BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION)
OF UTAH POWER AND LIGHT COMPANY)CASE NO. UPL-E-96-4
FOR APPROVAL OF NEW TARIFF )
PROVISIONS RELATING TO NEW SERVICE)SECOND PRODUCTION
ATTACHMENTS AND DISTRIBUTION LINE)REQUEST OF THE
INSTALLMENTS OR ALTERATIONS.)COMMISSION STAFF
)TO UTAH POWER & LIGHT
___________________________________________)
The Staff of the Idaho Public Utilities Commission, by and through its attorney of record, Brad Purdy, Deputy Attorney General, requests that Utah Power and Light Company, a division of PacifiCorp, provide the following documents and information, pursuant to Rule 225 of the Idaho Public Utilities Commission’s Rules of Procedure, IDAPA 31.01.01, on or before NOVEMBER 8, 1996.
This Production Request is to be considered as continuing, andUtah Power and Light Company is requested to provide, by way of supplementary responses, additional documents that it or any person acting on its behalf may later obtain that will augment the documents produced.
For each item, please indicate the name of the person(s) preparing the answers, along with the job title of such person(s) and the witness who can sponsor the answer at hearing.
Unless stated otherwise, all requests should be considered for Utah Power’s or PacifiCorp’s Idaho jurisdiction only.
Request No. 44: Provide a copy of source documents and any associated workpapers used to develop Exhibit Nos. 1 and 2 of the direct testimony of PacifiCorp witness D. Douglas Larson.
Request No. 45: Provide at least two additional examples of the line extension charges under the current and the proposed line extension policies for each of the following types of customers: residential subdivisions, single residential customers, and commercial customers.
Request No. 46: Provide an analysis showing whether a correlation exists, and if so, what the relationship is, between the cost of terminal facilities (transformer, meter, and service) and connected load. In addition, provide revised copies of Response No. 8 to Staff’s First Production Request that also include either the connected load for each customer or the kva rating of the transformer for each customer.
DATED at Boise, Idaho, this day of November 1996.