HomeMy WebLinkAbout20070205_1830.pdfDECISION MEMORANDUM
TO:COMMISSIONER KJELLANDER
COMMISSIONER SMITH
COMMISSIONER HANSEN
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM:SCOTT WOODBURY
DATE:FEBRUARY 6, 2007
SUBJECT:CASE NOS. IPC-06-34 (Hot Springs) AND IPC-06-35 (Bennett Creek)
FIRM ENERGY SALES AGREEMENTS - IDAHO POWER
On December 26, 2006, Idaho Power Company (Idaho Power; Company) filed
Applications with the Idaho Public Utilities Commission (Commission) requesting approval of
two 20-year Firm Energy Sales Agreements: (1) Idaho Power and Hot Springs Windfarm LLC
(Hot Springs) dated December 20 2006 and (2) Idaho Power and Bennett Creek Windfarm LLC
(Bennett Creek) dated December 20 2006 (collectively Agreements).
Background
On August 4, 2005, the Idaho Public Utilities Commission (Commission) in Case
No. IPC-05-, Order No. 29839, reduced the eligibility cap for avoided cost published rates
for non-firm wind projects from 10 aMW to 100 kW, required individual negotiation for larger
wind qualifying facilities (QFs), and established criteria for assessing QF contract entitlement.
Reference Public Utility Regulatory Policies Act of 1978 (PURPA). By Commission Order No.
29872 the date for grandfathering eligibility was changed from July 1 , 2004, the Notice of
Petition date, to August 4 2005 , the date of Interlocutory Order No. 29839.
In Order No. 29839, the Commission also identified several criteria that it would
consider to determine whether a particular QF wind generation facility, that had been in the
negotiation queue when Order No. 29839 was issued, was sufficiently mature so as to justify
grandfathering" the wind generation facility to entitlement to the published rates. These criteria
are as follows:
(1) Submittal of a signed power purchase agreement to the utility, or
(2) Submittal to the utility of completed Application for Interconnection
Study and payment of fee.
DECISION MEMORANDUM FEBRUARY 6, 2007
In addition to a finding of existence of one or both of the preceding threshold criteria
the QF must also be able to demonstrate other indicia of substantial progress and project
maturity, e.
(1) A wind study demonstrating a viable site for the project
(2) A signed contract for wind turbines
(3) Arranged financing for the project, and/or
(4) Related progress on the facility permitting and licensing path.
(Order No. 29839, p. 10, August 4 2005; final Order No. 29851).
Agreements
The Hot Springs facility will be located within Sections 25 , SE Quarter of 26, 34, 35
and 36, Township 4 S, Range 8 E, and Sections 2 and 3, Township 5 S , Range 8 E, Boise
Meridian, Elmore County, Idaho. The Bennett Creek facility will be located within Sections 22
, 26 (less southeast quarter) and 27, Township 4 S, Range 8 E, Boise Meridian, Elmore
County, Idaho. Hot Springs and Bennett Creek (collectively QFs) warrant the respective
facilities will be qualified small power production facilities (QFs) under the applicable
provisions of the Public Utility Regulatory Policies Act of 1978 (PURP A). The QF facilities will
consist of 12 Vestas wind turbines with individual nameplate ratings of 1.65 MW for each unit
for a total facility nameplate generator rating of 19.8 MW. The Agreements contain the non-
levelized, published avoided cost rates set forth in Order No. 29391. Under normal and/or
average operating conditions, the QFs will not generate more than 10 aMW on a monthly basis.
Energy delivered in excess of this monthly amount is Inadvertent Energy. Idaho Power will
accept Inadvertent Energ~ that does not exceed the Maximum Capacity Amount (20 MW) but
will not purchase or pay for Inadvertent Energy. Agreement ~ 7.
Based on Idaho Power Company s review of the information provided by the
common developer of the two projects, Idaho Windfarms LLC, and in light of the procedure the
Commission accepted in Cassia Wind Order No. 29954, Case No. IPC-05-, Idaho Power has
determined that it would be reasonable to grandfather the Hot Springs and Bennett Creek
facilities based on satisfaction of the following criteria identified by the Commission in Order
No. 29839, Case No. IPC-05-22.
Primary criteria:
Prior to August 5 , 2005 , the developer had tendered signed Firm Energy
Sales Agreements to Idaho Power for the facilities. This satisfies one of the
two primary criteria for grandfathering.
DECISION MEMORANDUM FEBRUARY 6 , 2007
Secondary criteria:
As of August 5 , 2005, the facilities did not have signed contracts for turbines.
Idaho Power has reviewed the information provided by the developer and
determined that this developer believed that obtaining financing was the
highest priority on the critical path to project development and directed its
resources to that goal rather than turbine acquisition. As a result, prior to
August 4, 2005 , the developer had entered into binding commitments to
obtain financing. The Company has also confirmed that as of August 4
2005, the facilities had made substantial progress on the other secondary
criteria, except for acquisition of turbines. As in the case of Cassia Wind, the
developer has now obtained a firm commitment for turbines for the facilities
and filed the necessary applications for interconnection to satisfy the second
primary criteria.
Idaho Power notes that there are three provisions the Commission should be aware of
in its consideration of the Agreements:
1. In the negotiations of these projects, Idaho Power, Bennett Creek and Hot
Springs agreed that an on-line date of December 2007 is crucial to
demonstrate that the projects were viable projects in August of 2005.
This Agreements contain delay damage provisions that require the
projects to pay Idaho Power damages if the projects come on-line after
December 31 , 2007. The delay damages will accrue for a period of up to
90 days.
2. The Agreements contain the methodology for computing shortfall energy
payments the Commission approved in the Firm Energy Sales Agreement
between Idaho Power and Fossil Gulch Wind Park, LLC (Case No. IPC-
04-, Order No. 29630) and recently approved for Magic Wind Park
in Order No. 30206 issued in Case No. IPC-06-26. Hot Springs and
Bennett Creek have voluntarily selected the Fossil Gulch Method. Use
the Fossil Gulch methodology is a negotiated term of the Agreements and
is mutually acceptable to Idaho Power, Bennett Creek and Hot Springs.
3. The Agreements reflect the changes to Idaho Power s Schedule 72
(Uniform Interconnection Agreement) approved in Order No. 30179
issued on November 17, 2006 in Case No. IPC-06-18.
Hot Springs and Bennett Creek have selected March 31, 2007 as the Scheduled First
Energy Date and December 31 , 2007 as the Scheduled Operation Date.
Section 24 of the Agreements provide that the Agreements will not become effective
until the Commission has approved all of the Agreement terms and conditions and declared that
all payments Idaho Power makes to Hot Springs and Bennett Creek for purchases of energy will
be allowed as prudently incurred expenses for ratemaking purposes.
DECISION MEMORANDUM FEBRUARY 6, 2007
On January 4, 2007 , the Commission issued Notices of Application and Modified
Procedure in Case Nos. IPC-06-34 and IPC-O6-35. The deadline for filing comments was
January 26, 2007. Comments were filed by supporters of renewable energy and by the
Commission Staff. Reply comments were filed on February 5, 2007 by Idaho Windfarms LLC
the developer of both Hot Springs and Bennett Creek. Idaho Power filed reply comments on
February 6 2007.
Staff Comments
Grandfathering
Based on Staff s review of the information provided with regard to the primary and
secondary grandfathering criteria, Staff agrees with Idaho Power that the Bennett Creek and Hot
Springs facilities should be grandfathered.
Staff also comments on three provisions of the Agreements that distinguish them
from other recent PURP A agreements.
On-Line Delay Damages
In the contract negotiations for the two projects, Idaho Power and the QFs agreed that
an on-line date of December 2007 is crucial to demonstrate that the projects were viable projects
in August of 2005. The Agreements contains delay damage provisions that require the projects
to pay Idaho Power damages if the projects come on-line after December 31, 2007. The delay
damages will accrue for a period of up to 90 days. Staff supports this contract provision. Staff
notes that at least six recent QF projects have failed to meet their contractual on-line dates;
therefore, Staff believes it is reasonable for Idaho Power to begin inserting damage provisions
into PURP A contracts to provide a mechanism for the Company to be made whole if it incurs
higher costs to acquire replacement power.
Shortfall Energy Payments
The Agreements contain the methodology for computing shortfall energy payments
the Commission approved in the Firm Energy Sales Agreement between Idaho Power and Fossil
Gulch Wind Park, LLC (Case No. IPC-04-, Order No. 29630) and recently approved for
Magic Wind Park in Order No. 30206 issued in Case No. IPC-06-26. Use of the Fossil Gulch
methodology is a negotiated term of the Agreement and is mutually acceptable to Idaho Power
and the QFs. Staff believes that both the Fossil Gulch method and the U.S. Geothermal method
are acceptable alternatives for computing shortfall energy payments and has no objection to
developers choosing their preferred method.
DECISION MEMORANDUM FEBRUARY 6, 2007
Separate Interconnection Agreement
The Agreements reflect the changes to Idaho Power s Schedule 72 approved in Order
No. 30179 issued on November 17 2006 in Case No. IPC-06-18. One of the significant
changes in Schedule 72 was the creation of a standard interconnection agreement (Uniform
Interconnection Agreement) that is separate from the power sales agreement. The Bennett Creek
and Hot Springs projects are the first wherein separate agreements will exist for power sales and
for interconnection. Neither project has yet to sign an interconnection agreement.
In response to production requests, Idaho Power states that it has no reason to believe
that a Uniform Interconnection Agreement will not be signed for the two projects, and further
that if there are no cluster or queue issues that arise requiring additional studies, it is anticipated
that the Uniform Interconnection Agreement could be signed by year end 2007. (December 31
2007 is the Scheduled Operation Date for the projects.
Ideally, Staff states that it would prefer that transmission and interconnection issues
be resolved, and that a signed interconnection agreement be submitted at the same time a power
sales agreement is submitted for Commission approval. Staff recognizes, however, that a QF
may have good reason to pursue each agreement separately, even consecutively. The power
sales agreement and the interconnection agreement for both Hot Springs and Bennett Creek are
on separate tracks and their timing does not coincide. The risk to this approach, however, Staff
contends, must remain with the project developer. In instances where firm transmission may not
be available to accommodate a project without additional investment by the Company or
consideration of non- firm transmission as an alternative, Staff contends that prices in the related
power sales agreement may be affected.
The published avoided cost rates contained in the Agreements, Staff believes, are
based on an assumption that firm transmission would be available to deliver a project's output
without additional Company investment. Consequently, Staff believes that firm transmission
capacity is a prerequisite in order for a project's output to be deliverable on a firm basis. As long
as Bennett Creek and Hot Springs request firm transmission and agree to appropriate terms
subsequently established for making the required transmission upgrades, the two Firm Energy
Sales Agreements, Staff believes, can stand unaffected. However, should either project request
non-firm transmission, Staff submits that the power product that it delivers must also be
considered non-firm. Staff cannot support payment of the full published avoided cost rates
contained in the Agreements unless the projects acquire firm transmission. Conversely, Staff
DECISION MEMORANDUM FEBRUARY 6, 2007
suggests that some downward adjustment to the contract rates could be warranted if non-firm
transmission service is requested. Staff believes that the energy product delivered by Hot
Springs and Bennett Creek and the price ultimately paid for that product is necessarily
determined by both the terms in the power purchase agreement and the interconnection
agreement.
Staff recommends approval of the terms and conditions of the two Agreements.
However, Staff recommends that Commission approval of the Agreements be contingent upon
the QFs requesting firm transmission service and agreeing to participate in funding any
necessary transmission upgrades. Should the QFs request non-firm transmission service and
decline to participate in funding any transmission upgrades, Staff recommends that the
Commission reserve the ability to adjust the rates contained in the Agreements to fairly account
for the reduced firmness of the energy delivered or any additional transmission cost incurred by
Idaho Power.
Reply Comments - Idaho Windfarms LLC
Idaho Windfarms LLC on behalf of its affiliates Bennett Creek and Hot Springs
disagrees with the portions of Staff comments that recommend inclusion of conditions related to
transmission services. While Idaho Windfarms recognizes the implicit linkage between avoided
cost calculations and firm transmission services, it contends that this is not the proper proceeding
to deal with transmission-related issues. Idaho Windfarms' objection is based on the following:
A record for transmission related decisions has not been developed.
A decision on such issues is not currently required.
Adding transmission
grandfathering.
considerations now inconsistent with
Idaho Windfarms states it is aware that most of the PURP A wind projects with
approved power purchase agreements are currently negotiating their interconnection
arrangements. This process, it contends, has been complicated by a lack of existing policies
related to the cost responsibilities associated with system upgrades. The parties face many
complex issues, such as:
The lack of explicit system upgrade costs in the current avoided cost
calculation.
The FERC requirement for reimbursement of system upgrade costs which
produce network benefits.
DECISION MEMORANDUM FEBRUARY 6, 2007
The quantification of network benefits.
The reasonableness of the load and resource scenario used in the N-
study.
The reasonableness of the system upgrade plan.
The appropriateness of various full or partial funding and reimbursement
mechanisms.
The above issues, it states, are presently being addressed through discussions and negotiations
between the parties. Idaho Windfarms contends that Bennett Creek and Hot Springs are not in
the transmission constrained area near Twin Falls. Some of the issues faced by the other projects
will, however, it contends, impact Idaho Windfarms transmission negotiations.Idaho
Windfarms states that there has been no information placed in the record of these two
proceedings which would allow for an informed Commission decision on any of these matters.
Regardless of the manner in which the issues noted above are resolved with regard to
the two projects, Idaho Windfarms contends that they will almost certainly be brought to the
Commission for approval. That, it states, will be the appropriate time to make decisions related
to transmission services and establish the Commission s policies on these matters.
The Hot Springs and Bennett Creek projects, Idaho Windfarms contends, have each
requested firm transmission service. The completed Transmission Feasibility Studies have
preliminarily identified the costs associated with such service. Idaho Windfarms contends that
there is no reason, in the context of this case, to assume the projects and Idaho Power will fail to
achieve an appropriate agreement regarding transmission cost responsibility. Nor, it contends, is
there any reason in this proceeding to predetermine the substance of, or limits on, the
interconnection agreements. Idaho Windfarms believes that transmission service consistent with
Idaho s avoided cost calculation is achievable, but it is too early to determine the form the
interconnection agreements will take. Idaho Windfarms contends that it is unfair to force it to
accept restrictions which have not been applied to the rest of the PURP A proj ects. That, it states
would be unreasonably prejudicial to Idaho Windfarms' upcoming interconnection negotiations.
Idaho Windfarms ' projects, it states, should have the same rights and obligations that are
ultimately applied to the other PURP A projects.
Staff comments, Idaho Windfarms notes, correctly states that the Hot Springs and
Bennett Creek projects are the first to separate transmission service and power purchasing
DECISION MEMORANDUM FEBRUARY 6, 2007
obligations, in compliance with the Commission s Order No. 30179. Those changes, however, it
states, were essentially ministerial and did not address any of the issues related to firm
transmission services and cost responsibility. Those changes, it states, do not provide a basis for
restricting the projects transmission options before the establishment of the Commission
ultimate transmission policies.
Reply Comments - Idaho Power
The avoided costs contained in the Agreements, Idaho Power contends, were
established on the assumption that the costs Idaho Power can avoid by purchasing firm energy
from Bennett Creek and Hot Springs are financially equivalent to the fixed and variable costs of
a firm, dispatchable, combined cycle combustion turbine owned and operated by Idaho Power.
At this time, Idaho Power states it has no reason to believe that the Bennett Creek
and Hot Springs projects will not acquire firm transmission to allow deliveries of firm energy to
Idaho Power. Idaho Power states it does not know what system upgrade costs, if any, the
projects may be asked to pay so that delivery can provide firm transmission and the projects can
deliver firm energy to Idaho Power. Finally, it states there is no indication that the projects
intend to do anything differently than what they have contractually committed to do, that is
deliver firm energy to Idaho Power.
All that being said, Idaho Power states it is in full agreement with Staff s Comments
that the projects are not entitled to be paid the published avoided cost rates contained in the
Agreements unless the projects contract for firm transmission service to be provided for the full
20-year term ofthe Agreements.
Idaho Power recommends that the Commission include findings in its Order
confirming that the published avoided cost rates are only available to QFs that obtain firm
transmission for the full term of the firm energy sales agreements. The Order, it states should
also provide that the requirement to obtain firm transmission would not preclude QFs from
seeking lower cost firm transmission service. Finally, it contends that the Order should provide
that after the projects have entered into transmission arrangements, then Idaho Power or Staff
can ask the Commission to review the transmission arrangements to confirm that the rates
contained in the Agreements are appropriate based on the type of transmission the projects have
acquired.
DECISION MEMORANDUM FEBRUARY 6, 2007
COMMISSION DECISION
Firm Energy Sales Agreements for the Bennett Creek and Hot Springs wind farms
have been presented for Commission approval. Idaho Power contends and Staff agrees that the
projects are entitled to grandfathered treatment and exemption from the Commission s Order
reducing the eligibility cap for avoided costs published rates for non-firm wind projects from 10
aMW to 100 kW. Does the Commission agree that grandfathering is appropriate?
The Agreements contain rates approved by the Commission and specific contract
provlSlons for on-line delay damages and the Fossil Gulch method for computing shortfall
energy payments. Does the Commission find the contract terms and rates to be reasonable?
Neither project has yet to sign an interconnection agreement. Staff contends that the
published firm rates presume that the energy will be delivered on a firm basis. Should firm
transmission capacity not be requested by the QFs, Staff contends that the rates should be
adjusted downward. Idaho Power is in general agreement with Staff and believes that the Order
should not be silent on this issue. Idaho Windfarms contends that the two projects have each
requested firm transmission service, and that there is no reason, in the context of this case, to
assume that the projects and Idaho Power will fail to achieve an appropriate agreement regarding
transmission cost responsibility. Idaho Windfarms contends further that the developed record in
these cases provides no basis for establishing conditions to its generation agreements related to
transmission services. Does the Commission find it reasonable to approve the Bennett Creek and
Hot Springs Agreements? With or without conditions related to transmission service?
Scott Woodbury
blslM:IPC-O6-34 IPC-O6-35 sw
DECISION MEMORANDUM FEBRUARY 6, 2007