HomeMy WebLinkAbout20200904CDS Stoneridge to Staff 4-9.pdfi{Ei;ttvr*
To whom it may concern,
This is a response to the First production request from the IPUC staff. Case# SWS-W-20-6{;* S[f -fu PS 3:39
: :'.i.'- i:ti*Lii:
, - :.-: ," * r.rrJiiMi$sishi
Answer to request #4.
A) The complete break-down for the cost of parts is attached. Estimate E20252 from H.D.
Fowler Dated 71912020. Also attached is the current cost for the meter in the estimate from
Consolidated Supply. The full cost of $ZZlg.SZ and 5826.80 is for a connection that must be
tied back to the water main. These costs do not reflect excavation labor. Parts costs can be
reduced for connections that have curb stops in place by subtracting line items 1, 2 and 5
bringing the cost of parts to 52038.64 plus the cost of the meter. These are approximate
prices and the most up to date that we can provide at this time.
B) To complete a road crossing a bore is achieved by the contractor exposing the water line
and preparing a pit on both sides of the road. The contractor then pulls a 3-inch casing
under the road to install the water connection in. exploratory excavation and labor (hand
digging around underground utilities) takes time to accomplish safely. Boring prevents the
need of closing the road and putting unneeded asphalt patches in our roads. Pavement
cutting and patching falls in the contingency category and is not included in the cost
estimate for a standard bore. Asphalt cutting and patching is based on the size of area
effected and the cost of product at the time. This will be discussed in greater depth in
request #9.
C) The responsibilities of the operator, at the point that a person turns in their application for
water service, the operator must do a preliminary survey of the lot for a will or will not serve
letter. Next is a location plan, locate all utilities and the location of the new services. This
can include reading maps and looking for valves and lines with a metal detector or other
locating devices. Determining if a bore will be needed, do we have a curb stop or will we
need to tap the main. Will a shut down of the neighborhood be needed. lf so a 24-hour
notice must be handed out, construction samples must be taken after wards. At this point
the contractor is scheduled. The operator observes all phases of the work preformed by the
contractor. The operator completes the documentation and returns it to the office staff for
the setup of accounting. With the lack of verifiable information and the age of the
subdivisions this can be a lengthy process.
Request #5
A) The bid from Leo's excavation. Leo was given the required parts list that was included in our
application from consolidated supply dated 6/20119. I can not speak for Leos excavation but
I assume the 52500.00 included all of the required parts.
B) Leo did not give a breakdown of his estimates, but what was expected is the excavation of
the water main, open a pit to bore from, open a pit to set the meter and perform the tie in,
bore under the road. with appropriate backfill and compaction.
C) Once again, I cannot speak for Leos excavation. The work expected is, hot tap the water
main. Assemble all required parts and install the meter set. Test and back fill with proper
compaction.
D) To my knowledge this bid did not include any permitting, traffic control or company
administrative Costs.
E) To my knowledge this bid did not include any contingency estimates.
Request #6
Request #7
Request #8
Request #9
A) Swank Excavation was given the same required parts list as Leo's. this was included in the
application and you can see the parts again in the "parts estimates'attached to this email.
Due to the environment in this country at the moment prices are fluctuation regularly.
These costs would be under the 52462.27 parts and materials. The estimated cost of
53708.00 to my understanding was for exploratory excavation to locate all unmarked
utilities and the close proximity to the phone and power "hand work" that was required on
both sides of the road. Also, reshaping of the ditch line after installation of the meter set
that was required.
B) The scope of work that was expected was the excavation of the water main, open a pit to
bore from, open a pit to set the meter and perform the tie in, bore under the road. lnstall a
3-inch sleeve and finish with appropriate backfilland compaction.
C) No patching was required
D) Yes, this bid included traffic control
E) No, to my knowledge this bid did not include any of the Stoneridge administrative costs.
F) No, to my knowledge this bid did not include any contingency estimates.
as in response to the work preformed by C&D Dirtworks that was included in the application.
That was completed prior to my employment with Stoneridge. I have no information to add to
the invoices and the employees that were involved no longer work here. So I can not expand on
the scope of work preformed or why the costs. That invoice was included to show actual cost
being paid by Stoneridge for connections not just bids. But those costs reflect prices from 2019.
To my understanding C&D Dirtworks is no longer available to or will perform the work at those
costs any longer.
Contingencies: are costs that accrue from abnormal conditions. Damage to unmarked or
unknown utilities. Excessive exploratory excavation to locate utilities. Asphalt cutting and
patching. Reconstruction of landscape or ditch lines due to excessive exploration. Or any other
unforeseen issue. Each of these issues are priced on an individual basis by cost, size or time
allotted.
To whom it may concern,
This is a response to the First production request from the IPUC staff. Case# SWS-W-20-01
Answer to request #4
A) The complete break-down for the cost of parts is attached. Estimate E2O252 from H.D.
Fowler Dated7l9l2020. Also attached is the current cost for the meter in the estimate from
Consolidated Supply. The full cost of 52273.52 and 5825.80 is for a connection that must be
tied back to the water main. These costs do not reflect excavation labor. Parts costs can be
reduced for connections that have curb stops in place by subtracting line items 1, 2 and 5
bringing the cost of parts to 52038.64 plus the cost of the meter. These are approximate
prices and the most up to date that we can provide at this time.
B) To complete a road crossing a bore is achieved by the contractor exposing the water line
and preparing a pit on both sides of the road. The contractor then pulls a 3-inch casing
under the road to install the water connection in. exploratory excavation and labor (hand
digging around underground utilities) takes time to accomplish safely. Boring prevents the
need of closing the road and putting unneeded asphalt patches in our roads. Pavement
cutting and patching falls in the contingency category and is not included in the cost
estimate for a standard bore. Asphalt cutting and patching is based on the size of area
effected and the cost of product at the time. This will be discussed in greater depth in
request #9.
C) The responsibilities of the operator, at the point that a person turns in their application for
water service, the operator must do a preliminary survey of the lot for a will or will not serve
letter. Next is a location plan, locate all utilities and the location of the new services. This
can include reading maps and looking for valves and lines with a metal detector or other
locating devices. Determining if a bore will be needed, do we have a curb stop or will we
need to tap the main. Will a shut down of the neighborhood be needed. lf so a 24-hour
notice must be handed out, construction samples must be taken after wards. At this point
the contractor is scheduled. The operator observes all phases of the work preformed by the
contractor. The operator completes the documentation and returns it to the office staff for
the setup of accounting. With the lack of verifiable information and the age of the
subdivisions this can be a lengthy process.
Request #5
A) The bid from Leo's excavation. Leo was given the required parts list that was included in our
application from consolidated supply dated 6/20/19. I can not speak for Leos excavation but
I assume the 52500.00 included all of the required parts.
B) Leo did not give a breakdown of his estimates, but what was expected is the excavation of
the water main, open a pit to bore from, open a pit to set the meter and perform the tie in,
bore under the road. with appropriate backfill and compaction.
C) Once again, I cannot speak for Leos excavation. The work expected is, hot tap the water
main. Assemble all required parts and install the meter set. Test and back fill with proper
compaction.
D)
E)
Request #6
A)
B)
c)
D)
E)
F)
Request #7
Request #8
Request #9
To my knowledge this bid did not include any permitting, traffic control or company
administrative Costs.
To my knowledge this bid did not include any contingency estimates.
Swank Excavation was given the same required parts list as Leo's. this was included in the
application and you can see the parts again in the "parts estimates' attached to this email.
Due to the environment in this country at the moment prices are fluctuation regularly.
These costs would be under the 52462.27 parts and materials. The estimated cost of
53708.00 to my understanding was for exploratory excavation to locate all unmarked
utilities and the close proximity to the phone and power "hand work" that was required on
both sides of the road. Also, reshaping of the ditch line after installation of the meter set
that was required.
The scope of work that was expected was the excavation of the water main, open a pit to
bore from, open a pit to set the meter and perform the tie in, bore under the road. lnstall a
3-inch sleeve and finish with appropriate backfill and compaction.
No patching was required
Yes, this bid included traffic control
No, to my knowledge this bid did not include any of the Stoneridge administrative costs.
No, to my knowledge this bid did not include any contingency estimates.
as in response to the work preformed by C&D Dirtworks that was included in the application.
That was completed prior to my employment with Stoneridge. I have no information to add to
the invoices and the employees that were involved no longer work here. So I can not expand on
the scope of work preformed or why the costs. That invoice was included to show actual cost
being paid by Stoneridge for connections not just bids. But those costs reflect prices from 2019.
To my understanding C&D Dirtworks is no longer available to or will perform the work at those
costs any longer.
Contingencies: are costs that accrue from abnormal conditions. Damage to unmarked or
unknown utilities. Excessive exploratory excavation to locate utilities. Asphalt cutting and
patching. Reconstruction of landscape or ditch lines due to excessive exploration. Or any other
unforeseen issue. Each of these issues are priced on an individual basis by cost, size or time
allotted.
**Ship Tieket **
CONSOLIDATED SUPPLY CO - CDA
155 EiAST DAIJTON AVE
DAIJTON GARDENS, ID 83815
Phone # z 208-762-2558
Consolidated
Supply Co.
lll il llillilll]ilrilililfl]il1iltil r I t[Printad: 10:21:36 09 JUL 2020
BILL To: 130397
LUKE SWAI{K
1380 EWEIJIJ
POST FAIJLS,rD 83854
sfiIP ro:
LUKE SVIAI{K
1380 EWEI,I,
POST FALLS, ID 83854
208 - 659 - 70 08
Pieees:_ Box€s:_ PalleEs:_ Bags:_ Bundles:_ thwrs:_
Plcked By:
07/oe/2a s009846881. 0ol
*c. o. D. c. o. D. *
l-ofL
o7 09 20 DOI.]OH I ******e.o.D. onI WCN WC NOW Prc Br 14
L4
Stoner HOUSE CDA Plumb 0.0 BilIable
ea
fMTERGRAL A}ITENNA A}TD PIT MOTJNT
TOUCH PAD, L2FT IJEADLoc: BB02-07-1F Pn: L3]-52L7
Invoice Amount.
ORDER TOTAI,Sales tax
.00Oea
780.00
45.80
825.80
780.
Customer:
Estimator:
Iob Name:
Location:
H.D. FOWLER
COMPANY
SWANK EXCAVATING
Josh Shore
STONERIDGE RESORT
BLANCHARD IDAHO
Estimate:
Bid Date:
Bid No: E420252 page 1of2
E420252
7lsl2izo
Line Qty UonA Description
WATEB SERVTCE1 EA 9.05 X 1" lp 202 SADDLE BODY ONLY 8.63 - 9.05 ROMAC2 EA 9.80 S S STRAP WITH NUTS FOR SADDLE RANGE 8,53 .9.05 - 9.80 ROMAC
FB11O1.4q.NL 1* MIP X PEP QUICK JOINT BALLCORP CORP STOP NO-LEAD
FORD
C86.44Q-NL 1" MIP X PEP QUICK JOINT COUPLING NO-LEAD FORD
811.444.N1 1" FIP X FIP BALI VALVE CURB SrOP NO-LEAD FORD
6.'SDR35 3034 GASKETED PVC SEWER PIPE 14'LENGTH
6, PSM CAP SW FOR SEWER OR DRAIN
C16-44Q-NL 1" FIP X PEP QUICK JOINT COUPLING NO-LEAD FORD
1" rps QUICK JOTNT SnFFENER ST2QALSO CAN BE USED AS 1_U4" CTS
STIFFENER S53Q FORD
1" tpsstDR-7 250 pst poLy ptpE lo0,ROLL pE4710 ASTM D_2239
PFCBHH-488-18'48-R-NL 1" corL prr SETTER BALL VALVE x cHEcK VALVE 18',
X 48'' NO-LEAD FORD
CCID-l8 18- CC INSULATING DISC FORD
PPSC.18-L 18'ONE PIECE FLAT LOCKING METER BOX COVER FORD
1.,SCH 40 GALVANIZED COUPLING IMPORT
L" XL2" SCH 40 GALVANIZED NIPPLE A53 ERW
1, SCH 40 GALVANIZED CAP IMPORT
Section Subtotal:
Unit Price Extended price
1EA
1EA
1EA
L4 FT
1EA
1EA
3EA
1OO FT
1EA
1EA
1EA
1EA
1EA
1EA
1
2
3
4
5
6
7
8
9
10
11
L2
13
t4
15
16
42.86
58.20
721.71
48.27
L33.82
3.22
14.78
41.55
3.11
0.85
L,423.25
42.86
116.40
L2L,7L
48.27
133.82
45.08
L4.78
41.55
9.33
86.00
L,423.25
47.3L
125.98
4.87
9.31
3.00
7.L6
2.56
0.64
3.18
5.13
124.60
47.31
125.98
4.87
9.31
3.00
7.16
5.t2
6.40
3.18
10.26
L24.60
4zffiffi
L7
18
19
20
2t
22
1EA
2EA
10 EA
TEA
2EA
1EA
1EA
1EA
1EA
1EA
20 FT
40 FT
2EA
2EA
23
24
25
26
27
28
29
30
YARD HYDRANT
L,,X314" SCH 40 GALVANTZED TEE tMpoRT
1,' SCH 40 GALVANIZED MALE INSERT ADAPTER IMPORT
L3/16" - 1-314" SS WORM DRTVE HOSE CLAMP
314" X 6" SCH 40 GALVANIZED NIPPLE A53 ERW
1" SCI.I 40 GALVANIZED 90 STREET ELBOW IMPORT
SIMMONS 4'BURYYARD HYDRANT 3/4' FlpT TNLET 4804 LEAD FREE **78.5'
OVERALL LENGTH
Section Subtotal:
SEWER SERVTCE
4" SCH 40 PVC COUPUNG SXS
4" SCH 40 PVC TEE SXSXS
4u X 2" SCH 40 PVC BUSHING SXS
4., PVC PRO SPAN EXPANSION REPAIR COUPLING IPS HUB X SPIGOT lsOPSI#0118-40 FLO CONTROL
4" SCH 40 IPS SOLVENT WELD PVC PIPE 20' LENGTH
2.' SCH 40 IPS SOLVENT WELD PVC PIPE 20, LENGTH
2, PVC BALL VALVE IPS SLIP X SLIP lsOPSI E1310.20
2" SCH 40 PVC 45 ELBOW SXS
10.95
35.40
L4.45
59.92
ffi"ab
10.95
35.40
14.45
59.92
57,80
39.20
25.24
8.60
2.89
0.98
12.62
4.30
Bid No: E420252 Page 2 of 2
31
32
33
2EA10 FT
2E
2" SCH 40 PVC 90 ELBOW SXS
6' 2729 SOLID SOLVENT WELD PVC DRATN PIPE 10' LENGTH
6'' PSM CAP SW FOR SEWER OR DRAIN
Section Subtotal:
3.65
1.93
14.78
7.30
19.30
29.55
?07.72
Approximate Total 2,737.96
-*- i,'t- t-o{* c/e(; .V,(:
1fl
"i :; {o"4. ,? tr