Loading...
HomeMy WebLinkAbout20210920PAC to Bayer 117-1 Q0542 Bowler Flats LGI SIS Final to Cust.pdf      Large Generator Interconnection System Impact Study Report Completed for Bowler Flats Energy Hub, LLC Bowler Flats Energy Hub LGIQ# Q0542 Proposed Interconnection To the Existing 230 kV Frannie - Yellowtail Transmission Line August 19, 2014 System Impact Study Report Bowler Flats Energy Hun, LLC Page i August 19, 2014 Bowler Flats Energy Hub, Q0542 TABLE OF CONTENTS 1.0 DESCRIPTION OF THE GENERATING FACILITY .................................................................... 1  2.0 SCOPE OF THE STUDY ................................................................................................................. 1  3.0 TYPE OF INTERCONNECTION SERVICE .................................................................................. 2  4.0 DESCRIPTION OF PROPOSED INTERCONNECTION ............................................................... 2  4.1 Other Options Considered (NERC Requirement) ...................................................................... 2  5.0 STUDY ASSUMPTIONS ................................................................................................................. 2  5.1 Energy Resource (ER) Interconnection Service ......................................................................... 5  5.1.1 Study Results 5  5.1.2 Requirements 10  5.1.1 Cost Estimate 18  5.1.2 Schedule 19  5.1.3 Maximum Amount of Power that can be delivered into Network Load, with No Transmission Modifications (for informational purposes only). 19  5.1.4 Additional Transmission Modifications Required to Deliver 100% of the Power into Network Load (for informational purposes only) 20  5.2 Network Resource (NR) Interconnection Service .................................................................... 21  5.2.1 Study Results 21  5.2.2 Network Resource Requirements 23  5.2.3 Network Resource Cost Estimate 27  5.2.4 Schedule 28  6.0 PARTICIPATION BY AFFECTED SYSTEMS ............................................................................ 28  7.0 APPENDIX 1: PROPERTY REQUIREMENTS ............................................................................ 29  8.0 APPENDIX 2: COMBINED QUEUE ............................................................................................ 31  System Impact Study Report Bowler Flats Energy Hub, LLC Page 1 August 19, 2014 Bowler Flats Energy Hub, Q0542 1.0 DESCRIPTION OF THE GENERATING FACILITY Bowler Flats Energy Hub, LLC (“Interconnection Customer”) proposed interconnecting 240 MWs of new generation to PacifiCorp’s (“Transmission Provider”) Frannie – Yellowtail 230 kV transmission line approximately 2.75 miles north of the Frannie substation located in Park County, Montana. The Bowler Flats Energy Hub project (“Project”) will consist of 120 Gamesa 2.0 G114 wind turbine generators for a total output of 240 MWs. The requested commercial operation date is approximately December 1, 2015. Interconnection Customer will NOT operate this generator as a Qualified Facility as defined by the Public Utility Regulatory Policies Act of 1978 (PURPA). The Transmission Provider has assigned the project “Q0542.” 2.0 SCOPE OF THE STUDY The interconnection system impact study shall evaluate the impact of the proposed interconnection on the reliability of the transmission system. The interconnection system impact study will consider Base Case as well as all generating facilities (and with respect to (iii) below, an identified network upgrades associated with such higher queued interconnection) that, on the date the interconnection system impact study is commenced: (i) are directly interconnected to the transmission system; (ii) are interconnected to Affected Systems and may have an impact on the interconnection request; (iii) have a pending higher queued interconnection request to interconnect to the transmission system; and (iv) have no Queue Position but have executed an LGIA or requested that an unexecuted LGIA be filed with FERC. The interconnection system impact study will consist of a short circuit analysis, a stability analysis, and a power flow analysis. The interconnection system impact study will state the assumptions upon which it is based; state the results of the analyses; and provide the requirements or potential impediments to providing the requested interconnection service, including preliminary indication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the interconnection. The interconnection system impact study will provide a list of facilities that are required as a result of the Interconnection Request and a non-binding good faith estimate of the cost responsibility and a non-binding good faith estimated time to construct. System Impact Study Report Bowler Flats Energy Hub, LLC Page 2 August 19, 2014 Bowler Flats Energy Hub, Q0542 3.0 TYPE OF INTERCONNECTION SERVICE The Interconnection Customer has selected Network Resource (NR) interconnection service, but has also elected to have the interconnection studied as an Energy Resource (ER). The Interconnection Customer will select NR or ER prior to the facilities study. 4.0 DESCRIPTION OF PROPOSED INTERCONNECTION To interconnect the Q0542 Project to the 230 kV Frannie – Yellowtail transmission line will require the construction of a new 230 kV three breaker ring bus switching substation including control house and the installation of metering, protection and control and communications equipment. Transmission system upgrades will also be required at Frannie substation, Yellowtail substation, Cedar Mountain substation, Oregon Basin substation, McCullough Peak microwave station, Cody Service Center, Casper Service Center, Portland Control Center and Salt Lake Control Center. 4.1 Other Options Considered (NERC Requirement) The Interconnection Customer could have chosen to interconnect directly to the Frannie substation but, chose to have the Q0542 Project tap the existing 230 kV Frannie – Yellowtail transmission line approximately 2.75 miles North of the Frannie substation. 5.0 STUDY ASSUMPTIONS  All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are listed in Appendix 1. If any of these requests are withdrawn, the Transmission Provider reserves the right to re-evaluate this request, and the results and conclusions could significantly change.  For study purposes there are two separate queues: o Transmission Service Queue: to the extent practical, all network upgrades that are required to accommodate active transmission service requests and are expected to be in-service on or after the Interconnection Customer’s requested in-service date for the Project will be modeled in this study. o Generation Interconnection Queue: when relevant, interconnection facilities associated with higher queue interconnection requests will be modeled in this study. However, no generation will be simulated from any higher queued project unless a commitment has been made to obtain transmission service. System Impact Study Report Bowler Flats Energy Hub, LLC Page 3 August 19, 2014 Bowler Flats Energy Hub, Q0542  The Interconnection Customer’s request for energy or network resource interconnection service in and of itself does not convey transmission service. Only a Network Customer can make a request to designate a generating resource as a network resource. Since the queue of higher priority transmission services requests may be different when and if a Network Customer’s requests network resource designation for this generation facility, the available capacity or transmission modifications, if any, necessary to provide network resource interconnection service may be significantly different. Therefore, the Interconnection Customer should regard the results of this study as informational rather than final.  Under normal conditions, the Transmission Provider does not dispatch or otherwise directly control or regulate the output of generation facilities. Therefore, the need for transmission modifications, if any, which are required to provide network resource interconnection service will be evaluated on the basis of 100 percent deliverability (i.e., no displacement of other resources in the same area). However, a network customer can elect to designate more generating resources in an area than can be accommodated by existing or planned transmission capacity. The network customer would then be required to dispatch the resources so as to limit total generation so as not to exceed the network customer’s transmission rights.  This study assumes the project will be integrated into the Transmission Provider’s system to the existing Frannie – Yellowtail 230kV line at or near a point approximately 2.75 miles north of Frannie substation located in Park County, Wyoming.  This study assumes that the Railroad – Silver Creek 138kV line planned for December 2015 is in-service.  This study assumes that Q0542 is in-service in summer 2016. The 2016 heavy and light load conditions are applied to this study.  PacifiCorp standards require post contingency voltage limits of 0.9 per unit and 1.1 per unit.  The Interconnection Customer will construct and own any facilities required between the Point of Change of Ownership and the project.  Generator tripping may be required for certain outages.  All facilities will meet or exceed the minimum WECC, NERC, and the Transmission Provider’s performance and design standards. System Impact Study Report Bowler Flats Energy Hub, LLC Page 4 August 19, 2014 Bowler Flats Energy Hub, Q0542  This report is based on information available at the time of the study. It is the Interconnection Customer’s responsibility to check the Transmission Provider’s web site regularly for transmission system updates at http://www.pacificorp.com/tran.html  If wind turbines are connected electrically near series capacitors, then specialized studies to consider SSR (Sub-Synchronous Resonance) and Sub-Synchronous Control Interactions (SSCI) may be required. If N-1 or N-2 contingencies result in a radial path of the turbines into the series capacitors, then studies are essential – for other non-radial configurations, the studies are necessary at the discretion of the Transmission Provider. Such studies must demonstrate that the wind turbine controls do not contribute negative damping to the system, and that the mechanical modes of resonance in the turbine do not interact with system series capacitors. If such interactions occur, it is the responsibility of the wind developer to provide remedies, and to provide adequate protection to ensure the sub-synchronous interactions are detected and the wind turbines tripped.  The Latham/Platte 230kV line upgrades from a DUTT relaying scheme to a POTT relaying scheme using mirrored bits, associated with the TOT4 project, have been completed.  The 230kV bus configuration modifications at Latham substation associated with the TOT4A project have been completed. System Impact Study Report Bowler Flats Energy Hub, LLC Page 5 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.1 Energy Resource (ER) Interconnection Service Energy resource interconnection service allows the Interconnection Customer to connect its generating facility to the Transmission Provider’s transmission system and to be eligible to deliver electric output using firm or non-firm transmission capacity on an as available basis. Consistent with the Transmission Provider’s Open Access Transmission Tariff, the facility will be studied such that deliverability will be determined to the Transmission Provider’s aggregate network loads assuming some portion of existing network resources are displaced by the output of the Interconnection Customer’s large generating facility. Energy resource interconnection service in and of itself does not convey transmission service. 5.1.1 Study Results The PSS/E version 33.5 program was used to evaluate the steady state performance of the system for contingencies described in Table 1. The 2014 Heavy Summer WECC case was modified for the study. The study area was limited to the Big Horn area in Wyoming since the Point of Interconnection (POI) is located on the Frannie – Yellowtail 230 kV line. System Impact Study Report Bowler Flats Energy Hub, LLC Page 6 August 19, 2014 Bowler Flats Energy Hub, Q0542 System Impact Study Report Bowler Flats Energy Hub, LLC Page 7 August 19, 2014 Bowler Flats Energy Hub, Q0542 The case was tuned to meet the maximum path flow on the Yellowtail South path. The Yellowtail South path is jointly owned between PacifiCorp (PAC) and Western Area Power Administration (WAPA). The path limit is 625 MW, with ownership split 400 MW for PacifiCorp (230 kV lines) and 225 MW for WAPA (115 kV lines). The Yellowtail South path consists of the following lines:  Yellowtail (PAC) – Frannie 230 kV (owned by PAC) *  Yellowtail (PAC) – Sheridan 230 kV (owned by PAC)  Yellowtail (WAPA) – Lovell 115 kV #1 line (owned by WAPA)  Yellowtail (WAPA) – Lovell 115 kV #2 line (owned by WAPA) *Post Q0542, the metering point for the Yellowtail – Frannie 230 kV line would move from Yellowtail to the new Q0542 Point of Interconnection so that the power flow from this Project is captured in the path flow. System Impact Study Report Bowler Flats Energy Hub, LLC Page 8 August 19, 2014 Bowler Flats Energy Hub, Q0542 Table 1 N-1 Outages PAC owned facilities # Contingency 1 Yellowtail (PAC) - Point of Interconnection 230kV line 2 Point of Interconnection - Frannie - Garland - Oregon Basin 230kV line 3 Oregon Basin - Grass Creek - Thermopolis (PAC) 230kV line 4 Thermopolis (PAC) - Riverton 230kV line 5 Riverton - Casper 230kV line 6 Yellowtail (PAC) - Sheridan 230kV line 7 Sheridan - Buffalo 230kV line 8 Buffalo - Kaycee - Midwest - Claim Jumper 230kV line 9 Buffalo - Carr Draw 230kV line 10 Carr Draw - Casper 230kV line 11 Yellowtail (PAC) – Rim Rock 161kV line 12 Thermopolis (PAC) - Kirby Creek - Hilltop 115kV line 13 Thermopolis (PAC) - Thermopolis (WAPA) 115kV #1 line 14 Thermopolis (PAC) - Thermopolis (WAPA) 115kV #2 line 15 Riverton 230/115kV transformer 16 Thermopolis 230/161kV transformer 17 Thermopolis 230/115kV #2 transformer WAPA owned facilities # Contingency 1 Yellowtail (PAC) - Yellowtail (WAPA) 230kV line 2 Yellowtail (WAPA) - Crossover 230kV line 2 Thermopolis (PAC) - Bad Water 230kV line 3 Bad Water - Buffalo Head - Spence 230kV line 4 Spence - Casper 230kV line 5 Lovell - Nahne Jensen - Basin - Worland - Hilltop & Thermopolis (WAPA) 115kV line 6 Lovell - Big George -Meeteesee - Carter Mountain - Thermopolis (WAPA) 115kV line 7 Yellowtail 60MW hydro generator #1 8 Yellowtail 60MW hydro generator #2 9 Yellowtail 60MW hydro generator #3 10 Yellowtail 60MW hydro generator #4 System Impact Study Report Bowler Flats Energy Hub, LLC Page 9 August 19, 2014 Bowler Flats Energy Hub, Q0542 NorthWestern Energy owned facilities # Contingency 1 Yellowtail (PAC) - Billings 230kV line Tri-State owned facilities # Contingency 1 Thermopolis 230/115kV #1 transformer Customer owned facilities # Contingency 1 Point of Interconnection - Collection Site 230kV line 2 New 240MW wind generator Table 1: List of Contingencies Prior to adding Q0542, no thermal overload and voltage issues are observed under N-0 conditions. After adding Q0542, no thermal overload and voltage issues are observed under N-0 conditions. There are known system conditions following contingencies that exist prior to the addition of the Q0542 project which are provided here for documentation purposes. The following contingencies cause the overload on Worland Tap – Basin – Nahne Jensen 115kV WAPA line:  N-1 outage of the Yellowtail (PAC) – Yellowtail (WAPA) 230kV line, or  N-1 outage of Yellowtail – Frannie – Garland – Oregon Basin 230kV line. To mitigate this issue, tripping the section of Worland Tap – Basin 115kV line or Basin – Nahne Jensen 115kV line is required. WAPA indicates that within five years there are plans to reconductor the Worland Tap – Basin – Nahne Jensen 115kV line with 477ACSS (Aluminum Conductor Steel Supported) which has a limit of 800 amps (159 MVA). The tripping scheme will no longer be required if this new reconductor project is completed. The following contingency causes low voltage issues in WAPA 115kV system:  N-1 outage of the Yellowtail (PAC) – Yellowtail (WAPA) 230kV line Tripping the Meeteesee Tap – Big George 115kV WAPA line alleviates this low voltage issue. No new voltage violations or thermal overloads are identified in the study for N-1 contingencies with Q0542 in-service other than the existing issues identified. However, coordination with WAPA is still required to operate the new generation facility properly under certain N-1 conditions described above or for other outage conditions that may occur from time to time. System Impact Study Report Bowler Flats Energy Hub, LLC Page 10 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.1.2 Requirements 5.1.2.1 Generating Facility Modifications The Generation and Interconnection facilities owned by the Interconnection Customer are required to operate under automatic voltage control with the voltage sensed electrically at the Point of Interconnection. The generating and interconnecting facility should have sufficient reactive capacity to enable the delivery of 100 percent of the plant output to the Point of Interconnection at unity power factor measured at 1.0 per unit voltage under steady state conditions. Generators capable of operating under voltage control with a voltage droop are required to do so. Studies will be required to coordinate the voltage droop setting with other facilities in the area. As required by NERC standard VAR-001-1a, the Transmission Provider will provide a voltage schedule for the Point of Interconnection. When voltage droop controls are not available, the generation and interconnection facilities should be operated so as to maintain the voltage at the Point of Interconnection between 1.01 pu to 1.04 pu. At the Transmission Provider’s discretion, these values might be adjusted depending on the operating conditions. Within this voltage range, the generating and interconnecting facilities should operate so as to minimize the reactive interchange between the generation/interconnection facilities and the Transmission Provider’s system (operation fixed at unity power factor at the Point of Interconnection). If the voltage is outside the upper or lower range, the voltage control scheme should operate so as to utilize the reactive capabilities of the generating and interconnecting facilities to maintain the voltage to a value within the control band. The voltage control settings of the generation and interconnection facilities must be coordinated with the Transmission Provider prior to energization (or interconnection). The reactive compensation must be designed such that the reactive switching (if required by the Interconnection Customer) does not cause step voltage changes greater than +/-3% on the Transmission Provider’s system. As the Transmission Provider cannot submit a user written model to WECC for inclusion in base cases, a standard model from the WECC Approved Dynamic Model Library is required prior to interconnection. The list of approved generator models is continually updated and is available on the http://www.WECC.biz website. The Transmission Provider was unable to obtain a working generator model from the Interconnection Customer. System Impact Study Report Bowler Flats Energy Hub, LLC Page 11 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.1.2.2 Transmission Modifications The Point of Interconnection substation is to be looped in to the Frannie – Yellowtail 230kV Transmission line approximately 2.75 miles north of the Frannie substation located in Park County, Wyoming. This new switching substation will split the line into two new sections: Q0542-Yellowtail on the northern end and Frannie - Q0542 on the southern end. The Q0542 Point of Interconnection substation will be located one span away from the existing transmission line between structures 8/123 and 1/124. A loop in of the Point of Interconnection substation off the transmission line toward Frannie will require removing H-frame structures 8/123 and 1/124 and replacing them with two new 3-pole TI451 structures and 2 new 3-pole TI452 structures. All structures will be guyed wood poles. System Impact Study Report Bowler Flats Energy Hub, LLC Page 12 August 19, 2014 Bowler Flats Energy Hub, Q0542 Figure 1: System One Line Diagram System Impact Study Report Bowler Flats Energy Hub, LLC Page 13 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.1.2.3 Existing Circuit Breaker Upgrades – Short Circuit The increase in the fault duty on the system as a result of the addition of the generation facility with the 120 – 2.35 MVA generators fed through 1 – 156/208/260 MVA step up transformer with 8% impedance will not push the fault duty above the interrupting rate of any of the existing fault interrupting equipment. 5.1.2.4 Protection Requirements As indicated in the one line diagram shown in Figure 1, the proposed Point of Interconnection 2.75 miles north of Frannie substation in the Yellowtail – Oregon Basin 230 kV line will require the construction of a new Point of Interconnection substation with three 230 kV breakers. There will be a 9.51 mile line from the Point of Interconnection substation to the Generation Interconnection Customer’s collector substation. The line between Yellowtail and Oregon Basin substations is protection with line relays using power line carrier for communication. Since in this part of the Transmission Provider’s service territory the communication options are limited we will plan to continue to use the power line carrier for the line relay communication media between the Point of Interconnection substation and Yellowtail substation, and between the Point of Interconnection substation and Oregon Basin substation. In each case we will continue to use one set of frequency shift transmitters and receivers using direct underreaching transfer trip line logic schemes. The line relays at Yellowtail and Oregon Basin have been replaced in recent years and with the development of new settings these relays will function with the relays that are planned for the Point of Interconnection substation. For the line between the Point of Interconnection substation and the collector substation a line current differential system will be used. The Transmission Provider will design and built a panel containing the line relays that will be compatible with the units being installed at the Point of Interconnection substation. The two line relay set will communication over an optical fiber cable that will need to be installed in conjunction with the 9.51 mile 230 kV tie line. At the Point of Interconnection substation a relay will be installed that will monitor the voltage magnitude and frequency. If the voltage, magnitude or frequency, is outside of the normal operation range this relay will send a trip signal to cause the Interconnection Customer’s 34.5 kV line breakers at the collector substation to open. 5.1.2.5 Data (RTU) Requirements The installation of a RTU is required at the Transmission Provider’s Point of Interconnection substation. Additional data for the operation of the power system will be needed from Interconnection Customer’s collector substation. RTU units will be installed at both locations to acquire the operational data and send the data back to the Transmission Provider’s operational center. In addition to the control and indication of the 230 kV breakers in the Point of Interconnection substation the following data from the Point of Interconnection substation and the Interconnection Customer’s collector substation will be monitored: System Impact Study Report Bowler Flats Energy Hub, LLC Page 14 August 19, 2014 Bowler Flats Energy Hub, Q0542 From the Point of Interconnection substation: Analogs:  Net generation MW  Net generation MVAr  Energy register values  230 kV A phase voltage  230 kV B phase voltage  230 kV C phase voltage From the Interconnection Customer’s collector substation: Analogs:  Real power flow 34.5 kV line #1  Reactive power flow 34.5 kV line #1  Real power flow 34.5 kV line #2  Reactive power flow 34.5 kV line #2  Real power flow 34.5 kV line #3  Reactive power flow 34.5 kV line #3  Real power flow 34.5 kV line #4  Reactive power flow 34.5 kV line #4  Real power flow 34.5 kV line #5  Reactive power flow 34.5 kV line #5  Real power flow 34.5 kV line #6  Reactive power flow 34.5 kV line #6  Real power flow 34.5 kV line #7  Reactive power flow 34.5 kV line #7  Real power flow 34.5 kV line #8  Reactive power flow 34.5 kV line #8  Real power flow 34.5 kV line #9  Reactive power flow 34.5 kV line #9  Real power flow 34.5 kV line #10  Reactive power flow 34.5 kV line #10  Real power flow 34.5 kV line #11  Reactive power flow 34.5 kV line #11  Real power flow 34.5 kV line #12  Reactive power flow 34.5 kV line #12  Reactive power flow 34.5 kV from reactive device  Total Wind Farm Generation (MW)  Average Wind Farm Wind Speed (m/s)  Average Wind Farm Atmospheric Pressure (Bar)  Average Wind Farm Temperature (Celsius)  Wind Direction System Impact Study Report Bowler Flats Energy Hub, LLC Page 15 August 19, 2014 Bowler Flats Energy Hub, Q0542 Status:  230 kV transformer breaker  34.5 kV transformer breaker  34.5 kV Line #1 breaker  34.5 kV Line #2 breaker  34.5 kV Line #3 breaker  34.5 kV Line #4 breaker  34.5 kV Line #5 breaker  34.5 kV Line #6 breaker  34.5 kV Line #7 breaker  34.5 kV Line #8 breaker  34.5 kV Line #9 breaker  34.5 kV Line #10 breaker  34.5 kV Line #11 breaker  34.5 kV Line #12 breaker  34.5 kV Reactive Device breaker 5.1.2.6 Substation Requirements Oregon Basin substation No major substation modifications are required at Oregon Basin substation. Yellowtail substation No major substation modifications are required at Yellowtail substation. Q0542 Point of Interconnection substation The Point of Interconnection substation will be built as a three breaker ring bus with all necessary equipment such as: circuit breakers, CCVT’s, lightning arresters, an SSVT, and group operated switches. Bus, bus support structures, and dead end towers will be installed as well as conduit, cable trench, and yard lights. The substation will be fenced and a ground grid installed. A control house will be installed to enclose all of the relay and communication equipment. Q0542 Customer substation Relay panels and a separate battery system will need to be installed in the Customer substation. This equipment will need to be installed in a separate lockable room within the Customer’s control house, or a separate control building will need to be installed. With either option, only Transmission Provider personnel will have access to that area. Since PacifiCorp personnel will require access into the Customer substation, a Current Distribution, Electromagnetic Fields, Grounding and Soil Structure Analysis CDEGS analysis will be required to verify the grounding design safe step and touch potentials. System Impact Study Report Bowler Flats Energy Hub, LLC Page 16 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.1.2.7 Communication Requirements Communication requirements to physically connect the Q0542 project will consist of:  Install fiber on the existing 2.75 miles line between Frannie substation and Point of Interconnection substation.  The Interconnection Customer will be required to install fiber on the new 9.51 mile line between the Point of Interconnection substation and the Q0542 collector substation.  Upgrade the MAS radio between Frannie substation and McCullough Peak microwave station.  Install a new microwave tower at Frannie substation.  Upgrade the Fractional T1 radios from McCullough Peak to Cedar Mountain microwave stations and Cody Service Center with larger Microwave.  Install leased T1 line at Cody Service Center and interface with the microwave.  Install multiplex, communication batteries and chargers at all the locations requiring upgrades.  Install Fiber DMX nodes at Frannie, the Q0542 Point of Interconnection substation and the Q0542 collector substations.  Install new RTUs at Point of Interconnection substation and the Q0542 collector substation.  Install substation network at all sites.  Power line carrier will be required on the 230 kV transmission line from Point of Interconnection substation to the Yellowtail substation and on the 230 kV transmission line from the Point of Interconnection substation to the Oregon Basin substation.  Mirrored bit relaying will be used on the Q0542 Point of Interconnection to Q0542 collector substation line.  Communications work will also be required at other locations to include Casper Service Center, Portland Control Center (PCC), and the Salt Lake Control Center (SCC). System Impact Study Report Bowler Flats Energy Hub, LLC Page 17 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.1.2.8 Metering Requirements Interchange Metering At the Transmission Provider’s Q0542 Point of Interconnection substation the interchange metering will be designed bidirectional and rated for the total net generation of the project including metering the retail load (per tariff) delivered to the customer. The Transmission Provider will specify and order all interconnection revenue metering, including the instrument transformers, metering panels, junction box and secondary metering wire. The primary metering transformers shall be combination CT/VT extended range for high accuracy metering with ratio’s to be determined during the design phase of the project The metering instrument transformers are long lead items and should be given appropriate time to meet in-service expectations. The metering design package will include two revenue quality meters, test switch, with DNP real time digital data terminated at a metering interposition block. One meter will be designated a primary SCADA meter and a second meter will be used designated as backup with metering DNP data delivered to the alternate control center. The metering data will include bidirectional KWH KVARH, revenue quantities including instantaneous PF, MW, MVAR including per phase voltage and amps data. An Ethernet connection is required for retail sales and generation accounting via the MV-90 translation system. The Transmission Provider recommends the Interconnection Customer install meter by-pass switches to reduce operational disruption. If the Interconnection Customer elects not to install metering bypass switches, the Interconnection Customer’s generator will need to be taken off line for metering testing, repair and service. System Impact Study Report Bowler Flats Energy Hub, LLC Page 18 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.1.1 Cost Estimate Q0542 Collector substation – Engineering, procurement and installation of protection and control and communications equipment. $300,000 Q0542 Point of Interconnection substation - Engineering, procurement and construction of a substation take-off structure and associated installation of the Interconnection Customer’s last span of conductor. $425,000 Q0542 Point of Interconnection substation - Engineering, procurement and installation of metering and communications equipment. $250,000 Q0542 Point of Interconnection substation to Frannie substation – Engineering, procurement and installation of approximately 2.75 miles of fiber optic cable. $390,000 Sub-total Direct Assignment Costs $1,365,000 Interconnection – Network Upgrade Costs Q0542 Point of Interconnection substation – Engineering, procurement and construction of the 230 kV three breaker ring bus point of interconnection switching substation. $9,000,000 230 kV Frannie – Yellowtail transmission line – Engineering, procurement and construction to loop in/out the 230 kV Frannie – Yellowtail transmission line. $330,000 Frannie substation - Engineering, procurement and installation of communication upgrades including MAS radio and microwave upgrades. $305,000 McCullough Peak microwave station - Engineering, procurement and installation of communication and protection and control upgrades including upgrading the MAS and Fractional T1 radio equipment. $365,000 Cedar Mountain substation - Engineering, procurement and installation of communication upgrades including upgrading the Fractional T1 radio equipment. $305,000 Cody Service Center - Engineering, procurement and installation of communication upgrades including upgrading the Fractional T1 radio equipment, installing a T1 line and updating the microwave interface. $320,000 System Impact Study Report Bowler Flats Energy Hub, LLC Page 19 August 19, 2014 Bowler Flats Energy Hub, Q0542 Yellowtail substation - Engineering, procurement and installation of protection and control upgrades. $90,000 Oregon Basin substation - Engineering, procurement and installation of protection and control upgrades. $95,000 Casper Service Center, Portland Control Center and Salt Lake Control Center - Engineering, procurement and installation of communication upgrades. $45,000 Sub-total Network Upgrade Costs $10,855,000 Total Cost – ER Interconnection Service – Interconnection Only $12,220,000 5.1.2 Schedule At this time, it is estimated that the upgrades required to place this project in service could be completed within 24 months of a signed interconnection agreement. Further details regarding the schedule will be available through the Facilities Study when a more detailed estimate has been prepared. The two items will be necessary before any construction starts: 1. Obtain the necessary permits and rights of way to construct the facilities necessary to interconnect the Q0542 project (Interconnection Customer’s responsibility) 2. Execute a Large Generation Interconnection Agreement. Please note the time required to execute the scope of work coupled with the anticipated date the Interconnection Agreement will be signed, results in a timeframe that does not support the Interconnection Customer’s requested in-service date of December 1, 2015. 5.1.3 Maximum Amount of Power that can be delivered into Network Load, with No Transmission Modifications (for informational purposes only). Zero megawatts can be delivered to network load with no transmission modifications. System Impact Study Report Bowler Flats Energy Hub, LLC Page 20 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.1.4 Additional Transmission Modifications Required to Deliver 100% of the Power into Network Load (for informational purposes only) In order to deliver 100% of the Project output to network load, all of the improvements identified in the Energy Resource Section of this report would be required, as well as the following improvements (see Figures 2 and 3):  A new 150-mile 230 kV line from Shirley Basin substation to the Bitter Creek substation with connections to the Standpipe and Latham substations. The line termination at Point of Rocks to Bridger will be removed as the line will be extended and terminate at the Bitter Creek substation, creating the Bridger – Bitter Creek line which is part of the 150 mile line mentioned above.  The line from Bridger to Point of Rocks will be removed and extended to terminate at Bitter Creek  Addition of a new bay at Shirley Basin substation with one 230kV circuit breaker to add the new line termination. The substation will still operate as a ring bus.  A new cross bay at Standpipe substation with three new 230 kV circuit breakers and two new line terminations  Expansion of the Latham substation with new cross bays, two new 230 kV circuit breakers and two new line terminations  A new four-breaker ring bus substation, adjacent to the existing Bitter Creek substation and construction of four line terminations.  Accelerate the reconfiguration of the Bridger substation (see Figure 3)  A new 50-mile 230 kV line from White Horse to Jonah Gas new substations  A new 230 kV three-breaker substation at White Horse  A new 230 kV three-breaker substation at Jonah Gas  Two (2) new 230 kV phase shifting transformers at Craven Creek substation System Impact Study Report Bowler Flats Energy Hub, LLC Page 21 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.2 Network Resource (NR) Interconnection Service Network Resource interconnection service allows the Interconnection Customer to integrate its large generating facility with the Transmission Provider’s transmission system in a manner comparable to that in which the Transmission Provider integrates its generating facilities to serve native load customers. The transmission system is studied under a variety of severely stressed conditions in order to determine the transmission modifications. If any, which are necessary in order to deliver the aggregate generation in the area of the Point of Interconnection to the Transmission Provider’s aggregate load, and assumes that some portion of existing network resources are displaced by the output of the Interconnection Customer’s large generating facility. Network resource interconnection service in and of itself does not convey transmission service. 5.2.1 Study Results Wyoming has more generation than load, and as such, surplus energy must be exported to network loads in other states. Projects are planned to construct additional transmission lines (the Energy Gateway projects) from Wyoming to points in Idaho, Oregon, Utah, and the Desert Southwest to accommodate additional exports from Wyoming; however these projects will not be in-service in time for the proposed interconnection. An overview of these plans can be found at the Northern Tier Transmission Group website (http://www.nttg.biz/site/) or at the Informal Message section of Transmission Provider’s OASIS website (http://www.oasis.pacificorp.com/OASIS/PPW/). In order to deliver 100 percent of the Project output to network loads prior to the completion of the Aeolus to Populus segment of Energy Gateway, additional system improvements are required for the Q0542 project. There are several transmission constraints in Wyoming that need to be alleviated in order to accommodate the 240 MW Q0542 output (see Figure 2): (1) TOT 4A. TOT 4A is defined as the sum of the flows on the following 230kV lines: Riverton – Wyopo, Spence – Mustang and Miners – Platte. This path is fully committed at this time. (2) Rock Springs / Firehole West. This path is defined as the sum of the flows on the Rock Springs – Raven 230 kV and the Firehole - Mansface 230 kV lines. This path is fully committed at this time. To accommodate the Project output, a new approximately 150-mile long 230 kV line from Shirley Basin to Bitter Creek substation, will be necessary in order to increase the constrained TOT 4A transmission path. Additional studies will be required to determine the new TOT 4A path rating after the addition of the new line and it will have to go through the WECC Three Phase Facility Rating process. System Impact Study Report Bowler Flats Energy Hub, LLC Page 22 August 19, 2014 Bowler Flats Energy Hub, Q0542 Additionally, a new approximately 50-mile long 230 kV line from a new substation (White Horse) on the Atlantic City – Rock Springs 230 kV line, to a new substation near Jonah Gas is required. A 230 kV phase shifting transformer at Craven Creek is required for flowability as the Monument West path is also phase shifted. A portion (128 MW) of the 240 MW project output could be scheduled on the Bridger West system. The Bridger West (three 345 kV lines) path capacity is 2400 MW and current obligations total 2208 MW. The remaining 192 MW of capacity is shared between Idaho Power, 64 MW (one-third) and PacifiCorp, 128 MW (two-thirds). The remainder will be scheduled on the improved Rock Springs/Firehole West path (White Horse – Jonah). The new proposed projects are in Figures 2 and 3. Pinedale Jonah FieldChappel Creek Chimney Butte Labarge Kemmerer Monument Exxon Blacks Fork South Trona Palisades Blue Rim Mansface Firehole Little Mtn Rock Springs Jim Bridger Point of RocksBitter Creek Bar X Atlantic City Mustang Great Divide Bairoil 115 kV Spence Riverton Echo Springs Latham Wyopo TOT4A 850MW Lima Columbia Geneva Steel Platte Flaming Gorge Naughton Craven Creek Railroad Paradise Raven Idaho Wyoming Utah Colorado Treasureton Ben  Lomond To Populus To Three Mile Knoll Birch Creek 230 kV345 kV <230 kV Foreign owned Miners White Horse Standpipe Shirley Basin Proposed 230kV Evanston West 1280 MW Monument West 475 MW Bridger West 2400 MW Rock Springs – Firehole 640 MW Figure 2: Central & Southwest Wyoming Transmission System System Impact Study Report Bowler Flats Energy Hub, LLC Page 23 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.2.2 Network Resource Requirements 5.2.2.1 Generating Facility Modifications See Section 5.1.2.1. 5.2.2.2 Network Resource Transmission Modifications Transmission modifications required include the following (refer to Figures 2 and 3):  Construct a new 150-mile 230 kV transmission line from Shirley Basin to the Bitter Creek substation.  Construct a new 50-mile 230 kV transmission line from White Horse to the Jonah Gas substation. Figure 3 – New 230 kV Line from Shirley Basin to Bitter Creek substation and Other Improvements System Impact Study Report Bowler Flats Energy Hub, LLC Page 24 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.2.2.3 Network Resource Protection and Control Requirements To support the Transmission line upgrades required for the NR part of the project the following protective relaying will be required along with communication links to support the line relaying: Shirley Basin – Standpipe Standpipe – Latham Latham – Platte Latham #1 Bitter Creek Latham #2 Basin –Bitter Creek Bitter Creek – Point of Rocks Bitter Creek– Jim Bridger White Horse – Jonah Gas Rock Springs – White Horse White Horse – Atlantic City All of the transmission lines will be built with optical fiber cable in the shield wire position. This communication media will be used by the line relay in most locations. For each of the transmission lines, permissive overreaching transfer trip scheme will be used except for the short line between the Bitter Creek and the Bridger substations which will use line current differential and the White Horse to Atlantic City transmission line which will continue to use power line carrier. Relaying will be needed for the new phase shifting transformers in the Craven Creek substation. 5.2.2.4 Network Resource Substation Requirements Shirley Basin substation At Shirley Basin substation a new bay will be added with one 230 kV circuit breaker to add the new line termination. The substation will still operate as a ring bus. Other major equipment installed include: CCVT’s, group operated switches, and lightning arresters. Standpipe substation Standpipe substation will need to be expanded to the south/west which includes additional fence, ground grid, and grading. A new bay will be installed with three 230 kV circuit breakers to terminate the two new line positions in the breaker and a half configuration. Other major equipment include: CCVT’s group operated switches, and lightning arresters. Latham substation At Latham substation two new 230 kV circuit breakers will be installed to terminate the two new line positions. Other major equipment include: CCVT’s, group operated switches, and lightning arresters. System Impact Study Report Bowler Flats Energy Hub, LLC Page 25 August 19, 2014 Bowler Flats Energy Hub, Q0542 Echo Springs substation Relaying on the existing 230kV line from Latham to Point of Rocks will be mirrored bits. Two wave traps will be removed. Bitter Creek substation Bitter Creek substation will be completely expanded. A new substation will be constructed directly adjacent to the existing substation. The new substation will be a four breaker ring bus with four 230kV, 3000A breakers and four line terminations. Other major equipment include: CCVT’s, group operated switches, lightning arresters, and a new control building. It is assumed a distribution line can be built to provide station service. The fence will enclose both old and new yards and the new ground grid will be tied with the existing ground grid. The 230kV Monell line will remain in its existing position. Point of Rocks substation The existing 230kV position to Jim Bridger substation will be removed. Two 230 kV switches will be removed. Jim Bridger substation As part of the Jim Bridger reconfiguration, two 230kV bays will be installed with five 230kV, 3000A circuit breakers. Other major equipment required include: group operated switches, CCVT’s, and lightning arresters. Additional AC and DC load centers will be required. One 230kV breaker and one 230kV switch will be removed. The 230kV line terminations will be moved within the substation. Jonah Field substation A new substation will be constructed near the Jonah Gas facility. This substation will be a three breaker ring bus with three 230kV circuit breakers. Other major equipment required include: CCVT’s, group operated switches, a control building, and lightning arresters. It is assumed a distribution line is in close proximity and can be expanded to serve the station service of the substation. Fencing, grading, ground grid, conduit, cable trench, and yard lighting will be required. White Horse substation A new substation will be constructed in between Atlantic City substation and Rock Springs substation. This substation will be a three breaker ring bus with three 230kV circuit breakers. Other major equipment required include: CCVT’s (one with a line tuner and carrier accessories), a wavetrap, an SSVT, group operated switches, a control building, and lightning arresters. Fencing, grading, ground grid, conduit, cable trench, and yard lighting will be required. Atlantic City substation No major substation modifications are required at Atlantic City substation. System Impact Study Report Bowler Flats Energy Hub, LLC Page 26 August 19, 2014 Bowler Flats Energy Hub, Q0542 Rock Springs substation One 230kV wavetrap will be removed (old Atlantic City line). Craven Creek substation Two 230kV phase shifting transformers will be installed (one for redundancy). Three 230kV circuit breakers will be installed. Other major equipment include: lightning arresters and group operated switches; three CCVT’s will be relocated within the substation. The installation of the transformers will require expanding the substation which includes fencing, grading, and new ground grid. 5.2.2.5 Network Resource Communication Requirements Communication Requirements to deliver the Q0542 Projects generation to the Transmission Provider’s Network Load include:  Install OPGW fiber optic cable on the new 150 mile line from Shirley Basin to Bitter Creek and on to Jim Bridger substation.  Fiber nodes and multiplex will need to be installed at Platte, Latham, Echo, Bar X, Bitter Creek and Point of Rocks.  Mirrored bits line protection will be over the OPGW fiber installed on the new lines.  Install a new RTU at Bitter Creek substation  Install 48 volt battery and chargers at Echo, BarX, and Bitter Creek substations.  Install OPGW fiber optic cable on the new line from Jonah Field to the new White Horse substation.  Install a new RTU at the White Horse substation  Install fiber node and multiplex at the White Horse substation.  Communications work will also be required at other locations to include Casper Service Center, Portland Control Center (PCC), and the Salt Lake Control Center (SCC). System Impact Study Report Bowler Flats Energy Hub, LLC Page 27 August 19, 2014 Bowler Flats Energy Hub, Q0542 5.2.3 Network Resource Cost Estimate Interconnection – ER Only $12,220,000 NR Interconnection Shirley Basin substation – Bitter Creek substation - Engineering, procurement and construction of a new 150 mile 230 kV transmission line. $88,500,000 White Horse substation – Jonah Gas substation - Engineering, procurement and construction of a new 150 mile 230 kV transmission line. $26,500,000 Shirley Basin substation - Engineering, procurement and construction of a new bay and 230 kV circuit breaker including CCVT’s, group operated switches, and lightning arresters. $3,300,000 Standpipe substation - Engineering, procurement and construction to expand substation, add a bay and three 230 kV circuit breakers including CCVT’s group operated switches, and lightning arresters. $6,700,000 Latham substation - Engineering, procurement and construction to add two new 230 kV circuit breakers including CCVT’s, group operated switches, and lightning arresters. $2,750,000 Echo Springs substation - Engineering, procurement and installation of mirrored bits relaying and removal of two wave traps. $2,650,000 Bitter Creek substation - Engineering, procurement and construction of a new four breaker ring bus substation including CCVT’s, group operated switches, lightning arresters, and a new control building. $17,700,000 Point of Rocks substation – Engineering and removal of the 230 kV line position to the Jim Bridger substation and the removal of two switches. $285,000 Jim Bridger substation - Engineering, procurement and construction of two new bays and five new 230 kV circuit breakers, new AC and DC load centers and the installation of group operated switches, CCVT’s, and lightning arresters. $8,850,000 Jonah Field substation - Engineering, procurement and construction of a 230 kV three breaker ring bus including CCVT’s, group operated switches, a control building, and lightning arresters. 15,500,000 System Impact Study Report Bowler Flats Energy Hub, LLC Page 28 August 19, 2014 Bowler Flats Energy Hub, Q0542 White Horse substation - Engineering, procurement and construction of a new 230 kV three breaker ring bus substation including CCVT’s (one with a line tuner and carrier accessories), a wavetrap, an SSVT, group operated switches, a control building, and lightning arresters. 12,600,000 Atlantic City substation – Engineering and labor to upgrade the protection and control equipment at the Atlantic City substation. $80,000 Rock Springs substation - Engineering and labor to remove one 230 kV wavetrap. $43,000 Craven Creek substation - Engineering, procurement and construction to expand the substation and install two 230 kV phase shifting transformers and three 230 kV circuit breakers including group operated switches, a control building, lightning arresters and relocation of three CCVT’s. $44,400,000 Total Cost – NR Interconnection Service – Interconnection Only $242,078,000 5.2.4 Schedule The Transmission Provider estimates it will require approximately 7 to 10 years to design and build both the Energy Resource and Network Resource facilities described in this report after the completion of both items below. 1. Obtain the necessary permits and rights of way to construct the facilities necessary to interconnect the Q0542 project (Interconnection Customer’s responsibility) 2. Execute a Large Generation Interconnection Agreement. Please note the time required to execute the scope of work coupled with the anticipated date the Interconnection Agreement will be signed, results in a timeframe that does not support the Interconnection Customer’s requested in-service date of December 1, 2015. 6.0 PARTICIPATION BY AFFECTED SYSTEMS Transmission Provider has identified the following affected systems: Western Area Power Administration. A copy of all reports will be shared the each affected system. System Impact Study Report Bowler Flats Energy Hub, LLC Page 29 August 19, 2014 Bowler Flats Energy Hub, Q0542 7.0 APPENDIX 1: PROPERTY REQUIREMENTS Property Requirements for Point of Interconnection Substation The following applies to property acquired by an Interconnection Customer on which a Point of Interconnection substation will be built to accommodate the Interconnection Customer’s project. The property will ultimately be assigned to PacifiCorp, the Transmission Provider.  Property must be environmentally, physically and operationally acceptable to the Transmission Provider without any material defects of title (or as deemed acceptable to the Transmission Provider) and without unacceptable encumbrances. The property shall be a permitted or permittable use in all zoning districts. Property lines shall be surveyed and show all encumbrances, roads (private or public); easements (prescriptive or express) etc. Examples of potentially unacceptable environmental, physical, or operational conditions:  Environmentally unacceptable conditions could include but are not limited to known contamination of site; evidence of environmental contamination by any dangerous, hazardous or toxic materials as defined by any governmental agency; property is in violation of building, health, safety, environmental, fire, land use, zoning or other such regulation, ordinances, or statues of any governmental entities having jurisdiction over the property; underground or above ground storage tanks; known remediation sites on property; ongoing mitigation activities or monitoring activities; asbestos; lead-based paint, etc. At a minimum, a phase I environmental study is required for company land being acquired in fee. Evidence will be required 60 days prior to the start of construction.  Physically unacceptable conditions could include but are not limited to inadequate drainage; in flood zone; erosion issues; wetland overlays; threatened and endangered species; archeological or culturally sensitive areas; inadequate sub- surface elements, etc. Geotechnical studies are required by the Transmission Provider.  Operationally unacceptable conditions could include but are not limited to inadequate access for company equipment; existing structures on land that require removal prior to building of substation; ongoing maintenance for landscaping or extensive landscape requirements; ongoing homeowner's or CC&R's that are not acceptable to the Transmission Provider.  Property should be acquired by fee ownership. If fee acquisition is not possible, then the term shall be perpetual and the use exclusive and provide the Transmission Provider with all property rights it deems necessary (perpetual easement). All contracts are subject to the Transmission Provider’s approval prior to execution. System Impact Study Report Bowler Flats Energy Hub, LLC Page 30 August 19, 2014 Bowler Flats Energy Hub, Q0542  The Interconnection Customer is required to identify any and all land rights to the subject property, which are to be retained by the Interconnection Customer prior to conveying property. All retained land rights are subject to the Transmission Provider’s approval.  If the Interconnection Customer is building facilities to be owned by the Transmission Provider, then the Interconnection Customer must obtain all permits required by all relevant jurisdictions for the use including but not limited to conditional use permits, Certificates of Public Convenience and Necessity, California Environmental Quality Act, etc., as well as all construction permits for the project  Interconnection Customer will not reimburse through network upgrades for more than the market value of the property.  Property must be assignable to company and without litigation, suit, liens, condemnation actions, foreclosures actions, etc. System Impact Study Report Bowler Flats Energy Hub, LLC Page 31 August 19, 2014 Bowler Flats Energy Hub, Q0542 8.0 APPENDIX 2: COMBINED QUEUE QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 2 01/19/01 East N/A SF Phosphates Substation, 230 kV 02/01/02 11 3 01/23/01 East N/A West Valley Substation, 138 kV 09/01/01 200 7 03/07/01 East N/A Foote Creek Substation, 34.5 kV 08/01/01 50 8 03/08/01 East N/A Monument Switching Station, 230 kV 10/01/04 110 9 04/01/01 East N/A Rowley Substation, 138 kV 06/15/01 80 11 07/20/01 East N/A Gatsby Substation, 138 kV 09/01/02 120 12 08/27/01 East N/A Longhollow Switching Station, 138 kV 12/26/03 146 18 10/21/02 East N/A Northwest Substation, 46 kV 10/06/04 25 20 04/30/03 East GEN Mona 345kV 03/22/06 280 21 04/30/03 East GEN Mona 345kV 03/22/06 245 29a 09/18/03 East GEN Goshen 161kV 02/12/06 64.5 29b 09/18/03 East GEN Goshen 161kV 10/20/10 129 System Impact Study Report Bowler Flats Energy Hub, LLC Page 32 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 44 06/03/04 East ER Timp - Tri-City Line, 138kV 07/29/07 535-S 567-W 52 03/28/05 East GEN Terminal Sub Distribution Circuit, 12.47kV 07/20/06 3.2 59 08/24/05 East NR North of Antelope Mine Sub, 230kV 06/01/11 250-S 285-W 66 12/05/05 East NR Blundell Geothermal Sub 10/19/07 11-S 15-W 73 03/27/06 East GEN Spanish Fork - Santaquin, 46Kv 07/31/08 18.9 310 339268 04/12/06 East NT PACE (Resource) PACE 04/15/06 141 78 04/25/06 East NR Mona Substation, 345Kv 04/25/06 59 90 06/22/06 East ER Uinta Long Hollow, 138kV 05/15/08 60 93 09/19/06 East GEN Tooele Substation, 47- kV 03/01/08 1 96 10/09/06 East NR w/ER Uinta Long Hollow, 138kV 07/02/08 79.5 107 11/14/06 East NR Timp-Tri-City line, 138kV 08/18/08 79-S 49-W System Impact Study Report Bowler Flats Energy Hub, LLC Page 33 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 111 12/08/06 East NA 2700 East 11600 South, Sandy, UT 08/09/07 0.511 117 01/18/07 East NR w/ER Miners- Difficulty Line, 230kV 12/09/08 99 118 01/18/07 East NR w/ER Miners- Difficulty Line, 230kV 12/09/08 19.5 119a 01/29/07 East NR w/ER Foote Creek Sub. 230kV 09/30/09 127.5 120 02/08/07 East NA Existing point of service in Laramie, WY 10/04/07 0.65 126 03/05/07 East NR Near Glenrock Mine 230kV 01/02/09 237 129 03/30/07 East N/A Oquirrh-Lark, 46-kV 04/01/09 4.8 138 05/22/07 East N/A Green River 12 circuit, 12.5kV 05/22/09 0.575 139 05/25/07 East N/A University Substation, 46kV 10/09/09 7.6 150 07/13/07 East N/A PacifiCorp's 24.9-kV Circuit, QRY15, out of Quarry Substation 6/18/2009 1 System Impact Study Report Bowler Flats Energy Hub, LLC Page 34 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 153 08/08/07 East NR w/ER Dave Johnston- Yellowcake Line, 230-kV 10/28/10 200.5 154 08/10/07 East N/A Goshen-Ucon Line, 69-kV 04/30/12 19.8 161 09/04/07 East N/A 14.4-kV Circuit out of Pinedale Substation 1/22/2009 0.05 165 10/12/07 East N/A 3474 N. 3rd Street 3/11/2008 0.03 171 11/08/07 East N/A PacifiCorp's 69- kV, Sand Hills Line between Casper & Platte Junction 12/25/2009 19.5 175 12/07/07 East NE w/ER Craven Creek to Chappel Creek 230 kV 11/30/12 150 191 01/25/08 East NR w/ER PAC's 230 kV Jim Bridger - Aeolus 08/01/14 500 199 02/20/08 East NR PacifiCorp's proposed 230- kV Aeolus Substation 12/01/14 200 System Impact Study Report Bowler Flats Energy Hub, LLC Page 35 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 200 02/20/08 East NR PacifiCorp's proposed 230- kV Aeolus Substation 12/01/14 100 201 02/20/08 East NR PacifiCorp's proposed 230- kV Aeolus Substation 12/31/15 100 203 02/26/08 East NR w/ER Shirley-Basin Substation on the PacifiCorp's 230-kV Miners- Difficulty Line 09/30/10 111 213   04/22/08 West N/A  Bernice #22 circuit out of Bernice Substation   8/4/2009 0.3  214 04/24/08 East N/A Pinedale Circuit #23 02/18/09 1.96 220 05/12/08 East NR w/ER Latigo Substation between Casper and Windstar 230- kV line 11/20/09 100.5 947 493092 05/23/08 East NT PACE (Resource) PACE 6/1/2012 316 - S 562-W 224a 05/27/08 East NR w/ER PacifiCorp's 345 kV Mona substation 05/15/15 320 System Impact Study Report Bowler Flats Energy Hub, LLC Page 36 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 224b 05/27/08 East NR w/ER PacifiCorp's 345 kV Mona substation 05/15/15 230 252 11/25/08 East N/A Customer's existing 46-kV system 3/1/2009 0.23 253 11/26/08 East N/A 1600 West B Avenue, Utah Industrial Depot, Tooele, Utah 2/20/2009 0.05 255 12/23/08 West NR w/ER 3.2 miles NE of PacifiCorp's Goshen Substation 05/20/12 151.8 256 01/14/09 West NA HPS 12 Circuit 04/15/09 1.696 267-A 04/13/09 East NR w/ER PacifiCorp's 345-kV Jim Bridger Power Plant, Point of Rocks, WY 6/12/10 18.3- S 22-W 267-B 04/13/09 East NR w/ER PacifiCorp's 345-kV Jim Bridger Power Plant, Point of Rocks, WY 5/5/13 18.3- S 22-W System Impact Study Report Bowler Flats Energy Hub, LLC Page 37 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 267-C 04/13/09 East NR w/ER PacifiCorp's 345-kV Jim Bridger Power Plant, Point of Rocks, WY 5/22/11 18.3- S 22-W 267-D 04/13/09 East NR w/ER PacifiCorp's 345-kV Jim Bridger Power Plant, Point of Rocks, WY 5/27/12 18.3- S 22-W 270-A 04/30/09 East ER PacifiCorp's Huntington Power Plant, Huntington, UT 11/21/10 16.2 270-B 04/30/09 East ER PacifiCorp's Huntington Power Plant, Huntington, UT 4/30/15 16.2 271-A 04/30/09 East ER PacifiCorp's Hunter Power Plant, Castledale, UT 4/13/10 17.0 271-B 04/30/09 East ER PacifiCorp's Hunter Power Plant, Castledale, UT 4/30/15 17.0 271-C 04/30/09 East ER PacifiCorp's Hunter Power Plant, Castledale, UT 4/30/16 8.7 System Impact Study Report Bowler Flats Energy Hub, LLC Page 38 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 272 05/14/09 East NR w/ER PacifCorp's proposed new substation on the 230-kV Miners- Difficulty Line 9/30/10 12.0 1145 563529 06/26/09 East NT PACEW PACEW 4/1/10 25.0 282 08/07/09 East N/A PacifiCorp's 138/46-kV Lampo Substation 9/25/09 0.0360 290-A 09/22/09 East NR/ER 17 miles south SE of Rock Springs, WY 6/30/12 100.8 290-B 09/22/09 East NR/ER 17 miles south SE of Rock Springs, WY 12/31/12 100.8 290-C 09/22/09 East NR/ER 17 miles south SE of Rock Springs, WY 6/30/13 50.4 291 09/25/09 East NR/ER PacifiCorp's Emery to Spanish Fork 345 kV line 12/31/11 100.0 1167 581025 10/05/09 East NT PACE PACE (Load) 3/1/11 53-S 94-W 1169 583608 10/14/09 East NT GSHN GSHN (Load) 1/1/13 32-S 64-W System Impact Study Report Bowler Flats Energy Hub, LLC Page 39 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 1170 583614 10/14/09 East NT PACE PACE (Load) 9/1/10 21 301 10/27/09 East NR/ER PacifiCorp's proposed new substation adjacent to the Lake Side Power Gen Facility 6/1/14 707-S 670-W 306-A 11/13/09 East NR/ER PacifiCorp's Amassa Substation, (DJ-Difficulty 230-kV) 1/31/11 48.3 310 12/21/09 East N/A PacifiCorp's 34.5-kV Parowan Substation 10/31/10 20.0 311 12/22/09 East N/A Three Peaks Substation Substation 10/31/10 20.0 313 12/22/09 East NR PacifiCorp's 138 kV switch 132 located 3/4 mile N of the generation facility site 12/31/12 25-S 65-W 314 12/31/09 East NR PacifiCorp's 34.5-kV West Cedar Substation 12/31/10 20.0 1190 603498 02/15/10 East NT PACE PACE (Load) 7/1/10 12.0 System Impact Study Report Bowler Flats Energy Hub, LLC Page 40 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 323-A 03/03/10 East NR/ER PacifiCorp's 230-kV Sunbeam Substation 5/31/11 21.6 323-B 03/03/10 East NR/ER PacifiCorp's 230-kV Sunbeam Substation 11/30/11 21.6 324 03/08/10 East N/A Parowan - Rocky Mountain Power Substation 8/10/12 40.0 1202 614127 04/09/10 East NT WYOEAST WYODAK (Load) 11/17/10 35.0 332 04/29/10 East N/A PacifiCorp's 24.9-kV circuit, SML21, out of South Milford Substation 6/1/11 2.8 1209 617716 05/03/10 East NT GSHN GSHN (Load) 1/1/13 39.0 1210 618363 05/03/10 East PTP PACE MDWP 6/1/11 3.0 1214 618940 05/14/10 East NT WYOCENTRAL WYOCENTRAL (Load) 10/1/10 10.0 333 05/17/10 East N/A PacifiCorp's 24.9 kV circuit, SML21, out of South Milford Substation 10/1/11 2.8 1215 620282 05/19/10 East NT PACE PACE (Load) 6/30/11 17.0 1216 621679 05/27/10 East NT PACE PACE (Load) 7/1/10 15.0 System Impact Study Report Bowler Flats Energy Hub, LLC Page 41 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 335 06/01/10 East NR/ER PacifiCorp's Amassa Substation, (DJ-Difficulty 230-kV) 3/1/12 49.5 341 06/10/10 East NR/ER PacifiCorp's Goshen Substation at 161 kV 11/1/12 120.0 1223 625986 06/17/10 East NT WYOEAST WYOEAST (Load) 1/1/11 2.0 1224 626003 06/17/10 East NT PACE PACE (Load) 10/1/10 2.0 1225 626275 06/17/10 East NT WYOEAST WYOEAST (Load) 12/10/10 9 1229 626453 06/23/10 East NT PACE PACE (Load) 7/1/11 150.0 1230 626791 06/23/10 East NT PACE PACE (Load) 2/24/11 30.0 1231 626864 06/23/10 East NT PACE PACE (Load) 11/1/10 6.0 1236 630525 07/15/10 East NT WYOEAST WYOEAST (Load) 6/1/11 15.0 1237 634125 08/03/10 East NT PACE PACE (Load) 10/1/10 8.0 348 08/09/10 East N/A PacifiCorp's 24.9-kV Circuit, QRY15, out of Quarry Substation 4/30/11 0.22 1238 635532 08/09/10 East NT WYOEAST WYOEAST (Load) 7/31/13 67.0 1241 637972 08/20/10 East NT PACE PACE (Load) 7/1/13 21.0 1248 645170 09/22/10 East PTP PACE MDWP 1/1/12 3.0 1251 645781 09/29/10 East NT PACE PACE (Load) 10/1/11 4.0 1252 645790 09/29/10 East NT PACE PACE (Load) 12/1/10 8.0 1256 648008 10/08/10 East NT PACE (Resource) PACE 5/1/14 660.0 1258 648377 10/12/10 East NT PACE PACE (Load) 5/1/13 13.0 1263 656398 11/09/10 East NT DJ WYOEAST (Load) 12/1/10 1.0 System Impact Study Report Bowler Flats Energy Hub, LLC Page 42 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 363   12/13/10 East N/A  PacifiCorp's  24.9‐kV  Southfork  Circuit, 4H27,  out of South  Cody  Substation    TBD 0.1  365   12/20/10 East N/A  PacifiCorp's  34.5‐kV N  Rawlins  Curcuit, 9H440,  out of Platte  Substation    5/1/2011 0.11  367   12/27/10 East N/A  PacifiCorp's  proposed  Sigurd‐Red  Butte 345‐kV  transmission  line    1/1/2014 169-S 172-W 375   03/04/11 East NR/ER Difficulty Substation 10/1/2014 351  1305 686836 03/18/11 East NT PACE PACE (Load) 4/1/2011 6.00  384   03/30/11 East NR/ER Pinto Substation 12/31/2012 60  1312 692513 04/04/11 East NT PACE PACE (Load) 7.00  1317 702580 05/11/11 East NT PACE PACE (Load) 04/01/12 70 1326 709355 06/07/11 East PTP PACE PACE 1/1/2015 20  396   08/04/11 East N/A  Circuit OQU18, Oquirrh #18 feeder, out of Oquirrh substation 12/1/2011 0.585  System Impact Study Report Bowler Flats Energy Hub, LLC Page 43 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 1361 741886 10/12/11 East NT WYOCENTRAL WYOCENTRAL (Load) 1/1/2012 37 403   10/25/11 East NR/ER Sigurd Substation 7/1/2014 525  1376 752491 11/29/11 East NT PACE PACE (Load) 1/1/2013 5 407   01/17/12 East NR/ER  Rock Springs- Naughton Line, 230kV 12/31/2012 79.8  409   01/26/12 East NR/ER  Windstar- Aeolus line, 230kV 9/30/2014 320  1405 769663 02/27/12 East NT PACE PACE (Load) 5/1/2012 89  1407 770827 03/07/12 East NT WYON WYON (Load) 5/1/2012 4  415   03/12/12 East N/A  24.9-kV circuit, SML21, out of South Milford 12/1/2012 10  420   03/26/12 East NR/ER  Carbide substation, 69kV 10/1/2014 200  1412 775561 03/28/12 East NT GSHN GSHN (Load) 10/1/2013 3  1497 785040 05/23/12 East NT WYOEAST PACE 11/01/13 25 425   06/01/12 East N/A Chappel Creek substation 7/30/2016 156.2  426   06/26/12 East NR/ER Moab-Pinto Line, Pole #365 8/31/2014 80  1520 804038 08/15/12 East NT PACE PACE 8/15/2012 2  1521 804043 08/15/12 East NT WYOCENTRAL WYOCENTRAL 10/15/2012 1  1523 805002 08/23/12 East NT PACE PACE 12/1/2012 46  1524 805181 08/23/12 East NT WYOCENTRAL WYOCENTRAL 11/1/2012 5  System Impact Study Report Bowler Flats Energy Hub, LLC Page 44 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 432   08/27/12 East N/A  Customer's existing 138kV substation 5/1/2013 6.3  1530 806472 08/30/12 East NT TRONA TRONA 11/1/2012 8  1531 806486 08/30/12 East NT TRONA TRONA 1/1/2015 29  1532 806494 08/30/12 East NT PACE PACE 1/1/2012 2  1533 806544 08/30/12 East NT PACE PACE 1/1/2012 4  1534 806561 08/30/12 East NT PACE PACE 1/1/2013 6  1535 806585 08/30/12 East NT PACE PACE 12/1/2012 8  1536 807115 08/31/12 East NT PACE PACE (Load) 9/1/2013 5  1540 809252; 809367 09/14/12 East NT BOZ ANDK (Load) 8/1/2016 50  1541 809254; 809362 09/14/12 East NT BOZ ANDK (Load) 8/1/2016 100  1542 809337; 809374 09/14/12 East NT BOZ ANDK (Load) 1/1/2013 20  1543 809340; 809375 09/14/12 East NT BOZ ANDK (Load) 1/1/2015 24  1544 809347; 809376 09/14/12 East NT BOZ ANDK (Load) 2/1/2015 3  1545 809353; 809378 09/14/12 East NT BOZ ANDK (Load) 1/1/2016 3  1546 809355; 809380 09/14/12 East NT BOZ ANDK (Load) 9/1/2016 3  1547 809357; 809382 09/14/12 East NT BOZ ANDK (Load) 1/1/2017 11  1548 809397 ; 809398 09/14/12 East NT BOZ ANDK (Load) 1/1/2013 30  437   09/17/12 East N/A  Circuit PRS13, Preston #13, out of Preston substation 4/17/2014 0.5  System Impact Study Report Bowler Flats Energy Hub, LLC Page 45 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 438   09/18/12 East N/A  Customer's electric system from Tooele Depot substation 4/1/2013 1.75  439   09/18/12 East N/A  Customer's electric system from Tooele Depot substation 4/1/2013 1.56  442   10/11/12 East N/A  RIGBY- REXBURG TAP TO WEBSTER 9/30/2014 5.6  1578 77610461 12/06/12 East NT Sunbeam BRDY 3/1/2013 45  450   12/21/12 East N/A Pavant substation 3/15/2014 50  451   01/02/13 East N/A  Circuit CLM11, Coleman #11, out of Coleman substation 12/13/2013 3  1591 77717778 01/02/13 East PTP PACE 4C 1/1/2014 66  1592 77717792 01/02/13 East PTP PACE 4C 1/1/2014 100  453   01/07/13 East N/A  Circuit CLF11, CLIFTON #11 DAYTON & BANIDA, out of Clifton substation 12/31/2013 1.6  System Impact Study Report Bowler Flats Energy Hub, LLC Page 46 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 454   01/10/13 East N/A  Circuit WCD28, West Cedar #28, out of West Cedar substation 6/30/2014 3  455   01/10/13 East N/A  Circuit WCD28, West Cedar #28, out of West Cedar substation 6/30/2014 3  456   01/10/13 East N/A  Circuit BKl12, Brooklawn #12, out of Brooklawn substation 6/30/2014 2.1  457   01/10/13 East N/A  Circuit BKl11, Brooklawn #11, out of Brooklawn substation 6/30/2014 2.1  1599 77699698 01/16/13 East NT GSHN GSHN 11/1/2013 1  459   01/18/13 East N/A  Circuit SML12, South Milford #12, out of South Milford substation 6/30/2014 3  460   01/18/13 East NR/ER  Pavant-Gonder Transmission Line 12/31/2014 160  1603 77786388 01/23/13 East NT PACE MDGT 01/01/15 24 System Impact Study Report Bowler Flats Energy Hub, LLC Page 47 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 1605 77762035 01/25/13 East NT NEWPOINT NEWPOINT 01/01/16 84 1607 77762000 01/30/13 East NT NEWPOINT NEWPOINT 01/01/16 164 463   02/11/13 East N/A  Circuit ENO12, Enoch#12, out of Enoch substation 6/30/2014 3  464   02/11/13 East N/A  Circuit WCD28, West Cedar# 28, out of West Cedar substation 6/30/2014 3  465   02/11/13 East NR/ER Abajo substation 12/31/2015 50.4  471   02/28/13 East N/A  Circuit WCD28, West Cedar #28, out of West Cedar substation 6/30/2014 3  472   02/28/13 East N/A  Circuit WCD28, West Cedar #28, out of West Cedar substation 6/30/2014 3  473   02/28/13 East N/A  Circuit WCD28, West Cedar #28, out of West Cedar substation 6/30/2014 3  System Impact Study Report Bowler Flats Energy Hub, LLC Page 48 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 475   03/08/13 East N/A  Circuit ENV12, Enterprise #12, out of Enterprise Valley substation 12/31/2013 3  488   03/19/13 East N/A  Circuit PRV25, Parowan Valley#25, out of Parowan Valley substation 12/31/2013 3  489   03/19/13 East N/A  Circuit ENO12, Enoch#12, out of Enoch substation 12/31/2013 3  491   03/19/13 East N/A  Circuit BKl12, Brooklawn #12, out of Brooklawn substation 12/31/2013 3  492   03/19/13 East N/A  Circuit SML12, South Milford #12, out of South Milford substation 12/31/2013 3  System Impact Study Report Bowler Flats Energy Hub, LLC Page 49 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 493   03/19/13 East N/A  Circuit SML11, South Milford #11, out of South Milford substation 12/31/2013 3  1722 78169628 04/30/13 East PTP TRONA REDB 5/1/2014 30 1723 78170277 04/30/13 East PTP TRONA MPAC 5/1/2014 30 500   06/12/13 East N/A Circuit RKW11, Porter Rockwell #11, out of Porter Rockwell substation 9/1/2013 2.589  1747 78351080 06/18/13 East NT PINTO PACE 11/30/2015 80 502   06/27/13 East N/A Circuit MLF12, Milford#12, out of Milford substation 10/15/2015 2.97  503   06/27/13 East N/A Circuit SML21, South Milford #21, out of South Milford substation 10/15/2015 2.97  System Impact Study Report Bowler Flats Energy Hub, LLC Page 50 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 504   06/27/13 East N/A Circuit SML12, South Milford #12, out of South Milford substation 10/15/2015 2.97  512   08/22/13 East N/A Milford substation 72- 47kv distribution circuit, pole number I73-28- 10#, 059303 3/1/2015 3  513   09/10/13 East NR/ER 138kV bus at West Cedar substation (or) 138kV bus at Three Peaks substation 12/31/2015 80  514   09/13/13 East NR/ER Tap to the 138 kV Enterprise Valley – West Cedar transmission line 12/1/2015 80  515   09/13/13 East NR/ER Sigurd to Red Butte No. 2 345kV transmission line 12/1/2015 80  System Impact Study Report Bowler Flats Energy Hub, LLC Page 51 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 516   09/13/13 East NR/ER Sigurd to Red Butte No. 2 345kV transmission line 6/30/2015 3  1766 78752066 09/26/13 East NT DJ WYOE 10/1/2014 50 1767 78752068 09/26/13 East NT DJ WYOE 10/1/2014 50 1768 78752070 09/26/13 East NT DJ WYOE 10/1/2014 50 1769 78752071 09/26/13 East NT DJ WYOE 10/1/2014 109 1770 78752072 09/26/13 East NT DJ WYOE 10/1/2014 109 1771 78752081 09/26/13 East NT Fourcorners DJ 10/1/2014 85 518   10/01/13 East N/A Tap to 34.5 kV MDD24 (Middleton 24) circuit feeding Dixie Deer substation 6/30/2015 2.97  519   10/01/13 East N/A Tap to 34.5 kV MDD24 (Middleton 24) circuit feeding Dixie Deer substation 6/30/2015 3  520   10/01/13 East N/A Tap to 34.5 kV MDD24 (Middleton 24) circuit feeding Dixie Deer substation 6/30/2015 2.97  521   10/01/13 East N/A Tap to 12.5 kV DXD12 (Dixie Deer 12) circuit 11/1/2015 3  System Impact Study Report Bowler Flats Energy Hub, LLC Page 52 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 523   10/08/13 East N/A Santaquin- Nebo #2, tap to Burgin (one of two 46kV lines in the area) 11/1/2015 6  524   10/08/13 East N/A Terminal – Tooele 46kV 11/1/2015 6  525   10/09/13 East NR/ER Parowan substation 11/30/2016 40  526   10/16/13 East N/A TAR11, Tamarisk 11 (to the immediate north of substation) 12/31/2014 3  527   10/16/13 East N/A HUC13, Huntington 13 (South of town, on Route10) 12/31/2014 3  528   10/16/13 East N/A HUC12, Huntington 12 12/31/2014 3  1778 78834184 10/18/13 East NT PACE PACE 12/1/2013 10 529   10/22/13 East N/A WCD 28 6/30/2015 3  530   10/22/13 East N/A WCD 28 6/30/2015 3  531   10/22/13 East N/A WCD 28 6/30/2015 3  1780 78849614 10/22/13 East NT WYOC WYOC 1/1/2014 21 1781 78865513 10/25/13 East NT WYOE WYOE 1/1/2014 20 532   11/07/13 East NR/ER Pavant substation 7/1/2016 50  1787 78984295 11/26/13 East NT WYOE WYOE 7/30/2014 7.5 System Impact Study Report Bowler Flats Energy Hub, LLC Page 53 August 19, 2014 Bowler Flats Energy Hub, Q0542 QUEUE OASIS AREF Completed Request Received Control Area Type of Request POR (TSR) / Location of Interconnection (GI) POD (TSR) Start Date (TSR) / Cust. Requested Commercial Operation (GI) MW 539   12/13/13 East NR/ER 138k/ linetap on PacifiCorp's Wecco Radial line 3/31/2016 130.4  541   12/23/13 East NR/ER Pinto substation at 138 kV through facilities constructed for Q0384 12/31/2015 138  1794 79099043 12/23/13 East NT PACE PACE 3/31/2014 1 1796 79132251 01/03/14 East NT PACE PACE 1/1/2014 25 1797 79164408 01/09/14 East NT PACE PACE 2/1/2014 200 542   01/23/14 East NR/ER 230 kV Frannie – Yellowtail line approximately 3 miles North of the Frannie substation 12/1/2015 240