Loading...
HomeMy WebLinkAbout20210920PAC to Bayer 117-142 SIS Report_Rev1.pdf Large Generator Interconnection System Impact Study Report Completed for PacifiCorp Energy Supply Management Pryor Mountain Wind Proposed Point of Interconnection Frannie-Yellowtail 230 kV transmission line August 16, 2019 System Impact Study Report TABLE OF CONTENTS 1.0 DESCRIPTION OF THE GENERATING FACILITY .................................................................... 1 2.0 SCOPE OF THE STUDY ................................................................................................................. 1 3.0 TYPE OF INTERCONNECTION SERVICE .................................................................................. 2 4.0 DESCRIPTION OF PROPOSED INTERCONNECTION ............................................................... 2 5.0 STUDY ASSUMPTIONS ................................................................................................................. 3 6.0 ENERGY RESOURCE (ER) INTERCONNECTION SERVICE .................................................... 4 6.1.1 Requirements 4 6.1.2 Cost Estimate (ER) 11 7.0 APPENDICES ................................................................................................................................ 13 7.1 Appendix 1: Higher Priority Requests ............................................................................................ 14 7.2 Appendix 2: Contingent Facilities .................................................................................................. 15 7.3 Appendix 3: Property Requests ....................................................................................................... 16 7.4 Appendix 4: Study Results .............................................................................................................. 18 System Impact Study Report PacifiCorp Energy Supply Management Page 1 August 16, 2019 Pryor Mountain Wind, Q0542 1.0 DESCRIPTION OF THE GENERATING FACILITY PacifiCorp ESM (“Interconnection Customer”) proposed interconnecting 240 MWs of new generation to PacifiCorp’s (“Transmission Provider”) Frannie–Yellowtail 230 kV transmission line approximately 14 miles north of the Frannie substation located in Park County, Montana. The Pryor Mountain Wind project (“Project”) will consist of 55 Vesta V110-2.0MK10B, 24 Vestas V110-2.2MK10C, 29 Vestas V110-2.2MK10D, and 4 GE2.3-116 wind turbine generators for a total output of 240 MWs. The requested commercial operation date is approximately December 1, 2020. Interconnection Customer will NOT operate this generator as a Qualified Facility as defined by the Public Utility Regulatory Policies Act of 1978 (PURPA). 2.0 SCOPE OF THE STUDY This restudy is being performed for the following reasons: 1. The Interconnection Customer requested to move the physical location of the Point of Interconnection substation which the Transmission Provider determined was not a Material Modification. 2. The Interconnection Customer requested to switch the jurisdiction of the Interconnection Request from a state jurisdictional qualifying facility project to a FERC jurisdictional project which the Transmission Provider determined was not a Material Modfication. The interconnection system impact study shall evaluate the impact of the proposed interconnection on the reliability of the transmission system. The interconnection system impact study will consider Base Case as well as all generating facilities (and with respect to (iii) below, an identified network upgrades associated with such higher queued interconnection) that, on the date the interconnection system impact study is commenced: (i) are directly interconnected to the transmission system; (ii) are interconnected to Affected Systems and may have an impact on the interconnection request; (iii) have a pending higher queued interconnection request to interconnect to the transmission system; and (iv) have no Queue Position but have executed an LGIA or requested that an unexecuted LGIA be filed with FERC. The interconnection system impact study will consist of a short circuit analysis, a stability analysis, and a power flow analysis. The interconnection system impact study will state the assumptions upon which it is based; state the results of the analyses; and provide the requirements or potential impediments to providing the requested interconnection service, including preliminary indication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the interconnection. The interconnection system impact study will provide a list of facilities that are required as a result of the Interconnection Request and a non-binding good faith estimate of the cost responsibility and a non-binding good faith estimated time to construct. System Impact Study Report PacifiCorp Energy Supply Management Page 2 August 16, 2019 Pryor Mountain Wind, Q0542 3.0 TYPE OF INTERCONNECTION SERVICE The Interconnection Customer has selected Energy Resource (ER) Interconnection Service. 4.0 DESCRIPTION OF PROPOSED INTERCONNECTION The Interconnection Customer’s proposed Generating Facility is to be interconnected to the Frannie-Yellowtail 230 kV transmission line via a new Point of Interconnection substation to be located approximately 14 miles from the Frannie substation. Figure 1 below is a one-line diagram that illustrates the interconnection of the proposed Generating Facility to the Transmission Provider’s system. System Impact Study Report PacifiCorp Energy Supply Management Page 3 August 16, 2019 Pryor Mountain Wind, Q0542 Yellowtail Substation Q0542 POI Substation 230 kV Frannie Substation Garland Substation Point of Interconnection Change of ownership 14.26 Miles 41.14 Miles M Oregon Basin Substation 34.5 kV Q0542 Collector Substation 12 – 2.0 MW WTG M2.0 MW 690 V 2.1 MVA Z=8.7% @1.9 MVA 690 V 2.2 MW 2.3 MVA Z=8.7% @ 2.06 MVA1 – 2.2 MW WTG 11 – 2.0 MW WTGTotal 35-1 35-2 12 – 2.0 MW WTG 35-3 12 – 2.0 MW WTG 35-4 3 – 2.2 MW WTG 8 – 2.0 MW WTG 35-5 M 9 – 2.2 MW WTG 2 – 2.0 MW WTG 35-6 690 V 690 V 2.3 MW 2,421 kVA 2.3 MVA Z=5.75 %7 – 2.2 MW WTG 4 – 2.3 MW WTGTotal 35-7 2.2 MW 11 – 2.2 MW WTG 35-8 11 – 2.2 MW WTG 35-9 11 – 2.2 MW WTG 35-10 2.3 MVA Z=8.7% @ 2.06 MVA 90/120/150 MVA Z=9% 90/120/150 MVA Z=9%230-1 230-2 Figure 1: Simplified System One Line Diagram 5.0 STUDY ASSUMPTIONS  All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are listed in Appendix 1. If any of these requests are withdrawn, the Transmission Provider reserves the right to restudy this request, and the Results and conclusions could significantly change.  For study purposes there are two separate queues: System Impact Study Report PacifiCorp Energy Supply Management Page 4 August 16, 2019 Pryor Mountain Wind, Q0542 o Transmission Service Queue: to the extent practical, all network upgrades that are required to accommodate active transmission service requests will be modeled in this study. o Generation Interconnection Queue: Interconnection Facilities associated with higher queue interconnection requests will be modeled in this study.  The Interconnection Customer’s request for energy or network resource interconnection service in and of itself does not convey transmission service. Only a Network Customer may make a request to designate a generating resource as a Network Resource. Because the queue of higher priority transmission service requests may be different when a Network Customer requests network resource designation for this Generating Facility, the available capacity or transmission modifications, if any, necessary to provide Network Resource Interconnection Service may be significantly different. Therefore, the Interconnection Customer should regard the results of this study as informational rather than final.  Under normal conditions, the Transmission Provider does not dispatch or otherwise directly control or regulate the output of generating facilities. Therefore, the need for transmission modifications, if any, which are required to provide Network Resource Interconnection Service will be evaluated on the basis of 100 percent deliverability (i.e., no displacement of other resources in the same area).  This study assumes the Project will be integrated into the Transmission Provider’s system at agreed upon and/or proposed Point of Interconnection.  The Interconnection Customer will construct and own any facilities required between the Point of Change of Ownership and the Project unless specifically identified by the Transmission Provider.  Line reconductor or fiber underbuild required on existing poles will be assumed to follow the most direct path on the Transmission Provider’s system. If during detailed design the path must be modified it may result in additional cost and timing delays for the Interconnection Customer’s Project.  Generator tripping may be required for certain outages.  All facilities will meet or exceed the minimum Western Electricity Coordinating Council (“WECC”), North American Electric Reliability Corporation (“NERC”), and the Transmission Provider’s performance and design standards.  This report is based on information available at the time of the study. It is the Interconnection Customer’s responsibility to check the Transmission Provider’s web site regularly for Transmission System updates at http://www.pacificorp.com/tran.html 6.0 ENERGY RESOURCE (ER) INTERCONNECTION SERVICE Energy Resource Interconnection Service allows the Interconnection Customer to connect its Generating Facility to the Transmission Provider’s Transmission System and to be eligible to deliver electric output using firm or non-firm transmission capacity on an as available basis. 6.1.1 Requirements 6.1.1.1 Generating Facility Modifications All interconnecting synchronous and non-synchronous generators are required to design their Generating Facilities with reactive power capabilities necessary to operate within the full power factor range of 0.95 leading to 0.95 lagging. This power factor range shall be dynamic and can be System Impact Study Report PacifiCorp Energy Supply Management Page 5 August 16, 2019 Pryor Mountain Wind, Q0542 met using a combination of the inherent dynamic reactive power capability of the generator or inverter, dynamic reactive power devices and static reactive power devices to make up for losses. For synchronous generators, the power factor requirement is to be measured at the Point of Interconnection. For non-synchronous generators, the power factor requirement is to be measured at the high-side of the generator substation. The Generating Facility must provide dynamic reactive power to the system in support of both voltage scheduling and contingency events that require transient voltage support, and must be able to provide reactive capability over the full range of real power output. If the Generating Facility is not capable of providing positive reactive support (i.e., supplying reactive power to the system) immediately following the removal of a fault or other transient low voltage perturbations, the facility must be required to add dynamic voltage support equipment. These additional dynamic reactive devices shall have correct protection settings such that the devices will remain on line and active during and immediately following a fault event. Generators shall be equipped with automatic voltage-control equipment and normally operated with the voltage regulation control mode enabled unless written authorization (or directive) from the Transmission Provider is given to operate in another control mode (e.g. constant power factor control). The control mode of generating units shall be accurately represented in operating studies. The generators shall be capable of operating continuously at their maximum power output at its rated field current within +/- 5% of its rated terminal voltage. As required by NERC standard VAR-001-4.2, the Transmission Provider will provide a voltage schedule for the Point of Interconnection. In general, Generating Facilities should be operated so as to maintain the voltage at the Point of Interconnection, typically between 1.00 per unit to 1.04 per unit, or other designated point as deemed appropriated by Transmission Provider. The Transmission Provider may also specify a voltage and/or reactive power bandwidth as needed to coordinate with upstream voltage control devices such as on-load tap changers. At the Transmission Provider’s discretion, these values might be adjusted depending on operating conditions. Generating Facilities capable of operating with a voltage droop are required to do so. Voltage droop control enables proportionate reactive power sharing among Generation Facilities. Studies will be required to coordinate voltage droop settings if there are other facilities in the area. It will be the Interconnection Customer’s responsibility to ensure that a voltage coordination study is performed, in coordination with Transmission Provider, and implemented with appropriate coordination settings prior to unit testing. For areas with multiple generating facilities additional studies may be required to determine whether or not critical interactions, including but not limited to control systems, exist. These studies, to be coordinated with Transmission Provider, will be the responsibility of the Interconnection Customer. If the need for a master controller is identified, the cost and all related installation requirements will be the responsibility of the Interconnection Customer. Participation System Impact Study Report PacifiCorp Energy Supply Management Page 6 August 16, 2019 Pryor Mountain Wind, Q0542 by the generation facility in subsequent interaction/coordination studies will be required pre- and post-commercial operation in order ensure system reliability. To facilitate collection and validation of accurate modeling data to meet NERC modeling standards, PacifiCorp, as the Planning Coordinator, requires Phasor Measurement Units (PMUs) at all new Generating Facilities with an individual or aggregate nameplate capacity of 75 MVA or greater. In addition to owning and maintaining the PMU, the Generating Facility will be responsible for collecting, storing (for a minimum of 90 days) and retrieving data as requested by the Planning Coordinator. Data must be collected and be able to stream to Planning Coordinator for each of the Generating Facility’s step-up transformers measured on the low side of the GSU at a sample rate of at least 60 samples per second and synchronized within +/- 2 milliseconds of the Coordinated Universal Time (UTC). Initially, the following data must be collected:  Three phase voltage and voltage angle (analog)  Three phase current (analog) Data requirements are subject to change as deemed necessary to comply with local and federal regulations. All generators must meet the Federal Energy Regulatory Commission (FERC), North American Electric Reliability Corporation (NERC) and WECC low voltage ride-through requirements as specified in the interconnection agreement. Inverters must be designed to stay connected to the grid in the case of severe faults and may not momentarily cease output within the no-trip area of the voltage curves. Figure 2 illustrates the voltage ride-through capability as per NERC PRC- 024. Importantly, inverters should be designed such that a trip outside of the curves is a “may- trip” area (if needed to protect equipment) not a “must-trip” area. Inverters that momentarily cease active power output for these voltage excursions should be configured to restore output to pre- disturbance levels in no greater than five seconds, provided the inverter is capable of these changes. Generators must provide test results verifying in writing that the inverters have been programmed to meet ALL PRC-024 requirements vs. the manufacturers IEEE distribution settings. Figure 2 – Voltage Ride-Through Curve System Impact Study Report PacifiCorp Energy Supply Management Page 7 August 16, 2019 Pryor Mountain Wind, Q0542 As the Transmission Provider cannot submit a user written model to WECC for inclusion in base cases, a standard model from the WECC Approved Dynamic Model Library is required 180 days prior to trial operation. The list of approved generator models is continually updated and is available on the http://www.WECC.biz website. 6.1.1.2 Transmission System Modifications Construct a new 230 kV three breaker ring substation to serve as the Point of Interconnection. A remedial action scheme (RAS) will be required that trips the Q0542 Project for loss of the Q0542 POI–Yellowtail 230 kV transmission line under certain heavy load, heavy generation conditions. 6.1.1.3 Transmission/Distribution Line Modifications Construct a 400 ft- 230 kV Loop-in on both the north and south ends of the Q0542 POI near structure 3/135 and 4/135 on the Thermopolis- Yellowtail 230 kV Transmission Line. Install 14.06 miles of 3/8” OPGW between Frannie Sub and the POI sub (replacing one of the two existing 3/8” Steel Shield wires). Correct approx. 10 Class B – structural defect conditions. Additionally, replace one x-brace in this section. Replace one shield wire with 3/8” OPGW (replacing one of the two existing 3/8” shield wires) between Q0542 and Yellowtail Sub on the Thermopolis-Yellowtail 230 kV Transmission Line. The distance is 41.34 miles. Correct approx. 30 Class B – structural defect conditions. Additionally, replace 7 x-braces in this section. 6.1.1.4 Existing Circuit Breaker Upgrades – Short Circuit The increase in the fault duty on the system as a result of the addition of the generation facility with the 57 – 2.0 MW wind turbine generators connected to 57 - 34.5 kV – 690 V 2.1 MVA transformers with Z= 8.7 % @1.9 MVA, 50 – 2.2 MW wind turbine generators connected to 57 – 2.3 MVA 34.5 kV – 690 V 2.3 MVA transformers with Z=8.7% @2.06 MVA, and 4 – 2.3 MW wind turbine generators connected to 4 – 2.3 MVA 34.5 kV – 690 V transformers with Z=5.75 % and then the combination fed through 2 – 90/120/150 MVA 230 – 34.5 kV transformers with 9% impedance will not push the fault duty above the interrupting rate of any of the existing fault interrupting equipment. 6.1.1.5 Protection Requirements The installation of protective relays for line fault detection will be required at the Transmission Provider’s new 230 kV Point of Interconnection (POI) Substation for the protection of the line to the Interconnection Customer’s Collector substation and the lines to Yellowtail and Oregon Basin substations. The lines to Yellowtail and Oregon Basin substation will use permissive over reaching transfer trip line relaying logic. The line relay systems will require communication System Impact Study Report PacifiCorp Energy Supply Management Page 8 August 16, 2019 Pryor Mountain Wind, Q0542 circuits between the substations. The line relays currently in Yellowtail and Oregon Basin substations will be compatible with the relays to be installed at the POI substation so only relay setting changes will be required at those substations for this project. The collector substation will be adjacent to the POI substation. With the two substations sharing a common fence the ground mats of the two substations can be tied together and metallic control cables can be used for protection and control circuits. The line between POI substation and the Generation Interconnection Customer’s collector substation will be protected with a bus differential relay systems. The bus differential relays will be located in the POI substation. The Generation Interconnection Customer will need to provide the output from two sets of current transformers from the transformer 230 kV breaker. These currents will be fed into the bus differential relays. If a fault is detected both the 230 kV breakers in the POI substation and the 230 kV breaker in the collector substation will be tripped. In addition to the line protective relaying a relay used for under/over voltage and over/under frequency protection of the system will be installed at the POI substation. If the voltage, magnitude or frequency, is outside of the normal operation range this relay will trip open the Interconnection Customer’s 230 kV transformer breaker at the collector substation. To meet the requirements for the RAS listed in section 6.1.1.2 line loss logic units will be installed in Yellowtail and the Q0542 POI substations. Redundant communication paths will be required between the two substations. If both breakers for the Yellowtail – Q0542 POI 230 kV line are opened at either terminal of the line the line loss logic unit at Q0542 POI will trip the two breakers for the tie line to the Q0542 Collector substation. 6.1.1.6 Data (RTU) Requirements The installation of a RTU is required at the Transmission Provider’s Point of Interconnection (POI) substation. Additional data for the operation of the power system will be needed from Interconnection Customer’s collector substation. These quantities will be wired into the RTU at the POI substation. In addition to the control and indication of the 230 kV breakers in the POI substation the following data from the POI substation and the Interconnection Customer’s collector substation will be monitored: From the POI substation: Analogs:  Net generation MW  Net generation MVAr  Energy register values From the Interconnection Customer’s collector substation: Analogs:  Generation MW Transformer 1  Generation MVAr Transformer 1  Energy register values Transformer 1 System Impact Study Report PacifiCorp Energy Supply Management Page 9 August 16, 2019 Pryor Mountain Wind, Q0542  Generation MW Transformer 2  Generation MVAr Transformer 2  Energy register values Transformer 2  Real power flow 34.5 kV line #1  Reactive power flow 34.5 kV line #1  Real power flow 34.5 kV line #2  Reactive power flow 34.5 kV line #2  Real power flow 34.5 kV line #3  Reactive power flow 34.5 kV line #3  Real power flow 34.5 kV line #4  Reactive power flow 34.5 kV line #4  Real power flow 34.5 kV line #5  Reactive power flow 34.5 kV line #5  Real power flow 34.5 kV line #6  Reactive power flow 34.5 kV line #6  Real power flow 34.5 kV line #7  Reactive power flow 34.5 kV line #7  Real power flow 34.5 kV line #8  Reactive power flow 34.5 kV line #8  Real power flow 34.5 kV line #9  Reactive power flow 34.5 kV line #9  Real power flow 34.5 kV line #10  Reactive power flow 34.5 kV line #10  Average Wind Farm Wind Speed (m/s)  Average Wind Farm Atmospheric Pressure (Bar)  Average Wind Farm Temperature (Celsius) Status:  230 kV transformer 1 breaker  230 kV transformer 2 breaker  34.5 kV Line #1 breaker  34.5 kV Line #2 breaker  34.5 kV Line #3 breaker  34.5 kV Line #4 breaker  34.5 kV Line #5 breaker  34.5 kV Line #6 breaker  34.5 kV Line #7 breaker  34.5 kV Line #8 breaker  34.5 kV Line #9 breaker  34.5 kV Line #10 breaker 6.1.1.7 Substation Requirements Frannie Substation Conduit will be installed to support the installation of fiber into the substation. Oregon Basin Substation System Impact Study Report PacifiCorp Energy Supply Management Page 10 August 16, 2019 Pryor Mountain Wind, Q0542 The substation fence will be expanded to support the installation of a control house and microwave tower. The Yellowtail line wave trap and power line carrier equipment will be removed. Yellowtail Substation Remove the wave trap and power line carrier equipment. One relay panel will be installed. Q0542 Point of Interconnection substation The Point of Interconnection substation will be built as a three breaker ring bus substation. The following equipment has been identified as being required and may change during detailed design. 3 – 230kV, breaker 6 – 230kV, CCVT 3 – 230kV, combined CT/VT metering unit 8 – 230kV, switch, breaker disconnect 3 – 230kV, switch, line disconnect 1 – 230 kV, switch, meter disconnect 9 – 230kV, lightning arrester 1 – 230 kV, SSVT 1 – control house Q0542 Customer substation A CDEGS grounding analysis will be required to verify safe step and touch potentials. Six, 230 kV metering instrument transformers will be installed. The customer shall provide a disconnect switch on each side of each metering instrument transformer. The customer shall provide a separate lockable room with unencumbered access for PacifiCorp to install metering and communication equipment. 6.1.1.8 Communication Requirements Communication requirements to physically connect the Q0542 project will consist of:  Install fiber on the existing 14.26 miles line between Frannie substation and Point of Interconnection substation.  Upgrade the existing radio system between McCullough Peak to Frannie substation, McCullough Peak to Oregon Basin substation and McCullough Peak to Cody service center with company standard microwave radios. This requires new towers at Frannie, Oregon Basin and Cody service center.  Install multiplex, routers, communication batteries and chargers at all the locations requiring upgrades.  Install Fiber nodes at Frannie and the Q0542 Point of Interconnection substation.  Install new RTUs at Point of Interconnection substation and the Q0542 collector substation with a new data concentrator. System Impact Study Report PacifiCorp Energy Supply Management Page 11 August 16, 2019 Pryor Mountain Wind, Q0542  Remove Power line carrier and use mirrored bits on the 230 kV transmission line from Oregon Basin substation to the Yellowtail substation with interface of WAPA’s new microwave system at McCullough Peak to Yellowtail substation.  Communications work will also be required at other locations to include Casper Service Center, Portland Control Center (PCC), and the Salt Lake Control Center (SCC). 6.1.1.9 Metering Requirements Interchange Metering At the Transmission Provider’s Q0542 Point of Interconnection substation the interchange metering will be designed bidirectional and rated for the total net generation of the project including metering the retail load (per tariff) delivered to the customer. The Transmission Provider will specify and order all interconnection revenue metering, including the instrument transformers, metering panels, junction box and secondary metering wire. The primary metering transformers shall be combination CT/VT extended range for high accuracy metering with ratio’s to be determined during the design phase of the project The metering instrument transformers are long lead items and should be given appropriate time to meet in-service expectations. The metering design package will include two revenue quality meters, test switch, with DNP real time digital data terminated at a metering interposition block. One meter will be designated a primary SCADA meter and a second meter will be used designated as backup with metering DNP data delivered to the alternate control center. The metering data will include bidirectional KWH KVARH, revenue quantities including instantaneous PF, MW, MVAR including per phase voltage and amps data. An Ethernet connection is required for retail sales and generation accounting via the MV-90 translation system. 6.1.2 Cost Estimate (ER) The following estimate represents only scopes of work that will be performed by the Transmission Provider. Costs for any work being performed by the Interconnection Customer are not included. Direct Assigned Q0542 POI Substation Line termination and metering $451,000 Total Direct Assigned $451,000 Network Upgrades Q0542 POI Substation Construct 230 kV substation $8,037,000 Frannie-Yellowtail Transmission Line System Impact Study Report PacifiCorp Energy Supply Management Page 12 August 16, 2019 Pryor Mountain Wind, Q0542 Install fiber, loop line in/out of POI substation $3,337,000 Yellowtail Substation Protection and communications equipment $221,000 Oregon Basin Substation Substation expansion, protection and communications equipment $1,595,000 Frannie Substation Communications equipment $404,000 Cody Substation Communications equipment $237,000 McCullough Peak Communications Site Communications equipment $164,000 Total Network Upgrades $13,990,000 Total Cost $14,441,000 *Any distribution line modifications identified in this report will require a field visit analysis in order to obtain a more thorough understanding of the specific requirements. The estimate provided above for this work could change substantially based on the results of this analysis. Until this field analysis is performed the Transmission Provider must develop the Project schedule using conservative assumptions. The Interconnection Customer may request that the Transmission Provider perform this field analysis, at the Interconnection Customer’s expense, prior to the execution of an Interconnection Agreement in order to obtain more cost and schedule certainty. Note: Costs for any excavation, duct installation and easements shall be borne by the Interconnection Customer and are not included in this estimate. This estimate is as accurate as possibly given the level of detailed study that has been completed to date and approximates the costs incurred by Transmission Provider to interconnect this Generating Facility to Transmission Provider’s electrical distribution or transmission system. A more detailed estimate will be calculated during the Facilities Study. The Interconnection Customer will be responsible for all actual costs, regardless of the estimated costs communicated to or approved by the Interconnection Customer. 6.1.1 Schedule The Transmission Provider estimates it will require approximately 24 months to design, procure and construct the facilities described in Network Resource sections of this report following the execution of an Interconnection Agreement. The schedule will be further developed and optimized during the Facilities Study. System Impact Study Report PacifiCorp Energy Supply Management Page 13 August 16, 2019 Pryor Mountain Wind, Q0542 Please note, the time required to perform the scope of work identified in this report appears to result in a timeframe that may support the Interconnection Customer’s requested commercial operation date of December 1, 2020. 7.0 APPENDICES Appendix 1: Higher Priority Requests Appendix 2: Contingent Facilities Appendix 3: Property Requirements Appendix 4: Study Results System Impact Study Report PacifiCorp Energy Supply Management Page 14 August 16, 2019 Pryor Mountain Wind, Q0542 7.1 Appendix 1: Higher Priority Requests All active higher priority Transmission Provider projects, and transmission service and/or generator interconnection requests will be considered in this study and are identified below. If any of these requests are withdrawn, the Transmission Provider reserves the right to restudy this request, as the results and conclusions contained within this study could significantly change. Transmission/Generation Interconnection Queue Requests considered: None System Impact Study Report PacifiCorp Energy Supply Management Page 15 August 16, 2019 Pryor Mountain Wind, Q0542 7.2 Appendix 2: Contingent Facilities The following Interconnection Facilities and/or upgrades to the Transmission Provider’s system are Contingent Facilities for the Interconnection Customer’s Interconnection Request and must be in service prior to the commencement of generation activities: None System Impact Study Report PacifiCorp Energy Supply Management Page 16 August 16, 2019 Pryor Mountain Wind, Q0542 7.3 Appendix 3: Property Requirements Property Requirements for Point of Interconnection Substation Requirements for rights of way easements Rights of way easements will be acquired by the Interconnection Customer in the Transmission Provider’s name for the construction, reconstruction, operation, maintenance, repair, replacement and removal of Transmission Provider’s Interconnection Facilities that will be owned and operated by PacifiCorp. Interconnection Customer will acquire all necessary permits for the Project and will obtain rights of way easements for the Project on Transmission Provider’s easement form. Real Property Requirements for Point of Interconnection Substation Real property for a point of interconnection substation will be acquired by an Interconnection Customer to accommodate the Interconnection Customer’s Project. The real property must be acceptable to Transmission Provider. Interconnection Customer will acquire fee ownership for interconnection substation unless Transmission Provider determines that other than fee ownership is acceptable; however, the form and instrument of such rights will be at Transmission Provider’s sole discretion. Any land rights that Interconnection Customer is planning to retain as part of a fee property conveyance will be identified in advance to Transmission Provider and are subject to the Transmission Provider’s approval. The Interconnection Customer must obtain all permits required by all relevant jurisdictions for the planned use including but not limited to conditional use permits, Certificates of Public Convenience and Necessity, California Environmental Quality Act, as well as all construction permits for the Project. Interconnection Customer will not be reimbursed through network upgrades for more than the market value of the property. As a minimum, real property must be environmentally, physically, and operationally acceptable to Transmission Provider. The real property shall be a permitted or able to be permitted use in all zoning districts. The Interconnection Customer shall provide Transmission Provider with a title report and shall transfer property without any material defects of title or other encumbrances that are not acceptable to Transmission Provider. Property lines shall be surveyed and show all encumbrances, encroachments, and roads. Examples of potentially unacceptable environmental, physical, or operational conditions could include but are not limited to: 1. Environmental: known contamination of site; evidence of environmental contamination by any dangerous, hazardous or toxic materials as defined by any governmental agency; violation of building, health, safety, environmental, fire, land use, zoning or other such regulation; violation of ordinances or statutes of any governmental entities having jurisdiction over the property; underground or above ground storage tanks in area; known remediation sites on property; ongoing mitigation activities or monitoring activities; asbestos; lead-based paint, etc. A System Impact Study Report PacifiCorp Energy Supply Management Page 17 August 16, 2019 Pryor Mountain Wind, Q0542 phase I environmental study is required for land being acquired in fee by the Transmission Provider unless waived by Transmission Provider. 2. Physical: inadequate site drainage; proximity to flood zone; erosion issues; wetland overlays; threatened and endangered species; archeological or culturally sensitive areas; inadequate sub-surface elements, etc. Transmission Provider may require Interconnection Customer to procure various studies and surveys as determined necessary by Transmission Provider. Operational: inadequate access for Transmission Provider’s equipment and vehicles; existing structures on land that require removal prior to building of substation; ongoing maintenance for landscaping or extensive landscape requirements; ongoing homeowner's or other requirements or restrictions (e.g., Covenants, Codes and Restrictions, deed restrictions, etc.) on property which are not acceptable to the Transmission Provider. System Impact Study Report PacifiCorp Energy Supply Management Page 18 August 16, 2019 Pryor Mountain Wind, Q0542 7.4 Appendix 4: Study Results This is a restudy due to the requested change in wind turbine generators by the Customer. A restudy of the power flow and transient stability analysis was conducted to determine if the change in the type of wind turbines as proposed by the Customer would negatively impact the reliability of the transmission system. Study results indicate that a remedial action scheme (RAS) will be required that trips the Q0542 Project for loss of the Q0542 POI-Yellowtail 230 kV line under some heavy load and heavy wind generation conditions. Identification of specific load and wind generation conditions will be identified during RAS scoping and design. The following modeling data were used in this analysis:  Collector system – PME-B-D002-1 Rev 0A.pdf, PME-B-D002-2 Rev 0A.pdf, PME-B- D002-3 Rev 0A.pdf drawings providing cable lengths and sizes. Individual wind turbine generator (WTG) step-up transformers of 2.6 MVA, 5.75%, 34.5/0.69 kV and two main station transformers of 90/120/150 MVA, 9.0%, 230/34.5 kV from collector drawings.  WTG data – 55 x Vesta V110-2.0MK10B WTGs, 24 x Vestas V110-2.2MK10C WTGs, 29 x Vestas V110-2.2MK10D WTGs, and 4 x GE2.3-116 WTGs. (Due to model coordination constraints, the four GE WTGs were modeled as Vestas V110-2.2MK10D turbines.) These Vestas WTGs have very limited reactive power capability. Maximum gross capability of the WTGs modeled as 239.4 MW with a reactive power range of +23 to -45 MVAR (power factor range of 0.995 capacitive and 0.982 inductive).  Point of Interconnection (POI) – approximately 14 miles north of Frannie 230 kV substation on Frannie-Yellowtail 230 kV line. Power Flow Study Results:  Steady-state conditions – heavy stressed conditions modeled with maximum Q0542 generation, peak area loads and heavy south bound system transfers (625 MW Yellowtail south). It was necessary to add 30 MVAR of 34.5 kV shunt capacitors added on Pryor Mt. 34.5 kV system to provide a net delivery of 235 MW at 0.998 power factor (235 +j 16 MVA); however, it is noted that is it the Customer’s responsibility to design its Project to meet all interconnection requirements, including power factor.  N-1 outage conditions – worst case N-1 outage is loss of Q0542 POI -Yellowtail 230 kV line resulting in extremely high voltage (1.4 pu) conditions on the 230 kV and 34.5 kV transmission and collector systems. Note – Vestas WTGs have limited reactive power capability to respond to high voltage conditions. Dynamic Study Results: (worst case N-1 outage)  N-1 outage, no remedial actions - loss of Q0542 POI -Yellowtail 230 kV line resulting in extremely high voltage conditions (1.15 pu on 230 kV system) and over-voltage tripping of all Vestas WTGs approximately 23 cycles (< 0.4 seconds) after fault clearing and loss of the 230 kV line. System performance does not meet criteria.  N-1 outage, with capacitor trip - loss of Q0542 POI -Yellowtail 230 kV line and high speed tripping of 40 MVAR Frannie 230 kV capacitor banks resulting in high voltage conditions and over-voltage tripping of one Vestas WTG equivalent (114 MW) approximately 40 System Impact Study Report PacifiCorp Energy Supply Management Page 19 August 16, 2019 Pryor Mountain Wind, Q0542 cycles after fault clearing and loss of the 230 kV line. System performance does not meet criteria.  N-1 outage, with Project Q0542 trip - loss of Q0542 POI - Yellowtail 230 kV line and tripping of Q0542 Project approximately 5 cycles after fault clearing and loss of the 230 kV line. System performance is marginally acceptable.