HomeMy WebLinkAbout20230525AVU to IFG 75 Attachment C.pdfAcvity ID Acvity Name Orig Dur Rem Dur % Comp Contract Start Date Contract Start Date Start Finish Responsibility Comments Southeast 115kV Substation Phase 2 - Replace Switches (78)Southeast 115kV Substation Phase 2 - Replace Switches (78)353 257 27.2%15-Feb-21 23-Mar-22 15-Feb-21 A 06-Jul-22 PLANNING & DESIGN PHASEPLANNING & DESIGN PHASE 210 114 15-Feb-21 25-Aug-21 15-Feb-21 A 10-Dec-21 Physical DesignPhysical Design 113 17 15-Feb-21 24-Jun-21 15-Feb-21 A 23-Jul-21 SE03-2020 Prepare Physical Design 113 17 84.96%15-Feb-21 24-Jun-21 15-Feb-21 A 23-Jul-21 Sub.Sub Engr.Physical Calendar adjusted 23rd Electrical DesignElectrical Design 146 51 16-Feb-21 25-Aug-21 16-Feb-21 A 10-Sep-21 SE03-2095 Plan Outages 78 0 100%16-Feb-21 15-Jun-21 16-Feb-21 A 06-Jun-21 A Sub.Sub Engr.Site Civil Ok SE03-2080 Complete Dra.ing 84 35 58.33%18-Mar-21 15-Jul-21 18-Mar-21 A 18-Aug-21 Sub.Dra.ing Ok SE03-2055 Review 30% Electrical Design 5 2 60%27-Apr-21 03-May-21 27-Apr-21 A 01-Jul-21 Sub.Sub Engr.Elect Data Date Pushes out to July 1 Finish SE03-2060 Prepare 60% Electrical Design 26 20 23.08%21-May-21 28-Jun-21 21-May-21 A 28-Jul-21 Sub.Contract.B&V Pushed out 1 month to July 28 SE03-2065 Review 60% Electrical Design 10 10 0%22-Jun-21 06-Jul-21 28-Jun-21 A 14-Jul-21 Sub.Sub Engr.Elect Pushed out 8 days by SE03-2060 SE03-2070 Prepare 90% Electrical Design 13 13 0%07-Jul-21 30-Jul-21 29-Jul-21 16-Aug-21 Sub.Contract.B&V Pushed out by 2060 and 2065 SE03-2075 Complete Electrical Design - Issue for Construc6on (IFC) 8 8 0%02-Aug-21 11-Aug-21 17-Aug-21 26-Aug-21 Sub.Contract.B&V SE03-2085 Perform Peer Review with Project Team 5 5 0%13-Aug-21 19-Aug-21 27-Aug-21 02-Sep-21 Sub.Sub Engr.Site Civil SE03-2090 Transmit Design 10 10 0%12-Aug-21 25-Aug-21 27-Aug-21 10-Sep-21 Sub.Sub Engr.Site Civil Protection and Integration DesignProtection and Integration Design 81 81 0%02-Aug-21 13-Aug-21 17-Aug-21 10-Dec-21 SE03-2200 Prepare Protec6on Se:ngs 81 81 0%02-Aug-21 13-Aug-21 17-Aug-21 10-Dec-21*Sub.Prot.R Roman SE03-2220 Protec6on Se:ngs Deployed 0 0 0%13-Aug-21 10-Dec-21 Sub.Prot.UA PDF shows June 1 Transmission DesignTransmission Design 93 18 15-Feb-21 24-Jun-21 15-Feb-21 A 26-Jul-21 SE03-2270 Perpare Transmission Design 93 18 80.65%15-Feb-21 24-Jun-21 15-Feb-21 A 26-Jul-21 Sub.Trans.Design Pushed out Design CompleteDesign Complete 0 0 0%25-Aug-21 25-Aug-21 10-Dec-21 10-Dec-21 SE03-2300 Design Complete - Project Execu6on Plan Approved (PG-2) 0 0 0%25-Aug-21 10-Dec-21 Sub.Proj.Lead EXECUTION PHASEEXECUTION PHASE 84 84 0%18-Nov-21 23-Mar-22 09-Mar-22 06-Jul-22 Management During ConstructionManagement During Construction 2 2 0%18-Nov-21 19-Nov-21 09-Mar-22 10-Mar-22 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Protec6on Se:ngs Deployed Project Lead - Aaron Henson PL-309 - Aaron Henson - SU TASK filter: PL -309 - Aaron Henson. Remaining Level of Effort Actual Level of Effort Remaining Work Actual Work Planned Outage Bar Scheduled Outage Bar Unassigned Milestone Completed Milestone Cri6cal Milestone Baseline Bar Baseline Milestone SUBSTATION MASTER SCHEDULE POTENTIAL NON PUBLIC TRANSMISSION FUNCTION INFORMATION. DO NOT DISCLOSE TO MARKETING FUNCTION EMPLOYEES OF AVISTA CORPORATION - FERC Standards of Conduct 18 CFR 358 Data Date 30-Jun-21 Print Date 13-Jul-21 Page 1 of 2 IFG_PR_075 Attachment C Page 1 of 2 Acvity ID Acvity Name Orig Dur Rem Dur % Comp Contract Start Date Contract Start Date Start Finish Responsibility Comments SE03-3020 Hold Pre-Construc6on Mee6ng 2 2 0%18-Nov-21 19-Nov-21 09-Mar-22 10-Mar-22 Sub.Proj.Lead OutagesOutages 56 56 0%06-Dec-21 25-Feb-22 23-Mar-22 09-Jun-22 SE03-3100 Hold Planned Outage # 1 - SUN-A311 5 5 0%06-Dec-21 10-Dec-21 23-Mar-22 29-Mar-22 Sub.SysOps.Outage SE03-3110 Hold Planned Outage # 2 - A312-A452 3 3 0%13-Dec-21 15-Dec-21 30-Mar-22 01-Apr-22 Sub.SysOps.Outage SE03-3120 Hold Planned Outage # 3 - SUN - A311 2 2 0%17-Feb-22 18-Feb-22 01-Jun-22 02-Jun-22 Sub.SysOps.Outage SE03-3130 Hold Planned Outage # 4 - A800-A425 1 1 0%25-Feb-22 25-Feb-22 09-Jun-22 09-Jun-22 Sub.SysOps.Outage Electrical WorkElectrical Work 28 28 0%14-Feb-22 23-Mar-22 26-May-22 06-Jul-22 SE03-3200 Install Mobile 5 5 0%14-Feb-22 18-Feb-22 26-May-22 02-Jun-22 Sub.Elect.Weil Crew SE03-3210 Install Switches and Circuit Switcher 15 15 0%03-Mar-22 23-Mar-22 15-Jun-22 06-Jul-22 Sub.Elect.Weil Crew Distribution WorkDistribution Work 2 2 0%22-Feb-22 23-Feb-22 06-Jun-22 07-Jun-22 SE03-3300 Complete Dx Switching 2 2 0%22-Feb-22 23-Feb-22 06-Jun-22 07-Jun-22 Sub.Distrib.Feild Transmission WorkTransmission Work 69 69 0%18-Nov-21 02-Mar-22 09-Mar-22 14-Jun-22 SE03-3440 Pre-Outage Line Work 10 10 0%18-Nov-21 03-Dec-21 09-Mar-22 22-Mar-22 Sub.Transmis.Constr SE03-3400 Unassigned 15 15 0%13-Dec-21 04-Jan-22 30-Mar-22*19-Apr-22 Sub.Mech.UA SE03-3410 Install Moble Structure 3 3 0%03-Feb-22 05-Feb-22 19-May-22 21-May-22 Sub.Transmis.Constr SE03-3450 Remove Strain Bus 3 3 0%28-Feb-22 02-Mar-22 10-Jun-22 14-Jun-22 Sub.Transmis.Constr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Project Lead - Aaron Henson PL-309 - Aaron Henson - SU TASK filter: PL -309 - Aaron Henson. Remaining Level of Effort Actual Level of Effort Remaining Work Actual Work Planned Outage Bar Scheduled Outage Bar Unassigned Milestone Completed Milestone Cri6cal Milestone Baseline Bar Baseline Milestone SUBSTATION MASTER SCHEDULE   POTENTIAL NON PUBLIC TRANSMISSION FUNCTION INFORMATION. DO NOT DISCLOSE TO MARKETING FUNCTION EMPLOYEES OF AVISTA CORPORATION - FERC Standards of Conduct 18 CFR 358 Data Date 30-Jun-21 Print Date 13-Jul-21 Page 2 of 2 IFG_PR_075 Attachment C Page 2 of 2