Loading...
HomeMy WebLinkAbout20210714FLS to Staff 16.pdf Rates & Regulatory Affairs FLS-W-21-01 Falls Water Company Application for Approval of Three Capital Projects Data Request Response Request No.: FLS-W-21-01 IPUC DR 16 REQUEST NO. 16: Please provide the detailed source information (vendor bids, cost estimates, calculations, etc.) associated with each Estimated Cost in Exhibits 2 and 3 of the Company's Application. Please include within your response the dollar amount for each activity by vendor, specifically identifying activities performed by the Company and any affiliated companies or individuals. Response: The cost estimates provided in Exhibits 2 and 3 of the Company’s Application are engineering estimates provided by S&A Engineers. The estimates for the storage tank and booster pump station and for the Taylor Mountain Well 2 well building from Exhibit 2 are entirely engineering estimates. The Exhibit 3 cost estimates for the storage tank and booster pump station (repeat of cost estimate shown in Exhibit 2) and the 1,500 gpm well and pump station are also entirely engineering estimates. The cost estimate for Well 11 and the pump station have some actual cost components. The drilling of the well began in November 2020. The drilling was completed and test pumped in April 2021. The test pump revealed that the well capacity is 2,500 gpm. Copies of the two invoices are included in FLS-W-21-01 IPUC DR 16 Attachment 1 (Exhibit 4). The total cost to drill the well was $234,375.00. FLS-W-21-01 IPUC DR 16 Attachment 2 (Exhibit 5) are copies of the cost estimates/invoices from the following vendors:  American Pump for the cost of the pumping equipment and column (excluding electrical, plumbing, and concrete) for $182,790  Rocky Mountain Valves & Automation, Inc. for part of some of the valves for the well house piping for $7,240.82  Ferguson Waterworks for pipe and fittings for the flow to waste line and pipe from well house to existing distribution main and connection fittings to connect to the existing main for $24,359.02. Due to the system pressure issues caused by drought and hot temperatures, the Company’s employees will work on Well 11 and complete items 11, 13-16. They will also dig the footings for the wellhouse (portion of Item 6) and connect the pipes and FLS-W-21-01 IPUC DR 16 NWN Response Page 2 of 2 valves from the wellhead to the distribution main (portion of Item 9). Labor costs associated with the Company’s employees completing these items and known materials costs at the time of completing this response are listed below. Please see FLS-W-21- 01 IPUC DR 16 Attachment 3 (Exhibit 6) for Labor cost calculations. that the Company’s employees will complete. The difference will be bid out to be The remaining items on Well #11 project’s list will be put out for bid. Currently, the engineering cost estimate is available for these items. The other projects listed in the Company’s application Exhibits 2 and 3 have not begun and no bid process has been done. The engineering cost estimates methodology for the storage tank and booster pump station project, the Taylor Mountain Well #2 well house project, and the 1,500 gpm well as an alternative to the storage tank and booster pump station are shown in FLS-W-21-01 IPUC DR 16 Attachment 4 (Exhibit 7) prepared by S&A Engineering. IPUC DR 16 ATTACHMENT 1 FALLS WATER CO., INC. Well #11 Drilling and Test Pump Invoices (2 PAGES) f-ALLS VvATEh CO.. !IM!^ , Due Date / Account Code i Amount ^ P.O. Box 3810-BuHe.MT 59702 Office: (406) 494-3310 Fax: (406) 494-3301 Email: info@okeefedrilling.com Client: Falls Water tSmpany Attention: Tom Wood Project; Falls Water Company Well 11 Item Number and Description Unit Price Written In Words I - MOBILIZATION / DEMOBIUZATION -20-INCH DRIVE SHOE ; - 20-INCH DRILLING Quantity Unit Price Dollars I Cts S 14,000.00 1 EACH $ 475.00 ___ ^ LF S 210.00 FWC21-01 15-Mar-21 208-589-5555 Total Amount i • 20-INCH TEMPORARY CASING S 200.00 • 16-INCH DRIVE SHOE - 16-INCH DRIltiNG • 16-INCH .375" WALL CASING - 12-INCH DRILUNGW/CASING - 12-lNCH .375" WALL CASING "" - CUT AND PULL 12-INCH CASING & Perforate if needed - 12-INCH TELESCOPING SS SCREEN (144' of 10" Casing and 55' of 12-inch SS Screen) -GROUTING Cement Hole -PULL 20-INCH TEMPORARY CASING -10-INCH HEAD PIPE $ 375.00 139_ $ 160.00 ^ $ 85.00 601 LF 400 IF , S 63.50 260 LF S 46.00 ^ S 80.00 3_ S 200.00 i_ a_ $ 3,250.00 36 1^ S 40.00 0. L^ S 55.00 l-K-PACKER 16 TO 10-INCH I - WELL DEVELOPMENT I-WELL DISINFECTION I - PUMP TEST MOBIUZATION/DEMOBILIZATION I-PUMPINGTEST I - RIG DIRECTED RATE 0 EACH $ 750.00 8_ HOUR $ 450.00 IS_ S 4,000.00 S 15,000.00 S 300.00 S 450.00 Total Amount Due:$ 195,275.00 FLS-W-21-01 IPUC DR 16 Attachment 1 Page 1 of 2 FALLS V\^ATER CO., INC. Inv Date Due Date En-Zl Invoice # C52^ Account Code $ Amount Posted by:, td t<aiu Client: Attention: Posted. Falls Water Company Tom Wood P.O. Box 3810 - Butte, MI 59702 Office: (406) 494-3310 Fax: (406) 494- Email: info@okeefedrillins.com Falls Water Company Well 11 Item Number and Description Unit Price Written in Words DRItilNG AND TESTING WEU. 11 - MOBILIZATION / DEMOBILIZATION -20-INCH DRIVE SHOE - 20-INCH DRILLING - 2Q-INCH TEMPORARY CASING -16-INCH DRIVE SHOE - 16-INCH DRIIUNG - 16-INCH .375" WALL CASING - 12-INCH DRILLING W/CASING - 12-INCH .375" WALL CASING - CUT AND PULL 12-INCH CASING & Perforate if needed - 12-INCH TELESCOPING SS SCREEN (144' of 10" Casing and 55' of 12-inch SS Screen) -GROUTING Cement Hole -PULL 20-INCH TEMPORARY CASING - 10-INCH HEAD PIPE •K-PACKER 16 TO 10-INCH -WELL DEVELOPMENT - W;LL DISINFECTfON - PUMP TEST MOBILIZATION/DEMOBILIZATION -PUMPING TEST -RIG DIRECTED RATE Invoice: FWC21-02 Date: 15-Api-21 Phone: 208-589-5555 Quantity Total Amount Unit Price Doiiars I c5 Dollars S 14,000.00 S 47S.00 $ 210.00 $ 200.00 $ 375.00 S 160.00 S 85.00 $ 63.50 S 46.00 S 80.00 ^ S 200.00 C^ $ 3,250.00 _____ 1^ n S 40.00 ; 0_ 1^ j S 55.00 $ 750.00 HOUl S 450.00 1_ ^ S 4,000.00 1_ S 15,000.00 67_ HR. S 300.00 S 450.00 Total Amount Due: FLS-W-21-01 IPUC DR 16 Attachment 1 Page 2 of 2 IPUC DR 16 ATTACHMENT 2 FALLS WATER CO., INC. Cost Estimates / Invoices (4 PAGES) American Pump PO Box 267 Ucon,ID 83454 (208) 557-8677 info@americanpumpco.com CUSTOMER FALLS WATER CO. 2180 N. DEBORAH DRIVE IDAHO FALLS ID 83401 (208) 522-1300 Estimate ESTIMATE# DATE PC# 56350090 06/17/2021 SERVICE LOCATION FALLS WATER CO. 2180 N. DEBORAH DRIVE IDAHO FALLS ID 83401 (208) 522-1300 DESCRIPTION Estimate Description Qty Rate Total SS CONE STRAINER 1.00 600.00 600.00 14RJHC-6 STAGE, WATER LUBE, 12" DISCHARGE, THREADED SUCTION BS17I BLANK SHAFTING 17-4 1 15/16 (UPGRADE SHAFT) LBR14 INSTALL ALUM BRONZE WEAR RINGS ON BOWLS (6 STAGE) STEEL BACKED RUBBER BUSHINGS 1.00 17,550.00 1.00 2,700.00 1.00 3.150.00 1.00 952.00 17,550.00 2,700.00 3,150.00 952.00 SS BOLTING UPGRADE FOR BOWLS 240' 12" COLUMN ASSEMBLY (12" X 1-15/16" SS SHAFT, W/L RETAINERS) Install PVC STILLING TUBE GPHDIX12 GOULDS PUMP HEAD DUCTILE IRON 12" (Including 1-15/16" packing box, head shaft, head nut, base plate 400 HP VHS Motor 450HP VFD LOW HARMONIC DRIVE (NO FILTER REQUIRED) OUT DOOR RATED TRANSDUCER LEG KIT STRIKE SORBS DISCONNECT 1.00 600.00 1.00 56,000.00 1.00 1,000.00 1.00 8,700.00 1.00 33,908.00 1.00 47,630.00 600.00 56,000.00 1,000.00 8,700.00 33,908.00 47,630.00 EXTEND WELL CASING, INSTALL PUMP 1.00 10,000.00 10,000.00 FLS-W-21-01 IPUC DR 16 Attachment 2 Page 1 of 4 CUSTOMER MESSAGE ASSUMES COLUMN COMING FROM MANUFACTURE NEAR FRESNO DOES NOT INCLUDE ELECTRIAL WORK, PLUMBING, OR CONCRETE DOES NOT INCLUDE FREIGHT VFD WILL NEED A PAD TO STAND ON AND SHOULD HAVE A SUN SHADE INSTALLED OVER IT TO HELP KEEP IT COOL Estimate Total;$182,790.00 PRE-WORK SIGNATURE Signed By: FLS-W-21-01 IPUC DR 16 Attachment 2 Page 2 of 4 ROCKV MOUNTAIN VALVES & AUTOMATION, INC. Rocky Mountain Valves & Automation, Inc Salt Lake City, Utah 84104 Order Acknowledgement Date P.O. No. 6/25/2021 Well #11 Name I Address Falls Water Company Tony Wise 2180 N Deborah Or Idaho Fails, ID 83401 Ship To Falls Water Company Tony Wise 2180 N Deborah Dr Idaho Falls Rep S.O. No.Terms Est. Ship Date Ship Via FOB Project ALS 16401 COD 8/13/2021 Included Factory Item Description Quantity Rate Amount VM-7212 VM-102SXr Shipping 12" Val-Matic Surge Buster Check Valve Model 7212, Ductile Iron Body, 125# FLG Ends, Buiia-N Coated Disc, Fusion Bonded Epoxy Coated IN70UT, 302 SST Disc Accelerator 8-10 Weeks ARC 2" Val-Matic Air/Vacuum Valve, Model 102SXF, Cast Iron Body, 316 SS Trim, Buna-N Seat, N.P.T Threaded Iniet, Rated 300PS1, Fusion Bonded Epoxy Lined & Coated Stock in SLC Shipping Sales Tax 5,995.77 5,995.77T 505.00 505.00T 350.00 6.00% 350.00 390.05 Please Contact Rocky Mountain Valve Immediately If There Are Any Discrepencies. (801)-438-1038 Total $7,240.82 FLS-W-21-01 IPUC DR 16 Attachment 2 Page 3 of 4 ^FERGUSON^ WATERWORKS 6715 WEST OVERLAND DRIVE IDAHO FALLS. ID 83402-5700 TOTAL PJJEhL xVCUSTpMSlV PAGE 0786808 $24,359.02 40882 1 Of 1 PLEASE REFER TO INVOICE NUMBER WHEN MAKING PAYMENT AND REMIT TO: Please contact with Questions: 208-528-7490 FERGUSON WATERWORKS #1701 PO BOX 802817 CHICAGO. IL 60680-2817 SHIPTOr FALLS WATER COMPANY I NO 2180 N DEBORAH DRIVE IDAHO FALLS. ID 83401 FALLS WATER COMPANY INC 1770SABIN DRIVE IDAHO FALLS. ID 83406 SHIP WHSE. 1701 SELL WHSE. 1701 TAX CODE IDONLY CUSTOMER ORDER NUMBER WELL PIPING SALESMAN BDO JOB NAME INVOICE DATE 08/28/21 BATCH lO 39644 ORDERED SHIPPED ITEM NUMBERS ,,, > DKCRIFpjDN UNIT PRICE UM AMOUNT 700 80 80 1 3 7 1 1 1 1 10 1 1 1 700 80 80 1 3 7 1 1 1 1 10 1 1 1 DR18BPX AFT50PX AFT50P12 MJF9LAX MJ9LAX T602210 MJ9LA12 MJF9LA12 MJTLA12 MJLSLA12 T602220 MA236123120L FNWNBGZ1RR812 FNWNBGZ1RR8X 8 0900 DR18 PVC GJ BLUE PIPE 8 CL50 CL Dl FASTITE PIPE J312CL50CLDIFASTITEPIPE ^ t. t-gtft '38 MJXFLG C153 90 BEND L/A 8 MJ C153 90 BEND L/A - > f2 8 DI/PVC MJ REST TUFGRIP GLND PK 12 MJ 0153 90 BEND L/A "3^ 12 MJXFLG 0153 90 BEND L/A 12 MJ 0153 TEE L/A 12X12 MJ 0153 LONG SLV L/A i- « 12 DI/PVO MJ REST TUFGRIP GLND PK I " 12 Dl MJ RW OL GATE VLV L/A > 12 ZN 150# RR RNG 1/8 FLG PKG J * 8ZN150#RRRNG1/8FLGPKG fS / Lf I 14.790 23.970 39.990 331.459 224.328 79.815 478.135 775.801 664.356 364.533 145.858 2134.960 48.357 22.532 FT FT FT EA EA EA EA EA EA EA EA EA EA EA LEAD LAW US FEDERAL PRODUOTS W NON-POTABLE O ^ R CAl NING: IT IS ILLEG OTHER APPLI TH -NP IN THE DS APPLIOATIONS AL TO INSTALL PRODL BLELAWIN POTABLE SORIPTION ARE NOT LI BUYER IS SOLELY RESFl INVOICE SUB-TOTAL TAX OTS THAT ARE NOT "LEAD FREE" IN ACCORDANCE WITH WATER SYSTEMS ANTICIPATED FOR HUMAN CONSUMPTION IAD FREE AND CAN ONLY BE INSTALLED IN ONSIBLE FOR PRODUCT SELECTION. Idaho FALLS o;;. mc. Date „ Due uato $ AmountAccount uode Inv Invoice # Poe tsy D Pttia Posted Looking for a more convenient way to pay your bill? Log in to Ferguson.com and request access to Online Bill Pay. 10353.00 1917.60 3199.20 331.46 672.98 558.71 478.14 775.80 664.36 364.53 1458.58 2134.96 48.36 22.53 22980.21 1378.81 TERMS:NET10TH PROX ORIGINAL INVOICE TQTALDUE $24,359.02 All past due amounts are subject to a service charge of 1.5% per month, or the maximum allowed by law, If lower. If Buyer falls to pay within terms, then In addition to other remedies. Buyer agrees to pay Seller all costs of collection. Including reasonable attorney fees. Complete terms and conditions are available upon request or at https://www.ferguson.com/content/webslte-info/terms-of-sale, incorporated by reference. Seller may convert checks to ACH. FLS-W-21-01 IPUC DR 16 Attachment 2 Page 4 of 4 IPUC DR 16 ATTACHMENT 3 FALLS WATER CO., INC. Labor Cost Calculations (16 PAGES) PROVIDED SEPARATELY AS CONFIDENTIAL IPUC DR 16 ATTACHMENT 4 FALLS WATER CO., INC. Engineering Cost Estimates Methodology (8 PAGES) June 30, 2021 Scott Bruce Falls Water Company 2180 N Deborah Idaho Falls, ID 83401 Re: Methodology to Develop Recent Cost Estimates for Well 11 and Pump Station, Storage Tank and Booster Pump Station at Well 9 Site, Future 1,500 gpm Well and Pump Station and Well 2 Site and Pump Station Rehabilitation in the Taylor Mountain Water System Dear Scott, Per your request and pursuant to answering questions posed by the IPUC regarding our cost estimates for the referenced projects, we give our methodology used to develop these cost estimates. We describe the methodology first philosophically and secondly with details drawn from the methodology. Our cost estimating for these facilities is based on communications with pipe and equipment suppliers, contractors, engineering subconsultants and knowledge and experience gained through the engineering design process, which for me personally, now spans 29 years. I spend the bulk of my effort on the high-dollar cost items and apply limited broad effort to the small dollar items as they do not affect the bottom line near as much as the larger items. My experience includes dozens of pump stations and a sufficient number of storage tanks that helps me make good assumptions and estimates of construction of the unique facilities we plan for and engineer. Little that we do is “cookie-cutter” that easily lends itself to using nationally produced cost estimate tables or software that is constantly outdated, costly to purchase and perhaps not specific enough to adequately describe the uniqueness of the facility. For instance, no nationally produced cost table can predict the cost of drilling a well in the Snake Plain Aquifer better than those drillers locally who have done regularly. The specifics of my methodologies are my own and can only be described generally. But experience has refined my process sufficiently to satisfy nearly all client types. My engineering estimates are typically accepted, without undue questioning, by private owners, municipalities, self-governed private water corporations, other branches of Idaho State government (Idaho Department of Commerce, Idaho Division of Public Works, and Idaho Department of Water Resources and DEQ) and agencies of the federal government (US Army Corps of Engineers & USDA-Rural Development). I will now describe, on a per item basis, how my personally developed methodology was applied to these cost estimates being questioned by the IPUC to these future facilities. FWC Well 11 & Pump Station Item 1 - na FLS-W-21-01 IPUC DR 16 Attachment 4 Page 1 of 8 Scott Bruce June 30, 2021 Page 2 Item 2 – Well 11 is now drilled so the cost is the actual cost. Item 3 – Mobilization covers a general contractors management, bonding, mobilization of equipment and demobilization and cleanup at end of project. Five percent of the other items were applied to calculate this. Item 4 – This item was priced with support from a pump supplier and installer then contractor overhead and profit was applied. Item 5 – A generator supplier assisted me with sizing and costing for equipment delivery. I then applied a markup to include installation and troubleshooting. Item 6 – A reasonable unit price was applied to obtain the cost of the structural shell and finishes. Item 7 – Experience and the help of an electrical engineering subconsultant was obtained. Item 8 – Experience based on other new installations was applied. Item 9 – I listed out the piping, valves and misc. sensors and small components in a spreadsheet and applied a cost to each based on phone call with material supplier, summed them, then applied a markup for labor. Item 10 – I obtained equipment suppliers cost for delivery and added a markup for installation. Item 11 – An estimate was used for removal of topsoil, then the pit-run fill amount was calculated at the local cost per unit by consulting with a general contractor. The same method was used for the crushed aggregate material needed for the final grading. Item 12 – A unit price was applied by consulting with a local concrete contractor and examining recent bid results on my own projects. Items 13-15 – A unit price was used that fits the effort to bury these lines and construct the unique facilities associated with each. Item 16 – This is the typical cost to install a tee and valve into an existing mainline. FWC Storage Tank & Booster Pump Station at Well 9 Item 1 - na Item 2 – Mobilization covers a general contractors management, bonding, mobilization of equipment, demobilization and cleanup at end of project. Five percent of the other items were applied to calculate this. Items 3&4 – these were estimated based on other projects where vertical turbine pumps had to be removed from the well, worked on, then reinstalled. The majority of the cost is labor and equipment. Items 5&6 – I listed out the piping, valves and misc. sensors and small components in a spreadsheet and applied a unit cost to each based on a phone call with material supplier, summed them, then applied a markup for labor. Item 7 – We used our knowledge of storage tank costs, consulted a local tank supplier who has recently built similar sized tanks in Eastern Idaho. Item 8 – General knowledge and experience was applied. Item 9 - This item was priced with support from a local pump supplier and installer then contractor overhead and profit was applied based on experience with similar installations. Item 10 – I listed out the piping, valves and misc. sensors and small components in a spreadsheet and applied a cost to each based on phone call with material supplier, summed them, then applied a markup for labor. Item 11 – A reasonable unit price was applied to obtain the cost of the addition to the existing pump station. This is a masonry block building. FLS-W-21-01 IPUC DR 16 Attachment 4 Page 2 of 8 Scott Bruce June 30, 2021 Page 3 Items 12&13 – Experience, the use of past bid results and the help of an electrical engineering subconsultant was obtained. Item 14 – Estimated based on experience. Item 15 – This will be an addition to an existing SCADA link so less hardware will be required. Items 16&17 – An estimate was used for importing and placing pit-run fill amount was calculated at the local cost per unit by consulting with a general contractor. The same method was used for the crushed aggregate material needed for the final grading. Item 18 – A unit price was applied by consulting with a local concrete contractor and examining recent bid results on my own projects. FWC 1,500 gpm Well 11 & Pump Station (Exhibit B in Tank vs Well Memo) Item 1 - na Item 2 – This is the same cost as the actual cost of Well 11. For a 1,500 gpm well within the FWC service area, the casing size will be the same as Well 11 (16” dia) and the drilling depth will be the same due to the nature of the aquifer. All the other drilling steps to complete the well are the same: surface seal, screen (size could vary a little), K-packer, development (could be more on a same size well of lesser production), test pumping (could be incrementally higher for a higher production well), and water quality testing. FWC was fortunate to get 2,500 gpm production rate out of Well 11. But for budgeting and planning, as is the case here, it would not be prudent to plan on that. Item 3 – Mobilization covers a general contractors management, bonding, mobilization of equipment and demobilization and cleanup at end of project. Five percent of the other items were applied to calculate this. Item 4 – This item was priced with support from a pump supplier and installer, then contractor overhead and profit was applied. Support was also obtained by looking at the completion cost of a recent similar well. Item 5 – We examined the cost of a similar sized installation and called a generator supplier for budgetary insight. We then applied a markup to include installation and troubleshooting. Item 6 – A reasonable unit price was applied to obtain the cost of the structural shell and finishes. The size of the building was also adjusted downward (compared to Well 11). Item 7 – Experience and the help of an electrical engineering subconsultant was obtained. Item 8 – Experience based on other new installations was applied. Item 9 – I listed out the piping, valves and misc. sensors and small components in a spreadsheet and applied a cost to each based on phone call with material supplier, summed them, then applied a markup for labor. Item 10 – I obtained equipment suppliers cost for delivery and added a markup for installation. Item 11 –We used the same cost calculated for Well 11 as this well would be placed on a similar site with some fill requirements to finish the well head a few feet higher than surrounding ground. Item 12 – We used the same cost calculated for Well 11 as this well would be placed on a similar site. This is a projected future well on an unknown site so this cost merely acknowledges that some site concrete will be required, but unknown at this point. Item 13- A much lower number compared to Well 11 was used for this cost. We assumed our discharge point was much closer to the pump station than for Well 11. Actual conditions are completely unknown until a site is located. Item 14-16. These are typical costs for pump stations and are small costs relatively. We used the same costs here as in the Well 11 cost estimate. FLS-W-21-01 IPUC DR 16 Attachment 4 Page 3 of 8 FLS-W-21-01 IPUC DR 16 Attachment 4 Page 4 of 8 Item No.Item Unit Quantity Unit Cost Total Cost 1 Land acquisition (contribution in aid of construction)acre 0.55 $0 $0 2 Well drilling lump sum 1 $234,000 $234,000 3 Mobilization for pump station construction lump sum 1 $34,300 $34,300 4 Pump system including VFD, panel, motor, discharge head, column pipe, lineshaft and pump lump sum 1 $244,500 $244,500 5 Backup generator lump sum 1 $114,400 $114,400 6 Pump house structure (incl. interior & exterior finishes)sq, feet 896 $80 $71,680 7 Pump house electrical and mechanical lump sum 1 $60,000 $60,000 8 SCADA link lump sum 1 $12,000 $12,000 9 Pump station piping & valves lump sum 1 $75,600 $75,600 10 Sand separator each 2 $20,000 $40,000 11 Site grading lump sum 1 $18,560 $18,560 12 Concrete approach sq. yards 220 $60 $13,200 13 Pump to waste pipeline linear foot 590 $45 $26,550 14 Waste line to small pit for sand separator lump sum 1 $2,500 $2,500 15 Drain line and small drainfield lump sum 1 $3,500 $3,500 16 Connection to existing system lump sum 1 $3,000 $3,000 Total projected construction cost $953,790 Engineering, legal, & contingency @ 10% of construction $95,380 Total Estimated Project Cost $1,049,170 Estimated Project Cost for Well 11 & Associated Pump Station Falls Water Company Prepared by S&A Engineers, PC 4/26/2021 FLS-W-21-01 IPUC DR 16 Attachment 4 Page 5 of 8 Item No.Item Unit Quantity Unit Cost Total Cost 1 Land acquisition (previously purchased about 2006)acre 2.5 $0 $0 2 Mobilization lump sum 1 $177,800 $177,800 3 Reconfigure pump bowls on Well 9 lump sum 1 $20,000 $20,000 4 Reconfigure pump bowls on Well 5 lump sum 1 $10,000 $10,000 5 Yard piping (connect discharge to existing mainlines, connect wells to tank and connect to pump-to-waste) lump sum 1 $215,500 $215,500 6 Piping and valves to fill tank off the system (for redundancy & emergency utilization)lump sum 1 $10,000 $10,000 7 AWWA prestressed concrete storage tank gallon 2,000,000 1.25 $2,500,000 8 Excavation and backfill for the tank lump sum 1 $10,000 $10,000 9 Booster pump cans, short shaft, column & pump, discharge head, 200 Hp pump, VFD each 3 $129,000 $387,000 10 Pump station piping & valves lump sum 1 $100,050 $100,050 11 Structural Addition to pump station made of masonry block and wood truss roof sq. feet 860 $150 $129,000 12 Electrical and additions & alterations lump sum 1 $90,000 $90,000 13 Mechanical lump sum 1 $5,000 $5,000 14 Connect drain line to existing drainfield lump sum 1 $2,500 $2,500 15 SCADA link alternations and additions lump sum 1 $8,000 $8,000 16 Pitrun for grade raising ton 2,080 $16 $33,280 17 Crushed aggregate beneath concrete approacg and for access to tank and booster pumps ton 550 $24 $13,200 18 Concrete approach sq. yards 370 $60 $22,200 Total projected construction cost $3,733,530 Engineering, legal, & contingency @ 10% of construction $373,350 Total Estimated Project Cost $4,106,880 Falls Water Company Estimated Project Cost for 2.0 MG Storage Tank & Booster Pump Station (Projects B-1, B-2 & B-3 in the 2019 Facility Planning Study) Prepared by S&A Engineers, PC 4/27/2021 FLS-W-21-01 IPUC DR 16 Attachment 4 Page 6 of 8 Item No.Item Unit Quantity Unit Cost Total Cost 1 Mobilization for pump station construction lump sum 1 $15,600 $15,600 2 New pump panel and reinstall VFD lump sum 1 $25,000 $25,000 3 Backup generator lump sum 1 $32,006 $32,006 4 Pump station structure (incl. interior & exterior finishes)lump sum 360 $100 $36,000 5 Pump station electrical and mechanical lump sum 1 $40,000 $40,000 6 Reinstall existing SCADA link lump sum 1 $5,000 $5,000 7 Pump station piping & valves lump sum 1 $30,225 $30,225 8 Site grading lump sum 1 $2,200 $2,200 9 Pit-run gravel beneath concrete and roadbase lump sum 1 $3,670 $3,670 10 Road base beneath concrete and around generator lump sum 1 $2,520 $2,520 11 Drain rock for landscaping lump sum 1 $4,233 $4,233 12 Erosion control fabric beneath drainrock lump sum 1 $1,539 $1,539 13 Retaining wall sq. feet 515 $30 $15,450 14 Concrete approach sq. yard 250 $60 $15,000 15 Storm drain catch basin, piping and French drain lump sum 1 $11,925 $11,925 16 Catch basin, pipline for pump-to-waste and reconnection to existing waste line at golf course property line lump sum 1 $11,225 $11,225 17 Plumbing drain line beneath building to catch basin lump sum 1 $2,000 $2,000 18 Connection to existing pitless unit lump sum 1 $2,000 $2,000 19 Connection to existing system lump sum 1 $3,000 $3,000 20 Seeding lump sum 1 $2,000 $2,000 21 Fencing linear foot 392 $40 $15,680 Total projected construction cost $258,593 Engineering, legal & contingency @ 12% of construction $31,030 Total Estimated Project Cost $289,623 Taylor Mountain Water System, Well 2 Falls Water Company Estimated Project Cost for Pump Station & Site Improvements Prepared by S&A Engineers, PC 4/26/2021 FLS-W-21-01 IPUC DR 16 Attachment 4 Page 7 of 8 Item No.Item Unit Quantity Unit Cost Total Cost 1 Land acquisition (contribution in aid of construction)acre 0.55 $0 $0 2 Well drilling lump sum 1 $234,000 $234,000 3 Mobilization for pump station construction lump sum 1 $25,200 $25,200 4 Pump system including VFD, panel, motor, discharge head, column pipe, lineshaft and pump lump sum 1 $170,000 $170,000 5 Backup generator lump sum 1 $75,000 $75,000 6 Pump house structure (incl. interior & exterior finishes)sq, feet 672 $80 $53,760 7 Pump house electrical and mechanical lump sum 1 $55,000 $55,000 8 SCADA link lump sum 1 $12,000 $12,000 9 Pump station piping & valves lump sum 1 $69,120 $69,120 10 Sand separator each 1 $20,000 $20,000 11 Site grading lump sum 1 $18,560 $18,560 12 Concrete approach sq. yards 220 $60 $13,200 13 Pump to waste pipeline linear foot 200 $38 $7,600 14 Waste line to small pit for sand separator lump sum 1 $2,500 $2,500 15 Drain line and small drainfield lump sum 1 $3,500 $3,500 16 Connection to existing system lump sum 1 $3,000 $3,000 Total projected construction cost $762,440 Engineering, legal, & contingency @ 10% of construction $76,240 Total Estimated Project Cost $838,680 Falls Water Company Estimated Project Cost for 1,500 gpm Well & Associated Pump Station Prepared by S&A Engineers, PC 4/28/2021 FLS-W-21-01 IPUC DR 16 Attachment 4 Page 8 of 8