HomeMy WebLinkAbout20031229_718.pdfDECISION MEMORANDUM
TO:COMMISSIONER KJELLANDER
COMMISSIONER SMITH
COMMISSIONER HANSEN
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL STAFF
FROM:WELDON STUTZMAN
DATE:DECEMBER 23, 2003
RE:CASE NO. IPC-93-
APPROVAL OF SETTLEMENT STIPULATION BETWEEN IDAHO
POWER COMPANY AND NEW VILLAGER CONDOMINIUM
ASSOCIATION
Following an earlier pre-hearing conference, the Commission on October 23, 2003
issued a procedural order approving a schedule to process this case, including a hearing set for
March 4, 2004. On December 19, 2003 , Idaho Power and New Villagers Condominium
Association filed a Settlement Stipulation and a Petition for Approval of Settlement and Stay of
Procedural Schedule. In their joint petition, the parties indicate that the Settlement Agreement
resolves their dispute, pending completion of construction work contemplated in the spring or
fall of 2004. The parties asked the Commission to approve their Settlement Agreement, and also
issue an order vacating the procedural schedule. After the construction work is complete, the
parties can so notify the Commission and this case can then be dismissed.
Pursuant to Commission Rule of Procedure 274, the Commission "may summarily
accept settlement of an essentially private dispute that has no significant implications for
regulatory law or policy or for other utilities or customers upon the written request of the
affected parties." The Settlement Stipulation between Idaho Power Company and New Villager
Condominium Association may be summarily accepted by the Commission pursuant to this rule.
Staff recommends the Commission accept and approve the Settlement Stipulation filed by Idaho
Power Company and the New Villager Condominium Association, and issue an order vacating
the procedural schedule previously established by the Commission.
DECISION MEMORANDUM
COMMISSION DECISION
Should the Commission issue an order approving the Settlement Stipulation filed by
the parties and vacating the procedural schedule?
.....
Weldon Stutzman
Vld/M:IPEE9310 ws2
DECISION MEMORANDUM