HomeMy WebLinkAbout20210415Avista to Staff 101.pdfProject Initiation Charter
Little Falls Unit 4 Upgrade - Charter Page 1 of 4
Project Name: Little Falls Unit 4 Upgrade Project
Program ID: ER-4152
Project ID: 20205045
1 Key Roles
• Steering Committee:
o Jacob Reidt - Project Delivery & Engineering Manager
o Alexis Alexander – Maintenance, Management & Construction Manager
o Bob Weisbeck - Hydro Operations and Maintenance Manager
• Project Sponsor: Andy Vickers – GPSS Director
• Program & Project Manager: Crystal Lewis
• Team Stakeholders:
o Engineering Managers: PJ Henscheid (Mechanical/Civil), Kristina Newhouse (Controls), Glen
Farmer (Electrical)
o Operations: Ryan Bean (Spokane River Mgr), Kevin Powell (Chief Operator)
o AVA Construction: Randy Pierce (Mechanic Shop GF), Brad McNamara (Electric Shop GF), Jeff
Vogel (Relay Shop GF)
o EAM/Maximo: Jennifer Lund (EAM Manager)
o SCADA Engineering: Brad Calbick
o Protection Engineering: Randy Spacek, Calvin Howard, Beth Andrews
o Environmental: Robin Bekkedahl (SHPO, Historic Building Specialist)
o Network: Mike Lang (ET Project Manager)
o Contracts: Karen Carter (Contracts Mgr, Services), Shelly Campbell (Contracts Mgr, Procurement)
2 Statement of Mission Need
2.1 Business Need/Project Objectives
Little Falls Unit 4 Upgrade Overview
The Little Falls Modernization Program (LFMP) will replace equipment at the end of useful life associated with
the generating units. This program is set up to first replace the equipment responsible for the majority of the
outages, followed by preparing the plant for the large generation unit upgrades, and concluding by doing yearly
projects structured to replace the majority of the generator’s components.
The Little Falls Unit 4 (U4) project’s scope is to modernize the unit. The major components that are in need of
substantial overhaul or complete replacement include the generator (windings, core and frame), governor, exciter,
field poles, bearings, generator cables, turbine assembly, wicket gates, bushing assemblies, control system,
protection system, bearing lube oil and cooling systems, AC station service upgrades from stepdown transformer
to motor control centers and feeder buckets. Additionally, upgrades as part of the final plant upgrade and cleanup
of other ancillary systems includes GSU Bus 2 protection, SCADA controls, removal of the old 240VDC system, and
removal of the Bailey cabinet to provide minimum clearance from 480V panel and relocation of its remaining
components.
Avista crews will be used for the majority of the work. The majority of the mechanical and electrical portions of
the unit will remain the same and Avista’s crews have the knowledge and experience on these types of units.
During the construction of the first unit (U3), crew time was spent fabricating tooling and stands that will be
used for the other unit upgrades. This contributed to a longer schedule on U3 than the other units that followed.
Unit 4 will be the fourth and final unit upgraded at Little Falls; using the tools and techniques from the previous
upgrades to help provide for a more efficient and effective project. We will use the previous unit and systems
upgrade actuals for project schedule and costs, lessons learned, and involve the craft workers to more
accurately estimate the time and resources required for each individual Work Breakdown Structure (WBS)
activity based upon their prior unit upgrade experience. This historical information along with group discussions
and input will aid in refining the overall Unit 4 project schedule and cost estimates.
Project Initiation Charter
Little Falls Unit 4 Upgrade - Charter Page 2 of 4
LFU4 Objectives:
Primary LFU4 objectives include:
• Upgrade or replace U4 equipment and remaining ancillary systems that are at end of useful life to reduce
equipment failure, forced outages and loss of generation.
Secondary LFU4 objectives include:
• Continued development of a robust schedule and WBS that can be used for performance reporting.
2.2 Regulatory Drivers
Little Falls HED is listed on the National Register of Historic Places as having significance to the history of their
community state or the nation. Upgrades should be documented and conducted in such a manner as to
preserve the historic feel of the plant.
2.3 Metrics Demonstrating Need
Little Falls Unit 4 is the last of four units scheduled to be upgraded as part of the LFMP. It is the only unit still
connected to and using the old control systems, protection systems, and bailey cabinet. Its physical components,
equipment, and systems are beyond their useful life and are to be upgraded or replaced as part of this work.
2.4 Measures to Determine Project Success
Primary objectives will be met when plant operation and reliability metrics for the plant are improved then
maintained over time, and project completion is on time and within budget to the approved performance
baseline while maintaining compliance with all environmental requirements. Units 1, 2 and 3 have all been
upgraded, are performing as designed with little or no issues to date.
If the secondary objectives are met, it will improve accuracy of cost and schedule estimation, which in turn
improves resource planning for engineering, functional area support, and crafts.
2.5 Impact if Not Approved
Evaluation of expected lifecycle of the plant indicates continuing with the current maintenance and inspection
program combined with major equipment replacements should be planned by 2020 to avoid generator failure.
• Unit 4 is beyond its useful life and is the last of four units to be upgraded under the program.
• Unit 4 is still tied into the old controls and protection system, which have been upgraded for all previous
units.
• Personnel safety is at increased risk for unit failure if not undertaken.
• A savings in Operations and Maintenance (O&M) costs is anticipated with the upgrade of the units as
they will have new equipment and components, also under warranty.
2.6 What will NOT be delivered?
• Out of Scope: Spillway system, Headgate system, Substation work, Repairs to the powerhouse
3 Assumptions, Risks, and Considerations
3.1 Assumptions: (Expected Conditions)
• Little Falls HED is excluded from the Federal Energy Regulatory Commission (FERC) Spokane River
Project licensing.
• Infrastructure requirements at the site were completed prior to undertaking the first of the unit
overhauls preparing the necessary stands, spreader beams and tools to perform the work.
Project Initiation Charter
Little Falls Unit 4 Upgrade - Charter Page 3 of 4
• Duplication drawings from the completed Unit 2 will be generated by Cirrus Design (Consultant) to
provide updated drawings for Unit 4 providing more accurate and up to date details than existing
historical information.
• An approach of buying new parts vs. rehabilitation of old parts will be used since expected conditions
based on the age and complexity of the units cannot be effectively predicted.
• Avista crews will be used to perform the unit overhauls and other significant work.
• Unit 4 Construction will be completed in 2019.
• A steering committee has been established for management check in’s and approval of decision gates
throughout the project lifecycle. These decision gates are approving the Mission Need (Business Case),
approval of Alternative Analysis, and approval of the Project Execution Plan.
3.2 Risks: (Potential Deviations)
• Equipment in the field does not match original equipment manufacturer drawings
• Design and operation standards for department are not well established
• Drawings are inaccurate and/or institutional knowledge is not well aggregated and documented that
resolves differences in existing drawings. Existing and future conditions of Unit 4 may not match
duplicated drawings from Unit 2 requiring revisions.
• Equipment is not delivered on time or is delivered with non-conformance to plans and specifications.
• Avista crews are called off the project to attend to an unplanned, or emergency need
• Unexpected conditions may become evident as the unit is disassembled and assembled requiring
unplanned fabrication, machining, or repair.
3.3 Considerations
Project Team Stakeholders input will be sought at a minimum to (1) identify resources upon approval of the
Charter, (2) ensure functional requirements and scope are comprehensively defined by the project team at the
onset of the project, (3) ensure adequate criteria and options are evaluated prior to selection of alternatives
based on the complexity of the project, and (4) review the final design documents to ensure requirements were
successfully met. This will allow for transfer of institutional knowledge within Avista to the project team.
4 Resource Requirements
4.1 Applicable Interfaces
Stakeholder interfaces requiring assigned resources in order to achieve the project objectives are as follows
(check all that apply). The specific roles and responsibilities, frequency/ type of communication, and agreed
upon engagement points will be documented in a Communication Plan as part of the Project Execution Plan.
Primary Project Team:
Avista Engineering: Amber Fowler (Electrical), Jeremy Winkle (Controls), Jeremy Fauth (Controls), Nick
Agostinelli (Mechanical)
Avista Construction Foreman: Chuck Parker (Mechanical), Howard Johnson (Electrical), Tom Berg (Relay)
Secondary Stakeholders:
☒ Electrical Engineering
☒ Controls Engineering
☒ Mechanical Engineering
☐ Civil Engineering
☒ Drafting & Survey
☒ Substation Engineering
☐ Distribution Engineering
☐ Transmission Engineering
☐ Operations Engineering
☒ Operations (Electric/Gas/Hydro)
☐ Gas Engineering
☒ Protection Engineering
☒ SCADA Engineering
☐ Facilities
Project Initiation Charter
Little Falls Unit 4 Upgrade - Charter Page 4 of 4
☒ Asset Management
☒ MM&C/Maximo Planner
☒ Master Scheduler
☒ Maintenance Engineers
☒ Crews
☒ Environmental
☒ Cultural/SHPO Resources
☐ Hydro/FERC Licensing
☒ Network Communication (IT/ET)
☒ Supply Chain – Contracts (Bid)
☒ Supply Chain – Materials/Equipment
☐ Real Estate
☒ Legal
☐ Corporate Communications
☐ Corporate Marketing
☐ Fleet
☒ Rates and Regulatory
☒ Project Accounting
☒ Power Schedulers
External:
• Cirrus Design (Design and Drafting)
• Supplier/Vendor:
Alstom (Generator) L&S (Governor)
GE (Field Poles) Hudson Bay (Ducting/Insulation)
Wagstaff (Wicket Gates & Distributor Disks) HydroTech (Bearings)
Voith (Shaft & Runners)
Others: AllWest, Concrete Cutters, Jetco, Northwest Sandblast & Paint, HydraFab, Rhodes, K&N,
CIP, S&S NDT
4.2 High Level Program Deliverables & Milestones
The following is a preliminary project list and tentative construction window for the LFMP:
Unit 1 Overhaul Complete – April 2017
Unit 2 Overhaul Complete – June 2018
Unit 4 Overhaul Sept 2018 – Aug 2019
Design Drawings April 2018 – transmittal Sept 2018
Disassembly Begins Sept 2018
Fabrication/Machining Begins Dec 2018
Assembly/Install Begins Feb 2019
Checkout/Commissioning Begins Aug 2019
Project Closeout/Lessons Learned/Archiving Sept 2019 – Sept 2020
4.3 Planning Cost Estimate
The Little Falls U4 expected transfer to plant is estimated to be $7.8MM in August 2019.
5 Approval Signatures
_________________________________________________________ _____________
Jacob Reidt, Project Delivery & Engineering Manager Date
_________________________________________________________ _____________
Alexis Alexander, Maintenance, Management & Construction Manager Date
_________________________________________________________ _____________
Bob Weisbeck, Hydro Operations and Maintenance Manager Date
Project Execution Plan Project Name: Little Falls HED Unit 4 Upgrade
Accounting Project ID: CPR#: 20205045
Business Case Name: Little Falls Powerhouse Modernization
ER/BI: 4152/DG100
Jason Thackston
Andy Vickers
Jacob Reidt
$8,200,000
Generation Production
& Substation Support
Andy Vickers
Crystal Lewis
Jacob Reidt, Bob Weisbeck, Alexis Alexander
K. Newhouse J. Winkle H. Johnson
G. Farmer N. Agostinelli C. Parker
P. Hensheid A. Fowler T. Berg
B. McNamara J. Fauth
R. Pierce
J. Vogel
R. Bean K. Powell Power Supply
System Operations
Project Description:
Modernize the Unit 4 generator through replacement of the generator, field poles, governor and
control system, turbine assembly, perform rehabilitation and fabrication of miscellaneous parts,
complete GSU 2 protection upgrade, SCADA PLC modifications, and Bailey cabinet and component
removal.
Project Execution Plan Checklist:
Change Management Plan Component of Project Execution Plan (PEP)
Project Name: Little Falls HED Unit 4 Upgrade
Project ID: CPR#: 20205045
The purpose of the Change Management Plan is to document the process of how project
change requests will be monitored and controlled, implemented or denied.
1. Identify Benefits, Impacts & Alternatives
a. The Project Team monitors and controls changes within a project;
b. Project Team members identify the need for a change request;
c. Project Team members evaluate the impacts to the project scope, schedule, budget and risks;
d. Project Manager initiates a Change Request form.
i. Change Request Form - documents the request and research necessary to fully
understand and evaluate the request.
Avoid over analysis, you may not need to complete the change request form for all changes, but you should
at least record the change in the Change Register.
2. Review & Evaluate
a. Project Manager evaluates and assesses the Change Request and builds consensus across the
team.
It may not be practical to bring every small change to the Project Sponsor and/or Steering Committee for
approval. However, the cumulative impacts of small changes can have a major impact on the project
schedule and budget. Collect small changes together, evaluate their impacts and benefits and present a set
of them to the Project Sponsor and/or Steering Committee for approval.
3. Obtain Project Sponsor Approval
a. Project Manager routes the Change Request through to the Project Sponsor and/or Steering
Committee for approval;
b. If Approved;
4. Update Project Execution Plan & Implement Change
a. Document changes to the Baseline - Change Register provides a historical record of the change
and its impact on the project;
b. Coordinate changes with the Project Team;
c. Update the Risk Plan;
d. Update the Scope, Schedule and Cost Plans
Role Responsibilities
*Evaluates the need for change against scope, schedule and cost baselines
*Forwards change requests for review/approval
Members/
Stakeholders
*Creates change requests
*Helps evaluate risk and impact analysis of change requests
Communication Management Plan Component of Project Execution Plan (PEP)
Project Name: Little Falls HED Unit 4 Upgrade
Project ID: CPR#: 20205045
The purpose of the Communication Management Plan is to define the communication requirements
for the project and how information will be distributed to keep all stakeholders informed on progress
and key issues.
Kick-off Meeting Introduce project,
team roles &
responsibilities,
review project
objectives &
Steer Co.
Project Team
Manager
Minutes
Action Items
Meetings project, discuss and
develop solutions for
project issues
and/or
Conference
Call
during
Execution
or, as
needed
during
Manager
Minutes
Action Items
Reports project; major
milestones, progress,
costs & risks
Steer Co.
Project Team
Manager Status
Report
Updates
(if applicable)
Spend, release or
request funds
Planning Group Project
Manager
expected
spend
Updates Plant and/or other
miscellaneous
Asset
Accounting
Manager Schedule
updates
Stakeholder
Check-In’s
issues, seek
resolution and/or
direction
Needed Manager
Minutes
Requests and impacts of
formal Change
Requests
Needed Steer Co. Manager Change
Request
approved or
Coordination of the project to Managers, Manager project
Cost Baseline & Cost Management Plan Component of Project Execution Plan (PEP)
Project Name: Little Falls HED Unit 4 Upgrade
Project ID: CPR#: 20205045
The purpose of the Cost Baseline is to define the current estimated cost of the project and the
current approved version of the budget (from the Business Case).
The purpose of the Cost Management Plan is to define how the costs on the project will be managed
throughout the project’s lifecycle. It sets the format and standards by which the project costs are
measured, reported & controlled.
Total Project Costs $ 8,200,000
Approved Amount (CPR) 2/19/16 $8,456,000
Anticipated Transfer to Plant (TTP)
“In-Service” Date
August 2019
Deliverable Objective Frequency Audience Responsible
Reports expected spend,
identify budget
status
Steer Co.
Project Team
Manager
Updates spend, release or Group (CPG) Manager
other misc. (as needed) Asset Manager
Reporting cost performance CPG Manager
Reconciliation to contract Approvers
Manager
Request baseline Steer Co.
Project Team
Stakeholders
Manager
Procurement Management Plan Component of Project Execution Plan (PEP)
Project Name: Little Falls HED Unit 4 Upgrade
Project ID: CPR#: 20205045
The purpose of the Procurement Management Plan is to describe how goods and services
will be acquired from outside of the organization. The following Vendors/Suppliers/Service
Providers are to be used as part of the Unit 4 upgrade and many have been previously
procured/RFP’d/selected for work on Units 1, 2, & 3.
Item/Service Justification Process/Needed
By
Type of
Contract
Decision
Criteria
Rough Cost
Estimate
Owner
services
(Cirrus)
design support
during project
January, 2017
work already
done by
Manager
(GE) Equipment in 2014 for all 4 Price previous RFP Manager
(HydroTech) Equipment in 2014 for all 4 Price previous RFP Manager
(Alstom) Equipment in 2013 for all 4 Price Evaluation U4 Manager
(L&S) Equipment in 2014 for all 4 Price Evaluation Manager
Runners/Shaft Equipment in 2014 for 3 Price previous RFP U4 Manager
Disks /Fabricator completed in Price Local Manager
(Hudson Bay) March 2019 Price work U1, U2, Manager
parts/pieces - lead
(Northwest
/Abatement Dec 2018 work U1, U2,
U3
Manager
Eccentric Pins /Fabricator Jan 2019 Unit Price U2, U3 Manager
Project Team Management Plan Component of Project Execution Plan (PEP)
06 Project Team Management Plan v1 11/1/2018 v1 Page 1 of 2
Project Name: Little Falls HED Unit 4 Upgrade
Project ID: CPR#: 20205045
The purpose of the Project Team Management Plan is to define the Roles & Responsibilities
of the Project Team and Stakeholders.
Name
Role Responsibilities Functional Team
A. Vickers
Owner *Approves scope, schedule & budget
*Identifies major stakeholders
*Identifies Functional Requirements
*Approves Project Execution Plan & Baseline
*Ensures Stakeholder involvement
*Ensures PM can obtain necessary resources
*Champions the project
*Supports project management process
*Approves Change Requests
*Resolves escalated issues
B. Weisbeck Committee *Approves escalated Change Requests GPSS
Project
Manager
*Completes Capital Project Request
*Develops Project Execution Plan
*Executes the Project Execution Plan
*Ensures continued alignment with Charter
*Facilitates RFP Process
*Manages day to day work of the project
*Manages Change Requests
*Manages vendors & contractors
*Identifies project team needs
GPSS
G. Farmer,
P. Hensheid,
B. McNamara,
R. Pierce,
J. Vogel,
Managers/
Shop General
Foreman
*Identifies and assigns necessary resources
*Ensures Stakeholder/Core Team involvement
*Supports project management process and team
*Provide expertise
*Approves project key deliverables (Engineering)
GPSS, Protection,
Network
J. Fauth
A. Fowler
N. Agostinelli
B. Andrews
C. Howard
N. Ethun
Engineers/
Core Team
Members
*Identify work required to complete the project
*Provide estimates of effort and time
*Provide expertise/seek guidance
*Completes assigned tasks and deliverables
*Complete design/specs for crew/vendor/contractor work
*Complete RFP process, bid sheet/SOW as needed
*Identify risk, issues and changes
GPSS, Protection,
Network
Project Team Management Plan Component of Project Execution Plan (PEP)
06 Project Team Management Plan v1 11/1/2018 v1 Page 2 of 2
Name Role Responsibilities Functional Team
C. Parker
T. Berg
Members *Identify work required to complete the project
*Provide estimates of effort and time
*Provide expertise/seek guidance
*Completes assigned tasks and deliverables
*Complete design/specs for crew/vendor/contractor work
*Complete RFP process, bid sheet/SOW as needed
*Identify risk, issues and changes
Mech/Structural,
Electrical,
Relay
Jen Lund *Identify work required to complete the maintenance
*Logs/Updates assets into Maximo
K. Powell
System Ops,
Power Supply,
C. Figart-SCADA
Stakeholders *Identify work required to complete the project
*Provide expertise/seek guidance
*Completes assigned tasks and deliverables
*Complete RFP process, bid sheet/SOW as needed
*Identify risk, issues and changes
Risk Management Plan Component of Project Execution Plan (PEP)
Project Name: Little Falls HED Unit 4 Upgrade
Project ID: CPR#: 20205045
The purpose of the Risk Management Plan is to document the foreseen risks, estimate the
impacts and define risk responses.
Risk Management output is the “Risk Register” contained in the Project Plan Budget Model.
1. Identify Risk
a. Project Team members, stakeholders, subject matter experts and the Project Manger identify
potential risk events
i. Facilitated risk discussions
ii. Risk registers from other projects
iii. Lessons Learned from past projects
2. Analyze Risk
a. Impact to project scope, schedule, budget and/or quality
i. Very low – barely noticeable or insignificant
ii. Low – minor impact
iii. Moderate – major impact
iv. High – impact is unacceptable
v. Very high – project deliverables become unusable or useless
b. Probability of risk event occurring
i. Very low - <10% chance of occurring
ii. Low – 10-25% chance of occurring
iii. Moderate – 25-50% chance of occurring
iv. High – 50-75% chance of occurring
v. Very high - >75% chance of occurring
c. Priority is based on the impact and probability ratings (risk score)
i. Low
ii. Medium
iii. High
iv. Critical
3. Assign Risk Manager
a. Risk is assigned to a team member responsible for monitoring the risk.
4. Develop Risk Response Strategy
a. Identifying options and determining actions to reduce threats to the projects objectives.
i. Accept – no change to project plan
ii. Monitor – see whether it is more or less likely to occur as time goes on
iii. Mitigate – up front action to reduce the probability and/or impact
iv. Transfer – shifts the risk, or part of the risk to another party
v. Avoid – project changes so the risk event is no longer a threat
5. Verify Funding for Contingent Responses
a. Create a contingency response plan to implement immediately if risk event occurs
Schedule Baseline & Schedule Management Plan Component of Project Execution Plan (PEP)
Project Name: Little Falls HED Unit 4 Upgrade
Project ID: CPR#: 20205045
The purpose of the Schedule Baseline is to define the original predicted start, milestone and
finish dates of the project.
The purpose of the Schedule Management Plan is to establish the procedures and
documentation for developing, managing, executing and controlling the project schedule.
Report Manager milestone dates,
updates
schedule
Project Team
Stakeholders
Meetings Manager updates/reviews
Plant Updates Manager expected TTP Group (CPG)
Change Request Manager schedule
baseline
Project Team
Scope Baseline & Scope Management Plan Component of Project Execution Plan (PEP)
Project Name: Little Falls HED Unit 4 Upgrade
Project ID: CPR#: 20205045
The purpose of the Scope Baseline is to define the original approved scope statement.
and ancillary
systems as part
of completion of
the plant
upgrade
program
*Reduce O&M
costs, reduce
risk of
equipment
failure and loss
of generation
generator frame
& windings,
turbine assmbly,
field poles,
governor,
bearings, wicket
gates, cables,
lube oil system,
GSU 2, controls,
protection,
SCADA, and
bailey removal
functional and
commissioned
Outdated/
Obsolete
systems are
removed
upgrade of
Unit 4
generator
ready for
commercial
operation
will perform
work
Vendors/
Suppliers
will provide
materials
and parts
within spec
& schedule
place
9/2018 to
8/2019
include
headgates,
spillgates,
substation,
or facility
work
The purpose of the Scope Management Plan is to establish processes used to ensure the
project includes all the tasks required to complete the project.
Manager deliverables,
update scope
Project Team
Stakeholders
Meetings Manager updates/reviews
Schedule Manager Schedule
Request Manager baseline Project Team
Project Execution Plan – Approval Form Project Name: Little Falls HED Unit 4 Upgrade
Project ID: CPR#: 20205045
Approval Signatures: Project Execution Plan (PEP) – Baseline
_________________________________________________________ _____________
Andy Vickers, Director - GPSS Date
_________________________________________________________ _____________
Jacob Reidt, Manager – Project Delivery & Engineering Date
_________________________________________________________ _____________
Alexis Alexander, Manager – Maintenance, Management & Construction Date
_________________________________________________________ _____________
Bob Weisbeck, Manager – Hydro Operations & Maintenance Date
_________________________________________________________ _____________
Crystal Lewis, Project Manager Date
Project Execution Plan Component Revision History
EVISION OMPONENT ATE OF ELEASE SUMMARY OF HANGES
0 Initial document version
ID Task Name Start Finish Predecessors Cost
1 Design daysMon 11/14... 11/14/1 $0
15 SEL Testing 11.2 dayTue 9/4/18 Fri 9/21/18 $0
16 Construction daSun 8/5/18 Fri 8/2/19 $930,057
17 Disassembly dayTue 9/4/18 Wed 1/9/19 $216,544
18 Clearance and Dewater dayTue 9/4/18 Tue 9/25/18 $25,043
19 Clearance ‐ Electrical 1 day Tue 9/4/18 Wed 9/5/18 15SS $513
20 Clearance ‐ Mechanical 1 day Tue 9/4/18 Wed 9/5/18 19SS $518
21 Electrical Component Isolation 3 days Wed 9/5/18 9/10/1819 $4,324
22 Mechanical Component Isolation 3 days Wed 9/5/18 9/10/1820 $5,729
23 Headgate Seal 1 day Mon 9/24/18 Tue 9/25/18 22SS,15 $1,381
24 Turbine 5 days Mon 9/24/18 Tue 10/2/18 $10,127
25 Remove Ductwork & Overhead Oil Piping 4 days Mon 9/24/18 Fri 9/28/18 15 $9,206
26 Uncouple Shaft 1 day Mon 10/1/18 Tue 10/2/18 25 $921
27 Inspect/Document/As‐Found all Parts & Pieces dayMon 9/24/18 Fri 11/16/18 15 $83,084
28 Remove Oil & Water System Piping 2 days Mon 9/24/18 9/26/18 $4,143
29 Oil Tanks ‐ Overhead 1 day Mon 9/24/18 Tue 9/25/18 $2,302
30 Oil Tanks ‐ In‐floor 2 days Mon 9/24/18 9/26/18 $1,841
31 Remove Brake System 2 days Mon 9/24/18 9/26/18 $3,682
32 Remove Reach Arms daysWed 9/26/18 Thu 9/27/18 31 $460
33 Remove Operating Shaft & Assess 2 days Thu 9/27/18 10/1/1832 $1,841
34 Remove Saddle & Transitions 2 days Thu 9/27/18 10/1/1832 $4,603
35 Remove Turb Bearings & Stands ‐Ship to HydroTe2 days Mon 10/1/18 Thu 10/4/18 34 $3,682
36 Record Wicket Gate Clearances 1 day Thu 10/4/18 Fri 10/5/18 35 $921
37 Remove Upstream Distributor 1 day Fri 10/5/18 10/8/1836 $2,302
38 Remove Dwnstrm Distr & Packing Water Piping daysMon 10/8/18 10/10/137 $3,452
39 Remove Scroll Case Elbows 1 day Wed 10/10/... 10/11/1838 $2,302
40 Remove Turbine ALL HANDS 2 days Thu 10/11/18 10/16/1839 $5,063
41 Remove Turbine & Rings 1 day Thu 10/11/18 Fri 10/12/18 $3,682
42 Load/Transport to NM 1 day Mon 10/15/... 10/16/1841 $1,381
43 Remove Wicket Gates & Levers 2 days Fri 10/5/18 Tue 10/9/18 $2,762
44 Remove/Load/Haul 2 days Fri 10/5/18 Tue 10/9/18 36 $2,762
45 Reassemble Seal Rings, Distributors, Elbows 4 days Tue 10/9/18 10/16/1844 $9,206
46 Piano Wire & Take As‐Found Measurements 8 days Tue 10/16/18 10/30/1845 $18,412
47 Disassemble Rings, Distributors, Elbows 4 days Tue 10/30/18 Tue 11/6/18 46 $9,206
48 Record As‐found Measurements 2 days Tue 11/6/18 Fri 11/9/18 47 $1,841
49 Load/Transport to Wagstaff/NW Sandblast 4 days Fri 11/9/18 Fri 11/16/18 47,48 $9,206
50 Generator dayWed 9/5/18 Wed 1/9/19 $75,661
51 Remove Generator Covers (load/haul)1 day Wed 9/5/18 Thu 9/6/18 19,20 $1,381
52 Remove Upper Half of Stator 3 days Tue 11/6/18 11/12/147 $8,261
53 Load/Haul (7+ days notice)1 day Mon 11/12/... 11/13/1852 $1,381
54 Remove Brush Holders, innerpole connections 2 days Mon 11/12/... 11/15/1852 $1,825
55 Remove Field Poles days Thu 11/15/18 12/25/1854 $33,142
56 Drill/Tap 4 days Thu 11/15/18 11/22/18 $5,524
57 Remove Poles 18 days Thu 11/22/18 12/24/156 $24,856
58 Box/Load/Transport 2 days Fri 12/21/18 12/25/1857FF+1 day $2,762
59 Remove Rotational Exciter/Armature 1 day Mon 9/24/18 Tue 9/25/18 15 $1,841
60 Remove Rotor ALL HANDS 1 day Mon 12/24/... 12/25/1857 $3,214
61 Remove Lower Half of Stator ALL HANDS 1 day Tue 12/25/18 12/27/1860 $3,214
62 Load/Haul (7+ days notice)1 day Thu 12/27/18 Fri 12/28/18 61 $1,381
63 Remove Generator Cables 4 days Thu 12/27/18 Thu 1/3/19 61 $9,124
64 Remove Gen Bearings and Stands daysThu 12/27/18 12/27/1861 $460
65 Remove Generator Shaft 7 days Thu 12/27/18 Wed 1/9/19 64 $10,438
66 Rotate Shaft Vertically daysThu 12/27/18 Fri 12/28/18 60 $1,381
67 Heaters & Wiring 3 days Fri 12/28/18 Thu 1/3/19 66 $5,474
68 Wrap 1 day Thu 1/3/19 Fri 1/4/19 67 $1,741
69 Heat Up daysFri 1/4/19 Tue 1/8/19 68 $0
70 Pull Shaft/Lay Down/Load/Haul 1 day Tue 1/8/19 Wed 1/9/19 69 $1,841
71 Misc Electrical days Tue 9/25/18 Fri 10/26/18 18 $19,984
72 Removal Plan/Coordination (Relay)5 days Tue 9/25/18 10/3/18 $2,645
73 Remove CR Control Panel 2 days Wed 10/3/18 Fri 10/5/18 72 $912
74 Remove Floor Control Panel 3 days Mon 10/8/18 10/11/1873 $4,106
75 Remove Exciter Control Panel 2 days Thu 10/11/18 10/16/1874 $1,825
76 Remove Control Cables 4 days Tue 10/16/18 10/23/1875 $7,299
77 Remove Cable Trays 2 days Tue 10/23/18 10/25/1876 $1,825
78 Remove Misc Electrical Equipment 1 day Tue 9/25/18 9/26/18 $0
79 Brakes/Limitorques/Lube Oil Motor/Servo Heads 1 day Thu 10/25/18 Fri 10/26/18 77 $1,373
80 Removal Drawing Updating/Obsoleting (Relay)5 days Wed 10/3/18 10/11/1872 $2,645
81 Property Removal Notice 1 day Wed 1/9/19 Thu 1/10/19 17 $400
82 External Work daSun 8/5/18 Thu 6/13/19 $0
83 Rebabbit Generator Bearings (HydroTech)48 days Thu 1/3/19 Thu 3/28/19 64,97FF+11 days $0
84 Rebabbit Turbine Bearings (HydroTech)48 days Mon 10/8/18 Fri 12/28/18 35 $0
85 Seal Rings (Wagstaff) days Fri 11/16/18 Thu 1/10/19 $0
86 Measure Rings 10 days Fri 11/16/18 Tue 12/4/18 49 $0
87 Develop and Approve DWGs 3 days Tue 12/4/18 12/10/186 $0
88 Machining/Acceptance/Pick‐up 18 days Mon 12/10/...Thu 1/10/19 87 $0
89 Wicket Gates (Wagstaff) daTue 10/9/18 Thu 4/18/19 $0
90 Initial Machining 16 days Tue 10/9/18 Tue 11/6/18 44 $0
91 Cut to size 16 days Tue 11/6/18 Tue 12/4/18 90 $0
92 US Machine Wicket Gates/Pick‐up 45 days Wed 1/30/19 Thu 4/18/19 90,91,127 $0
93 DS Machine Wicket Gates/Pick‐up 45 days Wed 1/30/19 Thu 4/18/19 90,91,127 $0
94 Painting (NWS&P)34 days Fri 11/16/18 Tue 1/15/19 49,34 $0
95 Field Pole Rehab (GE)47 days Tue 12/25/18 3/18/1958 $0
96 Field Pole Keys (Jetco)38 days Mon 12/24/...Thu 2/28/19 57 $0
97 Generator Shaft Machining (Jetco)34 days Wed 1/9/19 Fri 3/8/19 70 $0
98 Wicket Gate Bushings (CIP)18 days Mon 12/10/...Thu 1/10/19 87,48 $0
99 Eccentric Pin Manufacture (Jetco)43 days Fri 11/9/18 Thu 1/24/19 48 $0
100 Brake Hub (Jetco) ? if needed 48 days Fri 11/9/18 Fri 2/1/19 48 $0
101 Operating Shaft (??) ? if needed 12 days Mon 10/29/...Fri 11/16/18 79,33 $0
102 Concrete Cutting (U3 oil tank relocation)2 days Sun 8/5/18 Tue 8/7/18 $0
103 Ductwork Insulation (Hudson Bay)23 days Mon 5/6/19 Thu 6/13/19 25,140 $0
104 Assembly Prep daWed 9/5/18 4/17/19 $102,261
105 Generator Pit Prep 4 days Thu 1/3/19 Thu 1/10/19 63 $9,597
106 Paint Pit 1 day Thu 1/3/19 Fri 1/4/19 63 $912
107 Build and Install CT 2 days Thu 1/3/19 Mon 1/7/19 63SS $912
108 Epoxy Cracks/Sole Plate 4 days Thu 1/3/19 Thu 1/10/19 63SS $3,650
109 Install Cable Brackets 1 day Thu 1/3/19 Fri 1/4/19 63SS $456
110 Concrete Boring 2 days Thu 1/3/19 Mon 1/7/19 63SS $3,666
111 Install Generator Shaft 4 days Thu 3/28/19 Thu 4/4/19 97 $4,599
112 Heat 1 day Thu 3/28/19 Fri 3/29/19 97,83 $456
1.2 days
1/9
9/25
1 day A Frmn Elec
1 day A Frmn M/S
3 days Jmn Elec #1,Jmn Elec #2,Sr P‐C Mtr Tech
3 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Sr P‐C Mtr Tech
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
4 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
1 day Jmn M/S #1,Jmn M/S #2
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
2 days Jmn M/S #1,Jmn M/S #2
Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
0.5 days Jmn M/S #1,Jmn M/S #2
Jmn M/S #1,Jmn M/S #2
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
1 day Jmn M/S #1,Jmn M/S #2
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
1.5 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5,Jmn M/S #6,Jmn M/S #7,Jmn M/S #8
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
4 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
8 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
4 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
2 days Jmn M/S #1,Jmn M/S #2
4 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
3 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn Elec #1,Jmn Elec #2
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
2 days Jmn Elec #1,Jmn Elec #2
4 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
18 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5,Jmn Elec #1,Jmn Elec #2
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5,Jmn Elec #1,Jmn Elec #2
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
4 days Jmn Elec #1,Jmn Elec #2,Jmn Elec #3,Jmn Elec #4,Jmn Elec #5
0.5 days Jmn M/S #1,Jmn M/S #2
0.5 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5,Jmn M/S #6
3 days Jmn Elec #1,Jmn Elec #2,Jmn Elec #3,Jmn Elec #4
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,App Lnmn 4
1.5 days
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
5 days Sr P‐C Mtr Tech
2 days Jmn Elec #1
3 days Jmn Elec #1,Jmn Elec #2,Jmn Elec #3
2 days Jmn Elec #1,Jmn Elec #2
4 days Jmn Elec #1,Jmn Elec #2,Jmn Elec #3,Jmn Elec #4
2 days Jmn Elec #1,Jmn Elec #2
1 day
1 day Jmn Elec #1,Jmn Elec #2,Jmn M/S #1
5 days Sr P‐C Mtr Tech
1 day Project Manager
48 days
48 days
10 days
3 days
18 days
16 days
16 days
45 days
45 days
34 days
47 days
38 days
34 days
18 days
43 days
48 days
12 days
23 days
1 day Jmn Elec #1,Jmn Elec #2
2 days Jmn Elec #1
4 days Jmn Elec #1,Jmn Elec #2
1 day Jmn Elec #1
2 days Jmn Elec #1,Jmn Elec #2,Jmn M/S #1,Jmn M/S #2
1 day Jmn Elec #1
26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19
Page 1
ID Task Name Start Finish Predecessors Cost
113 Install Shaft 1 day Mon 4/1/19 Tue 4/2/19 112 $1,841
114 Set Screws (Rotor keys) 2 days Tue 4/2/19 Thu 4/4/19 113,70 $921
115 Remove Insulators & Heaters 1 day Tue 4/2/19 Wed 4/3/19 114SS $1,381
116 Clean and Paint Rotor 8 days Wed 4/3/19 4/17/19115 $3,682
117 Install Governor 6 days Tue 1/15/19 Fri 1/25/19 $5,984
118 Mount HPU and Tanks to Floor 1 day Tue 1/15/19 Thu 1/17/19 94 $1,381
119 Install Servo Head 1 day Thu 1/17/19 Fri 1/18/19 118 $921
120 Plumb Servo Head 4 days Fri 1/18/19 Fri 1/25/19 119 $3,682
121 Cable Tray Install 7 days Wed 9/5/18 9/17/1819 $9,124
122 Cable Trays 2 days Wed 9/5/18 Fri 9/7/18 $2,737
123 Concrete Cutting 7 days Wed 9/5/18 9/17/18122SS $6,387
124 Floor Plate Fabrication (servo shaft/U4M/U4G)4 days Wed 9/5/18 9/12/18123SS $3,682
125 Line Boring dayTue 1/15/19 Tue 3/12/19 $45,340
126 Install Distrbtr (Set Seal Rings & Scroll Case Elbow5.7 daysTue 1/15/19 Thu 1/24/19 88,98,94 $10,495
127 Alignment of Disks 3 days Fri 1/25/19 1/30/19126 $4,143
128 Set Up for Boring daysWed 1/30/19 Tue 2/12/19 127 $9,528
129 Line Boring 15 days Tue 2/12/19 3/11/19128 $20,714
130 Disassemble Distributors (Remove Elbows)1 day Mon 3/11/19 Tue 3/12/19 129 $460
131 Turbine days Mon 12/31...Tue 1/29/19 $20,253
132 Machine Turbine Shaft 10 days Mon 12/31/... 1/16/1984 $13,809
133 Wearsleeve Welding & NDT 4 days Mon 1/14/19 Fri 1/18/19 132FF+2 days $1,841
134 Wearsleeve Machine Finish Work 5 days Mon 1/21/19 Tue 1/29/19 133 $4,603
135 Modify Transition Pieces 7 days Tue 1/29/19 Fri 2/8/19 134 $0
136 Prep/Haul Turbine Runner Assembly 2 days Mon 2/11/19 2/13/19135 $0
137 Assemble Turbine Assembly days Fri 4/19/19 Thu 7/11/19 $112,083
138 Install Turbine days Fri 4/19/19 Tue 5/21/19 $33,142
139 Assemble Distributor/Wicket Gates/Gland 8 days Fri 4/19/19 Thu 5/2/19 130,92,93 $18,412
140 Install Turbine (ALL HANDS)1 day Fri 5/3/19 Mon 5/6/19 136,139 $3,682
141 Install Distributors/Seal Rings 2 days Mon 5/6/19 Wed 5/8/19 140 $4,603
142 Install Lower Inner Head Covers 5 days Wed 5/8/19 Thu 5/16/19 141 $4,603
143 Install New Lines Oil & Water 4 days Tue 5/14/19 Tue 5/21/19 142FS‐2 days $1,841
144 Install Draftchest 6 days Tue 5/21/19 Thu 5/30/19 143 $11,047
145 Install Concrete 2 days Tue 5/21/19 Thu 5/23/19 $3,682
146 Install Scrollcase/Transitions/Saddles (Fitment)4 days Fri 5/24/19 Thu 5/30/19 145 $7,365
147 Install Turbine Bearings days Fri 5/24/19 Tue 6/18/19 146SS $14,730
148 Scrape Thrust Bearings 10 days Fri 5/24/19 Tue 6/11/19 84,136,140 $9,206
149 Install Bases/Pedestals/Bearings/Align 4 days Tue 6/11/19 Tue 6/18/19 148,83,141,84 $5,524
150 Alignment 7 days Tue 6/18/19 Mon 7/1/19 149 $10,127
151 Align Turbine 4 days Tue 6/18/19 Tue 6/25/19 $7,365
152 Dowel Turbine Pedestal Bases 3 days Tue 6/25/19 Mon 7/1/19 151 $2,762
153 Install Operating Shaft/Alignment 7 days Wed 5/8/19 Tue 5/21/19 101,141 $6,444
154 Install Reach Arms 8 days Tue 5/21/19 Tue 6/4/19 141 $14,269
155 Install Reach Arm Tops 1 day Tue 5/21/19 5/22/19101,153 $1,381
156 Wicket Gate Timing 7 days Wed 5/22/19 Tue 6/4/19 155 $12,888
157 Coupling days Tue 6/18/19 Thu 7/11/19 149 $18,412
158 Align Coupling 4 days Tue 6/18/19 Tue 6/25/19 $3,682
159 Line Bore Coupling Holes 10 days Tue 6/25/19 Thu 7/11/19 158 $9,206
160 Turn Coupling Bolts 4 days Fri 7/5/19 Thu 7/11/19 159FF $1,841
161 Install Bolts & Torque 3 days Tue 6/25/19 Mon 7/1/19 158 $2,762
162 Install Nut Covers 1 day Mon 7/1/19 Tue 7/2/19 161 $921
163 Install Brake System daysTue 5/21/19 Fri 5/24/19 154SS $3,913
164 Install Brake System Equipment 2 days Tue 5/21/19 Thu 5/23/19 120,104,100 $3,682
165 Plumb New Air Supply daysFri 5/24/19 Fri 5/24/19 164 $230
166 Assemble Generator Assembly daWed 9/5/18 Tue 7/23/19 $82,331
167 Install Generator Cables 6 days Mon 1/7/19 Thu 1/17/19 $13,686
168 1500kcm Cables 3 days Fri 1/11/19 Thu 1/17/19 169 $6,843
169 3000kcm Cables 3 days Mon 1/7/19 Fri 1/11/19 110 $6,843
170 Install Lower Half of Generator 2 days Fri 1/11/19 Tue 1/15/19 169 $4,595
171 Install Rotor 2 days Thu 3/28/19 Tue 4/2/19 170 $2,762
172 Install Generator Bearings 1 day Thu 3/28/19 Fri 3/29/19 83 $460
173 Install Rotor 1 day Mon 4/1/19 Tue 4/2/19 172 $2,302
174 Install Field Poles dayMon 3/18/19 Fri 5/3/19 $20,253
175 Receive/Load Poles 1 day Mon 3/18/19 Tue 3/19/19 95 $1,381
176 Install Field Poles 8 days Tue 4/2/19 Tue 4/16/19 175,173,96 $11,047
177 Wedge Field Poles 3 days Tue 4/16/19 Fri 4/19/19 176 $4,143
178 Cut/Trim Wedges 8 days Mon 4/22/19 Fri 5/3/19 177 $3,682
179 Install Rotational Exciter 1 day Mon 5/6/19 Tue 5/7/19 178 $1,841
180 Install Upper Half of Generator 1 day Tue 5/7/19 Wed 5/8/19 179 $1,381
181 Stator Roundness (GE‐External)1 day Wed 5/8/19 Thu 5/9/19 180 $1,841
182 Generator Splice (External) 15 days Thu 5/9/19 Wed 6/5/19 181 $0
183 Stator/Turbine Final alignment 1 day Mon 6/3/19 Tue 6/4/19 149,182 $0
184 Terminate Gen Cables dayMon 1/7/19 Tue 6/11/19 $11,861
185 Closet Splice 3 days Thu 1/17/19 Tue 1/22/19 168,169 $2,737
186 4kV Switchgear 3 days Tue 1/22/19 1/28/19185 $2,737
187 Generator 3 days Wed 6/5/19 Tue 6/11/19 182 $2,737
188 Wye Point‐CT skid 4 days Mon 1/7/19 1/14/19107 $3,650
189 Final Rotor Assembly days Wed 6/5/19 Fri 7/12/19 $15,365
190 Install & Wedge Last 10 Field Poles 8 days Wed 6/5/19 6/19/19182 $3,682
191 Cut/Trim Wedges 8 days Wed 6/19/19 Wed 7/3/19 190 $3,682
192 Solder Innerpole Connections 3 days Wed 7/3/19 Tue 7/9/19 191 $4,106
193 Install Rotor Cable 1 day Tue 7/9/19 7/10/19192 $1,369
194 Perform Rotor Pole Drop Testing daysWed 7/10/19 Thu 7/11/19 193 $684
195 Install Rotor Fan Blades 2 days Wed 7/10/19 Fri 7/12/19 194SS $1,841
196 Install Generator Covers daWed 9/5/18 Tue 7/23/19 $8,746
197 Add Man Door/Access 2 days Wed 9/5/18 Fri 9/7/18 20,19 $921
198 Install Spacers 1 day Wed 9/5/18 Thu 9/6/18 197SS $921
199 Drill and Tap Holes 3 days Mon 7/15/19 Thu 7/18/19 198,195 $1,381
200 Modify Covers to Mate‐up 3 days Thu 9/6/18 9/12/18198 $2,762
201 Install Covers 2 days Thu 7/18/19 Tue 7/23/19 200,195,199 $2,762
202 Final Electrical Install daWed 9/5/18 6/12/19104SS $57,029
203 Unit PLC Install days Fri 1/11/19 Tue 2/19/19 $10,036
204 Layout Wire 2 days Fri 1/11/19 Tue 1/15/19 169 $912
205 Wire PLC 15 days Tue 1/15/19 2/11/19204 $6,843
206 Terminate Field Wiring 5 days Mon 2/11/19 Tue 2/19/19 205 $2,281
207 Unit Protection/Control PNL days Fri 1/11/19 Fri 2/22/19 169 $10,949
208 Layout Protection Panel 2 days Fri 1/11/19 Tue 1/15/19 $912
209 Layout Control Panel 1 day Tue 1/15/19 Thu 1/17/19 208 $456
210 Wire Protection Panel 8 days Thu 1/17/19 Thu 1/31/19 209 $3,650
211 Wire Control Panel 8 days Thu 1/31/19 Thu 2/14/19 210 $3,650
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
2 days Jmn M/S #1
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
8 days Jmn M/S #1
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
1 day Jmn M/S #1,Jmn M/S #2
4 days Jmn M/S #1,Jmn M/S #2
2 days Jmn Elec #1,Jmn Elec #2,Jmn Elec #3
7 days Jmn Elec #1,Jmn Elec #2
4 days Jmn M/S #1,Jmn M/S #2
5.7 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
3 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
6.9 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
15 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
4 days Jmn M/S #1
5 days Jmn M/S #1,Jmn M/S #2
7 days
2 days
8 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5,Jmn M/S #6,Jmn M/S #7,Jmn M/S #8
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
5 days Jmn M/S #1,Jmn M/S #2
4 days Jmn M/S #1
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
4 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
10 days Jmn M/S #1,Jmn M/S #2
4 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
4 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
3 days Jmn M/S #1,Jmn M/S #2
Jmn M/S #1,Jmn M/S #2
6/4
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
7 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
7/11
4 days Jmn M/S #1,Jmn M/S #2
10 days Jmn M/S #1,Jmn M/S #2
4 days Jmn M/S #1
3 days Jmn M/S #1,Jmn M/S #2
1 day Jmn M/S #1,Jmn M/S #2
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
0.5 days Jmn M/S #1
3 days Jmn Elec #1,Jmn Elec #2,Jmn Elec #3,Jmn Elec #4,Jmn Elec #5
3 days Jmn Elec #1,Jmn Elec #2,Jmn Elec #3,Jmn Elec #4,Jmn Elec #5
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn Elec #5
1 day Jmn M/S #1
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4,Jmn M/S #5
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
8 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
3 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
8 days Jmn M/S #1
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3,Jmn M/S #4
15 days
3 days Jmn Elec #1,Jmn Elec #2
3 days Jmn Elec #1,Jmn Elec #2
3 days Jmn Elec #1,Jmn Elec #2
4 days Jmn Elec #1,Jmn Elec #2
7/12
8 days Jmn M/S #1
8 days Jmn M/S #1
3 days Jmn Elec #1,Jmn Elec #2,Jmn Elec #3
1 day Jmn Elec #1,Jmn Elec #2,Jmn Elec #3
0.5 days Jmn Elec #1,Jmn Elec #2,Jmn Elec #3
2 days Jmn M/S #1,Jmn M/S #2
2 days Jmn M/S #1
1 day Jmn M/S #1,Jmn M/S #2
3 days Jmn M/S #1
3 days Jmn M/S #1,Jmn M/S #2
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
6/12
2/19
2 days Jmn Elec #1
15 days Jmn Elec #1
5 days Jmn Elec #1
2/22
2 days Jmn Elec #1
1 day Jmn Elec #1
8 days Jmn Elec #1
8 days Jmn Elec #1
26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19
Page 2
ID Task Name Start Finish Predecessors Cost
212 Terminate Field Wiring 5 days Thu 2/14/19 Fri 2/22/19 211 $2,281
213 Unit Exciter Control PNL 9 days Fri 1/11/19 1/28/19169 $4,106
214 Layout Exciter Panel 5 days Fri 1/11/19 1/21/19 $2,281
215 Wire Exciter Panel 3 days Mon 1/21/19 Fri 1/25/19 214 $1,369
216 Terminate Field Wiring 1 day Fri 1/25/19 1/28/19215 $456
217 Wire Governor System 9 days Thu 1/17/19 Fri 2/1/19 $6,387
218 Wiring Governor System 5 days Thu 1/17/19 Fri 1/25/19 118 $4,562
219 Terminate Field Wiring 4 days Fri 1/25/19 Fri 2/1/19 218 $1,825
220 Wire switchgear 5 days Fri 1/11/19 1/21/19169 $3,650
221 Layout and Wire Switchgear 3 days Fri 1/11/19 Thu 1/17/19 $2,737
222 Terminate Field Wiring 2 days Thu 1/17/19 1/21/19221 $912
223 Unit Monitoring Enclosure (U2M) days Fri 1/11/19 Fri 2/22/19 169 $10,949
224 Layout and Wire Enclosure 20 days Fri 1/11/19 Fri 2/15/19 $9,124
225 Terminate Field Wiring 4 days Fri 2/15/19 Fri 2/22/19 224 $1,825
226 Wire MCC ‐ 5 Buckets dayWed 9/5/18 Mon 2/4/19 $917
227 Terminate Field Wiring ‐ 2 Oil Pumps 1 day Fri 2/1/19 Mon 2/4/19 241 $460
228 Terminate Field Wiring ‐ 2 Governor Pumps daysThu 1/17/19 Thu 1/17/19 118 $228
229 Terminate Field Wiring ‐ 1 Fan Motor daysWed 9/5/18 Wed 9/5/18 104SS $228
230 Generator RTD box 4 days Wed 6/5/19 6/12/19 $1,825
231 Layout RTD Box 2 days Wed 6/5/19 Fri 6/7/19 182 $912
232 Terminate Field Wiring 2 days Mon 6/10/19 6/12/19231 $912
233 Device Wiring dayWed 9/5/18 Tue 1/15/19 $8,212
234 Field Devices: Oil 2 days Wed 9/5/18 Fri 9/7/18 241SS $1,825
235 Field Devices: Water 2 days Wed 9/5/18 Fri 9/7/18 253SS $1,825
236 Field Devices: Vacuum Breaker Valve 2 days Fri 1/11/19 Tue 1/15/19 169 $912
237 Field Devices: Speed Sensors 2 days Fri 1/11/19 Tue 1/15/19 236SS $1,825
238 Field Devices: Vibration System 2 days Fri 1/11/19 Tue 1/15/19 237SS $1,825
239 Final Mechanical Install daTue 8/7/18 Fri 8/2/19 104SS $37,883
240 Install Shaft Packing 4 days Tue 7/23/19 Tue 7/30/19 131,201 $3,682
241 Lower Oil System daTue 8/7/18 Fri 2/1/19 104SS $11,047
242 Install New Oil Tank 2 days Wed 9/5/18 Fri 9/7/18 104SS,243 $1,841
243 Relocate U3 Oil Tank 8 days Tue 8/7/18 Tue 8/21/18 102 $0
244 Install New Return Oil Piping 3 days Fri 1/25/19 Thu 1/31/19 120,242SS $2,762
245 Install Pumps 3 days Fri 1/25/19 Thu 1/31/19 244SS $2,762
246 Install Wall Panel Piping 4 days Fri 1/25/19 Fri 2/1/19 245SS $3,682
247 Ductwork dayFri 6/14/19 Thu 8/1/19 $12,428
248 Gather Duct Work Sections 3 days Fri 6/14/19 6/19/19103 $4,143
249 Install & Field Fit Sections 6 days Tue 7/23/19 Thu 8/1/19 248,201 $8,285
250 Upper Oil System Install daWed 9/5/18 Thu 8/1/19 $4,143
251 Install Upper Oil Tank 1 day Wed 9/5/18 Thu 9/6/18 104SS $1,381
252 Install Oil Header Lines 2 days Tue 7/30/19 Thu 8/1/19 $2,762
253 Unit Water System daWed 9/5/18 Fri 8/2/19 $6,582
254 Install Water Piping daysMon 7/29/19 Thu 8/1/19 249FF,104SS $2,394
255 Fabricate Drip Pans daysWed 9/5/18 9/19/18104SS $3,728
256 Install Drip Pans daysThu 8/1/19 Fri 8/2/19 254 $460
257 GSU Protection Bus 2 dayMon 4/8/19 Fri 6/28/19 $0
258 Settings from Protection 1 day Mon 4/8/19 Tue 4/9/19 260SS $0
259 GSU Install days Mon 4/8/19 Fri 5/31/19 $0
260 Yellow Line Drawings 5 days Mon 4/8/19 Tue 4/16/19 $0
261 PLC Programming/SCADA (Controls)25 days Mon 4/8/19 Tue 5/21/19 260SS $0
262 Panel Layouts 2 days Mon 4/8/19 4/10/19261SS $0
263 Build Drawers 1 day Mon 4/8/19 Tue 4/9/19 262SS $0
264 Panel Wiring 20 days Wed 4/10/19 5/15/19263,262 $0
265 Modify & Terminate Field Cables 9 days Wed 5/15/19 Thu 5/30/19 264 $0
266 Bus 2 Outage (w Unit 3) dayMon 6/3/19 Thu 6/27/19 265 $0
267 Install drawers, cable wiring daysMon 6/3/19 Fri 6/7/19 265 $0
268 Checkout 8 days Mon 6/10/19 Fri 6/21/19 $0
269 Checkout 3 days Mon 6/10/19 Thu 6/13/19 267 $0
270 SS ‐ update settings 2 days Thu 6/13/19 Tue 6/18/19 269 $0
271 SCADA 5 days Thu 6/13/19 Fri 6/21/19 269 $0
272 GSU Commissioning (including re‐syncro U3)4 days Mon 6/24/19 Fri 6/28/19 268 $0
273 Red Line Drawings 8 days Mon 7/1/19 Fri 7/12/19 272 $0
274 Commissioning daFri 1/11/19 8/21/19 $79,281
275 Check Out days Fri 1/11/19 Mon 6/3/19 104SS,169 $44,747
276 Relays ‐ SEL‐700G, SEL‐351, LOR, Syncronization 6 days Fri 1/11/19 Tue 1/22/19 $3,173
277 Meters ‐ SEL‐735 2 days Tue 1/22/19 Fri 1/25/19 276 $1,058
278 PLCs ‐ wiring, I/O check, logic, comm, DNP, modbus 25 days Fri 1/25/19 3/11/19277 $13,223
279 XM Modules,SEL‐2600,wiring,comm,device net com5 days Mon 3/11/19 Tue 3/19/19 278 $2,645
280 CTs/PTs ‐ gen bkr, wiring, function 5 days Tue 3/19/19 Thu 3/28/19 279 $2,645
281 HMI 4 days Thu 3/28/19 Thu 4/4/19 280 $4,022
282 Controls & Protection ‐ headgate, auxillary, OIT, wir 3 days Thu 4/4/19 Tue 4/9/19 281 $1,587
283 Field Devices ‐ including auxillaries 3 days Tue 4/9/19 4/15/19282 $1,587
284 Sensors‐Oil flow/levl,air,water,RTD,vibe,speed,+spe 15 days Mon 4/15/19 Fri 5/10/19 283 $7,934
285 Exciter‐wiring, OIT, SEL‐2664, comm, logic, schem, fu7 days Fri 5/10/19 Thu 5/23/19 284 $3,702
286 Governor ‐ wiring, I/O check, comm 3 days Thu 5/23/19 Tue 5/28/19 285 $1,587
287 MCC (6 buckets) ‐ schematics, wiring, settings, funct3 days Tue 5/28/19 Mon 6/3/19 286 $1,587
288 Commissioning (2wks) days Mon 8/5/19 8/21/19275,256,238 $34,534
289 Dry Test 1 day Mon 8/5/19 Tue 8/6/19 $1,878
290 Water Up 1 day Tue 8/6/19 Wed 8/7/19 289 $2,366
291 First Spin/Flash Field 1 day Wed 8/7/19 Thu 8/8/19 290 $2,822
292 Exciter 5 days Wed 8/7/19 Thu 8/15/19 291SS $2,645
293 Governor 9 days Tue 8/6/19 8/21/19289 $4,760
294 Adjust Stator 2 days Thu 8/8/19 Tue 8/13/19 291 $2,754
295 Closeout daWed 8/21/19 Mon 7/6/20 288 $162,869
296 Commercial Operation (GOC ends 8/30/19 6pm) daysWed 8/21/19 Fri 8/23/19 $600
297 Notify/Coordinate Operations 1 day Wed 8/21/19 Thu 8/22/19 $400
298 TTP/ In‐Service/Used and Useful Notification daysThu 8/22/19 Fri 8/23/19 297 $200
299 As‐Builts days Wed 8/21/19 Fri 12/6/19 $19,569
300 Relay Tech ‐ Yellow Line Verification/submit to Cirru7 days Wed 8/21/19 Tue 9/3/19 $3,702
301 Elect Engr 10 days Wed 8/21/19 Fri 9/6/19 $0
302 Mech Engr 10 days Wed 8/21/19 Fri 9/6/19 $0
303 Controls Engr 10 days Wed 8/21/19 Fri 9/6/19 $0
304 Drafter ‐ Cirrus 15 days Tue 9/3/19 Fri 9/27/19 300 $0
305 Relay Tech ‐ Review with Cirrus 10 days Fri 9/27/19 10/16/1304 $5,289
306 Drafter ‐ Avista 10 days Wed 10/16/...Fri 11/1/19 305 $0
307 Relay Tech ‐ Review/Approve Asbuilts from Drafting20 days Fri 11/1/19 Fri 12/6/19 306 $10,578
308 Closeout Checklist & Final Project Report dayWed 8/21/19 Fri 5/8/20 $60,000
309 Approval to Close 5 days Fri 5/8/20 Tue 5/19/20 308 $2,000
310 Hard Close Project 1 day Fri 7/3/20 Mon 7/6/20 day$400
5 days Jmn Elec #1
1/28
5 days Jmn Elec #1
3 days Jmn Elec #1
1 day Jmn Elec #1
2/1
5 days Jmn Elec #1,Jmn Elec #2
4 days Jmn Elec #1
1/21
3 days Jmn Elec #1,Jmn Elec #2
2 days Jmn Elec #1
2/22
20 days Jmn Elec #1
4 days Jmn Elec #1
2/4
1 day Jmn M/S #1
0.5 days Jmn Elec #1
0.5 days Jmn Elec #1
6/12
2 days Jmn Elec #1
2 days Jmn Elec #1
1/15
2 days Jmn Elec #1,Jmn Elec #2
2 days Jmn Elec #1,Jmn Elec #2
2 days Jmn Elec #1
2 days Jmn Elec #1,Jmn Elec #2
2 days Jmn Elec #1,Jmn Elec #2
4 days Jmn M/S #1,Jmn M/S #2
2 days Jmn M/S #1,Jmn M/S #2
3 days Jmn M/S #1,Jmn M/S #2
3 days Jmn M/S #1,Jmn M/S #2
4 days Jmn M/S #1,Jmn M/S #2
3 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
6 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
1 day Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
2 days Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
2.6 days Jmn M/S #1,Jmn M/S #2
8.1 days Jmn M/S #1
0.5 days Jmn M/S #1,Jmn M/S #2
4.1 days
3 days
5 days
8 days
8/21
6 days Sr P‐C Mtr Tech
2 days Sr P‐C Mtr Tech
25 days Sr P‐C Mtr Tech
5 days Sr P‐C Mtr Tech
5 days Sr P‐C Mtr Tech
4 days Sr P‐C Mtr Tech,Jmn P/C Mtr Tech 1
3 days Sr P‐C Mtr Tech
3 days Sr P‐C Mtr Tech
15 days Sr P‐C Mtr Tech
7 days Sr P‐C Mtr Tech
3 days Sr P‐C Mtr Tech
3 days Sr P‐C Mtr Tech
1 day Sr Comm Tech,Jmn Elec #1,Jmn M/S #1,Jmn M/S #2
1 day Sr P‐C Mtr Tech,Jmn Elec #1,Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
1 day Sr P‐C Mtr Tech,Jmn Elec #1,Jmn Elec #2,Jmn M/S #1,Jmn M/S #2,Jmn M/S #3
5 days Sr P‐C Mtr Tech
9 days Sr P‐C Mtr Tech
2 days Jmn M/S #1,Jmn M/S #2,Jmn Elec #3
8/23
1 day Project Manager
0.5 days Project Manager
7 days Sr P‐C Mtr Tech
10 days
10 days
10 days
15 days
10 days Sr P‐C Mtr Tech
10 days
20 days
150 days
26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19
Page 3
e) Project Completion Analysis
e. iii. Baseline Schedule to Actual Schedule Comparison: Project Schedules: The Unit 4 Upgrade project schedule is provided in a snapshot below showing the Completion
Dates identified in the Baseline Schedule with a data date of 10/2018 and the updated Project
Schedule with a data date of 5/2019. Baseline Project Schedule dated 10/12/18:
This shows the original Unit 4 completion of work when the generator is released to the Operations
group for commercial operation and production on the dates shown as early as 8/21/19 to 8/23/19.
Updated Project Schedule dated 5/22/19:
This shows the updated/revised Unit 4 completion of work when the generator is released to the
Operations group for commercial operation and production on the dates shown as early as 9/19/19 to 9/23/19. The project experienced a delay in delivery of critical materials from a fabricator that resulted in a negative impact to the project completion dates. To mitigate this delay of one month in the completion dates for Unit 4, the project team has made arrangements and taken additional
steps to compress the unit commissioning from two weeks down to one week with anticipation of
releasing the unit to Operations before the revised 9/19/19 date above.
Project Monthly Report – August 2019
Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2019 Budget: $ 4,300,000 Approved Lifetime Budget: $9,500,000
Accrued 2019 to Date (through July): $ 3,238,437 Accrued Life to Date (through July): $7,942,543
2019 Estimate at Complete: $ 4,500,000 Total Project Estimate at Complete: $9,500,000
Expected Transfer to Plant Date: Sept 2019 Expected Transfer to Plant Amount: $9,050,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system. The budget for the project including all trailing costs with plant and program closeout and drawings into Sept 2020 is $9.5M.
Unit 4’s construction began Sept 2018, with outage thru Aug 2019, extended to 9/30/2019 due to wicket gate delay.
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete Unit 4 Drawing Duplication October 2018 Complete Unit 4 Outage GOC Start/Finish 9/4/18 – 9/30/19 Outage in Progress GSU 2 Outage (w/U3 GOC) 6/3/19-6/28/19 Complete Unit 4 Commissioning 9/9/19 – 9/20/19 Wicket gates – delay, GOC extended
Accomplishments:
•Drawing duplication complete.
•Outage began for unit on 9/4, GOC in place thru 8/2019. GOC extended to 9/30/19
•Project Execution Plan signed Nov 2018, Schedule baseline 10/12/18
•Turbine & Generator bearings returned and installed
•All cables and wires installed, pulled into place and being terminated,
•Line boring complete, field poles installed and wedged, stator halves in place and spliced, field poles installed
•Hudson Bay completed ducting insulation, Concrete Cutters completed U3 & U2 vault work
Upcoming Activities
•Materials and equipment orders continue for unit install work, receiving new parts and materials, almost complete
•Continued progress in assembly, parts and pieces received from vendors and are at plant
•Assembly of equipment and materials is occurring
•Wicket gates install complete, last 10 field poles installed and wedged, oil and water line install and prep in progress
•Hudson Bay final banding of ducting TBD after unit completion
•Turbine and Stator alignment and coupling complete, generator connections in pit ongoing, wiring and terminations ongoing
•SCADA PLC design and Bailey Retirement design transmittal forthcoming. Work to be completed after Unit 4 is online but beforeend Oct 2019.
Risks and Mitigation Strategies:
•Issues with Wagstaff and quality of wicket gates and potential delays is continually being monitored. Completion dates are set,pending actual delivery of gates. GOC modified, and commissioning dates communicated to internal and external stakeholders.Continued updates to Steering Committee are occurring. Gates received and installed. Project schedule and GOC updated. Tofurther mitigate this project delay, a one week (compressed) commissioning schedule is being implemented by the Project Teamto be able to release the unit to Operations for commercial production in advance of the Sept 30 GOC expiration. COMPLETED
•Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2commissioning and Unit 4 commissioning. - COMPLETED
•Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings,prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for properpart/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 1 of 16
Project Monthly Report – July 2019 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2019 Budget: $ 3,480,000 Approved Lifetime Budget: $9,500,000
Accrued 2019 to Date (through June): $ 2,654,156 Accrued Life to Date (through June): $7,358,261
2019 Estimate at Complete: $ 4,500,000 Total Project Estimate at Complete: $9,500,000
Expected Transfer to Plant Date: Sept 2019 Expected Transfer to Plant Amount: $8,800,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system.
The budget for the project including all trailing costs with plant and program closeout and drawings into Sept 2020 is now estimated at $9.5M.
Unit 4’s construction began Sept 2018, outage thru Aug 2019, extended to 9/30/2019. Delay in Wicket Gate delivery.
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete Unit 4 Drawing Duplication October 2018 Complete Unit 4 Outage Start 9/4/18 Outage in Progress GSU 2 Outage (w/U3 GOC) 6/3/19-6/28/19 Work Complete Unit 4 Commissioning 9/9/19 – 9/20/19 Wicket gates – delay, GOC extended Accomplishments:
• Drawing duplication complete. • Outage began for unit on 9/4, GOC in place thru 8/2019. GOC extended to 9/30/19
• Project Execution Plan signed Nov 2018, Schedule baseline 10/12/18
• Turbine & Generator bearings returned and installed
• All cables and wires installed, pulled into place and being terminated,
• Line boring complete, field poles installed and wedged, stator halves in place and spliced, field poles installed
• Hudson Bay completed ducting insulation, Concrete Cutters completed U3 vault work Upcoming Activities
• Materials and equipment orders continue for unit install work, receiving new parts and materials
• Continued progress in assembly, parts and pieces shipped off to vendors and arriving back at plant
• Assembly of equipment and materials is occurring
• Wicket gates back from Wagstaff following repairs of non-conformance issues with several gates completed. Downstream gates received 6/5. Upstream gates received 6/25. Project delay determined as 30 day delay and extended GOC to 9/30/19.
• Hudson Bay final banding TBD after unit completion, Concrete Cutters pending U2 vault as available
• Turbine and Stator alignment ongoing, generator connections in pit ongoing, wiring and terminations ongoing
• SCADA PLC design and Bailey Retirement design anticipated transmittal 7/19. Work for these to be completed under Unit 4 scope, not during outage but before end Oct 2019. Risks and Mitigation Strategies:
• Issues with Wagstaff and quality of wicket gates and potential delays is continually being monitored. Completion dates are set, pending actual delivery of gates. GOC modified, and commissioning dates communicated to internal and external stakeholders. Continued updates to Steering Committee are occurring. COMPLETED
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning. - COMPLETED
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 2 of 16
Project Monthly Report – June 2019 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2019 Budget: $ 3,480,000 Approved Lifetime Budget: $9,500,000
Accrued 2019 to Date (through May): $ 2,335,768 Accrued Life to Date (through May): $7,039,874
2019 Estimate at Complete: $ 4,500,000 Total Project Estimate at Complete: $9,500,000
Expected Transfer to Plant Date: Sept 2019 Expected Transfer to Plant Amount: $8,800,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system.
The budget for the project including all trailing costs with plant and program closeout and drawings into Sept 2020 is now estimated at $9.5M.
Unit 4’s construction began Sept 2018, outage thru Aug 2019, extended to 9/30/2019. Delay in Wicket Gate delivery.
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 Complete Unit 4 Outage Start 9/4/18 Outage in Progress GSU 2 Outage (w/U3 GOC) 6/3/19-6/28/19 Outage in Progress Unit 4 Commissioning 9/9/19 – 9/20/19 Wicket gates – delay, GOC extended Accomplishments:
• Drawing duplication complete. • Outage began for unit on 9/4, GOC in place thru 8/2019. GOC extended to 9/30/19
• Project Execution Plan signed Nov 2018, Schedule baseline 10/12/18
• Turbine & Generator bearings returned to Little Falls
• All cables and wires installed, pulled into place and being terminated,
• Line boring complete, field poles installed and wedged, stator halves in place pending ongoing splicing
• Hudson Bay completed ducting insulation, Concrete Cutters completed U3 vault work Upcoming Activities
• Materials and equipment orders continue for unit install work, receiving new parts and materials
• Continued progress in assembly, parts and pieces shipped off to vendors and arriving back at plant
• Assembly of equipment and materials is occurring
• Wicket gates in progress at Wagstaff, repairs of non-conformance issues with several gates completed. Downstream gates received 6/5. Upstream gates anticipated 6/26. Communication with Steering Committee and Engineering Team ongoing, project delays – extent determined as 30 day delay and extend GOC to 9/30/19.
• Hudson Bay final banding TBD after unit completion, Concrete Cutters pending U2 vault as available
• GE on site for stator roundness, shimming, splicing, and load testing week 6/17
• SCADA PLC design on going, Bailey Retirement design in progress. Work for these to be completed under Unit 4 scope, not during outage but before end Dec 2019. Risks and Mitigation Strategies:
• Issues with Wagstaff and quality of wicket gates and potential delays is continually being monitored. Completion dates are set, pending actual delivery of gates. GOC modified, and commissioning dates communicated to internal and external stakeholders. Continued updates to Steering Committee are occurring. ON-GOING
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning. - COMPLETED
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 3 of 16
Project Monthly Report – May 2019 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2019 Budget: $ 3,480,000 Approved Lifetime Budget: $8,200,000
Accrued 2019 to Date (through Apr): $ 1,910,963 Accrued Life to Date (through Apr): $6,615,068
2019 Estimate at Complete: $ 3,480,000 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system. The budget for the project remains at $8.2M. Unit 4’s construction began Sept 2018, outage thru Aug 2019. Delay in Wicket Gate delivery.
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 Complete Unit 4 Outage Start 9/4/18 Outage in Progress GSU 2 Outage (w/U3 GOC) 6/3/19-6/28/19 Unit 4 Commissioning 8/5/19 – 8/23/19 Wicket gates - possible delay
Accomplishments:
• Drawing duplication complete.
• Outage began for unit on 9/4, GOC in place thru 8/2019.
• New stator halves ready at Little Falls. Paint repair of stator halves completed by GE (S&S Coatings)
• Project Execution Plan signed Nov 2018, Schedule baseline 10/12/18
• Turbine & Generator bearings returned to Little Falls
• All cables and wires installed, pulled into place and being terminated,
• Line boring complete, field poles installed and wedged, stator halves in place pending ongoing splicing Upcoming Activities
• Materials and equipment orders continue for unit install work, receiving new parts and materials
• Continued progress in assembly, parts and pieces shipped off to vendors and arriving back at plant
• Assembly of equipment and materials is occurring
• Wicket gates in progress at Wagstaff, repairs of non-conformance issues with several gates currently in progress. Communication with Steering Committee and Engineering Team ongoing, potential project delays – extent unknown.
• Hudson Bay to begin ducting insulation May 13, Concrete Cutters work on vaults as available
• GE on site for stator roundness, shimming, splicing, and load testing 5/6 to 6/5
• SCADA PLC design on going, Bailey Retirement design in progress. Work for these to be completed under Unit 4 scope, not during outage but before end Dec 2019.
Risks and Mitigation Strategies:
• Issues with Wagstaff and quality of wicket gates and potential delays is continually being monitored to get final report and completion dates before identifying full extent of project delay. Upon final analysis of delay and impact to the project a revised schedule, request to modify the GOC, and commissioning dates will be communicated to internal and external stakeholders. Continued updates to Steering Committee are occurring.
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning. - COMPLETED
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 4 of 16
Project Monthly Report – April 2019 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2019 Budget: $ 3,480,000 Approved Lifetime Budget: $8,200,000
Accrued 2019 to Date (through Mar): $ 1,189,176 Accrued Life to Date (through Mar): $5,893,281
2019 Estimate at Complete: $ 3,480,000 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system. The budget for the project remains at $8.2M. Unit 4’s construction began Sept 2018, outage thru Aug 2019
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 Complete Unit 4 Outage Start 9/4/18 Outage in Progress GSU 2 Outage (w/U3 GOC) 6/3/19-6/28/19 Unit 4 Commissioning 8/5/19 – 8/23/19
Accomplishments:
• Drawing duplication complete.
• Outage began for unit on 9/4, GOC in place thru 8/2019.
• New stator halves ready at Little Falls. Paint repair of stator halves completed by GE (S&S Coatings)
• Project Execution Plan signed Nov 2018, Schedule baseline 10/12/18
• Turbine & Generator bearings returned to Little Falls
• All cables and wires installed, pulled into place and being terminated Upcoming Activities
• Materials and equipment orders continue for unit install work, receiving new parts and materials
• Continued progress in assembly, parts and pieces shipped off to vendors and arriving back at plant, line boring complete
• Assembly of equipment and materials is occurring, Field Poles installed and wedged pending final completion after stator splicing
• Wicket gates in progress at Wagstaff, issues with 4 gates currently under review and discussion with Steering Committee and Engineering Team, potential project delays – extent unknown
• Hudson Bay to begin ducting insulation May 6, Concrete Cutters work on vaults as available
• GE to be on site for stator roundness, shimming, splicing, and load testing 5/6 to 6/5
• SCADA PLC design on going, Bailey Retirement design in progress. Work for these to be completed under Unit 4 scope, not during outage but before end Dec 2019. Risks and Mitigation Strategies:
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning. - COMPLETED
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 5 of 16
Project Monthly Report – Mar 2019 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2019 Budget: $ 3,480,000 Approved Lifetime Budget: $8,200,000
Accrued 2019 to Date (through Feb): $ 835,862 Accrued Life to Date (through Feb): $5,539,968
2019 Estimate at Complete: $ 3,480,000 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system. The budget for the project remains at $8.2M. Unit 4’s construction began Sept 2018, outage thru Aug 2019
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 Complete Unit 4 Outage Start 9/4/18 Outage in Progress GSU 2 Outage (w/U3 GOC) 6/3/19-6/28/19 Unit 4 Commissioning 8/5/19 – 8/23/19
Accomplishments:
• Drawing duplication complete.
• Outage began for unit on 9/4, GOC in place thru 8/2019.
• New stator halves ready at Little Falls. Paint repair of stator halves completed by GE (S&S Coatings)
• Project Execution Plan signed Nov 2018, Schedule baseline 10/12/18
• Turbine & Generator bearings returned to Little Falls
• All cables and wires installed, pulled into place and being terminated Upcoming Activities
• Materials and equipment orders continue for unit install work, receiving new parts and materials
• Continued progress in assembly, parts and pieces shipped off to vendors and arriving back at plant, line boring in progress
• Assembly of equipment and materials is occurring
• Wicket gates in progress at Wagstaff, Hudson Bay to begin ducting insulation May 6, Concrete Cutters work on vaults as available
• SCADA PLC design on going, Bailey Retirement design in progress. Work for these to be completed under Unit 4 scope, not during outage but before end Dec 2019. Risks and Mitigation Strategies:
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning. - COMPLETED
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 6 of 16
Project Monthly Report – Feb 2019 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2019 Budget: $ 3,480,000 Approved Lifetime Budget: $8,200,000
Accrued 2019 to Date (through Jan): $ 464,084 Accrued Life to Date (through Jan): $5,168,189
2019 Estimate at Complete: $ 3,480,000 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system. The budget for the project remains at $8.2M. Unit 4’s construction began Sept 2018, outage thru Aug 2019
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 In progress Unit Outage Start 9/4/18 Outage in Progress SEL Generator Testing 9/4/18 – 9/20/18 Testing Complete
Accomplishments:
• Drawing duplication started. Mechanical package transmitted 10/24. Electrical & Controls packages transmitted.
• Outage began for unit on 9/4, GOC in place thru 8/2019.
• New stator halves arrived, uncrated by crews and stored in Long Lake HED. Paint repair pending by GE.
• Project Execution Plan signed Nov 2018, Schedule baseline 10/12/18
• Stator halves removed, turbine removed, distributors and wicket gates removed, old cabling and wiring removed
• Turbine & Generator bearings returned from vendor for rebabbitting.
• 3000 kcm and 1000 kcm cables installed, all other cables pulled into place and being terminated
• Paint repair of stator halves by GE to be completed by S&S Coatings
• FAT’s for turbine bearings and field poles completed in January 2019
Upcoming Activities
• Materials and equipment orders continue in anticipation of unit install work, receiving new parts and materials
• Continued progress in assembly, parts and pieces shipped off to vendors and arriving back at plant
• Assembly of equipment and materials is occurring Risks and Mitigation Strategies:
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning. - COMPLETED
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 7 of 16
Project Monthly Report – Jan 2019 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2018 Budget: $ 1,290,000 Approved Lifetime Budget: $8,200,000
Accrued 2018 to Date (through Dec): $ 1,243,252 Accrued Life to Date (through Dec): $4,785,331
2018 Estimate at Complete: $ 1,243,252 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system. The budget for the project remains at $8.2M. Unit 4’s construction began Sept 2018, outage thru Aug 2019
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 In progress Unit Outage Start 9/4/18 Outage in Progress SEL Generator Testing 9/4/18 – 9/20/18 Testing Complete
Accomplishments:
• Drawing duplication started. Mechanical package transmitted 10/24. Electrical & Controls packages transmitted.
• Outage began for unit on 9/4, GOC in place thru 8/2019.
• New stator halves arrived, uncrated by crews and stored in Long Lake HED. Paint repair pending by GE.
• Project Execution Plan signed Nov 2018, Schedule baseline 10/12/18
• Stator halves removed, turbine removed, distributors and wicket gates removed, old cabling and wiring removed
• Turbine & Generator bearings shipped to vendor for rebabbitting.
• 3000 kcm and 1000 kcm cables installed, all other cables pulled into place Upcoming Activities
• Paint repair of stator halves by GE to be completed by S&S Coatings beginning Jan 14
• Materials and equipment orders continue in anticipation of unit install work, receiving new parts and materials
• Continued progress in disassembly, parts and pieces shipped off to vendors
• FAT’s for turbine bearings and field poles to occur in January 2019
• Assembly of some equipment and materials is occurring Risks and Mitigation Strategies:
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning. - COMPLETED
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 8 of 16
Project Monthly Report – Dec 2018 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2018 Budget: $ 900,000 Approved Lifetime Budget: $8,200,000
Accrued 2018 to Date (through Nov): $ 830,089 Accrued Life to Date (through Nov): $4,290,943
2018 Estimate at Complete: $ 1,330,000 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system.
The budget for the project remains at $8.2M. Project was under budget due to progress payments on turbine bumped into 2017
Unit 4’s construction began Sept 2018, outage thru Aug 2019
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 In progress Unit Outage Start 9/4/18 Outage in Progress SEL Generator Testing 9/4/18 – 9/20/18 Testing Complete Accomplishments:
• Drawing duplication started. Mechanical package transmitted 10/24. Electrical & Controls packages transmitted. • Outage began for unit on 9/4, GOC in place thru 8/2019.
• New stator halves arrived, uncrated by crews and stored in Long Lake HED. Paint repair pending by GE.
• Project Execution Plan signed Nov 2018, Schedule baseline 10/12/18
• Stator halves removed, turbine removed, distributors and wicket gates removed, old cabling and wiring removed
• Turbine & Generator bearings shipped to vendor for rebabbitting.
• 3000 kcm and 1000 kcm cables installed Upcoming Activities
• Paint repair of stator halves by GE to be completed by S&S Coatings
• Materials and equipment orders continue in anticipation of unit install work
• Continued progress in disassembly, parts and pieces shipped off to vendors
• FAT’s for turbine bearings and field poles to occur in January 2019
• Assembly of some equipment and materials is occurring Risks and Mitigation Strategies:
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning. - COMPLETED
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 9 of 16
Project Monthly Report – Nov 2018 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2018 Budget: $ 900,000 Approved Lifetime Budget: $8,200,000
Accrued 2018 to Date (through Oct): $ 335,630 Accrued Life to Date (through Oct): $3,796,484
2018 Estimate at Complete: $ 900,000 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system.
The budget for the project remains at $8.2M. Project was under budget due to progress payments on turbine bumped into 2017
Unit 4’s construction began Sept 2018
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 In progress Unit Outage Start 9/4/18 Outage in Progress SEL Generator Testing 9/4/18 – 9/20/18 Testing Complete Accomplishments:
• Drawing duplication started. Mechanical package transmitted 10/24. Electrical package to transmit mid Nov • Outage began for unit on 9/4, GOC in place thru 8/2019.
• New stator halves arrived, uncrated by crews and stored in Long Lake HED. Paint repair pending by GE.
• Unit 4 project schedule completed with team, issued 10-12
• AUS performed diving to seal headgates on 9/24
• Stator halves removed, turbine removed, distributors and wicket gates removed, old cabling and wiring removed
• Turbine bearings shipped to vendor for rebabbitting – almost ready to return. Generator bearings shipped.
• 3000 kcm and 1000 kcm cables installed Upcoming Activities
• Continued drawing duplication with Cirrus Design. Electrical package with Drafting, Controls in review and to transmit after Thanksgiving
• Materials and equipment orders continue in anticipation of unit work
• Continued progress in disassembly, parts and pieces to ship off to vendors
• PEP complete – final signatures in progress Risks and Mitigation Strategies:
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning.
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 10 of 16
Project Monthly Report – Oct 2018 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2018 Budget: $ 900,000 Approved Lifetime Budget: $8,200,000
Accrued 2018 to Date (through Sept): $ 36,375 Accrued Life to Date (through Sept): $3,624,824
2018 Estimate at Complete: $ 900,000 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system.
The budget for the project remains at $8.2M. Project was under budget due to progress payments on turbine bumped into 2017
Unit 4’s construction began Sept 2018
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 In progress Unit Outage Start 9/4/18 Outage in Progress SEL Generator Testing 9/4/18 – 9/20/18 Testing Complete Accomplishments:
• Drawing duplication started • Outage began for unit on 9/4, GOC in place thru 8/2019.
• SEL destructive testing completed
• Concrete cutting completed 8/14 for U3 oil tank relocation
• New stator halves arrived, uncrated by crews and stored in Long Lake HED
• AUS performed diving to seal headgates on 9/24
• Stator top half removed, turbine removed, distributors and wicket gates removed old cabling and wiring
• Turbine bearings shipped to vendor for rebabbitting Upcoming Activities
• Continued drawing duplication with Cirrus Design. Electrical/Mechanical packages transmit by end Oct, Controls end Nov
• Materials and equipment orders continue in anticipation of unit work
• Continued work on Unit 4 project schedule with team
• Continued progress in disassembly, parts and pieces to ship off to vendors
• New 1500 mcm cables to be installed Risks and Mitigation Strategies:
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning.
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 11 of 16
Project Monthly Report – Sept 2018 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2018 Budget: $1,400,000 Approved Lifetime Budget: $8,200,000
Accrued 2018 to Date (through Aug): ($138,352) Accrued Life to Date (through Aug): $3,322,502
2018 Estimate at Complete: $1,400,000 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system.
The budget for the project remains at $8.2M. Project was under budget due to progress payments on turbine bumped into 2017
Unit 4’s construction began Sept 2018
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, stored in Long Lake HED Unit 4 Drawing Duplication October 2018 In progress Unit Outage Start 9/4/18 Outage in Progress SEL Generator Testing 9/4/18 – 9/20/18 Outage/Testing in Progress Accomplishments:
• Drawing duplication started • Outage began for unit on 9/4, GOC in place thru 8/2019.
• SEL on site 9/6 to review set up, verify points, and readiness, testing 9/10-9/13 and 9/17-9/20
• Concrete cutting completed 8/14 for U3 oil tank relocation
• Stator halves arrived, uncrated by crews and stored in Long Lake HED Upcoming Activities
• Continued drawing duplication with Cirrus Design
• Materials and equipment orders continue in anticipation of unit work
• AUS to perform diving to seal headgates on 9/24
• Continued work on Unit 4 project schedule with team
Risks and Mitigation Strategies:
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning.
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 12 of 16
Project Monthly Report – August 2018 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2018 Budget: $1,400,000 Approved Lifetime Budget: $8,200,000
Accrued 2018 to Date (through July): ($521,628) Accrued Life to Date (through July): $2,939,226
2018 Estimate at Complete: $1,400,000 Total Project Estimate at Complete: $8,200,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,200,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system.
The budget for the project remains at $7.5M. Project was under budget due to progress payments on turbine bumped into 2017
Unit 4’s construction will begin Sept 2018
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, store in Long Lake HED Unit 4 Drawing Duplication August 2018 On Track – in progress Unit Outage Start 9/4/18 On Track – GOC in place SEL Generator Testing 9/4/18 – 9/20/18 On Track – GOC in place Accomplishments:
• Drawing duplication started • Visited SEL to see test set up for generator testing, SEL met with Team on 8/1 to discuss testing process, safety and logistics
• Stator halves arrived, uncrated by crews and stored in Long Lake HED Upcoming Activities
• Continued drawing duplication with Cirrus Design
• SEL to visit site on 9/6 to review set up, verify points, and readiness
• Materials and equipment orders continue in anticipation of unit work
• Concrete cutting to occur 8/14 & 8/15 in preparation for U3 oil tank relocation before unit outage, Unit 3 GOC in place
• Outage for unit on 9/4, GOC in place.
• AUS to perform diving to seal headgates on 9/24
Risks and Mitigation Strategies:
• Following feedback from crews, adjusted GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning.
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 13 of 16
Project Monthly Report – July 2018 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2018 Budget: $1,400,000 Approved Lifetime Budget: $8,000,000
Accrued 2018 to Date (through June): ($645,432) Accrued Life to Date (through June): $2,848,078
2018 Estimate at Complete: $1,500,000 Total Project Estimate at Complete: $8,000,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,000,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system.
The budget for the project remains at $7.5M. Project was under budget due to progress payments on turbine bumped into 2017
Unit 4’s construction will begin Sept 2018
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 Complete, store in Long Lake HED Unit 4 Drawing Duplication August 2018 On Track – in progress Unit Outage Start 9/4/18 On Track – GOC in place SEL Generator Testing 9/4/18 – 9/21/18 On Track Accomplishments:
• Drawing duplication started • Visited SEL to see test set up for generator testing
• Stator halves arrived, uncrated by crews and stored in Long Lake HED Upcoming Activities
• Continued drawing duplication with Cirrus Design
• SEL continues to prepare for Unit 4 destructive testing, meeting on 8/1 with team at Little Falls to discuss testing, process, safety
• Materials and equipment orders continue in anticipation of unit work
• Concrete cutting to occur in preparation for oil tank relocation before unit outage
• Outage for unit on 9/4, GOC in place.
• Diving anticipated to seal headgates following completion of SEL testing
Risks and Mitigation Strategies:
• Following feedback from crews, considering adjusting GSU commissioning in Unit 4 schedule to allow for more time between GSU 2 commissioning and Unit 4 commissioning.
• Continue to work with Engineers and Crews to review and discuss the planned activities at weekly construction meetings, prepare work authorizations and procurements in advance of need, check all parts/equipment deliveries for proper part/size/damage, etc before installation dates. ON-GOING
Staff_PR_136 Attachment A Page 14 of 16
Project Monthly Report – June 2018 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2018 Budget: $1,400,000 Approved Lifetime Budget: $8,000,000
Accrued 2018 to Date (through May): ($664,627) Accrued Life to Date (through May): $2,796,227
2018 Estimate at Complete: $1,500,000 Total Project Estimate at Complete: $8,000,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,000,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, GSU, governor and control system.
The budget for the project remains at $7.5M. Project was under budget due to progress payments on turbine bumped into 2017
Unit 4’s construction will begin Sept 2018
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 In Progress Unit 4 Drawing Duplication August 2018 On Track Unit Outage Start 9/4/18 On Track SEL Generator Testing 9/4/18 – 9/21/18 On Track Accomplishments:
• Drawing duplication started • Visited SEL to see test set up for generator testing Upcoming Activities
• Continued drawing duplication
• Stator Halves arrived in Tacoma 6/6, anticipate delivery to Rhodes for unloading/storage week 6/11
• Avista crews to uncrate stator halves and store inside Long Lake plant upon removal of bulkheads
• SEL continues to prepare for Unit 4 destructive testing Risks and Mitigation Strategies:
• Following feedback from crews, considering adjusting GSU commissioning in Unit 4 schedule to allow for more time between GSU commissioning and Unit 4 commissioning.
Staff_PR_136 Attachment A Page 15 of 16
Project Monthly Report – May 2018 Little Falls Unit 4 Modernization – 20205045 Project Manager: Crystal Lewis
Approved 2018 Budget: $1,400,000 Approved Lifetime Budget: $8,000,000
Accrued 2018 to Date (through Apr): ($743,989) Accrued Life to Date (through Apr): $2,716,859
2018 Estimate at Complete: $1,500,000 Total Project Estimate at Complete: $8,000,000
Expected Transfer to Plant Date: Aug 2019 Expected Transfer to Plant Amount: $8,000,000
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
The scope remains fixed: Modernize the unit through replacement of turbine, generator, field poles, governor and control system.
The budget for the project remains at $7.5M. Project was under budget due to progress payments on turbine bumped into 2017
Unit 4’s construction is delayed until 2018. This has been approved by the project steering committee.
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Status/Performance Delivery of Generator June 2018 On Track Unit 4 Drawing Duplication August 2018 On Track Unit Outage Start September 2018 On Track SEL Generator Testing 9/4/18 – 9/21/18 On Track Accomplishments:
• Drawing duplication started
• Visited SEL to see test set up for generator testing Upcoming Activities
• Continued drawing duplication
• Risks and Mitigation Strategies:
•
Staff_PR_136 Attachment A Page 16 of 16
Alternatives Analysis Planning Phase Continued
Project Name: Cabinet Gorge Unit 2 Automation Replacement
Project ID: 30405082
1 Introduction
The project team, having defined the Functional Requirements of this project, has developed the
below Alternatives Analysis. Whereas the Functional Requirements define the project
deliverables, the Alternatives Analysis details how the requirements will be delivered by reviewing
alternatives and analyzing associated risks.
2 Performance Metrics
Specifically, this project will seek to improve in five major performance metrics:
• Communication improvements to the Unit subsystems via Ethernet.
• Improvement in programmability of devices (patching/updating for future
requirements/needs).
• Increased Unit availability as evidenced by an increase in the Equivalent Availability Factor
(EAF) over time.
• Reduced number of work orders related to critical maintenance issues.
• Meet NERC PRC-025 requirements for Generator Relay Loadability.
• Increase in Unit operating flexibility by incorporating AGC controls.
Alternatives Analysis Planning Phase Continued
3 Requirements and Methods Analysis
It should be noted that, in all cases, “doing nothing” is an option. However, in addition to any noted
risks, “doing nothing” will not meet the functional requirements of this project.
Requirement Alternative #1 Alternative #2 Alternative #3 Chosen Method for
Delivery
will be protected from
excessive heat, cold
and moisture.
will be insulated.
Barrel heaters will
be installed.
the powerhouse. RISK: Damage to
the unit due to
excessive heat,
cold and moisture
This is the most cost
effective way to protect
the generator. The
combined act of installing
both the barrel heaters
and insulating the lid
provides the most
efficient and effective
protected from
flooding.
monitoring
devices will be
installed.
Sump Pumps will
be installed.
RISK: doesn’t
provide visibility
of flooding during
loss of power.
may be possible
but, significant
cost savings
would not be
realized.
Installing pit level
monitoring devices and
sump pumps is the most
effective method for
keeping the turbine pit
Power Supply with
operational flexibility.
system and
Automatic
Generation
Control (AGC) will
be installed.
other of
blowdown or AGC
but, not both
AGC is required for Avista
to enter into the EIM
market which should
provide financial benefit.
Adding a blowdown
system to motor the unit
greatly enhances our
ability to respond to
frequency excursions and
meet Avista’s Frequency
Response Obligation.
Failing to meet these
requirement would have
negative operational and
financial impacts.
monitored in both the
X and Y positions and
related data captured
VibroSystM.
manufacturers. X and Y positions
for mechanical
protection but, do
VibroSystM is standard
equipment on the Clark Fork River Project
Alternatives Analysis Planning Phase Continued
analysis not create nuisance alarms.
Note: Add HMI inputs for
will provide indication
when racked out and
the fan(s) will provide
necessary cooling.
when racked out.
Replace the fan
motor and/or add
a redundant fan.
JRW: Providing
racked out
indication has
safety benefits
when conducting
maintenance.
• There is certainly
some
operational risk
if a second trip
coil is not
installed which is
the typical Avista
standard.
• Does the age
and condition of
the existing
breaker add a
significant
amount of
failure risk
compared to
replacing the
coil.
RISK: There is
some operational
risk of not
installing a second
trip coil which is
the typical Avista
standard.
breaker. Racked out indication has
safety benefits when
conducting maintenance.
Overheating the breaker
causes it to trip.
generator windings will
be monitored.
system will be
upgraded but, we
will not change
out the capacitive
probes.
ETHERNET CABLE
will require port
open on the corp
visual inspections. IRIS system provides
periodic monitoring
without a significant
outage which greatly
reduces the risk of an
unplanned outage due to
failure.
water system will be
refurbished.
control valves
coils generator air
housing coolers.
alternatives 1, 2 and 3
The current air coolers
are inefficient due to
their age. Cooling is
Alternatives Analysis Planning Phase Continued
generator health.
Without a well-
functioning system we
are susceptible to
unplanned outages.
information will be
collected in the
penstock to accurately
reflect real-time river
installed
Accusonic system.
ETERNET CABLE
methods for
measurement (i.e.
turbine flow
tables . . .).
products/systems RISK: Are the probes in
good working order?
They will need to be
tested.
control system will be
modernized to improve
efficiency and
frequency response.
Bradley
ControlLogix PLC
based Governor.
Switch, ports and
cables.
VIe governor based governor Avista standard
Familiarity with control
system programming and
operation greatly
enhance engineer and
technician’s ability to
troubleshoot and
exciter will be replaced
with a modern, digital
Switch, ports and
cables
Already purchased
(R-39696)
controls system will be
replaced with a
modern PLC that will
improve efficiency,
monitoring capabilities
and reliability.
Bradley
ControlLogix PLC
Switch, ports and
cables
Avista standard
The spare parts to the
Bailey are no longer in
production and the
product is not supported.
We are currently
operating with significant
mechanical/electrical
protection relays will
be replaced with
modern, multi-function
relays to meet NERC
requirements and
ensure electrical
of-the-art multi-
function SEL
relays.
ETHERNET CABLE
NAT ADDRESS
REQUIRED
(ETHUN FOR
Avista standard
Network will be reliable isolate Unit from
Alternatives Analysis Planning Phase Continued
control systems. equipment. network
will be modified to
provide data from Unit
2 to SCADA for System
Operations for
monitoring and AGC
control.
SCADA to identify
critical points and
configure control
system to deliver
information to
SCADA.
Network
Engineering –
similar to line 12
(SEL-3620 =
be upgraded to
revenue quality
standards to more
accurately monitor
power generation for
marketing purposes
and to help improve
the System Operator’s
area load control.
meter and
revenue grade
CTs.
ETHERENET CABLE
Avista Standard
Unit metering is critical to
participation in the EIM
market. Care should be
taken to evaluate the
location of the new CTs.
NOTE: have we evaluated
the current CTs for
compliance? Dave
Should probably plan to
temperature
monitoring and
alarming system will be
replaced to integrate
into the new PLC
control system.
with dual element
Resistive
Temperature
Devices (RTD) and
signal condition
equipment.
Potential
ETHERNET CABLE
RISK: Loss of
temperature
monitoring can
result in
unknowingly wipe
the bearing which
can cause
significant outage.
The dual element RTD
provides greater
reliability than the single
element units currently in
use.
Which device are we
going to purchase –
standard is no longer
provided to the thrust
bearings.
filtration system.
filtration machine.
RISK: higher
equipment and
Improved bearing life will
be realized with filtration
system.
bearing oil system will overhaul system; could result in Oil has an optimal
Alternatives Analysis Planning Phase Continued
heating, control,
indication and
alarming.
coolers. prevents the Unit
from starting
helps maintain the oil
temperature in this
optimal range which will
extend the life of the oil
in use. Provides
antiquated high lift
pump system oil to the
thrust bearings
including motors and
motor starters will be
replaced.
reliable
equipment with
enhanced
monitoring and
control
capabilities.
Damage to the Thrust
bearing would require a
significant outage.
Improving the monitoring
of the system greatly
reduces the chance of
oil pumps are
Woodward XX pumps
that have not been
completely overhauled
since installation in the
late 1950’s. Governor
pump and motor for
Unit 2 should be
overhauled during the
motor off-site to
American
Governor to be
overhauled
Governor train
one or more of
our mechanics in
the process
offsite.
4. Approval Signatures
Alexis had the following comments:
Regarding the VibroSystM, Alexis commented, “We have struggled with analyzing the data generated
from Vibrosystem and went another direction on the lower Spokane River.”
JRW - I agree with Alexis regarding VibroSystM. We are currently testing out another solution
for LF that could be used for CG as well. But I’d certainly defer to other that are more familiar
Alternatives Analysis Planning Phase Continued
with the product. I’ve always felt that we struggle maintaining the system, because we analyze
it remotely. We would need users to be more invested in the Vibrosystem product to fully take
advantage of its capabilities.
DJS - Dave – VibroSystM was never installed and was not necessary on the Spokane River plants
due to unit size and most of them being horizontal shaft.
Since I’m the designate SME for the VibroSystM for now, I plan of being able to use it for
preventive maintenance activities, however the equipment needs to be updated in order to
accomplish this. We are also considering a duplicative bearing runout system – VibroSystM for
remote (CORP network monitoring) and a second set of sensors wired directly to the Unit PLC
(GEN Network)
AA – Sounds like progress, I’m only concerned we have an event and are unable to process and analyze
the data.
Regarding the generator breaker indication, Alexis asked, “Was remove rackout capability considered?”
JRW – perhaps we didn’t describe this correctly; we are simply looking to add “rackout”
indication. Currently, the generator breaker has no status to the HMI system of racked in or racked out.
AA – so there will not be new switchgear, simply added racked out indication? Make sure the indication
is accurate when the breaker is racked out.
Regarding Accusonic, Alexis commented, “Visit why flow monitoring was not installed at LF.”
JRW - I’m not familiar with the reasoning, but there are requirements at LF for reporting flow to
the tribes. We use a look up table based on test data to provide flow indication. I believe an accurate
and reliable flow meter would be preferred.
AA- An accurate and reliable system was difficult to find 2 years ago. We determined it wasn’t worth the
cost.
Regarding kidney loop filtration system, Alexis commented, “I imagine this addresses the oil
temperature issues on Unit 1.”
DJS - This is also the same system that was installed at Little Falls with the unit upgrades.
BZN - The kidney loop oil filtration is for the Thrust-tub oil that is specific to Unit 2. This oil is
pumped from the main sump during commissioning, and then valves are closed and that
quantity of oil will live in the Thrust tub (Oil pot on the drawings) for the duration of that
operation cycle. The kidney loop oil filter will run all the time, cycling the oil in the tub through
dual stage filtration to remove any contaminants that build up in the oil as the unit runs. The oil
inside the thrust tub is cooled by copper heat exchangers that are inside the thrust tub near the
Alternatives Analysis Planning Phase Continued
thrust bracket and are supplied cold river water via the cooling water valves, the replacement of
which (Both valves and the heat exchanger coils) is/are also part of this project.
The oil temperature issues on unit 1 are unique to the Kaplan design, as unit 2 does not supply
pressurized oil down the spinning shaft. That being said, as part of the unit 1 failure and repair,
a kidney loop oil filter with an included orifice heating device was installed on the main sump
that provides oil for unit 1 Kaplan operation. Heat trace was also added to the associated piping
and accumulator as well as insulation to keep this oil at a controlled viscosity during operation.
AA – Sounds good!
ID Task Name Duration Start Finish % Complete
1 CGU2 Automation Upgrade Project 400.7 days?Thu 6/21/18 Mon 6/1/20 88%
2 ConstructionTransmittal 0.8 daysWed 7/18/18 Wed 7/18/18 100%
3 Review & Yellow Line Prints (W/O# 1005022790)4 mons Mon 11/26/18Fri 4/12/19 100%
4 move PPT from Noxon to Cabinet 0.8 daysFri 3/15/19 Fri 3/15/19 100%
5 Electrical Procurement 24 days Mon 1/7/19 Fri 2/15/19 100%
6 Procure CTs 0.8 daysMon 1/7/19 Mon 1/7/19 100%
7 Procure PTs 0.8 daysMon 1/7/19 Mon 1/7/19 100%
8 Procure Cable Tray & Cable 24 days Mon 1/7/19 Fri 2/15/19 100%
9 Protection & SCADA 80 days Mon 1/7/19 Fri 5/24/19 100%
14 Controls & Integration 39.2 daysTue 12/18/18 Fri 2/22/19 99%
15 PLC Program 39.2 daysTue 12/18/18 Fri 2/22/19 100%
16 HW I/O 39.2 daysTue 12/18/18 Fri 2/22/19 100%
17 Auxiliairies 39.2 daysTue 12/18/18 Fri 2/22/19 100%
18 Master 39.2 daysTue 12/18/18 Fri 2/22/19 100%
19 Start 39.2 daysTue 12/18/18 Fri 2/22/19 100%
20 Governor Control 39.2 daysTue 12/18/18 Fri 2/22/19 100%
21 Governor - Gate 39.2 daysTue 12/18/18 Fri 2/22/19 100%
22 Governor - MW 39.2 daysTue 12/18/18 Fri 2/22/19 100%
23 Governor - Flow 39.2 daysTue 12/18/18 Fri 2/22/19 100%
24 Governor - Motor 39.2 daysTue 12/18/18 Fri 2/22/19 100%
25 Governor AGC 0.8 daysTue 12/18/18 Tue 12/18/18 100%
26 AVR Control 39.2 daysTue 12/18/18 Fri 2/22/19 100%
27 AVR - Volt 39.2 daysTue 12/18/18 Fri 2/22/19 100%
28 AVR - Mvar 39.2 daysTue 12/18/18 Fri 2/22/19 100%
29 Trip 39.2 daysTue 12/18/18 Fri 2/22/19 100%
30 Stop 39.2 daysTue 12/18/18 Fri 2/22/19 100%
31 HMI I/O 39.2 daysTue 12/18/18 Fri 2/22/19 100%
32 Unit OIT Program 39.2 daysTue 12/18/18 Fri 2/22/19 100%
33 Governor OIT Program 39.2 daysTue 12/18/18 Fri 2/22/19 100%
34 HMI Program 39.2 daysTue 12/18/18 Fri 2/22/19 90%
35 Integration Points List 39.2 daysTue 12/18/18 Fri 2/22/19 100%
36 Networking 0.8 daysTue 1/8/19 Tue 1/8/19 100%
37 0.8 daysTue 1/8/19 Tue 1/8/19 100%
38 SCADA 20 days?Tue 5/28/19 Mon 7/1/19 0%
39 Prepare SCADA Design Configuration 0.8 days?Tue 5/28/19 Tue 5/28/19 0%
40 DB Modeled 0%
41 Checkout Sheet Distributed 0%
42 DB Updated/Deployed 0%
12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/2 3/9 3/16 3/23 3/30
December January February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: CG Automation Constru
Date: Tue 2/4/20
ID Task Name Duration Start Finish % Complete
43 Displays Updated 0%
44 Update SCADA/AGC Model 5 wks Tue 5/28/19 Mon 7/1/19 0%
45 Pre-Work - Shop 48 days?Thu 6/21/18 Wed 9/12/18 98%
46 Electrical Construction 28 days Mon 12/17/18Fri 2/1/19 100%
52 PCM Checkout (W/O#10050033414)43.2 daysWed 1/16/19 Mon 4/1/19 97%
53 Upgrade firmware on the PLCs 0.8 daysWed 1/16/19 Wed 1/16/19 100%
54 Upgrade versions on OITs 0.8 daysWed 1/16/19 Wed 1/16/19 100%
55 Solidify the network Ips 0.8 daysWed 1/16/19 Wed 1/16/19 100%
56 Cable up the network and set all Ips 0.8 daysWed 1/16/19 Wed 1/16/19 100%
57 Wire Check & Terminal Test U2C1 1.6 daysWed 1/16/19 Fri 1/18/19 100%
58 Wire Check & Terminal Test U2M1 1.6 daysFri 1/18/19 Tue 2/5/19 100%
59 Wire Check & Terminal Test U2P1 1.6 daysTue 1/22/19 Wed 2/6/19 100%
60 Wire Check & Terminal Test U2GOV 1.6 daysWed 2/6/19 Fri 2/8/19 100%
61 Setup & Pre-Test U2 Switch 1.6 daysThu 2/7/19 Mon 2/11/19 100%
62 Setup & Pre-Test U2 DLR Ring 1.6 daysMon 2/11/19 Tue 2/12/19 100%
63 Setup & Pre-Test SEL700G(1) SCADA DNP 1.6 daysWed 2/13/19 Thu 2/14/19 100%
64 Setup & Pre-Test SEL700G(1) U2 PLC DNP 1.6 daysFri 2/15/19 Mon 2/18/19 100%
65 Setup & Pre-Test SEL700G(2) SCADA DNP 1.6 daysTue 2/19/19 Wed 2/20/19 100%
66 Setup & Pre-Test SEL700G(2) U2 PLC DNP 1.6 daysThu 2/21/19 Fri 2/22/19 100%
67 Setup & Pre-Test SEL351 SCADA DNP 1.6 daysMon 2/25/19 Tue 2/26/19 100%
68 Setup & Pre-Test SEL351 U2 PLC DNP 1.6 daysWed 2/27/19 Thu 2/28/19 100%
69 Setup & Pre-Test SEL735 SCADA DNP 1.6 daysFri 3/1/19 Mon 3/4/19 100%
70 Setup & Pre-Test SEL735 U2 PLC DNP 1.6 daysTue 3/5/19 Wed 3/6/19 100%
71 Setup & Pre-Test SMP SCADA 1.6 daysThu 3/7/19 Fri 3/8/19 100%
72 Setup & Pre-Test Governor OIT 2.4 daysMon 3/11/19 Wed 3/13/19 100%
73 Setup & Pre-Test U2 OIT 2.4 daysThu 3/14/19 Mon 3/18/19 100%
74 Setup & Pre-Test U2 HMI 8 days Tue 3/19/19 Mon 4/1/19 100%
75 Acceptance Testing 20 days Tue 4/2/19 Mon 5/6/19 80%
76 PLC Program Checkout 14.4 daysTue 4/2/19 Thu 4/25/19 72%
77 HW I/O 0.8 daysTue 4/2/19 Tue 4/2/19 100%
78 Auxiliairies 0.8 daysWed 4/3/19 Wed 4/3/19 100%
79 Master 0.8 daysThu 4/4/19 Thu 4/4/19 100%
80 Start 0.8 daysFri 4/5/19 Fri 4/5/19 100%
81 Sync 0.8 daysMon 4/8/19 Mon 4/8/19 100%
82 Governor Control 0.8 daysTue 4/9/19 Tue 4/9/19 0%
83 Governor - Gate 0.8 daysWed 4/10/19 Wed 4/10/19 0%
84 Governor - MW 0.8 daysThu 4/11/19 Thu 4/11/19 0%
85 Governor - Flow 0.8 daysFri 4/12/19 Fri 4/12/19 0%
12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/2 3/9 3/16 3/23 3/30
December January February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: CG Automation Constru
Date: Tue 2/4/20
ID Task Name Duration Start Finish % Complete
86 Governor - Motor 0.8 daysMon 4/15/19 Mon 4/15/19 0%
87 AVR Control 0.8 daysTue 4/16/19 Tue 4/16/19 100%
88 AVR - Volt 0.8 daysWed 4/17/19 Wed 4/17/19 100%
89 AVR - Mvar 0.8 daysThu 4/18/19 Thu 4/18/19 100%
90 Trip 0.8 daysFri 4/19/19 Fri 4/19/19 100%
91 Stop 1.6 daysMon 4/22/19 Tue 4/23/19 100%
92 HMI I/O 1.6 daysWed 4/24/19 Thu 4/25/19 100%
93 Unit OIT Program 1.6 daysFri 4/26/19 Mon 4/29/19 100%
94 Governor OIT Program 1.6 daysTue 4/30/19 Wed 5/1/19 100%
95 HMI Program 2.4 daysThu 5/2/19 Mon 5/6/19 100%
96 Transport Panels to Cabinet 1 day Tue 6/18/19 Wed 6/19/19 100%
107 Pre-Work Plant Thu 6/21/18 98%
108 Mechanical 4.8 daysMon 1/28/19 Mon 2/4/19 100%
109 transport PPT from Noxon to Cabinet 1.6 daysWed 1/30/19 Thu 1/31/19 100%
110 Blowdown 4.8 daysMon 1/28/19 Mon 2/4/19 100%
111 Build Level Sending Sensor 3.2 daysMon 1/28/19 Thu 1/31/19 100%
112 Install valves 1.6 daysFri 2/1/19 Mon 2/4/19 100%
113 Electrical Thu 6/21/18 97%
114 Blowdown Thu 6/21/18 75%
115 Core drill barrel 0.8 daysWed 1/16/19 Wed 1/16/19 100%
116 Core drilling for panels 4 days Mon 1/21/19 Fri 1/25/19 100%
117 Set U2P1 4 days Wed 6/19/19 Wed 6/26/19 100%
118 Set U2C1/M1 4 days Wed 6/26/19 Wed 7/3/19 100%
119 Set PPT 4 days Wed 7/3/19 Thu 7/11/19 100%
120 Cable tray around barrel 4 days Mon 2/18/19 Fri 2/22/19 100%
121 Primary Connections 4 days Mon 1/28/19 Fri 2/1/19 100%
122 VibroSystM 8 days Mon 2/11/19 Fri 2/22/19 90%
123 Unit2 Upgrade Pre-Work Vibro PCM (W/O# 1005022711)0.8
days
Thu 6/21/18 Thu 6/21/18 100%
124 Turbine Sump Pumps 2 days Thu 6/21/18 Mon 6/25/18 100%
125 build control box 2 days Thu 6/21/18 Mon 6/25/18 100%
126 install control box 1 day Thu 6/21/18 Fri 6/22/18 100%
127 Wire control box 1 day Thu 6/21/18 Fri 6/22/18 100%
128 OUTAGE 27 wks Tue 9/3/19 Fri 3/13/20 59%
129 Level 2 Clearance Issued 0.8 daysTue 9/3/19 Wed 9/4/19 100%
130 Unit 2 control clearance issued 0.8 daysWed 9/4/19 Thu 9/5/19 100%
131 Mechanical 60 days?Tue 7/30/19 Tue 11/12/19 86%
132 Governor 8.8 daysTue 9/3/19 Wed 9/18/19 100%
12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/2 3/9 3/16 3/23 3/30
December January February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: CG Automation Constru
Date: Tue 2/4/20
ID Task Name Duration Start Finish % Complete
140 Governor Oil Pump 29.5 days?Tue 7/30/19 Thu 9/19/19 100%
144 Cooling Water 4.8 daysTue 11/5/19 Tue 11/12/19 100%
149 Turbine Pit Sump Pumps 1.6 daysThu 11/7/19 Fri 11/8/19 0%
150 modify piping 1.6 daysThu 11/7/19 Fri 11/8/19 0%
151 Level sensor /alarms 0.8 daysThu 11/7/19 Thu 11/7/19 0%
152 install flow meters 0.8 daysThu 11/7/19 Thu 11/7/19 0%
153 Turbine Bearing Flow & Pressure Xducer plumbing 2.4 daysTue 9/3/19 Thu 9/5/19 90%
154 Install sump level transducer 0.8 daysTue 7/30/19 Tue 7/30/19 0%
155 Electrical 4 days Tue 9/3/19 Tue 9/10/19 100%
157 Generator Breaker 32 days Mon 11/11/19Thu 1/9/20 100%
163 PPT 4 days Fri 9/20/19 Fri 9/27/19 100%
166 Exciter 16.8 daysFri 9/27/19 Mon 10/28/19 100%
173 Field Ground Protection 50.5 daysWed 10/9/19 Fri 1/10/20 92%
174 Install 1.6 daysWed 10/9/19 Mon 1/6/20 100%
175 Field connections 1.6 daysTue 1/7/20 Wed 1/8/20 100%
176 ground brush 0.8 daysThu 1/9/20 Thu 1/9/20 50%
177 power and fiber 0.8 daysFri 1/10/20 Fri 1/10/20 100%
178 Partial Discharge 4 days Fri 11/1/19 Wed 1/8/20 75%
179 Remove Vib/Temp Monitoring Panel 0.8 daysFri 11/8/19 Mon 11/11/19 100%
180 CT&PT 36.1 daysMon 11/11/19Fri 1/17/20 99%
181 New Wye Point cTs (6)2.4 daysMon 11/11/19Wed 12/4/19 100%
182 New U2 Switchgear CTs (6)2.4 daysMon 1/6/20 Wed 1/8/20 100%
183 Remove old 13.8kV A Bus PT 8 days Mon 1/6/20 Fri 1/17/20 100%
184 Remove Existing B-phase Bus Sync PT 1 day Mon 1/6/20 Tue 1/7/20 100%
185 U1 CO2 System Removal 1 day Tue 1/7/20 Wed 1/8/20 90%
186 U1 CT1 Replace CTs Switchgear - Bus Side 1 day Wed 1/8/20 Thu 1/9/20 100%
187 U1 CT2 Replace CTs Breaker 1 day Thu 1/9/20 Fri 1/10/20 100%
188 U1 CT3 Replace CTs Switchgear - Generator Side 1 day Mon 1/13/20 Tue 1/14/20 100%
189 U1 CT4 - CT5 Replace Neutral CTs 1 day Tue 1/14/20 Wed 1/15/20 100%
190 U1 Replace Generator PTs 1 day Wed 1/15/20 Thu 1/16/20 100%
191 U2 CT1 Replace CTs Switchgear - Bus Side 1 day Thu 1/16/20 Fri 1/17/20 100%
192 Turbine Bearing Flow and Pressure devices - wire 2.4 daysMon 1/6/20 Wed 1/8/20 100%
193 Generator Lockout (86G) - wiring 0.8 daysTue 12/3/19 Tue 12/3/19 100%
194 Generator Lockout (86GD) - wiring 0.8 daysTue 12/3/19 Tue 12/3/19 100%
195 Communications - IRIG & Ethernet 1.6 daysMon 11/11/19Wed 11/13/19 100%
196 AC Turbine Sump Pumps 4 days Mon 1/6/20 Fri 1/10/20 50%
197 AC & DC Turbine Oil Pumps 112.8 daysWed 6/19/19 Mon 6/1/20 1%
198 Governor 9.6 daysFri 11/15/19 Thu 12/5/19 100%
mechanic
mechanic
mechanic
1/9
10/28
1/10
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
1/17
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
12/5
12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/2 3/9 3/16 3/23 3/30
December January February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: CG Automation Constru
Date: Tue 2/4/20
ID Task Name Duration Start Finish % Complete
211 U2PIT Jbox wiring 4 days Tue 12/3/19 Mon 12/9/19 100%
212 Cooling Water 6.4 daysFri 9/20/19 Tue 10/1/19 100%
218 Jacking Oil Pump wire 1.6 daysMon 1/6/20 Tue 1/7/20 100%
219 High Lift Oil Pump wire 1.6 daysWed 1/8/20 Thu 1/9/20 100%
220 Blowdown 92.7 daysWed 6/19/19 Tue 12/3/19 71%
221 Level tube coating 0.8 daysWed 6/19/19 Wed 6/19/19 0%
222 Panel U2BD wire 1.6 daysMon 9/30/19 Tue 10/1/19 100%
223 Wire 3" valve 0.8 daysMon 9/30/19 Mon 9/30/19 100%
224 Wire 6" valve 0.8 daysMon 9/30/19 Mon 9/30/19 100%
225 Wire Level Sensor 0.8 daysMon 9/30/19 Mon 9/30/19 0%
226 improved barrel lighting (safety)0.8 daysTue 12/3/19 Tue 12/3/19 100%
227 Remedial Action Scheme (RAS) - Panel 9F wire 0.4 daysMon 12/9/19 Mon 12/9/19 100%
228 13.8kV Bus Differential (87B) - Panel BP1 wire 0.4 daysTue 12/3/19 Tue 12/3/19 100%
229 Breaker Failure (86BF) - Panel 8 wire 1.6 daysTue 12/3/19 Thu 12/5/19 100%
230 Flow Meter (Accusonic) wire 2.4 daysTue 9/3/19 Fri 9/6/19 100%
231 Bailey DCS 2.4 daysTue 9/3/19 Fri 9/6/19 100%
235 PCM Checkout 103.9 days?Thu 7/25/19 Wed 1/29/20 84%
236 Remove old Controls (Panel2 4F & 4R) (W/O#1005022544)4 days Tue 9/3/19 Tue 9/10/19 100%
237 Generator Breaker (W/O#1005022509)25.6 daysThu 7/25/19 Mon 9/9/19 98%
238 wire check 0.8 daysThu 7/25/19 Thu 7/25/19 100%
239 Ratio, SAT, Polarity CTs (3)0.8 daysFri 7/26/19 Fri 7/26/19 100%
240 Test Trip circuit 0.8 daysFri 9/6/19 Fri 9/6/19 90%
241 Test Close circuit 0.8 daysMon 9/9/19 Mon 9/9/19 100%
242 PPTs (W/O#1005022650)19.6 daysFri 8/2/19 Fri 9/6/19 100%
248 Exciter (W/O# 1005022869)12 days Wed 10/9/19 Wed 10/30/19 100%
261 Field Ground Protection -Wire check 0.8 daysMon 1/13/20 Mon 1/13/20 100%
262 Field Ground Protection -Test SEL2664 Alarm & Trip 0.8 daysTue 1/14/20 Tue 1/14/20 100%
263 Panel U2P1 (W/O# 1005023103)8 days Tue 9/10/19 Tue 9/24/19 68%
264 wire check 1.6 daysTue 9/10/19 Thu 9/12/19 100%
265 Power supply & IO circuits 1.6 daysThu 9/12/19 Mon 9/16/19 100%
266 Test Protection cicuits 1.6 daysMon 9/16/19 Wed 9/18/19 90%
267 Test SEL-3400 1.6 daysWed 9/18/19 Fri 9/20/19 0%
268 Test Sync circuit 1.6 daysFri 9/20/19 Tue 9/24/19 50%
269 Panel U2C1 (W/O# 1005023040)8 days Tue 9/24/19 Tue 10/8/19 91%
270 wire check 0.8 daysTue 9/24/19 Wed 9/25/19 100%
271 Power supply & IO circuits 0.8 daysWed 9/25/19 Thu 9/26/19 100%
272 Test PLC20 DI1 (see Hardware I/O Sheet)1.6 daysThu 9/26/19 Mon 9/30/19 95%
electric Shop
electric Shop
electric Shop
12/3
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
electric Shop
1/29
10/30
PCM Shop
PCM Shop
10/8
PCM Shop
12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/2 3/9 3/16 3/23 3/30
December January February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: CG Automation Constru
Date: Tue 2/4/20
ID Task Name Duration Start Finish % Complete
273 Test PLC20 DI2 (see Hardware I/O Sheet)0.8 daysMon 9/30/19 Tue 10/1/19 90%
274 Test PLC20 DI3 (see Hardware I/O Sheet)0.8 daysTue 10/1/19 Wed 10/2/19 70%
275 Test PLC20 DO1 (see Hardware I/O Sheet)0.8 daysWed 10/2/19 Thu 10/3/19 100%
276 Test PLC20 AI1 (see Hardware I/O Sheet)0.8 daysThu 10/3/19 Fri 10/4/19 80%
277 Test PLC20 AI2 (see Hardware I/O Sheet)0.8 daysFri 10/4/19 Mon 10/7/19 70%
278 Test PLC20 AI3 (see hardware I/O Sheet)0.8 daysTue 9/24/19 Wed 9/25/19 100%
279 Test PLC20 AO1 (see Hardware I/O Sheet)0.8 daysMon 10/7/19 Tue 10/8/19 100%
280 Panel U2M1 (W/O# 1005042376)8 days Tue 10/8/19 Tue 10/22/19 99%
281 wire check 0.8 daysTue 10/8/19 Wed 10/9/19 100%
282 Power supply & IO circuits 0.8 daysWed 10/9/19 Thu 10/10/19 100%
283 Test PLC22 AI1 (see Hardware I/O Sheet)0.8 daysThu 10/10/19 Fri 10/11/19 100%
284 Test PLC22 AI2 (see Hardware I/O Sheet)0.8 daysFri 10/11/19 Mon 10/14/19 100%
285 Test PLC22 AI3 (see Hardware I/O Sheet)0.8 daysMon 10/14/19Tue 10/15/19 100%
286 Test PLC22 AI4 (see Hardware I/O Sheet)0.8 daysTue 10/15/19 Wed 10/16/19 100%
287 Test PLC22 AI5 (see Hardware I/O Sheet)0.8 daysWed 10/16/19Thu 10/17/19 100%
288 Test PLC22 AI6 (see Hardware I/O Sheet)0.8 daysThu 10/17/19 Fri 10/18/19 100%
289 Test PLC22 AI7 (see Hardware I/O Sheet)0.4 daysFri 10/18/19 Mon 10/21/19 100%
290 Test PLC22 AI8 (see Hardware I/O Sheet)0.4 daysMon 10/21/19Mon 10/21/19 100%
291 Test PLC22 DO1 (see Hardware I/O Sheet)0.4 daysMon 10/21/19Tue 10/22/19 100%
292 Test PLC22 DYM1 (see Hardware I/O Sheet)0.4 daysTue 10/22/19 Tue 10/22/19 80%
293 VibroSystems - Test I/O to PLC20 (W/O# 1005042456)3.2 daysMon 11/11/19Fri 11/15/19 0%
294 Status & Warning Lights (W/O# 1005042502)0.8 daysTue 12/10/19 Tue 12/10/19 100%
297 CT&PT (W/O# 1005042605)4 days Thu 11/21/19 Mon 12/2/19 90%
298 Ratio, Sat & Pol check CT1 (3)0.8 daysThu 11/21/19 Fri 11/22/19 100%
299 Ratio, Sat & Pol check CT3 (3)0.8 daysFri 11/22/19 Mon 11/25/19 100%
300 Ratio, Sat & Pol check CT4 (3)0.8 daysMon 11/25/19Tue 11/26/19 100%
301 Ratio, Sat & Pol check CT5 (3)0.4 daysTue 11/26/19 Wed 11/27/19 100%
302 Ratio and test Gen PTs (3)0.4 daysWed 11/27/19Wed 11/27/19 100%
303 Verify Generator phasing 0.4 daysWed 11/27/19Mon 12/2/19 100%
304 Test Wye Point grounding transformer 0.4 daysMon 12/2/19 Mon 12/2/19 0%
305 Master Start/Stop Circuit (W/O# 1005042736)3.2 daysTue 9/10/19 Mon 9/16/19 90%
306 wire check 1.6 daysTue 9/10/19 Thu 9/12/19 100%
307 test 1.6 daysThu 9/12/19 Mon 9/16/19 80%
308 Generator Lockout (86G) (W/O# 1005042806)0.8 daysTue 10/22/19 Wed 10/23/19 100%
311 Generator Lockout (86GD) (W/O# 1005042833)0.8 daysWed 10/23/19Thu 10/24/19 100%
312 wire check 0.4 daysWed 10/23/19Thu 10/24/19 100%
313 test 0.4 daysThu 10/24/19 Thu 10/24/19 100%
314 Comm Network (W/O# 1005042878)8 days Wed 11/13/19Wed 11/27/19 100%
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
10/22
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
12/10
12/2
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
10/23
10/24
PCM Shop
PCM Shop
11/27
12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/2 3/9 3/16 3/23 3/30
December January February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: CG Automation Constru
Date: Tue 2/4/20
ID Task Name Duration Start Finish % Complete
322 AC Turbine Sump Pump 1 - Test (W/O# 1005042918)1.6 daysMon 1/13/20 Tue 1/14/20 100%
323 AC Turbine Sump Pump 2 - Test (W/O# 1005042918)0.8 daysMon 1/13/20 Mon 1/13/20 100%
324 AC Turbine Sump Pump 3 - Test (W/O# 1005042918)0.8 daysMon 1/13/20 Mon 1/13/20 100%
325 U2PIT Terminal Box - wire check (W/O# 1005042947)0.8 daysTue 12/10/19 Tue 12/10/19 100%
326 AC Turbine Oil Pump (W/O# 1005043040)2 days Tue 1/7/20 Thu 1/9/20 80%
327 wire check & Test 0.8 daysTue 1/7/20 Tue 1/7/20 100%
328 Test Brg Oil Flow alarm (80T-1)0.4 daysWed 1/8/20 Wed 1/8/20 0%
329 Test status to PLC20 0.4 daysWed 1/8/20 Wed 1/8/20 100%
330 Test pressure switch (63T)0.4 daysThu 1/9/20 Thu 1/9/20 100%
331 DC Turbine Oil Pump (W/O# 1005051075)1.6 daysTue 1/7/20 Wed 1/8/20 75%
332 wire check & Test 0.8 daysTue 1/7/20 Tue 1/7/20 100%
333 Test Brg Oil Flow alarm (80T-2)0.4 daysWed 1/8/20 Wed 1/8/20 0%
334 Test status to PLC20 0.4 daysWed 1/8/20 Wed 1/8/20 100%
335 Governor (W/O# 1005051193)16 days Thu 12/5/19 Mon 1/6/20 92%
336 Wire check U2GV 1.6 daysThu 12/5/19 Mon 12/9/19 100%
337 Test & Calibrate Gate Feedback (2)1.6 daysMon 12/9/19 Wed 12/11/19 80%
338 Test & Calibrate LVDT 0.8 daysWed 12/11/19Thu 12/12/19 100%
339 wire check and calibrate pressure transducers, brake air transducer and
meter
1 day Thu 12/5/19 Mon 12/9/19 100%
340 Wire check & test Speed sensors (ZVPUx2)0.8 daysThu 12/12/19 Fri 12/13/19 50%
341 Wire check & test Speed sensors (PTx2)0.8 daysFri 12/13/19 Mon 12/16/19 50%
342 Wire check & test U2GV power supply 0.8 daysMon 12/16/19Tue 12/17/19 100%
343 Wire check & test brakes 0.8 daysTue 12/17/19 Wed 12/18/19 100%
344 Wire check & test local controls 0.8 daysWed 12/18/19Thu 12/19/19 100%
345 Wire check & test I/O to U2P1 & U2M1 0.8 daysThu 12/19/19 Fri 12/20/19 100%
346 Wire check & test pressure switches 0.8 daysFri 12/20/19 Mon 12/23/19 100%
347 Calibrate & test pressure switches 0.8 daysMon 12/23/19Thu 12/26/19 100%
348 Wire check & test mechanical overspeed sw's 0.8 daysThu 12/26/19 Fri 12/27/19 80%
349 Wire check & test PLC21 HSC (2)0.8 daysFri 12/27/19 Mon 12/30/19 100%
350 Wire check & test PLC21 AI1 0.8 daysMon 12/30/19Tue 12/31/19 100%
351 Wire check & test PLC21 AI2 0.8 daysTue 12/31/19 Wed 1/1/20 100%
352 Wire check & test PLC21 AO1 0.8 daysWed 1/1/20 Thu 1/2/20 100%
353 Wire check & test PLC21 DI1 0.8 daysThu 1/2/20 Fri 1/3/20 100%
354 Wire check & test PLC21 DO1 0.8 daysFri 1/3/20 Mon 1/6/20 100%
355 Cooling Water (W/O# 1005051877)4 days Wed 10/2/19 Tue 10/8/19 80%
356 Wire check U2CW panel 0.8 daysWed 10/2/19 Wed 10/2/19 100%
357 Test Thrust Brg CW flow meter 0.8 daysThu 10/3/19 Thu 10/3/19 100%
358 Test Thrust Brg CW flow switch 0.8 daysFri 10/4/19 Fri 10/4/19 100%
PCM Shop
PCM Shop
PCM Shop
PCM Shop
1/9
PCM Shop
PCM Shop
PCM Shop
PCM Shop
1/8
PCM Shop
PCM Shop
PCM Shop
1/6
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/2 3/9 3/16 3/23 3/30
December January February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: CG Automation Constru
Date: Tue 2/4/20
ID Task Name Duration Start Finish % Complete
359 Test Packing water flow switch 0.8 daysMon 10/7/19 Mon 10/7/19 0%
360 Test Thrust CW Control valve switch 0.4 daysTue 10/8/19 Tue 10/8/19 100%
361 Test Stator CW Control valve switch 0.4 daysTue 10/8/19 Tue 10/8/19 100%
362 Jacking Oil Pump (W/O# 1005051916)0.8 daysWed 1/8/20 Wed 1/8/20 50%
363 Wire check 0.4 daysWed 1/8/20 Wed 1/8/20 100%
364 test status to PLC20 0.4 daysWed 1/8/20 Wed 1/8/20 0%
365 High Lift Oil Pump (W/O# 1005056394)0.8 daysFri 1/10/20 Fri 1/10/20 50%
366 wire check 0.4 daysFri 1/10/20 Fri 1/10/20 100%
367 test status to PLC20 0.4 daysFri 1/10/20 Fri 1/10/20 0%
368 Blowdown (W/O# 1005056429)52.1 daysFri 10/4/19 Thu 1/9/20 96%
369 wire check Panel U2BD 0.8 daysTue 1/7/20 Tue 1/7/20 100%
370 Test 6" valve control & feedback 0.8 daysWed 1/8/20 Wed 1/8/20 100%
371 Test 3" valve control & feedback 0.4 daysThu 1/9/20 Thu 1/9/20 100%
372 Calibrate & test Bindicator 0.4 daysFri 10/4/19 Thu 1/9/20 75%
373 Remedial Action Scheme (RAS) (W/O# 1005056483)0.8 daysThu 12/5/19 Fri 12/6/19 100%
377 13.8KV Bus Differnetial (87B) - Test CTs to SEL-487B (W/O# 1005056523)0.8
days
Fri 12/6/19 Mon 12/9/19 100%
378 Breaker Failure (86BF) - Test Trip & Block close circuits (W/O# 1005056554)0.8
days
Mon 12/9/19 Tue 12/10/19 0%
379 Bus Lockout Auxiliaries (86M,94M) (W/O# 1005056594)0.8
days
Tue 12/10/19 Wed 12/11/19 100%
382 Flow Meter (Accusonic) (W/O# 1005056639)5.5 daysTue 9/3/19 Wed 9/11/19 71%
383 Build Scaffolding 5 days Tue 9/3/19 Wed 9/11/19 100%
384 Penstock Flowmeter sensor alignment 0.8 daysTue 9/3/19 Tue 9/3/19 100%
385 Test I/O 1.6 daysFri 9/6/19 Tue 9/10/19 0%
386 Test Ethernet comms 0.8 daysTue 9/10/19 Wed 9/11/19 0%
387 Bailey DCS - Test Bailey Module Bus (W/O# 1005056661)0.8
days
Fri 9/6/19 Mon 9/9/19 100%
388 HMI (W/O# 1005069678)3.2 daysThu 10/24/19 Wed 10/30/19 50%
389 Test HMI (Plant)1.6 daysThu 10/24/19 Mon 10/28/19 50%
390 Test HMI (GCC)1.6 daysMon 10/28/19Wed 10/30/19 50%
391 SCADA (W/O# 1005069718)48.8 days?Wed 10/30/19Wed 1/29/20 0%
392 SCADA Checkout 2.4 daysWed 10/30/19Mon 11/4/19 0%
393 Test DI points with SO 0.8 daysWed 10/30/19Thu 10/31/19 0%
394 Test AI points with SO 0.4 daysThu 10/31/19 Fri 11/1/19 0%
395 Test DO points with SO 0.4 daysFri 11/1/19 Fri 11/1/19 0%
396 Test DI points with SO 0.4 daysFri 11/1/19 Mon 11/4/19 0%
397 Test AO points with SO 0.4 daysMon 11/4/19 Mon 11/4/19 0%
398 Verify SCADA checkout complete w/SCADA 0.8 days?Tue 1/28/20 Wed 1/29/20 0%
PCM Shop
PCM Shop
PCM Shop
1/8
PCM Shop
PCM Shop
1/10
PCM Shop
PCM Shop
1/9
PCM Shop
PCM Shop
PCM Shop
PCM Shop
12/6
PCM Shop
PCM Shop
12/11
10/30
PCM Shop
PCM Shop
1/29
PCM Shop
PCM Shop
PCM Shop
PCM Shop
PCM Shop
1/29
12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/2 3/9 3/16 3/23 3/30
December January February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: CG Automation Constru
Date: Tue 2/4/20
ID Task Name Duration Start Finish % Complete
399 Runner Welding 8 wks Mon 11/18/19Thu 1/16/20 100%
400 Bindicater Sandblasting 2 days Fri 1/17/20 Tue 1/21/20 0%
401 Remove Scaffolding 1 day Tue 1/21/20 Wed 1/22/20 100%
402 Plumb Unit 10 days Wed 1/22/20 Mon 2/10/20 60%
403 Dry Testing (W/O# 1005069782)8 days Mon 2/17/20 Fri 2/28/20 0%
418 Vendor Commissioning (W/O# 1005069830)9.7 daysMon 2/24/20 Tue 3/10/20 0%
419 Governor Prechecks 1 day Mon 2/24/20 Tue 2/25/20 0%
420 ABB Exciter Prechecks 1 day Tue 2/25/20 Wed 2/26/20 0%
421 IRIS - HydroGuard 1 day Tue 3/3/20 Wed 3/4/20 0%
422 Accusonic 1 day Wed 3/4/20 Thu 3/5/20 0%
423 Vibration System 3 days Tue 2/25/20 Fri 2/28/20 0%
424 Modified Clearance 0%
425 Water Up (W/O# 1005069872)1.8 daysTue 2/25/20 Thu 2/27/20 0%
426 Governor Offline Testing 0.8 daysTue 2/25/20 Wed 2/26/20 0%
427 ABB Exciter Offline Testing 0.8 daysWed 2/26/20 Thu 2/27/20 0%
428 Verify w/SCADA that all points are in service and live 0%
429 Online (on the grid) (W/O# 1005069930)25.6 days?Mon 2/17/20 Tue 3/31/20 0%
430 Governor Online Testing 1.6 daysWed 2/26/20 Fri 2/28/20 0%
431 ABB Exciter Online Testing 1.6 daysThu 2/27/20 Mon 3/2/20 0%
432 IRIS - HydroGuard Testing 1.6 daysWed 3/4/20 Fri 3/6/20 0%
433 Vibration System Testing 25.6 days?Mon 2/17/20 Tue 3/31/20 0%
434 Supervision of the replacement of one damaged air gap sensor. Supervision
of instsallation of airgap triaxle cables & LIN modules, displacement probes,
stator core/frame accelerometers and TWR probe
4.1
days
Mon 2/17/20 Fri 2/21/20 0%
435 Commissioning of the sensor, which includes - TWR Support and installation
materials
4.1
days
Mon 2/24/20 Fri 2/28/20 0%
436 Commission Report Tue 3/31/20 0%
437 Avista/Unit Controls Tuning (W/O# 1005069954)3.2 daysWed 4/1/20 Mon 4/6/20 0%
438 Unit Start/Stop Testsing 3.2 daysWed 4/1/20 Mon 4/6/20 0%
439 Unit Online Mode Testing 3.2 daysWed 4/1/20 Mon 4/6/20 0%
440 Misc Testing (AGC, Motoring, etc.)3.2 daysWed 4/1/20 Mon 4/6/20 0%
441 Release for Service (The End)0.8 days?Tue 4/7/20 Tue 4/7/20 0%
442 Commission Blowdown 0%
443 WECC testing 0%
444 As-builts 0%
445 update parts list 0%
NW Sandblast
L&S/CE/PCM
ABB/CE/PCM
IRIS
Accusonic
VibroSystM
2/27
L&S/CE/PCM
ABB/CE/PCM
3/31
L&S/CE/PCM
L&S/CE/PCM
IRIS
3/31
4/6
Control Eng / PCM
Control Eng / PCM
Control Eng / PCM,SCADA
12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24 3/2 3/9 3/16 3/23 3/30
December January February March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: CG Automation Constru
Date: Tue 2/4/20
Scope Baseline & Scope Management Plan Component of Project Execution Plan (PEP)
1
Project Name: Cabinet Gorge Unit 2 Automation
Project ID: 30405082
The purpose of the Scope Baseline is to define the original approved scope statement.1
be protected from
excessive heat, cold and
moisture.
insulated.
Barrel heaters will be
installed.
temperature will
be maintained at a
steady
Generator barrel heater
installation
protected from flooding. devices will be installed.
Sump Pumps will be
not flood. monitoring devices.
Installation of Sump
Supply with operational
flexibility.
Automatic Generation
Control (AGC) will be
installed.
employ operational
flexibility with
Cabinet Gorge Unit
blowdown system;
Installation of AGC.
monitored in both the X
and Y positions and related
data captured and stored.
monitoring will
provide operational
alerts to Unit
VibroSystM equipment.
provide indication when
racked out and the fan(s)
will provide necessary
racked out.
Replace the fan motor
and/or add a redundant
will be employed;
breaker cooling will
be employed.
be installed; fans will be
installed.
windings will be monitored. will be upgraded but, we
will not change out the
capacitive probes.
ETHERNET CABLE will
require port open on the
monitored and
provide operational
alerts to Unit
performance.
HydroTrac equipment.
system will be refurbished. valves be supplied to the water system.
will be collected in the
penstock to accurately
reflect real-time river
Accusonic system.
ETERNET CABLE
flows will be
monitored
information.
1 For more information on project scope, please reference the attached Functional Requirements and Alternative Analysis
documents.
Scope Baseline & Scope Management Plan Component of Project Execution Plan (PEP)
2
system will be modernized
to improve efficiency and
frequency response.
ControlLogix PLC based
Governor.
Switches, ports and
cables.
governor control
system will be used
to improve
efficiency and
frequency
Governor.
will be replaced with a
modern, digital static
Switches, ports and
cables
be employed using
a digital static
static exciter.
system will be replaced
with a modern PLC that will
improve efficiency,
monitoring capabilities and
ControlLogix PLC
Switches, ports and
cables
monitoring and
reliability will be
improved upon.
PLC.
mechanical/electrical
protection relays will be
replaced with modern,
multi-function relays to
meet NERC requirements
and ensure electrical
art multi-function SEL
relays.
ETHERNET CABLE
NAT ADDRESS REQUIRED
(ETHUN FOR
CONFIGURATION)
will be met;
electrical
protections will be
enhanced.
multi-function relays.
Network will be expanded
to integrate Unit 2 into the
networking equipment.
integrate Unit 2
into the modern
and reliable network
equipment.
modified to provide data
from Unit 2 to SCADA for
System Operations for
monitoring and AGC
control.
to identify critical points
and configure control
system to deliver
information to SCADA.
Network Engineering –
similar to line 12 (SEL-
monitor critical
system operations
and AGC control
data.
network.
upgraded to revenue
quality standards to more
accurately monitor power
generation for marketing
purposes and to help
improve the System
Operator’s area load
revenue grade CTs.
ETHERENET CABLE
will be improved;
power generation
for marketing
purposes will be
improved.
temperature monitoring dual element Resistive temperature monitoring and
Scope Baseline & Scope Management Plan Component of Project Execution Plan (PEP)
3
the new PLC control
system.
condition equipment.
Potential ETHERNET
PLC control system.
to the thrust bearings. filtration system. thrust bearings will loop filtration system.
bearing oil system will be
upgraded to provide more
reliable cooling, heating,
control, indication and
system; install heaters
and coolers.
bearing oil system
will experience
increased
reliability.
bearing oil system
including installation of
heaters and coolers.
high lift pump system oil to
the thrust bearings
including motors and
motor starters will be
equipment with
enhanced monitoring
and control capabilities.
system reliability
will be enhanced.
reliable
pumps are Woodward XX
pumps that have not been
completely overhauled
since installation in the late
1950’s. Governor pump
and motor for Unit 2
should be overhauled
off-site to American
Governor to be
overhauled
governor oil pumps
will provide years
of reliable service.
pumps.
The purpose of the Scope Management Plan is to establish processes used to ensure the
project includes all the tasks required to complete the project.
Report deliverables, update
scope status
Project Team
process quality
Request Project Team
Functional Requirements Planning Phase Continued
Project Name: Cabinet Gorge Unit 2 Automation Replacement
Project ID: 30405082
1 Introduction
Avista’s Safe and Reliable Infrastructure strategic initiative seeks to leverage advancing technology
and innovative business models to improve products and services offered to existing and new
customers. The work proposed for Unit 2 will ensure system compatibility with current standards
and will improve system reliability. Plant standardization improves efficiencies and reduces
unpredictable and costly outages.
This Functional Requirements document will identify the current state, performance metrics and
project requirements. It will complement the Methods Analysis, which defines the scope
expectations by identifying recommended upgrades to specific systems and alternatives where
available. The recommended upgrades shall be compliant with all requirements identified herein.
2 Current State
Construction on Cabinet Gorge, one of four regulating hydro plants owned and operated by Avista
Utilities, was completed in 1953. The plant consists of four generating units. The Business Case
supporting this capital work (ER4163) is identified as “Cabinet Gorge Automation” indicating that
the Business Case aims to address plant wide automation. The decision to address Unit 2 first was
largely based on a variety of mechanical issues related to the governor, excitation system, cross
current compensation, stator cooling water valves, RTDs and various other mechanical issues that
contribute to this Unit’s inability to run reliably and without operator intervention. Each
sequential Unit will in turn be addressed in separate projects.
3 Performance Metrics
Specifically, this project will seek to improve in five major performance metrics:
• Communication improvements to the Unit subsystems via Ethernet.
• Improvement in programmability of devices (patching/updating for future
requirements/needs).
• Increased Unit availability as evidenced by an increase in the Equivalent Availability Factor
(EAF) over time.
• Reduced number of work orders related to critical maintenance issues.
• Meet NERC PRC-025 requirements for Generator Relay Loadability.
Functional Requirements Planning Phase Continued
4 Requirements
1. The generator barrel will be protected from excessive heat, cold and moisture.
2. The turbine pit will be protected from flooding.
3. The braking and jacking system will provide position indication.1
4. The Unit will provide Power Supply with operational flexibility.
5. Unit vibration will be monitored in both the X and Y position and related data captured and
stored.
6. The generator breaker will meet plant standards.
7. The health of the generator windings will be monitored.
8. The aging cooling water system will be refurbished.
9. Reliable flow information will be collected in the penstock to accurately reflect real-time river
flows.
10. The aging governor control system will be modernized to improve efficiency and frequency
response.
11. The aging rotating exciter will be replaced with a modern, digital static exciter.
12. The aging Bailey controls system will be replaced with a modern PLC that will improve efficiency,
monitoring capabilities and reliability.
13. The aging mechanical/electrical protection relays will be replaced with modern, multi-function
relays to meet NERC requirements and ensure electrical protection.
14. The Generation Control Network will be upgraded to integrate modern control systems.
15. The SCADA network will modified to provide data from Unit 2 to SCADA for System Operations
for monitoring and AGC control.
16. The Unit metering will be upgraded to revenue quality standards to more accurately monitor
power generation for marketing purposes and to help improve the System Operator’s area load
control.
17. The longevity of generator windings will be improved upon.2
18. Aging thrust shoe temperature monitoring and alarming system will be replaced to integrate
into the new PLC control system.
19. Clean oil will be provided to the thrust bearings.
20. The aging turbine guide bearing oil system will be upgraded to provide more reliable cooling,
heating, control, indication and alarming.
21. The aging generator guide bearing monitoring system will be replaced.3
22. The aging and antiquated high lift pump system including motors and motor starters will be
replaced.
23. The governor oil pumps will be overhauled.
1 Defer this work to the rotor pull portion of Unit 2 work
2 Defer this work to the rotor pull portion of Unit 2 work
3 Defer this work to the rotor pull portion of Unit 2 work
Project Monthly Report
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Approved 2016 Budget: $616,000 Approved Lifetime Budget: $2,941,000
Accrued 2016 YTD (8/31/16) $171,335 Accrued Life to Date (8/31/16): $266,289
2017 Estimate at Complete: $2,308,044 Total Project Estimate at Complete: $$2,096,181
Expected Transfer to Plant Date: Sept 2018 Expected Transfer to Plant Amount: $$2,096,181
Table 1. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
This project will replace the existing Bailey
control equipment with a new system that
will be integrated with the OIT and other plant devices. Work also includes:
Governor upgrade
Vibro System incorporation Iris system update
Blowdown upgrade
Exciter replacement
PPT replacement
Protection and control panels
Penstock flow meter Field brushes
Business case requested amount
$2,941,000
Total CPR amount = $865,856
(12/1/15)
2016 Budget = $616,000
2016 Spend to Date = $171,335 (28%)
2016 Average monthly spend = $21,417
Due to significant underspend, a recommendation was made to release
$300k to the CPG.
Completion of this project is
predicated by completion of the
Cabinet Gorge DC System Upgrade which is not slated to
begin until Q2 2017 and may
take up to seven weeks to
complete. There is ample time to
thoroughly plan for this work
but, care must be taken to keep
the schedule on track.
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Date Actual/Projected Completion Date Total Float Status/Performance
Draft Charter 10/31/16 15% complete
Complete design
Construct Control panels 12/31/16 0% complete
Construct Relay panels 12/31/16 0% complete
Accomplishments:
Rob Selby traveled to Montreal for FAT of the
exciter
Upcoming Activities
Draft Charter
Complete design – Rob Selby
Construct control and relay panels this year
Risks and Mitigation Strategies:
Approved $300k capital release for 2016
Project Monthly Report
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Approved 2016 Budget: $316,0001 Approved Lifetime Budget: $2,941,000
Accrued 2016 YTD (9/30/16) $272,806 Accrued Life to Date (9/30/16): $285,831
2016 Estimate at Complete: $303,051 Total Project Estimate at Complete: $2,042,077
Expected Transfer to Plant: April 2018 Expected Transfer to Plant Amount: $2,042,077
Table 3. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
This project will replace the existing Bailey
control equipment with a new system that
will be integrated with the OIT and other plant devices. Work also includes:
Governor upgrade
Vibro System incorporation Iris system update
Blowdown upgrade
Exciter replacement
PPT replacement
Protection and control panels
Penstock flow meter Field brushes
Projected to come in under budget for
2016.
Completion of this project is predicated by
completion of the Cabinet Gorge DC System
Upgrade which is not slated to begin until Feb 2017 and may take up to seven weeks to
complete. Annual planning has this project slated
to begin construction in late August 2017.
Table 4. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Date Actual/Projected Completion Date Total Float Status/Performance
Draft Charter 10/31/16 15% complete
Complete design
Construct Control panels 12/31/16 0% complete
Construct Relay panels 12/31/16 0% complete
Accomplishments:
Controlling spend; shepherding planning
Upcoming Activities
Draft Charter – meeting setup with key stakeholders on
Friday, October 14th
Complete design – Rob Selby
Construct control and relay panels this year
Risks and Mitigation Strategies:
Due to significant 2016 underspend, approved $300k capital
release.
1 Returned $300k to CPG in September 2016
Project Monthly Report
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Approved 2016 Budget: $316,000 Approved Lifetime Budget: $2,941,000
Accrued 2016 YTD (10/31/16) $272,806 Accrued Life to Date (10/31/16): $290,558
2016 Estimate at Complete: $316,000 Total Project Estimate at Complete: $2,422,025
Expected Transfer to Plant: April 2018 Expected Transfer to Plant Amount: $2,422,025
Table 5. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
Charter approved. Though the planning
phase will define the full scope, Power Supply requires that Cabinet Unit 2 be
equipped with Automatic Generation
Control (AGC) and that unit metering be
brought up to our current design
standards (5 minute revenue quality metering).
Projected to come in under budget for
2016.
Completion of this project is predicated by
completion of the Cabinet Gorge DC System Upgrade which is not slated to begin until Feb
2017 and may take up to seven weeks to
complete. Annual planning has this project slated
to begin construction in late August 2017.
Table 6. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Complete design
Accomplishments:
Charter approved
Controlling spend; shepherding planning
Upcoming Activities
Site visit scheduled for November 30, 2016
Complete design – Rob Selby
Risks and Mitigation Strategies:
Gantry crane unavailable – no plans to pick the
rotor
CG Automation Replacement ‐
30405082
Project Manager: Terri Echegoyen
Project Monthly Report
Approved 2016 Budget: $316,000 Approved Lifetime Budget: $2,941,000
Accrued 2016 YTD (11/30/16) $281,830 Accrued Life to Date (11/30/16): $294,855
2016 Estimate at Complete: $316,000 Total Project Estimate at Complete: $2,422,025
Expected Transfer to Plant: April 2018 Expected Transfer to Plant Amount: $2,422,025
Table 7. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
Preliminary scoping meeting conducted on December 2nd. Notes are out to the team
for review. Annual Master Schedule has
this work slated to begin in late August
2017. Unless scope is reduced, this date
cannot be met. Master scheduling has been advised.
Projected to come in under budget for 2016. Annual Master Schedule has this work slated to begin in late August 2017. I have communicated
with scheduling that this date may not be
realistic. One of two things must happen:
Either scope must be reduced or the start date
must be pushed out – likely to 2018
Table 8. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16
Functional Requirements
Methods Analysis
Project Execution Plan
Accomplishments:
Preliminary scoping meeting conducted on December 2nd.
Electrical engineering responsibilities shifted from Rob
Selby to Dave Schwall.
Upcoming Activities
Governor discussion scheduled for Monday, December
12th.
Working to define scope: differentiate between “must
have” and “nice to have” components.
Risks and Mitigation Strategies:
Gantry crane unavailable – no plans to pick the rotor
Power Supply has indicated the desire for Unit 2 to be
equipped with Automatic Generation Control (AGC) but, operations indicates that the cost benefit of AGC on Unit 2 is
limited due to the mixed flow runner that constrains operational flexibility to 90-100% of wicket gate.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
Approved 2016 Budget: $316,000 Approved Business Case Lifetime
Budget: $2,941,000
Accrued 2016 YTD (12/31/16) $317,073 Accrued Life to Date (12/31/16): $330,098
Expected Transfer to Plant: Q4 2018 Estimated 2017 Spend2: $750,000
Table 9. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
Scope continues to be refined. Power
Supply has requested that the project team
consider refocusing this work effort away
from Unit 2 and onto Unit 4 where ACG will be a more effective tool. A decision point is
scheduled for Friday, January 20th.
2016 YTD spend came in flat to
expected spend. With construction
pushed out to Aug 2018, the 2017
estimated spend has been revised from $1.56mm to $750k.
This project has been removed from the annual
master schedule until such time as planning is
more complete. It is anticipated that
construction/execution will begin in Aug 2018 though this is just an estimate.
Table 10. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Date Actual/Projected Completion Date Total Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 50% complete
Functional Requirements TBD
Methods Analysis TBD
Project Execution Plan TBD
Accomplishments:
2nd scoping meeting conducted on Friday,
Jan. 6th at which Glen Farmer announced
Power Supply’s request to switch focus from
Unit 2 to Unit 4.
Working to differentiate between “must
have” and “nice to have” components.
Upcoming Activities
L&S scheduled to visit Cabinet Gorge next
month.
Project team decision point w/ramifications
scheduled for Friday, January 20th.
Risks and Mitigation Strategies:
Switching focus from Unit 2 to Unit 4 should not pose a problem since the scope of this project has not yet
been clearly defined and not much work effort beyond the purchase of the ABB exciter has transpired.
With the announcement of Ryan Bean’s new role as Manager, Enterprise Asset Management (Maximo), Civil
Engineering responsibilities have been transferred to Nick Agostinelli.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
2 This figure is primarily comprised of engineering labor and governor purchase.
Project Monthly Report
Approved 2017 Budget: $1,561,000 Accrued LTD (1/31/17) $372,043
2017 Forecast $751,565 Expected Transfer to Plant: Q4 2018
Table 11. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
It has been decided to stay with Unit 2 which has some substantial operational
issues rather than switching to Unit 4.
Scope is 90% defined.
On track for now. Waiting for quote from L&S on the governor after which a
revised 2017 spend can be calculated.
This project has been removed from the annual master schedule until such time as planning is
more complete. It is anticipated that
construction/execution will begin in Aug 2018
though this is just an estimate.
Table 12. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 90% complete
Functional Requirements 3/31/17
Methods Analysis TBD
Project Execution Plan TBD
Accomplishments:
Scope @ 90%
Site visit with L&S – 2/2/17
Began determining Functional Requirements.
Upcoming Activities
Second Functional Requirements meeting scheduled for
February 22nd.
Risks and Mitigation Strategies:
It is the desire of the controls group to standardize the
governor to a PLC based system. Jeremy Winkle is
composing a request to standardize for submission to
Andy Vickers for approval.
If approved, we have an opportunity to purchase all three
Cabinet Gorge governors for Units 2, 3 and 4 on one contract with L&S which could represent substantial
savings.
If purchased, there is an additional opportunity to install all three governors concurrently prior to the full
upgrades on Units 3 and 4. This work would add the benefit of Frequency Response to all three Units.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
Approved 2017 Budget: $1,561,000 Accrued LTD (2/28/17) $373,1223
2017 Forecast $779,545 2017 YTD Spend (2/28/17) $31,800
2017 Estimate at Complete (EAC) $811,345 Expected Transfer to Plant: Q4 2018
Table 13. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
No change On track On track
Table 14. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 99% complete
Functional Requirements 3/31/17
Methods Analysis TBD
Project Execution Plan TBD
Accomplishments:
Scope @ 99%
L&S delivered digital governor quote
Upcoming Activities
Functional requirements gathering continues
Risks and Mitigation Strategies:
Many items have long lead times. Material orders may be
placed this year for items to be used next year.
It is the desire of the controls group to standardize the
governor to a PLC based system. Jeremy Winkle is
composing a request to standardize for submission to
Andy Vickers for approval.
If approved, we have an opportunity to purchase all three
Cabinet Gorge governors for Units 2, 3 and 4 on one contract with L&S which could represent substantial
savings.
If purchased, there is an additional opportunity to install all three governors concurrently prior to the full
upgrades on Units 3 and 4. This work would add the benefit of Frequency Response to all three Units.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
3 $35,110 professional services credit posted in February for charges mistakenly attributed to this project.
Project Monthly Report
Approved 2017 Budget: $1,561,000 Accrued LTD (3/31/17) $373,1224
2017 Forecast $779,545 2017 YTD Spend (3/31/17) $31,800
2017 Estimate at Complete (EAC) $811,345 Expected Transfer to Plant: Q4 2018
Table 15. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
No change On track On track
Table 16. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 99% complete
Functional Requirements 3/31/17
Methods Analysis TBD
Project Execution Plan TBD
Accomplishments:
Scope @ 99%
L&S delivered digital governor quote
Upcoming Activities
Functional requirements gathering continues
Risks and Mitigation Strategies:
Many items have long lead times. Material orders may be
placed this year for items to be used next year.
It is the desire of the controls group to standardize the
governor to a PLC based system. Jeremy Winkle is
composing a request to standardize for submission to
Andy Vickers for approval.
If approved, we have an opportunity to purchase all three
Cabinet Gorge governors for Units 2, 3 and 4 on one contract with L&S which could represent substantial
savings.
If purchased, there is an additional opportunity to install all three governors concurrently prior to the full
upgrades on Units 3 and 4. This work would add the benefit of Frequency Response to all three Units.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
4 $35,110 professional services credit posted in February for charges mistakenly attributed to this project.
Project Monthly Report
Approved 2017 Budget: $1,561,000 Accrued LTD (4/30/17) $401,365
2017 Forecast $951,319 2017 YTD Spend (4/30/17) $71,267
2017 Estimate at Complete (EAC) $811,345 Expected Transfer to Plant: Q4 2018
Table 17. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
No change On track On track
Table 18. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 99% complete
Functional Requirements
finalized 6/6/17
Functional Requirements
approved 6/9/17
Project Execution Plan TBD
Accomplishments:
Cirrus Design delivered the 3D Point Cloud of
Pipe Floor, 3D Point Cloud of Operating Floor
and AutoCAD XREF .dwgs of both floors.
Upcoming Activities
Governor Evaluation and Recommendation
Finalize Functional Requirements
H2E to begin General Arrangements
Risks and Mitigation Strategies:
Many items have long lead times. Material
orders may be placed this year for items to be
used next year.
It is the desire of the controls group to
standardize the governor to a PLC based
system. Jeremy Winkle is composing a request
to standardize for submission to Andy Vickers for approval.
If approved, we have an opportunity to purchase all three Cabinet Gorge governors for Units 2, 3 and 4 on one
contract with L&S which could represent substantial savings.
If purchased, there is an additional opportunity to install all three governors concurrently prior to the full
upgrades on Units 3 and 4. This work would add the benefit of Frequency Response to all three Units.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
Approved 2017 Budget: $1,561,000 Accrued LTD (5/31/17) $429,550
2017 Forecast $876,437 2017 YTD Spend (5/31/17) $99,452
2017 Estimate at Complete (EAC) $975,889 Expected Transfer to Plant: Q4 2018
Table 19. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
On Track On track On track
Table 20. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 99% complete
Functional Requirements
finalized 6/6/17 6/9/17 100% complete
Methods Analysis
approved 6/30/17
Project Execution Plan TBD
Accomplishments:
Functional Requirements developed
Upcoming Activities
Governor Evaluation and Recommendation
Methods Analysis submitted for review and approval.
Risks and Mitigation Strategies:
Many items have long lead times. Material orders may be
placed this year for items to be used next year.
It is the desire of the controls group to standardize the
governor to a PLC based system. Discussions are
underway with L&S.
If approved, we have an opportunity to purchase all three
Cabinet Gorge governors for Units 2, 3 and 4 on one contract with L&S which could represent substantial
savings.
If purchased, there is an additional opportunity to install all three governors concurrently prior to the full
upgrades on Units 3 and 4. This work would add the benefit of Frequency Response to all three Units.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
Approved 2017 Budget: $1,561,000 Accrued LTD (6/30/17) $472,075
2017 Forecast $395,162 2017 YTD Spend (5/31/17) $141,977
2017 Estimate at Complete (EAC) $537,139 Expected Transfer to Plant: Q4 2018
Table 21. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
On Track On track On track
Table 22. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 99% complete
Functional Requirements
finalized 6/6/17 6/9/17 100% complete
Methods Analysis
approved 6/30/17
Project Execution Plan TBD
Accomplishments:
Quote received from L&S for all four governors.
Controls Engineering memo written in support of
governor standardization.
Statement of Work for governor purchase underway.
Transition to the new business case format; looking
to transfer $1MM dollars from this year to next.
Upcoming Activities
Manager review and approval of governor specifications.
Methods Analysis submitted for review and approval. Waiting on feedback.
Risks and Mitigation Strategies:
Many items have long lead times. Material orders may be placed this year for items to be used next year.
If purchased, there is an additional opportunity to install all three governors concurrently prior to the full
upgrades on Units 3 and 4. This work would add the benefit of Frequency Response to all three Units.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
Approved 2017 Budget: $561,000 Accrued LTD (7/31/17) $507,950
2017 Remaining Forecast $97,530 2017 YTD Spend (7/31/17) $177,852
2017 Estimate at Complete (EAC) $275,382 Expected Transfer to Plant: Q4 2018
Table 23. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
With the prospect of having a
functioning crane at the start of
this work, the scope has been
increased to include pulling the
rotor which will enable work to be
performed on the brakes and DC
jacking system as well as
performing the stator re-wedge
and field pole key insulation.
On track On track
Table 24. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 99% complete
Functional Requirements
finalized 6/6/17 6/9/17 100% complete
Alternatives Analysis
approved TBD
Project Execution Plan TBD
Total cost for this project has not changed -
$2,422,025. Timing for spend has changed.
Construction is not slated to begin until Aug/Sep 2018
due to crew workload and planning constraints.
Accomplishments:
Governor specification completed
Statement of Work for governor purchase underway.
Upcoming Activities
Finalization of Alternatives Analysis
Risks and Mitigation Strategies:
Many items have long lead times. Material orders may be placed this year for items to be used next year.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
2015 2016 2017 2018 Total
Budget 13,025$ 316,000$ 561,000$ 1,532,000$ 2,422,025$
Actual 13,025$ 317,073$ 213,734$ 543,832$
Forecast 140,624$
EAC 354,358$
Variance (0)$ (1,073)$ 206,642$ 22%
Table 25. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
Meeting scheduled with steering
committee to address scope creep.
On track On track
Table 26. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 99% complete
Functional Requirements
finalized 6/6/17 6/9/17 100% complete
Alternatives Analysis
approved TBD
Project Execution Plan TBD
Accomplishments:
Statement of Work for governor purchase drafted
and under review.
Upcoming Activities
Finalization of Alternatives Analysis
Finalization of Methods Analysis
Risks and Mitigation Strategies:
Many items have long lead times. Material orders
may be placed this year for items to be used next
year.
CG Automation Replacement ‐
30405082
Project Manager: Terri Echegoyen
Project Monthly Report
2015 2016 2017 2018 Total
Budget 13,025$ 316,000$ 561,000$ 1,532,000$ 2,422,025$
Actual 13,025$ 317,073$ 225,917$ 556,015$
Forecast 79,645$
EAC 305,562$
Variance (0)$ (1,073)$ 255,438$ 23% Table 27. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
Met with steering committee to
address scope creep.
On track On track
Table 28. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date
Total
Float Status/Performance
Draft Charter 10/31/16 11/4/16 100% complete
Scope Defined 12/30/16 99% complete
Functional Requirements
finalized 6/6/17 6/9/17 100% complete
Alternatives Analysis
approved TBD
Project Execution Plan TBD
Accomplishments:
Met with steering committee to discuss perceived
project scope deviance when compared to the
business case.
L&S purchase agreement finalized
Upcoming Activities
2 day L&S kick off meeting on site October 10 - 11
PM will present steering committee w/scope
options (full-meal deal vs. ala carte)
Prepared to release $200k to capital planning
Risks and Mitigation Strategies:
Many items have long lead times. Material orders
may be placed this year for items to be used next
year.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Due to the low level of certainty related to the 2017 spend projection for this project, a funds change
request was submitted to the Capital Planning Group on October 12th. Please see the details below.
Project Monthly Report
Table 29. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
PM will present detailed scope
with costs ranging from minimum
work to meet the business case to
full unit overhaul.
Released $200k in October
2017; requested additional
$200k in 2018.
On track
Table 30. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Date Actual/Projected Completion Date Status/Performance
Scope Defined 12/30/16 99% complete
Functional Requirements finalized 6/6/17 6/9/17 100% complete
Alternatives Analysis approved TBD
Project Execution Plan TBD
Accomplishments:
Piping and Instrumentation Diagram (PNID) drawing development meeting w/reps from H2E conducted on
11/8/17
Upcoming Activities
Anticipating proposal from L&S to extend delivery date of first governor for Unit 1.
Risks and Mitigation Strategies:
Will this project focus on just excitation and controls upgrades w/digital governor or, will this project seek to
overhaul the entire Unit? To be determined.
Many items have long lead times. Material orders may be placed this year for items to be used next year.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
2015 2016 2017 2018 Total
Budget 13,025$ 316,000$ 361,000$ 1,732,000$ 2,422,025$
Actual 13,025$ 317,073$ 301,322$ 631,420$
Forecast 17,952$
EAC 319,274$
Variance (0)$ (1,073)$ 41,726$ 26%
Table 31. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
PM will present detailed scope
with costs ranging from minimum
work to meet the business case to
full unit overhaul.
On track On track
Table 32. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date Status/Performance
Scope Defined 12/30/16 99% complete
Functional Requirements finalized 6/6/17 6/9/17 100% complete
Alternatives Analysis approved TBD
Project Execution Plan TBD
Accomplishments:
Delivery date for first
governor unit has been
extended from 3/1/18 to
5/17/18
Upcoming Activities
Blowdown system
intended for Unit 2 will
be installed on Unit 1.
Parts will be reordered
for Unit 2.
Risks and Mitigation
Strategies:
Will this project focus on
just excitation and controls upgrades w/digital governor or, will this project seek to overhaul the entire Unit?
To be determined.
Many items have long lead times. Material orders may be placed this year for items to be used next year.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
2015 2016 2017 2018 Total
Budget 13,025$ 316,000$ 361,000$ 1,732,000$ 2,422,025$
Actual 13,025$ 317,073$ 329,150$ 659,248$
Forecast 1,732,000$
EAC 329,150$ % spend to date
Variance (0)$ (1,073)$ 31,850$ 27%
Table 33. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
There is still some question as to
the scope of this project. To pull
the rotor in order to address poles
and stator windings or not.
On track
2017 underspent by $31,850
Master schedule has this work
starting on 8/6/18. Is there an
opportunity to move this date
up?
Table 34. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Date Actual/Projected Completion Date Status/Performance
Scope Defined 12/30/16 99% complete
Functional Requirements finalized 6/6/17 6/9/17 100% complete
Alternatives Analysis approved TBD
Project Execution Plan TBD
Accomplishments:
Notice to proceed with Field Pole Insulation
Rewinding delivered to GE 12/28/17.
Waiting on confirmation of scheduling
timeline.
Upcoming Activities
If approved, anticipate pulling the rotor
with the strand jack the week of July 9th
spill permitting.
Risks and Mitigation Strategies:
With regard to the business case which is
ambiguously written as “Cabinet Gorge
Automation,” it will be necessary to do one of two things:
o Either limit this business case strictly to automation of all units to include governs, exciters and
controls, or
o Expand this business case to include mechanical and automation overhaul of units 2, 3 and 4.
The budget for 2018 is $1.732mm which will not cover the poles and stator windings along with all the other
work. Would have to make a request of CPG if we decided to proceed with that work. A compelling case would
have to be made.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
2015 2016 2017 2018 Total
Budget 13,025$ 316,000$ 361,000$ 1,732,000$ 2,422,025$
Actual 13,025$ 317,073$ 329,150$ 16,031$ 675,279$
Forecast 1,587,667$
EAC 329,150$ % spend to date
Variance (0)$ (1,073)$ 31,850$ 28%
Table 35. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
On Trac On Trac On trac
Table 36. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date Status/Performance
Scope Defined 12/30/16 99% complete
Functional Requirements finalized 6/6/17 6/9/17 100% complete
Alternatives Analysis approved 2/15/17
Project Execution Plan TBD
Accomplishments:
The decision was made to not pull the rotor:
o Would have necessitated an additional $1.7mm ask of
the CPG
o Too risky with respect to the crane
o No evidence to suggest this work must be performed
“now.”
Rescinded NTP with GE for field poles.
GE Contract amended.
Submittal #2 from L&S received: drawing and bill of
material for the speed sensing retrofit
Upcoming Activities
Alternatives Analysis complete. Meeting with SteerCo slated for 2/15/18. Approval of Alternatives Analysis
and related financial forecast authorizes the purchase of materials.
Risks and Mitigation Strategies:
This work is slated to begin on 8/6/18 according to the master schedule. However, this work can provide
float to other projects since it is not dependent on weather and spill.
With regard to the business case which is ambiguously written as “Cabinet Gorge Automation,” it will be
necessary to do one of two things:
o Either limit this business case strictly to automation of all units to include governs, exciters and
controls, or
o Expand this business case to include mechanical and automation overhaul of units 2, 3 and 4.
The budget for 2018 is $1.732mm which will not cover the poles and stator windings along with all the other
work. Would have to make a request of CPG if we decided to proceed with that work. A compelling case would
have to be made.
CG Automation Replacement ‐ 30405082
Project Manager: Terri Echegoyen
Project Monthly Report
2015 2016 2017 2018 Total
Budget $13,025 $316,000 $361,000 $1,732,000 $2,422,025
Actual $13,025 $317,073 $329,150 38,887$ $675,279
Forecast 1,741,605$ $1,980,850
EAC $329,150 $1,996,881 $2,656,129
Variance $0 ($1,073)$31,850 ($264,881) ($234,104)
Table 37. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
If project is pushed out to next
year, scope will increase.
On Track Construction may be pushed out
to 2019 once the crane is
available.
Table 38. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Date
Actual/Projected
Completion Date Status/Performance
Scope Defined 12/30/16 99% complete
Functional Requirements finalized 6/6/17 6/9/17 100% complete
Alternatives Analysis approved 2/15/17
Project Execution Plan TBD
Accomplishments:
Upcoming Activities
With the crane project back on for 2018, a request has been made to revisit sequencing of work at Cabinet Gorge:
o Crane Rehabilitation
o Unit 2 Automation
o Station Service A
o Station Service B
o HVAC
o Unit 3 Automation
o Unit 4 Automation
o Unit 1 Governor
More to come following March 15th sequencing meeting
Risks and Mitigation Strategies:
This work is slated to begin on 8/6/18 according to the master schedule. However, this work can provide
float to other projects since it is not dependent on weather and spill. Revisiting construction schedule.
With regard to the business case which is ambiguously written as “Cabinet Gorge Automation,” it will be
necessary to do one of two things:
o Either limit this business case strictly to automation of all units to include governs, exciters and
controls, or
o Expand this business case to include mechanical and automation overhaul of units 2, 3 and 4.
Cabinet Gorge Automation – 30405082
Project Manager – Terri Echegoyen
Approved 2018 Budge $1,532,000 Approved Lifetime Budge $2,222,025
Project Monthly Report
Accrued 2018 to date thru
(3/31/18)
$127,686 Accrued Life to Date (thru
3/31/18)
$786,939
2018 Estimate at Complete $1,599,811 Total Project Estimate at
Complete
$2,259,059
Expected Transfer to Plant - date 12/31/19 Expected transfer to plant - $$$ $2,259,059
Table 39. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope Budget Schedule
On Track On Track On Track
Table 40. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion
Date
Actual/Projected
Completion Date
Status/Performance
Electrical Design IFC 4/12/18
Panel Construction
Protection Settings 7/27/18
Pre-construction Meeting 7/19/18
Construction Begins 8/13/18
Construction Ends 11/21/18
Summary
With the crane rehabilitation project now
underway, the expectation is that the main hoist
will be fully functional @ 340 Tons by year’s end.
This project will focus 2018 efforts on the controls,
governor and excitation systems along with a few
mechanical components. Pulling the rotor to
address the field poles and remaining mechanical
components will take place in 2019.
Accomplishments
Approval of detailed governor drawings
Control Cabinets ordered and received.
Upcoming Activities
Factory Acceptance Test of governor at L&S
Scheduling ABB representative for exciter commissioning
Expect delivery of panel design packages (IFC) from H2E by 4/12/18
Procure materials for panels (cable tray, cable, etc.)
Protection Relay Settings expected late July
Cabinet Gorge Automation – 30405082
Project Manager – Terri Echegoyen
Approved 2018 Budge $1,532,000 Approved Lifetime Budge $2,222,025
Project Monthly Report
Accrued 2018 to date thru
(4/30/18)
$150,354 Accrued Life to Date (thru
4/30/18)
$809,602
2018 Estimate at Complete $1,416,987 Total Project Estimate at
Complete
$2,076,235
Expected Transfer to Plant - date 12/31/19 Expected transfer to plant - $$$ $2,076,235
Table 41. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope Budget Schedule
On Track On Track On Track
Table 42. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion
Date
Actual/Projected
Completion Date
Status/Performance
Electrical Design IFC 4/12/18 5/31/18
Governor FAT 5/1-5/2 Complete
Panel Construction Q2 2018
Protection Settings 7/27/18
Pre-construction Meeting 7/19/18
Construction Begins 8/13/18
Construction Ends 11/21/18
Summary
With the crane rehabilitation project now
underway, the expectation is that the main hoist will
be fully functional @ 340 Tons by year’s end. Pulling
the rotor to address the field poles and remaining
mechanical components will take place in 2019.
This project will focus 2018 efforts on the controls,
governor and excitation systems along with a few
mechanical components.
Accomplishments
Governor Factory Acceptance Testing
completed
Upcoming Activities
Scheduling ABB representative for exciter commissioning
Expect delivery of panel design packages (IFC) from H2E by 5/31/18
L&S governor expected to ship the week of May 21st.
Procure materials for panels (cable tray, cable, etc.)
Protection Relay Settings expected late July
L&S tentatively scheduled governor commissioning for 9/10/18
Cabinet Gorge Automation – 30405082
Project Manager – Terri Echegoyen
Approved 2018 Budge $1,532,000 Approved Lifetime Budge $2,222,025
Project Monthly Report
Accrued 2018 to date thru
(5/31/18)
$150,354 Accrued Life to Date (thru
5/31/18)
$809,602
2018 Estimate at Complete $1,416,987 Total Project Estimate at
Complete
$2,076,235
Expected Transfer to Plant - date 12/31/18 Expected transfer to plant - $$$ $2,076,235
Table 43. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope Budget Schedule
On Track On Track On Track
Table 44. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion
Date
Actual/Projected
Completion Date
Status/Performance
Electrical Design IFC 4/12/18 5/31/18
Governor FAT 5/1-5/2 5/1-5/2 Complete
Panel Construction Q2 2018
Protection Settings 7/27/18
Pre-construction Meeting 7/19/18 6/21/18
Construction Begins 8/13/18
Construction Ends 11/21/18
Summary
With the crane rehabilitation project now
underway, the expectation is that the main hoist will
be fully functional @ 340 Tons by year’s end. Pulling
the rotor to address the field poles and remaining
mechanical components will take place in 2019.
This project will focus 2018 efforts on the controls,
governor and excitation systems along with a few
mechanical components.
Accomplishments
FAT completed
Governor received at plant
Upcoming Activities
Construction Transmittal to be delivered by June 29
Commissioning schedule:
o The governor must be commissioned prior to the exciter. L&S scheduled for the week of
11/5; ABB scheduled for the week of 11/12
Procurement of panel materials and cables underway
Protection Relay Settings expected late July
Cabinet Gorge Automation – 30405082
Project Manager – Terri Echegoyen
Approved 2018 Budge $1,532,000 Approved Lifetime Budge $2,222,025
Project Monthly Report
Accrued 2018 to date thru
(6/30/18)
$464,155 Accrued Life to Date (thru
6/30/18)
$1,418,383
2018 Estimate at Complete $1,416,987 Total Project Estimate at
Complete
$2,076,235
Expected Transfer to Plant - date 12/31/18 Expected transfer to plant - $$$ $2,076,235
Table 45. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope Budget Schedule
On Track On Track Some risk due to crew
availability and power
pricing/timing.
Table 46. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion
Date
Actual/Projected
Completion Date
Status/Performance
Electrical Design IFC 4/12/18 5/31/18
Governor FAT 5/1-5/2 5/1-5/2 Complete
Transmittal 6/29/18
Panel Construction Q2 2018 Q3 2018
Protection Settings 7/27/18
Pre-construction Meeting 7/19/18
Construction Begins 8/13/18
Construction Ends 11/21/18
Summary
There is a risk that this work will not be conducted in 2018 due to delayed transmittal and power
pricing/timing. Please find the risk register below.
RISK REGISTRY
RISK SME Probability Severity Risk Score Response
Resource Availability due to other work (Noxon U2 & Monroe Street) Alexis Possible Moderate 5 Accept revise the schedule; move outage window out to November
Crew inavailability to build panels Brad Possible Moderate 5 Transfer bring in contract crew to build panels (Pantrol)
Unable to meet 14 week outage schedule Brad Possible Serious 6 Mitigate bring in extra crew members; work 5 tens instead of 4
Critical Path: Controls Engineering Package Jeremy Likely Major 8 Transfer
Power Supply's concern about the outage window Robert F Likely Serious 7 Accept
Noxon Unit 2 will be out of commission until Septebmer 30, 2018. It is
unadvisable to have two units out on the Clark Fork river during peak
cooling season. Therefore, the CG Unit 2 outage cannot occur until
October 1, 2018. Robert F Expected Major 9 Accept
Delaying this project will necessitate the release of funds this year and
a request for funds next year. Terri Possible Serious 6 Accept
Event Estimate
Jeremy indicates that the Controls Engineering pkg will take a
miniumum of 30 days to complete and that work on it cannot
begin until the MS project is wrapped up ‐ i.e. after labor day.
Could we pull in other controls engineering resoruces? Quinton?
"we would not want the Cabinet outage to extend into 2019 if at
all possible. If we have to, we have to."
Cabinet Gorge Automation – 30405082
Project Manager – Terri Echegoyen
Project Monthly Report
Approved 2018 Budge $1,532,000 Approved Lifetime Budge $2,222,025
Accrued 2018 to date thru
(7/31/18)
$528,746 Accrued Life to Date (thru
7/31/18)
$1,187,994
2018 Estimate at Complete $1,298,278 Total Project Estimate at
Complete
$1,957,526
Expected Transfer to Plant - date 12/31/19 Expected transfer to plant - $$$
Table 47. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope Budget Schedule
Scope will not change due to
construction timing change.
Dollar variance YTD is
$1,003,254. Will need to request
funds for 2019.
Construction has been pushed
out to 2019 but is not yet on the
schedule.
Table 48. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion
Date
Actual/Projected
Completion Date
Status/Performance
Electrical Design IFC 4/12/18 5/31/18
Governor FAT 5/1-5/2 5/1-5/2 Complete
Transmittal 6/29/18 7/18/18
Panel Construction Q2 2018 Q3 2018 Q2
2019
Protection Settings 7/27/18
Pre-construction Meeting 7/19/18 Q2 2019
Construction Begins 8/13/18 8/13/19
Construction Ends 11/21/18 11/21/19
Summary
This work will not take place in 2018. The team will maintain the scope as is since the transmittal is
complete. The team will continue to purchase all necessary materials for this project, finalize protection
plans, review prints and work on PLC controls engineering package. Although delayed, this extra time
will ensure that we will be well positioned to begin construction following the 2019 spill season.
RISK REGISTRY
RISK SME Probability Severity Risk Score Response
Resource Availability due to other work (Noxon U2 & Monroe Street) Alexis Possible Moderate 5 Accept revise the schedule; move outage window out to Q3 2019.
Unable to meet 14 week outage schedule Brad Possible Serious 6 Mitigate bring in extra crew members; work 5 tens instead of 4
Critical Path: Controls Engineering Package Jeremy Likely Major 8 Transfer
Power Supply's concern about the outage window Robert F Likely Serious 7 Accept
Noxon Unit 2 will be out of commission until Septebmer 30, 2018.
Crews are slated to begin major maintenance work on NRU5 directly
afterward. Robert F Expected Major 9 Accept
Delaying this project will jeopardize full budget spend this year and
most certainly dictate a request for funds next year. Terri Possible Serious 6 Accept
Baily Breakdown Kristina Unlikely Serious 5 Accept
Event Estimate
Jeremy indicates that the Controls Engineering pkg will take a
miniumum of 30 days to complete and that work on it cannot
begin until the MS project is wrapped up ‐ i.e. after labor day.
Quinten has been pulled in to assist.
"we would not want the Cabinet outage to extend into 2019 if at
all possible. If we have to, we have to."
The Bailey is old; replacement parts are unreliable and at times
unavailable.
Project Monthly Report
Cabinet Gorge Automation – 30405082
Project Manager – Terri Echegoyen
Approved 2018 Budge $1,532,000 Approved Lifetime Budge $2,222,025
Accrued 2018 to date thru
(8/31/18)
$610,272 Accrued Life to Date (thru
8/31/18)
$1,269,520
2018 Estimate at Complete $1,343,069 Total Project Estimate at
Complete
$2,002,317
Expected Transfer to Plant - date 9/30/19 Expected transfer to plant - $$$ $2,002,317
Table 49. At‐a‐glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds
baseline and is non‐recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline
end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope Budget Schedule
Scope will not change due to
construction timing change.
Dollar variance YTD is
$921,728. Likely to release
funds this year and request
funds for 2019.
Construction has been pushed
out to 2019 but is not yet on the
schedule.
Table 50. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion
Date
Actual/Projected
Completion Date
Status/Performance
Electrical Design IFC 4/12/18 5/31/18
Governor FAT 5/1-5/2 5/1-5/2 Complete
Transmittal 6/29/18 7/18/18
Panel Construction Q2 2018 Q3 2018 Q2
2019
Protection Settings 7/27/18
Pre-construction Meeting 7/19/18 Q2 2019
Construction Begins 8/13/18 8/13/19
Construction Ends 11/21/18 11/21/19
Summary
This work will not take place in 2018. The team will maintain the scope as is since the transmittal is
complete. The team will continue to purchase all necessary materials for this project, finalize protection
plans, review prints and work on PLC controls engineering package. Although delayed, this extra time
will ensure that we will be well positioned to begin construction following the 2019 spill season.
RISK REGISTRY
Project Monthly Report
RISK SME Probability Severity Risk Score Response
Resource Availability due to other work (Noxon U2 & Monroe Street) Alexis Possible Moderate 5 Accept revise the schedule; move outage window out to Q3 2019.
Unable to meet 14 week outage schedule Brad Possible Serious 6 Mitigate bring in extra crew members; work 5 tens instead of 4
Critical Path: Controls Engineering Package Jeremy Likely Major 8 Transfer
Power Supply's concern about the outage window Robert F Likely Serious 7 Accept
Noxon Unit 2 will be out of commission until Septebmer 30, 2018.
Crews are slated to begin major maintenance work on NRU5 directly
afterward. Robert F Expected Major 9 Accept
Delaying this project will jeopardize full budget spend this year and
most certainly dictate a request for funds next year. Terri Possible Serious 6 Accept
Baily Breakdown Kristina Unlikely Serious 5 Accept
Event Estimate
Jeremy indicates that the Controls Engineering pkg will take a
miniumum of 30 days to complete and that work on it cannot
begin until the MS project is wrapped up ‐ i.e. after labor day.
Quinten has been pulled in to assist.
"we would not want the Cabinet outage to extend into 2019 if at
all possible. If we have to, we have to."
The Bailey is old; replacement parts are unreliable and at times
unavailable.
Lessons Learned – CGU2 Automation – GPSS
Lessons Learned Template 12.2016 v 1 Avista Confidential Page 1 of 8
Project Name: Cabinet Gorge Unit 2 Automation
Project ID: 30405082
Project Manager: Terri Echegoyen
1 Participants
Lessons Learned Participants
Project Team Dave Schwall, Jeremy Winkle, Brett Nephew, Mike Benstine, Shane Matteson, Dennis McCarty, Jim
Schmitt
Andrew Burgess, Chris Clemens, Laroy Dowd, Jeff Vogel, Brad McNamara, Loren Davidson
Steering Committee Alexis Alexander, Jacob Reidt, Bob Weisbeck
2 Project Performance Overview
2.1 This project was established to replace the existing Bailey control equipment for Unit 2 with a new system and to
integrate the new system with the OIT and other plant devices. It will also include a governor upgrade,
incorporate the VibroSystM into overall platform, update the Iris system, upgrade the blowdown, replace the
Exciter, install a new PPT, as well as new Protection and control panels, penstock flowmeter, and field brushes.
Total $3,269,973
For full details, please see the Final Project Report.
3 Lessons Learned Overview
Lessons Learned is defined as the learning gained from the process of performing the project. The purpose of
documenting Lessons Learned is to share and use knowledge derived from experience to:
o Promote recurrence of desirable outcomes (What went well?)
o Preclude the recurrence of undesirable outcomes (What opportunities were discovered for future
improvement?)
3.1 Project Plan – WBS Review
Task Name What went well? Opportunities for Improvement
OUTAGE No problems None
Lessons Learned – CGU2 Automation – GPSS
Lessons Learned Template 12.2016 v 1 Avista Confidential Page 2 of 8
Level 2 Clearance Issued
Mechanical
brakes
Electrical
– required modification
– ordered insulation for
-order.
Generator Breaker
PPT Something to consider
Exciter -commissioning to
Lessons Learned – CGU2 Automation – GPSS
Lessons Learned Template 12.2016 v 1 Avista Confidential Page 3 of 8
-visit.
Perhaps a pre-commissioning
Field Ground Protection
- leak. Build a
to prevent saturation.
–
– not a
Partial Discharge
– whoops!
Remove Vib/Temp Monitoring Panel
CT & PT
Turbine Bearing Flow and Pressure
gs. (RTDs)
Lessons Learned – CGU2 Automation – GPSS
Lessons Learned Template 12.2016 v 1 Avista Confidential Page 4 of 8
Generator Lockout (86G)No issues
Generator Lockout (86GD)No issues
Communications - IRIG & Ethernet
communication from Unit
/road map
AC Turbine Sump Pumps One of the very last things to
– difficult to test due to
AC & DC Turbine Oil Pumps
Governor
U2PIT Jbox No issues
Cooling Water
No issues -
(Mechanical)
Jacking Oil Pump & brakes
High Lift Oil Pump wire No issues
Blowdown
No issues wiring or plumbing
Turbine
– fixed blade vs.
Lessons Learned – CGU2 Automation – GPSS
Lessons Learned Template 12.2016 v 1 Avista Confidential Page 5 of 8
Remedial Action Scheme (RAS) - Panel 9F No issues
13.8kV Bus Differential (87B) - Panel BP1
wire
No issues
Breaker Failure (86BF) - Panel 8 wire Wiring and checkout were good –
no issues
PCM Checkout
Went well
Runner Welding
Plumb Unit
Dry Testing (W/O# 1005069782)
Able to do some great governor
testing!
Compressed but successful. Could
have used more time (1.5 days
Would have preferred to
Vendor Pre-Commissioning (W/O#
ABB
Accusonic
Verify w/SCADA that all points are in
– couldn’t communicate to
list.
Lessons Learned – CGU2 Automation – GPSS
Lessons Learned Template 12.2016 v 1 Avista Confidential Page 6 of 8
Online (on the grid) (W/O# 1005069930)
Avista Commissioning & Testing (W/O#
– hands on!
Release for Service (The End) vice document.
Lessons Learned – CGU2 Automation – GPSS
Lessons Learned Template 12.2016 v 1 Avista Confidential Page 7 of 8
4 Lessons Learned - Next Steps
4.1 Action Items
[Action items should include any near-term activity that you believe can be improved immediately as an outcome of this meeting.]
Owner Action Item Date Completed
organization ahead of time. Make a plan ahead of
4.2 Initiatives
[Initiatives are defined as items that are either complex in nature or may take longer in duration to resolve to reduce risk, increase
efficiencies, or improve future project performance.]
Owner Initiative Item Follow Up Date
4.3 Communication Plan
[The Communication Plan is developed in the meeting in order to understand how to and who will share the summarized
information.]
Owner Communication Item Date Completed/Follow Up
from management on new
Follow up:
• IRIS – PDA monitoring – will require visit once travel bans are removed.
• Exciter low power and PSS settings!!! Will require a visit from ABB once travel bans are removed
• Exciter control panel – loses connection to the exciter PLC when power cycles
• Unit synchronization – instability of the turbine – continue to look at ways to improve synchronization.
• Shane finalizing prints – back to Dave who will forward to H2E. Add P&IDs for plant review.
• PLC bearing runout probes – review dynamic settings
• Spare fuses needed – inventory and stock at plant – H2E – include fuses in material list
• Ensure that valves are ordered ahead of time.
• WECC testing – request schedule from Kestrel – Rob Selby – could we build into Unit 3 schedule along with
commissioning.
Lessons Learned – CGU2 Automation – GPSS
Lessons Learned Template 12.2016 v 1 Avista Confidential Page 8 of 8
• Operator training during commissioning week – Unit 2 still needs some training.
Project Initiation Charter Planning Phase Approval
Cabinet Gorge Gantry Crane Avista Confidential Page 1 of 7
Project Name: Cabinet Gorge Gantry Crane Replacement
Accounting Project ID: CPR 30405083
Business Case Name: Replace Cabinet Gorge Gantry Crane
ER/BI: 4178/IG502
1 Key Roles
Business Case Sponsor Jason Thackston
Andy Vickers
Business Case Owner Jacob Reidt
Business Case Funding $3,530,000 Business Case
Dept./Area
Generation &
Production
Project Sponsor Andy Vickers Program/Project
Manger
Terri Echegoyen
Steering Committee Operations
Stakeholders
Engineering
Stakeholders
Environmental
Stakeholder
Andy Vickers Alan Lackner EE – TBD Tim Swant
Mike Magruder Andrew Burgess CE – TBD
Bob Weisbeck Randy Pierce Tracy West
Brad McNamara Nathan Jones
PJ Henscheid
2 Statement of Mission Need
2.1 Business Need/Project Objectives
This project aligns with the Safe & Reliable Infrastructure strategic vision of Avista. The goal of the
project is to provide Cabinet Gorge HED with a safe and reliable crane system on top of the powerhouse,
adequate for all foreseeable lifting needs including lifting the Unit 1 generator, generator step-up
transformers and tailgate bulkheads. The objective is to replace the existing gantry crane with a
completely new crane that has a capacity of 330T.
2.2 Regulatory Drivers
There are no regulatory requirements that make this project necessary.
2.3 Metrics Demonstrating Need
The Cabinet Gorge gantry crane is over 65 years old and was used in the original construction of
Cabinet Gorge HED. Usual lifespan for equipment of this type is 50 years. Many of its components are
original equipment. Some work has been performed to update the buss bar system among other things
though past modifications have been relatively minor in scope and the crane has a long history of
breakdowns and operational problems.
Project Initiation Charter Planning Phase Approval
Cabinet Gorge Gantry Crane Avista Confidential Page 2 of 7
Most recently, during the Cabinet Gorge Unit #1 rehabilitation project spanning from 2014 to 2016,
problems with the crane caused significant delays. Some examples include:
• Relay/Contactor problem – approx. 6 days
• Gear/bearing problem – approx. 3 weeks
• Brake problem – approx. 2 days
Additional problems experienced with the crane during the Unit #1 rehabilitation are documented in a
memo by Ryan Bean, dated November 13, 2015, attached to this Project Initiation Charter as Appendix
A.
2.4 Measures to Determine Project Success
This project will be a success if a new gantry crane is transitioned into operation prior to the end of
2018, or prior to the requirements of any major transformer or generating unit replacements or
overhauls or repair. Additional measures of success include:
• Able to lift Unit 1 generator
• Extended reach to accommodate access to draft tube bulkheads
• Extended reach to accommodate access to Generation Step-up transformers
2.5 Impact if Not Approved
If the gantry crane is not replaced, its eminent failure could result in forced plant outages. Lead time
for manufacture of a gantry crane is lengthy; leaving the plant without a functioning crane puts the
plant at risk. Since there is no other means of lifting heavy unit loads, this project is necessary to
minimize lengthy forced outage time to execute major equipment upgrades in the future.
2.6 What will NOT be delivered?
No other plant systems will be altered, modified, or upgraded through the execution of this project.
3 Assumptions, Risks, and Considerations
3.1 Assumptions: (Expected Conditions)
a. The existing crane can be removed and the new crane installed without any need to upgrade or
modify the existing plant access road and powerhouse access tunnel.
b. Some rehabilitation of the existing concrete crane rail walls will be required.
c. Lead and asbestos abatement will be necessary.
d. The existing crane rails can be replaced if necessary without degrading the structural integrity
of the concrete crane rail walls on which they bear.
e. A portion of the parking area around the plant warehouse will be available for use as a laydown
area for the project.
f. Sufficient electrical power supply on the powerhouse side of the crane is available.
Project Initiation Charter Planning Phase Approval
Cabinet Gorge Gantry Crane Avista Confidential Page 3 of 7
3.2 Risks: (Potential Deviations)
a. Some components of the existing electrical power supply on the powerhouse side of the crane
may need to be replaced or upgraded.
b. An unexpected need for a heavy lift at the powerhouse could arise during the time that there is
no operable gantry crane.
c. The existing crane and trolley dead weight is unknown.
3.3 Considerations
1. Projects at Cabinet Gorge requiring use of the gantry crane will have to be scheduled around
the time period that the gantry crane is out of commission.
2. Access to the powerhouse will be restricted during the deconstruction of the existing crane and
installation of the new crane.
4 Resource Requirements
4.1 Applicable Interfaces
Requested resources in order to achieve the project objectives are as follows (check all that apply).
The specific roles and responsibilities, frequency/ type of communication, and agreed upon engagement points
will be documented in a communication plan as part of the project execution plan. This is anyone who gets
work done; anyone the project manager assigns work directly to. These stakeholders do not necessary need to
be tied to a person on the stakeholder list.
Internal (check all that apply):
☒ General Engineering
☒ Electrical Engineering
☒ Controls Engineering
☒ Mechanical Engineering
☒ Civil Engineering
☐ Substation Engineering
☐ Distribution Engineering
☐ Transmission Engineering
☒ Operations Engineering
☒ Operations (Electric/Gas/Hydro)
☐ Gas Engineering
☐ Protection Engineering
☐ SCADA Engineering
☐ Network/Communication Engineering/PM (IT/ET)
☒ Asset Management
☒ Construction Inspector
☒ Master Scheduler
☒ Maximo Support
☒ Crews/Shops: (Elect/Mech/Relay/Line)
☐ Environmental
☒ Cultural/SHPO Resources/TERO
☒ Hydro/FERC Licensing
☒ Power Supply
☒ Supply Chain – Contracts (Bid)
☒ Supply Chain – Materials/Equipment (Procurement)
☐ Real Estate
☒ Legal
☐ Corporate Communications
☐ Corporate Marketing
☐ Fleet
☒ Drafting & Survey
☒ Project & Fixed Asset Accounting
☒ Rates and Regulatory
☐ Facilities
Project Initiation Charter Planning Phase Approval
Cabinet Gorge Gantry Crane Avista Confidential Page 4 of 7
☒ External: (add/delete as applicable)
• Consultant Engineering
• Consultant Analysis/Study
• Contractor
• Inspector/Special Inspection Services
• Supplier/Vendor Engagement
4.2 High Level Project Deliverables & Milestones
To meet the primary project objective, the following artifacts will be completed.
Description Target date for completion/approval (MM/YY)
• Charter Approved
March 2017
Planning
• Owner’s Engineer on-boarded
• Technical Specifications approved
• RFP for manufacturing
• PEP Approved
•
• Operational Handoff
• Approval to Close
NLT December 2018
TBD
Closing
• Lessons Learned
• Project Closing Report
TBD
TBD
4.3 Planning Cost Estimate
Owner’s Engineer $250,000
Avista Project Management $42,000
Manufacturing $5,500,000
Demolition/Installation $975,000
AFUDC $505,000
Total $7,272,000
Assumptions in the planning cost estimate:
1. Class 4 AACE cost estimate classification: -15% to +50%
2. Avista electricians and mechanics will be required to support the project.
3. Avista Engineering will be primarily project management, however, other engineering disciplines will be
required to support the project.
4. A Consultant will be utilized to:
a. Write a performance specification for the crane.
b. Provide technical review and evaluation of crane bids.
c. Review submittals from the crane manufacturer during the design and fabrication process.
d. Provide periodic field observation of crane construction onsite.
5. Demolition of the old crane is included in the crane manufacturer’s bid.
Project Initiation Charter Planning Phase Approval
Cabinet Gorge Gantry Crane Replacement Avista Confidential - 12.2016 v1 Page 5 of 7
5 Approval Signatures
_________________________________________________________ 02/27/2017
Andy Vickers, Director GPSS Date
_________________________________________________________ _____________
Mike Magruder, Manager Hydro Ops & Maintenance Date
_________________________________________________________ _____________
Bob Weisbeck, Manager Project Delivery Date
Project Initiation Charter Planning Phase Approval
Cabinet Gorge Gantry Crane Replacement Avista Confidential - 12.2016 v1 Page 6 of 7
APPENDIX A
DATE: November 13th, 2015
TO: File, Jacob Reidt, Randy Pierce, Bob Weisbeck, Mike Shoff
FROM: Ryan Bean
SUBJECT: Cabinet Gorge Unit 1 – Gantry Crane Rotor Pick Problems
Background
The scope of work during the Unit 1 rehabilitation included two picks of the generator rotor complete with field
poles installed. The first pick removed the rotor from the stator and placed it in the shop for field pole removal.
The rotor was then moved to the rotor storage building until the field poles were returned after being
refurbished by RPR Hydro (subcontractor to GE). The field poles were reinstalled in the rotor storage building
and the rotor was then placed back in the stator.
An Engineered Pick Plan was produced in accordance with ASME Code Section B30.2-3.1.7 that allows for
occasional picks for loads exceeding rated limits up to 125% of the nameplate rating. The crane nameplate is
275 tons with an occasional pick of up to 343.8 tons. The rotor with lifting device weighs approx 330 tons. The
cranes ability to lift this load was confirmed by Bedford Crane during the initial installation. The code allows an
occasional pick not to exceed two occurrences in a 12 month period provided the crane manufacturer or other
qualified person has reviewed the crane design to handle the load.
Inconsistencies During Operation
During the initial removal of the rotor from the stator, the micro drive and main hoist motor were used. The
micro drive operated as expected, however the main hoist motor appeared to struggle when initially engaged.
While returning the rotor to the stator on September 22nd, 2015, an issue was experienced where the main hoist
did not operate as expected during raising. This was a repeatability issue with the main hoist where the hoist
may raise, stall, or lower the rotor when the control lever was taken back into the same notch repeatedly. The
lift was stopped and an investigation followed.
Investigation and Troubleshooting
With assistance from PCI and K&N Electric, an investigation and troubleshooting of the power and control
systems followed. Components checked included the control lever, overloads, contactors, resistors, motor
currents, brakes, and micro-drive operation. Everything appeared to be operating correctly, albeit in an
overloaded condition due to the above nameplate load. The micro-drive operated reliably throughout testing.
This lead us to believe the problem resides downstream of the control system, potentially with either the motor
output or mechanical drive system. The gear train was visually inspected via available access ports and
appeared to be in good shape and operated smoothly.
Original records of the hoist motor test data indicate the existing hoist motor reaches its nameplate current of
160 amps at a load of approximately 205 tons. This limits the service cycle at 240 amps with a load of approx.
320 amps to approximately one to two minutes without overheating resistor banks. This would require several
Project Initiation Charter Planning Phase Approval
Cabinet Gorge Gantry Crane Replacement Avista Confidential - 12.2016 v1 Page 7 of 7
lifting and cooling off periods to complete the lift. This reflects what we experienced in the field with tripping of
the overload relays during sustained lifting at approx. 250 amps.
The crane micro-drive arrangement was also inspected, which consists of an additional motor and speed reducer
that can be clutched in or out as necessary. The arrangement utilizes the same main hoist drivetrain and brakes
(with an additional motor brake) without using the main hoist motor. Per Mark Oney’s crane evaluation dated
May 10, 1994 and design drawings, the micro-drive is rated for continuous duty without overheating. Hoisting
speed is reduced during operation to slightly less than 0.5 feet per minute.
Conclusion
This has historically been a difficult pick for this crane and the system appears to have reached an impasse
where the main hoist is no longer capable of producing the power to function at 100%. We suspect the issue
lies in either the motor output, which has been operated above its nameplate current a number of times in the
past, or due to an increase in mechanical drag in the gear train.
Per the results of our initial investigation and a stakeholder meeting on October 5th, 2015, (Ryan Bean, Andy
Vickers, Mike Gonnella, Bob Weisbeck, Brand McNamara, Rob Selby, and Jeremy Winkle in attendance) and in
agreement with the project Foreman Mike Shoff, the rotor pick was completed using the installed micro-drive
system, without the use of the main hoist motor.
References
1. CG 1 Rotor Pick Plan Oct 2015 Rev1
2. ASME Crane code for CG1
3. Crane Report by Mark Oney, May 10 994
4. D-15701s001c1952 – Gantry Clearance Diagram with notes
5. 304E-25-040-01-01, 02, 03, 04, 05, 08 – Micro Drive Arrangement Drawings
6. 1952 Load Test Data
7. 1993 Load Test Data
CG Gantry Crane Requirements Gathering – Thursday, May 18, 2017
Attendees: Randy Pierce, Tracy West, Dick Garrison, Bob Weisbeck, Dave Schwall, Dennis McCarty, Terri
Echegoyen
Invitees included:
Must Haves Nice to Haves
Install midrail and toe plate around cab opening
CG Gantry Crane Requirements Gathering – Thursday, May 18, 2017
Attendees: Randy Pierce, Tracy West, Dick Garrison, Bob Weisbeck, Dave Schwall, Dennis McCarty, Terri
Echegoyen
Next Steps:
• Hire consultant to write specifications. Simmers? Eureka!Engineering? Other?
• Decision Point: rehab or new?
o Coffman’s replacement quote spanned $5.2 million to $6 million
o Simmer’s rehab quote was for $1.2 million
Quote does not include lead paint abatement and repainting w/epoxy paint
• Site visits to review some of Simmers other projects
o Affiliate company, Advanced Crane Technologies has worked on sites in Portland and
Walla Walla Districts and at Gavins/Garrisson/Ft Randall on the Missouri River
• Power rail (480V)?
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
1 Full Crane Rehabilitation 211 days?Thu 7/20/17 Thu 5/10/18 $307,123.00
2 Site visit 3 days Thu 7/20/17 Mon 7/24/17 $0.00
3 Drum cast iron testing 10 days Mon 8/14/17Fri 8/25/17 $0.00
4 Drums removed 1 day Thu 7/20/17 Thu 7/20/17 $0.00
5 Calculation and designs for new drive hoist including panel
arrangements and wiring interconnect
1 day Wed
8/30/17
Wed 8/30/17 $0.00
6 Capacity Analysis Report 1 day Fri 11/3/17 Fri 11/3/17 $0.00
7 Simmers Proposal (-1706963-6)1 day?Wed 11/29/17Wed 11/29/17 $0.00
8 Contract Fully Executed 1 day?Fri 3/23/18 Fri 3/23/18 $307,123.00
9 Site Visit #1 4 days Mon 4/9/18 Thu 4/12/18 Paul Miller $0.00
10 Site Visit #2 w/CSD, Rhodes, S&S and NW Sandblasting 4 days Mon 5/7/18 Thu 5/10/18 Chris Truitt $0.00
11 Concrete/Runway Evaluation 92 days Mon 3/26/18Tue 7/31/18 $0.00
12 Preliminary condition report 10 wks Wed 5/16/18Tue 7/24/18 CSD $0.00
13 Submittal 071018A 1 day Wed 5/16/18Wed 5/16/18 $0.00
14 Analysis Report 1 day Tue 7/31/18 Tue 7/31/18 CSD $0.00
15 Submittal 091818A 1 day Tue 7/31/18 Tue 7/31/18 $0.00
16 Runway Repair Details 1 day Mon 3/26/18Mon 3/26/18 $0.00
17 Submittal 102918A 1 day Mon 3/26/18Mon 3/26/18 $0.00
18 Priority 1 202 days Mon 3/26/18Tue 1/1/19 $767,808.00
19 Controls & Electrification Engineering 14 days Tue 6/5/18 Fri 6/22/18 8 $0.00
20 Submittal #060518a 14 days Tue 6/5/18 Fri 6/22/18 Quinton Snead,Dave Schwall $0.00
21 Order Controls & Electrification Materials 16 wks Mon 6/25/18Fri 10/12/18 19 $0.00
22 End Trucks, Bridge Wheels & Bridge Drive Engineering 1 day Tue 7/3/18 Tue 7/3/18 $0.00
23 Submittal #070218A 1 day Tue 7/3/18 Tue 7/3/18 $0.00
24 Order Bridge Materials 26 wks Wed 7/4/18 Tue 1/1/19 22 $0.00
25 Main Hoist Mechanical Components Engineering 12 wks Mon 3/26/18Fri 6/15/18 $0.00
26 Submittal #052218a 16 days Tue 5/22/18 Tue 6/12/18 Tracy West $0.00
27 Order Main Hoist Materials 19 wks Mon 5/14/18Fri 9/21/18 $0.00
28 Review & Acceptance of all Priority 1 Drawings 5 days Mon 6/4/18 Fri 6/8/18 $307,123.00
3/23
Paul Miller
Chris Truitt
Quinton Snead,Dave Schwall
Tracy West
6/8
T M F T S W S T M F T
Jun 18, '17 Jul 30, '17 Sep 10, '17 Oct 22, '17 Dec 3, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: CG Gantry Crane5
Date: Mon 4/15/19
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
29 Confirmation of Orders Placed for Priority 1 Materials 5 days Mon 5/21/18Fri 5/25/18 $460,685.00
30 Priority 2 210 days?Mon 4/9/18 Fri 1/25/19 $0.00
31 Aux Hoist Mechanical Engineering 10 wks Tue 8/28/18 Mon 11/5/18 $0.00
32 Submittal #082818A 10 days Tue 8/28/18 Mon 9/10/18 $0.00
33 Order Aux Hoist Materials 21 wks Mon 9/3/18 Fri 1/25/19 $0.00
34 Trolley Enclosure Engineering 9 wks Mon 5/21/18Fri 7/20/18 $0.00
35 Submittal 041119A 1 day Mon 5/21/18Mon 5/21/18 $0.00
36 Order Trolley Enclosure Materials & Fabricate 21 wks Mon 7/30/18Fri 12/21/18 $0.00
37 Trolley Wheels Engineering 8 wks Mon 4/9/18 Fri 6/1/18 $0.00
38 Submittal #121818A 1 day Mon 4/9/18 Mon 4/9/18 $0.00
39 Order Trolley Wheels Materials 18 wks Mon 6/11/18Fri 10/12/18 $0.00
40 Review & Acceptance of all Priority 2 Drawings 5 days Mon 9/10/18Fri 9/14/18 $0.00
41 Confirmation of Orders Placed for Priority 2 Materials Mon 9/10/18 $0.00
42
43
44 Receipt of Priority 1 Materials Mon 11/5/18 $0.00
45 Receipt of Priority 2 Materials Fri 1/25/19 $0.00
46
47 Priority 3 65 days?Mon 7/9/18 Fri 10/5/18 $0.00
48 Cab Windows & Other Miscellaneous Engineering 6 wks Mon 7/9/18 Fri 8/17/18 $0.00
49 Submittal 031219A 1 day Mon 7/9/18 Mon 7/9/18 $0.00
50 Review & Acceptance of all Priority 3 Drawings 5 days Mon 8/20/18Fri 8/24/18 $0.00
51 Order Cab Windows & Miscellaneous Materials 7 wks Mon 8/20/18Fri 10/5/18 $0.00
52 Confirmation of Order Placed for Priority 3 Materials Mon 9/10/18 $0.00
53 Evaluate & Update Lead Times & Discuss Installation 5 days Mon 7/9/18 Fri 7/13/18 $0.00
54 $0.00
55 Change Order #3 66 days Wed 5/1/19 Wed 7/31/19 $0.00
56 Below the Hook Analysis 66 days Wed 5/1/19 Wed 7/31/19 $0.00
57 Fall Protection (engineering, materials and installation)66 days Wed 5/1/19 Wed 7/31/19 $0.00
58 Trolley Drive Shaft Modifications (engineering, materials, installation)66 days Wed 5/1/19 Wed 7/31/19 $0.00
5/25TMFTSWSTMFT
Jun 18, '17 Jul 30, '17 Sep 10, '17 Oct 22, '17 Dec 3, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: CG Gantry Crane5
Date: Mon 4/15/19
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
59
60 Construction 16 wks Mon 3/18/19Fri 7/5/19 Simmers $0.00
61 Onsite Orientation/Safety Training 0.5 days Mon 3/18/19Mon 3/18/19 $0.00
62 Staging Equipment 1 day Mon 3/18/19Tue 3/19/19 61 $0.00
63 Demolition 14 days Tue 3/19/19 Mon 4/8/19 62 Simmers $0.00
64 Build Scaffolding 10 days Mon 4/8/19 Fri 4/19/19 63 Safway $0.00
65 Erect Containment 5 days Wed 4/17/19Tue 4/23/19 64 $0.00
66 Sandblast and Primer 7 wks Wed 4/24/19Tue 6/11/19 65 S&S Coatings $0.00
67 Full upgrade 13 wks Mon 6/17/19Fri 9/13/19 66 Simmers $0.00
76 Load Testing 1 wk Mon 9/16/19Fri 9/20/19 67 $0.00
77 Final paint 4 wks Mon 9/23/19Fri 10/18/19 76 S&S Coatings $0.00
78
79 Re-stripe the deck $0.00
T M F T S W S T M F T
Jun 18, '17 Jul 30, '17 Sep 10, '17 Oct 22, '17 Dec 3, '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: CG Gantry Crane5
Date: Mon 4/15/19
3/23
Paul Miller
Chris Truitt
7/31
Quinton Snead,Dave Schwall
Tracy West
6/8
T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W
Dec 3, '17 Jan 14, '18 Feb 25, '18 Apr 8, '18 May 20, '18 Jul 1, '18 Aug 12, '18 Sep 23, '18 Nov 4, '18 Dec 16, '18 Jan 27, '19 Mar 10, '19 Apr 21, '19 Jun 2, '19 Jul 14, '19 Aug 25, '19 Oct 6, '19
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: CG Gantry Crane5
Date: Mon 4/15/19
5/25
9/14
9/10
11/5
1/25
8/24
9/10
T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W
Dec 3, '17 Jan 14, '18 Feb 25, '18 Apr 8, '18 May 20, '18 Jul 1, '18 Aug 12, '18 Sep 23, '18 Nov 4, '18 Dec 16, '18 Jan 27, '19 Mar 10, '19 Apr 21, '19 Jun 2, '19 Jul 14, '19 Aug 25, '19 Oct 6, '19
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: CG Gantry Crane5
Date: Mon 4/15/19
Simmers
Safway
S&S Coatings
S&S Coatings
T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W
Dec 3, '17 Jan 14, '18 Feb 25, '18 Apr 8, '18 May 20, '18 Jul 1, '18 Aug 12, '18 Sep 23, '18 Nov 4, '18 Dec 16, '18 Jan 27, '19 Mar 10, '19 Apr 21, '19 Jun 2, '19 Jul 14, '19 Aug 25, '19 Oct 6, '19
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: CG Gantry Crane5
Date: Mon 4/15/19
Project Monthly Report – August 2019
Cabinet Gorge Gantry Crane – 30405083
Project Manager – Terri Echegoyen
(thru
7/31/19): $3,988,031 7/31/19): $5,746,745
2019
Expected Transfer to Plant Date: 9/16/19 at time of transfer: $7,238,741
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is
non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost;
Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Completion Date ormance
Fall Protection 07/31/19
Trolley Drive Shaft Modifications 07/31/19
Below the Hook Analysis 07/31/19 7/30/19 complete
Oil and lubricant installation 8/1/19 8/1/19 complete
Testing to begin 8/5/19
Load Test
Summary:
• North and East trolley walls are now installed. Final West wall is en-route. Next is the lower platform.
Once the hoist reeves are tested out, ceiling panels can be installed.
• Just received the wire rope for both main and aux hoist.
• Two cab windows are installed. Other frames are expected on Sunday and will be installed by Tuesday of
next week.
• Steelhead will work with Simmers on the AC unit for the control house.
• All conduit is complete. Everything is mounted, wire pulls are done and terminations continue with
exception of the trolley limits.
• Intend to change the tag over tomorrow; power up crane to begin checkout and setup steps w/Shane.
• Bump test motors; auto tune. Electrically speaking, everything should be completely wrapped up by the
weekend.
• Load test may occur the last week of August.
• Waiting on estimate for festoon replacement which will be presented to the steering committee.
Risks/Issues:
Project Monthly Report – August 2019
There is still some question as to what extent the crane can be used without concrete repairs. The crane is
critical path to most of the work scheduled to take place at Cabinet this fall. It has been suggested that
additional testing of core samples to verify strength and chemical composition would be appropriate.
Project Monthly Report – June 2019
Cabinet Gorge Gantry Crane – 30405083
Project Manager – Terri Echegoyen
(thru
6/30/19): $2,277,392 6/30/19): $4,036,106
2019
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is
non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Completion Date ormance
Runway Repair Design Drawings ($12,767) 7/12/19
Fall Protection 07/31/19
Trolley Drive Shaft Modifications 07/31/19
Below the Hook Analysis 07/31/19
Oil and lubricant installation 8/1/19
Testing to begin 8/5/19
Load Test
Release to Limited Service
Summary: All containment and scaffolding has been
removed. Painting will be performed by hand with brushes
and rollers rather than spray. Nearly all mechanical work has
been complete opening the door to the electrical portion.
Simmers has a crew of four on hand. Expecting to begin
testing the first week of August.
RFP for concrete repair/restoration will be launched as soon
as design drawings are delivered (expected 7/12/19)
Risks/Issues:
1) There is some question as to what extent the crane
can be used without concrete repairs. The crane is critical path to most of the work scheduled to take
place at Cabinet this fall. A meeting to discuss this issue has been scheduled for July 19th.
Project Monthly Report – July 2019
Cabinet Gorge Gantry Crane – 30405083
Project Manager – Terri Echegoyen
(thru
6/30/19): $1,590,644 6/30/19): $3,417,581
2019
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is
non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Completion Date ormance
Runway Repair Design Drawings ($12,767) 7/12/19
Fall Protection 07/31/19
Trolley Drive Shaft Modifications 07/31/19
Below the Hook Analysis 07/31/19
Trolley Enclosure Components
Trolley Wheels & Components
Cab Windows & Misc. Components
Summary: sandblasting, priming and intermiadate paint complete. All
spent sand blast media disposed of and equipment demobilized.
Painting will begin on the water side and will finish after all scaffolding is
removed – July 1st. With the containment and scaffolding removed,
Simmers will have better access to the crane which will expidite
installation. Painting will continue along side installation but will be
performed by hand with brushes and rollers rather than spray.
RFP for concrete repair/restoration will be launched as soon as design drawings are delivered (expected
7/12/19)
Risks/Issues:
1) There is some question as to what extent the crane can be used without concrete repairs. The crane is
critical path to most of the work scheduled to take place at Cabinet this fall.
Project Monthly Report – June 2019
Cabinet Gorge Gantry Crane – 30405083
Project Manager – Terri Echegoyen
(thru
5/31/19): $1,590,644 5/31/19): $3,417,581
2019
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is
non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost; Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Completion Date ormance
Runway Repair Design Drawings ($12,767) 7/12/19
Fall Protection 07/31/19
Trolley Drive Shaft Modifications 07/31/19
Below the Hook Analysis 07/31/19
Trolley Enclosure Components
Trolley Wheels & Components
Cab Windows & Misc. Components
Summary: sandblasting, priming and intermiadate paint complete. All
spent sand blast media disposed of and equipment demobilized.
Painting will begin on the water side and will finish after all scaffolding is
removed – July 1st. With the containment and scaffolding removed,
Simmers will have better access to the crane which will expidite
installation. Painting will continue along side installation but will be
performed by hand with brushes and rollers rather than spray.
RFP for concrete repair/restoration will be launched as soon as design drawings are delivered (expected
7/12/19)
Risks/Issues:
1) There is some question as to what extent the crane can be used without concrete repairs. The crane is
critical path to most of the work scheduled to take place at Cabinet this fall.
Project Monthly Report – April 2019
Cabinet Gorge Gantry Crane – 30405083
Project Manager – Terri Echegoyen
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is
non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost;
Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
addressed in Change Order #3.
Concrete work will be needed. See
funding in Q2 - $4m
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Completion Date ormance
Runway Repair Design Drawings
Controls & Electrical (060518A) 5/11/18 6/5/18 Complete
End Trucks, Bridge Wheels & Drive Bridge (070218A) 6/15/18 7/2/18 Complete
Main Hoist – Mechanical (052218A) 6/15/18 5/22/18 Complete
Trolley Wheels, axles and bushings (121818A) 9/7/18 12/18/18 Complete
Control House Mounting (110218A) Complete
Trolley Enclosure (041119A) 4/11/19 Complete
Cab Windows & Miscellaneous Items (031219A) Complete
Fall Protection 07/31/19
Trolley Drive Shaft Modifications 07/31/19
Priority 1 items ordered: Controls & Electrical Components,
bridge, main hoist
Orders placed:
September ‘18
Expected delivery:
January 2019
Aux Hoist Components 1/25/19
Trolley Enclosure Components
Trolley Wheels & Components
Cab Windows & Misc. Components
Other: Change Order #3 is in the supply chain queue. A steerco meeting has been scheduled for Monday, April
15th.
Risks/Issues:
1) The jib crane and access to the erection bay will be unavailable from May 6th to June 14th.
2) Meeting with Simmers, CSD and Avista engineering on April 1st to determine next steps with regard to
the condition of the concrete. What is the recommended path forward? We plan to proceed with a
limited RFP in order to obtain budgetary quotes for phased repair approach.
Project Monthly Report – March 2019
Cabinet Gorge Gantry Crane – 30405083
Project Manager – Terri Echegoyen
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is
non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost;
Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
addressed in Change Order #3.
Concrete work will be needed. See
will dramatically pick up this year
as construction gets underway.
March 2019. Concrete work
may delay the crane’s
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Completion Date ormance
Concrete Analysis – Preliminary Report (071018A) 7/9/18 7/10/18 Complete
Concrete Analysis – Final Report 7/31/18 9/18/15 Complete
Runway Repair Design Drawings Complete
Controls & Electrical (060518A) 5/11/18 6/5/18 Complete
End Trucks, Bridge Wheels & Drive Bridge (070218A) 6/15/18 7/2/18 Complete
Main Hoist – Mechanical (052218A) 6/15/18 5/22/18 Complete
Trolley Wheels, axles and bushings (121818A) 9/7/18 12/18/18 Complete
Control House Mounting (110218A) Complete
Trolley Enclosure Pending
Cab Windows & Miscellaneous Items Pending
Priority 1 items ordered: Controls & Electrical Components,
bridge, main hoist
Orders placed:
September ‘18
Expected delivery:
January 2019
Aux Hoist Components 1/25/19
Trolley Enclosure Components
Trolley Wheels & Components
Cab Windows & Misc. Components
Risks/Issues:
1) The jib crane and access to the erection bay will be unavailable from May 6th to June 14th.
2) Meeting with Simmers, CSD and Avista engineering on _______ to determine next steps with regard to
the condition of the concrete. What is the recommended path forward?
Project Monthly Report – February 2019
Cabinet Gorge Gantry Crane – 30405083
Project Manager – Terri Echegoyen
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is
non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost;
Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
addressed in Change Order #3.
Concrete work will be needed. See
will dramatically pick up this year
as construction gets underway.
March 2019. Concrete work
may delay the crane’s
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Baseline
Completion Completion Date ormance
Concrete Analysis – Preliminary Report (071018A) 7/9/18 7/10/18 Complete
Concrete Analysis – Final Report 7/31/18 9/18/15 Complete
Runway Repair Design Drawings Complete
Controls & Electrical (060518A) 5/11/18 6/5/18 Complete
End Trucks, Bridge Wheels & Drive Bridge (070218A) 6/15/18 7/2/18 Complete
Main Hoist – Mechanical (052218A) 6/15/18 5/22/18 Complete
Trolley Wheels, axles and bushings (121818A) 9/7/18 12/18/18 Complete
Control House Mounting (110218A) Complete
Trolley Enclosure Pending
Cab Windows & Miscellaneous Items Pending
Priority 1 items ordered: Controls & Electrical Components,
bridge, main hoist
Orders placed:
September ‘18
Expected delivery:
January 2019
Aux Hoist Components 1/25/19
Trolley Enclosure Components
Trolley Wheels & Components
Cab Windows & Misc. Components
Risks/Issues:
1) Upon receipt of the crane’s runway analysis report in September 2018, it was not immediately evident
that concrete repairs would be required in order to ensure the supporting concrete wall and gantry
crane rail anchorage is sufficiently robust to withstand the increase in potential loads. Not until Simmers
supplied CSD’s notes (1/30/19) regarding how Avista should proceed did we become aware that the
anchorage and supporting concrete wall is in generally poor condition and needs to be addressed. A
contractor will need to develop construction drawings based on CDS’s final design drawings, provide
additional analysis and design detail, and perform construction services to bring the gantry crane
Project Monthly Report – February 2019
runway to the conditions noted in the final construction drawings and as required by the additional
analysis.
2) Simmers has subcontracted with both Safway (scaffolding) and S&S Coatings (lead abatement, priming,
painting). The three vendors held an on-site meeting on February 12th to review the deck plan. Safway
will supply drawings for Avista to review and approve but, it should be noted that although every effort
will be made to ensure access to the jib crane is maintained throughout the duration of the
rehabilitation, there will be a period of roughly six weeks when the jib crane will be inaccessible.
Project Monthly Report – January 2019
Cabinet Gorge Gantry Crane – 30405083
Project Manager – Terri Echegoyen
1
Table 1. At-a-glance overall status report (see risks and mitigation section for detail). Red = cost and schedule exceeds baseline and is
non-recoverable; Yellow = currently overspent or currently behind schedule but recoverable to baseline end date and total cost;
Green =meeting or exceeding the baseline expectations for cost or schedule.
Scope: Budget: Schedule:
addressed in Change Order #3. by $3,906. to begin March 2019
Table 2. Milestone status and planned, projected and actual completion dates
Milestone Baseline Completion Completion Date ormance
Concrete Analysis – Preliminary Report (071018A) 7/9/18 7/10/18 Complete
Concrete Analysis – Final Report 7/31/18 9/18/15 Complete
Runway Repair Design Drawings Complete
Controls & Electrical (060518A) 5/11/18 6/5/18 Complete
End Trucks, Bridge Wheels & Drive Bridge (070218A) 6/15/18 7/2/18 Complete
Main Hoist – Mechanical (052218A) 6/15/18 5/22/18 Complete
Trolley Wheels, axles and bushings (121818A) 9/7/18 12/18/18 Complete
Control House Mounting (110218A) Complete
Trolley Enclosure Pending
Cab Windows & Miscellaneous Items Pending
Priority 1 items ordered: Controls & Electrical Components,
bridge, main hoist
Orders placed:
September ‘18
Expected delivery:
January 2019
Aux Hoist Components 1/25/19
Trolley Enclosure Components
Trolley Wheels & Components
Cab Windows & Misc. Components
Other:
• Jessica Bean is reviewing the design drawings provided by CSD for concrete repairs.
• Change Order #3 is begin drafted. It will incorporate costs for man lift rental, mobile crane and operator (previously identified
as Avista’s responsibility) and below-the-hook device analysis in addition to identifying costs for sandblasting and coating the
crane an element that had previously been identified in Change Order #1 but, was not given a budgetary quote.
• Mechanical Engineer Tracy West has suffered an accident and will be out-of-work until roughly January 21st. However, his
absence should not cause any risk to the project at this juncture.
• Runway Repair Design Drawings were stamped by a PE. Jessica reviewed and had no comments.
1 Budget increased by $169,366 with Change Order #2.