HomeMy WebLinkAbout20051205_1410.pdfDECISION MEMORANDUM
TO:CO MMISSI 0 NER KJELLAND ER
COMMISSIONER SMITH
COMMISSIONER HANSEN
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM:CECELIA A. GASSNER
DATE:NOVEMBER 30, 2005
SUBJECT:IDAHO POWER'S APPLICATION FOR APPROVAL OF A FIRM
ENERGY SALES AGREEMENT, CASE NO. IPC-05-
On October 19, 2005 , Idaho Power Company (Idaho Power) filed its Application for
approval of a 20-year Firm Energy Sales Agreement (Agreement) for the sale and purchase of
electric energy with G2 Energy Hidden Hollow, LLC, a Georgia limited liability company (G2).
Under the Agreement, G2 will sell and Idaho Power will purchase electric energy generated by
the Hidden Hollow Landfill Gas Project located at Ada County s Hidden Hollow Landfill near
Boise (the Project). The nameplate rating of the Project is 3.2 MW.
THE APPLICATION
On November 8 , 2005, the Commission issued a Notice of Modified Procedure
seeking comments on the Application on or before November 29 , 2005. The Commission
received two public comments and comments from the Staff.
The Project will be a qualified small power production facility (QF) under the
applicable provisions of the Public Utilities Regulatory Policy Act of 1978 (PURP A). G2 has
selected March 1 , 2006 as the scheduled operation date for the Project.
As represented by Idaho Power, the Agreement with G2 comports with the terms and
conditions of Commission Order No. 29632 (Us. Geothermal et al. v. Idaho Power) and
avoided cost Order No. 29646. G2 has elected to receive the non-Ievelized published avoided
cost rates set forth in Order No. 29646, as set forth in further detail in Section VI of the
Agreement.
DECISION MEMORANDUM
According to the Application, Idaho Power and G2 entered into the Agreement on or
about October 2005 pursuant to the rates, terms and conditions specified in Commission
Order Nos. 29632 and 29646. Section 24 of the Agreement provides that "the Agreement shall
not become effective until the Commission approves all terms and provisions thereof without
change or condition and declares that all payments to be made hereunder shall be allowed as
prudently incurred expenses for ratemaking purposes." The proposed effective date is October
2005.
COMMENTS
Two comments from the public were submitted in this matter. On November 23
2005, Mr. Bob Harder of Meridian submitted a comment regarding the availability of certain
equipment that may be relevant to the generation of electricity from landfill gases. On
November 29, 2005 , Ms. Vera Noyce of Boise submitted a comment in support of the
Application.
Staff reviewed the Agreement and believes that it comports with the rates, terms and
conditions of Commission Order No. 29632 (Us. Geothermal, et at. v. Idaho Power) and
avoided cost Order No. 29646. Because the Project will utilize landfill gas as its fuel source, the
Commission s recent Order (Order No. 29839) temporarily restricting entitlement for wind
projects does not apply.
To Staffs knowledge, the Project will be the first electrical generation facility in the
State to use landfill gas as its source. Staff is uncertain as to whether the fuel supply will
diminish over time and whether the Project can continue to produce its rated output over the 20-
year life of the Agreement. Staff is also uncertain as to whether the facility s equipment will
endure over the full term of the Agreement. Nevertheless, because this is a non-Ievelized
Agreement, there will be no overpayment liability and thus no risk to Idaho Power or its
ratepayers if the Agreement is terminated early.
Section 24 of the Agreement provides that the Agreement will not become effective
until the Commission has approved all the Agreement's terms and conditions and declared that
all payments that Idaho Power makes to G2 for purchases of energy will be allowed as prudently
incurred expenses for ratemaking purposes. The proposed effective date of the Agreement is
October 2005.
DECISION MEMORANDUM
Staff recommends approval of this Agreement with an effective date of October
2005.
COMMISSION DECISION
Does the Commission wish to approve this Agreement with an effective date of
October 11 20057
Cecelia A. assner
M:IPC-O5-29 _cg2
DECISION MEMORANDUM