HomeMy WebLinkAbout20210714FLS to Staff 16.pdf
Rates & Regulatory Affairs
FLS-W-21-01
Falls Water Company Application for Approval of Three Capital Projects
Data Request Response
Request No.: FLS-W-21-01 IPUC DR 16
REQUEST NO. 16: Please provide the detailed source information (vendor bids, cost
estimates, calculations, etc.) associated with each Estimated Cost in Exhibits 2 and 3 of
the Company's Application. Please include within your response the dollar amount for
each activity by vendor, specifically identifying activities performed by the Company and
any affiliated companies or individuals.
Response:
The cost estimates provided in Exhibits 2 and 3 of the Company’s Application are
engineering estimates provided by S&A Engineers. The estimates for the storage tank
and booster pump station and for the Taylor Mountain Well 2 well building from Exhibit 2
are entirely engineering estimates. The Exhibit 3 cost estimates for the storage tank
and booster pump station (repeat of cost estimate shown in Exhibit 2) and the 1,500
gpm well and pump station are also entirely engineering estimates.
The cost estimate for Well 11 and the pump station have some actual cost components.
The drilling of the well began in November 2020. The drilling was completed and test
pumped in April 2021. The test pump revealed that the well capacity is 2,500 gpm.
Copies of the two invoices are included in FLS-W-21-01 IPUC DR 16 Attachment 1
(Exhibit 4). The total cost to drill the well was $234,375.00.
FLS-W-21-01 IPUC DR 16 Attachment 2 (Exhibit 5) are copies of the cost
estimates/invoices from the following vendors:
American Pump for the cost of the pumping equipment and column (excluding
electrical, plumbing, and concrete) for $182,790
Rocky Mountain Valves & Automation, Inc. for part of some of the valves for
the well house piping for $7,240.82
Ferguson Waterworks for pipe and fittings for the flow to waste line and pipe
from well house to existing distribution main and connection fittings to connect
to the existing main for $24,359.02.
Due to the system pressure issues caused by drought and hot temperatures, the
Company’s employees will work on Well 11 and complete items 11, 13-16. They will
also dig the footings for the wellhouse (portion of Item 6) and connect the pipes and
FLS-W-21-01 IPUC DR 16
NWN Response
Page 2 of 2
valves from the wellhead to the distribution main (portion of Item 9). Labor costs
associated with the Company’s employees completing these items and known materials
costs at the time of completing this response are listed below. Please see FLS-W-21-
01 IPUC DR 16 Attachment 3 (Exhibit 6) for Labor cost calculations.
that the Company’s employees will complete. The difference will be bid out to be
The remaining items on Well #11 project’s list will be put out for bid. Currently, the
engineering cost estimate is available for these items. The other projects listed in the
Company’s application Exhibits 2 and 3 have not begun and no bid process has been
done. The engineering cost estimates methodology for the storage tank and booster
pump station project, the Taylor Mountain Well #2 well house project, and the 1,500
gpm well as an alternative to the storage tank and booster pump station are shown in
FLS-W-21-01 IPUC DR 16 Attachment 4 (Exhibit 7) prepared by S&A Engineering.
IPUC DR 16
ATTACHMENT 1
FALLS WATER CO., INC.
Well #11 Drilling and Test Pump Invoices
(2 PAGES)
f-ALLS VvATEh CO.. !IM!^ ,
Due Date /
Account Code i Amount
^ P.O. Box 3810-BuHe.MT 59702
Office: (406) 494-3310 Fax: (406) 494-3301
Email: info@okeefedrilling.com
Client: Falls Water tSmpany
Attention: Tom Wood
Project; Falls Water Company Well 11
Item Number and Description
Unit Price Written In Words
I - MOBILIZATION / DEMOBIUZATION
-20-INCH DRIVE SHOE
; - 20-INCH DRILLING
Quantity
Unit Price
Dollars I Cts
S 14,000.00
1 EACH
$ 475.00 ___
^ LF
S 210.00
FWC21-01
15-Mar-21
208-589-5555
Total Amount
i • 20-INCH TEMPORARY CASING
S 200.00
• 16-INCH DRIVE SHOE
- 16-INCH DRIltiNG
• 16-INCH .375" WALL CASING
- 12-INCH DRILUNGW/CASING
- 12-lNCH .375" WALL CASING ""
- CUT AND PULL 12-INCH CASING & Perforate if needed
- 12-INCH TELESCOPING SS SCREEN
(144' of 10" Casing and 55' of 12-inch SS Screen)
-GROUTING
Cement Hole
-PULL 20-INCH TEMPORARY CASING
-10-INCH HEAD PIPE
$ 375.00
139_
$ 160.00
^
$ 85.00
601 LF
400 IF
, S 63.50
260 LF
S 46.00
^
S 80.00
3_
S 200.00
i_ a_
$ 3,250.00
36 1^
S 40.00
0. L^
S 55.00
l-K-PACKER 16 TO 10-INCH
I - WELL DEVELOPMENT
I-WELL DISINFECTION
I - PUMP TEST MOBIUZATION/DEMOBILIZATION
I-PUMPINGTEST
I - RIG DIRECTED RATE
0 EACH
$ 750.00
8_ HOUR
$ 450.00
IS_
S 4,000.00
S 15,000.00
S 300.00
S 450.00
Total Amount Due:$ 195,275.00
FLS-W-21-01 IPUC DR 16 Attachment 1
Page 1 of 2
FALLS V\^ATER CO., INC.
Inv Date Due Date En-Zl
Invoice # C52^
Account Code $ Amount
Posted by:,
td t<aiu
Client:
Attention:
Posted.
Falls Water Company
Tom Wood
P.O. Box 3810 - Butte, MI 59702
Office: (406) 494-3310 Fax: (406) 494-
Email: info@okeefedrillins.com
Falls Water Company Well 11
Item Number and Description
Unit Price Written in Words
DRItilNG AND TESTING WEU. 11
- MOBILIZATION / DEMOBILIZATION
-20-INCH DRIVE SHOE
- 20-INCH DRILLING
- 2Q-INCH TEMPORARY CASING
-16-INCH DRIVE SHOE
- 16-INCH DRIIUNG
- 16-INCH .375" WALL CASING
- 12-INCH DRILLING W/CASING
- 12-INCH .375" WALL CASING
- CUT AND PULL 12-INCH CASING & Perforate if needed
- 12-INCH TELESCOPING SS SCREEN
(144' of 10" Casing and 55' of 12-inch SS Screen)
-GROUTING
Cement Hole
-PULL 20-INCH TEMPORARY CASING
- 10-INCH HEAD PIPE
•K-PACKER 16 TO 10-INCH
-WELL DEVELOPMENT
- W;LL DISINFECTfON
- PUMP TEST MOBILIZATION/DEMOBILIZATION
-PUMPING TEST
-RIG DIRECTED RATE
Invoice: FWC21-02
Date: 15-Api-21
Phone: 208-589-5555
Quantity Total Amount
Unit Price
Doiiars I c5 Dollars
S 14,000.00
S 47S.00
$ 210.00
$ 200.00
$ 375.00
S 160.00
S 85.00
$ 63.50
S 46.00
S 80.00
^
S 200.00
C^
$ 3,250.00 _____
1^
n S 40.00
; 0_ 1^
j S 55.00
$ 750.00
HOUl
S 450.00
1_ ^
S 4,000.00
1_
S 15,000.00
67_ HR.
S 300.00
S 450.00
Total Amount Due:
FLS-W-21-01 IPUC DR 16 Attachment 1
Page 2 of 2
IPUC DR 16
ATTACHMENT 2
FALLS WATER CO., INC.
Cost Estimates / Invoices
(4 PAGES)
American Pump
PO Box 267
Ucon,ID 83454
(208) 557-8677
info@americanpumpco.com
CUSTOMER
FALLS WATER CO.
2180 N. DEBORAH DRIVE
IDAHO FALLS ID 83401
(208) 522-1300
Estimate
ESTIMATE#
DATE
PC#
56350090
06/17/2021
SERVICE LOCATION
FALLS WATER CO.
2180 N. DEBORAH DRIVE
IDAHO FALLS ID 83401
(208) 522-1300
DESCRIPTION
Estimate
Description Qty Rate Total
SS CONE STRAINER 1.00 600.00 600.00
14RJHC-6 STAGE, WATER LUBE, 12" DISCHARGE, THREADED SUCTION
BS17I
BLANK SHAFTING 17-4 1 15/16 (UPGRADE SHAFT)
LBR14
INSTALL ALUM BRONZE WEAR RINGS ON BOWLS (6 STAGE)
STEEL BACKED RUBBER BUSHINGS
1.00 17,550.00
1.00 2,700.00
1.00 3.150.00
1.00 952.00
17,550.00
2,700.00
3,150.00
952.00
SS BOLTING UPGRADE FOR BOWLS
240' 12" COLUMN ASSEMBLY (12" X 1-15/16" SS SHAFT, W/L RETAINERS)
Install PVC STILLING TUBE
GPHDIX12
GOULDS PUMP HEAD DUCTILE IRON 12" (Including 1-15/16" packing box, head
shaft, head nut, base plate
400 HP VHS Motor
450HP VFD
LOW HARMONIC DRIVE (NO FILTER REQUIRED)
OUT DOOR RATED
TRANSDUCER
LEG KIT
STRIKE SORBS
DISCONNECT
1.00 600.00
1.00 56,000.00
1.00 1,000.00
1.00 8,700.00
1.00 33,908.00
1.00 47,630.00
600.00
56,000.00
1,000.00
8,700.00
33,908.00
47,630.00
EXTEND WELL CASING, INSTALL PUMP 1.00 10,000.00 10,000.00
FLS-W-21-01 IPUC DR 16 Attachment 2
Page 1 of 4
CUSTOMER MESSAGE
ASSUMES COLUMN COMING FROM MANUFACTURE
NEAR FRESNO
DOES NOT INCLUDE ELECTRIAL WORK, PLUMBING, OR
CONCRETE
DOES NOT INCLUDE FREIGHT
VFD WILL NEED A PAD TO STAND ON AND SHOULD
HAVE A SUN SHADE INSTALLED OVER IT TO HELP KEEP
IT COOL
Estimate Total;$182,790.00
PRE-WORK SIGNATURE
Signed By:
FLS-W-21-01 IPUC DR 16 Attachment 2
Page 2 of 4
ROCKV MOUNTAIN
VALVES & AUTOMATION, INC.
Rocky Mountain Valves & Automation, Inc
Salt Lake City, Utah 84104
Order Acknowledgement
Date P.O. No.
6/25/2021 Well #11
Name I Address
Falls Water Company
Tony Wise
2180 N Deborah Or
Idaho Fails, ID 83401
Ship To
Falls Water Company
Tony Wise
2180 N Deborah Dr
Idaho Falls
Rep S.O. No.Terms Est. Ship Date Ship Via FOB Project
ALS 16401 COD 8/13/2021 Included Factory
Item Description Quantity Rate Amount
VM-7212
VM-102SXr
Shipping
12" Val-Matic Surge Buster Check Valve Model 7212,
Ductile Iron Body, 125# FLG Ends, Buiia-N Coated
Disc, Fusion Bonded Epoxy Coated IN70UT, 302 SST
Disc Accelerator
8-10 Weeks ARC
2" Val-Matic Air/Vacuum Valve, Model 102SXF, Cast
Iron Body, 316 SS Trim, Buna-N Seat, N.P.T
Threaded Iniet, Rated 300PS1, Fusion Bonded Epoxy
Lined & Coated
Stock in SLC
Shipping
Sales Tax
5,995.77 5,995.77T
505.00 505.00T
350.00
6.00%
350.00
390.05
Please Contact Rocky Mountain Valve Immediately If There
Are Any Discrepencies. (801)-438-1038 Total $7,240.82
FLS-W-21-01 IPUC DR 16 Attachment 2
Page 3 of 4
^FERGUSON^
WATERWORKS
6715 WEST OVERLAND DRIVE
IDAHO FALLS. ID 83402-5700
TOTAL PJJEhL xVCUSTpMSlV PAGE
0786808 $24,359.02 40882 1 Of 1
PLEASE REFER TO INVOICE NUMBER WHEN
MAKING PAYMENT AND REMIT TO:
Please contact with Questions: 208-528-7490
FERGUSON WATERWORKS #1701
PO BOX 802817
CHICAGO. IL 60680-2817
SHIPTOr
FALLS WATER COMPANY I NO
2180 N DEBORAH DRIVE
IDAHO FALLS. ID 83401
FALLS WATER COMPANY INC
1770SABIN DRIVE
IDAHO FALLS. ID 83406
SHIP
WHSE.
1701
SELL
WHSE.
1701
TAX CODE
IDONLY
CUSTOMER ORDER NUMBER
WELL PIPING
SALESMAN
BDO
JOB NAME INVOICE DATE
08/28/21
BATCH
lO
39644
ORDERED SHIPPED ITEM NUMBERS ,,, > DKCRIFpjDN UNIT PRICE UM AMOUNT
700
80
80
1
3
7
1
1
1
1
10
1
1
1
700
80
80
1
3
7
1
1
1
1
10
1
1
1
DR18BPX
AFT50PX
AFT50P12
MJF9LAX
MJ9LAX
T602210
MJ9LA12
MJF9LA12
MJTLA12
MJLSLA12
T602220
MA236123120L
FNWNBGZ1RR812
FNWNBGZ1RR8X
8 0900 DR18 PVC GJ BLUE PIPE
8 CL50 CL Dl FASTITE PIPE J312CL50CLDIFASTITEPIPE ^
t. t-gtft '38 MJXFLG C153 90 BEND L/A
8 MJ C153 90 BEND L/A - > f2
8 DI/PVC MJ REST TUFGRIP GLND PK
12 MJ 0153 90 BEND L/A "3^
12 MJXFLG 0153 90 BEND L/A
12 MJ 0153 TEE L/A
12X12 MJ 0153 LONG SLV L/A i- «
12 DI/PVO MJ REST TUFGRIP GLND PK I "
12 Dl MJ RW OL GATE VLV L/A >
12 ZN 150# RR RNG 1/8 FLG PKG J *
8ZN150#RRRNG1/8FLGPKG fS
/ Lf
I
14.790
23.970
39.990
331.459
224.328
79.815
478.135
775.801
664.356
364.533
145.858
2134.960
48.357
22.532
FT
FT
FT
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
LEAD LAW
US FEDERAL
PRODUOTS W
NON-POTABLE
O
^
R CAl
NING: IT IS ILLEG
OTHER APPLI
TH -NP IN THE DS
APPLIOATIONS
AL TO INSTALL PRODL
BLELAWIN POTABLE
SORIPTION ARE NOT LI
BUYER IS SOLELY RESFl
INVOICE SUB-TOTAL
TAX
OTS THAT ARE NOT "LEAD FREE" IN ACCORDANCE WITH
WATER SYSTEMS ANTICIPATED FOR HUMAN CONSUMPTION
IAD FREE AND CAN ONLY BE INSTALLED IN
ONSIBLE FOR PRODUCT SELECTION.
Idaho
FALLS o;;. mc.
Date „ Due uato
$ AmountAccount uode
Inv
Invoice #
Poe tsy
D Pttia Posted
Looking for a more convenient way to pay your bill?
Log in to Ferguson.com and request access to Online Bill Pay.
10353.00
1917.60
3199.20
331.46
672.98
558.71
478.14
775.80
664.36
364.53
1458.58
2134.96
48.36
22.53
22980.21
1378.81
TERMS:NET10TH PROX ORIGINAL INVOICE TQTALDUE $24,359.02
All past due amounts are subject to a service charge of 1.5% per month, or the maximum allowed by law, If lower. If Buyer falls to
pay within terms, then In addition to other remedies. Buyer agrees to pay Seller all costs of collection. Including reasonable
attorney fees. Complete terms and conditions are available upon request or at
https://www.ferguson.com/content/webslte-info/terms-of-sale, incorporated by reference. Seller may convert checks to ACH.
FLS-W-21-01 IPUC DR 16 Attachment 2
Page 4 of 4
IPUC DR 16
ATTACHMENT 3
FALLS WATER CO., INC.
Labor Cost Calculations
(16 PAGES)
PROVIDED SEPARATELY AS CONFIDENTIAL
IPUC DR 16
ATTACHMENT 4
FALLS WATER CO., INC.
Engineering Cost Estimates Methodology
(8 PAGES)
June 30, 2021
Scott Bruce
Falls Water Company
2180 N Deborah
Idaho Falls, ID 83401
Re: Methodology to Develop Recent Cost Estimates for Well 11 and Pump Station, Storage
Tank and Booster Pump Station at Well 9 Site, Future 1,500 gpm Well and Pump Station
and Well 2 Site and Pump Station Rehabilitation in the Taylor Mountain Water System
Dear Scott,
Per your request and pursuant to answering questions posed by the IPUC regarding our cost
estimates for the referenced projects, we give our methodology used to develop these cost
estimates. We describe the methodology first philosophically and secondly with details drawn
from the methodology.
Our cost estimating for these facilities is based on communications with pipe and equipment
suppliers, contractors, engineering subconsultants and knowledge and experience gained through
the engineering design process, which for me personally, now spans 29 years. I spend the bulk of
my effort on the high-dollar cost items and apply limited broad effort to the small dollar items as
they do not affect the bottom line near as much as the larger items. My experience includes
dozens of pump stations and a sufficient number of storage tanks that helps me make good
assumptions and estimates of construction of the unique facilities we plan for and engineer. Little
that we do is “cookie-cutter” that easily lends itself to using nationally produced cost estimate
tables or software that is constantly outdated, costly to purchase and perhaps not specific enough
to adequately describe the uniqueness of the facility. For instance, no nationally produced cost
table can predict the cost of drilling a well in the Snake Plain Aquifer better than those drillers
locally who have done regularly.
The specifics of my methodologies are my own and can only be described generally. But
experience has refined my process sufficiently to satisfy nearly all client types. My engineering
estimates are typically accepted, without undue questioning, by private owners, municipalities,
self-governed private water corporations, other branches of Idaho State government (Idaho
Department of Commerce, Idaho Division of Public Works, and Idaho Department of Water
Resources and DEQ) and agencies of the federal government (US Army Corps of Engineers &
USDA-Rural Development).
I will now describe, on a per item basis, how my personally developed methodology was applied
to these cost estimates being questioned by the IPUC to these future facilities.
FWC Well 11 & Pump Station
Item 1 - na
FLS-W-21-01 IPUC DR 16 Attachment 4
Page 1 of 8
Scott Bruce
June 30, 2021
Page 2
Item 2 – Well 11 is now drilled so the cost is the actual cost.
Item 3 – Mobilization covers a general contractors management, bonding, mobilization of
equipment and demobilization and cleanup at end of project. Five percent of the other items were
applied to calculate this.
Item 4 – This item was priced with support from a pump supplier and installer then contractor
overhead and profit was applied.
Item 5 – A generator supplier assisted me with sizing and costing for equipment delivery. I then
applied a markup to include installation and troubleshooting.
Item 6 – A reasonable unit price was applied to obtain the cost of the structural shell and
finishes.
Item 7 – Experience and the help of an electrical engineering subconsultant was obtained.
Item 8 – Experience based on other new installations was applied.
Item 9 – I listed out the piping, valves and misc. sensors and small components in a spreadsheet
and applied a cost to each based on phone call with material supplier, summed them, then
applied a markup for labor.
Item 10 – I obtained equipment suppliers cost for delivery and added a markup for installation.
Item 11 – An estimate was used for removal of topsoil, then the pit-run fill amount was
calculated at the local cost per unit by consulting with a general contractor. The same method
was used for the crushed aggregate material needed for the final grading.
Item 12 – A unit price was applied by consulting with a local concrete contractor and examining
recent bid results on my own projects.
Items 13-15 – A unit price was used that fits the effort to bury these lines and construct the
unique facilities associated with each.
Item 16 – This is the typical cost to install a tee and valve into an existing mainline.
FWC Storage Tank & Booster Pump Station at Well 9
Item 1 - na
Item 2 – Mobilization covers a general contractors management, bonding, mobilization of
equipment, demobilization and cleanup at end of project. Five percent of the other items were
applied to calculate this.
Items 3&4 – these were estimated based on other projects where vertical turbine pumps had to be
removed from the well, worked on, then reinstalled. The majority of the cost is labor and
equipment.
Items 5&6 – I listed out the piping, valves and misc. sensors and small components in a
spreadsheet and applied a unit cost to each based on a phone call with material supplier, summed
them, then applied a markup for labor.
Item 7 – We used our knowledge of storage tank costs, consulted a local tank supplier who has
recently built similar sized tanks in Eastern Idaho.
Item 8 – General knowledge and experience was applied.
Item 9 - This item was priced with support from a local pump supplier and installer then
contractor overhead and profit was applied based on experience with similar installations.
Item 10 – I listed out the piping, valves and misc. sensors and small components in a spreadsheet
and applied a cost to each based on phone call with material supplier, summed them, then
applied a markup for labor.
Item 11 – A reasonable unit price was applied to obtain the cost of the addition to the existing
pump station. This is a masonry block building.
FLS-W-21-01 IPUC DR 16 Attachment 4
Page 2 of 8
Scott Bruce
June 30, 2021
Page 3
Items 12&13 – Experience, the use of past bid results and the help of an electrical engineering
subconsultant was obtained.
Item 14 – Estimated based on experience.
Item 15 – This will be an addition to an existing SCADA link so less hardware will be required.
Items 16&17 – An estimate was used for importing and placing pit-run fill amount was
calculated at the local cost per unit by consulting with a general contractor. The same method
was used for the crushed aggregate material needed for the final grading.
Item 18 – A unit price was applied by consulting with a local concrete contractor and examining
recent bid results on my own projects.
FWC 1,500 gpm Well 11 & Pump Station (Exhibit B in Tank vs Well Memo)
Item 1 - na
Item 2 – This is the same cost as the actual cost of Well 11. For a 1,500 gpm well within the
FWC service area, the casing size will be the same as Well 11 (16” dia) and the drilling depth
will be the same due to the nature of the aquifer. All the other drilling steps to complete the well
are the same: surface seal, screen (size could vary a little), K-packer, development (could be
more on a same size well of lesser production), test pumping (could be incrementally higher for a
higher production well), and water quality testing. FWC was fortunate to get 2,500 gpm
production rate out of Well 11. But for budgeting and planning, as is the case here, it would not
be prudent to plan on that.
Item 3 – Mobilization covers a general contractors management, bonding, mobilization of
equipment and demobilization and cleanup at end of project. Five percent of the other items were
applied to calculate this.
Item 4 – This item was priced with support from a pump supplier and installer, then contractor
overhead and profit was applied. Support was also obtained by looking at the completion cost of
a recent similar well.
Item 5 – We examined the cost of a similar sized installation and called a generator supplier for
budgetary insight. We then applied a markup to include installation and troubleshooting.
Item 6 – A reasonable unit price was applied to obtain the cost of the structural shell and
finishes. The size of the building was also adjusted downward (compared to Well 11).
Item 7 – Experience and the help of an electrical engineering subconsultant was obtained.
Item 8 – Experience based on other new installations was applied.
Item 9 – I listed out the piping, valves and misc. sensors and small components in a spreadsheet
and applied a cost to each based on phone call with material supplier, summed them, then
applied a markup for labor.
Item 10 – I obtained equipment suppliers cost for delivery and added a markup for installation.
Item 11 –We used the same cost calculated for Well 11 as this well would be placed on a similar
site with some fill requirements to finish the well head a few feet higher than surrounding
ground.
Item 12 – We used the same cost calculated for Well 11 as this well would be placed on a similar
site. This is a projected future well on an unknown site so this cost merely acknowledges that
some site concrete will be required, but unknown at this point.
Item 13- A much lower number compared to Well 11 was used for this cost. We assumed our
discharge point was much closer to the pump station than for Well 11. Actual conditions are
completely unknown until a site is located.
Item 14-16. These are typical costs for pump stations and are small costs relatively. We used the
same costs here as in the Well 11 cost estimate.
FLS-W-21-01 IPUC DR 16 Attachment 4
Page 3 of 8
FLS-W-21-01 IPUC DR 16 Attachment 4
Page 4 of 8
Item No.Item Unit Quantity Unit Cost Total Cost
1 Land acquisition (contribution in aid of
construction)acre 0.55 $0 $0
2 Well drilling lump sum 1 $234,000 $234,000
3 Mobilization for pump station construction lump sum 1 $34,300 $34,300
4 Pump system including VFD, panel, motor,
discharge head, column pipe, lineshaft and pump lump sum 1 $244,500 $244,500
5 Backup generator lump sum 1 $114,400 $114,400
6 Pump house structure (incl. interior & exterior
finishes)sq, feet 896 $80 $71,680
7 Pump house electrical and mechanical lump sum 1 $60,000 $60,000
8 SCADA link lump sum 1 $12,000 $12,000
9 Pump station piping & valves lump sum 1 $75,600 $75,600
10 Sand separator each 2 $20,000 $40,000
11 Site grading lump sum 1 $18,560 $18,560
12 Concrete approach sq. yards 220 $60 $13,200
13 Pump to waste pipeline linear foot 590 $45 $26,550
14 Waste line to small pit for sand separator lump sum 1 $2,500 $2,500
15 Drain line and small drainfield lump sum 1 $3,500 $3,500
16 Connection to existing system lump sum 1 $3,000 $3,000
Total projected construction cost $953,790
Engineering, legal, & contingency @ 10% of construction $95,380
Total Estimated Project Cost $1,049,170
Estimated Project Cost for Well 11 & Associated Pump Station
Falls Water Company
Prepared by S&A Engineers, PC 4/26/2021
FLS-W-21-01 IPUC DR 16 Attachment 4
Page 5 of 8
Item No.Item Unit Quantity Unit Cost Total Cost
1 Land acquisition (previously purchased about
2006)acre 2.5 $0 $0
2 Mobilization lump sum 1 $177,800 $177,800
3 Reconfigure pump bowls on Well 9 lump sum 1 $20,000 $20,000
4 Reconfigure pump bowls on Well 5 lump sum 1 $10,000 $10,000
5
Yard piping (connect discharge to existing
mainlines, connect wells to tank and connect
to pump-to-waste)
lump sum 1 $215,500 $215,500
6 Piping and valves to fill tank off the system (for
redundancy & emergency utilization)lump sum 1 $10,000 $10,000
7 AWWA prestressed concrete storage tank gallon 2,000,000 1.25 $2,500,000
8 Excavation and backfill for the tank lump sum 1 $10,000 $10,000
9 Booster pump cans, short shaft, column &
pump, discharge head, 200 Hp pump, VFD each 3 $129,000 $387,000
10 Pump station piping & valves lump sum 1 $100,050 $100,050
11 Structural Addition to pump station made of
masonry block and wood truss roof sq. feet 860 $150 $129,000
12 Electrical and additions & alterations lump sum 1 $90,000 $90,000
13 Mechanical lump sum 1 $5,000 $5,000
14 Connect drain line to existing drainfield lump sum 1 $2,500 $2,500
15 SCADA link alternations and additions lump sum 1 $8,000 $8,000
16 Pitrun for grade raising ton 2,080 $16 $33,280
17
Crushed aggregate beneath concrete
approacg and for access to tank and booster
pumps
ton 550 $24 $13,200
18 Concrete approach sq. yards 370 $60 $22,200
Total projected construction cost $3,733,530
Engineering, legal, & contingency @ 10% of construction $373,350
Total Estimated Project Cost $4,106,880
Falls Water Company
Estimated Project Cost for 2.0 MG Storage Tank & Booster Pump Station
(Projects B-1, B-2 & B-3 in the 2019 Facility Planning Study)
Prepared by S&A Engineers, PC 4/27/2021
FLS-W-21-01 IPUC DR 16 Attachment 4
Page 6 of 8
Item No.Item Unit Quantity Unit Cost Total Cost
1 Mobilization for pump station construction lump sum 1 $15,600 $15,600
2 New pump panel and reinstall VFD lump sum 1 $25,000 $25,000
3 Backup generator lump sum 1 $32,006 $32,006
4 Pump station structure (incl. interior & exterior
finishes)lump sum 360 $100 $36,000
5 Pump station electrical and mechanical lump sum 1 $40,000 $40,000
6 Reinstall existing SCADA link lump sum 1 $5,000 $5,000
7 Pump station piping & valves lump sum 1 $30,225 $30,225
8 Site grading lump sum 1 $2,200 $2,200
9 Pit-run gravel beneath concrete and roadbase lump sum 1 $3,670 $3,670
10 Road base beneath concrete and around
generator lump sum 1 $2,520 $2,520
11 Drain rock for landscaping lump sum 1 $4,233 $4,233
12 Erosion control fabric beneath drainrock lump sum 1 $1,539 $1,539
13 Retaining wall sq. feet 515 $30 $15,450
14 Concrete approach sq. yard 250 $60 $15,000
15 Storm drain catch basin, piping and French drain lump sum 1 $11,925 $11,925
16
Catch basin, pipline for pump-to-waste and
reconnection to existing waste line at golf course
property line
lump sum 1 $11,225 $11,225
17 Plumbing drain line beneath building to catch
basin lump sum 1 $2,000 $2,000
18 Connection to existing pitless unit lump sum 1 $2,000 $2,000
19 Connection to existing system lump sum 1 $3,000 $3,000
20 Seeding lump sum 1 $2,000 $2,000
21 Fencing linear foot 392 $40 $15,680
Total projected construction cost $258,593
Engineering, legal & contingency @ 12% of construction $31,030
Total Estimated Project Cost $289,623
Taylor Mountain Water System, Well 2
Falls Water Company
Estimated Project Cost for Pump Station & Site Improvements
Prepared by S&A Engineers, PC 4/26/2021
FLS-W-21-01 IPUC DR 16 Attachment 4
Page 7 of 8
Item No.Item Unit Quantity Unit Cost Total Cost
1 Land acquisition (contribution in aid of
construction)acre 0.55 $0 $0
2 Well drilling lump sum 1 $234,000 $234,000
3 Mobilization for pump station construction lump sum 1 $25,200 $25,200
4 Pump system including VFD, panel, motor,
discharge head, column pipe, lineshaft and pump lump sum 1 $170,000 $170,000
5 Backup generator lump sum 1 $75,000 $75,000
6 Pump house structure (incl. interior & exterior
finishes)sq, feet 672 $80 $53,760
7 Pump house electrical and mechanical lump sum 1 $55,000 $55,000
8 SCADA link lump sum 1 $12,000 $12,000
9 Pump station piping & valves lump sum 1 $69,120 $69,120
10 Sand separator each 1 $20,000 $20,000
11 Site grading lump sum 1 $18,560 $18,560
12 Concrete approach sq. yards 220 $60 $13,200
13 Pump to waste pipeline linear foot 200 $38 $7,600
14 Waste line to small pit for sand separator lump sum 1 $2,500 $2,500
15 Drain line and small drainfield lump sum 1 $3,500 $3,500
16 Connection to existing system lump sum 1 $3,000 $3,000
Total projected construction cost $762,440
Engineering, legal, & contingency @ 10% of construction $76,240
Total Estimated Project Cost $838,680
Falls Water Company
Estimated Project Cost for 1,500 gpm Well & Associated Pump Station
Prepared by S&A Engineers, PC 4/28/2021
FLS-W-21-01 IPUC DR 16 Attachment 4
Page 8 of 8