.
STAFF RECOMMENDATION
Staff recommends that the Commission issue an Order: (1) approving the First
Amendment to the Firm Energy Sales Agreement (Attachment 1) without change or condition;
and (2) confirming that the costs associated with the Agreement as amended will be approved as
prudent expenditures for ratemaking purposes as originally provided in Order No. 30246. Staff
recommends that the Commission decline to comment on the Company s proposal to use the
Liquid Security" amendment to the online delay damages provision agreed to by the contract
parties in this case as a template for other instances of QF failure to achieve scheduled operation
dates.
COMMISSION DECISION
Does the Commission wish to approve the First Amendment to the Firm Energy Sales
Agreement between Idaho Power and Hot Springs Windfarm LLC?
Does the Commission agree with Staff s recommendation that the Commission decline to
comment on the Company s proposal to use the "Liquid Security" amendment to the online
delay damages provision agreed to by the contract parties in this case as a template for other
instances of QF failure to achieve scheduled operation dates?
Rick Sterling
i:drnemos/ipceO634.drn
DECISION MEMORANDUM - 5 -JULY 25 , 2007