Falls Water Company Application for Approval of Three Capital Projects
Data Request Response
Request No.: FLS-W-21-01 IPUC DR 22
REQUEST NO. 22: Please provide the Company's planned schedule for completing the
remaining drinking water improvements shown in Table 7 – Projects Addressing
Existing Deficiencies of the 2019 Falls Water Company Drinking Water Capital Facilities
Plan.
Response:
The planned schedule to complete the projects shown in Table 7 – Projects Addressing
Existing Deficiencies of the 2019 Capital Facilities Plan is shown in the table below:
Project
ID Project Description Scheduled Planned/Completed
A-1 Ryan Anderson Development Well (Well 11) 2021 In Progress
A-2
Cowley Road from 1st Street to John Adams
Pkwy 2020 Completed
A-3
Lincoln Road from 4743 E Lincoln to Wood
River Road 2021 Completed
A-4
Replace 6” Pipe in Fall River Road with 8”
Pipe 2021 Planned
A-5 Replace 6” Pipe in Edwards Drive with 8” Pipe 2022 Planned
A-6 Harding Lane from Kit Lane to 1st Street 2024 Planned
A-7 25th East and Iona Road Waterline Extensions 2020 Completed
A-8
Ammon Road from Pearce Drive to
Greenwillow Dr Complete
A-9
Ammon Road from Greenwillow Drive to
O’Bryant Street 2024 Planned
A-10 Replace 6” Pipe in Dixie Street with 10” Pipe 2022 Planned
A-11 Replace 8” Pipe East of Well 2 with 12” Pipe 2023 Planned
A-12
First Street from Robison Drive to Wheatfield
Lane 2024 Planned
A-13
First Street from Ammon Road to Nassau
Drive 2022 Planned
A-14
Replace Fallsbrook asbestos cement pipe –
Lakewood St to Upland St 2026 Planned
FLS-W-21-01 IPUC DR 22
NWN Response
Page 2 of 2
Project
ID Project Description Scheduled Planned/Completed
A-15
Replace Fallsbrook asbestos cement pipe –
Jensen Drive 2026 Planned
A-16
Replace Fallsbrook asbestos cement pipe –
Contor Avenue 2025 Planned
A-17
Replace Fallsbrook asbestos cement pipe –
Crawford Street 2025 Planned
A-18
Replace Fallsbrook asbestos cement pipe –
North Adams Drive 2024 Planned
A-19
Replace Fallsbrook asbestos cement pipe –
Mobile Drive 2024 Planned
A-20
Increase the volumetric water right capacity by
at least 535 acre-feet and the diversion rate by
3,170 gpm
Obtain
water right
as
available
Purchased 208 AF
of water in 2021.
A-21
Reconfigure the SCADA system control of
pump start and stop triggers 2021 In Progress